Documente Academic
Documente Profesional
Documente Cultură
Dr NHAPI Innocent
Ir HATEGEKIMANA DUSHIMIRE Alexis
Consultants
0. EXECUTIVE SUMMARY........................................................................................ 3
I. INTRODUCTION .................................................................................................... 6
1.1. The Authors and Developer presentation......................................................... 6
1.2. Objective of the study........................................................................................... 7
1.3. Terms of Reference ............................................................................................... 7
II. LEGISLATIVE AND REGULATORY CONSIDERATIONS............................ 10
FOR ENVIRONMENTAL MANAGEMENT............................................................. 10
2.1. International regulations for environmental management .......................... 10
2.2. Institutional framework for environmental management in ....................... 11
Rwanda........................................................................................................................ 11
2.3. Legislative framework for environmental impact assessment..................... 12
(EIA) in Rwanda......................................................................................................... 12
III. BASELINE DATA .............................................................................................. 14
3.1. General description of the project area............................................................ 14
3.2. Bio-physical environment.................................................................................. 15
3.3. Socio-economical environment......................................................................... 19
IV. PROJECT DESCRIPTION ................................................................................. 21
4.1. The project objectives ......................................................................................... 21
4.2. The project strategies.......................................................................................... 21
4.3. Program activities ............................................................................................... 22
4.4. Expected results .................................................................................................. 22
4.5. Electrical power and drinking water infrastructures .................................... 23
4.6. Wastewater treatment systems ......................................................................... 24
4.7. Solid wastes management ................................................................................. 32
V. ENVIRONMENTAL IMPACT............................................................................. 35
5.1. Impacts classification.......................................................................................... 36
5.2. Impacts on bio-physical environment ............................................................. 36
5.3. Socio-economical impacts.................................................................................. 38
5.4. Impacts of the environment to the project ...................................................... 39
VI. ANALYSIS OF ALTERNATIVES .................................................................... 40
VII. MITIGATION MEASURES .............................................................................. 42
VIII. ENVIRONMENTAL MANAGEMENT PLAN FOR..................................... 44
MUHAZI BEACH RESORT PROJECT ....................................................................... 44
8.1. THE ENVIRONMENTAL MANAGEMENT PLAN ..................................... 44
8.2. EMERGENCY PLAN IN CASE OF ACCIDENT OR FIRE ........................... 48
IX. CONCLUSION AND RECOMMENDATIONS ............................................ 49
X. REFERENCES......................................................................................................... 51
2
List of figures
Figure 1 : The project site, where major construction works are finished………..14
Figure 2 : Map of the Eastern Province showing the project area in the
vicinity of Muhazi Lake…………………………………………………...19
Figure 3 : Map of Rwamagana District showing the project site………………….20
Figure 4 : The water reservoir and the end of electrical line………………………24
Figure 5 : General Flow Scheme for the wastewater treatment system
wetlands…………………………………..……………………………...…25
Figure 6 : A bed of papyruses……………………………………………………...…29
Figure 7 : Details for a constructed treatment wetland…………………………….31
Figure 8 : Detailed Flow Scheme for wastewater collection of Area1……….....…32
Figure 9 : Detailed Flow Scheme for wastewater collection of Area 2…………....33
List of Tables
3
0. EXECUTIVE SUMMARY
The project of construction and operation of a tourism village that is the subject
of this environmental impact assessment (EIA) concerns the implantation of a
beach resort in the vicinity of Muhazi Lake in Rwamagana District, the Eastern
Province. The development of this tourism resort will be made on a land of 6.56
Ha with buildings covering about 15% of the parcel. It will also be constructed
parking yards and internal roads network accessing the different parts of the
resort, a connection to an electrical line and facilities for ground water
abstraction, storage and treatment. The major construction works started well
before the EIA legislation as the project begun early in the year 2003 whereas the
Environmental Organic Law was published in May 2005. The current aim is then
to ensure that the existing and further developments will have minimal impacts
on the environment.
The identification of the impacts of this project on the environment showed that
during its two phases of construction and operation, there will be a big number
of positive impacts on the human environment such as the creation of jobs,
payment of different taxes to the State in particular, stimulation of the local
economy and the development of tourism industry in general. Also, this tourism
development project will increase the incomes for its investors and will be a good
opportunity for the exploitation of the country’s natural resources as well,
contributing then to the poverty alleviation program in line with the Vision 2020.
The project will also have negative impacts on the socio-economical and
biophysical environment as the increase of road traffic which would cause some
accidents, the restriction of fishing activities in the area of the resort, and a great
change in the natural ecological situation as a result of the destruction of fauna
and flora especially during the construction phase and the risks of lake water
pollution.
