Documente Academic
Documente Profesional
Documente Cultură
Do not cite
Swapnil Garg swapnilgarg@iimidr.ac.in
Page |1
Page |2
the original date of commissioning (July 2005), the provisional change of scope had been
finalized, with minimal amount of work at site visible.
Despite all the constraints, the project got commissioned on 25thJanuary 2008 and the
concessionaire started collecting toll. With 100 per cent time over run, cost overruns should
also be expected. At commissioning the project costed USD 195 million, almost double of the
initial estimate. The extra funds required for the project were sourced by the concessionaire
by withholding the bills of the construction contractors, which was a group company. The
USD 26 million provided and accepted by NHAI for scope changes to the project also helped
cover the gap. With traffic on the highway growing substantially, traffic jams at the toll plaza
became a regular figure and the concessionaire started facing increasing difficulties in toll
collection. The concessionaire requested for police assistance in traffic regulation at the toll
booths and filed a petition with the Punjab and Haryana High Courts. However, while police
did not entertain the request, and the courts refused to intervene.
ESCALATION OF ISSUES
No contractual provision existed to cover the large cost overruns. Re-servicing of the
debt emerged as the only option. Accordingly, the concessionaire approached a consortium of
State Bank of India and eight other nationalised banks for a debt of USD 210 million in
January 2009. NHAI, was required to be kept in confidence about all changes in the financial
structure as it provided the collateral on the road and also the right for toll collection, to
service the debt. It issued a conditional no objection certificate, after a considerable delay of
almost a year. Meanwhile, the concessionaire had some ideas. It got a loan of USD 270
million sanctioned by a consortium led by Infrastructure Development and Finance
Corporation (IDFC) with four nationalised banks, and intimated the same to NHAI on 9th
October 2010, after having taken the initial disbursements.
In concession projects, the overall project assets and its revenues stand guarantee
Page |3
against the loan provided. Any changes in the debt liabilities incurred without the knowledge
of the owning public agency is highly irregular. NHAI argued further that disbursements by
IDFC have been siphoned off by the SPV to the parent firm as loans and as payment for the
construction work, even before the change in the lending institutions had been informed to
them. Considering it a breach of trust and a highly irregular contractual activity, a preliminary
notice for termination was issued by NHAI on 7th December 2011 and a final termination
notice on 18th February 2012.
The dispute reached litigation and three courts in the country got involved. First, the
concessionaire moved the Delhi High Court against the termination notice, on which the
court asked the parties to hold a mutual settlement discussion and submit an affidavit. After
23 hearings a Memorandum of Understanding (MOU) was arrived at by all the concerned
parties and signed in the court on 18th September 2012.
Second, IDFC filed a petition in the Delhi High Court pleading that NHAI and
concessionaire be directed to sign the necessary escrow and substitution agreements as its
debt was not being serviced from the toll collection revenues. It also made a proposal for an
amicable settlement.
Third, the Punjab and Haryana High Courts, which had been deliberating on a request
by the concessionaire for provision of police help at the toll plaza for a decade, took
cognizance of increasing instances of traffic jams at the toll booth and the ensuing nightmare
for the travelling public. It asked the concessionaire three times to take action to de-congest
the traffic at the toll booths, however their was no visible on the ground. The Courts viewed it
harshly, and ordered stoppage of tolling at the booths. The tolling was again started only after
all the agencies had met, prepared and filed an action plan (recorded as minutes of the
meeting MOM) to de-congest the toll plaza.
Meanwhile, the Supreme Court of India was also approached, but it refused to
Page |4
the toll plaza with heavy traffic jams at the Delhi Gurgaon border would be closed
down,
the tolls for this stretch of expressway would be allowed to be collected at another toll
Page |5
concessionaire's claims of USD 160 million are not admissable and need to be
withdrawn,
IDFC has to undertake the responsibility to complete all the tasks as per the previous
MOU'sand meetings,
submitted an affidavit in the court stating that the agreements reached duirg the meeting. On
this affidavit, the court passed a consent order on 19th February 2014. As per the grapevine,
the secretary level meeting also passed numerous gaga orders on the participants. Most
importantly Mr B.D.Nirula the owner of DS Construction was asked to submit a written
assurance that he would not share his part of the story in press, in courts, or even share it
informally. And, further he and his firm would rescind themselves from the project
completely.
