Sunteți pe pagina 1din 184

ELEMENTS OF A

HYDROPOWER
FEASIBILITY STUDY
INTRODUCTION TO SELECTED TOPICS
RELEVANT FOR HYDROPOWER
PROJECT FEASIBILIT Y ANALYSIS
Sven Homscheid

29 t h April 2014
Georgetown, Guyana

Hydropower Consultant
1

OUTLINE

Elements of a hydropower feasibility study

Hydrological aspects of hydropower projects inflow


series

Hydrologic data collection campaigns

Exercise 1: Design of hydrometric gauging stations

Geotechnical investigations for hydropower feasibility


analysis

Principles of good project layout design

Exercise 2: Development of a project layout

Economic analysis and sensitivity analysis

Environmental and Social Considerations

Drawing conclusions from the results, question and


answer session

ELEMENTS OF A
HYDROPOWER
FEASIBILITY STUDY

ELEMENTS OF A HYDROPOWER FEASIBILIT Y STUDY


What is a Feasibility Study?
Wikipedia:
The feasibility study is an evaluation and analysis of the
potential of a proposed project which is based on extensive
investigation and research to support the process of decision
making.
Hydropower context:
The FS helps to decide if it makes sense to invest in a project.
The FS also helps to identify the best design option for the
project.
The decision is based on technical, economic, environmental
and social analysis.
4

ELEMENTS OF A HYDROPOWER FEASIBILIT Y STUDY


What is the context of a Feasibility Study?
Typical project development sequence:
1. Project identification
2. Pre-Feasibility Study
3. Feasibility Study
4. Application for project approval from authorities
5. Seeking of project financing
6. Additional studies as may be required
7. Detailed design or tender design and tender documents
8. Tendering and award of contract
9. Construction design
10. Construction As Built drawings
11. Commissioning and operation
5

ELEMENTS OF A HYDROPOWER FEASIBILIT Y STUDY


What does a Feasibility Study contain?
(1) Technical Project Analysis

Topography
Hydrology and Sedimentology
Geology
Design Study: selection of optimum design
Quantity estimate
Cost estimate
Power Output

(2) Power Market Analysis

Analysis of market regulation


Options for power off-taking and marketing
Marketing cost
Sales revenue projection

ELEMENTS OF A HYDROPOWER FEASIBILIT Y STUDY


What does a Feasibility Study contain? (continued)
(3) Economic Project Analysis

Cost / Benefit Analysis


Net Present Value Analysis
Internal Rate of Return Analysis
Levelized Cost of Electricity Generation Analysis
Sensitivity Analysis

(4) Environmental and Social Project Analysis


Analysis of environmental impacts and resulting project costs for
mitigation measures
Analysis of social impacts and resulting projects costs for mitigation
measures
Recommendations for environmental project monitoring plan
Recommendations for social acceptability and public communication
strategy and social monitoring plan
7

ELEMENTS OF A HYDROPOWER FEASIBILIT Y STUDY


What does a Feasibility Study contain? (continued)
(5) Risk and Opportunities Analysis (SWOT)
Strength, Weakness, Opportunities and Threads Analysis

(6) Conclusions and Recommendations


Main Finding: Is the project feasible or not?
Recommendations for further development

(7) Other contents as required

HYDROLOGICAL
ASPECTS OF
HYDROPOWER
PROJECTS
- INFLOW SERIES 9

HYDROLOGICAL ASPECTS - INFLOW SERIES


Why is good hydrological data so extremely important?
Q is one of three main parameters in the power output
equation

P=Q*H***g
Where:
P
Q
H

g
-

Power output
Discharge
Head (difference of water levels)
Plant efficiency
Density of water
Acceleration constant

10

HYDROLOGICAL ASPECTS - INFLOW SERIES

Q = flow in m3/s
Depending on
Geographic location
(rain forest or desert)

Elevation above sea level


(the higher, the wetter)

Time of the year


(rainy season or dry season)

11

HYDROLOGICAL ASPECTS - INFLOW SERIES

Hn = net head in m
Gross Head depending on
Topography

Net Head depending on


Friction losses

Mountain or valley
Dam, run-off river or
diversion

Pipe diameter/canal dimensions


Pipe/canal roughness
Length of pipe/canal

Other hydraulic losses


-

Trash rack
Bends
Valves

12

HYDROLOGICAL ASPECTS - INFLOW SERIES

= efficiency
Efficiency of
Turbine runner
-

Depending on turbine type, size and speed, quality, wear

Generator
-

Depending on type, size, speed, voltage level, age

Transformer
-

Depending on type, size, cooling system, voltage level, age

Usually: total 70 to 85 % for small hydropower


13

HYDROLOGICAL ASPECTS - INFLOW SERIES


Why is good hydrological data so extremely important?
Q is one of three main parameters in the power output
equation
Hydrology of a project is used for the power generation
prognosis
Power generation prognosis is decisive if a project is feasible
or not
Quality of hydrologic base data defines the projects risk level
and influences project financing conditions
Good hydrologic data good, reliable statistical basis for power
generation prognosis low risk level good financing conditions
Poor hydrologic database with many gaps and/or short data records
poor statistical basis for power generation prognosis high risk level
poor financing conditions, because financier will cover his risk
14

HYDROLOGICAL ASPECTS - INFLOW SERIES


What hydrological information is required for hydropower
projects?