Different mitigation measures for these negative impacts have been proposed to
reduce to the minimum their effects on the socio-economical environment as well
as on the biophysical environment. In order to put these measures into practice,
an environmental management plan has been developed to guide all activities of
the project concerning the protection of the environment. This plan specifies the
nature of the negative impact, the proposed mitigation measures for this impact,
the indicators in the execution of these mitigation measures, the time period, the
responsibilities and the follow-up needed from concerned authorities. A plan of
emergency in case of accident or fire is also developed.
However, some recommendations are also given so that the execution of the
project becomes a success without harming or with the least negative effect to the
environment in general.
4
The project offers numerous advantages to the State, the Rwandans in general as
well as to the owners of the project in particular; and these advantages or
positive impacts have been raised.
The project also presents negative impacts that can be eliminated or reduced if
the proposed environmental management plan is followed as it should be. This
will then drive to an effective implementation of the project and without any
danger or nuisance to the environment.
5
I. INTRODUCTION
The Developer:
6
1.2. Objective of the study
The project and its activities from the construction stage to the exploitation stage
may have potential impacts on the environment. The present study will not only
facilitate determining the magnitude and extent of negative environmental
impacts of the project but also will identify corresponding mitigation measures
that should be put in place to offset, reduce or minimize potential impacts, that
are likely to arise as a consequence of the project implementation. It will also
permit the developer to put in place an environmental management plan in
order to put properly in action the identified mitigation measures for negative
impacts and to ensure that positive impacts are given adequate importance.
Based on the terms of reference produced by REMA, the work of the consultant
should consist on the following:
7
- Description of relationship between activities and physical assets of the
project during exploitation
- Drawings of the proposed infrastructure and the site management
plan during the exploitation
- Risk and accidents prevention measures and other security measures
- Occupational health and safety
- Required labour and working hours
- Projected extension works if there is any
3. Baseline data: Analysis and evaluation and presentation of the initial state
of the site on relevant environment characteristics of the study area.
- Description of the study area and its topography with a particular
emphasis on sensitive elements such as the lake, the underground
water, the fauna and flora. The study area must cover all the activities
and direct and indirect impacts of the project on the biophysical and
socio-economic environment.
- Detailed description of the existing environment in the study area. This
will include the physical environment (climate, infrastructure, geology,
hydrology, water quality, air quality, ambient sound quality, etc.), the
biological environment (vegetation, terrestrial and aquatic fauna and
flora, protected species, protected areas, sensitive areas, etc.)
- Description of present land use of the project and areas contiguous to it
- Summary of information on the status of the location.
- Analysis of interactions likely to occur with all activities in the vicinity
and cumulative impacts on the environment.
- Description of existing conditions and the interrelationship between all
the project elements and the wider natural, cultural, social and
economic environments.
- Description of the interaction between the lake and the activities of the
project and the impacts on the lake as well as on the project.
8
- Identification and evaluation of significant positive and negative
impacts associated with the entire project as well as any cumulative
impacts. This will also include the methodology used in the
identification and evaluation of the impacts.
- Description of potential impacts of the environment on the project.
9
II. LEGISLATIVE AND REGULATORY CONSIDERATIONS
FOR ENVIRONMENTAL MANAGEMENT
10
The KYOTO Protocol to the Framework Convention on Climate Change adopted
at KYOTO on March 6, 1998 as authorised to be ratified by Law n° 36/ 2003 of 29
December 2003;
The BONN Convention opened for signature on June 23, 1979 on conservation of
migratory species of wild animals as authorised to be ratified by Law n° 35/2003
of 29 December 2003;
Within the ministry having the environment in its remit, the article 65 puts the
Rwanda Environment Management Authority in place, REMA in English
acronym. It is therefore this institution which is responsible for the follow-up of
the environmental impact studies concerning investment and development
projects. This legislation also puts in place the National Fund for Environment in
Rwanda, FONERWA in French acronym. The organisation, functioning and
responsibilities of these institutions will be determined by specific laws.
11
2.3. Legislative framework for environmental impact assessment
(EIA) in Rwanda
The article 70 states that an order of the Minister having environment in his
attributions establishes the list of projects for which the public administration
shall not warrant any authorization without an Environmental Impact
Assessment describing direct and indirect consequences of the project to the
environment.
Under the Title VI of this Organic Law, the article 81 stipulates that the following
activities are prohibited:
12
3° non authorised bush burning;
4° smoking in public and in any other place where many people meet;
5° defecating or urinating in inappropriate place;
6° spitting, discarding mucus and other human waste in any place.
For the article 87, it is prohibited to construct houses in wetlands (rivers, lakes,
big or small swamps), in urban or rural areas, to build markets there, a sewage
plant, a cemetery and any other buildings that may damage such a place in
various ways. All buildings shall be constructed in a distance of at least twenty
(20) metres away from the bank of the swamp. If it is considered necessary,
construction of buildings intended for the promotion of tourism may be
authorised by the Minister having environment in his or her attributions.
