Documente Academic
Documente Profesional
Documente Cultură
Peter L. King
Lean Dynamics, LLC
January 2010
AGENDA
Data boxes
Information flow
The Timeline
Mapping considerations ~ good VSM practices
Benefits of VSMs
Summary
AGGREGATED
DEMAND
(MONTHLY)
MASTER PRODUCTION
SCHEDULE (MONTHLY)
Order Lead
Time
1 week
# SKUs
1.8 Cars/Day
Lot Size
140K lbs
Transp time
7 Days
Invtry
1 Week
# SKUs
Frequency
1 Car/Day
Lot Size
140K lbs
Transp time
7 Days
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
SHEET
FORMING
6
(4)
SUPPLIER 2
ORDERS
PRODUCTION
SUPERVISOR
Order Lead
Time
CUSTOMER
SERVICE
REPS
CAPACITY FORECAST
(MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
Frequency
CUSTOMER FORECASTS
(QUARTERLY)
RAW MATERIAL
ORDERS (MONTHLY)
SUPPLIER 1
DEMAND
MANAGEMENT
PROCESS
6.3M lbs
Days
16
#
SKUs
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
CALENDARING
BONDING
(4)
6
Invtry
MATERIAL
RELEASES
SLITTING
(3)
2500 R
Days
12.6
#
SKUs
50
Effective
Capacity
8.9
TAKT
8.3
(Master Rolls/Hr)
Invtry
3650 R
Days
21
#
SKUs
200
Invtry
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
4000
Days
#
SKUs
1000
Effective
Capacity
TAKT
Invtry
29
Effective
Capacity
200
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
93%
Lead time
15 Min
Utilization
83%
Utilization
Lead time
17 Min
Yield
87%
Lead time
10 Min
Lead time
10 Min
Lead time
8 Min
Yield
87%
Reliability
Yield
98%
Yield
100%
Yield
100%
Reliability
95%
Reliability
98%
Reliability
90%
Reliability
98%
UPtime
73.6%
UPtime
61%
50
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
Batch size
1 roll
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
EPEI
9 days
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
C/O time
1 hr
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
2 Rolls
C/O loss
~0
Avail time
168 hr/wk
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
12.6 Days
3 M
7 Days
21 Days
17 Min
10 Min
10 Min
320K Sq Ft/Hr
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
322M sq Ft
Days
42
# SKUs
2,000
98%
Shift schd
15 Min
230M Sq Ft/Mo
TAKT
60%
# SKUs
16 Days
Quantity/time
KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000
42 Days
8 Min
MASTER PRODUCTION
SCHEDULE (MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
Order Lead
Time
1 week
# SKUs
Frequency
1.8 Cars/Day
Lot Size
140K lbs
CUSTOMER FORECASTS
(QUARTERLY)
CUSTOMER
SERVICE
REPS
CAPACITY FORECAST
(MONTHLY)
ORDERS
PRODUCTION
SUPERVISOR
RAW MATERIAL
ORDERS (MONTHLY)
SUPPLIER 1
DEMAND
MANAGEMENT
PROCESS
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
Transp time
DAILY PRODUCTION
SCHEDULE (WEEKLY)
7 Days
SHEET
FORMING
6
(4)
SUPPLIER 2
Order Lead
Time
1 Week
# SKUs
Frequency
Lot Size
Transp time
MATERIAL
RELEASES
CALENDARING
BONDING
(4)
6
SLITTING
(3)
5
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
6.3M lbs
Days
16
#
SKUs
Effective
Capacity
11.8
140K lbs
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
7 Days
Lead time
15 Min
1 Car/Day
Invtry
2500 R
Days
12.6
#
SKUs
50
Effective
Capacity
8.9
TAKT
8.3
(Master Rolls/Hr)
Utilization
93%
Lead time
17 Min
Invtry
3650 R
Days
21
#
SKUs
200
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Invtry
4000
Days
#
SKUs
1000
Invtry
Effective
Capacity
29
Effective
Capacity
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
83%
Utilization
60%
Lead time
10 Min
Lead time
8 Min
Yield
87%
Yield
87%
Reliability
90%
Yield
98%
Yield
100%
Yield
100%
Reliability
98%
UPtime
73.6%
Reliability
95%
Reliability
98%
Reliability
98%
UPtime
61%
UPtime
69%
UPtime
98%
UPtime
98%
1000
# SKUs
1800
# SKUs
2000
# SKUs
50
# SKUs
200
Batch size
1 roll