Inflow series
= statistics on availability of water for hydropower generation
Flow Duration Curve
Power output calculation influence on project benefits

Flood discharges
HQ 50 ; HQ 100 ; HQ 1 ,000 ; HQ PMF
Design of civil structures (permanent and temporary)
Influence on project costs

Climate change impact on the two above


Trend: drier dry seasons, larger flood events
What to expect in the future
15

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to get the required hydrologic data?
Ideal:

Long-term stream flow discharge measurements at the


dam site.
Long-term?
Rule of thumb for secure statistics:
Prognosis period = 3 x record period
However:
Data from the dam site is very rarely available.
Usually only short term records are available
16

HYDROLOGICAL ASPECTS - INFLOW SERIES


What if long-term data does not exist?
Long-term stream flow data of similar catchments in the
vicinity
Rainfall data from the catchment
Rainfall data from neighboring catchments and transfer to the
dam site
Use of hydrologic models to calculate stream flow data from
rainfall data
Use available previous reports to obtain primary data and to
verify own calculations

17

HYDROLOGICAL ASPECTS - INFLOW SERIES


Where to get primary data from?
Hydrometric or hydrologic units
Meteorological office
Hydropower development department
Forestry management department
Agricultural planning department
Airports authority
Environmental management department
Any other agency collecting hydrometric data

18

HYDROLOGICAL ASPECTS - INFLOW SERIES


What kind of data is required?
Stream flow data at the dam site
Stream flow data at other sites on the same river
Stream flow data from similar watersheds
Rainfall data from the same watershed
Rainfall data from similar watersheds
Temperature data
Evaporation and evapo-transpiration data
Dew point records
Land use maps (for hydrologic model)

19

HYDROLOGICAL ASPECTS - INFLOW SERIES


How is hydrologic data analysis done?
Overarching objective:
Generation of long-term stream flow discharge series.
1. Sorting collected data and digitizing analogous data
2. Data analysis for plausibility checks
Correlation analysis
Plotting data

3. Correlation analysis for gap filling of missing data


4. Generating synthetic long-term stream flow or rainfall series
5. If no stream flow data available: Application of hydrologic
model to convert rainfall data to stream flow data
20

HYDROLOGICAL ASPECTS - INFLOW SERIES


What tools exist for statistical analysis of hydrologic data?
HEC-SSP

http://www.hec.usace.army.mil/software/hec-ssp/
21

HYDROLOGICAL ASPECTS - INFLOW SERIES


What tools exist for statistical analysis of hydrologic data?
HEC-SSP
Microsoft Excel and additional statistic ad-ons
Other commercial software like
NCSS (www.ncss.com)
HyStat (http://www.hystat.de/default_e.htm)

22

HYDROLOGICAL ASPECTS - INFLOW SERIES


What is a synthetic inflow series?
If no recorded stream flow data is available that can be used
as inflow series, an inflow series needs to be generated.
Use of hydrologic and statistical models to produce long-term
series of daily average stream flow discharge data without
gaps
Any gaps in the series will be filled by application of
statistical methods
The synthetic series must reflect the real variability of water
availability
Discharge data is referenced to the point where water is
abstracted for hydropower purposes

23

HYDROLOGICAL ASPECTS - INFLOW SERIES


How does a storage reservoir influence water availability?
Run-off river Reservoir storage
If a storage reservoir is available, storage must be simulated
to reflect
water levels,
surface evaporation and
storage volume

The ability to store water defines the possible functions of the


hydropower project:
Base load supply
Peak-load supply
Pumped storage
24

HYDROLOGICAL ASPECTS - INFLOW SERIES


What is a Flow Duration Curve?
The Flow Duration Curve (FDC) is a statistical evaluation of a
time series of stream flows to obtain its exceedance probability,
either in %, or in days per year referring to a statistically
average year.
The daily values are sorted to get the flow duration curve.
The FDC tells for how long what amount of water will be
available
The FDC is the basis to select the design (turbine) discharge
for the project

25

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to calculate a Flow Duration Curve?
1. Sort the average daily discharges for the period of record
from the largest value to the smallest, involving all values
(number of values = n).
2. Assign each discharge value a rank (M), starting with 1 for
the largest daily discharge value.
3. Calculate exceedence probability (P) as follows:
P = 100 * [ M / (n + 1) ]
P = the probability that a given flow will be equalled or
exceeded (% of time)
M = the ranked position on the listing (dimensionless)
n = the number of events for period of record (dimensionless)

26

HYDROLOGICAL ASPECTS - INFLOW SERIES


The daily values are sorted to get the flow duration curve:

As a rule of thumb:
Rural electrification E = approx. 80%
Small HPP E = approx. 30%

27

HYDROLOGICAL ASPECTS - INFLOW SERIES


Example for Flow Duration Curve calculation:
Develop 500 random numbers
from 0 to 1 and multiply by, e.g.
35 to obtain synthetic
discharges
Sort the discharges starting with
the largest
Assign rank
Calculate exceedence probability