It is also prohibited to carry out any activities, except those related to research
and science, in reserved swamps.
For the purpose of enforcement, the article 95 announces that any one or
association that does not carry out environmental impact assessment prior to
launching any project that may have harmful effects on the environment is
punished by suspension of his or her activities and closure of his or her
association and without prejudice to be ordered to rehabilitate the damaged
property, the environment, people and the property. Falsification and alteration
of documents of environmental impact assessment is punished in the same
manner as what is provided for in paragraph one of this article.
13
III. BASELINE DATA
The site selected for the implementation of the project “Muhazi Beach Resort” is
located at Kabare on the sides of Muhazi Lake, in the Muhazi Sector,
Rwamagana District, the Eastern Province. The tourism village will be built on
the Plot N° 03/188, covering a total area of 6.56Ha, with about 30% from an
abandoned tourism project and the remaining land belonged to the local
residents.
The project started in 2003 before the Environmental Organic Law was
established, that’s the reason why an Environmental Impact Assessment was not
conducted prior to its commencement and at the time of this study, the project
was already in its construction phase.
Therefore, some constructions are too close to the lake in a distance of about 15m
from the lake banks whereas the Organic Law provides a minimum distance of
20m between the lake and any construction.
Figure 1 : The project site, where major construction works are finished
14
3.2. Bio-physical environment
i. Physical environment
The site is situated on a sloping hillside before Muhazi Lake, with a dominantly
sandy soil with loamy soil in some places. There is only little natural vegetation
consisting of some papyrus plants and bushes on the lake banks. About the half
of the site perimeter will be the lake water. The lake in this area is relatively deep
with about 3m of depth at a distance of 10m from the banks. This is the
consequence of sloping sides of the lake. These sides are subjected to erosion in
many places near the project area, due to agricultural activities and excessive
grazing without considering the minimum distance between the lake and such
activities.
ii. Climate
Precipitation: the average annual precipitation recorded in the area of the project
varies between 910mm and 1120mm.
iii. Altitude
The project site is located between 1449.8m and 1483.2m above sea level.
The site selected for the implementation of the project Muhazi Beach Resort has
little natural flora, and the existing land use at the beginning of the project
included subsistence crops like banana trees, sorghum and beans.
The site also presents different types of bushes that can, on the wildlife point of
view, shelter rodents and lizards or serve as ecological niche for various types of
birds.
15
v. Lake Muhazi environment (P. D. Plisnier, 1989)
Muhazi Lake is located in the north-east region of Kigali, between 1˚40’47’’ and
1˚50’29’’ latitude south, and 30˚10’3’’ and 30˚20’57’’ longitude east. The surface
area of the lake is 34.6km2, with a length of about 37km and a width of about
0.6km on average. The maximum depth of the lake is 14m, with an average
depth of around 6m. The following tables show some physical, chemical and
biological properties of the lake.
Parameter Values
pH 7.8
Temperature at midday (at 1m depth) 24.7˚C
Turbidity by Secchi disk 65.5cm
Conductivity 528µS/cm
Dissolved Oxygen (in 1m depth) >100% saturation
Chlorophyll a 34mg/m3
TAC (mg/l CaCO3) 111.0
HACH Spectrophotometer
16
b. The Flora
Type Name
Phytoplankton Microcystis aeruginosa
Microcystis delicatissima
Microcystis novacekii
Oscillatoria formosa
Ceratium hirundinella
Lyngbya contorta
Lyngbya limnetica
Merismopedia punctata
Macrophyte Phragmites mauritianus
Cladium
Cyperus papyrus
Typha angustifolia
Miscanthidium veraceum
c. The Fauna
Type Name
Protozoa Vorticella sp.
Epistylis sp.
Stentor sp.
Coleps sp.
Arcella sp.
Mollusc Melanoides tuberculata
Pila ovata
Lymnaea natalensis
Butinus aff. tropicus
Biomphalaria pfeifferi
Biomphalaria sudanica
Gyraulus sp.
Lentorbis chevalieri
Sphaerium hartmanni
Crustacea Argulus sp.
Thermocyclops macrocanthus
Thermocyclops infrequens
Moina dubia
Arachnidea Ranatra sp.
Coenodes sp.
Povilla adusta
Chironomus sp.
Chaoborus sp.
17
d. The fishes
- Tilapia nilotica
- Tilapia rendalli
- Gaurochromis sp.
- Clarias gariepinus
- Clarias liocephalus
- Afromastacembelus
- Barbus spp.
