Sunteți pe pagina 1din 27

MSAN Project Plan

Supervised by: Professor Dr. Hamdy Elwany


Prepared by: Mina Saad
Tony Nabil

Telecom Egypt- MSAN Project Plan

Table of Contents
1

PROJECT CHARTER............................................................................................................. 3

PROJECT DESCRIPTION...................................................................................................... 3
2.1
2.1.1
2.1.2

Customer Surveys...................................................................................................... 3
According to topography............................................................................................. 3
According to customers needs...................................................................................4

2.2
2.2.1
2.2.2
2.2.3
2.2.4
2.2.5

Planning..................................................................................................................... 4
Routes Planning......................................................................................................... 4
Choosing Locations.................................................................................................... 4
Power Supply............................................................................................................. 4
Designing Network..................................................................................................... 4
Calculating Materials Quantities (Work Sheet)..........................................................4

2.3
2.3.1
2.3.2
2.3.3

Procurement............................................................................................................... 5
MSAN Cabinets.......................................................................................................... 5
Cables........................................................................................................................ 5
Equipment and tools................................................................................................... 5

2.4
Technical specifications for the constructions.............................................................5
2.4.1
Technical specifications for the construction and installation of reinforced concrete
manholes of different models...................................................................................................... 5
2.4.2
Excavation, backfilling transport and drop..................................................................6
2.4.3
Technical specifications of trenching for pipes installation..........................................7
2.5
2.5.1
2.5.2
2.5.3

Technical specifications for the installations...............................................................8


Technical specifications for the installation of pipes....................................................8
Technical specifications of cable installation into pipes..............................................9
Technical specifications for the installation of MSAN distribution cabinets...............17

2.6
2.6.1

Technical specification for testing and delivery.........................................................17


Connect the MSAN cabinet with the proper power supply........................................17

PROJECT SCOPE................................................................................................................ 18

DELIVERABLES................................................................................................................... 18

WORK BREAKDOWN STRUCTURE (WBS).......................................................................18

APPENDIX A : PULLING CABLES INTO CONDUITS AND DUCTS...........................................19


Tension Limitation Using Wire Grip.......................................................................................20
APPENDIX B : TESTING AND DELIVERY SHEETS...................................................................23
APPENDIX C : MANHOLE SPECIFICATION..............................................................................24

Page 2

Telecom Egypt- MSAN Project Plan

PROJECT CHARTER

MSAN (Multiple Service Access Networks) is a project that will be held by Telecom Egypt. TE will
provide 160 MSAN Cabinets in Alexandria through 2015, with estimated budget 100 million
Egyptian pounds. It aims at serving 160,000 new customers, offering them a high quality voice
and higher data rates by using fiber cables.

PROJECT DESCRIPTION
MSAN project aims at raising the efficiency of the access network in Egypt, through
replacing the copper cables by fiber optic cables and replacing the traditional switching
systems with NGN (Next Generation Networks) platform. This project creates an easily
scalable access network making it easier to expand the network to provide wired
communication services for uncovered areas and increasing the number of customers
in currently served areas.
The following network diagram illustrates the network topology after adding MSAN units:

NGN
MSAN
Figure 2-1

2.1

Customer Surveys

Customers surveys will be classified into two major points.

2.1.1

According to topography

In this step, our teams will collect information about customers quantity and their topographic
distribution over different geographic zones. This step is necessary for the planning, because it
gathers information about the number of buildings, population capacity, average age and
Page 3

Telecom Egypt- MSAN Project Plan

educational level in every place to be covered in the MSAN project. This will help to optimize the
network and choose the best fitting to implement.

2.1.2

According to customers needs

In this step, our teams will collect data about customers needs to accomplish the highest
customer satisfaction. In this survey, customers are asked if they prefer to have data services or
only voice. They may be asked also, about their preferred buckets and plans. Moreover, they will
have the opportunity to give suggestions for any new services they want to be provided.
The last step is analyzing the data collected to help taking decisions according to standards.

2.2
2.2.1

Planning
Routes Planning

The first step is calibrating existing routes. Then, choosing best routes. After that, new routes
should be allocated. These steps are done through maps to put initial preview to the routes
available while execution in further steps.
Routes should be chosen to be of minimum length and away from other infrastructure (water, gas,
electricity). Also, the route should avoid passing water channels and rail roads as possible.

2.2.2

Choosing Locations

After the confirmation of routes is finished, locations for the MSAN cabinets should be selected
depending on the customer capacity and convenience.

2.2.3

Power Supply

The electric power supply source availability should be checked at the locations chosen in the
previous step, to know how the connection will be done according to the contract with the
Electricity Distribution Company.

2.2.4

Designing Network

This step includes all technical details including the connections redundancy and network
connections, Bandwidth for each cabinet, transmission network necessary upgrades and
preparation. It also includes IPs and dialing numbers allocation.