28

HYDROLOGICAL ASPECTS - INFLOW SERIES


Example for Flow Duration Curve calculation:

29

HYDROLOGICAL ASPECTS - INFLOW SERIES


Example for Flow Duration Curve calculation:

30

HYDROLOGICAL ASPECTS - INFLOW SERIES


Example for Flow Duration Curve calculation:

31

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to use the Flow Duration Curve?
The FDC shows the flows that are available with a certain
exceedence probability
From this data all discharges that cannot be used for
hydropower are subtracted to obtain the potentially available
discharge
All discharges larger than the design discharge of the
hydropower plant are set equal to the design discharge

32

HYDROLOGICAL ASPECTS - INFLOW SERIES

Q max

33

HYDROLOGICAL ASPECTS - INFLOW SERIES

34

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to use the Flow Duration Curve?
The FDC shows the flows that are available with a certain
exceedence probability
From this data all discharges that cannot be used for
hydropower are subtracted to obtain the potentially available
discharge
All discharges larger than the design discharge of the
hydropower plant are set equal to the design discharge
The remaining values are converted into power and integrated
over the respective time intervals. For this purpose, the FDC is
often discretized in 1, 5 or 10 % steps.
The discharge is converted via the respective power curve into
power output of the plant
35

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to use the Flow Duration Curve? (continued)
For the conversion of the plants power output, the head H
changes according to the hydraulic losses in the pipes that
depend on the plant discharge
Also the plant efficiency changes with varying discharge
The plant power output is calculated for the discrete
exceedence probabilities of the FDC and integrated to obtain
the average annual electricity generation.
Abstractions are made for down times of the generators to
obtain realistic power output

36

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to calculate design flood discharges?
From (measured or synthetic) flow series frequency
distribution functions for flood discharges are developed
This is either based on maximum yearly flows or, if those are
not available, maximum monthly flows over a period of time
The longer the records, the more reliable the results
By fitting several probability distribution functions, a best
fitting function will be identified and is then used to calculate
the design flood discharges

37

HYDROLOGICAL ASPECTS - INFLOW SERIES


How to calculate design flood discharges?

38

HYDROLOGICAL ASPECTS - INFLOW SERIES


What are appropriate design flood discharges?
DIN 19700 suggests the following discharges as design
discharges for dams:
Dam category 1 (>15 m height; > 1 million m 3 volume)
Design reservoir inflow at n-1: HQ 1 ,000
Design reservoir inflow at n: HQ 10,000

Dam category 2 (<15 m height; < 1 million m 3 volume)


Design reservoir inflow at n-1: HQ 500 (minimal HQ 100 )
Design reservoir inflow at n: HQ 5,000 (minimal HQ 1 ,000 )

Other regulations apply in different jurisdictions and for other


structures.

39

HYDROLOGIC DATA
COLLECTION
CAMPAIGNS

40

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What data is collected during a measuring campaign?
Stream flow discharge data over a long period
At the dam site if possible, or
In the same watershed if possible, or
In a similar watershed not too far away
Rainfall data
Temperature data
Evaporation and evapo-transpiration
Sediment freight
Water quality

41

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Data collection should start as early as possible in advance of
a project because long term data series are required
Minimum data record periods are, depending on project size, 2
to 20 years
The comprehension of a hydrologic data collection campaign
depends on the size of the project
For larger projects more parameters will be required
Larger projects need longer time series to reduce the planning
risk
Larger projects will also have bigger budgets for data
collection campaigns
Data collection should not stop before the project construction
commences, preferably data collection is done continuously

42

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What is a stream flow gauging station?
Usually, stream flow gauging stations measure water levels
and store the data on paper or on a digital data logger
The water levels are converted into stream flow discharge data
through application of rating curves
Rating curves are established by doing spot discharge
measurements and noting the corresponding gauge height to
establish a relationship between both

43

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow gauging process
Measuring the run-off in rivers
Stationary water level gauge

+ spot measurements to establish


rating curve

44

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Staff plate

45

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Floating gauge

46

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Pressure transducer,
external data logger

47

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Pressure transducer
internal data logger

48

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Radar sensor

49

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Water level gauging equipment
Pneumatic water level gauge

50

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow discharge spot measuring equipment
Low flows:
Salt dilution method
Principle:
Dilution effect of salt in water
Measuring concentration
Easy, fast and cheap

51

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow discharge spot measuring equipment
Mid flows: Aqua Profiler (acoustic doppler sensor)
Quick but expensive equipment

52

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow discharge spot measuring equipment
Mid flows: Area-velocity method
Classic with propeller or electromagnetic
Inexpensive but time consuming

53

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow discharge spot measuring equipment
High flows:
ADCP technology on boats
Comfortable, quick, expensive

54

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Stream flow discharge spot measuring equipment
High flows: Mobile crane or cable crane
Uses propeller or electric sensors
Time consuming
Inexpensive equipment

55

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Rainfall gauging equipment
Tipping bucket rain gauge

56

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Rainfall gauging equipment
Snowdon rain gauge

57

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Evaporation gauging equipment

58

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Temperature gauging equipment

59

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Climate Station Iwokrama

60

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Where is the best location to measure stream flow discharges?
The permanent gauging location should be:
Easily accessible
At a location where the riverbed does not change much; otherwise a
measuring weir would be required, which is very costly.
If possible use bridge cross sections
If the river describes a bend, select the outside of the bend as
sedimentation is more likely to occur on the inside
Select a site that is somewhat protected from damage through debris
and boulders that the river transports during floods
Imagine the state of the river during extremely high floods and
double check if the location would still be suitable
Protected from vandalism and theft. Solar panels are popular
souveniers for passers-by.