With these agreements, toll collections at the disputed plaza were formally stopped, and
the traffic movemnet became reasonably smooth. The project is now completely and firmly in
the hands of IDFC, with complete equity holding, debt obligations, and maintenance
responsbilities. After quite an effort, the susbtitution agreement was also signed with NHAI,
through which DS Constructions name was substituted with IDFC's name at all places in the
concession agreement. This agreement, in its new form, stands valid till end of 2023.
ONGOING ISSUES
The revenue collections from the two of the three operational toll plazas is not enough to
even cover the maintenance requirements of the expressway. It is envisaged that IDFC and its
lending partners will not only loose the equity component in the project, but they will also be
Page |6
required to set off a large part of the debt as bad debt, unless something is done soon. IDFC
has however registered a new company MCEPL (Millenium City Expressway Private
Limited) to look after the affairs of the project2 and has appointed Mr Raghuram, a veteran
PPP manager, as a dedicated CEO for the project. It has also approved repair and
maintenance works to the tune of Rs 100 crore to carry out the immediate repairs on the
highway, and has also carried out much of the overdue road resurfacing. However, a large
component of modification works, targeting smoothing of traffic at the toll plaza, remains
unattended to. This was to be attended on priority as agreed upon in the numerous earlier
meetings and understandings. These pending works consisted of removal of the toll collection
infrastructure and construction of a bypass flyover, for which land and partial fuding has been
promised by Ambience Mall, a Rs 500 crore mall which has come up in the vicinity.
The Delhi-Guragaon express-way is uniformly eight laned. At the toll plaza location the
road width increases to 32 lanes for the toll collection purposes. Despite the 32 lanes for
vehicular traffic at this location, this is the only bottleneck existing on the whole route. The
bottleneck is argued to exist for two possible reasons. Firstly, all vehicles have to slow down
as they pass through the narrow toll collection alleyway. These toll alleyways were orginally
designed for slower traffic and are by design narrow to ease exchange of toll money and
receipt between the driver and the toll agent. Secondly, the commercial traffic has to still pay
the state road entry tax and has to get seggregated out to the side lanes for the state entry tax
payments. Nothing much has moved on this front despite numerous high level meetings
between officials of the Delhi and Haryana Governments, leading to a highly ambigous
situation of who pays and who dosen't pay the entry tax for entering the almost porus state
borders, within the national capital region. There is no doubt that with the expressway being
eight lanes, both before and after the toll plaza, the removal of the toll collection structures
2 http://www.hindustantimes.com/gurgaon/gurgaon-e-way-to-get-new-name-millenniumcity-expressway-new-operator/article1-1217713.aspx
Page |7
would serve to help ease the flow of traffic. Even the courts had ordered for the removal of
these structures, and the next court hearing was scheduled for 26th May' 2015 when the status
of work completed has to be submitted for courts scrutiny.
The toll collection structures are very large and they require traffic to be stopped
while they are dismanteled. There is also an underground tunnel connecting all the toll
booths, which needs to be blocked. This tunnel served to facilitate cross movement of the toll
plaza staff without affecting the flow of road traffic. Mr Raghuram decided that the sooner
the work gets attended to, it was better for the project. Ofcourse, as the CEO it is he who is
held accountable in the court of law for any failures. He assumed that as there would be no
change in the road width (for almost 2 kms on either side of the toll plaza location), and the
eight vehicular traffic lanes would remain full operational, they could start work on the
demolition of tollplaza on Friday and finish the same by Sunday night, a day before the date
of court hearing.
