Document Title
Brief title
FOAC-PCMMSQA-001-SIHOPTSP
Document
purpose
Elaborated by
28/1/2015
References
Code:
Version
Validity
From: 05/11/2014
To: 31/03/2015
Draft
Substitutes the
Document
NA
State
Definitive
Distribution List
CIO: ERZ
Software Factory Manager: ERZ
Software Project Manager: ZAAA
Scrum Master: MASX
SCM Group: MHG, TOMN
Software Engineering Group: MIH, UMC, OOJY, ORIJ, PALI,
MEES, CUHJ, HEAL, AALJ, PELF, CAIM, MAVM.
Testing Group: RLO, BENN
QAG Group: JBB, FRT
Product Owner: BPM, FRT, RLO
Elaborated by
Authorization
Reviewed by
Authorized by
Cristina Dvila
Vega
SQA Manager
Marlen Zamorano
Software Project
Manager
1/17
CONFIDENTIAL MATERIAL
HISTORY
LOG
VERSION
DESCRIPTION
ID RESPONSIBLE
DATE
0.1
0.2
Versin Inicial
Versin con correciones
COMG
RELM
29/12/2014
28/1/2015
2/17
CONFIDENTIAL MATERIAL
CONTENTS
1 INTRODUCTION...............................................................................................................................................................4
1.1
1.2
PURPOSES......................................................................................................................................................................4
SCOPE............................................................................................................................................................................4
2 PROJECT DESCRIPTION................................................................................................................................................4
3 SQA ACTIVITIES ROLES AND DUTIES.......................................................................................................................4
3.1 REVIEW OBJECTS...........................................................................................................................................................7
3.2 REVIEWS AND AUDITS...................................................................................................................................................7
3.2.1
Reviews and Audits Criteria................................................................................................................................7
3.3 CORRECTIVE ACTIONS AND SUGGESTION NOTIFICATION.............................................................................................7
3.4 RESOURCES....................................................................................................................................................................7
3.5 WORK SCHEDULE..........................................................................................................................................................7
3.6 ESTIMATION COST.........................................................................................................................................................7
3/17
CONFIDENTIAL MATERIAL
INTRODUCTION
1.1
PURPOSES
The objective of the present document is to serve as a guide for implementing the SQA
activities of the project. These activities involve the control, tracking and revision of results
of the project on the application of standards (previously agreed) to guarantee its execution
and effective results within time, cost and expected quality.
1.2
SCOPE
Aplicable a todas las actividades realizadas a lo largo del proyecto de software, los productos
de software, entregables, normas y metodologas, cuya aplicacin ser revisada y auditada.
La revisin est diseado para cumplir un objetivo principal: "Sugerir mejoras en el
proceso de desarrollo de productos".
PROJECT DESCRIPTION
Praxis cuenta con el sistema SIHOWEB, Sistema de Horas, cuyo propsito principal es la
captura del esfuerzo real de horas hombre aplicadas en los diversos proyectos que dan
soporte a la operacin de Praxis.
SIHO est dirigido a todo el capital humano de Praxis, y dada su caracterstica de
obligatoriedad a nivel corporativo requiere garantizar un ptimo desempeo, en la
actualidad el aplicativo presenta problemas de performance lo cual dificulta su operacin,
adicional el cdigo fuente de la aplicacin no es flexible para cambios y genera costos de
licenciamiento.
SIHO carece de la funcionalidad Rentabilidad lo cual genera trabajo manual tanto en
reporte como en el anlisis y alejado de la vanguardia de tecnologa mvil, no cuenta con un
esquema de registro de horas y actividades offline. Como punto focal, dada la dinmica de
crecimiento del corporativo y la necesidad de competitividad en el mercado se requiere la
integracin de la metodologa de trabajo PSP-TSP.
Objetivo general
Implementar el Sistema de Horas Praxis SIHO con nueva funcionalidad orientada a la
metodologa PSP/TSP para uso de todos los recursos humanos de Praxis logrando una
plataforma de trabajo integral con tecnologa Java.
4/17
CONFIDENTIAL MATERIAL
Objetivos especficos:
1. Migracin de plataforma tecnolgica de .NET a Java.
2. Funcionalidad Offline que permita la captura de horas en un dispositivo mvil.
3. Integracin a SIHO la funcionalidad de la metodologa PSP TSP
Se calcula un total de 70 requerimientos autorizados que sern atendidos en 138 productos
de software; los cuales sern desarrollados por un equipo de trabajo integrado por: 1
Administrador de Proyectos de tiempo parcial, 1 Scrum Master de tiempo parcial, 1
arquitecto se software de tiempo parcial, 1 Lder Tcnico, 5 Implementadores jr. 1
Administrador de la Configuracin de tiempo parcial, 1 Consultor de Aseguramiento de la
Calidad de tiempo parcial, 1 Ingeniero de Pruebas de tiempo parcial, quienes realizarn las
actividades mencionadas en el plan de trabajo en un lapso de 5 meses.
