Sunteți pe pagina 1din 68

VALUE STREAM MAPPING

PROCESS INDUSTRY OPERATIONS

Peter L. King
Lean Dynamics, LLC
January 2010

AGENDA

Value Stream Map basics


Material flow
Process boxes
Icons

Data boxes
Information flow
The Timeline
Mapping considerations ~ good VSM practices
Benefits of VSMs
Summary

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

Lean is all about removing WASTE from our process


and improving FLOW
SALES &
OPERATIONS
PLANNING

AGGREGATED
DEMAND
(MONTHLY)

MASTER PRODUCTION
SCHEDULE (MONTHLY)

Order Lead
Time

1 week

# SKUs

1.8 Cars/Day

Lot Size

140K lbs

Transp time

7 Days

How do we understand the flow?

Invtry

1 Week

# SKUs

Frequency

1 Car/Day

Lot Size

140K lbs

Transp time

7 Days

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

SHEET
FORMING
6
(4)
SUPPLIER 2

ORDERS

PRODUCTION
SUPERVISOR

SCHEDULE UPDATES (DAILY)

Order Lead
Time

CUSTOMER
SERVICE
REPS

CAPACITY FORECAST
(MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

Frequency

CUSTOMER FORECASTS
(QUARTERLY)

How do we see waste?

RAW MATERIAL
ORDERS (MONTHLY)

SUPPLIER 1

DEMAND
MANAGEMENT
PROCESS

6.3M lbs

Days

16

#
SKUs

Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

CALENDARING
BONDING
(4)
6

Invtry

MATERIAL
RELEASES

SCHEDULE UPDATES (DAILY)

SLITTING
(3)

A Value Stream Map

2500 R

Days

12.6

#
SKUs

50

Effective
Capacity

8.9

TAKT

8.3

(Master Rolls/Hr)

Invtry

3650 R

Days

21

#
SKUs

200

Invtry

Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5

4000

Days

#
SKUs

1000

Effective
Capacity

TAKT

Invtry

29

Effective
Capacity

200

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

93%

Lead time

15 Min

Utilization

83%

Utilization

Lead time

17 Min

Yield

87%

Lead time

10 Min

Lead time

10 Min

Lead time

8 Min

Yield

87%

Reliability

Yield

98%

Yield

100%

Yield

100%

Reliability

95%

Reliability

98%

Reliability

90%

Reliability

98%

UPtime

73.6%

UPtime

61%

50

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

Batch size

1 roll

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

EPEI

9 days

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

C/O time

1 hr

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

2 Rolls

C/O loss

~0

Avail time

168 hr/wk

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

12.6 Days

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

3 M

7 Days

21 Days
17 Min

10 Min

10 Min

320K Sq Ft/Hr
7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

322M sq Ft

Days

42

# SKUs

2,000

98%

Shift schd

15 Min

230M Sq Ft/Mo

TAKT

60%

# SKUs

16 Days

Quantity/time

Lead time Exp

KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000

42 Days
8 Min

NVA Time = 99 Days


VA Time = 73 Min

ORIGINS OF VALUE STREAM MAPS


SALES &
OPERATIONS
PLANNING

MASTER PRODUCTION
SCHEDULE (MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

Order Lead
Time

1 week

# SKUs

Frequency

1.8 Cars/Day

Lot Size

140K lbs

CUSTOMER FORECASTS
(QUARTERLY)

CUSTOMER
SERVICE
REPS

CAPACITY FORECAST
(MONTHLY)

ORDERS

PRODUCTION
SUPERVISOR

RAW MATERIAL
ORDERS (MONTHLY)

SUPPLIER 1

DEMAND
MANAGEMENT
PROCESS

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

Based on Toyotas material and information flow


diagrams

Transp time

DAILY PRODUCTION
SCHEDULE (WEEKLY)

7 Days

SCHEDULE UPDATES (DAILY)

SHEET
FORMING
6
(4)

SUPPLIER 2
Order Lead
Time

1 Week

# SKUs

Frequency
Lot Size
Transp time

MATERIAL
RELEASES

SCHEDULE UPDATES (DAILY)

CALENDARING
BONDING
(4)
6

SLITTING
(3)
5

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5

Standardized and popularized by Rother and


Shook in Learning To See
Invtry

6.3M lbs

Days

16

#
SKUs

Effective
Capacity

11.8

140K lbs

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

7 Days

Lead time

15 Min

1 Car/Day

Invtry

2500 R

Days

12.6

#
SKUs

50

Effective
Capacity

8.9

TAKT

8.3

(Master Rolls/Hr)

Utilization

93%

Lead time

17 Min

Invtry

3650 R

Days

21

#
SKUs

200

Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

Lead time

10 Min

Invtry

4000

Days

#
SKUs

1000

Invtry

Effective
Capacity

29

Effective
Capacity

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

83%

Utilization

60%

Lead time

10 Min

Lead time

8 Min

Yield

87%

Yield

87%

Reliability

90%

Yield

98%

Yield

100%

Yield

100%

Reliability

98%

UPtime

73.6%

Reliability

95%

Reliability

98%

Reliability

98%

UPtime

61%

UPtime

69%

UPtime

98%

UPtime

98%

1000

# SKUs

1800

# SKUs

2000

# SKUs

50

# SKUs

200

Batch size

1 roll

# SKUs

Batch size

1 roll

EPEI

9 days

Batch size

1 roll

EPEI

13 days

C/O time

1 hr

EPEI

7 days

C/O time

45 Min

C/O loss

2 Rolls

C/O time

C/O loss

~0

C/O loss

Batch size 1 Slit Roll


EPEI

7 days

5 Min

7 days

C/O time

~0

C/O loss

C/O time

C/O loss

Avail time 168 hr/wk

Avail time 168 hr/wk

Shift schd

Avail time 168 hr/wk

Avail time 168 hr/wk

Avail time 168 hr/wk

Shift schd

Shift schd

Shift schd

Shift schd

3x8x7

16 Days

3x8x7

12.6 Days
15 Min

3x8x7

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

10 Min

10 Min

320K Sq Ft/Hr

Lead time Exp

7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

42

# SKUs

2,000

KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000

3x8x7

3 M

7 Days

21 Days
17 Min

3x8x7

230M Sq Ft/Mo

TAKT

322M sq Ft

Days

Batch size 1 Cut Roll


EPEI

Quantity/time

42 Days
8 Min

NVA Time = 99 Days


VA Time = 73 Min

A COMPLETE VSM

SALES &
OPERATIONS
PLANNING

MASTER PRODUCTION
SCHEDULE (MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