Remember: the gauging site must be visited regularly for data


retrieval and station maintenance
61

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Where is the best location to measure stream flow discharges?
The spot measuring location should be:
Easily accessible
Preferably in the same cross section as the permanent gauging site
Gauging location and gauging equipment need to fit each other. The
salt dilution method does not work at the lower Essequibo, and a
bridge crane does not work in small creeks.

The gauging site must be visited at different water levels and


discharges to establish a proper rating curve

62

HYDROLOGIC DATA COLLECTION CAMPAIGNS


When to use telemetry for data retrieval?
What is telemetry?
- Transferring data via remote data broadcasting, such as GSM,
VHF radio, internet, telephone modem
Basic consideration: data, that is not measured cannot be
brought back
Consequently: lost data records cannot be brought back
Gauged data is very valuable
Therefore, data records are often broadcasted daily
Also: broadcasting for weather forecasting and early warning
stations where real-time data is required

63

HYDROLOGIC DATA COLLECTION CAMPAIGNS


Telemetry Pros and Cons:
Pro:
Real-time data can be collected, including threshold alarms
Status of the gauging station, including battery voltage level,
is communicated regularly
Less visits to the station are required
Enables data collection even from very remote locations
Remote re-programming of data loggers possible
Contra:
Additional cost for equipment procurement
Depending on technology regular charges for data
transmission
More maintenance required for the high-tech equipment
Operators tend to neglect telemetric stations maintenance if
no error is reported
64

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What civil structures are required for gauging stations?
Structure to host the sensor and data logger

65

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What civil structures are required for gauging stations?
Measuring weir or reinforcement of riverbed

66

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What civil structures are required for gauging stations?
Measuring weir or reinforcement of riverbed

67

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What civil structures are required for gauging stations?
Housing for data loggers

68

HYDROLOGIC DATA COLLECTION CAMPAIGNS


What civil structures are required for gauging stations?
Security fencing

69

HYDROLOGIC DATA COLLECTION CAMPAIGNS


How to protect the station from theft and vandalism?
Most vulnerable: solar panels
and very remote stations
Select location for station so
that it is protected: either very
visible to the public or not visible
at all
Use fences, steel boxes, masonry
boxes
Camouflage
Technical equipment in
underground boxes
Boxes at power poles seem to be
safe... people fear electric
chocks
70

EXERCISE 1: DESIGN OF
HYDROMETRIC GAUGING
STATIONS

71

EXERCISE 1: DESIGN OF HYDROMETRIC GAUGING


STATIONS
First Exercise:
Situation:
The Troumassee River shown on the map was earmarked for
hydropower use
The hydrometric gauging stations shown on the map are
available
Challenge:
Design the hydrometric station design for the project area
Identify required data to be collected
Identify best locations for the required gauging stations
Select equipment, including power supply
Design civil structures
Define operation and maintenance program

72

GEOTECHNICAL
INVESTIGATIONS FOR
HYDROPOWER
FEASIBILITY ANALYSIS

This
chapter
was not
presented!

73

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Why geotechnical investigations?
To avoid that:

74

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
What are geotechnical investigations (GI)?
Physical field and laboratory tests to investigate the
mechanical properties of the underground
GI are a combination of
Geology
Mechanics
Statics
Chemistry
Geohydrology

GI reduce the construction risk and allow proper structural


and foundation design
Good GI safe money!
75

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
GI used for permanent and temporary structure design:
Definition of possible dam type
Construction pit slopes
Upstream and downstream slopes of fill dams
Size and shape of concrete dams
Foundation design of dams, powerhouses, pipelines, etc.
Design of cofferdams
Design of underground treatment measures
Slope protection design
Access road design
Power transmission tower foundations
Selection of construction materials
...

GI are important!
76

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
What is the right investigation scope for the project scale?
GI are generally expensive
They are even more expensive the larger the required
equipment
Equipment transport sometimes most of the cost
Scaling of the works to obtain the right cost/benefit ratio
The larger the project, the more GI will be done (more budget)
The more complicated the geology, the more GI need to be
done
77

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
How much geological risk can the investor absorb?
Large projects: Banks will require certain minimum
investigations to assess investment risk
Small projects (<500 kW):
Budget limitations are important restriction
Expensive investigations
+ Identification of need for additional protection measures
= Double cost

Consequence: invest in higher degree of protection in the first


place instead of geotechnical investigation (assume higher
risk)
Attention! Do not optimize by reducing both parameters:
investigation cost and protective measures!

