Sunteți pe pagina 1din 10

62912 Federal Register / Vol. 71, No.

208 / Friday, October 27, 2006 / Rules and Regulations

Alternative Methods of Compliance amends section 15 of the Natural Gas the Commission and other agencies with
(AMOCs) Act (NGA) 2 to provide the Federal respect to such authorizations. In this
(f) The Manager, Fort Worth Airplane Energy Regulatory Commission Final Rule, the Commission considers
Certification Office, FAA, Attn: Andrew (Commission) with additional authority comments submitted in response to the
McAnaul, Aerospace Engineer, ASW–150 to coordinate the processing of NOPR, and as a result, makes certain
(c/o MIDO–43), 10100 Reunion Place, Suite authorizations required under Federal modifications to the proposed
650, San Antonio, Texas 78216; telephone:
(210) 308–3365; facsimile: (210) 308–3370,
law for proposed natural gas projects regulatory revisions.
has the authority to approve AMOCs for this subject to NGA sections 3 and 7 and to
Background
AD, if requested using the procedures found maintain a complete consolidated
in 14 CFR 39.19. record of decisions with respect to such 2. The Commission authorizes the
Federal authorizations. This Final Rule construction and operation of proposed
Material Incorporated by Reference natural gas projects under NGA sections
promulgates regulations governing its
(g) You must do the actions required by exercise of this authority whereby the 3 and 7.5 However, the Commission
this AD following the instructions in Snow does not have jurisdiction over every
Commission will establish a schedule
Engineering Co. Service Letter #253, dated aspect of each natural gas project.
December 12, 2005. The Director of the for the completion of reviews of
Federal Register approved the incorporation requests for authorizations necessary for Hence, for a natural gas project to go
by reference of this service bulletin in a proposed project and compile a forward, in addition to Commission
accordance with 5 U.S.C. 552(a) and 1 CFR consolidated record to be used in the approval, several different agencies
part 51. To get a copy of this service event of review of actions by the must typically reach favorable findings
information, contact Air Tractor, Inc., P.O. Commission and other agencies in regarding other aspects of the project.
Box 485, Olney, Texas 76374; telephone: responding to requests for To better coordinate the activities of
(940) 564–5616; facsimile: (940) 564–5612. separate agencies with varying
authorizations necessary for a proposed
To review copies of this service information, responsibilities over proposed natural
go to the National Archives and Records project.
Administration (NARA). For information on DATES: Effective Date: The rule will gas projects, EPAct 2005 modified the
the availability of this material at NARA, go become effective December 26, 2006. Commission’s role. Section 313 of
to: http://www.archives.gov/federal_register/ FOR FURTHER INFORMATION CONTACT:
EPAct 2005 directs the Commission (1)
code_of_federal_regulations/ Gordon Wagner, Office of the General to establish a schedule for agencies to
ibr_locations.html or call (202) 741–6030. To
Counsel, Federal Energy Regulatory review requests for Federal
view the AD docket, go to the Docket authorizations required for a project 6
Management Facility; U.S. Department of Commission, 888 First Street, NE.,
Transportation, 400 Seventh Street, SW., Washington, DC 20426; 5 Under NGA section 7, the Commission has
Nassif Building, Room PL–401, Washington, gordon.wagner@ferc.gov; (202) 502– jurisdiction over the transportation or sale of
DC 20590–001 or on the Internet at http:// 8947. natural gas in interstate commerce and the
dms.dot.gov. The docket number is FAA– Lonnie Lister, Office of Energy construction, acquisition, operation, and
2006–24228; Directorate Identifier 2006–CE– Projects, Federal Energy Regulatory abandonment of facilities to transport natural gas in
22–AD. interstate commerce. Under NGA section 3(e), the
Commission, 888 First Street, NE., Commission has exclusive authority to approve or
Issued in Kansas City, Missouri, on Washington, DC 20426; deny an application for the siting, construction,
October 13, 2006. lonnie.lister@ferc.gov; (202) 502–8587. expansion, or operation of a liquefied natural gas
James E. Jackson, William O. Blome, Office of the (LNG) terminal. The Secretary of the Department of
Energy (DOE) has delegated to the Commission the
Acting Manager, Small Airplane Directorate, General Counsel, Federal Energy authority under NGA section 3 to approve or
Aircraft Certification Service. Regulatory Commission, 888 First disapprove applications for the siting, construction,
[FR Doc. E6–17828 Filed 10–26–06; 8:45 am] Street, NE., Washington, DC. 20426; and operation of facilities to import or export
(202) 502–8462. natural gas. The most recent delegation is in
BILLING CODE 4910–13–P Delegation Order No. 00–004–00A, effective May
SUPPLEMENTARY INFORMATION: 16, 2006.
Before Commissioners: Joseph T. Kelliher, 6 EPAct 2005 section 313 describes ‘‘Federal

Chairman; Suedeen G. Kelly, Marc authorizations’’ as decisions or actions by a Federal


DEPARTMENT OF ENERGY Spitzer, Philip D. Moeller, and Jon agency or official, ‘‘or State administrative agency
Wellinghoff or officer acting under delegated Federal authority,’’
Federal Energy Regulatory granting or denying requests for permits,
Commission 1. On May 18, 2006, the Commission certificates, opinions, approvals, and other
issued a Notice of Proposed Rulemaking authorizations. The United States Environmental
(NOPR) in Docket No. RM06–1–000,3 Protection Agency (EPA) asks what types of state
18 CFR Parts 153, 157, 375, and 385 actions would qualify as being under delegated
requesting comments on proposed Federal authority. The Commission finds that a
[Docket No. RM06–1–000; Order No. 687]
regulations to implement section 313 of state action qualifies as an action under delegated
the Energy Policy Act of 2005 (EPAct Federal authority if it is an action that (1) a State
Regulations Implementing the Energy entity is permitted, approved, or directed to take
Policy Act of 2005; Coordinating the 2005).4 EPAct 2005 section 313 amends under Federal law and (2) provides the basis for a
Processing of Federal Authorizations the Natural Gas Act (NGA) to provide reasoned decision on a request for a Federal
for Applications Under Sections 3 and the Commission with the authority (1) authorization. The United States Department of
to set a schedule for Federal agencies, Commerce, National Oceanic and Atmospheric
7 of the Natural Gas Act and Administration, National Marine Fisheries Service
Maintaining a Complete Consolidated and state agencies acting under federally (NMFS) asks whether a Federal authorization
Record delegated authority, to reach a final would include recommendations or biological
decision on requests for Federal opinions issued subsequent to consultations under
October 19, 2006. the Magnuson-Stevens Fishery Conservation and
authorizations necessary for proposed Management Act and Endangered Species Act
AGENCY: Federal Energy Regulatory NGA section 3 or 7 gas projects and (2) (ESA). To the extent recommendations and
Commission, DOE. to maintain a complete consolidated opinions are necessary for a Federal agency, or state
agency acting under federally delegated authority,
rmajette on PROD1PC67 with RULES1

ACTION: Final rule. record of all decisions and actions by


to reach a decision on a request for a Federal
SUMMARY: Section 313 of the Energy authorization that is needed for a proposed NGA
2 15U.S.C. 717n (2005). section 3 or 7 project to go forward, the Commission
Policy Act of 2005 (EPAct 2005) 1 3 71FR 30632 (May 30 2006); FERC Stats. & Regs. interprets EPAct 2005’s mandate as encompassing
¶ 32,601 (2006); 115 FERC ¶ 61,203 (2006). such recommendations and opinions as ‘‘Federal
1 Pub. L. 109–58, 119 Stat. 594 (2005). 4 Pub. L. 109–58, 119 Stat. 594 (2005). authorizations.’’