2.2.5

Calculating Materials Quantities (Work Sheet)

Table 2-1

seri
al
1
2
3
4
5
6
7
8
9
10

Item

uni
t

Fiber Cables
Power Cables (6 mm)
Copper Cables (Jelly Field 0.4 mm)

m
m
m

MSAN Cabinet
Joints
Connectors
Couplers

LS
LS
LS
LS
m
LS
m

Pipes and Sub-Ducts


Secured Manhole with Cover
Digging Permits

Page 4

Quantity
320000
16000
160000
160
800
16000
4800
320000
160
160000

Telecom Egypt- MSAN Project Plan

11 MSAN Cabinet Base


12 Sand

2.3
2.3.1

LS

160

8000

Procurement
MSAN Cabinets

Bid Awarding is done to choose among suppliers, whom provide the best facilities at least prices.

2.3.2

Cables

There are different types of cables needed for the project :Copper cables ( for rising the quality of
the secondary network) , Power Cables ( to provide necessary power supply for the cabinet) and
Fiber Cables ( needed for the main access network).
Cables are bought through Bid Awarding.

2.3.3

Equipment and tools

There are many assessing tools and equipment that are needed for the project and usually there
are bought directly upon needs. This item includes: joints, connectors, couplers, measuring
devices and jointing devices.

2.4
2.4.1

Technical specifications for the constructions


Technical specifications for the construction and installation of reinforced
concrete manholes of different models
2.4.1.1

Background Information

A manhole (alternatively utility hole, cable chamber, maintenance hole, inspection


chamber, access chamber, sewer hole or confined space) is the top opening to an
underground utility vault used to house an access point for making connections or
performing maintenance for buried cables.
Creating and manufacturing different manholes models which are H.H model I and HH
model II (C.H) and M.H models (I.II.III.IV) as well as base of cabinets and models
required by the working conditions.
Manholes with all the models and the base of cabinets must be prefabricated and
cast into a single site is equipped with all the services of lighting and water and
suitable places to garner raw materials in manufacturing and technical specifications.
Pour the manholes are using formwork (chop) either wooden or metal especially for
manholes.

2.4.1.2 Technical specifications of manholes:


Table 2-2

Man Hole type

Length (m)

Width (m)

Height (m)

I
II

3.4
4.8

2.4
2.4

2.65
2.65
Page 5

Total drilling
(cube in m3)
21.624
30.528

Telecom Egypt- MSAN Project Plan

III
IV
HHII
CB
Specially

5.9
6.9
2.9
1
As designed

2.8
3
1.9
1

2.65
2.65
1.65
.7

Refer to Appendix C for technical specifications of CH Type manhole


2.4.1.3

Adapter Plates for conduits in manhole

Figure 2-2

2.4.2

Excavation, backfilling transport and drop


2.4.2.1 Concrete Manhole we Location should be:
- Not at roads intersections.
- The site is chosen to be suitable at the mechanical drop projector.

Figure 2-3

Page 6

43.3778
54.855
9.09
.7

Telecom Egypt- MSAN Project Plan

2.4.3

Technical specifications of trenching for pipes installation


2.4.3.1

The preparation and convening of the formats with neighborhoods and


towns councils and various facilities for obtaining permits
implementation.

2.4.3.2

Deciding routing drilling and boring work for these tracks to make sure
that execution paths of the longitudinal and the implementation drilling
path in case of non-availability of maps from the information center.

2.4.3.3

Excavation and backfilling specification for installation of soil pipes in all


soil types (except rocky soil):

Space between the top layer and streets surface not less than 90 cm, and 70 cm
from the surface of the pavement.

The bottom ditch digging must be horizontal.

Soft sand layer is placed between the two pipes.

Cover the last layer pipes with soft sand and free of any impurities in the thickness
of 20 cm with water spray with manual backfilling .

Complete the backfill above the sand layer to output soft drilling thickness 30 cm
after placing warning signs.

Complete filling up the soil to street level mechanically.

2.4.3.4

Excavation and backfilling specification for the installation of pipes in the


rocky soil :

Space between the top layer and streets surface not less than 90 cm, 80 cm from
the surface of the pavement.

Soft sand layer is put down the pipe thickness not less than 10 cm.

Soft sand layer is placed between two layers pipes

Cover the last layer pipes with soft sand and free from any impurity with thickness
of 50 cm with water spray with manual backfilling then warning signs are placed.

Complete filling up the street level using fine sand.

Page 7

Telecom Egypt- MSAN Project Plan

2.5
2.5.1

Technical specifications for the installations


Technical specifications for the installation of pipes
2.5.1.1

The technician must check all pipes and fittings before installation to
ensure its integrity and absence of defects caused by transport (cracks,
broken parts, unstable rubber gasket).

2.5.1.2

Pipes are installed using a wooden hammer and liquid inorganic soap
diluted in water with ratio 1: 21 for easy installation and making sure that
the rubber gasket is not removed during installation.

2.5.1.3

Access to the pipes on the slots of the manholes and up to 3 cm from the
end of the sandy bang.

2.5.1.4

Use the semi-circle files and saws during installation if needed.