78

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
What parameters are typically investigated?
Compressive strength
Compactness
Bulk density
Modulus of elasticity
Shear strength
Cohesion
Inner friction angle
Granulometric distribution

Organic matter test


Alkali reaction
Ground water level
Compressibility/
compactibility
Hydraulic conductivity
Seepage
Mechanical defects

79

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Compressive strength:
Good for:
Foundation design of structures
Design of superstructures
Selection of concrete aggregates
Tested:
Compression test (laboratory)
Plate load test (in situ)

80

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Compactness:
Good for:
Structural engineering (load definition)
Tested:
Density of undisturbed sample (lab)
Proctor test (lab)

81

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Bulk density:
Good for:
Structural calculations (load)
Quantity estimates
Tested:
Laboratory:
Mercury displacement
Submerged weighing
Volumetric and weight measuring of specimen

Field tests:
Various volume displacement methods
82

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Modulus of elasticity (Youngs Modulus):
Good for:
Foundation design
Structural design
Underground works (tunneling)
Tested:
One-axial pressure test (lab+in situ)
Measuring of pressure and respective dilatation
Depends on direction of applied force

83

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Shear strength:
Good for:
Slope stability
Dam design
Foundation engineering
Construction pit design
Tested:
Direct shear test (lab)
Vane shear strength test (in situ)
Triaxial test (lab)

84

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Cohesion and inner friction angle:
Good for:
Slope stability
Slope gradient of fill dams
Cofferdam design
Tested:
Triaxial shear test

85

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Granulomatric distribution:
Good for:
Construction materials
Sediment analysis
Tested:
Sieving test
Slurry settling test

86

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Organic matter test:
Good for:
Construction material testing
Foundation engineering
Tested:
Incineration test
Incinerating soil at 550C
Weighing mass before and after glowing

87

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Alkali reaction:
Good for:
Concrete aggregates
Foundation engineering (no direct contact with fresh concrete)
Tested:
ASTM
ASTM
ASTM
ASTM
ASTM

C 227: Mortar-Bar Method


C289: Chemical Method
C1260: Mortar-Bar-Test
C1293: Length Change Test
C1567: Accelerated Mortar-Bar Method

88

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Ground water level:
Good for:
Foundation design
Construction pit design
Structural design (load)
Tested:
Ground water wells
Test pits

89

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Compressibility and compactibility:
Good for:
Foundation engineering
Structural design
Tested:
Plate load test (in situ)
Proctor test (lab)
Compression test (lab)

90

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Hydraulic conductivity and seepage:
Good for:
Foundation engineering
Construction pit design
Tested:
Pump test (in situ)
Darcy-test (lab)

91

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Mechanical defects:
Good for:
Structural design
Design of anti-seepage measures
Tested:
Test pit
Borehole video sounding
Looking for gaps, disturbances, clefts etc.

92

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Geological mapping with geological maps and visual surface
inspection
Hand dug holes/pits
Auger holes

93

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Standard Penetration Test

94

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Core ram test

95

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Drilling (coreless) and separate sampling

96

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Core drilling

97

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Video borehole sounding

98

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
Common geotechnical investigation methods:
Geophysics
Geoseismic with geophones and hydrophones
Electric resistance

Advantage: linear visualization of underground


Needs one or more reference core drillings for calibration of
test results

99

GEOTECHNICAL INVESTIGATIONS FOR HYDROPOWER


FEASIBILIT Y ANALYSIS
How expensive are geotechnical investigations?
Cost depends heavily on comprehension and technology
Access to the site is an important parameter
Relatively most expensive: site installation
Additional drill meters are not expensive
Geophysics tend to be inexpensive for the degree of detail it
produces
GI cost for large scale projects can be several million US$

100

PRINCIPLES OF GOOD
PROJECT LAYOUT
DESIGN

101

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN

First some bad examples:

102

TOTORA PAMPA , BOLIVIA

Totora Pampa, Bolivia

103

TOTORA PAMPA , BOLIVIA


Collapse of the stilling basin:
Project details
Small scale hydropower plant: 200 kW
Located in the Andes mountains in Bolivia
Problem: weir was built on the alluvial sand of the river bed

Consequence: downstream river bed erosion


104

TOTORA PAMPA , BOLIVIA

105

TOTORA PAMPA , BOLIVIA

106

TOTORA PAMPA , BOLIVIA

107

TOTORA PAMPA , BOLIVIA

108

MOCO MOCO, GUYANA

Moco Moco, Guyana

109

MOCO MOCO, GUYANA


Heavy rainfalls in 2003 caused the head pond to overflow and
a land slide to happen along the penstock

110

MOCO MOCO, GUYANA


Heavy rainfalls in 2003 caused the head pond to overflow and
a land slide to happen along the penstock
The landslide damaged the penstock like bending a straw

111

MOCO MOCO, GUYANA


Heavy rainfalls in 2003 caused the head pond to overflow and
a land slide to happen along the penstock
The landslide damaged the penstock like bending a straw
Consequently, a diesel generator was installed in Lethem to
supply the electricity needs
The electricity was fed back towards the hydropower
powerhouse
Due to the lack of load side over voltage protection a short
circuit occurred in the control board of the HPP and a fire
destroyed the control system

112

MOCO MOCO, GUYANA


Due to the lack of load side over voltage protection a short
circuit occurred in the control board of the HPP and a fire
destroyed the control system