- Protopterus aethiopicus
18
3.3. Socio-economical environment
The project
area near
Muhazi Lake
Figure 2 : Map of the Eastern Province showing the project area in the vicinity of
Muhazi Lake
19
DENSITE DE LAPOPULATION ET INFRASTRCUTRESSCOLAIRES ETDE SANTE
DANS LE DISTRICT DE RWAMAGANA
$ W E
FUMBWE $ S
$
$
Site provided for $
$
$ $
M
%UHAZI
%$
P
Æ Hôpital
Ñ Centre de santé
the construction Ñ$% $
MUSHA GISHARI $ $ Ecole primaire
Ñ% $
of the project $
% Ecole secondaire
$ MUNYIGINYA
$ Limite de district
“Muhazi Beach %$ $ Densité (Hab/Km²)
Resort” $
Ñ 236 - 237
238 - 292
$ GAHENGERI 293 - 314
$ $
$
$
$ ÆÑ%
P
$%
315 - 343
$
$ % 344 - 536
%
KIGABIRO
$
Ñ
$ MWULIRE
MUYUMBU $
$ %
$
$ $
NZIGEÑ $
$ Ñ
$ % $ MUNYAGA
Ñ $$$
Ñ
RUBONA $
$
NYAKARIRO
$
$
%
Ñ
$KARENGE
$
3 0 3 6 Kilometers
The site selected for the implementation of the project Muhazi Beach Resort is
located at Kabare, in the Muhazi Sector, Rwamagana District, the Eastern
Province. The area of the District covers 691.6 km2 with a population of about
225,000 and 48800 households. The only Muhazi sector has a population of about
19800 people in 3450 households. The District has about 15 tourism sites that can
be developed and visited by the tourists, including 3 sites from Muhazi Sector.
20
IV. PROJECT DESCRIPTION
The politics of socioeconomic development of Rwanda has for main goal to take
the Rwandan population to poverty alleviation up to year 2020. Considering the
available means to help the Government to reach this objective, the private sector
is the key to accelerate this development process.
The project is about the construction and exploitation of a tourism resort, in the
vicinity of the Muhazi Lake. The development of the project will have two main
phases: The construction phase and the exploitation phase. The exploitation will
start after construction is completed and has no limit in time.
The resort will have different parts such as hotel, bungalows, bar & restaurant,
swimming pool, sports grounds, gardens, parking yards and any related
services. The resort is adjacent to the Lake Muhazi and many activities of the
project will have a direct relationship with the lake.
The main objective of the project aims for the development of both mass and
selective tourism in Rwanda.
The specific objectives are as follows:
21
4.3. Program activities
22
4.4.4. Telecommunication service
(i) Internet
(ii) Telephone
(iii) Fax
4.4.5. Business centre (bank counter, massage, sauna, beauty shop, infirmary,
boutique, etc.)
i. Electricity
Electrical line with a medium tension links already the project site with the
national electrical network, and it is provided with a low tension transformer so
that an electrical connection to the resort would be easy. The tourism village will
consume about 6MWh every month.
ii. Water
The municipal water supply network does not exist in the area of the project, and
it was found that it would take long time to connect the project with a regular
network. It has been then decided to make a groundwater abstraction at the site
of the project as there are more chances that the groundwater table in the area is
not located at a shallow depth and therefore it can not easily be contaminated.
A water reservoir is already constructed and it is provided with a capacity of
storing 65m3, which would be enough to supply the resort in four days without
interruption as the water demand is expected to be about 16.5m3 per day.
A water treatment facility will also be provided with the capacity of treating
drinking water. It is expected that this underground water will not require much
forms of treatment and the major treatment would only be aeration. However, it
is necessary to carry out a hydrological study before the use of the borehole in
order to determine the quantity and water yields, but also the quality of this
groundwater by conducting physical, chemical and biological tests and to decide
the exact types of treatment required to be undertaken.
23
Figure 4 : The water reservoir and the end of electrical line
The raw wastewater from different activities in the resort should be treated
before it can be discharged in the receiving water media, in order to meet the
environmental requirements.
Parameter Concentration
BOD 500 mg/l
Total Phosphorus 10 mg/l
Total Nitrogen 70 mg/l
Total suspended solids 300 mg/l
Coliforms 10,000 Mpn/l
24
Table 3: International quality recommendations for wastewater disposal into
natural environment:
Parameter Concentration
BOD 50 mg/l
Total Phosphorus 2 mg/l
Total Nitrogen 10 mg/l
Total suspended solids 50 mg/l
Coliforms 4000 Mpn/l
Table 4: Expected quality of treated wastewater effluent discharged into the lake:
Septic Treated
Raw Constructed Lake
Septic
Treatment
Tank
Wastewater Effluent Wetland Effluent
25
These septic tanks will be provided respectively with volumes of 20m3 and 25m3.
