Combined Summer Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Project Location: South Coast AQMD


On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006
Off-Road Vehicle Emissions Based on: OFFROAD2007

Summary Report:
CONSTRUCTION EMISSION ESTIMATES
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
2009 TOTALS (lbs/day unmitigated) 8.05 68.22 33.45 0.05 75.18 3.08 78.26 15.72 2.83 18.56
2009 TOTALS (lbs/day mitigated) 8.05 68.22 33.45 0.05 13.48 3.08 16.57 2.84 2.83 5.67

2010 TOTALS (lbs/day unmitigated) 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
2010 TOTALS (lbs/day mitigated) 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18

Construction Unmitigated Detail Report:


CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Unmitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
Time Slice 1/5/2009-2/27/2009 Active Days: 40 6.35 68.22 30.11 0.05 75.18 3.08 78.26 15.72 2.83 18.56
Mass Grading 01/04/2009-02/28/2009 6.35 68.22 30.11 0.05 75.18 3.08 78.26 15.72 2.83 18.56
Mass Grading Dust 0.00 0.00 0.00 0.00 75.00 0.00 75.00 15.66 0.00 15.66
Mass Grading Off Road Diesel 3.18 26.46 12.98 0.00 0.00 1.33 1.33 0.00 1.23 1.23
Mass Grading On Road Diesel 3.13 41.70 16.00 0.05 0.17 1.74 1.92 0.06 1.60 1.66
Mass Grading Worker Trips 0.04 0.07 1.13 0.00 0.01 0.00 0.01 0.00 0.00 0.00

Time Slice 3/2/2009-3/31/2009 Active Days: 22 8.05 40.17 33.45 0.02 0.07 3.08 3.15 0.02 2.83 2.86
Asphalt 03/01/2009-03/31/2009 3.83 21.13 13.69 0.01 0.02 1.73 1.75 0.01 1.59 1.60
Paving Off-Gas 0.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 3.17 18.98 10.39 0.00 0.00 1.64 1.64 0.00 1.51 1.51
Paving On Road Diesel 0.15 2.00 0.77 0.00 0.01 0.08 0.09 0.00 0.08 0.08
Paving Worker Trips 0.08 0.15 2.54 0.00 0.01 0.01 0.02 0.00 0.01 0.01
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
11/10/2008 05:08:30 PM
Urbemis 2007 Version 9.2.4
Combined Summer Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Time Slice 4/1/2009-8/31/2009 Active Days: 109 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 9/1/2009-12/31/2009 Active Days: 88 6.96 19.05 19.90 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 1/1/2010-6/30/2010 Active Days: 129 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building 03/01/2009-06/30/2010 3.96 18.09 18.88 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building Off Road Diesel 3.65 16.55 11.20 0.00 0.00 1.19 1.19 0.00 1.10 1.10
Building Vendor Trips 0.10 1.15 0.88 0.00 0.01 0.05 0.06 0.00 0.04 0.05
Building Worker Trips 0.21 0.40 6.79 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Phase Assumptions
Phase: Mass Grading 1/4/2009 - 2/28/2009 - Default Mass Site Grading/Excavation Description
Total Acres Disturbed: 15
Maximum Daily Acreage Disturbed: 3.75
Fugitive Dust Level of Detail: Default
20 lbs per acre-day
On Road Truck Travel (VMT): 1219.51
Off-Road Equipment:
1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day
1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day
11/10/2008 05:08:30 PM
Urbemis 2007 Version 9.2.4
Combined Summer Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Phase: Paving 3/1/2009 - 3/31/2009 - Default Paving Description


Acres to be Paved: 3.75
Off-Road Equipment:
4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day
1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day
2 Paving Equipment (104 hp) operating at a 0.53 load factor for 6 hours per day
1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Phase: Building Construction 3/1/2009 - 6/30/2010 - Default Building Construction Description


Off-Road Equipment:
1 Cranes (399 hp) operating at a 0.43 load factor for 6 hours per day
2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day
1 Generator Sets (49 hp) operating at a 0.74 load factor for 8 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day
3 Welders (45 hp) operating at a 0.45 load factor for 8 hours per day

Phase: Architectural Coating 9/1/2009 - 6/30/2010 - Default Architectural Coating Description


Rule: Residential Interior Coatings begins 1/1/2005 ends 6/30/2008 specifies a VOC of 100
Rule: Residential Interior Coatings begins 7/1/2008 ends 12/31/2040 specifies a VOC of 50
Rule: Residential Exterior Coatings begins 1/1/2005 ends 6/30/2008 specifies a VOC of 250
Rule: Residential Exterior Coatings begins 7/1/2008 ends 12/31/2040 specifies a VOC of 100
Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Construction Mitigated Detail Report:


CONSTRUCTION EMISSION ESTIMATES Summer Pounds Per Day, Mitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
Time Slice 1/5/2009-2/27/2009 Active Days: 40 6.35 68.22 30.11 0.05 13.48 3.08 16.57 2.84 2.83 5.67
Mass Grading 01/04/2009-02/28/2009 6.35 68.22 30.11 0.05 13.48 3.08 16.57 2.84 2.83 5.67
Mass Grading Dust 0.00 0.00 0.00 0.00 13.31 0.00 13.31 2.78 0.00 2.78
Mass Grading Off Road Diesel 3.18 26.46 12.98 0.00 0.00 1.33 1.33 0.00 1.23 1.23
Mass Grading On Road Diesel 3.13 41.70 16.00 0.05 0.17 1.74 1.92 0.06 1.60 1.66
Mass Grading Worker Trips 0.04 0.07 1.13 0.00 0.01 0.00 0.01 0.00 0.00 0.00
11/10/2008 05:08:30 PM
Urbemis 2007 Version 9.2.4
Combined Summer Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Time Slice 3/2/2009-3/31/2009 Active Days: 22 8.05 40.17 33.45 0.02 0.07 3.08 3.15 0.02 2.83 2.86
Asphalt 03/01/2009-03/31/2009 3.83 21.13 13.69 0.01 0.02 1.73 1.75 0.01 1.59 1.60
Paving Off-Gas 0.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 3.17 18.98 10.39 0.00 0.00 1.64 1.64 0.00 1.51 1.51
Paving On Road Diesel 0.15 2.00 0.77 0.00 0.01 0.08 0.09 0.00 0.08 0.08
Paving Worker Trips 0.08 0.15 2.54 0.00 0.01 0.01 0.02 0.00 0.01 0.01
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 4/1/2009-8/31/2009 Active Days: 109 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 9/1/2009-12/31/2009 Active Days: 88 6.96 19.05 19.90 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 1/1/2010-6/30/2010 Active Days: 129 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building 03/01/2009-06/30/2010 3.96 18.09 18.88 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building Off Road Diesel 3.65 16.55 11.20 0.00 0.00 1.19 1.19 0.00 1.10 1.10
Building Vendor Trips 0.10 1.15 0.88 0.00 0.01 0.05 0.06 0.00 0.04 0.05
Building Worker Trips 0.21 0.40 6.79 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11/10/2008 05:08:30 PM
Urbemis 2007 Version 9.2.4
Combined Summer Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Construction Related Mitigation Measures


The following mitigation measures apply to Phase: Mass Grading 1/4/2009 - 2/28/2009 - Default Mass Site Grading/Excavation Description
For Soil Stablizing Measures, the Water exposed surfaces 3x daily watering mitigation reduces emissions by:
PM10: 61% PM25: 61%
For Soil Stablizing Measures, the Equipment loading/unloading mitigation reduces emissions by:
PM10: 69% PM25: 69%
For Unpaved Roads Measures, the Manage haul road dust 3x daily watering mitigation reduces emissions by:
PM10: 61% PM25: 61%
11/10/2008 05:09:09 PM
Urbemis 2007 Version 9.2.4
Combined Winter Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Project Location: South Coast AQMD


On-Road Vehicle Emissions Based on: Version : Emfac2007 V2.3 Nov 1 2006
Off-Road Vehicle Emissions Based on: OFFROAD2007

Summary Report:
CONSTRUCTION EMISSION ESTIMATES
ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
2009 TOTALS (lbs/day unmitigated) 8.05 68.22 33.45 0.05 75.18 3.08 78.26 15.72 2.83 18.56
2009 TOTALS (lbs/day mitigated) 8.05 68.22 33.45 0.05 13.48 3.08 16.57 2.84 2.83 5.67

2010 TOTALS (lbs/day unmitigated) 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
2010 TOTALS (lbs/day mitigated) 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18

Construction Unmitigated Detail Report:


CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Unmitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
Time Slice 1/5/2009-2/27/2009 Active Days: 40 6.35 68.22 30.11 0.05 75.18 3.08 78.26 15.72 2.83 18.56
Mass Grading 01/04/2009-02/28/2009 6.35 68.22 30.11 0.05 75.18 3.08 78.26 15.72 2.83 18.56
Mass Grading Dust 0.00 0.00 0.00 0.00 75.00 0.00 75.00 15.66 0.00 15.66
Mass Grading Off Road Diesel 3.18 26.46 12.98 0.00 0.00 1.33 1.33 0.00 1.23 1.23
Mass Grading On Road Diesel 3.13 41.70 16.00 0.05 0.17 1.74 1.92 0.06 1.60 1.66
Mass Grading Worker Trips 0.04 0.07 1.13 0.00 0.01 0.00 0.01 0.00 0.00 0.00

Time Slice 3/2/2009-3/31/2009 Active Days: 22 8.05 40.17 33.45 0.02 0.07 3.08 3.15 0.02 2.83 2.86
Asphalt 03/01/2009-03/31/2009 3.83 21.13 13.69 0.01 0.02 1.73 1.75 0.01 1.59 1.60
Paving Off-Gas 0.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 3.17 18.98 10.39 0.00 0.00 1.64 1.64 0.00 1.51 1.51
Paving On Road Diesel 0.15 2.00 0.77 0.00 0.01 0.08 0.09 0.00 0.08 0.08
Paving Worker Trips 0.08 0.15 2.54 0.00 0.01 0.01 0.02 0.00 0.01 0.01
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
11/10/2008 05:09:09 PM
Urbemis 2007 Version 9.2.4
Combined Winter Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Time Slice 4/1/2009-8/31/2009 Active Days: 109 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 9/1/2009-12/31/2009 Active Days: 88 6.96 19.05 19.90 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 1/1/2010-6/30/2010 Active Days: 129 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building 03/01/2009-06/30/2010 3.96 18.09 18.88 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building Off Road Diesel 3.65 16.55 11.20 0.00 0.00 1.19 1.19 0.00 1.10 1.10
Building Vendor Trips 0.10 1.15 0.88 0.00 0.01 0.05 0.06 0.00 0.04 0.05
Building Worker Trips 0.21 0.40 6.79 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Phase Assumptions
Phase: Mass Grading 1/4/2009 - 2/28/2009 - Default Mass Site Grading/Excavation Description
Total Acres Disturbed: 15
Maximum Daily Acreage Disturbed: 3.75
Fugitive Dust Level of Detail: Default
20 lbs per acre-day
On Road Truck Travel (VMT): 1219.51
Off-Road Equipment:
1 Graders (174 hp) operating at a 0.61 load factor for 6 hours per day
1 Rubber Tired Dozers (357 hp) operating at a 0.59 load factor for 6 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day
1 Water Trucks (189 hp) operating at a 0.5 load factor for 8 hours per day
11/10/2008 05:09:09 PM
Urbemis 2007 Version 9.2.4
Combined Winter Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Phase: Paving 3/1/2009 - 3/31/2009 - Default Paving Description


Acres to be Paved: 3.75
Off-Road Equipment:
4 Cement and Mortar Mixers (10 hp) operating at a 0.56 load factor for 6 hours per day
1 Pavers (100 hp) operating at a 0.62 load factor for 7 hours per day
2 Paving Equipment (104 hp) operating at a 0.53 load factor for 6 hours per day
1 Rollers (95 hp) operating at a 0.56 load factor for 7 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 7 hours per day

Phase: Building Construction 3/1/2009 - 6/30/2010 - Default Building Construction Description


Off-Road Equipment:
1 Cranes (399 hp) operating at a 0.43 load factor for 6 hours per day
2 Forklifts (145 hp) operating at a 0.3 load factor for 6 hours per day
1 Generator Sets (49 hp) operating at a 0.74 load factor for 8 hours per day
1 Tractors/Loaders/Backhoes (108 hp) operating at a 0.55 load factor for 8 hours per day
3 Welders (45 hp) operating at a 0.45 load factor for 8 hours per day

Phase: Architectural Coating 9/1/2009 - 6/30/2010 - Default Architectural Coating Description


Rule: Residential Interior Coatings begins 1/1/2005 ends 6/30/2008 specifies a VOC of 100
Rule: Residential Interior Coatings begins 7/1/2008 ends 12/31/2040 specifies a VOC of 50
Rule: Residential Exterior Coatings begins 1/1/2005 ends 6/30/2008 specifies a VOC of 250
Rule: Residential Exterior Coatings begins 7/1/2008 ends 12/31/2040 specifies a VOC of 100
Rule: Nonresidential Interior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250
Rule: Nonresidential Exterior Coatings begins 1/1/2005 ends 12/31/2040 specifies a VOC of 250

