Commissioning Procedure

For
ION-B System

TABLE OF CONTENTS
1. INTRODUCTION...............................................................................................................................................

Revision 0: 1st August 2011


Prepared by:

Andrew LLC
Wireless Innovations Group
2601 Telecom Parkway
Richardson, Texas 75082
2011 Andrew LLC. All rights reserved.
NOTICE: This document contains data and information proprietary to Andrew LLC. This proprietary information shall not be disclosed,
disseminated, or reproduced in whole or in part without the express written authorization of Andrew LLC.
Page i

Commissioning Procedure

Objective.................................................................................................................................................................
Document Organization..........................................................................................................................................
2. PARAMETERS OVERVIEW..............................................................................................................................
Gain Loss Distribution.............................................................................................................................................
Table 1: Downlink signal levels...............................................................................................................................
Table 2: Uplink signal levels...................................................................................................................................
3. EQUIPMENT VERIFICATION...........................................................................................................................
4. DOWNLINK SETUP..........................................................................................................................................
5. ANTENNA INSPECTION AND SIGNAL LEVEL VERIFICATION.....................................................................
6. UPLINK SETUP AND NOSIE FLOOR VERIFICATION....................................................................................
7. OPERATOR INTEGRATION............................................................................................................................
Downlink Setup.......................................................................................................................................................
Uplink Setup...........................................................................................................................................................
8. ATTACHMENTS................................................................................................................................................
Attachment 1: Equipment verification.....................................................................................................................
Attachment 2: Downlink Setup................................................................................................................................
Attachment 3: Antenna Signal Level Verification....................................................................................................
Attachment 4: Uplink Setup and Noise Floor Verification.....................................................................................
Attachment 5: Operator Downlink Setup...............................................................................................................
Attachment 6: Operator Uplink Setup...................................................................................................................

LIST OF FIGURES
Figure 1: Gain and Loss Block Diagram...................................................................................................... 4

REVISION REGISTER
Revisio
n No.

Date

08/01/2011

Description
Initial release

Page ii

Commissioning Procedure

Page iii

Commissioning Procedure

1.

INTRODUCTION
Objective
The objective of this document is to define the steps necessary for commissioning ION-B System
Document Organization
The document starts by summarizing the system parameters in Section 2. Section 3 includes Equipment
verification and Section 4 includes the steps for downlink set up. Steps for Antenna inspection and signal
level verification is are given in Section 5. Uplink set up and noise floor verification is given in Section
6.Section 7 describes the steps for operator integration. In addition to the above-mentioned Sections,
Section 8 document contains the following attachments:

2.

Attachment 1: Installation verification

Attachment 2: Downlink signal level at the input of TFLN

Attachment 3: Downlink signal level at Antenna port of the remote unit

Attachment 4: Minimum signal level at the Antenna

Attachment 5: Operator downlink and uplink levels

PARAMETERS OVERVIEW
Gain Loss Distribution

The gain and loss block diagram for a proposed ION-B System is shown below

Figure 1.

Figure 1: Gain and Loss Block Diagram

Revision: 0

Page 4
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure

Table 1: Downlink signal levels


** Note: Input Power Range to TPOI: +15 to +25 dBm per carrier

Table 2: Uplink signal levels

3.

EQUIPMENT VERIFICATION
The following steps describe the equipment verification steps prior to system setup:
1. Verify the Master Unit (MU) rack is built as per rack Layout
2. Verify the Fiber / Jumper Connectivity at the MU
3. Verify TSUN Connectivity to all MU Components
4. Check the Alarm Status on MU & RU components

Revision: 0

Page 5
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
5. Complete the Attachment 1 and list any issues noticed in the above steps.
4.

DOWNLINK SETUP
The following steps describe the downlink setting of the system:
1. Set up the CW transmitter or signal generator to the required downlink signal level into the TPOI as per
Table-1.
2. Measure the input power into the TFLN port.
3. Adjust the TPOIs programmable attenuation to match the expected input power into the TFLN
4. Record the measured level and TPOI setting in attachment 2.
5. Repeat the above steps for all zones and bands.
6. Record the measured values and TPOI setting in Attachment 2.

5.

ANTENNA INSPECTION AND SIGNAL LEVEL VERIFICATION


The following steps are used to verify connectivity to the antennas and verification of proper mapping of
remotes to the corresponding zones:
1. Set up the CW transmitter or signal generator to the required downlink signal level into the TPOI as per
Table-1.
2. Inspect the antenna orientation visually before checking the signal level below the antenna.
3. Measure the signal level below antenna
4. Verify that the measured values are greater than the expected minimum level given in Attachment 3.
5. Record the signal level below antenna in the form given in Attachment 3.

6.

UPLINK SETUP AND NOSIE FLOOR VERIFICATION


The following steps are used to setup the uplink path and measure the uplink noise floor for each zone:
1. Inject the CW transmitter or signal generator to the TFLN and measure the signal at the TPOI output.
Adjust the TPOIs programmable attenuation to match the expected uplink loss and record the TPOI
setting in attachment 4.
2. Ensure that all remotes for a given zone are connected and turned on.
3. Measure the uplink noise level in 30KHz at the Input of point of interface
4. Verify that the measured value is within expected level
5. Record the measured noise floor values in the form given in Attachment 4.
6. Save spectrum analyzer plot

Revision: 0

Page 6
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
7.

OPERATOR INTEGRATION
Downlink Setup
1. Ensure that all remotes for a given sector are connected and turned on.
2. For each sector measure the level at the TPOI.
3. Verify if the Input level is within expected level.
4. Save the spectrum analyzer plot.
5. Repeat the above steps for all bands all sectors
6. Record the measured values in the form given in Attachment 5
Uplink Setup
1. Measure the UL noise floor at the TPOI before and after operator is connected to the DAS
2. Provide the RTWP offset to the operator.
3. Verify if the measured Noise floor is within expected levels
4. Save the Spectrum analyzer plot.
5. Repeat the above steps for all bands all sectors
6. Record the measured values in the form given in Attachment 6

Revision: 0

Page 7
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
8.

ATTACHMENTS
Attachment 1: Equipment verification

Attachment 2: Downlink Setup

Revision: 0

Page 8
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
Attachment 3: Antenna Signal Level Verification

Revision: 0

Page 9
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
Attachment 4: Uplink Setup and Noise Floor Verification

Revision: 0

Page 10
This document contains Andrew LLC Proprietary Information see notice on cover page.

Commissioning Procedure
Attachment 5: Operator Downlink Setup

Attachment 6: Operator Uplink Setup

Revision: 0

Page 11
This document contains Andrew LLC Proprietary Information see notice on cover page.