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00038 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations 62913

and (2) to compile a record of each Crossroads Pipeline Company, Granite a project sponsor be permitted to file an
agency’s decision, together with the State Gas Transmission, Inc., and application with the Commission first;
record of the Commission’s decision, to Central Kentucky Transmission list the authorizations necessary for the
serve as a consolidated record for the Company (collectively NiSource); new project; identify those
purpose of appeal, including judicial Oregon Coastal Management Program; authorizations for which applications
review. United States Department of Commerce, have already been submitted and the
3. On November 17, 2005, the National Oceanic and Atmospheric dates upon which they were submitted;
Commission issued an order initially Administration, National Marine and then state the dates by which any
implementing the authority conferred Fisheries Service (NMFS); and Williston outstanding authorization requests will
by EPAct 2005 7 and delegating to the Basin Interstate Pipeline Company be submitted.
Director of OEP the authority to set (Williston). 9. The Commission observes that most
schedules for agencies to act on requests applications to construct major new gas
for Federal authorizations necessary for Discussion projects are filed with the Commission
natural gas projects to ensure such 5. The comments raise objections to after the project sponsor has
requests are processed expeditiously. In various aspects of the proposed participated in the Commission’s
that order, the Commission stated a regulatory revisions. In response, prefiling process. This prefiling period
subsequent rulemaking would codify various aspects of the NOPR’s proposed affords a project sponsor, Commission
the pertinent provisions of EPAct 2005. revisions are modified, as discussed staff, and staff from other agencies the
To that end, the May 2006 NOPR set below. opportunity to identify which Federal
forth proposed regulatory revisions. Electronic Submission of Information authorizations will be needed for a
In this Final Rule, the Commission project, and ample time for the project
responds to comments concerning the 6. There are several different events sponsor to prepare requests for related
NOPR, and adopts further regulatory that trigger the obligation on the part of Federal authorizations in advance of
revisions to implement its new other agencies and officials to submit filing an application with the
responsibilities under EPAct 2005. information to the Commission. In the Commission.9 Thus, the prefiling
NOPR, the Commission proposed all process can establish coordination
Notice and Comment such information be submitted among the agencies responsible for
4. Notice of the NOPR was published electronically, but requested that reviewing a project proposal and
in the Federal Register on May 30, affected agencies and officials comment diminish the chance that the
2006.8 Comments on the NOPR were on whether electronic submission could Commission might find an application
filed by Baker Botts, L.L.P. (Baker Botts); prove impractical. Several agencies to be incomplete.
Cheniere Energy, Inc. (Cheniere); City of stated that they are not yet prepared to 10. The Commission nevertheless
Fall River, Massachusetts; Coastal States transmit information by electronic acknowledges that there may be
Organization; Conservation Law means. Consequently, to avoid any circumstances that preclude a project
Foundation; Delaware Department of undue hardship, while stressing its sponsor from presenting all requests for
Natural Resources and Environmental preference to receive information via necessary Federal authorizations by the
Control, Division of Soil & Water electronic means, the Commission time it files an application with the
Conservation (Delaware DNR); U. S. removes the requirement to submit Commission.10 Therefore, §§ 153.8 and
Department of the Army Corps of information by electronic means.
Engineers (Army COE); Dominion 9 The NOPR noted that project sponsors that have

Transmission, Inc., Dominion Cove Coordinating Federal Authorizations made use of the prefiling period and process to
Point LNG, LP, and Dominion South prepare and submit requests for Federal
When to Submit Requests for Federal authorizations to agencies before an NGA
Pipeline Company, LP (Dominion); Authorizations application is filed with the Commission have been
Duke Energy Transmission, LLC (Duke); 7. Proposed §§ 153.8 and 157.14 able to compress the time needed to obtain
United States Environmental Protection Commission authorization. In large part, this is
specify that an application filed with because completion of the Commission’s
Agency (EPA); Interstate Natural Gas the Commission for a natural gas project assessment of an application often rests on other
Association of America (INGAA); under NGA section 3 or 7 must include: agencies reaching favorable determinations on
United States Department of the Interior separate authorization requests. Dominion and
(Interior); Islander East Pipeline A statement identifying each Federal Duke are concerned that the new filing requirement
authorization that the proposal will require; might force a project sponsor to devote undue
Company, L.L.C. (Islander East); Mr. resources to preparing to submit requests for related
the Federal agency or officer, or State agency
Mark Mendelson; Massachusetts Office or officer acting pursuant to delegated Federal authorizations at the same time as an NGA
of the Attorney General; Massachusetts Federal authority, which will issue each application. The Commission believes the prefiling
Executive Office of Environmental authorization; the date each request for process can minimize the resources needed by a
project sponsor by spacing out its submission of
Affairs (Massachusetts EOEA); New authorization was submitted; and the date by authorization requests over a period of several
Jersey Department of Environmental which final action on each Federal months.
Protection (New Jersey DEP); Columbia authorization has been requested or is 10 Cheniere, for example, posits that an agency

Gas Transmission Corporation, expected. may refuse to accept a request for a Federal
The NOPR observed that if an authorization ‘‘through no fault of the applicant.’’
Columbia Gulf Transmission Company, Were this to occur, the project sponsor should
application does not include this inform the Commission, which can then inquire as
7 Coordinated Processing of NGA Section 3 and proposed new information statement, to the circumstances. NMFS points out that with
7 Proceedings, 113 FERC ¶ 61,170 (2005). This Final the Commission may deem the respect to certain Federal authorizations, such as an
Rule codifies this delegation of authority by affirmation of compliance with the Endangered
revising § 375.308, Delegations to the Director of the
application incomplete.
Species Act or the National Historic Preservation
Office of Energy Projects (OEP), to add a new 8. Several commenters explain that it Act, the project sponsor is not in a position to
§ 375.308(bb), which delegates authority to the is impractical, if not impossible, to submit an authorization request, since a request to
rmajette on PROD1PC67 with RULES1

Director of OEP to establish schedules, consistent submit applications for all Federal initiate consultation with the responsible agency
with Federal law, for agencies to complete their authorizations before or must be submitted by the Commission. The
analysis and decision making processes and issue Commission notes this does not relieve the project
decisions on requests for Federal authorizations contemporaneously with the project sponsor of its obligation, as described in Part 380
necessary for natural gas projects. application filed with the Commission. of the existing regulations, to develop and submit
8 71 FR 30632 (May 30, 2006). These commenters propose instead that Continued

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00039 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
62914 Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations

157.14 of the Commission’s regulations later than 90 days after the issuance of discussed in the NOPR—between a
will be modified to provide for a the Commission’s final environmental ‘‘default’’ and a ‘‘project-specific’’
sponsor to explain why requests for document on the proposed project, or if schedule. For agencies without a
Federal authorizations remain no environmental document is issued, schedule established by Federal law, the
outstanding and state anticipated dates then no later than 90 days after issuance deadline for a final decision will follow
for submitting such requests. A project of a final order. from the date the Commission issues its
sponsor will now be required to state 12. Commenters point out that if no final environmental document by
‘‘the date each request for authorization schedule is included in the notice of an placing it in the public record, with the
was submitted; why any request has not application, agencies are left to wonder anticipated issuance date stated in the
been submitted and the date submission whether a project-specific schedule will NEPA notice. However, this anticipated
is expected; and the date by which final be issued at some later date, or whether issuance date is subject to change. As
action on each Federal authorization has silence indicates the default deadline explained in the NOPR, during the
been requested or is expected.’’ For applies. The Commission acknowledges course of considering an application or
requests that remain outstanding at the the desirability of informing agencies in a request for a Federal authorization,
time an application is filed, the a timely manner of the schedule that unanticipated issues and circumstances
Commission will review the reasons will apply in each case. Accordingly, can arise and affect the time needed to
given, the projected dates of submission, the Commission will adopt a different complete the review. The Commission
and an applicant’s interactions with the procedural approach, as described will monitor such changed
agencies. The Commission may then below. circumstances, and may find it
accept the application for consideration, 13. The NOPR proposed requiring that appropriate to revise the milestones set
and based on the state of documents and agency action on authorization requests out in its initial schedule for its
studies needed to support prospective be completed within 90 days of the environmental review.15 If the
authorization requests, accept the issuance of the Commission’s final Commission does so, it will issue a
projected submission dates as a basis for environmental document in a notice updating the milestones
establishing a schedule. proceeding, or if an environmental associated with its environmental
document were not prepared, then review process. Any revision that alters
Determining a Schedule for Federal within 90 days of the issuance of a final
Authorizations the date that the Commission
Commission order. Previously, the anticipates issuing its EA or final EIS
11. Initially, upon receiving an Commission has not always issued its will correspondingly shift the projected
application, the Commission issues a environmental assessment (EA) at the 90-day deadline for agencies without a
notice ‘‘within 10 days of filing,’’ in time of its completion. Going forward, schedule established by Federal law to
accordance with § 157.9 of its the Commission commits to issue its reach a final decision.
regulations,11 or rejects the application final environmental document in every
15. As described above, the
in accordance with § 157.8 of its proceeding by placing it in the public
Commission will now issue a notice
regulations. In issuing a notice of an record. In addition, going forward, the
describing the schedule for its
application, the Commission, or the Commission commits to issuing a notice
environmental review as a part of, or
Director of OEP acting pursuant to within 90 days of the notice of an
within 90 days of, its initial notice of an
delegated authority, may also declare a application describing the schedule that
application. Therefore, agencies will
schedule for final decisions on will apply to the environmental review
outstanding requests for Federal know, relatively early in the processing
process conducted by the Commission
authorizations. When a schedule is of all applications, where they stand
to ensure compliance with the National
established, it will comply with with respect to due dates for their final
Environmental Policy Act of 1969
agencies’ applicable schedules (NEPA).13 This notice of the schedule decisions on requests for Federal
established by Federal law.12 The NOPR for the environmental review will state, authorizations.16
stated that in the event the Commission among other milestones, the anticipated 16. Commenters expressed the
or the Director of OEP does not set a date for the Commission’s completion of concern that the Commission could
schedule for a particular project in the its EA or final environmental impact reach a decision on a schedule for
notice or at a later date, the default statement (EIS).14 This NEPA notice will agency action without first considering
deadline for decisions by those agencies thus serve to inform agencies without a 15 This flexibility should alleviate the concern of
without applicable schedules schedule established by Federal law of commenters such as the City of Fall River,
established by Federal law will be no the projected date by which they are to Massachusetts, regarding situations where
reach a decision on requested apparently straightforward issues are discovered
all necessary technical information. Baker Botts and authorizations, i.e., within 90 days after during the course of analysis to be more complex
INGAA call attention to difficulties that may be and time-consuming than originally anticipated.
presented by compelling a project sponsor to file a
the anticipated issuance of the 16 The New Jersey DEP recommends that each

permit under the Clean Air Act contemporaneously Commission’s EA or final EIS. Section State agency reviewing a request for a Federal
with an NGA section 3 or 7 application. Such 157.9 is revised accordingly. authorization be provided with formal notice of the
difficulties should be alleviated by the 14. Under this approach, there is no date the Commission issues a final environmental
modifications that this Final Rule makes to the document, arguing that ‘‘[w]ithout formal notice
filing requirements as proposed in the NOPR.
longer any distinction—as was . . . a State agency will not know that the 90-day
Provided a project sponsor presents good cause for review period for a decision has begun.’’ New Jersey
not submitting a particular authorization request by 13 42 U.S.C. 4321–4347 (2005). DEP’s Comments at 1 (July 28, 2006). In view of the
the time an application is submitted, the 14 Ithas been the Commission’s experience that Commission’s commitment to issue a formal notice
Commission stands ready to accept the application. in processing applications for certain minor and of the schedule for the environmental review,
11 Section 157.9 is revised by this Final Rule to routine projects, the Commission’s assessment, agencies should have adequate notice of the
state that in calculating this deadline, only days including its NEPA review, can often be completed anticipated start date of the last 90 days of the
during which the Commission is open for business within 90 days. For such projects, the Commission review period applicable to those agencies without
rmajette on PROD1PC67 with RULES1

are counted. will either include a notice of the environmental a schedule set by Federal law. State and Federal
12 In response to a query by NMFS, the schedule in conjunction with the notice of the agencies and officers are urged to make use of the
Commission states it interprets the reference in application (i.e., the initial notice issued within 10 Commission’s eSubscription service as a means to
EPAct 2005 section 313(c)(1)(B) to ‘‘Federal law’’ to days of an application’s being filed with the monitor documents submitted in a proceeding,
consist of schedules specified either in the United Commission), or will issue a separate notice of the updates, and the date of issuance of the
States Code or in the Code of Federal Regulations. environmental schedule shortly thereafter. Commission’s EA or final EIS.

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00040 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations 62915