Construction Mitigated Detail Report:


CONSTRUCTION EMISSION ESTIMATES Winter Pounds Per Day, Mitigated

ROG NOx CO SO2 PM10 Dust PM10 Exhaust PM10 PM2.5 Dust PM2.5 Exhaust PM2.5
Time Slice 1/5/2009-2/27/2009 Active Days: 40 6.35 68.22 30.11 0.05 13.48 3.08 16.57 2.84 2.83 5.67
Mass Grading 01/04/2009-02/28/2009 6.35 68.22 30.11 0.05 13.48 3.08 16.57 2.84 2.83 5.67
Mass Grading Dust 0.00 0.00 0.00 0.00 13.31 0.00 13.31 2.78 0.00 2.78
Mass Grading Off Road Diesel 3.18 26.46 12.98 0.00 0.00 1.33 1.33 0.00 1.23 1.23
Mass Grading On Road Diesel 3.13 41.70 16.00 0.05 0.17 1.74 1.92 0.06 1.60 1.66
Mass Grading Worker Trips 0.04 0.07 1.13 0.00 0.01 0.00 0.01 0.00 0.00 0.00
11/10/2008 05:09:09 PM
Urbemis 2007 Version 9.2.4
Combined Winter Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Time Slice 3/2/2009-3/31/2009 Active Days: 22 8.05 40.17 33.45 0.02 0.07 3.08 3.15 0.02 2.83 2.86
Asphalt 03/01/2009-03/31/2009 3.83 21.13 13.69 0.01 0.02 1.73 1.75 0.01 1.59 1.60
Paving Off-Gas 0.43 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Paving Off Road Diesel 3.17 18.98 10.39 0.00 0.00 1.64 1.64 0.00 1.51 1.51
Paving On Road Diesel 0.15 2.00 0.77 0.00 0.01 0.08 0.09 0.00 0.08 0.08
Paving Worker Trips 0.08 0.15 2.54 0.00 0.01 0.01 0.02 0.00 0.01 0.01
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 4/1/2009-8/31/2009 Active Days: 109 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03

Time Slice 9/1/2009-12/31/2009 Active Days: 88 6.96 19.05 19.90 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building 03/01/2009-06/30/2010 4.21 19.04 19.76 0.01 0.05 1.35 1.40 0.02 1.24 1.26
Building Off Road Diesel 3.87 17.35 11.50 0.00 0.00 1.28 1.28 0.00 1.17 1.17
Building Vendor Trips 0.11 1.26 0.95 0.00 0.01 0.05 0.06 0.00 0.05 0.05
Building Worker Trips 0.23 0.44 7.30 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.14 0.00 0.00 0.00 0.00 0.00 0.00 0.00

Time Slice 1/1/2010-6/30/2010 Active Days: 129 6.71 18.10 19.01 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building 03/01/2009-06/30/2010 3.96 18.09 18.88 0.01 0.05 1.26 1.31 0.02 1.16 1.18
Building Off Road Diesel 3.65 16.55 11.20 0.00 0.00 1.19 1.19 0.00 1.10 1.10
Building Vendor Trips 0.10 1.15 0.88 0.00 0.01 0.05 0.06 0.00 0.04 0.05
Building Worker Trips 0.21 0.40 6.79 0.01 0.04 0.02 0.06 0.01 0.02 0.03
Coating 09/01/2009-06/30/2010 2.75 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Architectural Coating 2.74 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Coating Worker Trips 0.00 0.01 0.13 0.00 0.00 0.00 0.00 0.00 0.00 0.00
11/10/2008 05:09:09 PM
Urbemis 2007 Version 9.2.4
Combined Winter Emissions Reports (Pounds/Day)
File Name: Z:\Alan Sako\947.02 Andora Ave TTM\Emissions\Urbemis Andora Construction.urb924
Project Name: Androa Avenue Construction Emissions

Construction Related Mitigation Measures


The following mitigation measures apply to Phase: Mass Grading 1/4/2009 - 2/28/2009 - Default Mass Site Grading/Excavation Description
For Soil Stablizing Measures, the Water exposed surfaces 3x daily watering mitigation reduces emissions by:
PM10: 61% PM25: 61%
For Soil Stablizing Measures, the Equipment loading/unloading mitigation reduces emissions by:
PM10: 69% PM25: 69%
For Unpaved Roads Measures, the Manage haul road dust 3x daily watering mitigation reduces emissions by:
PM10: 61% PM25: 61%