2.5.1.5

Use plastic sheets to cover the ends of pipes during installation to


prevent water leaks and dirt during installation.

2.5.1.6

Install pipe breaks (Spacer) every 1.5 meters to connect piping to each
other and maintain their horizontal orientation.

2.5.1.7

Use 45 degree /110 mm huts for the main pipes, also use 90degree /110
mm huts for the entering the base of the cabinets.

2.5.1.8

The order of pipes into trench excavation under the approved diagrams
(Conduit System Diagram) as shown below.

Figure 2-4

2.5.1.9

The tube cleaning and calibration:


After the completion of the reclamation and site cleanup of the waste product of
drilling is cleaning up all the pipes between the primary and secondary manholes
and cabinets using the brush and compressed air, etc.

The calibration of tubes is done by using cylindrical wooden body (mandrill) and
the length of mandrill of 30 cm and 9 cm for diameter tracks straight and in the
case of curves is used mandrill length 20 cm, 9 cm diameter to insure the safety
fittings pipes and to be suitable for pulling cables.
Page 8

Telecom Egypt- MSAN Project Plan

Must insure that there are no Splits in the pipe fittings.

Extend FLOSS nylon its thickness not less than 4 mm in all installed pipes with
length 10 meters into the manhole and linked to the (Sealing plug).

2.5.2

Technical specifications of cable installation into pipes


2.5.2.1

Make sure the spool number that will be drawn in terms of length,
capacity and contract number printed on it if exists.

2.5.2.2

The number of pipe that we will pull the cable in it.

2.5.2.3

The pull direction in the direction of the arrow indicated on the pulley in
one direction for Exchange.

2.5.2.4

Implementation engineer take the necessary precautions to secure work


area for pedestrians and vehicles.

2.5.2.5

Implementation engineer using a proper connection between the loader


and pulley cable to prevent cable form damage during the pulling
operation if any impediment appears.

2.5.2.6

Cable grease is a special paint for painting cable to be easy dragging it


into the pipe.

2.5.2.7

It is necessary to protect cable as you pull the cable at sharp curves or


places in manholes using metal curves dedicated for this purpose inside
manholes.

2.5.2.8

The tensile strength must be with in the allowed limit.

2.5.2.9

Installation of seals for pipes filled with cables (Sealing Ring).

2.5.2.10 The installation of seals for pipes which are not preoccupied with cables
(Sealing Plug).
2.5.2.11 The installation of seals for manholes slots which are not installed pipes
with the (Sealing Cup).
2.5.2.12 Pulling fiber cables in sub-ducts. Refer to Appendix A

2.5.2.13 SAFETY PRECAUTIONS


2.5.2.13.1

Cable Handling Precautions

Fiber optic cable is sensitive to excessive pulling, bending, and crush forces. Any such
damage may alter the cables characteristics to the extent that the cable section may
have to be replaced. To ensure all specificationsare met, consult the specific cable
specification sheet for the cable you are installing.
2.5.2.13.2

Corning Cable Systems cable specification sheets are available which list the maximum
tensile load for various cable types. The maximum pulling tension for stranded loose
tube cable and ribbon cable is 600 lb(2,700 Newtons).

Page 9

Telecom Egypt- MSAN Project Plan


2.5.2.13.3

Corning Cable Systems cable specification sheets also list the minimum cable bend
radius both Loaded (during installation) and
Installed (after installation). If these sheets are
not available on the job-site, the following
formulas may be used to determine general
guidelines for installing Corning Cable Systems
fiber optic cable:
To arrive at a working bend radius for cable installation,
multiply 15 times (15x) the cable outside diameter.
Example:
Cable Diameter = 0.46 in (11.8 mm)
15 x 0.46 in = 6.9 in (177 mm)
Minimum Working Bend Radius = 6.9 in (17.7 cm)
To find the minimum diameter requirement for pull wheels or
rollers, simply double the minimum working bend radius.

Figure 2-5
2.5.2.13.4

Whenever unreeled cable is placed on the pavement or surface above a manhole,


provide barricades or other means of preventing vehicular or pedestrian traffic through
the area.

2.5.2.13.5

Fiber optic cable which passes through manholes containing petroleum-based waste
will require special protection. Some petroleum products will deteriorate the cables
polyethylene sheath. Consult your company practices regarding manholes and
petroleum-based waste for specific instructions on how to remove the petroleum. Install
inner duct that is impervious to future petroleum exposure.

2.5.2.13.6

At the completion of a days installation, protect bare cable ends by placing a cable cap
on the end of the cable, followed by several wraps of tape around each cap. This will
assist the moisture-resisting material in Corning Cable Systems loose-tube cable in
preventing water ingress due to long-term exposure to moisture.If a cap is not available,
a few wraps of tape placed on the tip of the cable should prevent water from entering the
cable.

2.5.2.14 PLANNING AND PREPARATION


2.5.2.14.1

It is recommended that an outside plant engineer conduct a survey of the cable route.
Manholes and ducts should be inspected to determine the optimum splice point
locations and duct assignments. Identify potential problems with inner duct and cable
placement at this time.