On the morning of 22nd of May 2015 his assumptions have fallen to pieces. He had failed
to predict the habits of the Indian drivers. In India, the concept of land driving is non-existent.
For a driver in India, every open piece of road space, no matter how small, provides an
opportunity for the car to get in and beat the traffic. Hence, as soon as the road opens out
from eight lanes to thirty two lanes lanes (funnelling out), a fight for the least congested lane
at the funnel exit starts. The streamlined smooth flow of traffic suddenly becomes turbulent,
and turbulent flows are known to reduce flow rates, waste energy, and even heat up the
medium. All of which happened here everyday, and the sudden change to turbulent flow from
a streamlined flow has been the order of the day not only at this toll plaza, but even at others
toll plazas in the country. The same had happened that day, but with a difference. Today,
instead of removing one big funnel of 32 lanes with continuous lanes, he had inadvertently
substituted it with two narrower funnels, of eight lanes each. One on the approach to the toll
Page |8
plaza and the other on exiting from it (Refer Figure 1). With a 25% reduction from 32 lanes
to 8 lanes, the traffic log jam happened as it did, with vehicles criss crossing each others way
and blocking each other.
By the evening of 22nd May 2015, Mr Raghuram was left wondering, What to report in
the court on Monday?, How to address the media critism of, Why had the gurgaon traffic
police not been involved? He was left asking himself, How would the traffic police have
helped in this state? Does road discipline come with one day of traffic policing!
He, however, had no time to wonder as to what the Delhi-Gurgaon commuters have got
after an almost two decade long highway upgradation program and routine toll
payments......... .
Page |9
Project Award
Financial
closure
Concessionaire
Construction
Dispute
Positive aspects
Challenges
NH 8 Delhi Gurgaon
Negative grant Rs 61.06 cr (USD 10 million)
Revenue sharing above 1.3 lakh passenger carrying units
27 Km of 6/8 lanes and service lanes
DPR by M/S Rites ltd in 1997
Rs 547.5 cr (USD 90 Million)
Unanticipated growth in traffic
High level of coordination required not envisaged
Design of nine major structures required to be revised.
Lack of experience (early project)
31stJan02
20 year concession with 30 month construction period
Equity Rs 164.2 cr (USD 30 million) (originally 51% Jaypee, who reduce it to 1.2%)
76% taken over by IDFC, awaiting govt. clearance for rest
Debt Rs 383.3 cr, (USD 60 million) (Originally with HUDCO lead consortium)
SBI approves a debt of Rs 1275 Cr (Jan09)
IDFC approves a debt of Rs 1600 cr (9th Sept10)
Jaypee DSC ventures (early)
Delhi Gurgaon Super Connectivity Ltd
Starts: 12thJan03 Complete: 25thJan08 Time delay 3 years
Major scope changes
Cost escalation to Rs 1170 cr (USD 195 million)
Coordination issues with 15 government agencies
Rs 155.5 cr(USD 26 million) agreed for major scope changes only
Public discomfort at Toll Plaza
Irregular renegotiation of debt
Wrong toll reporting by concessionaire
Inadequate maintenance
Good traffic projections.
1.27 lakh PCUs per day in 2000
2.41 lakh PCUs per day in 2012
A brown field project
P a g e | 10
Government
(Ministry)
Concessionaire
Independent
engineer
High Courts
the same court seeking action and servicing of its debt, and proposes amicable settlement of issues.
Refuses to intervene as cases are in other courts.
Change in equity (Jaypee DSC IDFC)
Stand personal guarantee for IDFC loans
Payments for construction with held.
IDFC proposes to take over the project equity, but NHAI within its laws only allows 74% equity transfer.
Financiers
Pubic
Media
FINAL
RESOLUTION
IDFC agrees in court with the above order, and toll plazas are closed. New toll rates at the other toll plazas
to be announced, IDFC to still get necessary approvals and agreements for toll collection, as of July2014.
P a g e | 12
Figure 1
P a g e | 13