About this Document

This document is an integral part of the Departments planning documents, namely, the 5-Year Strategic Plan (2010/11 2014/15), the Annual
Performance Plan (APP), the Budget Statement II (Vote 1 in Provincial Treasurys White Book) and the Premiers 2013/14 Budget and Policy
Speech. The Operational Plan seeks to demonstrate how the Department intends to achieve its results as outlined by the performance
indicators and targets in the APP. The Operational Plan identifies critical projects, the amount of resources that have been earmarked for each
of these projects and a quarterly breakdown of the key activities that will be undertaken to achieve these projects. This plan is to be read in
conjunction with the above-mentioned documents. Every effort has been made to ensure that all result areas are addressed in the Operational
Plan. The Operational Plan is laid out in accordance with the Departments four Budget Programme and is owned by all Programme and SubProgramme Managers.

Table of Contents
About this Document........................................................................................................................................................................................................................ 1
Programme 1: Administration........................................................................................................................................................................................................... 7
Sub-Programme 1.1: Office of the Deputy Director General ....................................................................................................................................................... 7
Sub-Programme 1.2: Premiers Core Staff .................................................................................................................................................................................. 9
Sub-Programme 1.3: Office of the Director General .................................................................................................................................................................. 14
Sub-Programme 1.4: Strategic and Operational Support .......................................................................................................................................................... 21
Sub-Programme 1.5: Internal Human Resource Management ................................................................................................................................................. 28
Sub-Programme 1.6: Finance and Supply Chain Management ................................................................................................................................................ 36
Programme 2: Institutional Development and Organisational Support .......................................................................................................................................... 49
Sub-Programme 2.1: Office of the Deputy Director General ..................................................................................................................................................... 49
Sub-Programme 2.2: Transversal Organisational Development and Consultancy Services .................................................................................................... 51
Sub-Programme 2.3: Information Technology Management ..................................................................................................................................................... 68
Programme 3: Policy and Governance .......................................................................................................................................................................................... 73
Sub-Programme 3.1: Office of the Deputy Director General ..................................................................................................................................................... 73
Sub-Programme 3.2: Performance Monitoring and Evaluation ................................................................................................................................................. 75
Sub-Programme 3.3: Service Delivery Intervention and Co-ordination Support ....................................................................................................................... 88
Sub-Programme 3.4: Policy Planning and Research Co-ordination .......................................................................................................................................... 92
Programme 4: Executive Support Services ................................................................................................................................................................................... 99
Sub-Programme 4.1: Office of the Deputy Director General ..................................................................................................................................................... 99
Sub-Programme 4.2: Cabinet Secretariat and Protocol Services............................................................................................................................................ 102
Sub-Programme 4.3: Provincial Communication ..................................................................................................................................................................... 103
Sub-Programme 4.4: Intergovernmental and Stakeholder Relations ...................................................................................................................................... 112
Sub-Programme 4.5: Legal Services ....................................................................................................................................................................................... 115

Official Approval by Programme Managers


It is hereby certified that this Annual Operational Plan:
Was developed by the management of the Office of the Premier (OTP);
Takes into account all the relevant policies, legislation and other mandates for which the OTP is responsible;
Accurately reflects the strategic goals, objectives performance indicators and targets which the OTP will endeavour to achieve in the
2013/14 financial year.

Signed

Ms. N. Ngcakani
Programme Manager: Administration
Date: 25 March 2013

Ms. L. Geza
Programme Manager: IDOS
Date: 25 March 2013

Mr. C. Motsilili
Programme Manager: Policy and Governance
Date: 25 March 2013

Adv. H. Smith
Acting Programme Manager: Executive Support Services
Date: 25 March 2013

Programme 1: Administration
Sub-Programme 1.1: Office of the Deputy Director General
DIRECTORATE: DDGs OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R389 000

STRATEGIC OBJECTIVES
All strategic objectives applicable to Programme 1
PERFORMANCE INDICATORS
All performance indicators applicable to Programme 1
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate management meetings for


the programme and follow up decisions
thereof

Coordinate management meetings for


the programme and follow up decisions
thereof

Coordinate management meetings for


the programme and follow up decisions
thereof

Coordinate management meetings for


the programme and follow up decisions
thereof

Compile monthly reports and quarterly


reports for the programme and ensure
that there credible evidence associated
with all reported achievement

Compile monthly reports and quarterly


reports for the programme and ensure
that there credible evidence associated
with all reported achievement

Compile monthly reports and quarterly


reports for the programme and ensure
that there credible evidence associated
with all reported achievement

Compile monthly reports and quarterly


reports for the programme and ensure
that there credible evidence associated
with all reported achievement

Coordinate staff meetings and follow up


decisions thereof

Coordinate staff meetings and follow up


decisions thereof

Coordinate staff meetings and follow up


decisions thereof

Coordinate staff meetings and follow up


decisions thereof

Coordinate all planning activities for the


Programme and resulting in the
submission of draft programme APP and
budget.

Coordinate all planning activities for the


Programme and resulting in the
submission of the draft programme APP
and budget

Coordinate all planning activities for the


Programme and resulting in the
finalisation of the programme Plans
(APP, Operational Plan, Cash flows,
Procurement Plans)

Ensure all managers and staff in the


programme are evaluated through the
PMDS

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the first quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the second quarter)

Ensure that all SMS member have valid


performance agreements for the next
financial year

Ensure that all staff in the programme


have valid performance contracts for
2013/14 financial year

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the third quarter)

DIRECTORATE: DDGs OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R389 000

STRATEGIC OBJECTIVES
All strategic objectives applicable to Programme 1
PERFORMANCE INDICATORS
All performance indicators applicable to Programme 1
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Special Reports PCMT

Compile Special Reports PCMT

Compile Special Reports PCMT

Compile Special Reports PCMT

Correspondence Administration

Correspondence Administration

Correspondence Administration

Correspondence Administration

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Business change management plan


implemented.

Business change management plan


implemented.

Sub-Programme 1.2: Premiers Core Staff


CHIEF DIRECTORATE NAME: PREMIERS CORE STAFF

SECTION NAME: OFFICE OF THE CHIEF OF STAFF

PROJECT NAME: OVERALL MANAGEMENT OF THE PREMIERS OFFICE

BUDGET ALLOCATION: R5.96m

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATOR
1.1 Percentage of petition/complaints/ to the Premier resolved as part of the Departments efforts to promote and demonstrate good and responsive governance
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Manage the private office of the Premier

Manage the private office of the Premier

Manage the private office of the Premier

Manage the private office of the Premier

Coordinate and manage Premiers


engagements with Municipal Councils,
communities delegations and other
stakeholders

Coordinate and manage Premiers


engagements with Municipal Councils,
communities delegations and other
stakeholders

Coordinate and manage Premiers


engagements with Municipal Councils,
communities delegations and other
stakeholders

Coordinate and manage Premiers


engagements with Municipal Councils,
communities delegations and other
stakeholders

Coordinate Premier special visits to


communities, schools, hospitals, and
impromptu visits to other government
institutions

Coordinate Premier special visits to


communities, schools, hospitals, and
impromptu visits to other government
institutions

Coordinate Premier special visits to


communities, schools, hospitals, and
impromptu visits to other government
institutions

Coordinate Premier special visits to


communities, schools, hospitals, and
impromptu visits to other government
institutions

Facilitate Premiers Provincial outreach


programme

Facilitate Premiers Provincial outreach


programme

Facilitate Premiers Provincial outreach


programme

Facilitate Premiers Provincial outreach


programme

Manage Discretionary Fund

Manage Discretionary Fund

Manage Discretionary Fund

Manage Discretionary Fund

Advise Premier on Administrative


matters in the office

Advise Premier on Administrative


matters in the office

Advise Premier on Administrative


matters in the office

Advise Premier on Administrative


matters in the office

DIRECTORATE NAME: PREMIERS CORE STAFF

SECTION NAME: OFFICE OF THE SENIOR MANAGER

PROJECT NAME: EXECUTIVE MANAGEMENT & ADMINISTRATIVE SERVICES

BUDGET ALLOCATION: (covered in the R5.96m budget for the sub-programme)

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATOR
1.1 Percentage of petition/complaints/ to the Premier resolved as part of the Departments efforts to promote and demonstrate good and responsive governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Draft monthly analytical report on


petitions received and referred to
Departments/ Institutions

Draft analytical report on petitions


received and referred to Departments/
Institutions

Draft analytical report on petitions


received and referred to Departments/
Institutions

Draft analytical report on petitions


received and referred to Departments/
Institutions

Draft Quarterly report on success rate of


petitions responsiveness and success
rate per departments

Draft Quarterly report on success rate of


petitions responsiveness and success
rate per departments

Draft Quarterly report on success rate of


petitions responsiveness and success
rate per departments

Draft Quarterly report on success rate of


petitions responsiveness and success
rate per departments

Report on type of matters referred


including

Report on type of matters referred


including responsiveness and success
rate per departments

Report on type of matters referred


including responsiveness and success
rate per departments

Report on type of matters referred


including responsiveness and success
rate per departments

Manage quarterly programme of Premier


Diary Committee

Manage quarterly programme of Premier


Diary Committee

Manage quarterly programme of Premier


Diary Committee

Manage quarterly programme of Premier


Diary Committee

Manage procurement in relation to


procurement plan and cash flow
projections

Manage Finances in relation to


procurement plan and cash flow
projections

Manage Finances in relation to


procurement plan and cash flow
projections

Manage Finances in relation to


procurement plan and cash flow
projections

Quarterly Financial reconciliation


Reports on expenses and deviations

Quarterly Financial reconciliation


Reports on expenses and deviations

Quarterly Financial reconciliation


Reports on expenses and deviations

Quarterly Financial reconciliation


Reports on expenses and deviations

Leave reconciliation report

Leave reconciliation report

Leave reconciliation report

Leave reconciliation report

PMDS reports submitted

PMDS reports submitted

PMDS reports submitted

PMDS reports submitted

Coordinate training and development as


per PDPs

Coordinate training and development as


per PDPs

Coordinate training and development as


per PDPs

Coordinate training and development as


per PDPs

Management the implementation of


electronic and printed Media releases
and speeches

Management the implementation of


electronic and printed Media releases
and speeches

Management the implementation of


electronic and printed Media releases
and speeches

Management the implementation of


electronic and printed Media releases
and speeches

10

DIRECTORATE NAME: PREMIERS CORE STAFF

SECTION NAME: MEDIA LIAISON OFFICER

PROJECT NAME: RENDERING MEDIA LIAISON SERVICES

BUDGET ALLOCATION: (covered in the R5.96m budget for the sub-programme)