2.5.2.14.2

Rodding or slugging may be required to verify duct


suitability and accurate length. Cable cut length is
especially critical when installing factory-connectorized
cables.

Figure 2-6
2.5.2.14.3

Inspect manholes in which cables will be spliced and make plans for closure and cable
slack racking. Be sure to consider the accessibility of manholes to splicing vehicles.

2.5.2.14.4

Fiber optic cable must be protected in intermediate manholes. Carefully choose racking
space so that it will provide maximum protection for the cable and maintain its minimum
bend radius.
Page 10

Telecom Egypt- MSAN Project Plan


2.5.2.14.5

Based upon the cable route survey and the equipment / manpower resources available,
develop a cable pull plan. Inspect potential reel and winch locations for their suitability
and make plans for installation techniques such as back feeding or use of intermediate
assist winches.

2.5.2.14.6

Factors to consider in developing the pull plan include changes in elevation and the
locations of bends and offsets.

For ease of installation, pull cables from higher elevation manholes to lower ones, whenever
possible.

Bends describe pronounced turns in the routing of a duct system.


Offsets in a duct system are more gradual variations from the ideal, straight path of a duct
section. Offsets can impose greatly increased pulling tension. For example, a three foot offset
in a 10-foot run of duct can add an estimated 120 lb of tension to a pull. To minimize the effect
of bends and offsets, begin such pulls at the end of the inner duct section nearest the difficult
area.

2.5.2.15 INSTALLATION EQUIPMENT AND ACCESSORIES INNER DUCT

2.5.2.15.1

Inner duct is a way to subdivide the duct and to provide for future cable pulls. Three 1.25
inch inside diameter (I.D.) inner ducts can usually be pulled into a 4-inch duct. Proper
size and installation of the inner duct is critical for ease of cable installation.

2.5.2.15.2

Inner duct is available in ribbed, corrugated, and smooth-walled constructions of


polyethylene or PVC material. Corning Cable Systems fiber optic cable is compatible
with all major brands of inner duct. Consult your companys practices for inner duct
specifications.

2.5.2.15.3

Fill ratios are calculated by comparing the area of an inner diameter cross-section of the
inner duct to the outer diameter cross-section area of the fiber optic cable. Larger
diameter inner ducts (which result in smaller fill ratios) will normally reduce pulling
tension.

2.5.2.15.4

Multiple cables may be pulled simultaneously into one inner duct. Pulling a new fiber
optic cable over an existing one is not recommended due to the possibility of
entanglement.

2.5.2.15.5

Should an inner duct become twisted during installation, the twisting (helixing) can
dramatically increase pulling tension during cable installation. Corrugated inner duct
has less memory than other types of inner duct, and may tend to lay flatter in the duct.

2.5.2.15.6

Inner duct often stretches during installation. Allowance must be made for the relaxation
of this stretch by planning for extra slack to be pulled into manholes.

2.5.2.15.7

At points where inner duct will be continuous through a manhole, allow sufficient slack
so that the inner duct may be secured on the manhole racks and maintain the cables
minimum bend radius.

2.5.2.15.8

At points where the inner duct is not continuous through a manhole, some provision
must be made to provide a section to cover the cable in the manhole during and after
placement. This may be accomplished through one of the following methods:
a. Couplers which splice inner duct sections together are available from most inner duct
manufacturers. Do not use couplers which reduce the inside diameter of the inner duct.
b. Split duct may be applied to the cable during racking
c. A section of inner duct which has an inside diameter greater than the outside diameter of the
installed inner duct may be used in a sleeve operation. This section of inner duct must be slid
Page 11

Telecom Egypt- MSAN Project Plan


over the inner duct coming from the entrance duct BEFORE the pull-line is installed. larger
inner duct must be long enough to reach from the entrance duct to the exit duct while passing
around the periphery of the manhole where it will be racked, plus an additional 9 ft (3 m) on
each end which will be inside the duct bank after racking.

2.5.2.15.9

After placement, all inner duct must be capped or plugged to prevent moisture or foreign
matter from entering until the cable installation starts.

2.5.2.15.10 Various types of pull-line have been used successfully with fiber optic cable. Pull-lines
can be of either a round or flat cross section. Selection of a pull-line will depend upon
the length and conditions of the pull. Small diameter pull-line may have a tendency to cut
inner duct when under tension.
2.5.2.15.11 Available pull-line materials include wire rope, polypropylene, and aramid yarn. For pulls
using winches, materials with low elasticity such as wire rope and aramid yarn can
minimize surge induced fluctuation in pull line tension. Consult your companys
standard practices with regards to pull-line materials.
2.5.2.15.12 Some inner duct is available with preinstalled pull tape or line. Otherwise, pull-line can
be installed by rodding or blowing. Lubrication of the pull-line may be necessary for
ease of installation or to prevent the line from cutting the inner duct.
2.5.2.15.13 Corning Cable Systems recommends the use of a factory or field-installed wire mesh
pulling grip and swivel during cable pulls. Pulling grips provide effective coupling of
pulling loads to the jacket, aramid yarn, and central member of fiber optic cables.
2.5.2.15.14 The use of a swivel between the pull-line and pulling grip is required to prevent the pullline from imparting a twist to the cable. A swivel that contains ball-bearings is
recommended to prevent binding at high tensions.
2.5.2.15.15 Cable lubricant is recommended for most fiber optic cable pulls as a means of lowering
pulling tension. Short hand-pulls may not require lubricant. Considerations in choosing
a lubricant are material compatibility, drying time, temperature performance, and
handling characteristics.

