Documente Academic
Documente Profesional
Documente Cultură
)
2015 Taylor & Francis Group, London, ISBN: 978-1-138-02848-7
ABSTRACT: Offshore steel jackets are commonly supported by large diameter open ended steel piles. The
piles are installed by driving with hydraulic hammers to final penetration depth. The last sequence in the pile
driving is often performed with an additional insert piece (follower) between the pile and the hammer. This
is to avoid interference between hammer and jacket structural parts as pile sleeves, jacket legs and outfitting.
Installation of the follower requires a pause in the pile driving and this period usually lasts from one to twenty
hours. An increase in the driving resistance is often experienced after the stop in the driving process and this
is referred to as set-up of the soil. The rate and magnitude of set-up is a function of several factors and the
interrelationship is not well understood. Pile driving records from recent jacket installations in the North Sea
have been investigated for the purpose of establishing the rate and magnitude of set-up effect due to interruption
of pile driving. The projects included pile diameters from 1.829 m2.743 m, and sites with both sand and clay. The
focus is to back calculate the subsequent increase in blow counts in pile driving after interruption of pile driving
using a simple equation. The result of the study shows that set-up in the pile-soil interface can be significant
in pile driving. The proposed relatively simple equation with few calibrated parameters can be used to make a
preliminary assessment quickly about the increase in number of hammer blows due to interruption in pile driving
and change in hammer energy.
INTRODUCTION
It has been recognized that the load carrying capacity of driven piles increases with time in most soils,
including clay, loose to dense silt, sandy silt, silty sand,
and fine sand. An increase in pile capacity with time
is commonly known as soil set-up. Terms such as pile
set-up and freeze have been also used in the literature. The rate and magnitude of soil set-up is a function
of several parameters.
A number of investigators (Miller et al. 1978,
Randolph et al. 1979, Randolph 2003) have proposed
analytical models of pore pressure generation and
the subsequent dissipation process for piles in normally consolidated to lightly overconsolidated clays.
The effect of soil set-up is also addressed in international standards (ISO 19902/2007) and recommended
575
practice (API RP 2GEO/2011). Since excess pore pressures are generated by pile driving operations, any
dissipation of the excess pore pressures after installation should correspond to an equivalent increase
in the shear strength of the surrounding soil mass
and hence an increase in the capacity of the pile.
After dissipation of excess pore pressures, the capacity of a pile approaches long-term capacity, although
some strength gain may continue due to secondary
processes.
Komurka et al. (2003) divided the soil set-up mechanisms into three phases as shown in Figure 1. Stage
1: logarithmically nonlinear rate of excess pore water
pressure dissipation; Stage 2: logarithmically linear
rate of excess pore water pressure dissipation; and
Stage 3: independent of effective stress, additional setup may occur even at constant effective stress due to
ageing. Qinitial is the axial capacity of pile at end of
pile driving and Qfinal is the axial capacity of pile at
time t after driving.
During Stage 1 the rate of dissipation of excess
porewater pressures is not linear with respect to the
logarithm of time for some period after driving. This
is because of the highly disturbed state of soil. This
first stage of soil set-up has been demonstrated to
account for capacity increase in a matter of minutes
after pile installation or interruption of pile driving.
The duration of the logarithmically nonlinear rate of
excess porewater pressure dissipation is a function of
soil (type, permeability and sensitivity), and pile properties (type and size). The less permeable the soil, and
the greater volume of soil displaced by the pile, the
longer is the duration of the logarithmically nonlinear
rate of dissipation. In clean sands, the logarithmic rate
of dissipation may become linear almost immediately
after driving. In cohesive soils, the logarithmic rate
of dissipation may remain nonlinear for several days
(Komurka et al. 2003).
increased soil resistance that may occur due to soil setup. Effort should be made to minimize the interruption
of pile installation for different reasons such as insertion of follower or breakdown of hammer. Although
there are many advantages to be gained by considering long term soil set-up in pile design, short term soil
set-up is however a challenge during interrupted pile
driving process. Figure 2 shows a typical pile drivability chart with increased blow count due to interruption
of pile installation. The definition of pile refusal is
primarily to define the point where driving with a particular hammer should be stopped. Depending on the
duration of interruption and the type of soil condition
additional blows may be required not only to break
the pile loose but also for some subsequent penetration depths as shown in Figure 2. During continuous
driving of piles there is a reduction of axial resistance
of pile due to friction fatigue. During interruption of
pile driving there is a gain of axial resistance of pile
due to soil set-up. Figure 3(a) shows the reduction of
soil resistance during continuous driving. The gradual
decrease of skin friction along the pile shaft as the pile
is driven further is attributed to friction fatigue. Figure 3(b) shows the restoration (soil set-up) with time
due to interruption of pile driving. Rapid soil set-up
effects due to interruption of pile driving may lead to
premature refusal of pile.