Order Lead
Time

1 week

# SKUs

Frequency

1.8 Cars/Day

Lot Size

140K lbs

Transp time

7 Days

1 Week

# SKUs

Frequency

1 Car/Day

Lot Size

140K lbs

Transp time

7 Days

ORDERS

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

SHEET
FORMING
6
(4)
SUPPLIER 2

CUSTOMER
SERVICE
REPS

PRODUCTION
SUPERVISOR

SCHEDULE UPDATES (DAILY)

Order Lead
Time

CUSTOMER FORECASTS
(QUARTERLY)

CAPACITY FORECAST
(MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

SUPPLIER 1

DEMAND
MANAGEMENT
PROCESS

Invtry

6.3M lbs

Days

16

#
SKUs

Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

SCHEDULE UPDATES (DAILY)

CALENDARING
BONDING
(4)
6
Invtry

2500 R

Days

12.6

#
SKUs

50

Effective
Capacity

8.9

TAKT

8.3

(Master Rolls/Hr)

MATERIAL
RELEASES

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Invtry
Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5
4000

Days

#
SKUs

1000

Invtry
Effective
Capacity

29

Effective
Capacity

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

93%

Lead time

15 Min

Utilization

83%

Utilization

Lead time

17 Min

Yield

87%

Lead time

10 Min

Lead time

10 Min

Lead time

8 Min

Yield

87%

Reliability

Yield

98%

Yield

100%

Yield

100%

Reliability

95%

Reliability

98%

Reliability

90%

Reliability

98%

UPtime

73.6%

UPtime

61%

50

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

Batch size

1 roll

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

EPEI

9 days

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

C/O time

1 hr

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

2 Rolls

C/O loss

~0

Avail time

168 hr/wk

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

12.6 Days

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

3 M

7 Days

21 Days
17 Min

10 Min

10 Min

320K Sq Ft/Hr

Lead time Exp

7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

322M sq Ft

Days

42

# SKUs

2,000

98%

Shift schd

15 Min

230M Sq Ft/Mo

TAKT

60%

# SKUs

16 Days

Quantity/time

KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000

42 Days
8 Min

NVA Time = 99 Days


VA Time = 73 Min

VSM COMPONENTS

SALES &
OPERATIONS
PLANNING

Information Flow

MASTER PRODUCTION
SCHEDULE (MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

Order Lead
Time

1 week

# SKUs

Frequency

1.8 Cars/Day

Lot Size

140K lbs

Transp time

7 Days

1 Week

# SKUs

Frequency

1 Car/Day

Lot Size

140K lbs

Transp time

7 Days

ORDERS

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

SHEET
FORMING
6
(4)
SUPPLIER 2

CUSTOMER
SERVICE
REPS

PRODUCTION
SUPERVISOR

SCHEDULE UPDATES (DAILY)

Order Lead
Time

CUSTOMER FORECASTS
(QUARTERLY)

CAPACITY FORECAST
(MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

SUPPLIER 1

DEMAND
MANAGEMENT
PROCESS

Invtry

6.3M lbs

Days

16

#
SKUs

Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

SCHEDULE UPDATES (DAILY)

CALENDARING
BONDING
(4)
6
Invtry

2500 R

Days

12.6

#
SKUs

50

Effective
Capacity

8.9

TAKT

8.3

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Invtry
Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5

Material Flow

(Master Rolls/Hr)

MATERIAL
RELEASES

4000

Days

#
SKUs

1000

Invtry
Effective
Capacity

29

Effective
Capacity

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

93%

Lead time

15 Min

Utilization

83%

Utilization

Lead time

17 Min

Yield

87%

Lead time

10 Min

Lead time

10 Min

Lead time

8 Min

Yield

87%

Reliability

Yield

98%

Yield

100%

Yield

100%

Reliability

95%

Reliability

98%

Reliability

90%

Reliability

98%

UPtime

73.6%

UPtime

61%

50

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

Batch size

1 roll

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

EPEI

9 days

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

C/O time

1 hr

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

2 Rolls

C/O loss

~0

168 hr/wk

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

3 M

7 Days

21 Days
17 Min

10 Min

10 Min

7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

322M sq Ft

Days

42

# SKUs

2,000

Data boxes

Avail time

12.6 Days

320K Sq Ft/Hr

Lead time Exp

98%

Shift schd

15 Min

230M Sq Ft/Mo

TAKT

60%

# SKUs

16 Days

Quantity/time

42 Days
8 Min

KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000

NVA Time = 99 Days


VA Time = 73 Min

Timeline
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

MATERIAL FLOW ON A VSM

CALENDARING
BONDING
(4)
6
Eff Capac

TAKT

8.9
8.3

(Master Rolls/Hr)

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Eff Capac

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

Utilization

93%

Lead time

17 Min

Lead time

Yield

87%

Yield

Reliability

98%

UPtime

61%

CHOPPING
(3)
5
Invtry

4000

Days

#
SKUs

1000

WRAPPING
PACKAGING
LABELING 4

CUSTOMERS,
DISTRIBUTORS
Invtry

Eff Capac

29

Eff Capac

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

322M sq Ft

Quantity/time

230M Sq Ft/Mo

Days

42

TAKT

320K Sq Ft/Hr

# SKUs

2,000

Lead time Exp

7 Days

Utilization

83%

Utilization

60%

10 Min

Lead time

10 Min

Lead time

8 Min

Frequency

12 Trucks/Day

98%

Yield

100%

Yield

100%

Lot Size

648K Sq Ft

Reliability

95%

Reliability

98%

Reliability

98%

Transp time

3 Days

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

~0

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

THE PROCESS BOX


Each major process step will be represented by a PROCESS BOX
A machine
A process vessel, a tank
SLITTING
A process system
(3)