# SKUs
Batch size
1 roll
EPEI
9 days
Batch size
1 roll
EPEI
13 days
C/O time
1 hr
EPEI
7 days
C/O time
45 Min
C/O loss
2 Rolls
C/O time
C/O loss
~0
C/O loss
7 days
5 Min
7 days
C/O time
~0
C/O loss
C/O time
C/O loss
Shift schd
Shift schd
Shift schd
Shift schd
Shift schd
3x8x7
16 Days
3x8x7
12.6 Days
15 Min
3x8x7
10 Min
10 Min
320K Sq Ft/Hr
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
42
# SKUs
2,000
KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000
3x8x7
3 M
7 Days
21 Days
17 Min
3x8x7
230M Sq Ft/Mo
TAKT
322M sq Ft
Days
Quantity/time
42 Days
8 Min
A COMPLETE VSM
SALES &
OPERATIONS
PLANNING
MASTER PRODUCTION
SCHEDULE (MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
Order Lead
Time
1 week
# SKUs
Frequency
1.8 Cars/Day
Lot Size
140K lbs
Transp time
7 Days
1 Week
# SKUs
Frequency
1 Car/Day
Lot Size
140K lbs
Transp time
7 Days
ORDERS
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
SHEET
FORMING
6
(4)
SUPPLIER 2
CUSTOMER
SERVICE
REPS
PRODUCTION
SUPERVISOR
Order Lead
Time
CUSTOMER FORECASTS
(QUARTERLY)
CAPACITY FORECAST
(MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
SUPPLIER 1
DEMAND
MANAGEMENT
PROCESS
Invtry
6.3M lbs
Days
16
#
SKUs
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
CALENDARING
BONDING
(4)
6
Invtry
2500 R
Days
12.6
#
SKUs
50
Effective
Capacity
8.9
TAKT
8.3
(Master Rolls/Hr)
MATERIAL
RELEASES
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Invtry
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
4000
Days
#
SKUs
1000
Invtry
Effective
Capacity
29
Effective
Capacity
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
93%
Lead time
15 Min
Utilization
83%
Utilization
Lead time
17 Min
Yield
87%
Lead time
10 Min
Lead time
10 Min
Lead time
8 Min
Yield
87%
Reliability
Yield
98%
Yield
100%
Yield
100%
Reliability
95%
Reliability
98%
Reliability
90%
Reliability
98%
UPtime
73.6%
UPtime
61%
50
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
Batch size
1 roll
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
EPEI
9 days
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
C/O time
1 hr
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
2 Rolls
C/O loss
~0
Avail time
168 hr/wk
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
12.6 Days
3 M
7 Days
21 Days
17 Min
10 Min
10 Min
320K Sq Ft/Hr
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
322M sq Ft
Days
42
# SKUs
2,000
98%
Shift schd
15 Min
230M Sq Ft/Mo
TAKT
60%
# SKUs
16 Days
Quantity/time
KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000
42 Days
8 Min
VSM COMPONENTS
SALES &
OPERATIONS
PLANNING
Information Flow
MASTER PRODUCTION
SCHEDULE (MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
Order Lead
Time
1 week
# SKUs
Frequency
1.8 Cars/Day
Lot Size
140K lbs
Transp time
7 Days
1 Week
# SKUs
Frequency
1 Car/Day
Lot Size
140K lbs
Transp time
7 Days
ORDERS
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
SHEET
FORMING
6
(4)
SUPPLIER 2
CUSTOMER
SERVICE
REPS
PRODUCTION
SUPERVISOR
Order Lead
Time
CUSTOMER FORECASTS
(QUARTERLY)
CAPACITY FORECAST
(MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
SUPPLIER 1
DEMAND
MANAGEMENT
PROCESS
Invtry
6.3M lbs
Days
16
#
SKUs
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
CALENDARING
BONDING
(4)
6
Invtry
2500 R
Days
12.6
#
SKUs
50
Effective
Capacity
8.9
TAKT
8.3
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Invtry
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
Material Flow
(Master Rolls/Hr)
MATERIAL
RELEASES
4000
Days
#
SKUs
1000
Invtry
Effective
Capacity
29
Effective
Capacity
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
