Sunteți pe pagina 1din 52

FIRST WESTERN G.C.

PROFILE AND PRE-QUALIFICATIONS


PUMPS & BOOSTER SETS
PRODUCTS, SERVICES & COMPLETE WATER MANAGEMENT SOLUTIONS

Water Management Solutions Suppliers & Contractors


02 6673764 :
02 6673764 21391 116026 .
P.O. Box 116026 Jeddah 21391 Saudi Arabia Tel: 02 6673764 Fax: 02 6673764

FIRST WESTERN G.C.

INTRODUCTION

e are a very well establish supplier and contractor in the western

region. Our work however; is not limited to western region.

e are an authorized dealer and contractor of KSB Pumps Arabia

Ltd. We have a huge client base were KSB Pumps Boosters, Pumps and
control panels has been supplied and
many mechanical and
electrical field installations were executed at their projects.

have

been

working

in

different

fields

starting

from

electromechanical contracting to industrial equipments supply and


installations and industrial mechanical contracting.

e are also a recommended contractor by Atlas Copco for

installation of complete compressed air equipments and network.


Thank you for your interest in First Western G.C and assuring you of our
best-continued services at all times.

First Western staff

FIRST WESTERN G.C.

PRODUCTION DEPARTMENT
PUMPS AND CONTROL

FIRST WESTERN G.C.

INTRODUCTION TO PRODUCTION DEPARTMENT


First Western Staff has a long experience in fluid dynamic and thermal
engineering for more than a decade. Part of our experience is
represented through our collaboration with KSB PUMPS ARABIA.
Our services in that field represent a total engineered solution from
concept until completion.
Original KSB Pumps and control system are sized, designed at our
office premises and fabrication takes place at KSB Arabia Ltd. Factory
in Riyadh 2nd industrial city.
Noting that our projects department has a huge part in the success of
our Pumps Department as most of our pumps are installed by our own
staff.
Follows a sample of projects where our systems has been approved
and installed.

Date: 12 Aug 2009

TO WHOM IT MAY CONCERN

FIRST WESTERN G.C. guarantees that all KSB products submitted and supplied
are original KSB Pumps Arabia products.
Pumps origin

: as per KSB Certificate of Origin attached

Control panels

: Telemechanique & Merlin Gerin

VFDs

: Altivar of Group Schneider

Electric motors

: KSB Motors for Vertical Pumps


Siemens Motors for Horizontal Pumps

Assembly

: KSB Pumps Arabia Ltd - Riyadh

Warranty

: All items supplied by First Western G.C. are guaranteed


against manufacturing defects under normal operating
conditions for 12 months.

Best regards,

FIRST WESTERN G.C.

FIRST WESTERN G.C.

EYE ON PRODUCTION DEPARTMENT PROJECTS.


REFERENCE PROJECTS LIST

the Text Box Tools tab to change the formatting of the pull quote text box.]

FIRST WESTERN G.C.

KSB PUMPS CERTIFICATES & APPROVALS

FIRST WESTERN G.C.

PROJECTS DEPARTMENT
ELECTROMECHANICAL AND PIPING WORKS.

FIRST WESTERN G.C.

SWCC SHOIBA
BARGES INFRASTRUCTURE AND PUMP STATION
Located in on the western coastal city (Shoiba) and within the
restricted zone at Saline Water Conversion Corp- SWCC we have
executed a challenging project Barges Infrastructure.
Our performance was more than professional as we were able to
hand over the pipe net work, valves, pumps and lamination work in a
detailed and closely followed schedule under exhausting pressure
from authorities to deliver this critical project.
Such performance and both engineering and personal awareness
enabled us to gain both the project owner and the authorities trust
which led to assigning us to take the responsibility of doing the same
challenging project in the southern city of Shoqaiq.
A complete barge loaded desalination plant of 30,000 cu.m/day was
connected through sea laid 6 flexible PE 100 tubes of 125 mm size to a
common GRP 700 mm shore anchored header.
The header was connected through 700 mm GRP pipes to SWCC
strategic potable water tank.
Excavation of soil with many under ground utilities and road crossings
as well as above round laid GRP 700 mm pipes.