Includes the quantity of similar machines


Includes the approximate number of operators assigned
The process box is accompanied by a DATA BOX
Lists all data relevant to flow and capacity
Helps to indicate waste
Identifies bottlenecks
Highlights quality issues
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

Eff Capac

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

10 Min

Yield

98%

Reliability

95%

UPtime

69%

# SKUs

1000

Batch size

1 roll

EPEI

7 days

C/O time

5 Min

C/O loss

~0

Avail time

168 hr/wk

Shift schd

3x8x7

MATERIAL FLOW ICONS

External
Customer

Process
Step

BONDING
3

External
Supplier

Inventory

1.5

SHEET
FORMING
2
6

1.5

1.5

Process Step
Scheduled by
Product Wheel

Number of operators
assigned to a process
step

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

Inventory Managed
as a Supermarket

FIFO

Inventory Managed
in a
First In First Out
mode
9

MORE MATERIAL FLOW ICONS

PUSH Material Movement

Material flow in a Pull environment

Material to a customer
or from a supplier

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

10

TRANSPORTATION ICONS

Fork Truck

Conveyor

Tractor Trailer

Railcar

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

11

VSM DATA BOXES

CALENDARING
BONDING
(4)
6
Eff Capac

TAKT

8.9
8.3

(Master Rolls/Hr)

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Eff Capac

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

Utilization

93%

Lead time

17 Min

Lead time

Yield

87%

Yield

Reliability

98%

UPtime

61%

CHOPPING
(3)
5
Invtry

4000

Days

#
SKUs

1000

WRAPPING
PACKAGING
LABELING 4

CUSTOMERS,
DISTRIBUTORS
Invtry

Eff Capac

29

Eff Capac

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

322M sq Ft

Quantity/time

230M Sq Ft/Mo

Days

42

TAKT

320K Sq Ft/Hr

# SKUs

2,000

Lead time Exp

7 Days

Utilization

83%

Utilization

60%

10 Min

Lead time

10 Min

Lead time

8 Min

Frequency

12 Trucks/Day

98%

Yield

100%

Yield

100%

Lot Size

648K Sq Ft

Reliability

95%

Reliability

98%

Reliability

98%

Transp time

3 Days

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

~0

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

12

Process Step Data Box

Customer Data Box


Total Quantity per unit time
TAKT
Lead Time Expectations

xx
xx
xx

Cycle Time (Capacity)


TAKT
Utilization
Lead Time
Yield
Reliability
Uptime
# SKUs
Batch Size
EPEI
C/O Time
C/O Losses
Available Time
Shift Sched

VALUE STREAM MAP


Supplier Data Box DATA BOXES

Order Lead Time


xx
# SKUs
xx
Transport Data Box
Delivery Frequency
Lot Size
Transport Time

xx
xx
xx

xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx

List all data relevant to FLOW and


Capacity
Think of it from an Industrial
Engineers perspective
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

13

CUSTOMER DATA BOX

Total quantity = the sum


total of all products ordered by
all customers

Customer Data Box


Total Quantity per unit time
TAKT
Lead Time Expectations

xx
xx
xx

Takt = The time available to produce one unit of customer


demand, or the rate at which product must be produced to
meet customer needs
Lead time = The maximum time the customer allows from
receipt of order to receipt of goods

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

14

MANUFACTURING PROCESS STEP DATA BOX

Process Step Data Box


Cycle Time (Capacity)
TAKT
Utilization
Lead Time
Yield
Reliability
Uptime
# SKUs
Batch Size
EPEI
C/O Time
C/O Losses
Available Time
Shift Sched

xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx
xx

Utilization = The % of available time


needed to meet customer demand.
Cycle Time/Takt

Lead time = the time for a unit of


material to move through this process
step
UPtime = OEE

Batch size = the quantity made as


one lot. Several batches of the same
material = a campaign.
EPEI (Every Part Every Interval) =
the time span over which all products
are made

Note: Not all of these data will be relevant in every case - and others may be added
to completely describe issues relevant to specific processes .
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

15

INVENTORY STORAGE DATA BOX

The inventory data box is short and simple but it is very


important and very enlightening as a symptom of waste!
There should be an inventory data box for each inventory, including
Raw materials

WIP (work in process)


Finished products

Inventory Data Box


Average Inventory
Days of Supply
# SKUs

xx
xx
xx

Average inventory = The average total inventory of all products at this


STEP in the process (NOT necessarily all products at this location!) in
pounds, gallons, square feet, rolls, cases, etc.
Days of Supply = Total inventory/throughput
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

FIFO
16

TRANSPORTATION DATA BOX

A data box should be shown for each significant transportation step

Deliveries to customers, warehouses, distribution centers


Supply of major or critical raw materials

Transport Data Box


Delivery Frequency
Lot Size
Transport Time

xx
xx
xx

Delivery frequency = how often


shipments are received; how often
shipments are made (sum of all
destinations)

Lot size = the average quantity shipped or received. Same units as


production and/or customer demand data: gallons, pounds, square meters,
rolls, etc.
Transport time = the average time from shipment to receipt
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

17

SUPPLIER DATA BOX

Not all raw material suppliers need to be shown on the VSM.