113

MOCO MOCO, GUYANA


Prime cause of the damage:
Overestimation of the underground stability, presumably due
to the lack of geotechnical investigations during the design
phase

114

MOCO MOCO, GUYANA


Prime cause of the damage:
Overestimation of the underground stability, presumably due
to the lack of geotechnical investigations during the design
phase
Lack of drainage along the penstock alignment

115

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN

Now: Some guidelines for good project designs

116

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN


When visiting a site for the first time, or watching a topo map,
an initial project layout should be visualized
Logically: Upstream = water in; Downstream = water out
Dam and reservoir or Run-Off River?
Pressure head
High head (h > 50 m)
Medium head (15 m < h < 50 m)
Low head (h < 15 m)

Water availability
General geology
Solid rock
Soil and rock
Soil and sand

Look for good geology for the various structures!


117

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN


Try to avoid areas of high population density for project design
avoid need for resettlement and lengthy disputes
Try to maximize the hydropower potential of each site with the
layout design. If the potential is more than the power needed
for supply, a stage wise construction can be envisaged.
Integrate environmental considerations (fish ladders,
minimum flow donation, and so on) in your design to avoid
additional cost when these items are required later in the
process
Consider sediment handling to be a serious aspect
Do not omit the bottom outlet at dams and reservoirs
Design with realistic redundancy: black start hydropower plant
instead of diesel generators
Do not save on safety aspects
118

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN


What elements do hydropower projects contain?

119

ELEMENTS OF HYDROPOWER PLANTS

Diversion Weir and Intake

120

ELEMENTS OF HYDROPOWER PLANTS


Trash Rack
If required:
Trash rack cleaner

121

ELEMENTS OF HYDROPOWER PLANTS


Dam and Spillway

122

ELEMENTS OF HYDROPOWER PLANTS


Desilting Basin / Sand Trap

123

ELEMENTS OF HYDROPOWER PLANTS


Forebay / Storage Pond

124

ELEMENTS OF HYDROPOWER PLANTS


Headrace Channel / Pipeline

125

ELEMENTS OF HYDROPOWER PLANTS


Penstock

126

ELEMENTS OF HYDROPOWER PLANTS


Tunnel

127

ELEMENTS OF HYDROPOWER PLANTS


Powerhouse with substation

128

ELEMENTS OF HYDROPOWER PLANTS


Ship lock

129

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN

Selection of the right turbine type

130

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN


Selection of the right turbine type:

131

PRINCIPLES OF GOOD PROJECT LAYOUT DESIGN


Selection of the right turbine type:

132

PELTON TURBINE
Pelton turbine: Impulse turbine

up to 92%
(High efficiency at
partial flow down to10%)

133

TURGO TURBINE
Turgo turbine: Impulse turbine

up to 90%
(High efficiency at
partial flow down to10%)

134

TURGO TURBINE
Difference between Turgo and Pelton turbines

The Turgo turbine can process about twice the amount of water than Pelton turbines

135

CROSS-FLOW TURBINE
Cross-flow turbine: Impulse turbine

up to 80%
(less efficient at
partial flow)

136

CROSS-FLOW TURBINE
Cross-flow turbine: Impulse turbine

137

FRANCIS TURBINE
Francis turbine: Reaction turbine

up to 93%
(Applicable as
pump turbine)

138

FRANCIS TURBINE

Francis shaft (a) and spiral (b) turbine arrangements


139

FRANCIS TURBINE

Top left: vertical shaft


arrangement;
Top right: horizontal shaft
alignment;
Bottom left: double
flooded turbine;
Center: elements of a
Francis turbine

140

KAPLAN TURBINE
Kaplan type turbine: Reaction turbine

> 90%
(High efficiency at
partial flow)

141

KAPLAN / PROPELLER TURBINE

Kaplan turbine: guide vanes


and blades can be regulated;
Propeller turbine: only guide
vanes can regulate flow

142

KAPLAN / PROPELLER TURBINE


Related turbine types: Bulb turbine

143

KAPLAN / PROPELLER TURBINE


Related turbine types: HydroMatrixTM

144

KAPLAN / PROPELLER TURBINE


Related turbine types: HydroMatrixTM

145

KAPLAN / PROPELLER TURBINE


Related turbine types: Straflo Turbine

146

KAPLAN / PROPELLER TURBINE


Related turbine types: S-Bulb turbines

147

KAPLAN / PROPELLER TURBINE


Related turbine types: Cone-gearbox (a) and Gearbox (b) turbines

148

HYDRO WHEELS
(a) Breast wheel with cells
(b) Breast wheel with blades
(c) Overshot wheel
(d) Undershot wheel

Efficiency between 50
and 82%
Good partial load
efficiency due to slow
rotational speed
Eco friendly

149

HYDRODYNAMIC SCREW
Hydro-dynamic screw: Reaction turbine (Archimedical Principle)

> 80%
Eco-friendly
150

SOME EXAMPLES OF RECENT TECHNOLOGIES


Steff Turbine

151

EXERCISE 2:
DEVELOPMENT OF A
PROJECT LAYOUT

152

EXERCISE 2: DEVELOPMENT OF A PROJECT LAYOUT


Second exercise:
Situation:
The Troumassee River was earmarked for hydropower use
The topographic map shows the situation
Challenge:
Design the initial project layout to be used for feasibility study
to maximize the use of the sites hydropower potential
Define the location of the structures, such as weir, dam, powerhouse,
pipelines, power lines, access roads
Select the type of the structures, such as weir type, headrace canal or
pipeline, turbine type, ...
Draw project layout in the map and sketches of the structures on
separate papers
153

ECONOMIC ANALYSIS
AND SENSITIVITY
ANALYSIS

This
chapter
was not
presented!