93%
Lead time
15 Min
Utilization
83%
Utilization
Lead time
17 Min
Yield
87%
Lead time
10 Min
Lead time
10 Min
Lead time
8 Min
Yield
87%
Reliability
Yield
98%
Yield
100%
Yield
100%
Reliability
95%
Reliability
98%
Reliability
90%
Reliability
98%
UPtime
73.6%
UPtime
61%
50
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
Batch size
1 roll
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
EPEI
9 days
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
C/O time
1 hr
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
2 Rolls
C/O loss
~0
168 hr/wk
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
3 M
7 Days
21 Days
17 Min
10 Min
10 Min
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
322M sq Ft
Days
42
# SKUs
2,000
Data boxes
Avail time
12.6 Days
320K Sq Ft/Hr
98%
Shift schd
15 Min
230M Sq Ft/Mo
TAKT
60%
# SKUs
16 Days
Quantity/time
42 Days
8 Min
KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000
Timeline
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
CALENDARING
BONDING
(4)
6
Eff Capac
TAKT
8.9
8.3
(Master Rolls/Hr)
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Eff Capac
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Utilization
93%
Lead time
17 Min
Lead time
Yield
87%
Yield
Reliability
98%
UPtime
61%
CHOPPING
(3)
5
Invtry
4000
Days
#
SKUs
1000
WRAPPING
PACKAGING
LABELING 4
CUSTOMERS,
DISTRIBUTORS
Invtry
Eff Capac
29
Eff Capac
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
322M sq Ft
Quantity/time
230M Sq Ft/Mo
Days
42
TAKT
320K Sq Ft/Hr
# SKUs
2,000
7 Days
Utilization
83%
Utilization
60%
10 Min
Lead time
10 Min
Lead time
8 Min
Frequency
12 Trucks/Day
98%
Yield
100%
Yield
100%
Lot Size
648K Sq Ft
Reliability
95%
Reliability
98%
Reliability
98%
Transp time
3 Days
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
~0
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Eff Capac
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Yield
98%
Reliability
95%
UPtime
69%
# SKUs
1000
Batch size
1 roll
EPEI
7 days
C/O time
5 Min
C/O loss
~0
Avail time
168 hr/wk
Shift schd
3x8x7
External
Customer
Process
Step
BONDING
3
External
Supplier
Inventory
1.5
SHEET
FORMING
2
6
1.5
1.5
Process Step
Scheduled by
Product Wheel
Number of operators
assigned to a process
step
Inventory Managed
as a Supermarket
FIFO
Inventory Managed
in a
First In First Out
mode
9
Material to a customer
or from a supplier
10
TRANSPORTATION ICONS
Fork Truck
Conveyor
Tractor Trailer
Railcar
11
CALENDARING
BONDING
(4)
6
Eff Capac
TAKT
8.9
8.3
(Master Rolls/Hr)
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Eff Capac
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Utilization
93%
Lead time
17 Min
Lead time
Yield
87%
Yield
Reliability
98%
UPtime
61%
CHOPPING
(3)
5
Invtry
4000
Days
#
SKUs
1000
WRAPPING
PACKAGING
LABELING 4
CUSTOMERS,
DISTRIBUTORS
Invtry
Eff Capac
29
Eff Capac
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
322M sq Ft
Quantity/time
230M Sq Ft/Mo
Days
42
TAKT
320K Sq Ft/Hr
# SKUs
2,000
7 Days
Utilization
83%
Utilization
60%
10 Min
Lead time
10 Min
Lead time
8 Min
Frequency
12 Trucks/Day
98%
Yield
100%
Yield
100%
Lot Size
648K Sq Ft
Reliability
95%
Reliability
98%
Reliability
98%
Transp time
3 Days
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
~0
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
12
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
13
xx
xx
xx
14
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
Note: Not all of these data will be relevant in every case - and others may be added
to completely describe issues relevant to specific processes .