If they supply a very significant percentage of total raw materials

Low volume, critical materials which could shut down the process
Order lead time = the time from placing
the order to the time the supplier ships

Does not include transportation time

Supplier Data Box


Order Lead Time
# SKUs

xx
xx

# SKUs = the number of material types or part types normally received


from that suppler

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

18

MATERIAL FLOW ON A VSM


Icons

Process boxes

CALENDARING
BONDING
(4)
6
Eff Capac

TAKT

8.9
8.3

(Master Rolls/Hr)

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Eff Capac

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

Utilization

93%

Lead time

17 Min

Lead time

Yield

87%

Yield

Reliability

98%

UPtime

61%

CHOPPING
(3)
5
Invtry

4000

Days

#
SKUs

1000

WRAPPING
PACKAGING
LABELING 4

CUSTOMERS,
DISTRIBUTORS
Invtry

Eff Capac

29

Eff Capac

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

322M sq Ft

Quantity/time

230M Sq Ft/Mo

Days

42

TAKT

320K Sq Ft/Hr

# SKUs

2,000

Lead time Exp

7 Days

Utilization

83%

Utilization

60%

10 Min

Lead time

10 Min

Lead time

8 Min

Frequency

12 Trucks/Day

98%

Yield

100%

Yield

100%

Lot Size

648K Sq Ft

Reliability

95%

Reliability

98%

Reliability

98%

Transp time

3 Days

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

~0

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Data boxes

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

19

VSM INFORMATION FLOW


The VSM should show all of the major communications which influence
production planning, forecasting, order fulfillment, and detailed
scheduling
SALES &
OPERATIONS
PLANNING

MASTER PRODUCTION
SCHEDULE (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

DEMAND
MANAGEMENT
PROCESS

CAPACITY FORECAST
(MONTHLY)

CUSTOMER FORECASTS
(QUARTERLY)

CUSTOMER
SERVICE
REPS

ORDERS

PRODUCTION
SUPERVISOR
CURRENT
INVENTORIES

ORDER
GRANTS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

CUSTOMERS,
DISTRIBUTORS
Quantity/time

230M Sq Ft/Mo

TAKT

320K Sq Ft/Hr

Lead time Exp

7 Days

Starts with customer input orders and forecasts


Moves backward through various information processing steps
Goes through to detailed manufacturing schedules, releases for raw materials

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

20

COUPLING INFORMATION FLOW WITH MATERIAL FLOW

SALES &
OPERATIONS
PLANNING

MASTER PRODUCTION
SCHEDULE (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

DEMAND
MANAGEMENT
PROCESS

CUSTOMER FORECASTS
(QUARTERLY)

CUSTOMER
SERVICE
REPS

CAPACITY FORECAST
(MONTHLY)

ORDERS

PRODUCTION
SUPERVISOR

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

SCHEDULE UPDATES (DAILY)

SCHEDULE UPDATES (DAILY)

CALENDARING
BONDING
(4)
6

SLITTING
(3)

Eff Capac

8.9

Invtry

3650 R

TAKT

8.3

Days

21

#
SKUs

200

(Master Rolls/Hr)
Utilization

93%

Lead time

17 Min

MATERIAL
RELEASES

Eff Capac

CHOPPING
(3)
5

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

10 Min

Invtry

4000

Days

#
SKUs

1000

WRAPPING
PACKAGING
LABELING 4
Invtry

Eff Capac

29

Eff Caac

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

83%

Utilization

60%

Lead time

10 Min

Lead time

8 Min

Yield

87%

Yield

98%

Reliability

98%

Yield

100%

Yield

100%

Reliability

95%

UPtime

61%

Reliability

98%

Reliability

98%

UPtime

69%

# SKUs

200

UPtime

98%

UPtime

98%

# SKUs

1000

Batch size

1 roll

# SKUs

1800

# SKUs

2000

Batch size

1 roll

EPEI

13 days

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

7 days

C/O time

45 Min

EPEI

7 days

EPEI

7 days

C/O time

5 Min

C/O loss

~0

C/O time

C/O time

C/O loss

~0

Avail time

168 hr/wk

C/O loss

C/O loss

Avail time

168 hr/wk

Shift schd

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

Quantity/time

230M Sq Ft/Mo

TAKT

320K Sq Ft/Hr

Lead time Exp

7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

322M sq Ft

Days

42

# SKUs

2,000

21

COUPLING INFORMATION FLOW WITH MATERIAL FLOW

Any resource whose capacity is equal to


or less than the demand placed upon it

Any resource which, if not properly


scheduled and managed, is likely to
cause the actual flow of product
through the plant to deviate from the
desired product flow.
Integrating material flow and information flow on the same map helps to
uncover Capacity Constraints
From SYNCHRONOUS MANUFACTURING Umble and Srikanth, South-Western Publishing, 1990

THE VSM TIMELINE

The timeline appears on the bottom of the VSM, below the material flow
and data boxes
It is a square wave contrasts value-add time with non-value-add time
Normal convention NVA time is the high part of the wave, VA time the
low portion

17 Min

3 M

7 Days

21 Days
10 Min

10 Min

42 Days
8 Min

The timeline highlights all those wastes that add time (most of them do!)
In many assembly processes, NVA is 90% of total time
In process plants it can exceed 99%

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

23

THE VSM TIMELINE

CALENDARING
BONDING
(4)
6
Eff Capac

8.9

TAKT

8.3

(Master Rolls/Hr)

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Invtry

Eff Capac

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

Utilization

93%

Lead time

17 Min

Lead time

Yield

87%

Reliability
UPtime
# SKUs

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5
4000

Days

#
SKUs

1000

Invtry

Eff Capac

29

Eff Capac

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

83%

Utilization

10 Min

Lead time

10 Min

Lead time

8 Min

Yield

98%

Yield

100%

Yield

100%

98%

Reliability

95%

Reliability

98%

Reliability

98%

61%

UPtime

69%

UPtime

98%

UPtime

98%

200

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

~0

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

17 Min

10 Min

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

10 Min

Days

42

# SKUs

2,000

60%

3 M

7 Days

21 Days

322M sq Ft

42 Days
8 Min

24

A COMPLETE VALUE STREAM MAP

SALES &
OPERATIONS
PLANNING

MASTER PRODUCTION
SCHEDULE (MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