A long retention time of 3 days has been provided in order to meet the maximum
treatment in anaerobic conditions. The septic tanks will be constructed in
reinforced concrete to avoid any leakage or infiltration of wastewater into the
ground. Because of the high filtration rate of the soil at the site, but also the
vicinity of the lake, a soakage system was not appropriate for the final disposal
of the treated effluent to avoid the pollution of the lake. The best option was then
the use of a constructed wetland for the further treatment of the septic tank
effluent before its discharge into the lake.
Base data: - Total capacity of the hotel (number of equivalent beds): 73 people
- Part I: 41 people
- Part II: 32 people
- The average projected occupation : 65% (from the project study)
- Resident staff : 5 people
- Non resident staff : 50 people
The effective capacity of the septic tank (assuming 1 day retention time) is
obtained by:
V = ( S * P1 * Y ) + ( P2 * DF )
26
b) Septic tank No.2:
i. Accommodation = ( 48 * 41 * 1 ) + ( 48 * 100 ) = 6768 litres
ii. Bar trade = ( 5 * 60 * 1 ) + ( 150 * 10 ) = 1900 litres
iii. Dining room = ( 10 * 50 * 1 ) + ( 15 * 100 ) = 2000 litres
iv. Non resident staff = ( 25 * 25 * 1 ) + ( 25 * 30 ) = 1375 litres
Total needed capacity = ( 4736 * 65% ) + 1900 + 2000 + 1375 = 8353.4 litres
Hydraulic retention time : 3 days
The total capacity of the septic tank 1 = 8353.4 * 3 = 25060.2 litres
Let’s provide a capacity of 25m3 for the septic tank No.2
27
The papyrus has proved a great efficiency for systems of treatment under semi-
natural conditions, contributing to nutrient removal in the constructed wetlands.
The results showed high removal efficiencies for biochemical oxygen demand
(BOD), ammonium-nitrogen (NH4–N) and phosphorus (P) of more than 85%
( J. Kyambadee et al., 2005 ).
The macrophytes growing in constructed treatment wetlands have several
properties in relation to the treatment processes that make them an essential
component of the design. The most important effects of the macrophytes in
relation to the wastewater treatment processes are the physical effects as the
plant tissues give rise to erosion control, filtration effect and provision of surface
area for attached microorganisms. The metabolism of the macrophytes, like plant
uptake or oxygen release, affects the treatment processes to different extents
depending on design (H. Brix, 1997).
28
Figure 6 : A bed of papyruses
Q = Kh * Ac * S Q = flow (m3/day)
Ac = cross-sectional area (m2)
Kh = hydraulic conductivity (m/d)
S = dh/dL = hydraulic gradient (m/m)
Assumptions:
- Influent concentration (Ci) is 175 mg BOD /L
- The effluent concentration (Ce) is 20 mg BOD /L
- The hydraulic conductivity (Kh) is 200 m/day
- KBOD = 0.1 m/day
- Water depth at effluent side 0.4 m
- Gravel bed depth 0.6 m
- The maximum allowable head loss (dh) is 10 cm
29
a) The constructed treatment wetland for the first septic tank
q = Q / Ah Ah = 145.65 m2
W1 = 11m
L1 = 13.5m
q = Q / Ah Ah = 180.43 m2
W2 = 13.5m
L2 = 13.5m
30
L
Outlet
Inlet samp channel
Constructed Lake
W Treatment
Wetland
Distribution
pipes
Plan view
Zone II
Lake
Cross sectional
Elevation
Zone I Zone III
Zone I and Zone III : Inlet and Outlet zones with coarse gravel or rocks (±1m length)
Zone II: Gravel, sand and soil bed planted with papyruses.
Remark: The bottom of a constructed wetland should be well lined with a sheeting
material to avoid any infiltration in the soil that would cause groundwater pollution.
31
Rooms Staff Rooms
Bloc 1 Rooms Bloc 2
20m
S
+1m T Septic Tank 1
1
10m
Constructed
+0m Treatment
Wetland 1
32
Pavilions Residential Suites
20m
S
+1m T Septic Tank 2
2
10m
Constructed
+0m Treatment
Wetland 2
33
4.7. Solid wastes management
This consists of collection and disposal of all the solid wastes or garbage
produced by different activities in the resort. These solid wastes will be of two
types, namely:
Solid wastes will be collected in bins and trash cans that should be placed in
every corner of the resort and in rooms.
Places most likely to produce garbage are:
- The kitchen
- On the sides of internal roads
- In green spaces around the lake
- In rooms
- In bungalows
- In the restaurant and bar
- The conference hall
- Etc.
