Managing scope
Principles
Product and work and breakdown
Project definition
Project definition report
Avoiding unnecessary work
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Goals
Benefit
Operation
Outcomes
Resources
Project
Outputs
Do the right
project
Implementation
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
New
Asset
Goal
Capability
1
Step1
1
Step2
1
Problem
1
Capability
2
Step1
2
Step2
2
Problem
2
Capability
3
Step1
3
Step2
3
Problem
3
EuroProjex
jrt/epm/mar06
Goal
Value
rodneyturner@europrojex.co.uk
The project
Scope
Project
jrt/epm/mar06
Output
New
Asset
Outcome
Goal
Capability
1
Step1
1
Step2
1
Problem
1
Capability
2
Step1
2
Step2
2
Problem
2
Capability
3
Step1
3
Step2
3
Problem
3
EuroProjex
Goal
Value
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Managing scope
Principles
Product and work and breakdown
Project definition
Project definition report
Avoiding unnecessary work
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Henley
EuroProjex
jrt/epm/mar06
St Tropez
rodneyturner@europrojex.co.uk
Project definition
Purpose
Objective
get ti St Tropez
Scope
jrt/epm/mar06
go on holiday
EuroProjex
rodneyturner@europrojex.co.uk
Henley
Dover
Calais
Beaune
Milestones
Level 1 Plan
Lyons
Aix-en-Provence
EuroProjex
jrt/epm/mar06
Henley
St Tropez
rodneyturner@europrojex.co.uk
Dover
Portsmouth
Zeebrugge
Calais
Le Havre
Beaune
Coordinating with
other resources
Lyons
Geneva
Bordeau
Aix-en-Provence
jrt/epm/mar06
EuroProjex
St Tropez
rodneyturner@europrojex.co.uk
Level 2 plan
M40
M25
Dartford Crossing
M2
M4
M25
M20
EuroProjex
jrt/epm/mar06
Henley
rodneyturner@europrojex.co.uk
Dover
Calais
Beaune
Rolling wave
planning
Lyons
Aix-en-Provence
jrt/epm/mar06
EuroProjex
St Tropez
rodneyturner@europrojex.co.uk
Breakdown
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Portfolio
Objectives
Portfolio
Strategy
Program
Objectives
Program
Strategy
Project
Objectives
Project
Strategy
Work area
Objectives
Work area
Strategy
jrt/epm/mar06
Project strategy
EuroProjex
Team
Objectives
Team
Strategy
Individual
Objectives
rodneyturner@europrojex.co.uk
Programme
Project
Area of work
Work package
Activity
Task
Item
Step
Deliverable
Duration
Development
Opportunities
Project Objective
Milestone
Component
<
<
<
<
<
<
<
EuroProjex
jrt/epm/mar06
Years
Quarters
Quarters
Months
Weeks
Days
Hours
rodneyturner@europrojex.co.uk
Advantages of breakdown
Better control
avoid scope creep
configuration management
Coherent delegation
Better estimating
Containment of risk
jrt/epm/mar06
organization breakdown
rodneyturner@europrojex.co.uk
Managing scope
Principles
Product and work and breakdown
Project definition
Project definition report
Avoiding unnecessary work
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
The project
Scope
Project
jrt/epm/mar06
Output
New
Asset
Outcome
Purpose
Capability
1
Step1
1
Step2
1
Problem
1
Capability
2
Step1
2
Step2
2
Problem
2
Capability
3
Step1
3
Step2
3
Problem
3
EuroProjex
Goal
Value
rodneyturner@europrojex.co.uk
Project definition
Purpose/Outcome - (Business Objective)
Why?
Purpose
Facility
problem
opportunity
benefit - OOM - 50%
Work
Scope
How?
jrt/epm/mar06
problem solving
options, costs vs benefit, value
in - high level definition of work
EuroProjex
out - nice to haves/delegate/interfaces
Delegate
Share
IN
Nice to have
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Managing scope
Principles
Product and work and breakdown
Project definition
Project definition report
Avoiding unnecessary work
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Project charter
jrt/epm/mar06
to the project
Key assumptions
Business commercial needs
Scope of work
Identify key activities, budgets and dates
Comment on how the project is to be managed
Role of the project manager
Reporting structure
EuroProjex
rodneyturner@europrojex.co.uk
Background
Benefits map
Project definition
Work structure
responsibility chart
stakeholder analysis
Constraints
milestone plan
Organization
purpose/scope/objectives
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Background
Outline business case
Project definition
jrt/epm/mar06
reasons, purpose
link to company strategy
objectives, products
scope
constraints
interfaces
rodneyturner@europrojex.co.uk
Prince 2
senior management write the mandate to initiate
the project
the sponsor and manager and write the brief and
obtain senior management approval
the manager writes the project initiation
document and obtains the sponsors approval
PMI PMBoK
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Team charter
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Managing scope
Principles
Product and work and breakdown
Project definition
Project definition report
Avoiding unnecessary work
EuroProjex
jrt/epm/mar06
rodneyturner@europrojex.co.uk
Scope creep
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
32
Scope creep
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
EuroProjex
rodneyturner@europrojex.co.uk
33
Scope creep
jrt/epm/mar06
Scope creep
Impact
cost
time
Avoiding
contract
change management
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
Change management
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
36
Change management
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex
rodneyturner@europrojex.co.uk
38
Cost of change
Emphasis of
Configuration
Management
Cost of
Error
General
Shipbldg
IT
Stage
jrt/epm/mar06
Define
Specification
1
1
1
n
3
10
Feas Design
EuroProjex
Deliver
Specification
n2
9
100
Execution
n3
27
1000
Close
rodneyturner@europrojex.co.uk
jrt/epm/mar06
EuroProjex