Documente Academic
Documente Profesional
Documente Cultură
CHAPTER 4
SITE INVESTIGATION PRACTICE
MNMAR07
SITE INVESTIGATION
Introduction
4.3
Soil Reconnaissance/Visual Inspection
The inspection is to obtain the following information:
A General topography of the site; possible existence of drainage, creep of
slopes and deep, wide shrinkage cracks and expansive soil.
MNMAR07
SITE INVESTIGATION
4.4
The objectives of site investigation have been defined by the various Codes of
Practice (BS CP 2001:1950, 1957; BS 5930:1981). They can be summarized as
providing data for the following.
i. Site selection.
The construction of certain major projects, such as earth dams, is dependent on
the availability of a suitable site. Clearly, if the plan is to build on the cheapest,
most readily available land, geotechnical problems due to the high permeability
of the sub-soil, or to slope instability may make the final cost of the construction
prohibitive. Since the safety of lives and property are at stake, it is important to
consider the geotechnical merits or demerits of various sites before the site is
chosen for a project of such magnitude.
ii. Foundation and earthworks design.
Generally, factors such as the availability of land at the right price, in a good
location from the point of view of the eventual user, and with the planning
consent for its proposed use are of over-riding importance. For medium-sized
engineering works, such as motorways and multistorey structures, the
geotechnical problems must be solved once the site is available, in order to allow
a safe and economical design to be prepared.
iii. Temporary works design.
The actual process of construction may often impose greater stress on the
ground than the final structure. While excavating for foundations, steep side
slopes may be used, and the in-flow of groundwater may cause severe problems
and even collapse. These temporary difficulties, which may in extreme
circumstances prevent the completion of a construction project, will not usually
affect the design of the finished works. They must, however, be the object of
serious investigation.
iv. The effects of the proposed project on its environment.
The construction of an excavation may cause structural distress to neighbouring
structures for a variety of reasons such as loss of ground, and lowering of the
groundwater table. This will result in prompt legal action. On a wider scale, the
extraction of water from the ground for drinking may cause pollution of the aquifer
in coastal regions due to saline intrusion, and the construction of a major earth
dam and lake may not only destroy agricultural land and game, but may
MNMAR07
SITE INVESTIGATION
introduce new diseases into large populations. These effects must be the subject
of investigation.
v. Investigation of existing construction.
The observation and recording of the conditions leading to failure of soils or
structures are of primary importance to the advance of soil mechanics, but the
investigation of existing works can also be particularly valuable for obtaining data
for use in proposed works on similar soil conditions. The rate of settlement, the
necessity for special types of structural solution, and the bulk strength of the subsoil may all be obtained with more certainty from back-analysis of the records of
existing works than from small scale laboratory tests.
vi. The design of remedial works.
If structures are seen to have failed, or to be about to fail, then remedial
measures must be designed. Site investigation methods must be used to obtain
parameters for design.
vii. Safety checks.
Major civil engineering works, such as earth dams, have been constructed over a
sufficiently long period for the precise construction method and the present
stability of early examples to be in doubt. Site investigations are used to provide
data to allow their continued use.
4.5
Site Investigations
MNMAR07
SITE INVESTIGATION
solutions. All the data from these first three phases are summarized in a
Geotechnical and Foundation Recommendations Report.
Phase IV: Detailed Site Investigation.
Very large projects will require an expansion of the three phases above.
The site investigation works consists of planning, making some test boreholes
and collecting soil samples. It has been found that the best site investigations
involve a considerable number of activities, some of which may become relatively
unimportant in some cases, but should never be forgotten. An ideal order of
events might be as shown in Table 1.1.
The sequence of geotechnical site investigation might be:
1. preliminary desk study, or fact-finding survey;
2. air photograph interpretation;
3. site walk-over survey;
4. preliminary subsurface exploration;
5. soil classification by description and simple testing;
6. detailed subsurface exploration and field testing;
7. the physical survey (laboratory testing);
8. evaluation of data;
9. geotechnical design;
10. field trials; and
11. Liaison by geotechnical engineer with site staff during project construction.
Requirements for Boring Layout and Depth
Required minimum depth of the borings should be predetermined.
According to ASCE (American Society of Civil Engineers, 1972), the minimum
depth of boring (Db) shall be determined by the following: Net increase of stress () under a foundation (Figure 2)
MNMAR07
SITE INVESTIGATION
Estimate the variation of the vertical effective stress (V') with depth.
1
q . Where q is estimation
10
1.3
MNMAR07
SITE INVESTIGATION
The site investigation works sequence can also be presented in flow chart shown
in Fig. 1.