The bins will be visited and garbage collected every morning, and the
biodegradable and non-biodegradable materials separated as their disposal will
be different. A pit will be excavated in the space reserved for a vegetable garden
near the water reservoir, and it will be used as compost to produce manure for
vegetables cultivation. All the biodegradable wastes from the kitchen and other
food wastes will be disposed in this pit, whereas other biodegradable wastes, like
papers and brushes, will be collected with non-biodegradable wastes in a space
which will be provided near the compost. Once a week, the available garbage
will be transported to a public solid waste disposal site that should be indicated
by the Rwamagana District authorities.
34
V. ENVIRONMENTAL IMPACT
It is in this context therefore that both environmental and social aspects were
identified to determine the nature and magnitude of environmental concerns for
the Muhazi Beach Resort project.
For purposes of identifying the potential environmental impacts the project has
been described in two phases namely the construction phase and the exploitation
phase. The first phase mainly constitutes the civil works that are already being
undertaken and the second is the project operation.
The site chosen for the development of this project is adjacent to Lake Muhazi,
and some bungalows are built at a distance of 15m from the lake banks. This
distance is smaller than the minimum of 20m required in the Environmental
Organic Law, but as said earlier, the construction phase of the project started in
2003, well before this law was established.
During conducted field visits, we noted that the site is surrounded by banana
plantations and livestock farming areas, but the first inhabited houses are located
at a distance of about 400m from the project site. Also, as the project was already
undergoing the construction phase, it was not easy to ascertain the type of
vegetation cover on the site before the works started but it is obvious that there
was very little natural vegetation considering the agricultural activities in the
vicinity of the project site.
The project would definitely have some impacts (positive and negative) on the
surrounding environment in both direct and indirect ways, as there will be direct
and indirect interactions between project activities and the environment. This
will have different effects on the environment and on the project itself.
This chapter identifies, analyses and classifies these impacts that could arise from
the activities of the project, either during the construction phase or the operation
phase. The impacts apply as well on the socioeconomic environment (health,
security, economic activities, finances, etc) and on the biophysical environment
(fauna, flora, water, air, soil, energy).
35
All these impacts affect the environment at different degrees, and their duration
differs. That’s why the impacts are classified differently according to their range
in space and time.
It is necessary to note that it is not only the project that will have impacts on the
environment, but also the environment will have some impacts on the project.
These impacts can also be positive or negative, direct or indirect and they are
also described in this study.
The range of the impacts varies in space and time. The intensity of theses impacts
is classified according to following criteria:
• Loss of habitat for some fauna and flora species and biodiversity
reduction as a consequence of migrating species due to vegetation clearing
of the construction site.
→ Negative, middle and permanent impact
36
• Risks of lake water pollution due to soil and cut bushes transported by
runoff after site clearing works.
→ Negative, middle and temporary impact
• Soil erosion due to exposure of the soil after removal of ground cover.
→ Negative, weak and temporary impact
• Change in the natural ecosystem of the lake near the project site, resulting
in migration of fish species and other fauna, and then reduction of
biodiversity due to lake water pollution.
→ Negative, important and permanent impact
37
• Solid wastes from tourism activities on the resort, causing pollution on the
surrounding environment.
→ Negative, middle and permanent impact
• Job creation for those who will be employed by the project, either in the
construction phase or the implementation phase, but also there will be
business opportunities for related support services like supplies,
transport, furniture, selling art and crafts, etc.
→ Positive, important and permanent impact
38
• Risk of increase in road accidents resulting from increase in road traffic
essentially for the portion linking the tarmac road to the tourism village.
→ Negative, middle and permanent impact
• The site of the project being on the sides of the Lake Muhazi, and the
seaside tourism being the most prestigious form of tourism, the resort will
benefit a lot from the Lake like water sport, fishing, aesthetic view, etc.
→ Positive, important and permanent impact
• Water accidents, mainly drowning, would be caused by the fact that the
project is too close to Muhazi Lake, and many of the tourists might be
tempted to play in water without knowing how to swim.
→ Negative, important and permanent impact
39
VI. ANALYSIS OF ALTERNATIVES
This chapter analyzes the possible alternatives besides the methods and other
parameters already considered in the conception of the project. The analysis is
only about the alternatives for activities that could have a negative impact on the
environment.
Bearing in mind the critical need for the protection of environmental ecosystems
and the core role for life support systems, it’s imperative to analyse and balance
the need for conservation and development.
Zero scenario
In the case where the zero scenario is considered, this means that there won't be
construction of the tourism village, whereas the project is already in its
construction phase.
This alternative will have following effects:
- There won’t be tourism development in the area, and no taxes
collected for the State treasury.
- Lack of exploitation of natural resources in the area, then loss of
development opportunities.
- The Promoter won’t be able to honour his engagements towards the
banks and the suppliers.
- Lack of employment for the intended staff members, and job or
business opportunities in general.
- The population surrounding the proposed site would lose an
opportunity to develop income generating projects related to the
tourism activities, thus no poverty reduction in the area.