SQA Group
(Manager, Engineer)
INDIVIDUAL IN
DUTIES
CHARGE
Cristina Dvila
(CPD)
Mitzi Reyes
(RELM)
5/17
CONFIDENTIAL MATERIAL
ROLE
INDIVIDUAL IN
DUTIES
CHARGE
Software
Requirements
manager
Marlene
Zamorano
(ZAAA)
Software Project
Manager
Marlene
Zamorano
(ZAAA)
Scrum Master
Rodrigo
Martinez
(MASX)
SCM Group
(Manager, Engineer)
TEAM
Maribel
Hernndez
(MHG)
No Torres
(TOMN)
Rubn Murgua
(UMC)
Giovanni
Gonzalez
(GOHG)
Yolanda Ochoa
(OOJY)
Miguel Martinez
(MAVM)
Jose Maria
Ortega
(ORIJ)
Israel Paz
(PALI)
Sonia Mendoza
retrospective, administrative.
Participates in sessions of causal analysis.
Participates in sessions of taking of formal decisions.
Suggests improvements to the processes.
Feeds the measurement system.
Provides objective verification of the quantitative analysis
and it assures adherence to the process.
Reviews the fulfillment and trazability of the project
requirements throughout of each one of the project phases.
Revises the individual activities of the work team to make
sure that are continued according to the plans of the project.
Reviews that the standards, norms and procedures are
followed, settled down by the PRAXIS Software Factory (see:
Software Factory Quality Management System).
Reviews the SQA Plan.
Reviews the execution of the activities to make sure that
follow the project plan.
Reviews the non-compliances (identified by the SQA
Engineer), the change control request and follows them until
the closing.
Reviews the fulfillment and trazability of the project
requirements throughout of each one of the project phases.
Revises the individual activities of the work team to make
sure that are continued according to the plans of the project.
Follow ups to activities performed for the SQA group
according to management schedule (FOAC-PCMMSPP-007).
Reviews that the standards, norms and procedures are
followed, settled down by the PRAXIS Software Factory (see:
Software Factory Quality Management System).
Reviews the SQA Plan.
Remove impediments timely and relentless.
Share the team experience.
Radiate project information through task board and charts.
Foster team health.
Reviews the non-compliances (identified by the SQA
Engineer).
Reviews the fulfillment and trazability of the project
requirements throughout of each one of the project phases.
Revises the individual activities of the work team
Evaluates that a configuration control of the all products of
the project settles down.
Verifies that the configuration control activities are executed
correctly by all those involved in the project.
Reviews the SQA Plan.
Plans the physical and functional audits of the configuration
(PCA/FCA).
Participates in the project planning.
Reviews the SQA Plan
Participates in the in the reviews and audits
Reviews the Quality Control LogBook
Solve the non-compliances of the process that they execute
Send to repository the artifacts to be submitted for audit
Solve the non-compliances of the artifacts that they produced
6/17
CONFIDENTIAL MATERIAL
ROLE
INDIVIDUAL IN
DUTIES
CHARGE
(MEES),
Juan de la Cruz
(CUHJ),
Lizbeth
Hernndez
(HEAL),
Judith Alvarado
(AALJ),
Francisco Perez
(PELF),
Miguel Carrasco
(CAIM).
Testing Group
Carlos
Garca (RLO)
Nelly
Becerra
(BENN)
NA
Customers SQA
personnel
Experts independent
of the SQA group
Oficina de
Proyectos
Elsa Ramirez
(CIO)
CIO
SPONSOR
Product Owner
Customer care
3.1
REVIEW
Edmundo
Robert
Hernndez
(ERH)
Beatriz Perea
(BPM)
Fernando
Rueda
(FRT)
Carlos
Garcia
(RLO)
Claudia
Peregrino
(PEOC)
OBJECTS
Durante el desarrollo del proyecto se llevarn a cabo al menos 15 revisiones a los procesos
definidos en el documento Projects Defined Software Process (FOAC-PCMMOPFD-003SIHOPTSP) y que estn documentados dentro del Quality Management System del CEDS
(http://alfresco2.praxis.com.mx:8080/share/).
Las listas de verificacin (checklist) a ser usados, se listan en el documento Map of
Revisions/Audits of the CMMI Process (FOAC-PCMMSQA-005-SIHOPTSP).
7/17
CONFIDENTIAL MATERIAL
3.2
REVIEWS
DESCRIPTION
(CHARACTERISTICS)
OWNER
DISCIPLINE /
PHASE
REVISION TYPE
Tailoring
ZAAA
Sprint 1
In progress
Software
Project
Development Plan
Project Risk Management
Strategy
Sprint Backlog
ZAAA
Sprint 1
In progress
ZAAA
Sprint 1
In progress
MASX
ZAAA
Sprint 1
Sprint 1
In progress
In progress
ZAAA
Sprint 1
In progress
ZAAA
Sprint 1
In progress
JBB
Sprint 1
In progress
MHG
Sprint 1
In progress
REZ
Sprint 1
In progress
RLO
Sprint 1
In progress
Architecture
Test Strategy
AND
AUDITS
8/17
CONFIDENTIAL MATERIAL
se considera lo
Las revisiones y auditorias que se llevarn a cabo, se apegarn a los estndares (de
codificacin y diseo) y procesos descritos en el documento Software Development
Plan del proyecto (FOAC-PCMMSPP-006-SIHOPTSP) y de acuerdo al proceso estndar
9/17
CONFIDENTIAL MATERIAL
El estado de las desviaciones se revisa con el Scrum Master y/o con los responsables
asignados antes de su distribucin al CIO y Cliente.