FIRST WESTERN G.C.

Our scope of work included supply and installation of :


1) Lamination material and fittings of 700 mm GRP pipe.
2) Stain-less Steel 700 mm clamps with anchors.
3) Installation of 700 mm GRP pipes ( both above and under
ground).
4) Supply and installation of CS reducers and fitting (1000 mm, 800
mm, 700 mm).
5) Installation of main 120,000 cu.m tank main gate valve of 800 mm.
with necessary steel structure.
6) Fabrication and installation of steel walk-ways for service and
maintenance access.

Diesel pumping station from diesel tank to diesel operating barge


loaded generator was also fabricated supplied, installed and
commissioned.

FIRST WESTERN G.C.

SWCC SHOQAIQ
BARGES INFRASTRUCTURE AND PUMP STATION
120 KM North of southern city of Gizan lays a coastal city of Shoqaiq
embracing one of SWCC Saline Water Conversion Plants.
As every project has its own unique aspects and governing
environment, we have executed the infra-structure and mechanical
work by using PE 100 pipes instead of GRP as we have previously done
in SWCC-SHoiba.
More than 3,200 LM of 500 mm PE100 pipes were shipped from Jeddah
to SWCC-Shoqaiq.
Complete excavation, bedding, pipe laying, compacting and backfilling were done.
Our Scope of Work included:
1) Supply and installation of 125 mm PE100 flexible hoses from sea
anchored Barge to the shore area.
2) Fabrication and installation of Steel Header located on top of barge.
3) Polyethylene fusion welding of 500 mm PE joints. More than 270 joints
were welded both above and under ground.
4) Casting and laying of pipe concrete supports with steel clamps.

FIRST WESTERN G.C.

5) Fabrication and installation of CS fitting and reducers (1000 mm, 600


mm, 500 mm, 400 mm)
6) Installation of ELECTROMAGNATIC FLOWMETERS. Both 500 mm and 400
mm with supply and installation of shielded cables and conduits for our
mini panels installed near SWCC main Switch Gear Panels.
7) Tank connection points by installation of 2 gate valves of 500 mm in
size after drainage of SWCC main potable water tank.
8) Supply of Electric driven pumps set with control panel and coble
network and piping. Used to pump diesel from land tank to barge
generator tanks.
Our performance here was up to client expectations and satisfaction
as in our previous project at SWCC Shoiba.
Located in on the western coastal city (Shoiba) and within the
restricted zone at Saline Water Conversion Corp- SWCC we have
executed a challenging project Barges Infrastructure.
A complete barge loaded desalination plant of 30,000 cu.m/day was
connected through sea laid 6 flexible PE 100 tubes of 125 mm size to a
common GRP 700 mm shore anchored header.
The header was connected through 700 mm GRP pipes to SWCC
strategic potable water tank.
Excavation of soil with many under ground utilities and road crossings
as well as above round laid GRP 700 mm pipes.

FIRST WESTERN G.C.

Our scope of work included supply and installation of :


1)
2)
3)
4)

Lamination material and fittings of 700 mm GRP pipe.


Stain-less Steel 700 mm clamps with anchors.
Installation of 700 mm GRP pipes ( both above and under ground).
Supply and installation of CS reducers and fitting (1000 mm, 800 mm,
700 mm).
5) Installation of main 120,000 cu.m tank main gate valve of 800 mm.
with necessary steel structure.
6) Fabrication and installation of steel walk-ways for service and
maintenance access.
Diesel pumping station from diesel tank to diesel operating barge
loaded generator was also fabricated supplied, installed and
commissioned.

FIRST WESTERN G.C.

KING ABDUL AZIZ INTERNATIONAL AIRPORT KAIA


HAJJ TERMINAL COMPLEX
FIRE FIGHTING NETWORK BLOCK A & B
As most of our projects, the Hajj Terminal Complex has a critical time
limit of execution.
With main fire lines of 8 and 6 in size and a sprinklers network of
piping reaching up to 5,000 LM this project represents a challenge of
management and effectiveness of man-power utilization.
The project is due to finish in November 2009 and we are on the edge
of handing over more than 80% of the project.
Yet another success for First Western Staff.
Project located at Jeddah KAIA.