- As the project won’t be implemented, all the negative impacts
enumerated in the previous chapter will be avoided.
Site selection
The development plan of the Eastern Province provide the Lake Muhazi to be the
key factor for tourism development in the eastern region of the country, and then
tourism development projects must be given priority to develop on lakesides.
The actual site was selected mainly because it belonged already to an abandoned
tourism project. For that reason, the road linking the project site to the tarmac
road is relatively in good condition and therefore easing the accessibility to the
tourism village. Also, its location offers a panoramic view of a big part of the
lake, thus ideal for a tourism project. It is not easy to find an alternative site
with the same combined opportunities, because the others are either already
40
occupied and densely settled comparing to this which hadn’t any inhabited
house, or are located far from the Rwamagana town and not easily accessible.
Construction
The resort is constructed according to the best design for lakeside development
projects, using a number of scattered bungalows. The project will use local
construction materials as far as possible, and the emphasis has been made for the
use of stones and timber produced locally.
Wastewater treatment
The technology which has been considered in wastewater treatment uses a septic
tank system and a constructed wetland for a further treatment of the effluent
before it is disposed off.
The alternative technology which was suggested is the use of a wastewater
treatment plant using a ROTORDISK B15 developed by Seprotech Systems Inc.
This alternative was proved to be effective and space saving, but it is three times
more expensive than the combined wastewater septic tank and constructed
treatment wetland systems and it requires more energy input and a skilled
operator, without forgetting that the maintenance of new technologies is not easy
in developing countries where spare parts are always to be imported.
Conclusion:
While considering the importance of the aforesaid impacts, one could say that in
a general manner, the project of construction and implementation of Muhazi
Beach Resort will have important positive impacts on the socio-economic
environment of our country. However, a non negligible number of potential
negative impacts of the project to the environment has been put in evidence, and
require to be taken in consideration during both the construction and
implementation phases.
41
VII. MITIGATION MEASURES
Considering the study of the entire project and the site layout plans, most of the
mentioned impacts are not likely to happen. However, the following mitigation
measures have been recommended:
1) The high proximity of some resort buildings to the lake will produce
conditions with negative impacts leading to lake water pollution.
Appropriate and strict measures should then be taken by the management of
the resort in order to avoid any waste material to be thrown into the lake, and
with this regard a well designed sewerage system shall be implemented and
trash bins shall be placed anywhere necessary for the collection of solid
wastes in the resort.
2) The loss or migration of some fauna and flora species resulting from
construction works will be compensated by a creation of green spaces with
attractive plants and development of gardens inside the tourism village for
biodiversity conservation. It will be needed to mix local and exotic plants to
have as much as possible a natural environment in the area of the project.
3) A proper drainage system for storm water should be applied, and all exposed
surfaces other than access roads covered by grass planting in order to avoid
erosion and to restore infiltration capacities of the soil.
6) All the solid waste should be collected; the biodegradable organic material
composted properly on site for manure production and the non-
biodegradable disposed off in a public garbage collector or transported to a
Public Dumping Site that will be provided by the Rwamagana District
authorities.
42
7) In order to avoid road accidents, the road portion linking the tourism village
to the tarmac road should be well maintained, potholes covered, the
roadsides cleared and humps added where needed. Also, speed restriction
measures should be applied to protect road users.
8) As part of the initiative for maintenance of cultural heritage and value among
neighbouring communities, the Developer plans to promote traditional
dances at the camp as part of its tourism package.
10) Ensure clear separation of the water supply system from the sewerage
system, and frequent and regular check for drinking water quality.
11) Regular monthly check of the quality of the treated wastewater effluent, and
emptying of the septic tank once a year.
12) Proper maintenance and protection of the constructed wetland for effective
operation.
43
VIII. ENVIRONMENTAL MANAGEMENT PLAN FOR
MUHAZI BEACH RESORT PROJECT
Table 6: The Environmental Management Plan for the project of construction and
implementation of a Tourism village “Muhazi Beach Resort” at Muhazi,
Rwamagana District.
44
Components Negative Impacts Mitigation measures Implementation Timing Responsibility Monitoring
indicators
I. Construction - Loss of habitat for Creation of green spaces Presence of green End of The developer - REMA.
Phase some fauna and flora with attractive plants and spaces and construction
species and development of gardens gardens. phase.
biodiversity inside the tourism village
reduction as a for biodiversity
consequence of conservation.
migrating species
due to vegetation
clearing of the
construction site;
- Soil seepage
capacity for water
significantly reduced.
Risks of lake water - Proper compaction of the - Soil well All the - The developer - MINITERE ;
pollution due to soil excavated soil; compacted; construction
and cut bushes period. - Site manager - REMA.
transported by runoff - Collection and burning of - Cut bushes
after site clearing all the cut branches and burned properly.
works. bushes.