2.5.2.15.16 As noted in the cable precautions, cable lubricants must be compatible with the fiber
optic cables outer sheath. Refer to the lubricant manufacturers specifications. Use of
incompatible liquids, such as liquid detergent, for a lubricant can cause long term
sheath damage.
2.5.2.15.17 Lubricant should be applied according to the manufacturers recommendations. Some
lubricant vendors recommend an applicator to coat the cable as it enters the inner duct,
others suggest distributing lubricant throughout the inner duct by pulling a swab
through the inner duct as part of the pull-line placement. Pumps or gravity feed devices
can also be used to inject lubricant into the inner duct.
2.5.2.15.18 Additional lubricant should be added before bends and known severe offsets and
sections with uphill elevation changes.
2.5.2.15.19 Fiber optic cable is subject to damage if the cables specified maximum tensile force is
exceeded. Except for short runs or hand-pulls, tension must be monitored. Refer to
cable specification sheets for maximum tension. Exceeding the specified maximum
tension will void the warranty of the cable product.
2.5.2.15.20 The use of a winch with a calibrated maximum tension is an acceptable procedure. The
control device on such winches can be hydraulic or in the form of a slip clutch. Such
winches should be calibrated frequently.
Page 12

Telecom Egypt- MSAN Project Plan


2.5.2.15.21 The use of a breakaway link (swivel) can be used to ensure that the maximum tension of
the cable is not exceeded. Breakaway links react to tension at the pulling eye and should
be used as a fail-safe rather than a primary means of monitoring tension.
2.5.2.15.22 A dynamometer or in-line tensiometer may also be used to monitor tension in the pullline near the winch. This device must be visible to the winch operator or used to control
the winch. Special winches are available that monitor the tension remotely at the pulling
eye via a wire in the pull-line. Such winches may also provide a record of the tension
during pulls.
2.5.2.15.23 All pulling equipment and hardware which will contact the cable during installation must
maintain the cables minimum bend radius. Such equipment includes sheaves, capstans,
bending shoes, and quadrant blocks designed for use with fiber optic cable.
2.5.2.15.24 Situations that require use of a radius-maintaining device are encountered at feed and
pull manholes, at bends, and where entrance and exit ducts in a manhole are offset.
2.5.2.16

INSTALLATION TECHNIQUES

2.5.2.16.1

Various techniques are available to ease the installation of long lengths of fiber optic
cable. All have been used extensively in the field.

2.5.2.16.2

The length of cable that can be pulled in one operation will vary with duct conditions, the
equipment used, pulling technique selected, and the skill of the craftsmen. Normally, a
short pull [less than 3000 ft (913 m)] with two or fewer 90-degrees bends may be pulled
without an intermediate-assist winch or hand assistance.

2.5.2.16.3

Use of multiple winches requires compatible pulling equipment and careful coordination
of winch speeds. Consult the equipment manufacturers instructions for necessary
details.

2.5.2.16.4

Longer cable pulls, or those involving many bends, may also use center-pull and back
feeding techniques.

2.5.2.16.5

In a center-pull operation, set up the cable reel near the center of the duct run to be
pulled. Pull the cable in one direction to the next designated splice point.

2.5.2.16.6

Unreel the remaining cable in a figure-eight configuration.

2.5.2.16.7

Flip over the figure-eight so that the pulling-eye end of the cable is on top. This can be
easily accomplished by three installers, one at each end of the eight, and one at the
center.

2.5.2.16.8

Pull the exposed end of the cable in the opposite direction to complete the pull. Hand
tending of the cable paying off from the figure-eight is normally required.

2.5.2.16.9

Back feeding may be used to provide a series of shorter, lower-tension pulls in one
direction. When back feeding, pull enough cable out of the manhole to reach the
intended end point of the pull, plus racking and splicing slack. This cable should be
figure-eighted as it emerges from the manhole.

2.5.2.16.10
Flip over the figure-eight so that the pulling-eye end of the cable is on
top. This can be easily accomplished by three installers, one at each end
of the eight, and one at the center.

Page 13

Telecom Egypt- MSAN Project Plan


2.5.2.16.11 After the pulling eye is connected to the next section of the pull-line, feed the cable by
hand back into the manhole and pull it to its next destination. The cable may be pulled
directly from a figure-eight by a winch, provided the capstan or sheave used at the entry
manhole ensures sufficient bend radius. Hand tending of cable paying off from figureeighted is normally required.