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATOR
Number of press releases, speeches and interaction with the printed and electronic media
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Prepare Speeches and speaking notes


for Premier

Prepare Speeches and speaking notes


for Premier

Prepare Speeches and speaking notes


for Premier

Prepare Speeches and speaking notes


for Premier

Draft and publish Premiers press


statements/ releases

Draft and publish Premiers press


statements/ releases

Draft and publish Premiers press


statements/ releases

Draft and publish Premiers press


statements/ releases

Prepare and implement media/


communications strategy in consultation
with role players

Prepare and implement media/


communications strategy in consultation
with all role players

Prepare and implement media/


communications strategy in consultation
with all role players

Prepare and implement media/


communications strategy in consultation
with all role players

Provide Premier with daily synopsis of


media reports on matters of importance

Provide Premier with daily synopsis of


media reports on matters of importance

Provide Premier with daily synopsis of


media reports on matters of importance

Provide Premier with daily synopsis of


media reports on matters of importance

Conduct research on topics to be


covered in Premiers speeches

Conduct research on topics to be


covered in Premiers speeches

Conduct research on topics to be


covered in Premiers speeches

Conduct research on topics to be


covered in Premiers speeches

Coordinate and liaise with the print and


electronic media houses regarding
Premiers responses/ interviews

Coordinate and liaise with the print and


electronic media houses regarding
Premiers responses/ interviews

Coordinate and liaise with the print and


electronic media houses regarding
Premiers responses/ interviews

Coordinate and liaise with the print and


electronic media houses regarding
Premiers responses/ interviews

Represent Core Staff at Provincial


Planning Sessions

Represent Core Staff at Provincial


Outreach Planning Sessions

Represent Core Staff at Provincial


Outreach Planning Sessions

Represent Core Staff at Provincial


Outreach Planning Sessions

Attend Government MLO Fora/


Workshops, both Provincial and National

Attend Government MLO Fora/


Workshops, both Provincial and national

Attend Government MLO Fora/


Workshops, both Provincial and national

Attend Government MLO Fora/


Workshops, both Provincial and national

11

DIRECTORATE NAME: PREMIERS CORE STAFF

SECTION NAME: PARLIAMENTARY LIAISON OFFICER

PROJECT NAME: PARLIAMENTARY LIAISON SERVICES

BUDGET ALLOCATION: (covered in the R5.96m budget for the sub-programme)

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATOR
Number of Parliamentary business and sittings attended, and number of Parliamentary questions responded to
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Manage Premiers attendance of


Legislature sittings

Manage Premiers attendance of


Legislature sittings

Manage Premiers attendance of


Legislature sittings

Manage Premiers attendance of


Legislature sittings

Manage the written and oral responses


of the Premier to legislature/
Parliamentary questions

Manage the written and oral responses


of the Premier to legislature/
Parliamentary questions

Manage the written and oral responses


of the Premier to legislature/
Parliamentary questions

Manage the written and oral responses


of the Premier to legislature/
Parliamentary questions

Facilitate Premiers attendance of


Legislature and Parliamentary Sittings

Facilitate Premiers attendance of


Legislature and Parliamentary Sittings

Facilitate Premiers attendance of


Legislature and Parliamentary Sittings

Facilitate Premiers attendance of


Legislature and Parliamentary Sittings

Liaise with the NCOP and facilitate


Premiers participation in NCOP debates
in consultation with the legislature

Liaise with the NCOP and facilitate


Premiers participation in NCOP debates
in consultation with the legislature

Liaise with the NCOP and facilitate


Premiers participation in NCOP debates
in consultation with the legislature

Liaise with the NCOP and facilitate


Premiers participation in NCOP debates
in consultation with the legislature

Coordinate and facilitate Premiers


interaction with her Constituency

Coordinate and facilitate Premiers


interaction with her Constituency

Coordinate and facilitate Premiers


interaction with her Constituency

Coordinate and facilitate Premiers


interaction with her Constituency

Liaise with and service Premiers


Constituency office on behalf of the
Premier

Liaise with and service Premiers


Constituency office on behalf of the
Premier

Liaise with and service Premiers


Constituency office on behalf of the
Premier

Liaise with and service Premiers


Constituency office on behalf of the
Premier

Attend PLO Fora, National and


Provincial Workshops & briefing
sessions

Attend PLO Fora, National and


Provincial Workshops & briefing
sessions

Attend PLO Fora, National and


Provincial Workshops & briefing
sessions

Attend PLO Fora, National and


Provincial Workshops & briefing
sessions

Attend Legislature Sittings

Attend Legislature Sittings

Attend Legislature Sittings

Attend Legislature Sittings

Facilitate submission of Policy Speech,


Budget Vote, Response to House
Resolutions Reports to the Legislature

Facilitate submission of Annual Report,


Response to House Resolutions Reports
to the Legislature

Facilitate submission of Financial


Oversight and to House Resolutions
Reports to the Legislature

Facilitate House Resolutions Reports to


the Legislature.

12

DIRECTORATE NAME: PREMIERS CORE STAFF

SECTION NAME: ADMINISTRATIVE SECRETARY

PROJECT NAME: ADMINISTRATIVE SERVICES - REGISTRY

BUDGET ALLOCATION: (covered in the R5.96m budget for the sub-programme)

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATOR
1.1 Percentage of petition/complaints/ to the Premier resolved as part of the Departments efforts to promote and demonstrate good and responsive governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Receive and file correspondence

Receive and file correspondence

Receive and file correspondence

Receive and file correspondence

Attend weekly correspondence


committee meetings

Attend weekly correspondence


committee meetings

Attend weekly correspondence


committee meetings

Attend weekly correspondence


committee meetings

Compile weekly correspondence reports


for Premier

Compile weekly correspondence reports


for Premier

Compile weekly correspondence reports


for Premier

Compile weekly correspondence reports


for Premier

Daily capturing and updating database


and filing system

Daily capturing and updating database


and filing system

Daily capturing and updating database


and filing system

Daily capturing and updating database


and filing system

Draft monthly analytical report of


petitions received and referred per
Department/ Institutions

Draft monthly analytical report of


petitions received and referred per
Department/ Institutions

Draft monthly analytical report of


petitions received and referred per
Department/ Institutions

Draft monthly analytical report of


petitions received and referred per
Department/ Institutions

Draft Quarterly analytical report on


departmental/ institutional
responsiveness and success rate per on
addressing and solving petitions

Draft Quarterly analytical report on


departmental/ institutional
responsiveness and success rate per on
addressing and solving petitions

Draft Quarterly analytical report on


departmental/ institutional
responsiveness and success rate per on
addressing and solving petitions

Draft Quarterly analytical report on


departmental/ institutional
responsiveness and success rate per on
addressing and solving petitions

Follow-up on matters referred


(compile lists of outstanding matters)

Follow-up on matters referred


(compile lists of outstanding matters)

Follow-up on matters referred


(compile lists of outstanding matters)

Follow-up on matters referred


(compile lists of outstanding matters)

13

Sub-Programme 1.3: Office of the Director General


CHIEF DIRECTORATE NAME: DGs OFFICE

SECTION NAME: N/A

PROJECT NAMES
MONITORING THE IMPLEMENTATION OF THE OTP PROGRAMMES
PROVISION OF STRATEGIC SUPPORT & LEADERSHIP TO
DEPARTMENTS

BUDGET ALLOCATION: R494 900

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATORS
1.2 Number of management reports on implementation of OTP programmes to monitor the performance of the Department; and
1.3 Percentage of challenges from departments escalated to the Director Generals Office resolved.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Establishment of governance
/management structures, and
development of ToRs thereof, for the
OTP, e.g., Audit Committee, Risk
Management Committee, HRM
Committees, MPAT Committee, ICT
Governance Steering Committee, PMDS
Moderation Committees, Social
Committees, Audit Steering Committee,
Appeals Committee, etc.

Monitor the operations of the OTP


Governance Structures.

Monitor the operations of the OTP


Governance Structures.

Co-ordination of monthly
Management Reports

Co-ordination of monthly
Management Reports

Executive

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Oversee development and submission
of departmental compliance and
statutory plans for 2014/15 across
programmes.
Evaluate and review the OTP
Governance Structures.

Executive

Co-ordination of monthly
Management Reports

Executive

Co-ordination of monthly Executive


Management Reports

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Departments
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Departments
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Departments
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Departments
Management.

Facilitate one-on-one performance


reporting sessions with programmes and
sub-programmes.

Facilitate one-on-one performance


reporting sessions with programmes and
sub-programmes.

Facilitate one-on-one performance


reporting sessions with programmes and
sub-programmes.

Facilitate one-on-one performance


reporting sessions with programmes and
sub-programmes.

Monitor implementation of intervention


measures to improve performance in

Monitor implementation of intervention


measures to improve performance in

Monitor implementation of intervention


measures to improve performance in

Monitor implementation of intervention


measures to improve performance in

14

CHIEF DIRECTORATE NAME: DGs OFFICE

SECTION NAME: N/A

PROJECT NAMES
MONITORING THE IMPLEMENTATION OF THE OTP PROGRAMMES
PROVISION OF STRATEGIC SUPPORT & LEADERSHIP TO
DEPARTMENTS

BUDGET ALLOCATION: R494 900

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and Provincial administration
PERFORMANCE INDICATORS
1.2 Number of management reports on implementation of OTP programmes to monitor the performance of the Department; and
1.3 Percentage of challenges from departments escalated to the Director Generals Office resolved.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

identified sub-programmes.

identified sub-programmes.

identified sub-programmes.

identified sub-programmes.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Provincial
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Provincial
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Provincial
Management.

Monitor and report on the progress


made on implementing resolutions and
decisions taken by the Provincial
Management.

Facilitate one-on-one support sessions


with identified departments to address
their specific challenges.

Facilitate one-on-one support sessions


with identified departments to address
their specific challenges.

Facilitate one-on-one support sessions


with identified departments to address
their specific challenges.

Facilitate one-on-one support sessions


with identified departments to address
their specific challenges.