MNMAR07
SITE INVESTIGATION
MNMAR07
SITE INVESTIGATION
4.6
4.6.1 Introduction
Many different techniques are available for site investigation. The method
employed will depend on many factors such as depth required, area to be
covered, ease of access, etc. On large jobs preliminary borings are used to
furnish overall subsoil surveys followed by final borings so soil or rock profiles
may be determined at the most useful orientations. In general, exploration
contracts should be open ended so that intermediate borings may be added in
areas that prove to be critical.
4.6.2 Soil Drilling
A wide variety of equipment is available for performing borings and obtaining soil
samples. The method used to advance the boring should be compatible with the
soil and groundwater conditions to assure that soil samples of suitable quality are
obtained. Particular care should be exercised to properly remove all slough or
loose soil from the boring before sampling. Below the groundwater level, drilling
fluids are often needed to stabilize the sidewalls and bottom of the boring in soft
clays or cohesionless soils . Without stabilization, the bottom of the boring may
heave or the sidewalls may contract, either disturbing the soil prior to sampling or
preventing the sampler from reaching the bottom of the boring. In most
geotechnical explorations, borings are usually advanced with solid stem
continuous flight, hollow-stem augers, or rotary wash boring methods. These
methods are often augmented by in-situ testing .Assuming access and utility
clearances have been obtained and a survey base line has been established in
the field, field explorations are begun based on the information gained during the
previous steps. Many methods of field exploration exist; some of the more
common are described below.
4.6.3 Test Pits and Trenches
These are the simplest methods of inspecting subsurface soils. They consist of
excavations performed by hand, backhoe, or dozer. Hand excavations are often
performed with posthole diggers or hand augers. They offer the advantages of
speed and ready access for sampling. They are severely hampered by limitations
of depth and by the fact they cannot be used in soft or loose soils or below the
water table.
MNMAR07
SITE INVESTIGATION
4.6.4 Boreholes
Borings are probably the most common method of exploration. They can
be advanced using a number of methods, as described below. Upon completion,
all borings should be backfilled and in many cases this will require grouting.
i.
The hand auger provides a light, portable method of sampling soft to stiff soils
near the ground surface. At least six types of auger are readily available:
posthole or Iwan auger;
small helical auger (wood auger);
dutch auger;
gravel auger;
barrel auger; and
spiral auger.
MNMAR07
10
SITE INVESTIGATION
MNMAR07
11
SITE INVESTIGATION
ii.
Auger Borings
Rotating an auger while simultaneously advancing it into the ground; the auger is
advanced to the desired depth and then withdrawn. Samples of cuttings can be
removed from the auger; however, the depth of the sample can only be
approximated. These samples are disturbed and should be used only for material
identification.
This method is used to establish soil strata and water table elevations, or to
advance to the desired stratum before Standard Penetration Testing (SPT) or
undisturbed sampling is performed. However, it cannot be used effectively in soft
or loose soils below the water table without casing or drilling mud to hold the hole
open. See ASTM D 1452 (AASHTO T 203).
iii.
Mechanical Auger
A large variety of size and type are available. Basic types are:
(a) Plate Auger.
Used in strata which will stand unsupported. It is necessary to pull out every foot
to examine cuttings. Depth limited by length of kelly bar (generally 6 m).
MNMAR07
12
SITE INVESTIGATION
MNMAR07
13
SITE INVESTIGATION
MNMAR07
14
SITE INVESTIGATION
iv.
Wash Borings
MNMAR07
15
SITE INVESTIGATION
MNMAR07
16
SITE INVESTIGATION
4.7
SAMPLING
There are 2 types of soil samples, there are disturbed and undisturbed.
4.7.1 Disturbed Sampling
Disturbed samples are generally obtained to determine the soil type, gradation,
classification, consistency, density, presence of contaminants, stratification, etc.
The methods for obtaining disturbed samples vary from hand excavating of
materials with picks and shovels to using truck mounted augers and other rotary
drilling techniques. These samples are considered .disturbed. since the
sampling process modifies their natural structure.
4.7.2 Undisturbed Sampling
Undisturbed samples are used to determine the in place strength,
compressibility (settlement), natural moisture content, unit weight, permeability,
discontinuities, fractures and fissures of subsurface formations. Even though
such samples are designated as .undisturbed, in reality they are disturbed to
varying degrees. The degree of disturbance depends on the type of subsurface
MNMAR07
17
SITE INVESTIGATION
materials, type and condition of the sampling equipment used, the skill of the
drillers, and the storage and transportation methods used.