AGGREGATED
DEMAND
(MONTHLY)

Order Lead
Time

1 week

# SKUs

Frequency

1.8 Cars/Day

Lot Size

140K lbs

Transp time

7 Days

1 Week

# SKUs

Frequency

1 Car/Day

Lot Size

140K lbs

Transp time

7 Days

ORDERS

ORDER
GRANTS

CURRENT
INVENTORIES

CUSTOMERS,
DISTRIBUTORS

DAILY PRODUCTION
SCHEDULE (WEEKLY)

SHEET
FORMING
6
(4)
SUPPLIER 2

CUSTOMER
SERVICE
REPS

PRODUCTION
SUPERVISOR

SCHEDULE UPDATES (DAILY)

Order Lead
Time

CUSTOMER FORECASTS
(QUARTERLY)

CAPACITY FORECAST
(MONTHLY)

RAW MATERIAL
ORDERS (MONTHLY)

SUPPLIER 1

DEMAND
MANAGEMENT
PROCESS

Invtry

6.3M lbs

Days

16

#
SKUs

Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

SCHEDULE UPDATES (DAILY)

CALENDARING
BONDING
(4)
6
Invtry

2500 R

Days

12.6

#
SKUs

50

Effective
Capacity

8.9

TAKT

8.3

(Master Rolls/Hr)

MATERIAL
RELEASES

SLITTING
(3)
Invtry

3650 R

Days

21

#
SKUs

200

Invtry
Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%

WRAPPING
PACKAGING
LABELING 4

CHOPPING
(3)
5
4000

Days

#
SKUs

1000

Invtry
Effective
Capacity

29

Effective
Capacity

200

TAKT

24

TAKT

120

(Slit Rolls/Hr)

(Cut Rolls/Hr)

Utilization

93%

Lead time

15 Min

Utilization

83%

Utilization

Lead time

17 Min

Yield

87%

Lead time

10 Min

Lead time

10 Min

Lead time

8 Min

Yield

87%

Reliability

90%

Yield

98%

Yield

100%

Yield

100%

Reliability

95%

Reliability

98%

Reliability

Reliability

98%

UPtime

73.6%

UPtime

61%

50

UPtime

69%

UPtime

98%

UPtime

98%

# SKUs

200

Batch size

1 roll

# SKUs

1000

# SKUs

1800

# SKUs

2000

Batch size

1 roll

EPEI

9 days

Batch size

1 roll

Batch size

1 Slit Roll

Batch size

1 Cut Roll

EPEI

13 days

C/O time

1 hr

EPEI

7 days

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O time

5 Min

C/O time

C/O time

C/O loss

2 Rolls

C/O loss

~0

Avail time

168 hr/wk

C/O loss

~0

C/O loss

C/O loss

Avail time

168 hr/wk

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

12.6 Days

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

3 M

7 Days

21 Days
17 Min

10 Min

10 Min

320K Sq Ft/Hr

Lead time Exp

7 Days

Frequency

12 Trucks/Day

Lot Size

648K Sq Ft

Transp time

3 Days

322M sq Ft

Days

42

# SKUs

2,000

98%

Shift schd

15 Min

230M Sq Ft/Mo

TAKT

60%

# SKUs

16 Days

Quantity/time

KEY
K = 1,000
M = 1,000,000
B = 1,000,000,000

42 Days
8 Min

NVA Time = 99 Days


VA Time = 73 Min

25

BENEFITS OF A VSM

1. It gives the team a sense of flow, inventory, bottlenecks


2. It creates understanding of how value is created for customers
3. Brings everyone to a shared understanding of the end-to-end process
4. It highlights key areas of waste
5. It links planning and scheduling processes to material flow
6. It gives clues to root causes of waste
7. It provides a template for improvement plans, leading to the Future State
VSM

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

26

VSM BEST PRACTICES


Takt as a rate measure
Accounting for yield losses

Using the most appropriate units


Where to start the map
Convention on direction of flow
Parallel assets
Representing FLOW vs geography
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

27

TAKT TIME

Takt
A measure of the rate of customer demand
Takt in German means rhythm, or drum beat
Goal is to synchronize production to customer needs

Takt Time = Total available time / Customer demand


Units

Minutes (per car, per roll, per batch)


Also hours or seconds
A measure of how much time you have to produce a unit and meet
customer needs
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

28

TAKT TIME

Takt Time = Total available time / Customer demand


Available Time
The time you plan to run, the planned work schedule

Number of shifts
Hours per shift
Deduct time for lunch and breaks
If a plant runs 16 hours per day, 5 days each week, available time would
be 80 hours per week
If production suspends for an hour each shift for lunch and breaks,
available time is 70 hours per week
Do NOT deduct for equipment downtime
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

29

TAKT TIME

Takt Time = Total available time / Customer demand


Example
A salad dressing line has weekly demand of 45,000 cases for the flavors
made on that line
Three eight-hour shifts per day, 5 days per week
Production continues through lunch, breaks, shift changes
Available time = 3 x 8 x 5 = 120 hours/week
Takt = 120 hours / 45,000 cases = 9.6 seconds
So the plant must produce a case every 9.6 seconds to satisfy customer
demand
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

30

TAKT AS A RATE PARAMETER


The units for Takt Time can be awkward in a process plant
For a chemical process with a demand of 100 gal/min,
Takt time = 0.6 seconds/gal
For a plastic film line with a demand of 400 feet/min, Takt
time = 0.15 secs/foot
For our salad dressing line, if customer demand = 300
bottles/min, Takt time = 0.2 secs/bottle

Rate based parameters are often used instead of time


based units

Takt Time = Available time / Customer demand


Takt Rate = Customer demand/ Available time
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