15

DIRECTORATE NAME: INTERNAL AUDIT

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF THE ANNUAL INTERNAL AUDIT PLAN

BUDGET ALLOCATION: R2.53m

STRATEGIC OBJECTIVE: To provide an independent, objective assurance and consulting internal audit activity designed to add value and improve departments
operations
PERFORMANCE INDICATORS
1.5 Number of audit projects completed as part of the implementation of the internal audit plan;
1.6 Number of monthly monitoring reports of the audit intervention plan to ensure that deficiencies in the internal control environment are addressed; and
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Quarterly monitoring of the


implementation of the Internal Audit
Plan.

Quarterly monitoring of the


implementation of the Internal Audit
Plan.

Quarterly monitoring of the


implementation of the Internal Audit
Plan.

Development of the annual internal audit


plan.

Monitor and report on the


implementation of the departmental
Audit Intervention Plan.

Monitor and report on the


implementation of the departmental
Audit Intervention Plan.

Monitor and report on the


implementation of the departmental
Audit Intervention Plan.

Quarterly monitoring of the


implementation of the Internal Audit
Plan.

Monitor and report on the key control


environment.

Monitor and report on the key control


environment.

Monitor and report on the key control


environment.

Monitor and report on the


implementation of the departmental
Audit Intervention Plan.

Facilitate the sittings of the Audit


Committee meetings.

Facilitate the sittings of the Audit


Committee meetings.

Facilitate the sittings of the Audit


Committee meetings.

Monitor and report on the key control


environment.

Guide the department on the


remuneration of the Audit Committee
members.

Facilitate the sittings of the Audit


Committee meetings.

16

DIRECTORATE NAME: RISK MANAGEMENT

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF THE RISK MANAGEMENT STRATEGY

BUDGET ALLOCATION: R166 000

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATORS
1.4 Level of implementation of the approved Risk Management Strategy to organisational integrity; and
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

MANAGEMENT OF RISK STRUCTURES


Facilitate Risk Management Committee
Meeting

Facilitate Risk Management Committee


Meeting

Facilitate Risk Management Committee


Meeting

Facilitate Risk Management Committee


Meeting

Quarterly reports to Risk Management


Committee

Quarterly reports to Risk Management


Committee

Quarterly reports to Risk Management


Committee

Quarterly reports to Risk Management


Committee

Quarterly reports to Audit Committee

Quarterly reports to Audit Committee

Quarterly reports to Audit Committee

Quarterly reports to Audit Committee

Presentation of Risk Management


Status to the departmental management
structures

Presentation of Risk Management


Status to the departmental management
structures

Presentation of Risk Management


Status to the departmental management
structures

Presentation of Risk Management


Status to the departmental management
structures.

Facilitate Appointment of Risk


Committee Members.

Facilitate Appointment of Risk


Champions

RISK IDENTIFICATION AND ASSESSMENT


-

Facilitate risk assessments workshops

Approved Risk register

Monitor the implementation of risk


mitigation plans

Monitor the implementation of risk


mitigation plans

Monitor the implementation of risk


mitigation plans

Conduct Training and awareness


session on ERM

Conduct Training and awareness


session on ERM

Post articles on OTP plasma screens

Post articles on OTP plasma screens

RISK MITIGATION MONITORING


Monitor the implementation of risk
mitigation plans

IMPLEMENTATION OF THE AWARENESS PROGRAMME


Conduct Training and awareness
session on ERM

Conduct Training and awareness


session on ERM

Post articles on OTP plasma screens

Post articles on OTP plasma screens

17

DIRECTORATE NAME: RISK MANAGEMENT

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF THE RISK MANAGEMENT STRATEGY

BUDGET ALLOCATION: R166 000

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATORS
1.4 Level of implementation of the approved Risk Management Strategy to organisational integrity; and
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

ANNUAL REVIEW OF THE RISK MANAGEMENT STRATEGY


-

Detailed analysis of existing policies

Align with current requirements, e.g.


Treasury, governance developments,
etc.

Solicit management inputs

Submit and present to applicable


governance structures for approval

Approved Risk Management Strategy

18

DIRECTORATE NAME: ANTI-CORRUPTION & SECURITY MANAGEMENT

SECTION NAME: PROVINCIAL ANTI-CORRUPTION AND ETHICS

PROJECT NAMES
BUDGET ALLOCATION: R1 MILLION

OUTSOURCING OF THE CASE BACKLOG


INCREASING AWARENESS ON ANTI-CORRUPTION ACTIVITIES

STRATEGIC OBJECTIVE: Effectively coordinate efforts aimed at preventing, combating fraud and corruption focusing in transforming the culture of the provincial public
service to promote professionalism and sound ethics
PERFORMANCE INDICATORS
1.7 Percentage of backlog case investigations on fraud and corruption completed;
1.8 Number of Departments coordinated and supported in the implementation of security management policies;
1.17 Number of SMS disclosing their financial interests by 30 April 2013; and
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Facilitation of the tender process for the


outsourcing of case backlog

Investigation and monitoring thereof

Investigation and monitoring thereof

Investigation and monitoring thereof

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

3 departments. i.e. Health, Social


Development & Special Programmes
and Human Settlement monitored to
implement Fraud Prevention Plans

3 departments. i.e. Office of the Premier,


Transport and Provincial Treasury &
Planning monitored to implement Fraud
Prevention Plans

3 departments. i.e. Safety & Liaison,


Roads & Public Works, Rural
Development & Agrarian Reform
monitored to implement Fraud
Prevention Plans

4 departments. i.e. Education, Economic


Development & Tourism, Local
Government & Traditional Affairs
monitored to implement Fraud
Prevention Plans

1 District Municipality - [Chris Hani]


assisted with Fraud Risk Assessments
and Awareness sessions:

1 District Municipality [Cacadu DM]


assisted with Fraud Risk Assessments
and Awareness sessions

1 District Municipality [Nelson Mandela


Bay Metro] assisted with Fraud Risk
Assessments and Awareness sessions

1 District Municipality- [Buffalo City


Metro] assisted with Fraud Risk
Assessments and Awareness sessions

Verification and analysis of financial


disclosure submissions by SMS
members in the OTP.

Reporting to oversight bodies

19

DIRECTORATE NAME: ANTI-CORRUPTION AND SECURITY MANAGEMENT

SECTION NAME: PROVINCIAL SECURITY MANAGEMENT SERVICES

PROJECT NAME: IMPLEMENTATION OF THE MISS

BUDGET ALLOCATION: (included in the R1m under Anti-Corruption Projects)

STRATEGIC OBJECTIVE: Effectively coordinate efforts aimed at preventing, combating fraud and corruption focusing in transforming the culture of the provincial public
service to promote professionalism and sound ethics
PERFORMANCE INDICATORS
1.8 Number of Departments coordinated and supported in the implementation of security management policies
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

1 Security Awareness Workshop in


Cacadu District (departments within the
District).

1 Security Awareness Workshop Joe


Gabi District: departments within the
District).

1 Security Awareness Workshop in


Amathole District: departments within
the District).

1 Security Awareness Workshop I OR


Tambo District: departments within the
District).

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly reports to oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

Quarterly meetings with oversight bodies

Coordination of implementation of
Security Policies in 2 (Human
Settlement) and Safety and Liaison)
departments.

Coordination of implementation of
Security Policies in 2 (Provincial
Planning and Finance and Local
Government and Traditional Affairs)
departments.

Coordination of implementation of
Security Policies in 2 (Economic
Development and Roads and Public
Works) departments.

Coordination of implementation of
Security Policies in 2 (Health and Social
Development) departments.

Quarterly reports on the implementation


of, and compliance with, the MISS
handbooks by departments.

Quarterly reports on the implementation


of, and compliance with, the MISS
handbooks by departments

Quarterly reports on the implementation


of, and compliance with, the MISS
handbooks by departments

Quarterly reports on the implementation


of, and compliance with, the MISS
handbooks by departments

Office of the Premier assisted to review


Security Management Policy

Department of Roads and Public Works


assisted to review Security Management
Policy

Department of Transport assisted to


review Security Management Policy

Department of Local Government and


Traditional Affairs assisted to review
Security Management Policy

20

Sub-Programme 1.4: Strategic and Operational Support


DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: PLANNING, INSTITUTIONAL MONITORING & EVALUATION

PROJECT NAME: IMPROVEMENT OF MANAGEMENT OF PERFORMANCE


INFORMATION

BUDGET ALLOCATION: R400 000

STRATEGIC OBJECTIVES: Provide strategic leadership and support to the department and provincial administration
PERFORMANCE INDICATORS
1.9 Organisational self-assessment conducted to provide a critical lessons to inform the Departments strategy;
1.10 Number of departmental plans approved for tabling to parliament and/or presented to the Portfolio committee to allow parliament to exercise its oversight role on the
Department; and
1.11 Number of Departmental performance reports approved for tabling to parliament and/or presented to the Provincial Treasury to allow these institutions to exercise their
oversight roles on the Department.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Organise a pre-planning session to


develop a Planning Process Plan for the
2014/15 financial year

Develop and submit the First Draft of the


2014/15 Annual Performance Plan

Development of Operational Plans for


the Department and a Service Delivery
Improvement Plan for the Department

Finalisation of APP, Service Delivery


Improvement Plan, Operational Plans
and costed Monthly Activity Plan; and
quality assurance of the inputs into the
Budget Statement II

Develop and seek approval of the Policy


and Procedures for the Management of
Performance Information

Conduct organisational assessment for


the Department (MPAT assessment)

Collate and submit inputs to the Budget


Statement II

Update and submission of the Second


Draft of the Annual Performance Plans

Compile, validate, quality assure and


submit the Fourth Quarter Performance
Report to the Provincial and present the
report to Top Management

Compile, validate, quality assure and


submit the First Quarter Performance
Report to the Provincial and present the
report to Top Management

Compile, validate, quality assure and


submit the Second Quarter Performance
Report to the Provincial and present the
report to Top Management

Compile, validate, quality assure and


submit the Third Quarter Performance
Report to the Provincial and present the
report to Top Management

Compile, validate, quality assure and


present the 2012/13 Annual Report to
Management and submit the to the
Auditor General

Facilitate and support the process of


audit of performance information by the
Auditor General.