agency comments on authorization 180 days requested would be advance of deadlines allotted by Federal
requests. As discussed below, agencies’ incompatible with the EPAct 2005 law. The NOPR stated the aspiration
reports on authorization requests will mandate to ‘‘ensure expeditious that agencies might continue to do so,
still be due within 30 days of the receipt completion’’ of NGA section 3 and 7 recognizing that in exercising its new
of such requests. In addition, it is proceedings.19 On the other hand, the authority to set schedules, the
expected that project sponsors will Commission finds no reason to adopt a Commission can only encourage
submit as many requests for necessary 30-day requirement. Comments in favor agencies to act in advance of deadlines
Federal authorizations as possible by advocate harmonizing the amount of set by Federal law, it cannot compel
the time an application is filed with the time provided for agencies to act with them to do so.
Commission. Therefore, in most cases the 30 days from issuance of a 20. The Army COE states that the
the Commission will have Commission order currently provided deadlines established by the
approximately 60 days to consider for filing a request for rehearing or Commission for final agency action will
agency comments in advance of issuing accepting a certificate. The Commission be ‘‘voluntary and non-binding.’’ 22 This
the notice of its schedule for the sees no need to do so, as there is no would be the case if, as discussed above,
environmental review, enabling the evidence that project sponsors are the schedule set by the Commission
Commission to review agencies’ input currently hindered in reaching calling for a shorter time frame did not
in setting the milestones for the decisions on whether to seek rehearing meet the EPAct 2005 requirement that it
completion of the Commission’s of the Commission’s orders or accept a ‘‘comply with applicable schedules
environmental review.17 certificate when other agencies take established by Federal law.’’ 23
17. The Conservation Law Foundation more than 30 days after an order to However, if an agency without a
requests doubling the 90 days following complete action on authorization schedule established by Federal law
the issuance of the Commission’s final requests. The Commission believes that fails to meet a deadline set by the
environmental document to 180 days, the 90 days provided strikes an Commission, this ‘‘failure of the agency
whereas INGAA and interstate pipelines appropriate balance between providing to take action * * * in accordance with
promote reducing the time to 30 days. adequate time for agencies’ deliberation the Commission schedule established
The Conservation Law Foundation and avoiding delay to project sponsors. pursuant to section 15(c) shall be
points out that a final decision on a 18. The NOPR observed that: considered inconsistent with Federal
request for a necessary Federal In some cases—for example, when there is Law,’’ and as a result, can be brought to
authorization may not be reached a demonstrated need to have a new natural the attention of the United States Court
within 90 days of the issuance of the EA gas project in service by a certain date—the of Appeals, which can ‘‘remand the
or EIS. The Commission acknowledges Commission may set deadlines that are proceeding to the agency to take
that although infrequent, this can occur. shorter than the maximum times permitted appropriate action consistent with the
However, the Commission expects that under Federal law. In such cases, the order of the Court’’ by the ‘‘schedule
Commission recognizes that compliance with and deadline for the agency to act on
project sponsors’ increasing use of the its specified deadlines would be voluntary
Commission’s prefiling consultation for agencies with deadlines determined by
remand’’ that will be set by the court.24
process, in conjunction with the Federal law.20 Informing the Commission Upon
regulatory revisions instituted herein, 19. Several commenters contend this Receipt of an Authorization Request
will eliminate such delayed observation conflicts with Federal law.
authorization decisions.18 Further, the In setting a schedule for agencies to 21. New § 385.2013 specifies that
Commission believes that providing the conclude their reviews of requests for within 30 days of receiving an
Federal authorization, the Commission authorization request, an agency must
17 As noted above, in minor and routine cases
has no ability to contract or expand a inform the Commission of: (1) Whether
where issues that might complicate agencies’
schedule established by Federal law. the agency deems the application to be
reviews are unlikely to arise, the Commission may ready for processing and, if not, what
issue notice of its environmental schedule in its Consequently, there can be no conflict
initial notice of the filing of an application or between a schedule set by the additional information or materials will
shortly thereafter. However, if concerns regarding Commission and a schedule set by be necessary to assess the merits of the
authorization requests are subsequently raised in
Federal law.21 The Commission’s request; (2) the time the agency will
agency reports to the Commission, the Commission allot the applicant to provide the
would then reconsider the given time frames. In observation in the NOPR was no more
determining whether a proposal qualifies as minor than an acknowledgment of current necessary additional information or
and routine, and thereby suitable for processing on practice. Agencies frequently complete materials; (3) what, if any, studies will
an accelerated schedule, EPA recommends the
their review of certain project be necessary in order to evaluate the
Commission first consult with the other agencies request; (4) the anticipated effective date
that will be involved. The Commission expects proposals—most often for modest and
such projects to be readily identifiable or identified uncontroversial facilities—well in of the agency’s decision; and (5) if
in the course of a prefiling consultation. The
22 Army COE’s Comments at 3 (July 31, 2006).
Commission will not identify a proposal as a 19 EPAct 2005 section 313(c)(1)(A) (2005).
candidate for accelerated processing unless it is 23 EPAct 2005 section 313(c)(1)(B) (2005).
confident of consensus among agencies that it 20 71 FR 30632 at 30635 (May 30, 2006); FERC 24 EPAct 2005 section 313(d)(2) and (3). Note this
merits such treatment. An agency may object to any Stats. & Regs. ¶ 32,601 at 32,558 (2006); 115 FERC described civil action for the review of an agency’s
schedule set by the Commission, and the ¶ 61,203 at P 17 (2006). alleged failure to act on a requested authorization
Commission will reassess the grounds for its 21 Baker Botts raises a related issue in requesting does not apply to CZMA determinations, since the
determination. clarification that an agency presented with an Department of Commerce, not a Federal court, is the
18 The Commission notes that for the most part, authorization request must not be permitted to body to review a failure to act on, or the outcome
instances in which final decisions on requests for await the outcome of another agency’s action prior of, a CZMA request. This section of EPAct 2005 was
necessary Federal authorizations have not been to commencing its own review. While such an recently discussed and applied in Islander East
reached within the 90-day time frame designated approach might be viewed as contrary to EPAct Pipeline Co. LLC v. Connecticut Department of
herein, have involved authorizations for which a 2005’s expressed intent to expedite the review Environmental Protection, Docket No. 05–4139–ag
rmajette on PROD1PC67 with RULES1

schedule for agency action is established by Federal process for proposed gas projects, provided the (2d Cir. Oct. 5, 2006); the court found a State agency
law, e.g., a Coastal Zone Management Act (CZMA) agency in waiting is able to meet its deadline to acting under delegated Federal authority had not
consistency determination or a water quality reach a final decision—be it established by Federal conducted a complete and reasoned review of a
certification under section 401 of the Clean Water law or by the Commission—there would not request for a Federal authorization, and required the
Act (CWA). Nothing in this Final Rule will alter necessarily be cause to seek to compel the state agency to either do so within 75 days or
schedules set by Federal law. recalcitrant agency to commence its review sooner. abdicate its delegated Federal authority.

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00041 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
62916 Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations

applicable, the schedule set forth by may deny the request.26 In turn, the of the modification with the
Federal law for the agency to act. Commission may deny the application Commission—regardless of whether the
Further, if an agency asks for additional before it, or authorization to commence Commission has approved the
information, the agency is to provide the construction, due to the project application or whether the modification
Commission with a copy of its data sponsor’s failure to obtain a necessary would require amendment of the
request.25 Federal authorization. The Commission proposal before the Commission.
22. Commenters claim that 30 days is reiterates that whether an agency finds NiSource requests the Commission
an unreasonably short time to be able to a request complete has no bearing on clarify that a material modification
render a meaningful assessment of an the agency’s allotted response time. would include a modification to an
authorization request. The Commission That said, the Commission does not aspect of the proposal that would
recognizes that 30 days will often be expect to have to frequently reject NGA substantially change the overall
insufficient for agencies to reach applications due to imperfections in environmental impacts. The
definitive conclusions on each of the requests for related Federal Commission accepts this
stipulated aspects of an authorization authorizations in view of the decision to characterization. Following a project
request. But that is not the intent. revise the procedural schedule, as sponsor’s notice to the Commission of a
Instead, the information submission is described above, to tie agencies’ material modification, it will be within
intended to give the Commission an deadlines to issuance of the EA or final the discretion of the Director of OEP to
overview to enable it to determine a EIS. This approach to scheduling should determine whether the modification
realistic timetable for the environmental give agencies and applicants adequate will make it impossible for an agency to
review process. The Commission advance notice of when decisions on reach a final decision on a request for
recognizes that agencies’ reports will requests for Federal authorizations will a Federal authorization within 90 days
necessarily be provisional and subject to be due, and motivate project sponsors to of the issuance of the Commission’s
change, and will take this into account make all necessary information final environmental document.27 If so,
both when first determining a schedule available in order for agencies to reach pursuant to § 375.308, the Director of
for its NEPA review, and thereafter, to timely decisions on the merits. OEP may establish a revised, separate
take into account agencies’ progress in 25. The Army COE asks if submitting deadline for a final decision by that
processing authorization requests. an electronic copy to the Commission of agency. Finally, a material modification
the agency’s response to a project to a project pending approval by the
23. For the purpose of measuring the
sponsor’s authorization request would Commission may merit revising and re-
time for an agency to act on an
satisfy the § 385.2013 reporting noticing the schedule for the
authorization request, in the NOPR the
requirement. It would, provided the environmental review. The schedule for
Commission explained the clock begins
submission contains the specified agencies to complete their reviews
to run on the day a request is submitted
information; moreover, as discussed would then be adjusted in accordance
to the agency. Interior questions
herein, submission to the Commission with the revised schedule for
whether this would be the day a request
need not be by electronic means. completing the NEPA process.
is sent or the day it is received; the
Regardless of whether an agency’s 27. The New Jersey DEP suggests that
Commission clarifies that the day the
submission is made electronically or by in submitting a request for a necessary
agency receives a request is the first day
paper copy, it should be filed in the PF Federal authorization for an NGA
counted. This is unlikely to be the day
or CP docket number, if available, section 3 or 7 project, the project
an agency takes official notice that a
assigned to the project sponsor’s sponsor identify the request as such.
complete application has been received
application to the Commission. The Commission endorses this
and is ready for processing; rather, this
will be the first day an agency is in Procedural Clarifications suggestion, and urges project sponsors
receipt of a formal written request by a to include the Commission’s applicable
26. Once an application is filed with
project sponsor for an authorization PF or CP docket number, if available, in
the Commission and a schedule is
needed for a prospective NGA section 3 its authorization request. Identifying the
established, if a project sponsor seeks to
or 7 project. proposed project in this manner, and
make a modification to its proposal that
24. Commenters are concerned with informing the agency that the request is
is material to one or more of its
the prospect that an agency might being submitted in conjunction with an
requested Federal authorizations, the
receive a cursory authorization request application to the Commission, will
project sponsor should file a description
that could not be evaluated absent alert the agency of the need to inform
additional information. The NOPR 26 This presumably would be the outcome with the Commission of its receipt of the
stated that if an agency deems a request respect to an authorization required for a project if, request, pursuant to new § 385.2013.
to be incomplete, and the project as the Oregon Coastal Management Program and Agencies, in turn, in submitting a report
Coastal States Organization speculate, the agency is to the Commission on the status of a
sponsor fails to provide the necessary unable to obtain all the information needed to make
information in time for the agency to an appropriate assessment of the proposal in time
requested Federal authorization, should
reach a decision by the Commission’s to meet the scheduled deadline for a final decision. identify the party submitting the
scheduled deadline, then the agency Dominion requests that if an agency informs the request, identify the proposed project,
Commission that a project sponsor has not and include, if available, the applicable
adequately supported its request, then ‘‘the
25 This establishes the minimum information Commission will give the applicant an opportunity
PF or CP docket number.
required of an agency. EPA, Duke, and Islander East to respond and cure the alleged deficiencies.’’
suggest a more collaborative approach to establish Dominion’s Comments at 11 (July 31, 2006). In the 27 As one such instance, the Army COE describes