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
15
xx
xx
xx
FIFO
16
xx
xx
xx
17
Low volume, critical materials which could shut down the process
Order lead time = the time from placing
the order to the time the supplier ships
xx
xx
18
Process boxes
CALENDARING
BONDING
(4)
6
Eff Capac
TAKT
8.9
8.3
(Master Rolls/Hr)
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Eff Capac
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Utilization
93%
Lead time
17 Min
Lead time
Yield
87%
Yield
Reliability
98%
UPtime
61%
CHOPPING
(3)
5
Invtry
4000
Days
#
SKUs
1000
WRAPPING
PACKAGING
LABELING 4
CUSTOMERS,
DISTRIBUTORS
Invtry
Eff Capac
29
Eff Capac
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
322M sq Ft
Quantity/time
230M Sq Ft/Mo
Days
42
TAKT
320K Sq Ft/Hr
# SKUs
2,000
7 Days
Utilization
83%
Utilization
60%
10 Min
Lead time
10 Min
Lead time
8 Min
Frequency
12 Trucks/Day
98%
Yield
100%
Yield
100%
Lot Size
648K Sq Ft
Reliability
95%
Reliability
98%
Reliability
98%
Transp time
3 Days
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
~0
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Data boxes
19
MASTER PRODUCTION
SCHEDULE (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
DEMAND
MANAGEMENT
PROCESS
CAPACITY FORECAST
(MONTHLY)
CUSTOMER FORECASTS
(QUARTERLY)
CUSTOMER
SERVICE
REPS
ORDERS
PRODUCTION
SUPERVISOR
CURRENT
INVENTORIES
ORDER
GRANTS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
CUSTOMERS,
DISTRIBUTORS
Quantity/time
230M Sq Ft/Mo
TAKT
320K Sq Ft/Hr
7 Days
20
SALES &
OPERATIONS
PLANNING
MASTER PRODUCTION
SCHEDULE (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
DEMAND
MANAGEMENT
PROCESS
CUSTOMER FORECASTS
(QUARTERLY)
CUSTOMER
SERVICE
REPS
CAPACITY FORECAST
(MONTHLY)
ORDERS
PRODUCTION
SUPERVISOR
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
CALENDARING
BONDING
(4)
6
SLITTING
(3)
Eff Capac
8.9
Invtry
3650 R
TAKT
8.3
Days
21
#
SKUs
200
(Master Rolls/Hr)
Utilization
93%
Lead time
17 Min
MATERIAL
RELEASES
Eff Capac
CHOPPING
(3)
5
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Invtry
4000
Days
#
SKUs
1000
WRAPPING
PACKAGING
LABELING 4
Invtry
Eff Capac
29
Eff Caac
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
83%
Utilization
60%
Lead time
10 Min
Lead time
8 Min
Yield
87%
Yield
98%
Reliability
98%
Yield
100%
Yield
100%
Reliability
95%
UPtime
61%
Reliability
98%
Reliability
98%
UPtime
69%
# SKUs
200
UPtime
98%
UPtime
98%
# SKUs
1000
Batch size
1 roll
# SKUs
1800
# SKUs
2000
Batch size
1 roll
EPEI
13 days
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
7 days
C/O time
45 Min
EPEI
7 days
EPEI
7 days
C/O time
5 Min
C/O loss
~0
C/O time
C/O time
C/O loss
~0
Avail time
168 hr/wk
C/O loss
C/O loss
Avail time
168 hr/wk
Shift schd
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Quantity/time
230M Sq Ft/Mo
TAKT
320K Sq Ft/Hr
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
322M sq Ft
Days
42
# SKUs
2,000
21
The timeline appears on the bottom of the VSM, below the material flow
and data boxes
It is a square wave contrasts value-add time with non-value-add time
Normal convention NVA time is the high part of the wave, VA time the
low portion
17 Min
3 M
7 Days
21 Days
10 Min
10 Min
42 Days
8 Min
The timeline highlights all those wastes that add time (most of them do!)