Compile, validate, quality assure and


present the 2013/14 Financial and

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Print and submit the 2012/13 Annual

21

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: PLANNING, INSTITUTIONAL MONITORING & EVALUATION

PROJECT NAME: IMPROVEMENT OF MANAGEMENT OF PERFORMANCE


INFORMATION

BUDGET ALLOCATION: R400 000

STRATEGIC OBJECTIVES: Provide strategic leadership and support to the department and provincial administration
PERFORMANCE INDICATORS
1.9 Organisational self-assessment conducted to provide a critical lessons to inform the Departments strategy;
1.10 Number of departmental plans approved for tabling to parliament and/or presented to the Portfolio committee to allow parliament to exercise its oversight role on the
Department; and
1.11 Number of Departmental performance reports approved for tabling to parliament and/or presented to the Provincial Treasury to allow these institutions to exercise their
oversight roles on the Department.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Report to the Provincial Legislature

Performance Oversight Report to


Management and submit the report to
the Provincial Legislature

22

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: KNOWLEDGE & RECORDS MANAGEMENT

PROJECT NAME: OPERATION TIDY UP FILES

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATOR
1.12 Percentage of documents retrieved and submitted to the requester within two working days of the request being made
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Sorting out documents at Finance strong


room (ground floor) and DG and DDGs
nd
strong room (2 floor) and ensuring that
there are no files exceeding 3cm as
required by Provincial Archives

Sorting out documents at Cabinet


nd
Secretariat strong room (2 floor) and
ensuring that there are no files
exceeding 3cm as required by Provincial
Archives

Sorting out documents at Salaries room


0070 (ground floor) accordingly and
documents that were transferred to
State house from Inyathi boardroom
ECDC building and ensuring that there
are no files exceeding 3cm as required
by Provincial Archives

Records Management Support Services

Records Management Support Services

Records Management Support Services

Records Management Support Services

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Finance records, that was
issued by Provincial Archives

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Cabinet Secretariat Strong
records, that was issued by Provincial
Archives

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Cabinet Secretariat Strong
records, that was issued by Provincial
Archives

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Cabinet Secretariat Strong
records, that was issued by Provincial
Archives

Replacing files that are damages


through handling by the correct files

Replacing files that are damages


through handling by the correct files

Replacing files that are damages


through handling by the correct files

Replacing files that are damages


through handling by the correct files

Sorting-out documents at Department of


Sports, Recreation, Arts and Culture to
create space for the disposal of Records
that have reached their retention date

Sorting-out documents at Department of


Sports, Recreation, Arts and Culture to
create space for the disposal of Records
that have reached their retention date

Sorting-out documents at Department of


Sports, Recreation, Arts and Culture to
create space for the disposal of Records
that have reached their retention date

Sorting-out documents at Department of


Sports, Recreation, Arts and Culture to
create space for the disposal of Records
that have reached their retention date

Apply for disposal of Finance records to


the Department of Sports recreation Arts
and culture

Ordering of correct required files and file


boxes for storing documents from Tidy
Files

Ordering of correct required files and file


boxes for storing documents from Tidy
Files

Ordering of correct required files and file


boxes for storing documents from Tidy
Files

Request for a car with relevant capacity


to transport identified documents for
OTP ECDC Building to Department of
Sports, Recreation, Arts and Culture

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Finance Records, that was
issued by Provincial Archives

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Finance Records, that was
issued by Provincial Archives

Listing all documents that are ready for


disposal according to Directive DD3Disposal of Finance Records, that was
issued by Provincial Archives

Moving documents for disposal

Replacing files that are damages

Replacing files that are damages

Replacing files that are damages

23

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: KNOWLEDGE & RECORDS MANAGEMENT

PROJECT NAME: OPERATION TIDY UP FILES

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATOR
1.12 Percentage of documents retrieved and submitted to the requester within two working days of the request being made
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

/Destruction Certificate from OTP ECDC


building to the Department of Sports,
Recreation, Arts and Culture for
disposal/Destruction

through handling by the correct files

through handling by the correct files

through handling by the correct files

Memo to the OTP finance unit to confirm


the identified document for destruction

Ensuring that there are no files that


exceeds 3cm as required by NARS

Ensuring that there are no files that


exceeds 3cm as required by NARS

Ensuring that there are no files that


exceeds 3cm as required by NARS

Disposal of OTP Finance Records

Disposal of OTP Records at Cabinet


Secretariat Strong room

Disposal of OTP Records at Salaries


room 0070 and Documents at State
house

Records Management Support Services

Records Management Support Services

Render Records Management Support


Services

Render Records Management Support


Services

Liaise with Facilities management to get


the building plan

Check the availability of the budget

Liaise with Public works to estimate the


duration for this project

Get quotes from service providers for


the recommended infrastructure and
submit request to management for
appraisal

24

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: KNOWLEDGE & RECORDS MANAGEMENT

PROJECT NAME: SETTING THE RECORD STRAIGHT! & IMPLEMENTATION


OF RECORDS MANAGEMENT PLAN

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATOR
1.12 Percentage of documents retrieved and submitted to the requester within two working days of the request being made
Summary of Planned
Quarter 1 Activities

Summary of Planned
Quarter 2 Activities

Summary of Planned
Quarter 3 Activities

Summary of Planned
Quarter 4 Activities

Going through HR staff files to ensure


adherence to National Minimum
Information Requirements (NMIR)

Going through HR staff files to ensure


adherence to National Minimum
Information Requirements (NMIR)

Develop a schedule for Records


Management Awareness sessions

Conducting Records Management


Awareness sessions

Implementing Records Management


Plan

Operationalizing Records management


plan and giving support

Develop a schedule for Records


Management Implementation plan

Conducting Records management


Workshops

25

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: DEPARTMENTAL INFORMATION TECHNOLOGY SERVICES

PROJECTS

BUDGET ALLOCATIONS

MANAGING PRINTING SERVICES CONTRACTORS


MANAGING MICROSOFT ADMINISTRATION AND LICENCES
MANAGING DEPARTMENTAL TELEPHONE MANAGEMENT SYSTEM
PROVISION OF COMPUTER CONSUMABLES
MANAGING OUTSOURCED SERVICES

R3 250 000
R980 000
R4 301 000
R374 000
R911 000

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and provincial administration
PERFORMANCE INDICATOR/S: N/A
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Ensure that printing services for the


department is in place for efficient
service delivery.

Monitor that printing services for the


department is available and that there is
minimum interruptions to enhance
efficient service delivery.

Continue ensuring that printing services


for the department is available and that
there are minimum interruptions to
enhance efficient service delivery.

Continue ensuring that printing services


for the department is available and that
there are minimum interruptions to
enhance efficient service delivery.

Ensure that all Microsoft services are


available to the department by
contracting Microsoft specialists.

Monitor and ensure that Microsoft


services are such as outlook for e-mails
are available at all times.

Implementation of Mimecast solution


linked to Microsoft e-mail server to
ensure availability of e-mails at all times.

Continue monitoring Mimecast solution


for the availability of e-mails at all time
and escalate any problems encountered.

Procure ICT equipment for the


implementation of IPT solution in all
OTP sites.

Implement IPT solution in all OTP sites


in order to save on departmental
telephone costs

Monitor the effectiveness of the IPT


solution and pull out reports on costs
saved by the department.

Continue monitoring the effectiveness of


the IPT solution and pull out reports on
costs saved by the department.

Ensure that computer consumables and


ICT equipment is in place for efficient
service delivery.

Continue ensuring that computer


consumables and ICT equipment is in
place for efficient service delivery.

Continue ensuring that computer


consumables and ICT equipment is in
place for efficient service delivery.

Continue ensuring that computer


consumables and ICT equipment is in
place for efficient service delivery.

Ensure that service desk solution is in


place, manage and monitor all logged
calls and submit monthly reports to the
management.

Continue ensuring that service desk


solution is in place, manage and monitor
all logged calls and submit monthly
reports to the management.

Continue ensuring that service desk


solution is in place, manage and monitor
all logged calls and submit monthly
reports to the management.

Continue ensuring that service desk


solution is in place, manage and monitor
all logged calls and submit monthly
reports to the management.

26

DIRECTORATE NAME: STRATEGIC MANAGEMENT

SECTION NAME: FACILITIES MANAGEMENT

PROJECTS
ANNUAL REVIEW OF DEPARTMENTAL U-AMP;
CONTRACT MANAGEMENT (CLEANING & PLANS);
FACILITATION OF FACILITY MAINTENANCE

BUDGET ALLOCATIONS: R1.2m

STRATEGIC OBJECTIVE: Provide strategic leadership and support to the department and provincial administration
PERFORMANCE INDICATOR
1.13 Review and approval of the User Asset Management Plan (U-AMP) of the Department to ensure that the Departments infrastructural needs are catered for in its
strategy
Summary of Planned
Quarter 1 Activities

Summary of Planned
Quarter 2 Activities

Summary of Planned
Quarter 3 Activities

Summary of Planned
Quarter 4 Activities

Review of departmental U-AMP

Finalisation of the U-AMP

Monitoring and managing the day to day


facilities requirements for the
Department

Monitoring and managing the day to day


facilities requirements for the
Department

Monitoring and managing the day to day


facilities requirements for the
Department

Monitoring and managing the day to day


facilities requirements for the
Department

Monitoring and quality assurance of


service rendered on cleaning, plants,
and facilities maintenance contracts

Monitoring and quality assurance of


service rendered on cleaning, plants,
and facilities maintenance contracts

Monitoring and quality assurance of


service rendered on cleaning, plants,
and facilities maintenance contracts

Monitoring and quality assurance of


service rendered on cleaning, plants,
and facilities maintenance contracts

27

Sub-Programme 1.5: Internal Human Resource Management


DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT

SECTION NAME: HUMAN RESOURCE ADMINISTRATION

PROJECT NAME: RECRUITMENT AND MANAGEMENT OF PROBATIONARY


APPOINTMENTS

BUDGET ALLOCATION: R766 000

STRATEGIC OBJECTIVES: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014; Build a people
focused organisation; and ensure that institutions of the state are reflective of the demographics of society; and effectively coordinate and build capacity of the public sector
towards social and institutional transformation.
PERFORMANCE INDICATORS
1.15 Average number of days taken to fill a post from the date when approval was granted to fill the post;
116 Percentage of employees serving probation confirmed/or not confirmed (that is, where a review has conducted and the employee has not satisfied the obligations of
his/her duty) in the 13th month of them assuming duty in the Department;
1.25 Percentage of women in senior management position in the Department; and
1.26 Percentage of employees who are in the category of people with disability.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Approved Annual Recruitment plan for


13/14. Monitor and report on personnel
turnover to top Management for
prioritisation of natural attrition posts.

Approved Annual Recruitment plan for


13/14. Monitor and report on personnel
turnover to top Management for
prioritisation of natural attrition posts.