a schedule. To this end, the Commission invites event of a disagreement regarding the adequacy of circumstances where a project sponsor made a
agencies to go beyond the requisite minimum and the contents of a request for a Federal authorization, material modification that impacted the
provide additional information, which the the Commission may find reason to revise an authorization request under consideration by the
rmajette on PROD1PC67 with RULES1

Commission will consider in exercising its agency’s deadline for a final decision. However, Army COE after the Commission’s final EIS was
scheduling responsibilities. Further, in determining although the Commission implores project sponsors completed. Army COE Comments at 3 (July 31,
a schedule appropriate to a particular application, and agencies to work cooperatively, it cannot 2006). In such a case, the project sponsor should
Commission takes into account not only agencies’ compel them to do so. An agency retains the inform the Commission, and where appropriate, a
input but also the project sponsor’s proposed discretion to reject a request on the grounds that revised, separate deadline will be established for
construction schedule and in-service date. information necessary to reach a decision is lacking. the affected agency.

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00042 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations 62917

28. The New Jersey DEP and Delaware resolved and withdrawn, the ‘‘request schedule applicable to an ongoing
DNR propose making the project filed by the certificate holder shall be proceeding.
sponsor, rather than the agency treated as an application for section 7 34. Mr. Mark Mendelson is concerned
receiving a request for a Federal authorization for the particular that the Commission is creating a
authorization, responsible for activity.’’ 29 However, although a ‘‘standardized’’ schedule that will not
submitting to the Commission the protested blanket project proposal is allow for an adequate assessment of
agency’s initial 30-day status report and treated as an application for a case- safety risks and long-term project
any data requests. The Commission sees specific certificate, once the merits of impacts of proposed gas projects on
disadvantages in having the project the issues raised in the protest are individuals and communities. Mr.
sponsor assume this responsibility. In addressed, and provided the proposal is Mendelson expresses general
part, the aim of the 30-day report is to not denied, the project is authorized dissatisfaction regarding the content,
open, or extend, the dialogue between under the project sponsor’s existing timing, and availability of information
the agency and the Commission, since blanket certificate.30 A project sponsor concerning proposed projects. He
the Commission expects to confer with that makes a prior notice filing for a contends that affected individuals do
the responsible agencies over the course proposed project to be constructed not always receive adequate notice of
of the NEPA review process. Initial under blanket certificate authority is proposed projects and suggests all
contact would not necessarily be acting under the authority of its existing potential stakeholders be notified by
established early were the project blanket certificate issued pursuant to mail via the United States Postal Service
sponsor to act as an intermediary NGA section 7(c). Consequently, to of potential hazards or risks in their
between agencies and the Commission. undertake projects that comply with the general locale posed by a proposed
The burden on agencies to copy the blanket certificates provisions, the project.
Commission on a data request sent to a project sponsor does not need to obtain 35. The Commission’s new reporting
project sponsor is minimal; thus, the an additional, separate NGA section 7(c) requirements and commitment to issue
Commission finds that rather than certificate. Therefore, the new a notice of the environmental review
having project sponsors receiving an regulatory requirements promulgated schedule should serve to inform
agency’s data request forward it on, it is herein pursuant to EPAct 2005 will not potentially interested persons of a
better, in terms of timing and simplicity, apply to projects authorized pursuant to pending project proposal. The
to have the agency that generates the the blanket certificate program. Commission expects that its authority to
data request submit it directly to the establish schedules will lead to tailoring
32. The City of Fall River, milestones appropriate to the
Commission.
29. NMFS suggests the Commission Massachusetts, the Massachusetts particularities of proposed projects, and
serve as a central point of contact EOEA, and the Massachusetts Attorney not to a one-size-fits-all standard. Mr.
linking project sponsors to agencies. General seek clarification on how the Mendelson’s proposal to review and
The Commission sees no benefit to Federal NEPA review and the revise the existing public notice
placing itself between the company environmental review undertaken by a requirements is beyond the scope of and
seeking to develop a new project and State or the District of Columbia may is not germane to the matters being
the agencies responsible for examining interact. The different environmental addressed in this rulemaking
aspects of the proposal. As is, reviews proceed on separate proceeding. However, any affected
Commission staff maintains jurisdictional tracks, each on its own landowner that does not receive notice
communication with the project sponsor schedule and each arriving at its own of a proposed project in a docketed
and agencies from the receipt of a independent findings. However, as a proceeding as specified in the
request to make use of the prefiling practical matter, if Federal and State Commission’s regulations, or any
process through issuance of the final agencies are able to work in tandem, the individual that suspects the public
decision. result can be greater efficiencies for all notice provided is procedurally
30. The Commission declares, in concerned. Accordingly, where insufficient or substantively incomplete,
response to questions raised by INGAA possible, the Commission coordinates can bring such concerns to the
and Islander East, that the procedures its efforts with State agencies when Commission’s attention and the specific
described herein do not apply to assessing the environmental impacts of circumstances will be investigated.
activities that do not involve ‘‘an a proposed project and intends to
application for authorization under continue to do so going forward. Consolidated Record
section 3 or a certificate of public 33. Islander East seeks clarification on 36. Section 313 of EPAct 2005 directs
convenience and necessity under how the revised regulations will apply the Commission to ‘‘maintain a
section 7.’’ 28 For example, auxiliary to pending projects. The Commission, as complete consolidated record of all
installations and the replacement of a general matter, will not apply the decisions made or actions taken by the
facilities under § 2.55, and activities §§ 153.8 and 157.14 filing requirements Commission or by a Federal
authorized under the blanket certificate for project sponsors, or the § 385.2013 administrative agency or officer (or State
provisions of Part 157, subpart F, of the reporting requirements for agencies, to administrative agency or officer acting
Commission’s regulations, and certain applications filed prior to the effective under delegated Federal authority) with
activities undertaken in response to a date of this rule. That said, as noted respect to any Federal authorization.’’
gas emergency, do not require above, the Director of OEP currently has 37. The NOPR proposed to require
authorization under NGA section 3 or delegated authority to establish agencies and officers issuing decisions
issuance of a certificate under NGA schedules in pending proceedings,31 or approvals necessary for proposed
section 7. and if there is cause to do so, the projects under NGA sections 3 and 7 to
31. When a request to authorize a Director of OEP may establish a provide the Commission with a copy of
rmajette on PROD1PC67 with RULES1

proposed project under the blanket the final decision reached or action
certificate provisions is protested, and 29 18 CFR 157.205(f) (2006).
taken, or a summary thereof, within
the protest is not either dismissed or 30 See,e.g., Texas Eastern Transmission Corp., 76 three days of issuance of a final decision
FERC ¶ 61,178 (1996). or action. The Commission proposed
28 EPAct 2005 section 313(a)(3) (2005). 31 See note 7. requiring agencies and officers to file an