Possible pollution of Optimum use of Construction All the - The developer - MINITERE ;
the lake water due to construction materials to materials construction
wastes produced minimize wastes, and effectively used, period. - Site manager - REMA.
from construction avoid the disposal of any and no wastes
works. waste material into the disposed off into
lake. the lake.
45
Components Negative Impacts Mitigation measures Implementation Timing Responsability Monitoring
indicators
II. Operation Pollution and - The wastewater drainage - Proper Continuous The devoloper - Rwamagana
Phase possible and treatment systems wastewater for the District
contamination of should be properly drainage system ; lifetime of authorities;
groundwater table constructed, well operated the project.
and lake water due to and maintained in order to - Appropriate - MINITERE
failure of the avoid contamination of the wastewater
drainage system, the lake water. treatment system. - REMA.
effluent produced
after wastewater - Regularly check the - Final effluent
treatment in septic efficiency of the from constructed
tank or poor constructed treatment wetlands
maintenance of wetland systems. regularly
II. a. constructed (monthly)
Bio-physical
wetlands. analyzed.
environment
Solid wastes from All the solid waste should The compost is Continuous The developer - Rwamagana
tourism activities on be collected; the constructed for for the District
the resort, causing biodegradable organic manure lifetime of authorities;
pollution on the material composted production and the project.
surrounding properly on site for garbage - REMA.
environment. manure production and collection is
the non-biodegradable scheduled at least
disposed off in a public once a week.
garbage collector or
transported to a Public
solid wastes disposal site.
46
Components Negative Impacts Mitigation measures Implementation Timing Responsability Monitoring
indicators
II.2. Risk of increase of Installation of condom Presence of Continuous The devoloper - MINISANTE;
Socio- sexually transmitted dispensers in appropriate condom for the
economical diseases resulting places (toilets for example) dispensers. lifetime of - REMA.
environment from sex tourism. inside the hotel. the project.
Risk of increase in Rehabilitation of the road The road is At the - The - Rwamagana
road accidents portion to the Tourism rehabilitated. beginning Rwamagana District
resulting from village, and provision of of the District; authorities;
increase in road humps where needed for operation
traffic essentially for speed reduction. phase. - The - MININFRA ;
the portion linking developer.
the tarmac road to - REMA.
the tourism village.
Water accidents, To provide a staff member - A swimming At the - The developer - Rwamagana
mainly drowning, always present on the officer always beginning District
would be caused by beach for the supervision present on the of the authorities;
the fact that the of all water games. Life beach. operation
project is too close to jackets available for all phase. - REMA.
Muhazi Lake, and those who want to play in - Life jackets
many of the tourists water. available for
might be tempted to tourists.
play in water without
knowing how to
swim.
47
8.2. EMERGENCY PLAN IN CASE OF ACCIDENT OR FIRE
Fire fighting equipments should be available in all buildings and should be kept
in good working state. For this purpose we recommend the use of wet risers
installed in all houses and provided with automatic smoke detectors, but also the
installation of extinguishers in a case where an accident occurred when the
electrical power is cut. The use of these fire-fighting equipments should be one
of the key points during the training of the project staff. The technician in charge
of the maintenance and estate management should always check these
equipments and ensure that they are always ready to be used.
The tourism village will have also its own infirmary with a qualified staff, able to
give the first aid when necessary before transferring the critical cases toward the
hospitals.
48
IX. CONCLUSION AND RECOMMENDATIONS
The project of construction and operation of the tourism village “Muhazi Beach
Resort” has as the main objective, the promotion and exploitation of tourism
activities in Rwanda.
This project has many benefits on the socio-economic point of view, but this
study showed the existence of a non negligible number of negative
environmental impacts that may arise from the implementation of this project.
The mitigation measures of different negative impacts have been proposed and
an environmental management plan has been established. Therefore, the
implementation of the tourism village will be a successful project if the
environmental management plan proposed is followed by all persons directly or
indirectly involved in this project, and more especially the direction of the resort
that will have a major role to play.
We think that the present project is therefore acceptable and the direction of the
tourism village will be responsible to take all possible complementary
arrangements in addition to numerous proposed mitigation measures in order to
protect the environment.
So, based on the nature of project activities, biophysical conditions of the project
area and the potential negative impacts, it is imperative that the following be
given serious consideration and attention in order to preserve the environment:
- The Developer should ensure that the list of the tree species or flowers
for re-planting on the site is shared with the responsible government
agency to analyse its convenience.
49
- Maintain the initiative for community support in terms of trade,
culture and employment.
50
X. REFERENCES
Official Gazette of the Republic of Rwanda, Year 44 n° 9, 1st May 2005. Organic
Law n° 04/2005 of 08/04/2005, determining the modalities of protection,
conservation and promotion of environment in Rwanda.
51