Approved Annual Recruitment plan for


13/14. Monitor and report on personnel
turnover to top Management for
prioritisation of natural attrition posts.

Obtain prioritised post for 14/15 and


prepare draft annual recruitment plan for
14/15 and present to top management
and PCMT. Monitor and report on
personnel turnover to top Management
for prioritisation of natural attrition posts.

Analyse the Persal Data on probationary


appointments and verify actual number
of employees on 12 month probation
and put an action plan in place to clean
old probationary cases.

Obtain quarterly probation forms and


update Persal. Provide report on
outstanding probation reviews to be
conducted and action plans on any
probation cases that could not be
confirmed.

Obtain quarterly probation forms and


update Persal. Provide report on
outstanding probation reviews to be
conducted and action plans on any
probation cases that could not be
confirmed.

Obtain quarterly probation forms and


update Persal. Provide report on
outstanding probation reviews to be
conducted and action plans on any
probation cases that could not be
confirmed.

Employment equity plan reviewed and


approved. Employment equity
committee to meet on a quarterly basis.
Monthly monitoring and reporting on
employment equity reports submitted to
Top Management.

Prepare and submit the EEA 2 and EEA


4 reports for submission to the DPSA by
30 September 2013. Employment equity
committee to meet on a quarterly basis.
Monthly monitoring and reporting on
employment equity reports submitted to

Employment equity committee to meet


on a quarterly basis. Monthly monitoring
and reporting on employment equity
reports submitted to Top Management.

Employment equity committee to meet


on a quarterly basis. Monthly monitoring
and reporting on employment equity
reports submitted to Top Management.

28

DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT

SECTION NAME: HUMAN RESOURCE ADMINISTRATION

PROJECT NAME: RECRUITMENT AND MANAGEMENT OF PROBATIONARY


APPOINTMENTS

BUDGET ALLOCATION: R766 000

STRATEGIC OBJECTIVES: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014; Build a people
focused organisation; and ensure that institutions of the state are reflective of the demographics of society; and effectively coordinate and build capacity of the public sector
towards social and institutional transformation.
PERFORMANCE INDICATORS
1.15 Average number of days taken to fill a post from the date when approval was granted to fill the post;
116 Percentage of employees serving probation confirmed/or not confirmed (that is, where a review has conducted and the employee has not satisfied the obligations of
his/her duty) in the 13th month of them assuming duty in the Department;
1.25 Percentage of women in senior management position in the Department; and
1.26 Percentage of employees who are in the category of people with disability.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Top Management.

29

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

SECTION NAME: PERFORMANCE MGT, DEVELOPMENT & EMPLOYEE


WELLNESS

DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT


PROJECT NAMES
TRAINING AND DEVELOPMENT
MANAGEMENT OF BURSARIES
LEAVE MANAGEMENT

BUDGET ALLOCATION: R200 000

STRATEGIC OBJECTIVES
Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014;
Build a people focused organisation; and ensure that institutions of the state are reflective of the demographics of society; and
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATORS
1.18 Number staff trained as part of the implementation of the HRD policy of the Department;
1.19 Percentage of staff awarded with bursaries successfully completing their programmes on time; and
1.22 Percentage of leave captured on PERSAL within 30 days from the date when the leave was approved.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Submit HRD implementation plan to


st
DPSA by 31 April 2013. Develop Work
place skills plan (WSP). Submit WSP to
PSETA by 30 June 2013. Summit
annual training report for 12/13 to
PSETA attached to the WSP of 13/14.

Implementation of the Work place Skills


plan. Submit monitoring and evaluation
report on the HRD implementation plan
to DPSA. Expenditure report on training
in line with WSP submitted to PSETA.

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES
Implementation of the Work place Skills
plan. Expenditure report on training in
line with WSP submitted to PSETA.

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Implementation of the Work place Skills
plan. Submit monitoring and evaluation
report on the HRD implementation plan
to DPSA. Expenditure report on training
in line with WSP submitted to PSETA.

Advertise bursaries according to the


skills need in OTP in line with the
Strategic Objectives of department and
bursary policy. 2. Award bursaries to
eligible approved employees. 3. Ensure
payment to institutions.

Obtain progress reports from bursaries


and prepare and submit report to
Management on the bursary status.

Obtain progress reports from bursaries


and prepare and submit report to
Management on the bursary status.

Obtain progress reports from bursaries


and prepare and submit report to
Management on the bursary status.

Obtain monthly leave report from each


component. Submission of quarter 4
leave reconciliation for 12/13 fin year.

Obtain monthly leave report from each


component. Submission of quarter 1
leave reconciliation for 13/14 fin year.

Obtain monthly leave report from each


component. Submission of quarter 2
leave reconciliation for 13/14 fin year.

Obtain monthly leave report from each


component. Submission of quarter 3
leave reconciliation for 13/14 fin year.

30

DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT

SECTION NAME: PERFORMANCE MGT, DEVELOPMENT & EMPLOYEE


WELLNESS

PROJECT NAME: EMPLOYEE WELLNESS

BUDGET ALLOCATION: R685 000

STRATEGIC OBJECTIVES
Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014;
Build a people focused organisation; and ensure that institutions of the state are reflective of the demographics of society; and
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
1.24 Level of implementation of the Provincial Wellness Strategy as part of governments strategy to transform the public service and enhance service delivery
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Conduct an organisational assessment


of readiness for implementation of the
Provincial Wellness Strategy and
present analysis of the assessment
report to Top management.

Develop the Departmental Wellness


Policy

Obtain approval of draft Wellness policy

Roll out and implementation of the


Employee Wellness policy.

Implementation of Health and


Productivity Management.

Implementation of Health and


Productivity Management.

Implementation of Health and


Productivity Management.

Implementation of Health and


Productivity Management.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Analysis of Wellness Management


reports and submission to Top
Management

Analysis of Wellness Management


reports and submission to Top
Management. 4. HIV/Aids and TB status
report to Top Management.

HIV/Aids and TB status report to Top


Management

Prepare and submit annual employee


wellness report to Provincial
Organisational Wellness Support.

Obtain approval of draft Wellness policy.

Roll out and implementation of the


Employee Wellness policy.

Analysis of Wellness Management


reports and submission to Top
Management.
HIV/Aids and TB status report to Top
Management
Conduct an organisational assessment
of readiness for implementation of the
Provincial Wellness Strategy and
present analysis of the assessment
report to Top management.

Analysis of Wellness Management


reports and submission to Top
Management.
HIV/Aids and TB status report to Top
Management
Develop the Departmental Wellness
Policy.

31

DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT

SECTION NAME: PERFORMANCE MGT, DEVELOPMENT & EMPLOYEE


WELLNESS

PROJECT NAME: EMPLOYEE WELLNESS

BUDGET ALLOCATION: R685 000

STRATEGIC OBJECTIVES
Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014;
Build a people focused organisation; and ensure that institutions of the state are reflective of the demographics of society; and
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
1.24 Level of implementation of the Provincial Wellness Strategy as part of governments strategy to transform the public service and enhance service delivery
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Implementation of Health and
Productivity Management.

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Implementation of Health and


Productivity Management.

Implementation of Health and


Productivity Management.

Implementation of Health and


Productivity Management.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Implementation of SHERQ and


submission of report to Provincial
Organisational and Employee Wellness
support.

Analysis of Wellness Management


reports and submission to Top
Management.

Analysis of Wellness Management


reports and submission to Top
Management.

Analysis of Wellness Management


reports and submission to Top
Management.

Prepare and submit annual employee


wellness report to Provincial
Organisational Wellness Support.

HIV/Aids and TB status report to Top


Management.

HIV/Aids and TB status report to Top


Management

HIV/Aids and TB status report to Top


Management.

HIV/Aids and TB status report to Top


Management.

32

Analysis of Wellness Management


reports and submission to Top
Management.

DIRECTORATE NAME: EMPLOYEE SUPPORT AND TALENT MANAGEMENT

SECTION NAME: PERFORMANCE MGT, DEVELOPMENT & EMPLOYEE


WELLNESS

PROJECT NAME: PERFORMANCE MANAGEMENT AND DEVELOPMENT


SYSTEM

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVES
Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014;
Build a people focused organisation; and
Ensure that institutions of the state are reflective of the demographics of society; and effectively coordinate and build capacity of the public sector towards social and
institutional transformation.
PERFORMANCE INDICATORS
1.20 Number of employees with credible performance agreements by 30 April 2013 as part of the implementation of the Performance Management and Development
Policy; and
1.21 Number of employees whose performance has been reviewed and evaluated as part of the implementation of the Performance Management and Development Policy
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Facilitate the contracting of all


employees of the department

Implement Performance incentives for


2012/13 performance cycle

Coordinate quarter 2 reviews

Coordinate quarter 3 performance


reviews

Ensure that all contracts for 2013/14 are


captured on PERSAL

coordinate the quarter 1 performance


reviews

Ensure that all received reviews are


captured on PERSAL.

Senior management contracting for


2014/15 performance cycle

Coordinate the reviews of the quarter 4


of 2012/13 performance cycle.

Ensure that all received quarter 1


reviews are captured on PERSAL

Conduct half year validations for first


and second quarter reviews

coordinate the performance


assessments for 2012/2013

submit the half yearly SMS PMDS report


to DPSA

Facilitate assessments validations for


2012/13 performance cycle.

validate all performance agreements to


ensure that the objectives in the APP
are well covered

compile the 2012/13 closing report

33

DIRECTORATE NAME: STRATEGIC HR AND INSTITUTIONAL SUPPORT

SECTION NAME: HUMAN RESOURCE PLANNING, STRATEGY AND SYSTEM

PROJECT NAME: PROMOTION OF PUNCTUALITY AND DRESS CODE

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014.
PERFORMANCE INDICATOR
1.23 Level of implementation of the Provincial Culture Strategy to transform the public service and enhance service delivery
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Develop implementation plan for the
promotion of functionality and dress
code in OTP. 2. Awareness on
guidelines on punctuality and dress
code.
10% for the identification and
appointment of culture change agents
and 25% for the training of this group.

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Implementation, monitoring of the


change and improvement.

Implementation, monitoring of the


change and improvement.

Monitoring of the change and


improvement.