31

TAKT AS A RATE PARAMETER


Takt Time = Total available time / Customer demand
Takt Rate = Customer demand/ Available time
So on our salad dressing line
Takt Time = 120 hours / 45,000 cases = 9.6 seconds
So the plant must produce a case every 9.6 seconds to satisfy customer
demand
Takt rate = 45,000 cases/120 hours = 375 cases/ hour
So we must produce 375 cases per hour to meet customer demand

Takt Time seems to work best in most parts operations


Takt Rate seems more appropriate in most process operations
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

32

TAKT and YIELD LOSSES

Takt Rate = Customer demand/ Available time

Takt must be adjusted to account for yield losses


Step 4
Avail time = 24 hr/day
Yield = 100%
Takt = 55 rolls/hr

Step 5

Step 6

Avail time = 24 hr/day


Takt = 50 rolls/hr
Yield = 90%

Avail time = 24 hr/day


Takt = 50 rolls/hr

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

CUSTOMER

Demand = 1200
rolls/day

33

TAKT and AVAILABLE TIME

Takt Rate = Customer demand/ Available time

If Available time changes, Takt changes

Step 4

Step 5

Step 6

Avail time = 16 hr/day


Yield = 100%
Takt = 83 rolls/hr

Avail time = 24 hr/day


Yield = 90%
Takt = 50 rolls/hr

Avail time = 24 hr/day


Takt = 50 rolls/hr

Eff Capac
= 102 rolls/hr

Eff Capac
= 54 rolls/hr

Eff Capac
= 85 rolls/hr

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

CUSTOMER

Demand = 1200
rolls/day

34

Units of
Production
(Pounds?, Gallons?, Rolls?, Square Meters?)

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

35

UNITS OF PRODUCTION

The units by which production is measured may change from step to step

In a ketchup production line


Raw materials: pounds, gallons, cases
Kitchen: gallons per minute
Bottling line: Bottles per minute (BPM)
Label applicator: BPM
Case packer: Cases per hour
Palletizer: Pallets per hour

Two considerations:
1) Use the units most directly related to equipment throughput.
2) Use the units generally used within the area (by operators,
mechanics, process engineers, lab technicians).
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

36

Polymerization
Reactor 1 POUNDS

Roll Forming
Machine 1

or GALLONS

Roll Forming
Machine 2

Roll Bonder 1

Roll Forming
Machine 3

Roll Bonder 2

Roll Slitting
Machine 1

Roll Bonder 3

Roll Slitting
Machine 2

Chopper
1

UNITS OF PRODUCTION

Chopper
2

Roll Forming

MILL
ROLLS
Machine
4

Roll Bonder 4
MILL ROLLS

Roll Slitting
MILL
Machine 3

ROLLS or
SLIT ROLLS

Chopper
3

SLIT ROLLS or
SHEETS

BOXES, SHEETS, or SQUARE METERS


Packaging
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

37

UNITS OF PRODUCTION

In an paper sheet goods manufacturing line


Raw materials: pounds, gallons

Sheet forming: Mill rolls


Bonding: Mill rolls
Slitting: Mill rolls or slit rolls
Chopper: Slit rolls, cut rolls or sheets
Packaging: Cut rolls or sheets
Palletizing: Cut rolls or boxes
Customer orders: Square feet, square meters

Again two considerations:


Use the units most directly related to equipment throughput.
Use the units generally used within the area (by operators,
mechanics, process engineers, lab technicians)..
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

38

CUSTOMER TAKT CONVERTED FOR EACH PROCESS STEP

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

39

GENERATING THE VSM

Creating the VSM should be a team activity


Cross-functional
Process engineers
Operators
Mechanics

Lab technicians
Customer service reps
Production schedulers
Supervisors

Creates shared learning across different process areas


Builds ownership for potential improvements
Knowledge base to understand root cause
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

40

GENERATING THE VSM

Two approaches
1. Walk the line

Sketch the flow as you go

Engage operators in discussions of flow and problems

2. Gather the team in a conference room

Discuss the process

Generate the VSM electronically

Then walk the line

Return to conference room and upgrade the VSM

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

41

WHERE TO BEGIN

Two mapping approaches


1. Start at the shipping dock and work backwards

Begins with customer needs

Works very well for converging processes

2. Start with receipt of raw materials and work forward

The way most people think of their process

May put more focus on the process vs the customer

Works better for diverging processes

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

42

GOOD VSM PRACTICES

Always depict flow from left to right

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

43

LEVEL OF DETAIL

Keep the map at a relatively high level

Detailed enough to see flow and barriers to flow


Not so detailed that main messages get buried
4 to 8 process steps is typical
If additional detail becomes important, can be shown on more
specific process maps
Auxiliary processes may be shown if they affect flow

Re-work areas

Testing labs, QC labs

Waste streams

Adopt an interstate map mindset

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

44

GOOD VSM PRACTICES

NARROW ROLL
CHOPPER
(1' - 3')

(1)
Effective
Capacity

5
9

TAKT

(Slit Rolls/Hr)

SLITTING
(3)

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

10 Min

Yield

98%

Reliability

95%

UPtime

69%

# SKUs

1000

Batch size

1 roll

89%

Lead time

10 Min

Yield

100%

5
Invtry

Effective
Capacity

Utilization

EPEI

7 days

C/O time

5 Min

C/O loss

~0

Avail time

168 hr/wk

Shift schd

3x8x7

WRAPPING
PACKAGING
LABELING 4

4000

Days

#
SKUs

1000

Effective
Capacity

TAKT

(2)

Utilization

Effective
Capacity

20

TAKT

16

200
120

(Cut Rolls/Hr)

UNIVERSAL
CHOPPER
(1' - 6')

(Slit Rolls/Hr)
Utilization

80%

Lead time

10 Min

Yield

100%

60%

Lead time

8 Min

Yield

100%

Reliability

98%

UPtime

98%

# SKUs

2000

Batch size

1 Cut Roll

EPEI

7 days

C/O time

C/O loss

Avail time

168 hr/wk

Shift schd

3x8x7

Similar equipment in parallel


If nearly identical, show as one process box, noting the
number of machines in parallel
If different, in a way that impacts flow, show each machine