In many assembly processes, NVA is 90% of total time
In process plants it can exceed 99%
23
CALENDARING
BONDING
(4)
6
Eff Capac
8.9
TAKT
8.3
(Master Rolls/Hr)
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Invtry
Eff Capac
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Utilization
93%
Lead time
17 Min
Lead time
Yield
87%
Reliability
UPtime
# SKUs
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
4000
Days
#
SKUs
1000
Invtry
Eff Capac
29
Eff Capac
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
83%
Utilization
10 Min
Lead time
10 Min
Lead time
8 Min
Yield
98%
Yield
100%
Yield
100%
98%
Reliability
95%
Reliability
98%
Reliability
98%
61%
UPtime
69%
UPtime
98%
UPtime
98%
200
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
~0
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
17 Min
10 Min
10 Min
Days
42
# SKUs
2,000
60%
3 M
7 Days
21 Days
322M sq Ft
42 Days
8 Min
24
SALES &
OPERATIONS
PLANNING
MASTER PRODUCTION
SCHEDULE (MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
AGGREGATED
DEMAND
(MONTHLY)
Order Lead
Time
1 week
# SKUs
Frequency
1.8 Cars/Day
Lot Size
140K lbs
Transp time
7 Days
1 Week
# SKUs
Frequency
1 Car/Day
Lot Size
140K lbs
Transp time
7 Days
ORDERS
ORDER
GRANTS
CURRENT
INVENTORIES
CUSTOMERS,
DISTRIBUTORS
DAILY PRODUCTION
SCHEDULE (WEEKLY)
SHEET
FORMING
6
(4)
SUPPLIER 2
CUSTOMER
SERVICE
REPS
PRODUCTION
SUPERVISOR
Order Lead
Time
CUSTOMER FORECASTS
(QUARTERLY)
CAPACITY FORECAST
(MONTHLY)
RAW MATERIAL
ORDERS (MONTHLY)
SUPPLIER 1
DEMAND
MANAGEMENT
PROCESS
Invtry
6.3M lbs
Days
16
#
SKUs
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
CALENDARING
BONDING
(4)
6
Invtry
2500 R
Days
12.6
#
SKUs
50
Effective
Capacity
8.9
TAKT
8.3
(Master Rolls/Hr)
MATERIAL
RELEASES
SLITTING
(3)
Invtry
3650 R
Days
21
#
SKUs
200
Invtry
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
WRAPPING
PACKAGING
LABELING 4
CHOPPING
(3)
5
4000
Days
#
SKUs
1000
Invtry
Effective
Capacity
29
Effective
Capacity
200
TAKT
24
TAKT
120
(Slit Rolls/Hr)
(Cut Rolls/Hr)
Utilization
93%
Lead time
15 Min
Utilization
83%
Utilization
Lead time
17 Min
Yield
87%
Lead time
10 Min
Lead time
10 Min
Lead time
8 Min
Yield
87%
Reliability
90%
Yield
98%
Yield
100%
Yield
100%
Reliability
95%
Reliability
98%
Reliability
Reliability
98%
UPtime
73.6%
UPtime
61%
50
UPtime
69%
UPtime
98%
UPtime
98%
# SKUs
200
Batch size
1 roll
# SKUs
1000
# SKUs
1800
# SKUs
2000
Batch size
1 roll
EPEI
9 days
Batch size
1 roll
Batch size
1 Slit Roll
Batch size
1 Cut Roll
EPEI
13 days
C/O time
1 hr
EPEI
7 days
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O time
5 Min
C/O time
C/O time
C/O loss
2 Rolls
C/O loss
~0
Avail time
168 hr/wk
C/O loss
~0
C/O loss
C/O loss
Avail time
168 hr/wk
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
12.6 Days
3 M
7 Days
21 Days
17 Min
10 Min
10 Min
320K Sq Ft/Hr
7 Days
Frequency
12 Trucks/Day
Lot Size
648K Sq Ft
Transp time
3 Days
322M sq Ft
Days
42
# SKUs
2,000
98%
Shift schd
15 Min
230M Sq Ft/Mo
TAKT
60%
# SKUs
16 Days
Quantity/time
KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000
42 Days
8 Min
25
BENEFITS OF A VSM
26
27
TAKT TIME
Takt
A measure of the rate of customer demand
Takt in German means rhythm, or drum beat
Goal is to synchronize production to customer needs
28
TAKT TIME
Number of shifts
Hours per shift
Deduct time for lunch and breaks
If a plant runs 16 hours per day, 5 days each week, available time would
be 80 hours per week
If production suspends for an hour each shift for lunch and breaks,
available time is 70 hours per week
Do NOT deduct for equipment downtime
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
29
TAKT TIME
30
31
32
Step 5
Step 6
CUSTOMER
Demand = 1200
rolls/day
33
Step 4
Step 5
Step 6
Eff Capac
= 102 rolls/hr
Eff Capac
= 54 rolls/hr
Eff Capac
= 85 rolls/hr
CUSTOMER
Demand = 1200
rolls/day
34
Units of
Production
(Pounds?, Gallons?, Rolls?, Square Meters?)