Las desviaciones se consideran resueltas una vez que el SQA Engineer revisa la
evidencia y determina que es correcta en base al Proceso Definido del Proyecto
(FOAC-PCMMOPFD-003-SIHOPTSP), al documento Software Development Plan (FOACPCMMSPP-006-SIHOPTSP) y a los acuerdos establecidos del proyecto.
La periodicidad de revisiones y auditorias por parte del SQA Engineer del cliente (en
caso de existir) o su representante ser establecida en comn acuerdo y ser
programada.
CONFIDENTIAL MATERIAL
3.2.1.2
3.2.1.3
11/17
CONFIDENTIAL MATERIAL
3.2.1.4
Proces
o
RM
2
3
SPP
SPP
A&D
5
6
A&D
IMP
SPTO
TST
TST
10
SPTO
Punto crtico
Requerimientos completos incluyendo los diferentes tipos
revisados y autorizados con el usuario adecuado.
Kickoff involucrando a los interesados adecuados.
Plan de trabajo, sprint backlog o lista de actividades con
hitos y responsables y seguido por todo el equipo.
Tecnologa y arquitectura probada, revisada con cliente y a
cargo de arquitecto con experiencia en Praxis.
Responsable de base de datos con experiencia.
Desarrollar los requerimientos autorizados y siguiendo la
arquitectura definida.
Demostraciones frecuentes del avance de los productos con
el usuario adecuado.
Pruebas desde etapas tempranas planeadas y con una
estrategia definida para satisfacer los criterios de
aceptacin.
Ambientes definidos de desarrollo, pruebas y UAT
independientes as como mecanismos definidos de entrega y
aceptacin con el cliente.
Acuerdos, dependencias, issues y riesgos registrados,
evaluados, comunicados a los involucrados adecuados,
monitoreados y cumplidos.
Proyecto Completo
De igual manera se detendr el proyecto completo en los siguientes casos:
12/17
CONFIDENTIAL MATERIAL
Administracin de Proyectos
Se detendrn las actividades de administracin en los siguientes casos y
solo podrn continuar hasta que estos puntos sean resueltos:
Grupo de Ingeniera
Se detendrn las actividades de ingeniera en los siguientes casos y solo
podrn continuar hasta que estos puntos sean resueltos:
Grupo de Test
13/17
CONFIDENTIAL MATERIAL
SCM
Se detendrn las actividades de SCM en los siguientes casos y solo podrn
continuar hasta que estos puntos sean resueltos:
No se cuenta con el SCM Plan autorizado (FOAC-PCMMSCM-001-1SIHOPTSP) en la fecha que el calendario de administracin
(ICESCRUM) lo indique.
Cuando se tenga desactualizado el repositorio con ms de 5 das
calendario.
SQA
Se detendrn las actividades de SQA en los siguientes casos y solo podrn
continuar hasta que estos puntos sean resueltos:
No se cuenta con el SQA Plan autorizado en la fecha que el calendario
de administracin (ICESCRUM) lo indique.
Est desactualizado el documento Quality Control Logbook (FOACPCMMSQA-003-SIHOPTSP) por ms de 5 das hbiles.
Caso
Escalar a
Software
Factory
Manager
Engineering Manager
Test Manager
SCM Manager
CIO
14/17
CONFIDENTIAL MATERIAL
3.2.1.5
el nivel 1.
Sucede alguno de los casos
descritos arriba para detener el
proyecto.
No hay respuesta en el nivel 2.
La respuesta del nivel 2 no
soluciona las desviaciones.
Los responsables no cumplen la
fecha compromiso establecida en
el nivel 2.
Sucede alguno de los casos
descritos en el declogo SQA.
CEO
Oficina de Proyectos
3.3
CORRECTIVE ACTIONS
AND
SUGGESTION NOTIFICATION
3.4
RESOURCES
Para este proyecto, un SQA Engineer ha sido asignado, el cual est debidamente capacitado
para realizar todas las actividades de SQA, conoce su rol, responsabilidades y autoridad
dentro del proyecto y sus actividades sern coordinadas por un SQA Manager.
15/17
CONFIDENTIAL MATERIAL
A continuacin se listan las herramientas a utilizar y los accesos requeridos para el desarrollo
de las actividades de SQA:
16/17
CONFIDENTIAL MATERIAL
3.5
WORK SCHEDULE
Para un mayor detalle consultar la herramienta ICESCRUM, dentro del proyecto PX1412SIHOPTSP
http://192.168.2.40:8088/icescrum/p/PROJ15/#sprintPlan
3.6
ESTIMATION COST
El costo en tiempo y el costo por el recurso asignado (76 hrs.) asignado para el desarrollo de
las actividades de SQA, es descrita en el documento Project Product Size Estimation (FOACPCMMSPP-001-Agile_SIHO).
17/17