75962 Federal Register / Vol. 71, No.

243 / Tuesday, December 19, 2006 / Notices

DEPARTMENT OF ENERGY Approximately 95 percent of the Initiative (‘‘Coosa River’’): Sierra Club v.
original project analyzed in the FEIS is EPA, No. 1:06CV1523 (N.D. GA). On
Federal Energy Regulatory relatively unchanged, with the December 20, 2005 and January 3, 2006,
Commission exception of the 6-inch increase in Sierra Club, Coosa River, and the
pipeline diameter. The tunnel Georgia Public Interest Research Group
[Docket No. CP01–409–000] amendment would increase the pipeline petitioned EPA to object to certain Clean
diameter for the modified project from Air Act Title V permit amendments
Calypso U.S. Pipeline, L.L.C.; Notice Of proposed by the Georgia Environmental
24 inches to 30 inches and internally
Availability of the Environmental Protection Division for steam generating
coat the pipeline to allow increased
Assessment for the Proposed plants at Georgia Power’s (1) Bowen and
flow rates. Calypso does not propose to
Modifications to the Calypso Pipeline Branch Steam-Electric Generating
increase the certificated capacity
Project Plants, and (2) Hammond and Scherer
(832,000 dekatherms/day). The
December 12, 2006. maximum operating pressure (MOAP) Steam-Electric Generating Plants, all of
The staff of the Federal Energy would remain 2,200 pounds per square which are in the State of Georgia.
Regulatory Commission (FERC or inch (psig). Calypso indicates that the Subsequently, Sierra Club and Coosa
Commission) and the Mineral pipeline would most likely be operated River filed suit, alleging that the
Management Service (MMS) have at approximately 1530 psig. Administrator failed to perform his
prepared this Environmental The EA has been placed in the public nondiscretionary duty to respond to the
Assessment (EA) to discuss the files of the FERC and is available for petitions within sixty days of the date
environmental impacts of the public inspection at: Federal Energy they were filed. Under the terms of
Modifications to the Calypso Pipeline Regulatory Commission, Public today’s proposed consent decree, EPA
Project proposed by Calypso U.S. Reference Room, 888 First Street, NE., has agreed to respond to the petitions by
Pipeline L.L.C. (Calypso) in the above Room 2A, Washington, DC 20426, (202) January 8, 2007, and Sierra Club and
referenced docket. The proposed project 502–8371. Coosa River have agreed that if EPA
is located in Broward County, Florida; Additional information about the does so, and after parties negotiate
State Waters of Florida; and Federal project is available from the attorneys’ fees, they will move to
Commission’s Office of External Affairs, dismiss their suit with prejudice.
Waters of the United States.
This EA has been prepared to comply at 1–866–208–FERC or on the FERC DATES: Written comments on the
with the requirements of the National Internet Web site (http://www.ferc.gov) proposed consent decree must be
Environmental Policy Act (NEPA), the using the eLibrary link. Click on the received by January 18, 2007.
Council of Environmental Quality (CEQ) eLibrary link, click on ‘‘General Search’’ ADDRESSES: Submit your comments,
regulations for implementing NEPA and enter the docket number excluding identified by Docket ID number EPA–
(Title 40, Code of Federal Regulations the last three digits in the Docket HQ–OGC–2006–0972, online at
[CFR], sections 1500–1508), and the Number field. Be sure you have selected www.regulations.gov (EPA’s preferred
Commission’s regulations (18 CFR part an appropriate date range. For method); by e-mail to
380). The staff concludes that approval assistance with eLibrary, the eLibrary oei.docket@epa.gov; mailed to EPA
of this proposal would not constitute a helpline can be reached at 1–866–208– Docket Center, Environmental
major Federal action significantly 3676, TTY (202) 502–8659 or Protection Agency, Mailcode: 2822T,
affecting the quality of the human FERCOnlineSupport@ferc.gov. The 1200 Pennsylvania Ave., NW.,
environment. The EA also evaluates eLibrary link on the FERC Internet Web Washington, DC 20460–0001; or by
alternatives to the proposal, including site also provides access to the texts of hand delivery or courier to EPA Docket
system alternatives; major route formal documents issued by the Center, EPA West, Room 3334, 1301
alternatives; and route variations. Commission, such as orders, notices, Constitution Ave., NW., Washington,
The FERC prepared this EA to address and rulemakings. DC, between 8:30 a.m. and 4:30 p.m.
the potential environmental impacts of Magalie R. Salas, Monday through Friday, excluding legal
the proposed modifications. The holidays. Comments on a disk or CD–
Secretary.
original project was addressed by the ROM should be formatted in Word or
[FR Doc. E6–21556 Filed 12–18–06; 8:45 am]
Final Environmental Impact Statement ASCII file, avoiding the use of special
BILLING CODE 6717–01–P
for the Tractebel Calypso Pipeline characters and any form of encryption,
Project (FEIS) issued on January 23, and may be mailed to the mailing
2004. The modified project would use address above.
ENVIRONMENTAL PROTECTION FOR FURTHER INFORMATION CONTACT:
the same methodologies for deepwater
AGENCY Howard J. Hoffman, Air and Radiation
construction and onshore construction.
However, the landfall portion of the [FRL–8258–6] Law Office (2344A), Office of General
pipeline would be installed in a 3.2- Counsel, U.S. Environmental Protection
mile-long tunnel. The tunnel proposal Proposed Consent Decree, Clean Air Agency, 1200 Pennsylvania Ave., NW.,
eliminates the need for two HDD Act Citizen Suit Washington, DC 20460; telephone: (202)
segments, and 2,132 feet of open cut AGENCY: Environmental Protection 564–5582; fax number (202) 564–5603;
trench in shallow marine waters, in Agency (EPA). e-mail address:
addition to avoiding all impacts to John hoffman.howard@epa.gov.
ACTION: Notice of Proposed Consent
U. Lloyd State Park. The tunnel Decree; request for public comment. SUPPLEMENTARY INFORMATION:
amendment would also incorporate
hsrobinson on PROD1PC76 with NOTICES

minor route changes to accommodate SUMMARY: In accordance with section I. Additional Information about the
the methodology. These minor route 113(g) of the Clean Air Act, as amended Proposed Consent Decree
changes would result in a slight (‘‘Act’’), 42 U.S.C. 7413(g), notice is This proposed consent decree would
decrease in the length of the landfall hereby given of a proposed consent resolve a deadline suit to require EPA to
portion and thus the overall project decree, to address a deadline suit filed respond to two administrative petitions
length. by Sierra Club and Coosa River Basin that EPA object to certain Title V permit