20% implementation of quick win


projects

the 25% is for the development and


approval of the Departmental culture
change framework

20% implementation of quick win


projects

34

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

DIRECTORATE NAME: STRATEGIC HR AND INSTITUTIONAL SUPPORT

SECTION NAME: LABOUR RELATIONS

PROJECT NAMES: MANAGEMENT OF GRIEVANCES & MANAGEMENT OF


EMPLOYEE EXITING PROCESSES

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.27 Percentage of grievances finalised within 30 days; and
1.28 Percentage of exit interviews conducted to employees leaving the department.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Grievance Register to be developed.


Capture of 2. Grievances on PERSAL.
3. Report to Top Management on
Number of Grievances status.

Grievance Register to be developed.


Capture of 2. Grievances on PERSAL.
3. Report to Top Management on
Number of Grievances status.

Grievance Register to be developed.


Capture of 2. Grievances on PERSAL.
3. Report to Top Management on
Number of Grievances status.

Grievance Register to be developed.


Capture of 2. Grievances on PERSAL.
3. Report to Top Management on
Number of Grievances status.

Draw report on all Service terminations


and transfers out of the department on
PERSAL. 2. Analyse the outcome of
the exit interview. 3. Report on the
Number of exit interviews conducted to
Top Management and the outcomes of
the analysis.

Draw report on all Service terminations


and transfers out of the department on
PERSAL. 2. Analyse the outcome of
the exit interview. 3. Report on the
Number of exit interviews conducted to
Top Management and the outcomes of
the analysis.

Draw report on all Service terminations


and transfers out of the department on
PERSAL. 2. Analyse the outcome of
the exit interview. 3. Report on the
Number of exit interviews conducted to
Top Management and the outcomes of
the analysis.

Draw report on all Service terminations


and transfers out of the department on
PERSAL. 2. Analyse the outcome of
the exit interview. 3. Report on the
Number of exit interviews conducted to
Top Management and the outcomes of
the analysis.

35

Sub-Programme 1.6: Finance and Supply Chain Management


DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: SALARIES

PROJECT NAME: SALARY ADMINISTRATION AND REBATES MANAGEMENT

BUDGET ALLOCATION: R21 000

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Salary payments and allowances

Salary payments and allowances

Salary payments and allowances

Salary payments and allowances

Implementing general deductions

Implementing general deductions

Implementing general deductions

Implementing general deductions

Maintain and keep salary records

Maintain and keep salary records

Maintain and keep salary records

Maintain and keep salary records

Monitoring of ACB limits

Monitoring of ACB limits

Monitoring of ACB limits

Monitoring of ACB limits

Payroll management

Payroll management

Payroll management

Payroll management

Drawing and analysis of monthly


expenditure reports

Drawing and analysis of monthly


expenditure reports

Drawing and analysis of monthly


expenditure reports

Drawing and analysis of monthly


expenditure reports

Persal to Bas reconciliation

PERSAL to Bas reconciliation

Persal to Bas reconciliation

Persal to Bas reconciliation

Clearing of PERSAL exceptions

Clearing of PERSAL exceptions

Clearing of PERSAL exceptions

Clearing of PERSAL exceptions

Distribution of pay over schedules

Distribution of pay over schedules

Distribution of pay over schedules

Distribution of pay over schedules

Clearing of salary related suspense


accounts

Clearing of salary related suspense


accounts

Clearing of salary related suspense


accounts

Clearing of salary related suspense


accounts

Monthly tax reconciliation (EMP201)and


Annual tax reconciliation (EMP501)

Monthly tax reconciliation (EMP201).

Monthly tax reconciliation (EMP201)

Monthly tax reconciliation (EMP201)

Monthly reconciliation of ITA88

Monthly reconciliation of ITA88

Monthly reconciliation of ITA88

Monthly reconciliation of ITA88

ACB recalls

ACB recalls

ACB recalls

ACB recalls

Monitoring of ACB rejections

Monitoring of ACB rejections

Monitoring of ACB rejections

Monitoring of ACB rejections

Reversal and freezing of salaries

Reversal and freezing of salaries

Reversal and freezing of salaries

Reversal and freezing of salaries

36

DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: BOOK KEEPING

PROJECT NAME: BANK RECONCILIATION AND DEBT MANAGEMENT

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Monthly bank reconciliation

Monthly bank reconciliation

Monthly bank reconciliation

Monthly bank reconciliation

Monthly suspense accounts


reconciliation and analysis

Monthly suspense accounts


reconciliation and analysis

Monthly suspense accounts


reconciliation and analysis

Monthly suspense accounts


reconciliation and analysis

Debt management

Debt management

Debt management

Debt management

Inter-departmental claims management

Inter-departmental claims management

Inter-departmental claims management

Inter-departmental claims management

Processing of Journals

Processing of Journals

Processing of Journals

Processing of Journals

37

DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: EXPENDITURE MANAGEMENT

PROJECT NAME: EXPENDITURE SECTION

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Receive documents from SCM and other


Programmes.

Receive documents from SCM and other


Programmes.

Receive documents from SCM and other


Programmes.

Receive documents from SCM and other


Programmes.

Check authenticity compliance of


documents received from SCM and
other programmes.

Check authenticity compliance of


documents received from SCM and
other programmes.

Check authenticity compliance of


documents received from SCM and
other programmes.

Check authenticity compliance of


documents received from SCM and
other programmes.

Compile, check, verify and authorise the


document.

Compile, check, verify and authorise the


document.

Compile, check, verify and authorise the


document.

Compile, check, verify and authorise the


document.

Capture the document on LOGIS / BAS


on line.

Capture the document on LOGIS / BAS


on line.

Capture the document on LOGIS / BAS


on line.

Capture the document on LOGIS / BAS


on line.

Batch the vouchers & submit to preaudit.

Batch the vouchers & submit to preaudit.

Batch the vouchers & submit to preaudit.

Batch the vouchers & submit to preaudit.

Attend to pre-audit rejections

Attend to pre-audit rejections

Attend to pre-audit rejections

Attend to pre-audit rejections

Pre-authorise payments online

Pre-authorise payments online

Pre-authorise payments online

Pre-authorise payments online

Final authorisation of payments online

Final authorisation of payments online

Final authorisation of payments online

Final authorisation of payments online

After disbursement date, enter BAS


payment numbers on payment vouchers

After disbursement date, enter BAS


payment numbers on payment vouchers

After disbursement date, enter BAS


payment numbers on payment vouchers

After disbursement date, enter BAS


payment numbers on payment vouchers

Attend to system errors (failed payments


& bank rejection).

Attend to system errors (failed payments


& bank rejection).

Attend to system errors (failed payments


& bank rejection).

Attend to system errors (failed payments


& bank rejection).

Put paid stamp on payment vouchers &


file documents numerically at strong
room for audit purposes and future
references

Put paid stamp on payment vouchers &


file documents numerically at strong
room for audit purposes and future
references

Put paid stamp on payment vouchers &


file documents numerically at strong
room for audit purposes and future
references

Put paid stamp on payment vouchers &


file documents numerically at strong
room for audit purposes and future
references

Prepare expenditure report after each


and every payment run.

Prepare expenditure report after each


and every payment run

Prepare expenditure report after each


and every payment run

Prepare expenditure report after each


and every payment run

Prepare payment cycle, age analysis

Prepare payment cycle, age analysis

Prepare payment cycle, age analysis

Prepare payment cycle, age analysis

38

DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: EXPENDITURE MANAGEMENT

PROJECT NAME: EXPENDITURE SECTION

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

and creditors reconciliation on a monthly


basis.

and creditors reconciliation on a monthly


basis.

and creditors reconciliation on a monthly


basis.

and creditors reconciliation on a monthly


basis.

39

DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: SYSTEMS CONTROL AND REPORTING

PROJECT NAME: COMPILATION OF FINANCIAL STATEMENTS

BUDGET ALLOCATION: R2 000

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance;
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised; and
1.31 Financial delegations reviewed annually in accordance with the PFMA and National Treasury Regulations.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Perform month and year-end closure on


BAS

Perform month End closure on BAS

Perform month end closure on BAS

Perform month end closure on BAS

Collect and collate the financial


information for the preparation of the
Interim and Annual Financial Statements

Collect and collate the financial


information for the preparation of the
Interim Financial Statements

Collect and collate the financial


information for the preparation of the
Interim Financial Statements

Collect and collate the financial


information for the preparation of the
Interim Financial Statements

Prepare Interim and Annual Financial


Statements and submit to Provincial
Treasury and Auditor General

Prepare Interim Financial Statements


and submit to Provincial Treasury.

Prepare Interim Financial Statements


and submit to Provincial Treasury.

Prepare Interim Financial Statement and


submit to Provincial Treasury

Compilation and submission of


Compliance Certificates.

Compilation and submission of


Compliance Certificates.

Compilation and submission of


Compliance Certificates.

Compilation and submission of


Compliance Certificates.

Financial delegations reviewed in


accordance with the PFMA and National
Treasury Regulations

40

DIRECTORATE NAME: FINANCIAL MANAGEMENT

SECTION NAME: FINANCIAL MANAGEMENT SYSTEMS CONTROL AND


REPORTING

PROJECT NAME: CONTROL FINANCIAL MANAGEMENT SYSTEMS

BUDGET ALLOCATION: R49 000

STRATEGIC OBJECTIVE: Ensure sound organisational integrity inclusive of human resources, financial and SCM practices and systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.30 Percentage of approved budget spent to ensure that resources allocated to the Department are adequately utilised.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Monthly control and update


departmental code structure

Monthly control and update


departmental code structure

Monthly control and update


departmental code structure

Monthly control and update


departmental code structure

Ensure availability of financial


system(BAS) through registration of new
users and facilitate the training for them,
reset revoked users

Ensure availability of financial


system(BAS) through registration of new
users and facilitate the training for them,
reset revoked users

Ensure availability of financial


system(BAS) through registration of new
users and facilitate the training for them,
reset revoked users

Ensure availability of financial


system(BAS) through registration of new
users and facilitate the training for them,
reset revoked users

Providing user activity and user profile


reports on monthly basis for reviewal by
management.

Providing user activity and user profile


reports on monthly basis for reviewal by
management.

Providing user activity and user profile


reports on monthly basis for reviewal by
management.

Providing user activity and user profile


reports on monthly basis for reviewal by
management.

Provide year-end Trial balance both


immediate and deferred for the
preparation of Annual Financial
Statement

Ensure POC availability for adjustment


journals to capture and authorise

Final audit closure

Ensure year-end calls are logged 12


days before the closure date

41

Prepares and reconciles Budget and


Bas structure for the budget loading and
perform budget blocking of the next
financial year.