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00043 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
62918 Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations

index of the record, identifying all Foundation’s request to provide 43. The Army COE points out that
documents and materials—including reimbursement to agencies for expenses when it issues a requested permit, the
pleadings, comments, evidence, related to compliance with the permit with terms and conditions is sent
exhibits, transcripts of testimony, provisions of this rule. Compliance is to the applicant, which has 60 days to
project alternatives (including mandatory pursuant to the authority appeal the terms and conditions if it
alternative routings), studies, and provided to the Commission by EPAct chooses to do so; if the permit is denied,
maps—relevant to the decision, within 2005. Further, in view of the revision the applicant may appeal the denial.
three days of issuance of a final decision above regarding the time permitted and The Army COE asks that the date of
or action. means of submission, and the final agency action for purposes of
38. Commenters object to the clarification below regarding the providing the record to the Commission
proposed requirement that a copy of the contents of the index, the Commission be ‘‘at the end of any appeals process.’’
decision and an index to the record be expects the additional cost incurred by 44. The Commission expects that
filed within three days of the decision agencies to meet these new reporting individual agencies’ own regulations
and suggest that the Commission allow requirements will not be unduly will determine when their actions are
30 days for the filing of the decision and burdensome. considered ‘‘final’’ and thereby start the
record index. In addition to promoting 41. Commenters’ objections to 30-day clock for filing their decisions
a 30-day interval, the Conservation Law submitting an index appear to stem in and indices with the Commission.
Foundation recommends the part from an overly broad interpretation However, the Commission will consider
Commission reimburse agencies for of what this index must include. The a decision or action on a request for a
reasonable costs incurred in providing Commission clarifies that the index Federal authorization to be ‘‘final,’’ and
the index. need not summarize the contents of consequently subject to the 30-day
39. The Commission accepts the claim each item in the agency’s record; rather, deadline for filing with the Commission,
that three days may not provide every the index can be any method of notation if the project sponsor submitting the
agency with adequate time to organize capable of identifying each item in the request can rely on an affirmative
and send the requested information— record sufficiently to allow a reviewing determination as sufficient authority to
although, if an agency maintains and body to select items of relevance to an proceed. In other words, the agency’s
updates its index throughout the course issue on appeal. The Oregon Coastal deliberation must go beyond verification
of its proceeding, all it need do when a Management Program observes that it that a request is complete, or a
decision is issued is add the decision, preliminary determination, or an agency
typically relies on and references the
or a summary thereof, to the index and decision that approves a project
outcome of multiple state and local
submit it to the Commission. The sponsor’s application but makes its right
actions, but does not include in its
Commission anticipated agencies’ to proceed contingent on the outcome of
record the underlying documents that
submission of the requested information certain agency review or appeal
make up the record in those other
would be merely ministerial, i.e., that processes; i.e., the outcome of the
actions. There is no need for agencies
the information would be available and agency’s final decision or action must
that follow such an approach to make
electronically transmittable—or at least, grant, condition, or deny the applicant’s
any adjustment. Any methodology and
easily duplicated and then sent—on the requested authorization. At this point,
recordkeeping that an agency now
same day a final decision was reached. the 30-day period begins for an agency
employs that is sufficient to serve as the to provide the Commission with a copy
Commenters persuasively argue that this basis for appeals or reviews is an
is not the case. In any event, the of its decision, or a summary, and an
acceptable ‘‘index’’ for the purposes of index to its record in the proceeding.
Commission does not believe that it is the consolidated record. Note that in
necessary to receive an agency’s The 30-day period should permit the
filing an index, agencies should title the Commission to receive agencies’
information within three days of a final submission ‘‘Consolidated Record’’ and
decision in order to satisfy the EPAct decisions and indices in time to compile
include a prominent reference on the a complete consolidated record for the
2005 mandate to maintain a complete first page to the docket number applied
consolidated record. Accordingly, the purposes of judicial review (or in the
to the Commission proceeding which case of a CZMA determination, review
Final Rule revises the reporting gave rise to the request for agency
requirement to provide agencies and by the Department of Commerce).33
authorization. 45. The Army COE asserts the
officers 30 days, not three, to submit a 42. Baker Botts requests the
final decision, or summary thereof, and Commission should forward Freedom of
Commission require that agencies Information Act (FOIA) requests to
index to the Commission. Further, while provide the Commission with their full
the Commission encourages electronic agencies, instead of preparing a
record, and not just an index thereto. response using the consolidated record.
submissions, the proposed regulations The Commission finds no cause to
are modified to provide the option to The Commission clarifies that FOIA
require agencies to reproduce and requests should be submitted directly to
make paper filings with the transmit the contents of their entire
Commission.32 In view of this the agency responsible for generating
record to the Commission. Only in the the information in question. While an
modification to the means of filing, the event of appeal will there be any call to agency’s index filed with the
Commission will modify the time view the original or duplicate materials,
provided for agencies to file a copy of and even then it is unlikely anything 33 The Commission notes that when it issues an
data requests with the Commission, other than a limited subset of the record order granting a project sponsor a section 7
extending it from three days to 10 will be relevant. Therefore, provided an certificate or section 3 authorization under the NGA
business days. index is prepared, and original materials to construct gas facilities, clearance to commence
40. The Commission finds no cause to construction generally is withheld until the project
are retained and available for a sponsor has obtained other necessary authorizations
rmajette on PROD1PC67 with RULES1

adopt the Conservation Law minimum of three years, or until an from other agencies. However, once such
appeal or review is concluded, there authorizations have been obtained by the project
32 As is currently the case, agencies will be sponsor, the project sponsor generally is granted
expected to conform their filings to the
should be no delay in producing the clearance to commence construction,
requirements of 18 CFR 385.2003, to the extent that portion of an agency’s record requested notwithstanding any pending requests for
they are able. by a reviewing entity. rehearing.

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00044 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations 62919

Commission may be useful in OMB approve certain reporting, record in this Final Rule are: FERC–539, FERC–
identifying records relevant to a FOIA keeping, and public disclosure 537, FERC–606, and FERC–607. These
request, the Commission will not be (collections of information) are mandatory reporting requirements.
capable of effectively responding to requirements imposed by agency
FOIA requests, or other types of Public Reporting Burden
rules.34 Pursuant to OMB regulations,
requests, that concern the substantive the Commission is submitting these 47. The Commission did not receive
matters of another agency’s proceeding. reporting requirements to OMB for its specific comments concerning its
Further, the Commission’s review and approval under section burden estimates and uses the same
responsibilities under EPAct 2005 do 3507(d) of the Paperwork Reduction Act
not include compiling documents to estimates here in the Final Rule. Several
of 1995 (PRA).35 Upon approval of a commenters expressed concern with the
respond to FOIA requests. The
collection of information, OMB will burden that would be imposed if
Commission does not expect to receive
assign an OMB control number and an information was required to be
or respond to FOIA requests, unless the
information sought is part of the expiration date. Respondents subject to submitted under the initially proposed
Commission’s own record of its the filing requirements of this rule will time frame. However, as discussed
deliberations in a particular proceeding. not be penalized for failing to respond herein, the Commission has taken these
to these collections of information comments into consideration and
Information Collection Statement unless the collections of information extended the time frame for submitting
46. The Office of Management and display a valid OMB control number. information.
Budget (OMB) regulations require that The information collection requirements

Number of re- Number of re- Hours per re-


Data collection Total hours
spondents sponses sponse

FERC–537 ....................................................................................................... 76 815 0.5 408


FERC–539 ....................................................................................................... 12 12 0.5 6
FERC–606 ....................................................................................................... 48 1702 4.4 7,489
FERC–607 ....................................................................................................... 48 1654 6.3 10,423

Totals ........................................................................................................ ........................ ........................ ........................ 18,326