4
3
576
Table 1.
Number of
Hammer
Location hammer blows energy before Interruption
Platform
before and after and after (kJ) time (min)
11
12
13
21
22
23
31
41
51
61
62
71
1922
1415
1515
3949
5252
3330
1246
1830
2228
1929
2525
2732
14671451
14521452
16581680
13991363
23382271
24862219
14961420
25082508
16731673
17831983
23502515
18751906
54
69
56
883
1316
1269
1479
387
60
2308
166
68
excess porewater pressure dissipation becomes uniform (linear with respect to the log of time), as shown
in Figure 1, end of stage 1. It should be noted that to is
a function of soil type, and pile size accordingly different researchers recommend slightly different to values.
Camp & Parmar (1999) empirically determined to
equal to 2 days, but stated that to equal to 1 day seems
to be reasonable. Using pre-stressed concrete piles
installed in non-cohesive soils, Axelsson (1998) set to
equal to 1 day. Long et al. (1999) recommends using
to equal to 0.01 day. Svinkin et al. (1994) used to equal
to 1 to 2 days. Bullock (1999), and McVay (1999),
recommend standardizing to equal to 1 day (Komurka
et al. 2003).
The A parameter is a function of soil type, pile
material, type, size, and capacity but is independent
of depth, and porewater pressure dissipation. A values ranging from 0.2 to 0.8 are suggested in the
literature. For sand values of to = 0.5, A = 0.2, and
for clay to = 1.0, A = 0.6, are generally recommended
(Komurka et al. 2003, Budge 2009).
5
CASE STUDIES
577
Locations 1, 3, 5 and 6 are sites where the soil profile is dominated by clay, and the pile tip at break
in driving is founded in clay. For location 2 the soil
mainly consists of extremely hard clay, and the pile tip
is founded in either that soil or in dense sand. The soil
profile at location 4 is approximately 50 % sand and
50 % clay. Location 7 is mainly dense to very dense
sand.
Slightly different procedures are followed by different offshore installation contractors during insertion of
follower and resuming of pile driving. There are two
main procedures for including a follower in the pile
driving. The first approach is to drive each pile to target penetration before a new pile is driven. This implies
that each pile is driven to an intermediate depth and
the follower is stabbed immediately after, and the pile
driving is commenced. With this approach the break
in driving will be short. The other approach is to drive
some or all of the piles to an intermediate depth before
the follower is introduced. This approach leads to a
longer break in the driving.
The pile driving records from installation of piles
at Location 3 is presented as an example. The target
penetration of the piles was 47 m below the seabed for
all 12 piles. The outer diameter of the piles is 2.438 m.
Intermediate pile driving depth was 31 m below the
seabed, and a follower was installed after this depth
was reached. Pause in pile driving due to installation
of follower varied from 680 to 2638 minutes with an
average of 1479 minutes. The number of blows per
0.25 m is shown in Figure 4 below for a representative
pile installation, along with the hammer output energy
used.A slight decrease of the energy can be seen for the
blows immediately following the break which is a startup energy following the break. An increase in energy
can then be seen at 31.5 m. The influenced depth of
the break in extra number of hammer blows can be
seen from 31 m and is assumed to be down to 35 m.
The number of blows before and after the break was in
average 12 and 46 respectively. For the piles at this site
the appropriate value of the parameter a in Equation
2 below is 1.6. The soil at this site generally consists
of firm to very hard clay with few intermediate layers
of medium dense to dense sand. The plasticity of the
clay is between 12 and 20.