2.5.2.17 INSTALLATION PROCEDURE


2.5.2.17.1

This section will provide an overview of an installation operation. As noted earlier, our
companys practices and local conditions may take precedence over these guidelines.

2.5.2.17.2

Prepare the manholes in the duct section where the cable is to be placed:
a. Place barricades
b. Monitor gas
c. Establish ventilation
d. Pump water
e. Inspect ladders, racks, and duct banks

2.5.2.17.3

If not already in place, install the inner duct and pull-line. Tie down exposed inner duct in
manholes to prevent dragging of inner duct during pulling operations. Relocate existing
utilities if necessary.

2.5.2.17.4

Set up winches, monitoring devices, lubrication points, bend radius devices (sheaves,
capstans, bending shoes, etc.), and means of communications along the route
prescribed in the pull plan.

2.5.2.17.5

Locate the cable reels at the appropriate points of the route.

2.5.2.17.6

Remove reel lagging and retrieve the cable data sheets (if present) from each reel for
your companys as-built records.

2.5.2.17.7

Inspect the reels and equipment on which they are mounted for any bolts, nails or other
protrusions that could damage the cable as it is paid off.

2.5.2.17.8

Ensure that the reel trailer or jack stands are stable, and that the reel may turn freely
without binding. The reel must be level to allow proper pay off of cable.

2.5.2.17.9

Align the reel at the feed hole so that the cable can be routed from the top of the reel into
the duct bank in as straight a path as possible.

2.5.2.17.10 If not previously installed, attach the pulling grip to the cable, and attach the grip to a
swivel. The swivel should be securely fastened to the pull-line. See the pull-line
manufacturers recommendations for appropriate knots.
2.5.2.17.11 A warning marker (colored tape or similar material) may be attached to the pull-line
several feet in front of the pulling grip to alert observers at manholes that the cable is
approaching.

2.5.2.17.12 Apply cable lubricant as required.

2.5.2.17.13 Verify that communication lines are functional and crews are in place at feed, pull, and
intermediate manholes.
Page 14

Telecom Egypt- MSAN Project Plan

2.5.2.17.14 Start the pull at a slow speed, passing the pull-line and cable over and around the
capstans, sheaves, and other devices required to maintain the minimum bend radius.
Begin tension monitoring with a calibrated device as soon as tension is applied to the
cable. If necessary, aid the cable feed by turning the reel by hand. Ensure that the cable
is fed only as fast as the pull-line is moving. Back tension on the reel will prevent too
much cable being fed off.
2.5.2.17.15 Once the cable has moved a minimum of 5 ft (1.3 m) into the innerduct, accelerate the
pull smoothly to its intended speed [50-100 ft (15.2-30.4 m) per minute is desirable].

2.5.2.17.16 Continue the pull at a steady rate. If it is necessary to stop the pull at any point, the
winch operator should stop the pull, but NOT release the tension unless instructed to do
so. Pulls can be easily resumed if tension is maintained on the pull-line and cable.
2.5.2.17.17 The cable should be visually observed during the following situations:
a. When it passes through any intermediate manhole in which innerduct continuity is broken.
b. Where use of a radius-maintaining device is required due to a bend or offset of entrance and
exit ducts.
c. At intermediate-assist winches.
2.5.2.17.18 Ensure that the bend radius is maintained, and that the cable is properly routed through
the sheaves, capstans, bending shoes, etc.. Stop the pull if the cable is misrouted, and
correct the problem before resuming. If the inner duct is being pulled along with the
cable, stop the pull and secure the inner duct with temporary cable ties.
2.5.2.17.19 When the cable end reaches a back feed point or splice point manhole, pull the cable out
of the hole using a setup similar to that at the feed hole to maintain bend radius.After
passing around the winch, the cable slack should be figure-eighted in an area where it
will not be subject to damage by personnel or traffic. Follow the procedure in Step 4.9 for
flipping the figure-eight so that the pulling grip end of the cable will be on top before the
pull is resumed.
2.5.2.17.20 At splice points, pull sufficient slack (typically 40 ft [10 m] of slack from the lip of the
manhole) to reach the intended splicing location, plus enough slack to permit closure
preparation and splicing.
2.5.2.17.21 Verify and record the distance markings printed on the cable for as-built documentation.
2.5.2.17.22 Once the cable is pulled into place and appropriate slack is available at splice or
termination points, begin securing all the inner duct to cable racks on the manhole walls.
Begin racking at the center manhole and proceed to the end manholes. Maintain the
cables specific minimum bend radius.
2.5.2.17.23 At points where the inner duct is continuous through the manhole, push the inner duct
and cable to the rack and secure with appropriate cable ties. Maintain the cables
minimum bend radius.
2.5.2.17.24 If the inner duct is not continuous, rack the split duct, or the larger outside diameter
section of inner duct before the pull.
2.5.2.17.25 Store coiled splicing slack in the splicing manholes so that it is not likely to be damaged
during later work in the manhole. If possible, store the slack in an enclosure designed to
store splicing slack and a splice closure. Place an end cap on any bare cable ends to
prevent moisture or dirt intrusion.