154

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


What is economic analysis?
A systematic approach to determining the optimum use of
scarce resources, involving comparison of two or more
alternatives in achieving a specific objective under the given
assumptions and constraints.
Economic analysis takes into account the opportunity costs of
resources employed and attempts to measure in monetary
terms the private and social costs and benefits of a project to
the community or economy.
( S o u r c e : h t t p : / / w w w. b u s i n e s s d i c t i o n a r y. c o m / d e f i n i t i o n / e c o n o m i c analysis.html#ixzz2zjnCgz7x)

155

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


Economic Analysis:
allows identification of the optimum hydropower project
configuration
Can compare hydropower projects with other means to provide
electricity
Is used to optimize even individual structures, such as tunnels
and cofferdams
Expresses all benefits and costs in monetary terms to
compare them
Can be used to determine the profitability of a project
Gives the answer to the question Is the project economically
feasible?

156

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


What input data is required?
For the analysis of an entire hydropower project:
All project development cost
All construction cost
All re-investments over the analysis time span
Operation and maintenance costs
Environmental and social costs
Project benefits from power sales
Other project benefits (emission certificate trading, subsidies,
secondary income, ...)
Residual value of the project at the end of the analysed period

157

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


What input data is required?
For the analysis of an entire hydropower project: (continued)
Time when the costs and benefits incur
Financial parameters
Discount rate
Loan interest rate and repayment time
Share of equity
Price escalation rates

All costs are discounted to reference point in time

158

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


What are the results of the analysis?
Benefit / Cost Ratio
All discounted cost are divided through all discounted benefits
If B/C ration is >1 the project is profitable

Net Present Value (NPV)


All costs and benefits are summed up
A NPV > 0 means the project is profitable

Internal Rate of Return (on investment or equity)


The specific discount rate at which the NPV at the end of the
analysed period is = 0
Represents the interest rate for the investment (or equity)

Levelized Cost of Electricity


All discounted costs divided by all discounted generated energy units
at the end of the analysed period
Represents the cost for one generated energy unit
159

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


How are the results calculated?
Main mathematical formula: discounting of costs

Economic analysis tool in Excel

160

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


What is a sensitivity analysis (SA)?
The input parameters of an economic analysis underlie
uncertainties
Sensitivity Analysis: vary the value of critical parameters and
repeat EA
Results of a SA show under which conditions the feasibility of
a project changes
SA quantifies the risk emerging from parameter uncertainties
Typical parameters to vary are
Discount rate
Electricity sales tariff
Project investment cost
Loan interest rate
Share of equity
Price escalations
161

ECONOMIC ANALYSIS AND SENSITIVIT Y ANALYSIS


How are the results of an economic analysis and sensitivity
analysis used?
Different interpretations:
Private project developers
Consider projects as investment
Usually want to see high IRR (> 12%) and NPV
Are willing to take higher risk if the prospective profit is high enough

Public developers
Are happy with lower IRR (say 6-8 %) and if NPV is above 0
Seek to reduce project risks
Usually represent a public interest, such as electricity supply

Banks
Need to reduce risks significantly to protect investors money
Follow borrower with IRR and NPV requirements but adjust their
lending conditions to reflect lending risk
162

ENVIRONMENTAL AND
SOCIAL
CONSIDERATIONS

This
chapter
was not
presented!

163

ENVIRONMENTAL IMPACT ASSESSMENT


Importance:
Requirement (legal in most countries and/or for
financiers)
For macroeconomic cost-benefit analysis
For microeconomic viability of the project
Anticipated irreversible adverse impacts on the
environment may result in the discontinuation of
projects!

ENVIRONMENTAL IMPACT ASSESSMENT


Main issues:
Loss of natural resources, habitats, biodiversity,
ecosystem services
Alteration of the natural environment and its
consequences
Pollution and environmental degradation during
construction phase
Noise pollution from power house (and other noisy
equipment)

ENVIRONMENTAL IMPACT ASSESSMENT


Special issues for (large) dams:
Sediments and nutrients are trapped in dams if there
are no low-level outlets
Reduced oxygen levels in water due to decomposing
vegetation in dams
Release of methane and carbon dioxide from rotting
organic matters into the atmosphere
Mercury contamination in dams
High rates of water evaporation in tropical climate may
lead to significantly reduced water levels downstream
Reduced water levels downstream might cause loss of
floodplains and mangrove forests

ENVIRONMENTAL IMPACT ASSESSMENT


Special issues for (large) dams: (continued)
Seasonal variations of water levels in the river as well
as water temperature are lost through the regulation of
the dams outflow
Change of air flow patterns have an influence on air
quality and subsequently on local flora
Colonization by aquatic plants
Dams provide ideal breeding grounds for disease
vectors
Change of fish habitat from river to lake
Lakes might pose barriers to wildlife migration

ENVIRONMENTAL IMPACT ASSESSMENT

Are mitigation measures for all issues


encountered possible?
How much do they cost?