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

45

PARALLEL EQUIPMENT WITH DIFFERENT CAPABILITY

NARROW ROLL
CHOPPER
(1' - 3')

(1)

Effective
Capacity

TAKT

(Slit Rolls/Hr)

SLITTING
(3)
Effective
Capacity

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

10 Min

Yield

98%
95%

UPtime

69%

# SKUs

1000

Batch size

1 roll

89%
10 Min

Yield

100%

WRAPPING
PACKAGING
LABELING 4

10.3

Reliability

Utilization
Lead time

EPEI

7 days

C/O time

5 Min

C/O loss

~0

Avail time

168 hr/wk

Shift schd

3x8x7

Invtry

4000

Days

#
SKUs

1000

Effective
Capacity

20

TAKT

16

(Slit Rolls/Hr)
Utilization

80%

Lead time

10 Min

Yield

100%

120

Utilization

60%

Lead time

8 Min

Yield

100%

Reliability

98%

UPtime

98%

# SKUs

2000

Batch size

1 Cut Roll

EPEI

7 days

C/O time

C/O loss

Avail time

168 hr/wk

Shift schd

3x8x7

3 M

7 Days
10 Min

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

200

TAKT

(Cut Rolls/Hr)

UNIVERSAL
CHOPPER
(1' - 6')

(2)

Effective
Capacity

8 Min

46

GEOGRAPHIC DEPICTION ON A VSM

SHEET
FORMING
(4)
6
Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%

CALENDARING
BONDING
(4)
6

SLITTING
(3)

ROLL
GOODS
STORAGE

Effective
Capacity

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

AUTOMATIC
STORAGE &
RETRIEVAL SYSTEM

10 Min

CHOPPING
(3)
5

Effective
Capacity

8.9

Effective
Capacity

29

TAKT

8.3

TAKT

24

(Master Rolls/Hr)
Utilization

93%

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

(Slit Rolls/Hr)
Utilization

83%

Lead time

10 Min

47

LOGICAL DEPICTION ON A VSM


THESE ARE ALL WITHIN THE SAME
PHYSICAL INVENTORY STORAGE AREA

SHEET
FORMING
6
(4)
Effective
Capacity

11.8

TAKT
9.5
(Master Rolls/Hr)
Utilization
80%
Lead time

15 Min

CALENDARING
BONDING
(4)
6
Invtry
Days
#
SKUs

1990
Rolls
10
50

Effective
Capacity

8.9

TAKT

8.3

(Master Rolls/Hr)
Utilization

93%

Lead time

17 Min

SLITTING
(3)
1380
Rolls

Invtry
Days

#
SKUs

200

Effective
Capacity

CHOPPING
(3)
5

10.3

TAKT
7.2
(Bonded Rolls/Hr)
Utilization
70%
Lead time

10 Min

Invtry

4000

Days

#
SKUs

1000

Effective
Capacity

29

TAKT

24

(Slit Rolls/Hr)
Utilization

83%

Lead time

10 Min

Yield

87%

Yield

87%

Reliability

90%

Yield

98%

Yield

100%

Reliability

98%

UPtime

73.6%

Reliability

95%

Reliability

98%

UPtime

61%

# SKUs

50

UPtime

69%

UPtime

98%

# SKUs

200

Batch size

1 roll

# SKUs

1000

# SKUs

1800

Batch size

1 roll

Batch size

1 roll

Batch size

1 Slit Roll

EPEI

7 days

EPEI

7 days

C/O time

1 hr

EPEI

7 days

EPEI

7 days

C/O time

45 Min

C/O loss

2 Rolls

C/O time

5 Min

C/O time

C/O loss

~0

Avail time

168 hr/wk

C/O loss

~0

C/O loss

Avail time

168 hr/wk

Shift schd

3x8x7

Avail time

168 hr/wk

Avail time

168 hr/wk

Shift schd

3x8x7

Shift schd

3x8x7

Shift schd

3x8x7

10 Days
15 Min

17 Min

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

3 M

7 Days

8 Days
10 Min

10 Min

48

SUMMARY
In order to become more lean, you must be able to see the waste in
your process
Value Stream Mapping is a proven, effective way to do that
A well constructed VSM will enable you to see the major wastes
And clues to their root cause

The VSM provides a template for all improvement activity

Using all planned improvements to build a Future State VSM


insures that all efforts are
Coordinated
Integrated
Moving you toward a more waste-free process

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

49

SUMMARY II

A VSM consists of three key components


Material flow (with data boxes)
Information flow
A timeline
Integrating material and information flow on the same diagram
highlights areas where mishandling of information inhibits smooth
flow and creates waste
Because most sources of waste add time to the process, the
timeline focuses attention on these wastes

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

50

TO LEARN MORE ..

The material in this


presentation is featured in

Productivity Press
May 2009

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

51

Questions?
peterking@LeanDynamics.us
(302) 239-1667
(302) 528-2700

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

52

Appendix 1
TAKT TIME & CYCLE TIME

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

53

TAKT and CYCLE TIME

Takt
A measure of the rate of customer demand
Takt in German means rhythm, or drum beat
Goal is to synchronize production to customer needs

Takt Time = Total available time / Customer demand


Units

Minutes (per car, per roll, per batch)


Also hours or seconds
A measure of how much time you have to produce a unit and meet
customer needs
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

54

TAKT and CYCLE TIME

Takt Time = Total available time / Customer demand


Available Time
The time you plan to run, the planned work schedule

Number of shifts
Hours per shift
Deduct time for lunch and breaks
If a plant runs 16 hours per day, 5 days each week, available time would
be 80 hours per week
If production suspends for an hour each shift for lunch and breaks,
available time is 70 hours per week
Do NOT deduct for equipment downtime
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