Page 15

Telecom Egypt- MSAN Project Plan


2.5.2.17.26 Fiber optic warning signs should be placed on all inner duct containing fiber optic cable.
Warning signs can help prevent damage resulting from the cable being mistaken for
something else.

2.5.3

Technical specifications for Optical Distribution Frames (ODFs) and splices


2.5.3.1

Optical Distribution Frame Fiber Termination Blocks


with MPO Connectors Fiber termination blocks
(FTBs) with MPO connectors provide MPO connect
ability on the rear of the block for easy connection of
MPO fiber cables. The termination portion of the fiber
block utilizes sliding adapter packs to gain easy
access to standard connectors and adapters on the
front of the block and provides a location for
standard patch cord connections. The block is
internally cabled at the factory for easy installation
and occupies one position of the frame. Before
ordering, determine the block orientation needed as
the blocks may be ordered with a left orientation
(mounts on the left side of the frame) or a right
orientation (mounts on the right side of the frame).

Page 16

Figure 2-7

Telecom Egypt- MSAN Project Plan

2.5.4 Technical specifications for the installation of MSAN distribution cabinets


Selection of the location of the cabinet in the first third of the cabinet service area
boundaries.

Figure 2-8

2.5.4.1

Installation locates the cabinet away from any outside influences.

2.5.4.2

Cabinet is installed on a concrete base with 4 screws and connect the ground
wire from ground point cabinet to the ground with a depth of not less than 60
cm and not more than 25 ohms resistance to ground.

2.5.4.3

The cabinet shall be measured horizontally and vertically.

2.5.4.4

The installation is brought and rubber for cable entry and exit openings to
ensure no moisture or rodent inside the cabinet body and maintain the integrity
of the cables.

2.5.4.5

The installation and fixation of the cables in and out on the windows of the
cabinet under the cabinet according to its capacity with the approved planning.

Figure 2-9

Page 17

Telecom Egypt- MSAN Project Plan

2.6

Technical specification for testing and delivery

2.6.1

Connect the MSAN cabinet with the proper power supply.


2.6.1.1

Make the electrical maps each cable separately so that the maps are approved
by competent implementation management.

2.6.1.2

Check the network from MDF to the points of distribution to customers and
ascertain the following:

Arrange the cables and revise the cable labeling.

Assure that the cabinet is fixed well.

Make the proper tests using OTDR device, Migger device and Bico test device.

For Calibration sheets. Refer to Appendix B

Project Scope
The project will include digging paths, adding manholes, laying pipes and sub ducts,
pulling fiber optic cables, importing 160 MSAN units, preparing civil structure for the
cabinets, fixing the MSAN units, connecting MSAN units using copper cables to the
secondary network cabinets, applying necessary upgrades and additions for the existing
transmission equipment.
The project will exclude digging for secondary network, raising the efficiency of existing
distribution points, maintenance of existing copper cables, the upgrading of the NGN main
core switches.
The project will be finished by the end of the year 2015.

Deliverables

Surveys
Procurement
Civil Work
Installation
Commissioning and Testing
Setting in service

Work Breakdown Structure (WBS)

Plotted and attached.

Appendices

Page 18

Telecom Egypt- MSAN Project Plan

Appendix A : Pulling Cables into Conduits and Ducts


Cable Is Pulled Into Conduits And Ducts, Above Or Below Ground, By A Winch Attached To The
Cable By Means Of:
(A) Pulling Eyes
The Pulling Eye Is A Steel Eye Fastened Directly To The Cable End Either By Fitting The Copper
Or Aluminum Conductors Into A Socket Or Lacing The Conductors Around The Log Of The Eye.
(B) Cable Grips
Cables Of Moderate Size And Length Are Pulled Into Conduits And Ducts By Using A Cable Grip.
The Grip Consists Of An Endless Wire Woven To Form A Basket. This Is Slipped Over The End
Of A Cable And By Nature Of Its Design, Increases Its Grip On The Cable As The Tension
Increases.
STRAIGHT DUCT
Tension Needed To Pull Cable
T1 = Lwf (1)
Where T1 = Tension Required To Pull Cable In Pounds
L= Length Of Cable In Feet
W = Weight Of Cable In Pounds Per Foot
F = Coefficient Of Friction
Tension Limitation Using Pulling Eye
Tm = Ansm
Where Tm = Maximum Allowable Pulling Tension Of Each Cable In Pounds
A = Cross-Sectional Area Of Conductor (Kc Mil)
N = Number Of Conductors In Multi-Conductorcable (Assuming Same Size For All Conductors); If
Cables Are Singleconductor N = 1.
Sm = Maximum Allowable Pulling Stress (Lb/MCM)
Tension Limitation Using Cable Grip
Tm = 3.1416 Kmt (D-T)
Where T = Sheath Or Jacket Thickness (In)
D = Sheath Or Jacket Overall Diameter (In)
Km = Maximum Allowable Pulling Stress (Lb/In)