Total Annual Hours for Collection: Necessity of Information: EPAct 2005 Environmental Analysis
18,326. section 313 directs the Commission to 49. The Commission is required to
Information Collection Costs: Because (1) establish schedules for State and prepare an Environmental Assessment
of the regional differences and the Federal agencies and officers to act on or an Environmental Impact Statement
various staffing levels that will be requests for Federal authorizations for any action that may have a
involved in preparing the required for natural gas projects under significant adverse effect on the human
documentation (legal, technical, and sections 3 and 7 of the NGA and (2) environment.36 No environmental
support), the Commission is using an maintain a complete consolidated consideration is raised by promulgation
hourly rate of $150 to estimate the costs record of all decisions or actions taken of a rule that is procedural in nature or
for filing and other administrative by the Commission and other agencies that does not substantially change the
processes (reviewing instructions, and officers with respect to such effect of legislation or regulations being
searching data sources, completing and authorizations. The Commission amended.37 The regulations adopted
transmitting the collection of considers the regulatory provisions herein require authorizing agencies to
information). The estimated cost is adopted herein to be the minimum provide the Commission with copies or
$2,748,900. necessary for the Commission to summaries of decisions and indices to
Title: FERC–539 ‘‘Gas Pipeline implement the new authority provided the records of those decisions in cases
Certificates: Import/Export Related;’’ by EPAct 2005. arising under the Commissions
FERC–537 ‘‘Gas Pipeline Certificates: 48. For information regarding the jurisdiction under the Natural Gas Act.
Construction, Acquisition and requirements of the collections of These are minor procedural changes to
Abandonment;’’ FERC–606 ‘‘Gas information and the associated burden the Commission’s existing regulations
Pipeline Certificates: Notification of estimates, including suggestions for and do not substantially change the
Request for Federal Authorization;’’ and reducing this burden, please send effect of any legislation or regulations.
FERC–607 ‘‘Report on Decision or comments to the Federal Energy Nor do they substantially change any
Action on Request for Federal Regulatory Commission, 888 First regulatory requirements to which
Authorization.’’ Street, NE., Washington, DC 20426 pipeline companies or authorizing
Action: Data Collection. (Attention: Michael Miller, Office of the agencies are currently subject.
OMB Control No.: FERC–539 (1902– Executive Director), or send e-mail to Accordingly, the preparation of an
0062); FERC–537 (1902–0060); FERC– michael.miller@ferc.gov), or to the environmental document is not
606 and FERC–607 (To be determined). Office of Management and Budget required.
Respondents: Natural gas pipeline (Attention: Desk Officer for the Federal
companies and state agencies and Energy Regulatory Commission), by fax Regulatory Flexibility Act Certification
officers. to (202) 395–7285, or by e-mail to 50. The Regulatory Flexibility Act of
rmajette on PROD1PC67 with RULES1

Frequency of Responses: On occasion. oira_submission@omb.eop.gov. 1980 (RFA) 38 generally requires a


34 5 CFR 1320.11 (2006). 36 Order No. 486, Regulations Implementing the 37 18 CFR 380.4(a)(2)(ii) (2006).
35 44 U.S.C. 3507(d) (2005). National Environmental Policy Act, 52 FR 47897 38 5 U.S.C. 601–612 (2005).
(Dec. 17, 1987), FERC Stats. & Regs. Preambles
1986–1990 ¶ 30,783 (1987).

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00045 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
62920 Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations

description and analysis of final rules impact on a substantial number of small By the Commission.
that will have significant economic entities. Magalie R. Salas,
impact on a substantial number of small Secretary.
Document Availability
entities. The Commission is not ■ In consideration of the foregoing, the
required to make such an analysis if 53. In addition to publishing the full
Commission amends parts 153, 157,
proposed regulations would not have text of this document in the Federal
375, and 385, Chapter I, Title 18, Code
such an effect. Register, the Commission provides all
of Federal Regulations, as follows:
51. Although it appears that agencies interested persons an opportunity to
affected by the rule promulgated today view and print the contents of this PART 153—APPLICATIONS FOR
do not fall within the RFA’s definition document via the Internet through AUTHORIZATION TO CONSTRUCT,
of ‘‘small governmental jurisdiction’’ 39 FERC’s Home Page (http://www.ferc.gov) OPERATE, OR MODIFY FACILITIES
or its definition of ‘‘small entities,’’ 40 and in FERC’s Public Reference Room USED FOR THE EXPORT OR IMPORT
the Commission is nevertheless mindful during normal business hours (8:30 a.m. OF NATURAL GAS
of costs and burdens to be imposed to 5 p.m. eastern time) at 888 First
upon agencies required to provide Street, NE., Room 2A, Washington DC ■ 1. The authority citation for part 153
copies of decisions and indexes to the 20426. From FERC’s Home Page on the continues to read as follows:
record in Federal authorization Internet, this information is available in Authority: 15 U.S.C. 717b, 717o; E.O.
proceedings. In response to commenters the Commission’s document 10485, 3 CFR, 1949–1953 Comp., p. 970, as
that observe certain agencies may lack management system, eLibrary. The full amended by E.O. 12038, 3 CFR, 1978 Comp.,
the resources needed to comply with the text of this document is available in p. 136, DOE Delegation Order No. 0204–112,
proposed three-day deadline for filing eLibrary in PDF and Microsoft Word 49 FR 6684 (February 22, 1984).
and the proposed requirement for format for viewing, printing, and ■ 2. In subpart B, § 153.4 is added to
electronic filing, the Commission is downloading. To access this document read as follows:
adopting alternative requirements to in eLibrary, type RM06–1 in the docket
take into account the resources available number field. § 153.4 General requirements.
to the agencies to accommodate the 54. User assistance is available for The procedures in §§ 157.5, 157.6,
limited resources of small entities.41 eLibrary and the Commission’s Web site 157.8, 157.9, 157.10, 157.11, and 157.12
The three-day deadline is extended to during normal business hours at (202) of this chapter are applicable to the
30 days, and electronic filing, while still 502–8222 or the Public Reference Room applications described in this subpart.
the preferred option, is no longer at (202) 502–8371 Press 0, TTY (202) ■ 3. In § 153.8:
required. 502–8659. E-Mail the Public Reference ■ a. The word ‘‘and’’ is removed from
52. Most of the natural gas companies Room at public.referenceroom@ferc.gov. the end of paragraph (a)(7);
regulated by the Commission do notfall Effective Date and Congressional ■ b. The period is removed from the end
within the RFA’s definition of a small Notification of paragraph (a)(8), and ‘‘; and’’ is added
entity.42 Approximately 114 natural gas in its place; and
55. These regulations are effective ■ c. Paragraph (a)(9) is added to read as
companies are potential respondents
December 26, 2006. follows:
subject to the requirements adopted by
56. The Commission has determined,
this rule. For the year 2004 (the most
with the concurrence of the § 153.8 Required exhibits.
recent year for which information is
Administrator of the Office of (a) * * *
available), 32 companies had annual
Information and Regulatory Affairs of (9) Exhibit H. A statement identifying
revenues of less than $6.5 million. The
OMB, that this rule is not a ‘‘major rule’’ each Federal authorization that the
procedural modifications enacted herein
as defined in Section 351 of the Small proposal will require; the Federal
should have no significant economic
Business Regulatory Enforcement agency or officer, or State agency or
impact on those entities—be they large
Fairness Act of 1996.43 officer acting pursuant to delegated
or small—subject to the Commission’s
NGA jurisdiction. In view of these List of Subjects Federal authority, that will issue each
considerations, the Commission certifies required authorization; the date each
18 CFR Part 153 request for authorization was submitted;
that this Final Rule’s amendments to the
regulations will not have a significant Exports, Imports, Natural gas, why any request was not submitted and
Reporting and recordkeeping the date submission is expected; and the
39 5 U.S.C. 601(5) (2005) provides that ‘‘the term requirements. date by which final action on each
‘small governmental jurisdiction’ means Federal authorization has been
governments of cities, counties, towns, townships,
18 CFR Part 157 requested or is expected.
villages, school districts, or special districts, with Administrative practice and * * * * *
a populations of less than fifty thousand.’’ procedure, Natural gas, Reporting and
40 5 U.S.C. 601(6) (2005) provides that ‘‘the term