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: GOODS RECEIVED AND PAYMENTS

PROJECT NAME: PAYMENT OF INVOICES

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.32 Percentage of invoices /claims in good standing paid within 30 days.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Receive and record invoices on invoice


register

Receive and record invoices on invoice


register

Receive and record invoices on invoice


register

Receive and record invoices on invoice


register

Attach invoice to order voucher

Attach invoice to order voucher

Attach invoice to order voucher

Attach invoice to order voucher

Validate invoices by checking if order


number, description of goods /services
and amount on invoice agree with that of
the order.

Validate invoices by checking if order


number, description of goods /services
and amount on invoice agree with that of
the order.

Validate invoices by checking if order


number, description of goods /services
and amount on invoice agree with that of
the order.

Validate invoices by checking if order


number, description of goods /services
and amount on invoice agree with that of
the order.

Refer invoices that require variation of


order to the relevant directorate for
approval

Refer invoices that require variation of


order to the relevant directorate for
approval

Refer invoices that require variation of


order to the relevant directorate for
approval

Refer invoices that require variation of


order to the relevant directorate for
approval

Capture receipt and invoices on Logis

Capture receipt and invoices on Logis

Capture receipt and invoices on Logis

Capture receipt and invoices on Logis

Submit the voucher to Finance section


for payment

Submit the voucher to Finance section


for payment

Submit the voucher to Finance section


for payment

Submit the voucher to Finance section


for payment

Inform the CFO about all invoices that


are not validated within 7 days

Inform the CFO about all invoices that


are not validated within 7 days

Inform the CFO about all invoices that


are not validated within 7 days

Inform the CFO about all invoices that


are not validated within 7 days

42

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: ASSET MANAGEMENT AND LOGISTICS

PROJECT NAME: ASSET MANAGEMENT

BUDGET ALLOCATION: R8 057 000

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.33 Number of updates/ reviews on the fixed asset register of the Department to achieve the best match of assets with service delivery objectives.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Request and receive asset application


forms from directorates

Request and receive asset application


forms from directorates

Request and receive asset application


forms from directorates

Request and receive asset application


forms from directorates

Perform asset procurement plan for the


department

Perform asset procurement plan for the


department

Perform asset procurement plan for the


department

Perform asset procurement plan for the


department

Asses assets due for replacement

Asses assets due for replacement

Asses assets due for replacement

Asses assets due for replacement

Procure assets

Procure assets

Procure assets

Procure assets

Barcode and distribute assets

Barcode and distribute assets

Barcode and distribute assets

Barcode and distribute assets

Update asset register and inventory list

Update asset register and inventory list

Update asset register and inventory list

Update asset register and inventory list

Administer asset movement, transfers


and losses

Administer asset movement, transfers


and losses

Administer asset movement, transfers


and losses

Administer asset movement, transfers


and losses

Perform reconciliation between BAS


and asset register

Perform reconciliation between BAS


and asset register

Perform reconciliation between BAS


and asset register

Perform reconciliation between BAS


and asset register

Dispose redundant/obsolete assets

Perform Asset verification

Perform Annual stock count

Receive request list of new employees


from Directorates for officials who
qualify for cellphones

Receive request list of new employees


from Directorates for officials who
qualify for cellphones

Receive request list of new employees


from Directorates for officials who
qualify for cellphones

Receive request list of new employees


from Directorates for officials who
qualify for cellphones

Obtain approval from DDG for


acquisition of cellphone

Obtain approval from DDG for


acquisition of cellphone

Obtain approval from DDG for


acquisition of cellphone

Obtain approval from DDG for


acquisition of cellphone

Liaise with service provider for


acquisition of new phones

Liaise with service provider for


acquisition of new phones

Liaise with service provider for


acquisition of new phones

Liaise with service provider for


acquisition of new phones

Update cellphone register

Update cellphone register

Update cellphone register

Update cellphone register

Facilitate payment of cellphone account

Facilitate payment of cellphone account

Facilitate payment of cellphone account

Facilitate payment of cellphone account

43

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: ASSET MANAGEMENT AND LOGISTICS

PROJECT NAME: INVENTORY MANAGEMENT

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.33 Number of updates/ reviews on the fixed asset register of the Department to achieve the best match of assets with service delivery objectives.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Receive VA2 request form from


departmental users

Receive VA2 request form from


departmental users

Receive VA2 request form from


departmental users

Receive VA2 request form from


departmental users

Issue inventory stock to users

Issue inventory stock to users

Issue inventory stock to users

Issue inventory stock to users

Update bin cards

Update bin cards

Update bin cards

Update bin cards

Compile list of inventory stock for


procurement

Compile list of inventory stock for


procurement

Compile list of inventory stock for


procurement

Compile list of inventory stock for


procurement

Perform quarterly stock count

Perform quarterly stock count

Perform quarterly stock count

Perform quarterly stock count

Perform monthly reconciliation

Perform monthly reconciliation

Perform monthly reconciliation

Perform monthly reconciliation

Perform annual stock count

Identification of obsolesce stock and


disposal.

Identification of obsolesce stock and


disposal.

Identification of obsolesce stock and


disposal.

Identification of obsolesce stock and


disposal.

44

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: ASSET MANAGEMENT AND LOGISTICS

PROJECT NAME: FLEET MANAGEMENT

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.33 Number of updates/ reviews on the fixed asset register of the Department to achieve the best match of assets with service delivery objectives.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Receive approved trip authorities and all


related documents i.e garaging form,
after hour form, inspection form and
itinerary.

Receive approved trip authorities and all


related documents i.e garaging form,
after hour form, inspection form and
itinerary.

Receive approved trip authorities and all


related documents i.e garaging form,
after hour form, inspection form and
itinerary.

Receive approved trip authorities and all


related documents i.e garaging form,
after hour form, inspection form and
itinerary.

Allocation of vehicles.

Allocation of vehicles.

Allocation of vehicles.

Allocation of vehicles.

Inspection of vehicles with users before


trip.

Inspection of vehicles with users before


trip.

Inspection of vehicles with users before


trip.

Inspection of vehicles with users before


trip.

Close old authorisation numbers

Close old authorisation numbers.

Close old authorisation numbers.

Close old authorisation numbers.

Inspection of vehicles with users

Inspection of vehicles with users

Inspection of vehicles with users

Inspection of vehicles with users

Balancing of log books

Balancing of log books

Balancing of log books

Balancing of log books

Facilitate vehicle maintenance and


repairs.

Facilitate vehicle maintenance and


repairs.

Facilitate vehicle maintenance and


repairs

Facilitate vehicle maintenance and


repairs.

Monthly reconciliation of invoices from


DOT/First Auto

Monthly reconciliation of invoices from


DOT/First Auto

Monthly reconciliation of invoices from


DOT/First Auto

Monthly reconciliation of invoices from


DOT/First Auto

Request and receive new applications


for subsidised vehicles

Request and receive new applications


for subsidised vehicles

Request and receive new applications


for subsidised vehicles

Request and receive new applications


for subsidised vehicles

Prepare and submit applications to


Departmental Transport Advisory
Committee

Prepare and submit applications to


Departmental Transport Advisory
Committee

Prepare and submit applications to


Departmental Transport Advisory
Committee

Prepare and submit applications to


Departmental Transport Advisory
Committee

Submit the documentation to the Banks


and service providers

Submit the documentation to the Banks


and service providers

Submit the documentation to the Banks


and service providers

Submit the documentation to the Banks


and service providers

Receive the confirmation from the Bank,


if favourable the order will be placed.

Receive the confirmation from the Bank,


if favourable the order will be placed.

Receive the confirmation from the Bank,


if favourable the order will be placed.

Receive the confirmation from the Bank,


if favourable the order will be placed.

Inspection and confirmation of the


vehicle on delivery of subsidised vehicle.

Inspection and confirmation of the


vehicle on delivery of subsidised

Inspection and confirmation of the


vehicle on delivery of subsidised

Inspection and confirmation of the


vehicle on delivery of subsidised

45

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: ASSET MANAGEMENT AND LOGISTICS

PROJECT NAME: FLEET MANAGEMENT

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014
PERFORMANCE INDICATORS
1.29 An unqualified audit outcome with no matters of emphasis in pursuit of good corporate governance; and
1.33 Number of updates/ reviews on the fixed asset register of the Department to achieve the best match of assets with service delivery objectives.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

vehicles

vehicles

vehicles.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Facilitate the maintenance and repairs of


vehicles.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Facilitate the maintenance and repairs of


vehicles.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

Monitoring of monthly submission of Log


Book by users.

46

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: DEMAND MANAGEMENT

PROJECT NAME: DEVELOPMENT OF PROCUREMENT PLAN

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014.
PERFORMANCE INDICATOR
1.34 Development and approval of the procurement plan of the Department as part of efforts to improve planning and budgeting.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Develop a procurement process project
plan with clear delivery dates for
identified projects

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Monitor the implementation of


procurement plan

Monitor the implementation of


procurement plan

Monitor the implementation of


procurement plan

Assist directorates to complete


procurement plans in line with allocated
budget.

Consolidate plans to create a


departmental procurement plan

Identify projects that require SCM


intervention

Submit draft procurement plan to


Treasury for quality assurance

Submit the final procurement plan to the


Director General for Approval

Submit the approved procurement plan


to Provincial Treasury.

47

Write letter to Inform programmes to


prepare and submit procurement plans

DIRECTORATE NAME: SUPPLY CHAIN MANAGEMENT

SECTION NAME: ACQUISITION MANAGEMENT

PROJECT NAME: ADMINISTRATION OF BIDS

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Ensure Sound Organisational Integrity Inclusive of Human Resources, Financial and SCM Practices and Systems by 2014.
PERFORMANCE INDICATOR
1.35 Percentage of bids concluded within 90 days from the date of approval to procure to the date when bid is awarded.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Request and receive specifications from


directorates

Request and receive specifications from


directorates

Request and receive specifications from


directorates

Request and receive specifications from


directorates

Develop a bid project plan detailing all


the activities and timelines leading to the
award of the bid.

Develop a bid project plan detailing all


the activities and timelines leading to the
award of the bid.

Develop a bid project plan detailing all


the activities and timelines leading to the
award of the bid.

Develop a bid project plan detailing all


the activities and timelines leading to the
award of the bid.