Page 19

Telecom Egypt- MSAN Project Plan

Tension Limitation Using Wire Grip


For Lead-Sheathed Cables:
Tm= 4700 (D-- T)
(3)
Wheretm= Maximum Allowable Pull In Pounds
T =Thickness Of Lead Sheath In Inches
D= Outside Diameter Of Cable In Inches For Non-Loaded Cables:
Maximum Allowable Pull = 1000 Pounds
If Equation (1) Is Less Than Equation (2) Or (3) (Type Of Attachment) ,Then The Length Of Cable
Considered Is Within Safe Working Limits For Pulling Into Ducts. If, However, Equation (1) Is
Greater Than Equation (2) Or (3), Then The Length Of Cable Considered Exceeds The Safe
Working Limits.
CURVED DUCT
In Pulling Cable Around A Bend, An Additional Force Of Friction Is Introducedby The Pressure Of
The Cable Against The Side Of The Duct, Especially If Thelength Of Run Preceding The Bend Is
Large Or The Radius Of The Bend Is Relatively Small.
Tension Needed To Pull Cable
T3= T1 (Efa)
(4)
Where T2 = Pulling Tension At End Of Curved Section In Pounds
T1= Pulling Tension At End Of Straight Run Before Curved
Section (Equation 1) In Pounds' .
E = Naperian Logarithm Base = 2.718
F = Coefficient Of Friction
A = Angle Of Bend In Radians (1 Radian = 57.3 Degrees)
Maximum Tension At Bends
Lead-Sheathed Cables 400 X Radius Of Curvature In Feet, In Pounds
Rubber - And Thermoplastic-Insulated Cables 200 X Radius Of Curvature In Feet, In Pounds

CALCULATION SEQUENCE
Consider A Duct With (A) A Straight Section,
(B) Then A Carved Section,
(C) Followed By A Straight Section.
Pulling Tension At End Of (A)
T1 = Lwf (1)
From (1)
Where L1 = Length Of Straight Section Before Bend.
Table 6-3

Design Coefficient Of Friction


Polyethylene Cable Sheath
Duct Material
No
B Or C
D
Lubricant
Lubricant
Lubricant
Concrete
0.60
0.42
0.25
Fiber
0.47
0.44
0.25
Fiber Cement

0.50

0.50

0.25

Plastic

0.43

0.38

0.18

Page 20

Telecom Egypt- MSAN Project Plan

Calculate The Pulling Tension For Both Directions Of Pulling. The Calculated Tension For Either
Direction Must Not Exceed Either (1) The Cable Strength Or (2) 6500 Pounds (29 Kilo Newton
[KN]).

Page 21

Telecom Egypt- MSAN Project Plan

Figure 6-10

Page 22

Telecom Egypt- MSAN Project Plan


Table 6-4-Cable Pulling Tension Work Sheet

Straight Section
Segment
Location

Curved Section

To + w(F X x H) =T
200 9.9

0.7

200

To/(wXr) = To/ wr

1590
0.7 30 1580 9.9

2300 9.9

0.7 150

T/(wXr) = T/ wr

1590

2
3

,
40

4.0

5.8

9.9

40 2300

3340

Enter Alignment
Chart with these
values

To = Holdback Tension (Lbs)

x = Horizontal Projection of Segment

r =Radius (Ft)

F = Coefficient of Friction

h= Vertical Projection of Segment

To/wr= Back Tension Ratio

T =Tension Force (Lbs)

T/wr= Pulling Tension Ratio


from Alignment Chart

Cable (Lbs/Ft)

2300
3340

Read from
Alignment Chart

w= Weight Per Unit Length of

Total
Tension

=Angle in Degrees

Page 23

Telecom Egypt- MSAN Project Plan

Appendix B : Testing and Delivery Sheets


Table 6-5- Calibration Sheet
from
Serial Number

MH

CH

to
MH

Calibration per meter


CH

No. of Pipes

Subcontractor Supervisor
Signature

Length (m)

Remarks
Total
Length

Telecom Egypt Supervisor


Signature

Page 24

Telecom Egypt- MSAN Project Plan

Appendix C : Manhole Specification

Figure 6-11

Dimension
External 2.9x1.9x2.5 m
Internal 2.5x1.5x2.0 m

General Specifications
I- Normal Portoland Cement
2- Steel RFT.Dekhaila or Equivalent
3- 1 m3 Concrete Consists of 0.8 m3 Gravel + 0.4 m3 Sand + 360Kg Cement
4- External Isolation 2 Faces of hot or Cold Bitomin

Remark
A separate top slab can be used too, using the required quantity of RFT and separate strips.

Page 25

Telecom Egypt- MSAN Project Plan

Figure 6-12- Section A-A

Page 26

Telecom Egypt- MSAN Project Plan

Figure 6-13-Section C-C

Page 27

S-ar putea să vă placă și