4.7.3 Common Types of Samplers
The cuttings or washings from exploratory drill holes are inadequate to furnish a
satisfactory conception of the engineering characteristics of the soils
encountered, or even of the thicknesses and depths of the various strata. On the
contrary, such evidence more often than not is grossly misleading and has been
responsible for many foundation failures.
Proper identification of the subsurface materials requires that samples be
recovered containing all the constituents of the materials in their proper
proportions. Moreover, evaluation of the appropriate engineering properties, such
as the strength, compressibility, or permeability, may require the performance of
laboratory tests on fairly intact or even virtually undisturbed samples.
The expenditure of time and money increases rapidly as the requirements
become more stringent with respect to the degree of disturbance that can be
tolerated and with increasing diameter of sample. Therefore, on small projects or
in the initial exploratory stages of large or complex projects, it is usually
preferable to obtain relatively inexpensive, fairly intact samples from the
exploratory drill holes.
On the basis of the information obtained from these samples, the necessity for
more elaborate sampling procedures can be judged.
Types of Soil Sampler
MNMAR07
18
SITE INVESTIGATION
i.
MNMAR07
19
SITE INVESTIGATION
Figure 3-7: Split-Barrel Samplers: (a) Lengths of 457 mm (18 in) and 610
mm (24 in); (b) Inside diameters from 38.1 mm (1.5 in) to 89 mm (3.5 in).
As shown in Figure 3-8a, when the shoe and the sleeve of this type of
sampler are unscrewed from the split barrel, the two halves of the barrel
may be separated and the sample may be extracted easily.
The soil sample is removed from the split-barrel sampler it is either placed
and sealed in a glass jar, sealed in a plastic bag, or sealed in a brass liner
(Figure 3-8b).
Separate containers should be used if the sample contains different soil
types.
Alternatively, liners may be placed inside the sampler with the same inside
diameter as the cutting shoe (Figure 3-9a).
This allows samples to remain intact during transport to the laboratory.
In both cases, samples obtained with split barrels are disturbed and
therefore are only suitable for soil identification and general classification
tests.
Figure 3-8: Split Barrel Sampler: (a) Open sampler with soil sample and cutting
shoe; (b) Sample jar, split-spoon, shelby tube, and storage box for transport of
jar samples.
MNMAR07
20
SITE INVESTIGATION
ii.
MNMAR07
21
SITE INVESTIGATION
iii.
Piston Sampler
MNMAR07
22
SITE INVESTIGATION
iv.
MNMAR07
23
SITE INVESTIGATION
Figure 3-15: Pitcher Sampler. (a) Sampler Being Lowered into Drill Hole; (b)
Sampler During Sampling of Soft Soils, (c) Sampler During Sampling of Stiff or
Dense Soils. (Courtesy of Mobile Drilling, Inc.)
v.
Denison Sampler
MNMAR07
24
SITE INVESTIGATION
vi.
Is similar to a pitcher
sampler except that the
projection of the sampler
tube ahead of the outer
rotating barrel is manually
adjusted before
commencement of sampling
operations, rather than
spring-controlled during
sampler penetration.
The basic components of the
sampler (Figure 3-16) are :
an outer rotating core
barrel with a bit,
an inner stationary
sample barrel with a
cutting shoe,
inner and outer barrel
heads,
an inner barrel liner,
and
Figure 3-16: Denison Double-Tube
an optional basketCore Barrel Soil Sampler
type core retainer.
(Courtesy of Sprague & Henwood,
The coring bit may either be
Inc.)
a carbide insert bit or a
hardened steel saw tooth bit.
The shoe of the inner barrel has a sharp cutting edge.
The cutting edge may be made to lead the bit by 12 mm (0.5 in) to 75 mm
(3 in) through the use of coring bits of different lengths.
The longest lead is used in soft and loose soils because the shoe can
easily penetrate these materials.
The minimum lead is used in hard materials or soils containing gravel.
Used primarily in stiff to hard cohesive soils and in sands, which are not
easily sampled with thin-wall samplers owing to the large jacking force
required for penetration.
The sampler is also suitable for sampling soft clays and silts.
Block sampling
MNMAR07
25
SITE INVESTIGATION
Block sampling has traditionally involved the careful hand excavation of soil
around the sample position, and the trimming of a regular-shaped block. This
block is then sealed with layers of muslin, wax and clingfilm, before being
encased in a rigid container, and cut from the ground. The process is illustrated
in Fig. 6.5. A similar process can be carried out in shafts and large-diameter
auger holes.
