Documente Academic
Documente Profesional
Documente Cultură
NOTE:
Make sure you understand very well how the critical activities are defined and set in your project setting when you are dealing with longest path or critical
activities.
All the critical activities may not be on longest path but longest path activities are all critical if Make open-ended activities critical and Total Float less than or
equal to have been selected in Schedule Options box and project default setting. See below figures.
2) To find Critical activities with Start Constraint, select both Critical and Has Start Constraint.
3) To find Remaining Critical activities that have been started (in progress), select both Critical and In progress.
4) To find Negative float (total float less than 0 duration), select Negative Float filter.
5) In case you might just want to review critical milestone activities, then select both Critical and Milestone.
6) To find milestone activities on longest path, select Longest Path and Milestone.
2) Untitled filter (a new filter) box as shown in below will appear the moment New tag is clicked.
4) Once you have done item (3) , click Ok and then select Apply to see filter result.
6) Add BL Project Finish in 3rd row. Project Baseline must be available in your project in order to use this filter. If you are unsure how to maintain and assign a
project baseline, learn more at How to fix the problem Baseline Changes with the Data Date changes
7) In 3rd row, set the parameter as BL Project Finish is less than or equals to DD,
Add Activity Status is not equal to Completed in 4th row.
8) Select 1st row and add new row for additional criteria.
9) The moment Add tag is selected, a new row (2*) appears as 2nd row of the filter and the additional function or also appears in the filter box as below.
10) Select the new row (2*) and click Add to add an additional rows.
11) Once a new row (3*) appear, select BL Project Start and set the criteria as is less than DD.
12) Then, add a new row again (4*) and select Activity Status from drop-down list. Set the criteria as equals Not Started.
Finally, you have built a filter that return
(a) Activity planned to started before status date but not yet started
(b) Activity planned to finish by status date but not completed.
13) Click OK to close filter box window, then Apply filter to run filter.
You should be able to review activity lists that are behind schedule as below.
6) Click Ok and select the existing predefined filters Milestone and Not Completed to filter remaining milestone activities.
Finally, you should be able to see schedule variance for Milestone as below. Negative schedule variance means project is behind schedule and positive means
project is ahead of schedule.
NOTE:
Show the column Variance-BL Project Start Date to see schedule variance in activities view.
Select Project Baseline Milestone bar in Bars window to see milestone schedule variance on Gantt chart. Project Baseline must be available in your project in
order to use this filter. If you are unsure how to assign
and maintain project baseline line, learn more at How to fix the problem Baseline Changes with the Data Date changes
5) Select Predecessor in 2nd row. Set the parameter Predecessors equals blank. See below.
6) Select 2nd row and add a new (3rd row) to set filter parameter as Successors equals blank. See below.
9) Select additional filter Not Completed from Global filter list to show remaining activities with no relationship (broken logic). See below.
I hope you learnt how to build Schedule Analysis Filter by now. Happy Scheduling.
To identify top 3 float path activities and compare against the baseline, the following columns need to be shown other than any column that you want to display.
See sample layout picture below.
Original Duration
At Completion
Activity % Complete
Start
Finish
This layout is created by the combination of total two selected filters. See below snapshot.
Activity Status Filter ( Activity Status is not equal to complete)
Float Path Filter (Float Path is less than or equal to 3 )
All selected Filter
(2) Select Make open-ended activities critical and Use Expected Finish Dates to be as part of critical path.
(3) Select Longest Path to define critical activities as longest path.
download
Note: You wont be able to see "Baseline bar", any data in "Baseline Total Float" and "Variance Baseline
Finish" column if the baseline wasn't available in your schedule