MEASUREMENT (SBEQ3213)
Week 2 : Prime Cost (PC) Sums
TABLE OF CONTENTS
1. Preparation of Contract Bills
+
PREAMBLES
+
MEASURED WORKS
+
PRIME COST SUMS AND PROVISIONAL SUMS
+
APPENDICES
=
CONTRACT SUM
May comprise over 30 items, only a small number of item (15-20 items) priced
Value may account for between 8% and 15% of contract sum
Preambles
Measured
Works
PC & Prov
Sums
Appendices
Includes the tender summary, a list of the main contractors, nominated subcontractors, price list of materials and nominated sub-contractors works to be
tendered.
PURPOSE OF MEASUREMENT
Purpose of measurement Prime Cost Sum and Prov. Sum
are:
1.
2.
3.
4.
SECTION A
GENERAL RULES
TYPES OF ATTENDANCE
GENERAL ATTENDANCE: this is deemed to include the use of
contractors temporary roads, pavings and paths, standing
scaffolding, standing power, operated hoisting plant, the provision of
the sub contractors own offices and for storage of his materials and
space for the use of messrooms, sanitary accommodation and
welfare facilities.
SPECIAL ATTENDANCE: This includes the use by the sub contractors
of special scaffolding additional to the main contractors standard
scaffolding. The provision of temporary access roads, hard standing
in connection with structural steel works, precast concrete,
components piling, heavy plant and the like.
Description
Rate
RM
SUM
2,674,000
00
Electrical Works
Provide a Prime Cost Sums of Ringgit Malaysia :
Two Million Six Hundred Seventy Four Thousand
Only (RM2,674,000.00) for Electrical Works
Allow for profit .%
Allow for attendance
%
L.S.