35
UNITS OF PRODUCTION
The units by which production is measured may change from step to step
Two considerations:
1) Use the units most directly related to equipment throughput.
2) Use the units generally used within the area (by operators,
mechanics, process engineers, lab technicians).
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
36
Polymerization
Reactor 1 POUNDS
Roll Forming
Machine 1
or GALLONS
Roll Forming
Machine 2
Roll Bonder 1
Roll Forming
Machine 3
Roll Bonder 2
Roll Slitting
Machine 1
Roll Bonder 3
Roll Slitting
Machine 2
Chopper
1
UNITS OF PRODUCTION
Chopper
2
Roll Forming
MILL
ROLLS
Machine
4
Roll Bonder 4
MILL ROLLS
Roll Slitting
MILL
Machine 3
ROLLS or
SLIT ROLLS
Chopper
3
SLIT ROLLS or
SHEETS
37
UNITS OF PRODUCTION
38
39
Lab technicians
Customer service reps
Production schedulers
Supervisors
40
Two approaches
1. Walk the line
41
WHERE TO BEGIN
42
43
LEVEL OF DETAIL
Re-work areas
Waste streams
44
NARROW ROLL
CHOPPER
(1' - 3')
(1)
Effective
Capacity
5
9
TAKT
(Slit Rolls/Hr)
SLITTING
(3)
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Yield
98%
Reliability
95%
UPtime
69%
# SKUs
1000
Batch size
1 roll
89%
Lead time
10 Min
Yield
100%
5
Invtry
Effective
Capacity
Utilization
EPEI
7 days
C/O time
5 Min
C/O loss
~0
Avail time
168 hr/wk
Shift schd
3x8x7
WRAPPING
PACKAGING
LABELING 4
4000
Days
#
SKUs
1000
Effective
Capacity
TAKT
(2)
Utilization
Effective
Capacity
20
TAKT
16
200
120
(Cut Rolls/Hr)
UNIVERSAL
CHOPPER
(1' - 6')
(Slit Rolls/Hr)
Utilization
80%
Lead time
10 Min
Yield
100%
60%
Lead time
8 Min
Yield
100%
Reliability
98%
UPtime
98%
# SKUs
2000
Batch size
1 Cut Roll
EPEI
7 days
C/O time
C/O loss
Avail time
168 hr/wk
Shift schd
3x8x7
45
NARROW ROLL
CHOPPER
(1' - 3')
(1)
Effective
Capacity
TAKT
(Slit Rolls/Hr)
SLITTING
(3)
Effective
Capacity
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Yield
98%
95%
UPtime
69%
# SKUs
1000
Batch size
1 roll
89%
10 Min
Yield
100%
WRAPPING
PACKAGING
LABELING 4
10.3
Reliability
Utilization
Lead time
EPEI
7 days
C/O time
5 Min
C/O loss
~0
Avail time
168 hr/wk
Shift schd
3x8x7
Invtry
4000
Days
#
SKUs
1000
Effective
Capacity
20
TAKT
16
(Slit Rolls/Hr)
Utilization
80%
Lead time
10 Min
Yield
100%
120
Utilization
60%
Lead time
8 Min
Yield
100%
Reliability
98%
UPtime
98%
# SKUs
2000
Batch size
1 Cut Roll
EPEI
7 days
C/O time
C/O loss
Avail time
168 hr/wk
Shift schd
3x8x7
3 M
7 Days
10 Min
200
TAKT
(Cut Rolls/Hr)
UNIVERSAL
CHOPPER
(1' - 6')
(2)
Effective
Capacity
8 Min
46
SHEET
FORMING
(4)
6
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
CALENDARING
BONDING
(4)
6
SLITTING
(3)
ROLL
GOODS
STORAGE
Effective
Capacity
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
AUTOMATIC
STORAGE &
RETRIEVAL SYSTEM
10 Min
CHOPPING
(3)
5
Effective
Capacity
8.9
Effective
Capacity
29
TAKT
8.3
TAKT
24
(Master Rolls/Hr)
Utilization
93%
(Slit Rolls/Hr)
Utilization
83%
Lead time
10 Min
47
SHEET
FORMING
6
(4)
Effective
Capacity
11.8
TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
Lead time
15 Min
CALENDARING
BONDING
(4)
6
Invtry
Days
#
SKUs
1990
Rolls
10
50
Effective
Capacity
8.9
TAKT
8.3
(Master Rolls/Hr)
Utilization
93%
Lead time
17 Min
SLITTING
(3)
1380
Rolls
Invtry
Days
#
SKUs
200
Effective
Capacity
CHOPPING
(3)
5
10.3
TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time