‘small entity’ shall have the same meaning as the


recordkeeping requirements. PART 157—APPLICATIONS FOR
terms ‘small business,’ ‘small organization,’ and CERTIFICATES OF PUBLIC
18 CFR Part 375
‘small governmental jurisdiction.’ ’’ CONVENIENCE AND NECESSITY AND
41 5 U.S.C. 603(c)(1) and (2) (2005). Authority delegations (Government FOR ORDERS PERMITTING AND
42 See 5 U.S.C. 601(3) (2005), citing section 3 of agencies), Seals and insignia, Sunshine APPROVING ABANDONMENT UNDER
the Small Business Act, 15 U.S.C. 623 (2005). Act.
Section 3 of the SBA defines a ‘‘small business
SECTION 7 OF THE NATURAL GAS
concern’’ as a business which is independently 18 CFR Part 385 ACT
owned and operated and which is not dominant in
its field of operation. The Small Business Size Administrative practice and ■ 4. The authority citation for part 157
rmajette on PROD1PC67 with RULES1

Standards component of the North American procedure, Electric power, Penalties, continues to read as follows:
Industry Classification System defines a small Pipelines, Reporting and recordkeeping
natural gas pipeline company as one that transports Authority: 15 U.S.C. 717–717w.
natural gas and whose annual receipts (total income requirements.
plus cost of goods sold) did not exceed $6.5 million ■ 5. In § 157.9:
for the previous year. 43 5 U.S.C. 804(2) (2005). ■ a. The section heading is revised;

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00046 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1
Federal Register / Vol. 71, No. 208 / Friday, October 27, 2006 / Rules and Regulations 62921

■ b. The existing text is designated as § 375.308 Delegations to the Director of to delegated Federal authority,
paragraph (a) and the word ‘‘business’’ the Office of Energy Projects. considering a request for a Federal
is added immediately before the phrase * * * * * authorization that submits a data
‘‘days of filing’’; and (bb) Establish a schedule for each request to an applicant must file a copy
■ c. A new paragraph (b) is added, to
Federal agency or officer, or State of the data request with the Commission
read as follows: agency or officer acting pursuant to within 10 business days.
delegated Federal authority, to issue or
§ 157.9 Notice of application and notice of deny Federal authorizations required for § 385.2014 Petitions for appeal or review
schedule for environmental review. natural gas projects subject to section 3 of Federal authorizations (Rule 2014).
* * * * * or 7 of the Natural Gas Act.
(a) For each Federal authorization—
(b) For each application that will PART 385—RULES OF PRACTICE AND i.e., permit, special use authorization,
require an environmental assessment or PROCEDURE certification, concurrence, opinion, or
an environmental impact statement, other approval—required under Federal
notice of a schedule for the ■ 10. The authority citation for part 385 law with respect to a natural gas project
environmental review will be issued continues to read as follows: for which an application has been filed
within 90 days of the notice of the Authority: 5 U.S.C. 551–557; 15 U.S.C. for authorization under section 3 of the
application, and subsequently will be 717–717z, 3301–3432; 16 U.S.C. 791a–825r, Natural Gas Act for a certificate of
published in the Federal Register. 2601–2645; 28 U.S.C. 2461; 31 U.S.C. 3701, public convenience and necessity under
■ 6. In § 157.14, paragraph (a)(12) is 9701; 42 U.S.C. 7101–7352; 49 U.S.C. 60502;
49 App. U.S.C. 1–85 (1988).
section 7 of the Natural Gas Act, the
added to read as follows: Federal agency or officer, or State
§ 157.14 Exhibits.
■ 11. Section 385.2013 is redesignated agency or officer acting pursuant to
as § 385.2015 and the heading of newly delegated Federal authority, responsible
(a) * * * designated § 385.2015 is revised to read for each Federal authorization must file
(12) Exhibit J—Federal authorizations. as follows: with the Commission within 30 days of
A statement identifying each Federal § 385.2015 Videotapes (Rule 2015). the effective date of a final decision or
authorization that the proposal will action on a request for a Federal
require; the Federal agency or officer, or * * * * *
authorization or the expiration of the
State agency or officer acting pursuant ■ 12. New §§ 385.2013 and 385.2014 are
added to read as follows: time provided by the Commission or by
to delegated Federal authority, that will Federal law for a final decision or
issue each required authorization; the § 385.2013 Notification of requests for action, the following:
date each request for authorization was Federal authorizations and requests for
submitted; why any request was not further information (Rule 2013). (1) A copy of any final decision or
submitted and the date submission is (a) For each Federal authorization— action;
expected; and the date by which final i.e., permit, special use authorization, (2) An index identifying all
action on each Federal authorization has certification, concurrence, opinion, or documents and materials—including
been requested or is expected. other approval—required under Federal pleadings, comments, evidence,
* * * * * law with respect to a natural gas project exhibits, testimony, project alternatives,
for which an application has been filed studies, and maps—relied upon by the
■ 7. In subpart A, § 157.22 is added to under section 3 of the Natural Gas Act
read as follows: agency or official in reaching a decision
for a certificate of public convenience or action; and
§ 157.22 Schedule for final decisions on a and necessity under section 7 of the
(3) The designation ‘‘Consolidated
request for a Federal authorization Natural Gas Act, each Federal agency or
officer, or State agency or officer acting Record’’ and the docket number for the
For an application under section 3 or pursuant to delegated Federal authority, Commission proceeding applicable to
7 of the Natural Gas Act that requires a responsible for a Federal authorization the requested Federal authorization.
Federal authorization—i.e., a permit, must file with the Commission within (b) The agencies’ and officers’
special use authorization, certification, 30 days of the date of receipt of a decisions, actions, and indices, and the
opinion, or other approval—from a request for a Federal authorization, Commission’s record in each
Federal agency or officer, or State notice of the following: proceeding, constitute the complete
agency or officer acting pursuant to (1) Whether the application is ready
delegated Federal authority, a final consolidated record. The original
for processing, and if not, what documents and materials that make up
decision on a request for a Federal additional information or materials will
authorization is due no later than 90 the complete consolidated record must
be necessary to assess the merits of the be retained by agencies, officers, and the
days after the Commission issues its request;
final environmental document, unless a (2) The time the agency or official will Commission for at least three years from
schedule is otherwise established by allot the applicant to provide the the effective date of a decision or action
Federal law. necessary additional information or or until an appeal or review is
materials; concluded.
PART 375—THE COMMISSION (3) What, if any, studies will be (c) Upon appeal or review of a Federal
necessary in order to evaluate the authorization, agencies, officers, and the
■ 8. The authority citation for part 375 request; Commission will transmit to the
continues to read as follows: (4) The anticipated effective date of reviewing authority, as requested,
Authority: 5 U.S.C. 551–557; 15 U.S.C. the agency’s or official’s decision; and
rmajette on PROD1PC67 with RULES1

documents and materials that constitute


717–717w, 3301–3432; 16 U.S.C. 791–825r, (5) If applicable, the schedule set by
the complete consolidated record.
2601–2645; 42 U.S.C. 7101–7352. Federal law for the agency or official to
act. [FR Doc. E6–18025 Filed 10–26–06; 8:45 am]
■ 9. In § 375.308, paragraph (bb) is (b) A Federal agency or officer, or BILLING CODE 6717–01–P
added to read as follows: State agency or officer acting pursuant

VerDate Aug<31>2005 14:48 Oct 26, 2006 Jkt 211001 PO 00000 Frm 00047 Fmt 4700 Sfmt 4700 E:\FR\FM\27OCR1.SGM 27OCR1

S-ar putea să vă placă și