FIRST WESTERN G.C.

KING ABDUL AZIZ INTERNATIONAL AIRPORT KAIA


REHABILITATION OF LOAD CENTER
FIRE FIGHTING NETWORK & FM 200

In collaboration with our client (SELA-PASS TRADING) we have


executed the installation of fire fighting network and FM 200 at KAIA.
The project consisted of installation of:
1) Conventional sprinkler lines at 9 LM height
2) Deluge System for 5 main chillers.
3) FM 200 complete supply and installation.
4) Fire alarm network
More projects are being studied and shall be executed with our loyal
client SELA PASS TRADING.

Project located at Jeddah KAIA.

FIRST WESTERN G.C.

REZA INVESTEMENT GROUP


REZA HYGEIN
COMPRESSED AIR SYSTEM AND NETWORK
A new appreciated relation with new client was established through
installation of Altas Copco Compressors, Dryers, Air Reservoir and
control system.
Two 15 KW compressor with connected with filters and air dryer to a GI
pipes network of 160 LM.
Project located at Jeddah industrial city (phase 2).

FIRST WESTERN G.C.

REZA INVESTEMENT GROUP


REZA HYGEIN FACTORY JEDDAH
EXHAUST FANS
Following to handing over the compressor room to our client REZA
HYGIEN, we were rewarded a new contract to supply and install 12
Roof and Wall mounted exhaust fans of 10,000 CFM.
Fans are due to be at Jeddah port by first of November 2009.
Project located at Jeddah industrial city (phase 2).

FIRST WESTERN G.C.

RABYA GARDEN CENTER


50 MUNICIPAL GARDENS PROJECT

A unique relation binds us with RABYA GARDEN CENTER, a loyal client


that awarded us the 50 Gardens Project.
Our Scope of Work at each garden consists of :
1) Supply and installation of Simplex Vertical inline multi stage pumps
with SS 304 construction.
2) Supply and installation of disc filter 2
3) Supply and installation of Fertilizer tank 200 Liters
4) Supply and installation of Chemical Fertilizer Injector
5) Supply of 200 Liter pressure vessel
6) Supply of Auto/Manual control panel.
Project located at different locations in Jeddah City.

CASTING OF CONCRETE SUPPORTS OFR 700MM GRP PIPES


SWCC SHOIBA

GRP PIPING WITH STEEL STRUCTURAL SUPPORTS SWCC SHOIBA 2008

EXCAVATION WORKS AND PIPING WORKS OF 700 MM GRP POTABLE WATER LINES SWCC SHOIBA - 2008

INSTALLATION OF 800X700 CS REDUCER AT SWCC


SHOIBA MAIN POTABLE WATER STORAGE TANKS 2008

GRP 700MM PIPING (LAMINATION TYPE) WITH SS316 CLAMPS AND CONCRETE SUPPORTS
POTABLE WATER LINES (SWCC SHOIBA) - 2008
00

INSTALLATION OF COMPRESSED AIR SYSTEM


ATLAS COPCO COMPRESSORS, DRYERS, FILTERS AND AOR RECEIVER TANK
NATIONAL AUTOMATION INDUSTRIES (JUFFALI TRUCKS) 2007

PVC PIPING & SUPPORTS AT SWCC


SHOQAIQ 2009

PE 500 PIPES AT SWCC SHOQIAQ 2009


PE WELDING OF 500MM JOINTS

EXCAVATION, PIPE LAYING, WELDING, BACKFILLING AND TESTING


PE 500 MM
SWCC SHOQAIQ 2008/2009

INSTALLATION OF COMRESSED AIR SYSTEM UNITS AT BANAWAI PACKAGING FACOTRY JEDDAH 2010

INSTALLATION OF DEISEL PUMPING STATION WITH DIESEL UNDERGROUND PIPES

INSTALLATION OF SIEMENS 500MM DIA ELECTROMAGNETIC FLOWMETERS

INSTALLATION OF 125MM PE PIPES NETWORK FROM SWCC AREA TO FLOATING BARGE AT YANBU 2010

S-ar putea să vă placă și