55

TAKT and CYCLE TIME

Takt Time = Total available time / Customer demand


Example
A lawnmower plant has weekly demand of 2000 for a certain model
Two eight-hour shifts per day, 5 days per week
Production continues through lunch, breaks, shift changes
Available time = 2 x 8 x 5 = 80 hours/week

Takt = 80 hours / 2000 = 2.4 minutes


So the plant must produce a completed mower every 2.4 minutes to
satisfy customer demand

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

56

TAKT and CYCLE TIME

Takt Time = Total available time / Customer demand


Takt must be increased to accommodate losses
If step 4 in the process has a 10% yield loss or scrap rate
Steps 1, 2, and 3 must produce at a Takt of 2.2 minutes to match
customer needs

Step 2

Step 3

Step 4

Step 5

Takt = 2.2 min

Takt = 2.2 min

Takt = 2.4 min*

Avail time = 80 hr/wk

Yield = 90%

Takt = 2.4 min

CUSTOMER
Customer demand
= 2000 mowers
per week

* Takt is measured in terms of good output


2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

57

TAKT and CYCLE TIME

Cycle Time
If Takt represents customer demand.
Our process must be able to produce within that time
Cycle Time measures how long it takes to produce one unit, one
lot, one batch, etc.
If Cycle Time < Takt, we can produce faster than customer needs
If the cycle time for step 3 in the lawnmower plant is 2 minutes,
we can produce faster than needed, with about 10% spare
capacity

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

58

TAKT and CYCLE TIME

Cycle Time = Reality


Cycle time does not represent the best we can expect from our
process or a specific step.
It represents what we should expect under normal conditions,
allowing for PMs, unexpected downtime, rate reductions, yield
losses, time for product changeovers, etc

Cycle Time = 1 / Max Demonstrated Rate (MDR) x OEE


Cycle Time = 1
Cycle Time = 1

/ (MDR

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

/ (MDR

x UPtime)

x % Reliability x % Rate x % Yield)

59

TAKT and CYCLE TIME

Utilization
A measure of how fully occupied a process step is, how busy it is

Utilization = Cycle Time/ Takt


If Step 3 in the mower plant has a cycle time of 2 minutes, and a
Takt of 2.2 minutes
Utilization = 91%
Utilization is an indication of where there are bottlenecks in process
flow

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

60

TAKT and CYCLE TIME

Takt as a Rate parameter


The units for Takt and cycle time can be awkward in a process
plant
0.6 seconds/gal vs 100 gal/min
0.15 secs/ft vs 400 feet/min

0.171 secs/bottle vs 350 bottle/min


Rate based parameters are often used instead of time based
units

Takt Time = Available time / Customer demand


Takt Rate = Customer demand/ Available time
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

61

TAKT and CYCLE TIME

Takt as a Rate parameter


As before, available time is the time we intend to run
= no of shifts x (hrs/shift lunch breaks)
In the lawnmower example, Takt rate for Step 5 = 25 mowers/hr
(= 2000 mowers/week / 80 hrs/week)
Takt rate is simply the reciprocal of Takt time

Takt Rate = Customer demand/ Available time

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

62

TAKT and CYCLE TIME

Effective Capacity
The reciprocal of Cycle Time is often called Effective Capacity
As before, it represents realistic expectations, not perfection

Cycle Time = 1 / Max Demonstrated Rate (MDR) x OEE


Effective Capacity = Max Demonstrated Rate (MDR) x OEE

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

63

TAKT and CYCLE TIME

Utilization
A measure of how fully occupied a process step is, how busy it is

Utilization = Takt rate/ Effective capacity


If Step 3 in the mower plant has an effective capacity of 30
parts/min, and a Takt of 27.3 parts/min
Utilization = 91%

Everything works out the same, its just easier for some
people to relate to rate based parameters
2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

64

TAKT and CYCLE TIME

Another example ~ Roll forming

Step 4

Step 5

Yield = 100%
Takt = 55 rolls/hr

Yield = 90%
Takt = 50 rolls/hr

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

Step 6
Avail time = 24 hr/day
Takt = 50 rolls/hr

CUSTOMER
Demand = 1200
rolls/day

65

TAKT and CYCLE TIME

Takt Rate = Customer demand/ Available time

If Available time changes, Takt changes

Step 4

Step 5

Step 6

Avail time = 16 hr/day


Yield = 100%
Takt = 83 rolls/hr

Avail time = 24 hr/day


Yield = 90%
Takt = 50 rolls/hr

Avail time = 24 hr/day


Takt = 50 rolls/hr

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

CUSTOMER
Demand = 1200
rolls/day

66

TAKT and CYCLE TIME

Utilization = Takt rate/ Effective capacity

Step 4

Step 5

Step 6

Avail time = 16 hr/day


Yield = 100%
Takt = 83 rolls/hr

Avail time = 24 hr/day


Yield = 90%
Takt = 50 rolls/hr

Avail time = 24 hr/day


Takt = 50 rolls/hr

MDR = 120 rolls/hr


OEE = 85%
Eff Capac = 102 rolls/hr
Util = 81%

MDR = 72 rolls/hr
OEE = 75%
Eff Capac = 54 rolls/hr
Util = 93%

MDR = 100 rolls/hr


OEE = 85%
Eff Capac = 85 rolls/hr
Util = 59%

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

CUSTOMER
Demand = 1200
rolls/day

67

TAKT and CYCLE TIME

To summarize

Cycle time or effective capacity is a measure of what we can expect from


each step in our process under normal operating conditions

Take time or take rate is what each step in the process must make to meet
customer demand

If cycle time and takt time for a process step are exactly equal, that step is
perfectly synchronized to customer needs

If cycle time exceeds takt, we have a bottleneck

If cycle time is less than takt, we have some degree of excess capacity (this
is desirable)

It is up to the user to decide whether time or rate parameters make


more sense

2009 - LEAN DYNAMICS LLC ALL RIGHTS RESERVED

68

S-ar putea să vă placă și