Documente Academic
Documente Profesional
Documente Cultură
EE37/PWI
ET/1907/0004
MEASURING AND TEST EQUIPMENT CALIBRATION AND CONTROL
PROJECT
WORKING INSTRUCTIONS
Contents:
1.
PURPOSE ............................................................................................................3
2.
SCOPE .................................................................................................................3
3.
4.
5.
This document is the sole property of TGE. It must not be copied or used without written consent of TGE.
01548_EE37_PWI_ET_1907_0004 Rev.1
PAGE 2/3
01548
EE37/PWI
ET/1907/0004
MEASURING AND TEST EQUIPMENT CALIBRATION AND CONTROL
PROJECT
WORKING INSTRUCTIONS
1.
PURPOSE
The purpose of this project working instruction is to define the monitoring and control of
measuring equipment.
2.
SCOPE
This specification covers for 2 x 150.000 m LNG storage tanks (T211 & T221) of
REGANOSA terminal in Mugardos A Coruna SPAIN:
This procedure is applicable to ENTREPOSE Contracting involved with the Project and
their subcontractors.
3.
REFERENCE DOCUMENTS
1. CONSORTIUM Quality Plan 01548/TH02/PPR/ET/0000/0001 last revision
2. EE Quality Plan 01548/EE37/QAP/ET/1900/0001 latest revision
3. ISO 9001: 2000 - Quality Management System: Requirements
4. EE Calibration certificate register 01548/EE37/LST/ET/1900/0005 latest revision.
5. Dimensional examination procedure for tank erection 01548/EE37/PTS/ET/1919/0056
latest revision
6. Solution Film Test procedure by vacuum box 01548/EE37/PPR/ET/1919/0011 latest
revision
7. Ultrasonic examination procedure (applicable for 9%Ni only) 01548/EE37/PPR/ET/1919/0015 latest revision
8. Solution Film Test procedure for reinforcing pad plates of nozzles and manholes 01548/EE37/PPR/ET/1919/0017 latest revision
9. Control of nonconforming product - 01548/EE37/PPR/ET/1900/0044
4.
5.
PAGE 3/3