expense In our Autumn edition of Construct, my article Malmaison is back: clarity on concurrent delay on claims' reviewed how the English Courts assess delay in extension of time claims in light of the decision of the Technology and Construction Court in Walter Lilly -v- Giles Patrick MacKay [2012]. In this article, I review how the case clarified an important aspect concerning the mechanics of clause 26 (loss and expense) of the JCT 1998 (Private without Quantities in this case). The claimant, Walter Lilly, claimed just over 1.4m in respect of prolongation costs from the defendant, Mr Mackay. Clause 26 gave Walter Lilly a right to claim loss and expense in the following terms: 26.1 If the Contractor makes written application to the Architect that he has incurred or is likely to incur direct loss and/or expense for which he would not be reimbursed by a payment under any other provision in this Contractbecause the regular progress of the Works or of any part thereof has been or is likely to be materially affected and if and as soon as the Architect is of the opinion thatthe regular progress of the Works or of any part thereof has been or is likely to be so materially affected as set out in the application of the Contractor then the Architect from time to time thereafter shall ascertain, or shall instruct the Quantity Surveyor to ascertain, the amount of such loss and/or expense which has been or is being incurred by the Contractor; provided always that: 26.1.2 the Contractor shall in support of his application submit to the Architect such information as should reasonably enable the Architect to form an opinion as aforesaid; and 26.1.3 the Contractor shall submit to the Architect or to the Quantity Surveyor such details of such loss and/or expense as are reasonably necessary for such ascertainment as aforesaid.
October 2012
Judge Akenhead continued a theme which develops
throughout the 660 paragraph long judgment, namely that the contractor should not be punished for operating provisions of the contract which entitle him to relief, extensions of time or additional cost (Loss and Expense). At paragraph 463 he says: ...in considering Clause 26, one must bear in mind that most of the matters which entitle the Contractor to such loss and expense are the fault or at least the risk of the Employer, such as variations or the late provision of information or instructions by the Architect. One therefore needs to consider with some care precisely what the words mean, without construing them against the Contractor as such. The debate in this case centred on the extent of the documentation and information to be provided by the Contractor to the Architect in support of its loss and expense claim (Clause 26.1.2 and 26.1.3). Somewhat predictably, the defendant (Employer) argued that the Contractor should provide everything to effectively prove its case at the preliminary notification of the loss and expense stage. However, Judge Akenhead did not share this view: This is almost akin to saying that the Contractor must produce all conceivable material evidence such as is necessary to prove its claim beyond reasonable doubt. In my judgment, it is necessary to construe the words in a sensible and commercial way that would resonate with commercial parties in the real world. Judge Akenhead made it clear that clause 26.1.3 only requires the Contractor to submit details which are reasonably necessary for the ascertainment of loss and expense. In practice, what this detail means is that this could comprise the following:
an offer to the Architect or Quantity Surveyor
for them to inspect records at the Contractor's offices could be construed as submission of details of loss and expense
www.gateleyuk.com
a common sense approach to loss and expense
Details of the loss and expensedoes not
necessarily include all the backup accounting information which might support such detail.
Key to his consideration was the fact that:
The Architect already had a very substantial
amount of information at his fingertipsthe Architect and the Quantity Surveyor are not strangers to the project...;
It would be wrong that if, because some details
were not provided to support the loss and expense claim, the entire claim should fail: one would have the absurd position where 10 out of a 1 million claim is not adequately detailed but the rest of the claim is, the whole claim would satisfy the condition precedent [of 26.1.3];
The Contractor in this case had already produced
a fair amount of detailed information which demonstrated a prima facie case to support the loss and expense claim; and
There is a more definitive second bite of the
cherry. If there are elements of the loss and expense claim which were unsupportable at notification stage, this would be settled by adjudication or litigation/arbitration in the usual way on the balance of probabilities.
This clarification in terms of the practical ways of
evidencing and submitting loss and expense claims will provide a good degree of comfort to contractors. It is said that the JCT suite of contracts evenly balances the rights and remedies of the contractor and the employer. The Judge in this case amplified that by saying that in construing the provisions of clause 26 and in particular, Clause 26.1.3, there was no need to construe the provisions in a peculiarly strict way or in a way which is in some way penal against the contractor
It is clear from the judgment that Judge Akenhead was
influenced by the fact that Walter Lilly had provided a considerable amount of information to Mr MacKay in support of its loss and expense claim. However, in different circumstances, this judgment may have inadvertently created a justification for contractors to relieve themselves of properly substantiating loss and expense claims. All contractors need to do now is invite a client to inspect documents at its offices to support loss and expense claims, without having ordered them in any particular way. As such, the effect of this judgment may be to shift the onus from contractor to the employer to work out the detail of the claims. This presents a problem not only for the client who has to expend the time and cost undertaking that exercise themselves (where the claim should have been presented to them), but, no doubt, it will also fall upon the clients agent (architect, QS or PM) to do that task. That may lead to further scope and fee disputes between employers and their consultants. Judge Akenhead may have taken a pragmatic and common sense approach to his analysis of loss and expense claims. His judgment means that the bar has now been set for contractors and employers to do the same. But at whose cost now? Time will tell. For further information, please contact: Emlyn Hudson, Partner +44 (0) 161 836 7883 email EHudson@gateleyuk.com