Another installation from which the records are presented herein is the jackets at Location 1. The soil
conditions at the Location 1 site generally consist of
layers of stiff to hard sandy clay and medium dense
to very dense sand. The pile tip is founded in sandy
clay. Three jacket structures are installed at this location, each with 12 piles with a diameter of 2.438 m
driven partly with follower. Each pile was driven to
intermediate depth and then the follower was installed
and the piles were driven to target penetration. Thus the
interruptions in the pile driving lasted a short period of
time. The minimum interruption was 30 minutes while
the maximum interruption was 200 minutes. The intermediate driving depth varied from 37 to 59 m for the
different jacket piles. Target penetration depth varied
from 47 to 69 m. No significant soil set-up can be seen
Figure 4. Representative pile driving records from installation of piles at location 3 platform 1.
578
Table 2.
Soil type
Clay
Sand
0.31.6
0.30.6
0.20.5
0.10.3
Based on the case studies from 12 jacket installations at 7 locations in the North Sea, the authors
recommend the following empirical relation shown in
Equation 2 to estimate the number of hammer blows
after interruption of pile driving.
In the relation the hammer energy used before
and after the interruption of driving is included. The
parameters a and b are dependent on soil types and
thicknesses of the soil layer to which the pile is in contact with before interruption of pile driving. Parameter
b is directly related to the change in hammer energy
before and after interruption of pile driving, and is less
dependent to soil type. The ranges of parameters value
shown in Table 2 are proposed values for different soil
types.
Figure 5. Representative pile driving records from installation of piles at location 1 platform 2.
579
CONCLUSION
Bullock, P.J. 1999. Pile Friction Freeze: A Field and Laboratory Study, Volume 1, Ph.D. Dissertation, University of
Florida.
Budge, A.S. 2009. Study of Pile Setup Evaluation Methods,
Minnesota Department of Transportation. C-90707
Camp, W.M. & Parmar, H.S. 1999. Characterization of Pile
Capacity with Time in Cooper Marl: Study of Applicability of a Past Approach to Predict Long-Term Pile
Capacity, Transportation Research Record 1663, Paper
No. 991381, pp. 1624.
Jahr, A., Tefera, T., Hland, G. & Hennum, G. 2014.
Design and installation of Gudrun platform jacket piles,
International conference on piling & deep foundations,
Stockholm Sweden.
Karlsrud, K., Jensen, T.G., Lied, E.K.W., Nowacki, F. &
Simonsen, A.S. 2014. Significant ageing effects for axially loaded piles in sand and clay verified by new field
load tests, OffshoreTechnology Conference Houston, OTC
25197, Texas, USA, 58 May 2014.
Komurka, V.E. 2004. Incorporating Set-Up and Support Cost
Distributions into Driven Pile Design, Current Practices
and Future Trends in Deep Foundations, ASCE/GeoInstitute, Geotechnical Special Publication No. 125, pp.
1649.
Komurka, V.E., Wagner, A.B. & Edil, T.B. 2003. Estimating
Soil/Pile Set-Up, Wisconsin highway research program
#0092-00-14.
Long, J.H., Kerrigan, J.A. & Wysockey, M.H. 1999. Measured
Time Effects for Axial Capacity of Driven Piling, Transportation Research Record 1663, Paper No. 991183,
pp. 815.
Miller, T.W., Murff, J.D. & Kraft, L.M. 1978. Critical State
Soil Mechanics Model of Soil Consolidation Stresses
Around a Driven Pile. Proc. 10th Annual Offshore Technology Conf., OTC 3307, Houston, Texas.
McVay, M.C., Schmertmann, J., Townsend, F. & Bullock,
P. 1999. Pile Friction Freeze: A Field and Laboratory
Study, Florida Department of Transportation, Volume 1,
pp. 192195.
Randolph, M. F., Carter, J.P. et al. 1979. Driven pile in clay
the effects of installation and subsequent consolidation.
Geotechnique 29(4): 361393.
Randolph, M.F. 2003. 43rd Rankine Lecture: Science and
empiricism in pile foundation design. Geotechnique
53(10): 847875.
Svinkin, M.R., Morgano, C.M. & Morvant, M. 1994. Pile
Capacity as a Function of Time in Clayey and Sandy
Soils, Deep Foundations Institute Fifth International Conference and Exhibition on Piling and Deep Foundation.
580