10 Min
Invtry
4000
Days
#
SKUs
1000
Effective
Capacity
29
TAKT
24
(Slit Rolls/Hr)
Utilization
83%
Lead time
10 Min
Yield
87%
Yield
87%
Reliability
90%
Yield
98%
Yield
100%
Reliability
98%
UPtime
73.6%
Reliability
95%
Reliability
98%
UPtime
61%
# SKUs
50
UPtime
69%
UPtime
98%
# SKUs
200
Batch size
1 roll
# SKUs
1000
# SKUs
1800
Batch size
1 roll
Batch size
1 roll
Batch size
1 Slit Roll
EPEI
7 days
EPEI
7 days
C/O time
1 hr
EPEI
7 days
EPEI
7 days
C/O time
45 Min
C/O loss
2 Rolls
C/O time
5 Min
C/O time
C/O loss
~0
Avail time
168 hr/wk
C/O loss
~0
C/O loss
Avail time
168 hr/wk
Shift schd
3x8x7
Avail time
168 hr/wk
Avail time
168 hr/wk
Shift schd
3x8x7
Shift schd
3x8x7
Shift schd
3x8x7
10 Days
15 Min
17 Min
3 M
7 Days
8 Days
10 Min
10 Min
48
SUMMARY
In order to become more lean, you must be able to see the waste in
your process
Value Stream Mapping is a proven, effective way to do that
A well constructed VSM will enable you to see the major wastes
And clues to their root cause
49
SUMMARY II
50
TO LEARN MORE ..
Productivity Press
May 2009
51
Questions?
peterking@LeanDynamics.us
(302) 239-1667
(302) 528-2700
52
Appendix 1
TAKT TIME & CYCLE TIME
53
Takt
A measure of the rate of customer demand
Takt in German means rhythm, or drum beat
Goal is to synchronize production to customer needs
54
Number of shifts
Hours per shift
Deduct time for lunch and breaks
If a plant runs 16 hours per day, 5 days each week, available time would
be 80 hours per week
If production suspends for an hour each shift for lunch and breaks,
available time is 70 hours per week
Do NOT deduct for equipment downtime
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
55
56
Step 2
Step 3
Step 4
Step 5
Yield = 90%
CUSTOMER
Customer demand
= 2000 mowers
per week
57
Cycle Time
If Takt represents customer demand.
Our process must be able to produce within that time
Cycle Time measures how long it takes to produce one unit, one
lot, one batch, etc.
If Cycle Time < Takt, we can produce faster than customer needs
If the cycle time for step 3 in the lawnmower plant is 2 minutes,
we can produce faster than needed, with about 10% spare
capacity
58
/ (MDR
/ (MDR
x UPtime)
59
Utilization
A measure of how fully occupied a process step is, how busy it is
60
61
62
Effective Capacity
The reciprocal of Cycle Time is often called Effective Capacity
As before, it represents realistic expectations, not perfection
63
Utilization
A measure of how fully occupied a process step is, how busy it is
Everything works out the same, its just easier for some
people to relate to rate based parameters
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED
64
Step 4
Step 5
Yield = 100%
Takt = 55 rolls/hr
Yield = 90%
Takt = 50 rolls/hr
Step 6
Avail time = 24 hr/day
Takt = 50 rolls/hr
CUSTOMER
Demand = 1200
rolls/day
65
Step 4
Step 5
Step 6
CUSTOMER
Demand = 1200
rolls/day
66
Step 4
Step 5
Step 6
MDR = 72 rolls/hr
OEE = 75%
Eff Capac = 54 rolls/hr
Util = 93%
CUSTOMER
Demand = 1200
rolls/day
67
To summarize
Take time or take rate is what each step in the process must make to meet
customer demand
If cycle time and takt time for a process step are exactly equal, that step is
perfectly synchronized to customer needs
If cycle time is less than takt, we have some degree of excess capacity (this
is desirable)
68