SOCIAL IMPACT ASSESSMENT


Importance:
Requirement in some countries and for some
financiers
For macroeconomic cost-benefit analysis
For microeconomic viability of the project
Information, communication and consultation with
affected people is essential for a successful project!
People who are angry because they feel their concerns
are ignored may find ways to stop the project.

SOCIAL IMPACT ASSESSMENT


Main issues and mitigation measures to consider:
Communication, information and consultation
Establish good communications channels with affected
people from the start of the project (and keep complaints
management in place after construction is completed)
Hold open information and consultation meetings for the
affected people at the beginning of the project and in
regular intervals thereafter; involve the affected people in
the project planning
Manage expectations carefully: ensure the local
population benefits from the project but does not create
expectations the project cannot fulfill

SOCIAL IMPACT ASSESSMENT


Main issues and mitigation measures to consider:
(Continued)
Resettlement:
Negotiate fair deals with communities that have to be
resettled
Transparent decision-making processes and consultations
with the communities are essential
Pay attention to the following:
Land rights (customary and statutory land rights might be
overlapping, people might not have official land titles)
Water rights
Gender equality
Indigenous peoples rights

SOCIAL IMPACT ASSESSMENT


Main issues and mitigation measures to consider:
(Continued)
Compensation:
For loss of houses and land, livelihoods, cultural/ religious
goods and places, community services
Also consider communities downstream whose livelihoods
might be endangered through changes in the ecosystems
Might include training and initial resources for uptake of
new livelihoods

SOCIAL IMPACT ASSESSMENT


Main issues and mitigation measures to consider:
(Continued)
Health issues
Loss of cultural heritage sites
Noise pollution
Social disruptions
Large, especially cross-border projects add political
component and issues with water rights and water
usage on a national level

SOCIAL IMPACT ASSESSMENT

Positive social impacts might include:


Development impulses through access to electricity
Education benefits through access to electricity
Health benefits through access to clean water

SOCIAL IMPACT ASSESSMENT

The positive and negative impacts must be put


in relation to one another!

SOCIAL IMPACT ASSESSMENT


Assessment of the Ability and Willingness to Pay for
Electricity:
For electrification of unserved areas, including
communities affected by the hydropower plant
Importance:
Serves to project electricity demand
Informs electricity tariff setting
Projection of electricity sales and income important for the
economic analysis of a project
Projected demand, increase in demand and purpose of
electricity use should inform the grid design

SOCIAL IMPACT ASSESSMENT


Data to be collected:
Demographic data (population and growth rate, migration
patterns, seasonal variations)

Economic data (livelihoods, economic growth, possibilities


to increase cash income)

Electricity-specific data (types of users: residential/


commercial/ industrial and their relative share; projected
initial and overall connection rate; projected amount of
electricity demanded; projected increase in the electricity
demand over time; types of electrical equipment to be used)

Training needs among the population

INTERRELATION OF EIA , SIA & A/W TP


Social and environmental impacts are closely
related, especially in developing countries, as people
often depend on the environment for their livelihoods
People who are adversely affected by and feel they
do not benefit enough from the project might find
environmental impacts as reasons to stop the
project!
Access to electricity and clean water for communities
affected by the project should be ensured

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT


Conclusions:
The importance of ESIAs must not be underestimated
ESIAs should not be viewed as additional bureaucratic
hurdles to overcome, but as an instrument to inform the
debate about the costs and benefits of a proposed
project and its viability
Impact mitigation costs must be considered in the
economic viability analysis of a project
Local population must participate in the benefits of the
project and not just bear the costs

ENVIRONMENTAL & SOCIAL IMPACT ASSESSMENT


Conclusions (continued)
Expectations, concerns and grievances of affected
population must be considered and managed carefully;
otherwise conflicts will arise, which is very costly: angry
people might find ways to stop projects
High adverse environmental or social impacts may be a
reason to discontinue a project
But: environmental and social costs should not be
compared to status quo (zero development) but instead
to costs of realistic alternatives

DRAWING CONCLUSIONS
FROM THE RESULTS,
QUESTION AND ANSWER
SESSION

181

DRAWING CONCLUSIONS FROM THE RESULTS,


QUESTION AND ANSWER SESSION

Questions? Comments?

182

THANK YOU FOR YOUR


ATTENTION!
CONTACT
E-mail: mail@sven-homscheid.com
Web: http://www.sven-homscheid.com
183

REFERENCES
Hydrometry; Boiten; Edition 2003; ISBN 90-5410-423-6
www.ott.com
www.seba-hydrometrie.com
www.wikipedia.com
www.geomation.com
www.geotechnik-dunkel.de
Wasserkraftanlagen; Giesecke; Mosonyi; 2003; ISBN
3-540-44391-6
Hydraulik fuer Bauingenieure; Heinemann/Paul; ISBN
3-519-05082-x

184

S-ar putea să vă placă și