Trial pits are normally only dug to shallow depths, and shafts and large-diameter
auger holes tend to be expensive. Therefore block samples have not traditionally
been available for testing from deep deposits of clay. In the past decade,
however, there has been an increasing use of rotary coring methods to obtain
such samples. When carried out carefully, without displacing the soil, rotary
coring is capable of producing very good quality samples. When the blocks are
cut by hand then obviously the pit will be air-filled, but when carried out in a
borehole it will typically be full of drilling mud.
During the sampling process there is stress relief. At one stage or another the
block of soil will normally experience zero total stress. This will lead to a large
reduction in the pore pressures in the block. The soil forming the block will
attempt to suck in water from its surroundings, during sampling, either from the
soil to which it is attached, or from any fluid in the pit or borehole. This will result
in a reduction in the effective stress in the block.
In addition, where block sampling occurs in air, negative pore pressures may
lead to cavitations in any silt or sand layers which are in the sample. Cavitation in
silt and sand layers releases water to be imbibed by the surrounding clay, and
the effect will be a reduction in the average effective stress of the block.
Block sampling is an excellent method of ensuring that the soil remains
unaffected by shear distortions during sampling, but samples obtained in this way
may not (as a result of swelling) have effective stresses that are the same as
those in the ground. Therefore the strength and compressibility of the soil may be
changed. This should be allowed for either by using appropriate reconsolidation
procedures, or by normalizing strength and stiffness, where appropriate, with
effective stress.
MNMAR07
26
SITE INVESTIGATION
MNMAR07
27
SITE INVESTIGATION
MNMAR07
28
SITE INVESTIGATION
MNMAR07
29
SITE INVESTIGATION
4.8
MNMAR07
30
SITE INVESTIGATION
(These tests are from disturbed samples such as split spoon samplers (SPT),
bulk samples, etc.).
2. Chemical & Electro-chemical Tests: BS 1377 Part 3: 1990
Organic matter content,
Mass loss on ignition,
Sulphate content of soil and ground water,
Carbonate content,
Chloride content,
Total dissolved solids,
pH value,
3. Compaction-related (tests from bulk samples) Tests: BS 1377: Part
3.1 Dry density - moisture relationship (2.5 kg/4.5 kg hammer)
- Soil with some coarse gravels
- vibrating method
3.2 Moisture condition value (MCV)
3.3 CBR tests
4. Compressibility, Permeability and Durability Tests: BS 1377: Part 5
4.1 1-D consolidation test
4.2 Swelling and collapse tests
4.3 Permeability by constant head
4.4 Dispersibility
5. Consolidation & Permeability Tests in Hydraulic Cells & with pore pressure
measurements: BS 1377: Part 6
5.1 Consolidation Properties using hydraulic cell
5.2 Permeability in hydraulic consolidation cell
5.3 Isotropic consolidated properties using triaxial cell
5.4 Permeability in a triaxial cell
6. Shear Strength Tests (Total Stress) BS 1377: Part 7
6.1 Lab vane shear
6.2 Direct shear box (small)
6.3 Direct shear box (large)
6.4 Residual strength
6.5 Undrained shear strength (UU)
6.6 Undrained shear strength (multi loading)
7. Shear Strength Tests (Effective Stress) BS 1377: Part 8
7.1 CIU with pore pressure measurement
7.2 CD with pore pressure measurement
MNMAR07
31
SITE INVESTIGATION
MNMAR07
32
SITE INVESTIGATION
4.9
33
SITE INVESTIGATION
MNMAR07
34
SITE INVESTIGATION
MNMAR07
35
SITE INVESTIGATION
gravel deposits nor soft clays. The fact that the test provides both a sample and
a number is useful, yet problematic, as one cannot do two things well at the
same time.
MNMAR07
36
SITE INVESTIGATION
MNMAR07
37
SITE INVESTIGATION
The general expression for all types of vanes including standard rectangular
(Chandler, 1988), both ends tapered (Geonor in Norway), bottom taper only
(Nilcon in Sweden), as well as rhomboidal shaped vanes for any end angles is
given by:
MNMAR07
38
SITE INVESTIGATION
Vane Results
A representative set of shear strength profiles in San Francisco Bay Mud derived
from vane shear tests for the MUNI Metro Station Project are shown in Figure 512a. Peak strengths increase from suv = 20 kPa to 60 kPa with depth. The
derived profile of sensitivity (ratio of peak to remolded strengths) is presented in
Figure 5-12b and indicates 3 < St < 4.
MNMAR07
39
SITE INVESTIGATION
MNMAR07
40
SITE INVESTIGATION
MNMAR07
41
SITE INVESTIGATION
Figure 5-16. Example DMT Sounding in Piedmont residual soils (CL to ML) in
Charlotte, NC.
