GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 1 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
AUTHORIZATION AND RECORD
Rev.
Description
Prepared by
(Contractor)
Reviewed by
(Consultant)
Approved by
(GP)
Date
1.0
SIMON
FONG
11/11/2003
2.0
SIMON
FONG
20/06/2004
3.0
SIMON
FONG
Important
The information contained herein is the proprietary property of Gerbang
Perdana Sdn. Bhd. It shall not be reproduced, copied, revealed, published, or
distributed in whole or partly without authorization.
TABLE OF CONTENTS
Ref
Description
Page No.
1.0
INTRODUCTION.......................................................................................
2.0
SCOPE OF WORKS.................................................................................
3.0
4.0
METHOD STATEMENT.............................................................................
5.0
MATERIAL.................................................................................................
6.0
MACHINERY.............................................................................................
7.0
MANPOWER.............................................................................................
8.0
9.0
10.0
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 2 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
1.0
Introduction
The purpose of this method statement is to describe and define the process flow for
the installation of lifts and to ensure that the work is carried out in a controlled and
systematic manner conforming to the specific requirements.
2.0
Scope of works
The scope of works covers supply, install and commissioning of the lifts. All
materials and works shall comply with the tender specifications, construction drawing
and approved shop drawings and samples.
3.0
4.0
Method Statement
Handing Over of Lift Shaft (s) and Lift Machine Room (s)
4.10
Requirement for handing over the lift shaft (s) for commencement of lift installation
are as follows:a) Stages of floors to be handed over for lift installation shall be scheduled in
accordance with the Nam Fatt Construction Sdn. Bhd. Master Work Programme
approved by Gerbang Perdana Sdn. Bhd.
b) Scaffolding to be erected in the lift shaft (s).
c) Separator beams shall be installed if required.
d) Protections shall be provided to prevent seepage of water into the lift shaft (s).
e) To remove all formworks, timbers, or steel bars sticking out along the internal
shaft wall.
f) To clear all debris, water and unwanted material in the lift pit (s).
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 3 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
g) Curbs shall be provided at every lift entrance to prevent water from flowing into
the lift shaft (s).
h) Temporary power supply for lightings, power hand tools and light power
machinery shall be provided at every floor.
i) Lift door opening, lift well entrance and trap door hole shall be protected at all
time during construction.
j) A covered storage area at site will be allocated to lift equipment upon the delivery
of equipment. All items shall be stacked up properly and in safest possible way
during storage to keep away from rain and ground dirt and electronic parts shall
be protected from rain, dust and dirt before installation.
Preparatory works of lift installation are as follows:
i.
ii.
iii.
iv.
To remove all formworks and timbers in the lift machine room (s).
To clear all debris and unwanted material out of the lift machine room (s).
To ensure that there is no water seepage into the lift machine rooms (s)
Machine room shall be at least completed with screeded floor and plastered
walls.
v. Machine room shall be provided with lockable door (at least temporary) door
to be provided if permanent one is not available.
4.11
4.12
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 4 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
4.13
4.14
4.15
4.16
4.17
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 5 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
4.18
4.19
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 6 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
4.20
4.21
4.22
4.23
4.24
4.25
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 7 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
4.26
4.27
4.28
4.29
4.30
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 8 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
5.0
Materials
Lift Car, Lift Shaft, Guide Rail Brackets, Landing Door Frames, Landing Door
Panels, Conduits, Trunking, Shaft Wiring, Buffers, Hall Position Indicator, COP and
LMR Equipment.
6.0
7.0
Mobile Crane
Forklift
Scaffolding
Plumb
Hoisting Tools
Hand Tools
Man Power/Responsibilities
Below are the personnel involved in the installation of the Lifts
a.
b.
c.
d.
e.
f.
g.
8.0
Project Manager
Area Executive
Project Supervisor
Installation Supervisor
Finishing Supervisor
Installation Team
Adjusting Team
286267455.doc
METHOD STATEMENT
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 9 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
9.0
Standard Checklist
Pernas Otis Elevator Standard Checklist is attached in Section 3.
Drawing No.
Drawing Title
ii
iii
iv
vi
vii
viii
ix
xi
xii
xiii
xiv
xv
xvi
xvii
286267455.doc
METHOD STATEMENT
For Lift Works
Page No.
Revision No.
Issued
GERBANG PERDANA S B
(RoC No. 469478-X)
No. 3, Jalan 222,
46100 Petaling Jaya,
Selangor Darul Ehsan
: 10 of 10
: 3.0
: 13.01.2005
MS-CIQ02/M/032/R3.0
APPENDIX (1)
WORK SEQUENCE FLOW
Erection of
Scaffolding
Plumbing of Lift
Shaft
Approval of
Plumbing Result
Install Guide
Rails Bracket
Fabrication of
Guide bracket
Install Landing
Door Frames
Quality
Inspection
Install Shaft
Wirings
Install Machine
Room Equip.
Grouting of LDG Door
Frames
Install LDG
Door Frames
Lift Interior
Finishes
Practical
Completion
JKKP Inspection &
Handling Over
286267455.doc