Documente Academic
Documente Profesional
Documente Cultură
Page 2
November 2, 2011
Mr. Carlos Brown
Re: Repairs of Paver Block Pavement Phase 2 Extension of Time
On February 22 and 23 it was determined that the water was coming from the trough of
the landside crane rail beam through a damaged section of the beam itself. On February
24 and 25 the damaged section of the beam was cut out and reconstructed. We were
given verbal assurance on February 25, 2011 that the placement of the asphaltic concrete
would commence on February 28, 2011. However on February 28, 2011 while a
vibrating roller was brought to site the works did not commence. In response to the lack
of action on your part we wrote to you enquiring why the works had not commenced.
No response in writing was ever received.
While you have repeatedly suggested
thereafter that the delay was due to our request for a design for the asphaltic concrete mix
we hereby indicate yet again that this information had been requested from February 21,
2011 and was in fact a requirement of the Contract outlined in the Preliminaries. As
such we may not be held liable for the tardiness of your sub-contactor in providing this
information and any delay that may have resulted. Subsequent to the aforementioned we
are prepared to grant a further six (6) days extension of time covering the period February
22 27, 2011.
As there is no overlap between the two award periods, the overall extension of time to be
granted shall be twelve (12) calendar days or two (2) weeks in accordance with Clause 44
of the Conditions of Contract. This extension of time is granted with additional costs for
time-dependent preliminaries only as per Clause 44 (3) of the Conditions of Contract.
Based on the extended completion date of March 30, 2011 stated in our letter of March
15, 2011, the new extended completion date is April 11, 2011.
Yours sincerely,
THE PORT AUTHORITY OF JAMAICA
David Mudahy
CIVIL ENGINEER
DM/sh
Copy:
Mr. Mervis Edghill Senior Vice President Engineering & Port Development
Mr. Gary Lawrence Vice President - Engineering