MNMAR07
42
SITE INVESTIGATION
4.9.5
MNMAR07
43
SITE INVESTIGATION
MNMAR07
44
SITE INVESTIGATION
MNMAR07
45
SITE INVESTIGATION
Figure 5-19. Menard-type Pressure meter Results for Utah DOT Project.
MNMAR07
46
SITE INVESTIGATION
Most electric/electronic cones require a cable that is threaded through the rods to
connect with the power supply and data acquistion system at the surface. An
analog-digital converter and pentium notebook are sufficient for collecting data
at approximate 1-sec intervals.
Depths are monitored using either a potentiometer (wire-spooled LVDT),
depth wheel that the cable passes through, or ultrasonics sensor. Systems can
be powered by voltage using either generator (AC) or battery (DC), or
alternatively run on current. New developments include: (1) the use of audio
signals to transmit digital data up the rods without a cable and (2) memocone
systems where a computer chip in the penetrometer stores the data throughout
the sounding.
MNMAR07
47
SITE INVESTIGATION
MNMAR07
48
SITE INVESTIGATION
Piezocone Results
MNMAR07
49
SITE INVESTIGATION
where:
Need to determine the value of velocity (v) and the thickness of each layer (Zi).
Procedures:
(i)
Times of first arrival; t1, t2, t3 ... at various points and x1, x2, X3, ... from
point of impact,
(ii)
Plot the graph of time (t) vs distance (x).
(iii)
Determine slopes ab, be, cd ... by using slopes 1/v, and determine the
v values.
MNMAR07
50
SITE INVESTIGATION
( vi) note that the value of xc, Ti1 and Ti2 can be estimated from figure 1.21b
MNMAR07
51
SITE INVESTIGATION
MNMAR07
52
SITE INVESTIGATION
MNMAR07
53
SITE INVESTIGATION
L
t
MNMAR07
54
SITE INVESTIGATION
The most common procedure for measuring the electrical resistivity of a soil
profile makes use of four electrodes driven into the ground and spaced equally
along a straight line. The procedure is generally referred to as the Wenner
method (Figure 2.37a). The two outside electrodes are used to send an electrical
current I (usually a dc current with nonpolarizing potential electrodes) into the
ground. The current is typically in the range of 50-100 milliamperes. The voltage
drop, V, is measured between the two inside electrodes. If the soil profile is
homogeneous, its electrical resistivity is
In most cases, the soil profile may consist of various layers with different rest
tivities, and equation above will yield the apparent resistivity. To obtain the actual
resistivity of various layers and their thicknesses, one may use an empirical
method that involves conducting tests at various electrode spacings (i.e., d is
changed). The sum of the apparent resistivities, Sp, is plotted against the
spacing d, as shown in Figure 2.37b. The plot thus obtained has relatively
straight segments, the slopes of which give the resistivity of individual layers. The
thicknesses of various layers can be estimated as shown in Figure 2.37b.
The resistivity survey is particularly useful in locating gravel deposits within a
fine-grained soil.
MNMAR07
55
SITE INVESTIGATION
Figure 2.37 Electrical resistivity survey: (a) Wenner method; (b) empirical method
for determining resistivity and thickness of each layer
MNMAR07
56
SITE INVESTIGATION
4.12
Location:
Site, including project name, town country or state name where
necessary
(ii)
Grid Reference which should always be stated to at least 1 Om
accuracy. Appropriate local co-ordinate systems should be applied
(iii)
Elevation relative to C.O. for the ground level at the borehole site to an
accuracy of 0.05m.
(iv)
Orientation of the borehole given as an angle to the horizontal (-ve
upwards, +ve downwards) and azimuth (0 to 360 clockwise relative
to Grid North).
(i)
c.
Drilling technique:
The following should be stated
(i)
The method of penetration and flush system
(ii)
The make of machine with the model number
(iii)
The type of core barrel and bit
d.
Contract details:
The following should be noted (with the agreement of the client)
(i)
Name of site investigation contractor
(ii)
Name of client or authority
(iii)
Job reference number
(iv)
Name and profession of logger
e.
Miscellaneous:
MNMAR07
57
SITE INVESTIGATION
Drilling progress
Descriptive geology
MNMAR07
58
SITE INVESTIGATION
MNMAR07
59
SITE INVESTIGATION
MNMAR07
60
SITE INVESTIGATION
MNMAR07
61
SITE INVESTIGATION
MNMAR07
62
SITE INVESTIGATION
MNMAR07
63