Convene Bid Specification Committee


meeting to consider the Terms of
Reference/specification

Convene specification committee


meeting to consider the Terms of
Reference/specification

Convene specification committee


meeting to consider the Terms of
Reference/specification

Convene specification committee


meeting to consider the Terms of
Reference/specification

Advertise bid on tender bulletin and


news papers

Advertise bid on tender bulletin and


news papers

Advertise bid on tender bulletin and


news papers

Advertise bid on tender bulletin and


news papers

Convene Bid Evaluation Committee


meeting to evaluate the submitted bid
proposals

Convene bid evaluation committee


meeting to evaluate the submitted bid
proposals

Convene bid evaluation committee


meeting to evaluate the submitted bid
proposals

Convene bid evaluation committee


meeting to evaluate the submitted bid
proposals

Convene Bid Award Committee meeting


to consider the evaluated bid

Convene bid Award Committee meeting


to consider the evaluated bid

Convene bid Award Committee meeting


to consider the evaluated bid

Convene bid Award Committee meeting


to consider the evaluated bid

Submit BAC recommendations to the


Accounting Officer for approval and
award of bid.

Submit BAC recommendations to the


Accounting Officer for approval and
award of bid.

Submit BAC recommendations to the


Accounting Officer for approval and
award of bid.

Submit BAC recommendations to the


Accounting Officer for approval and
award of bid.

48

Programme 2: Institutional Development and Organisational Support


Sub-Programme 2.1: Office of the Deputy Director General
DIRECTORATE: DDGS OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R389 000

STRATEGIC OBJECTIVES: All strategic objectives applicable to Programme 2


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 2
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate the Programme


Management meetings and follow up on
the decisions thereof

Coordinate the Programme


Management meetings and follow up on
the decisions thereof

Coordinate the Programme


Management meetings and follow up on
the decisions thereof

Coordinate the Programme


Management meetings and follow up on
the decisions thereof

Compile 3 monthly, 1 quarterly, and the


annual report for the programme and
ensure that there is credible evidence
associated with all reported achievement

Compile 3 monthly and 1 quarterly


report for the programme and ensure
that there is credible evidence
associated with all reported achievement

Compile 3 monthly, 1 quarterly and a


mid-year report for the programme and
ensure that there is credible evidence
associated with all reported achievement

Compile 3 monthly and 1 quarterly


report for the programme and ensure
that there is credible evidence
associated with all reported achievement

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate all planning activities for the


Programme and resulting in the
submission of draft Programme APP
and budget.

Coordinate all planning activities for the


Programme and resulting in the
submission of the draft Programme APP
and budget

Coordinate all planning activities for the


Programme and resulting in the
finalisation of the Programme Plans
(APP, Operational Plan, Monthly Activity
Plans, Cash flows, Procurement Plans)

Ensure all managers and staff in the


programme are evaluated through the
PMDS

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the first quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the second quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the third quarter)

Ensure that all staff in the programme


have valid performance contracts for
2013/14 financial year

Ensure that all staff members have valid


performance agreements for the next
financial year

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

49

DIRECTORATE: DDGS OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R389 000

STRATEGIC OBJECTIVES: All strategic objectives applicable to Programme 2


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 2
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Effective and efficient management of


correspondence

Effective and efficient management of


correspondence

Effective and efficient management of


correspondence

Effective and efficient management of


correspondence

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

50

Sub-Programme 2.2: Transversal Organisational Development and Consultancy Services


CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT
SUPPORT SERVICES (HCTMSS)

SECTION NAME: HUMAN RESOURCE STRATEGY AND POLICY SERVICES

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON HR PLANNING AND IMPLEMENTATION

BUDGET ALLOCATION: R380 000

STRATEGIC OBJECTIVES: Build a people focussed organisation; Ensure that the institution of the state are reflective of the demographics of the society; Effectively
coordinate and build the capacity of the public sector towards social and institutional transformation; and Ensure sound organisational integrity inclusive of human resource,
financial, risk and supply chain managerial practices and systems.
PERFORMANCE INDICATORS
2.1 Number of departments with credible HR Effectiveness & Capacity Assessment and developing credible improvement plans;
2.2 Number of departments with credible revised annual human resource plans by the end of June 2013;
2.3 Number of departments submitting credible six monthly and annual human resource implementation reports;
2.4 Number of departments with credible Annual Recruitment Plans (ARPs);
2.5 Percentage of provincial executive management posts filled within 6 months of them being vacant; and
2.6 Number of departments implementing credible HRM delegations.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Departments submit HR effectiveness


assessments for 2012/13 to OTP.

The analysis report on the assessments


is finalised. Feedback is provided to
departments.

Monitor and report on the


implementation of the Planned
Interventions

Departments conduct HR effectiveness


assessments for 2013/14.

The analysis report on the assessments


is finalised

Monitor and report on the


implementation of the Planned
Interventions

Submission of assessments to DPSA.

OTP commences the analysis of the


assessments.

Departments update Annually Adjusted


HRPs and submit to OTP, which
forwards these to DPSA

OTP analyses the Annually Adjusted


HRPs and provides feedback to
departments

The Annual HRP Implementation


Reports for 2012/13 are analysed and
feedback is provided to departments.

The six monthly HRP Implementation


Reports for 2013/14 are analysed and
feedback is provided to departments.

51

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: HUMAN RESOURCE STRATEGY AND POLICY SERVICES

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON HR PLANNING AND IMPLEMENTATION

BUDGET ALLOCATION: R380 000

STRATEGIC OBJECTIVES: Build a people focussed organisation; Ensure that the institution of the state are reflective of the demographics of the society; Effectively
coordinate and build the capacity of the public sector towards social and institutional transformation; and Ensure sound organisational integrity inclusive of human resource,
financial, risk and supply chain managerial practices and systems.
PERFORMANCE INDICATORS
2.1 Number of departments with credible HR Effectiveness & Capacity Assessment and developing credible improvement plans;
2.2 Number of departments with credible revised annual human resource plans by the end of June 2013;
2.3 Number of departments submitting credible six monthly and annual human resource implementation reports;
2.4 Number of departments with credible Annual Recruitment Plans (ARPs);
2.5 Percentage of provincial executive management posts filled within 6 months of them being vacant; and
2.6 Number of departments implementing credible HRM delegations.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Monthly reports from departments on the


implementation of ARPs consolidated
and analysed

Monthly reports from departments on the


implementation of ARPs consolidated
and analysed

Monthly reports from departments on the


implementation of ARPs consolidated
and analysed

Monthly reports from departments on the


implementation of ARPs consolidated
and analysed

Conclude appointments of HoDs:


DRDAR; DEDEAT; DLGTA; DRPW

Conclude appointment of HoD: Human


Settlements

Conclude appointment of HoD: SD&SP


& SRAC

Monitor and report on EM vacancies

Monitor and report on EM vacancies

Monitor and report on EM vacancies

Monitor and report on EM vacancies

Monitor and report on implementation of


HRM delegations

Monitor and report on implementation of


HRM delegations

Monitor and report on implementation of


HRM delegations

Monitor and report on implementation of


HRM delegations

Monitor and support implementation of


departmental Attraction and Retention
Strategies

Monitor and support implementation of


departmental Attraction and Retention
Strategies

Monitor and support implementation of


departmental Attraction and Retention
Strategies

Monitor and support implementation of


departmental Attraction and Retention
Strategies

Facilitate approval of Succession


Planning Policy in the Province

Roll out Succession Planning Policy in


the Province

Roll out Succession Planning Policy in


the Province

Roll out Succession Planning Policy in


the Province

Finalise validation of HRM Competency


Assessment Tool in the Province

Facilitate approval of HRM Competency


Assessment Tool in the Province

Roll out HRM Competency Assessment


Tool in the Province

Roll out HRM Competency Assessment


Tool in the Province

Consolidate Provincial HRM Status


Report

Consolidate Provincial HRM Status


Report

Consolidate Provincial HRM Status


Report

Consolidate Provincial HRM Status


Report

Consolidate departmental Management

Consolidate departmental Management

Consolidate departmental Management

Consolidate departmental Management

52

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: HUMAN RESOURCE STRATEGY AND POLICY SERVICES

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON HR PLANNING AND IMPLEMENTATION

BUDGET ALLOCATION: R380 000

STRATEGIC OBJECTIVES: Build a people focussed organisation; Ensure that the institution of the state are reflective of the demographics of the society; Effectively
coordinate and build the capacity of the public sector towards social and institutional transformation; and Ensure sound organisational integrity inclusive of human resource,
financial, risk and supply chain managerial practices and systems.
PERFORMANCE INDICATORS
2.1 Number of departments with credible HR Effectiveness & Capacity Assessment and developing credible improvement plans;
2.2 Number of departments with credible revised annual human resource plans by the end of June 2013;
2.3 Number of departments submitting credible six monthly and annual human resource implementation reports;
2.4 Number of departments with credible Annual Recruitment Plans (ARPs);
2.5 Percentage of provincial executive management posts filled within 6 months of them being vacant; and
2.6 Number of departments implementing credible HRM delegations.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Information Systems (MIS) Reports

Information Systems (MIS) Reports

Information Systems (MIS) Reports

Information Systems (MIS) Reports

Consolidated report on the HR portion of


the 2011/12 Departmental Audit
Intervention Plans (AIPs)

Monitor and Report on progress on the


HR portion of the 12/13 Departmental
Audit Intervention Plans (AIPs)

Monitor and Report on progress on the


HR portion of the 12/13 Departmental
Audit Intervention Plans (AIPs)

Monitor and Report on progress on the


HR portion of the 12/13 Departmental
Audit Intervention Plans (AIPs)

53

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: HUMAN RESOURCE STRATEGY AND POLICY SERVICES

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON EMPLOYEE AND ORGANISATIONAL WELLNESS

BUDGET ALLOCATION: R475 000

STRATEGIC OBJECTIVE
Build a people focussed organisation
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATORS
2.9 Number of departments implementing employee wellness programmes; and
2.10 Number of departments implementing Policy and Procedure on Incapacity Leave and Ill-health Retirement (PILIR) Framework effectively.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Develop employee wellness audit tool

Conduct employee wellness audit in 2


pilot depts.

Conduct briefing sessions with 13


departments on the audit

Conduct employee wellness audit in 4


departments

Development of project plan

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES
Conduct employee wellness audit in 7
departments

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Analyse data and compile annual report.
Facilitate Planning sessions with 13
departments for 2014/15
Analyse data and compile report and
conduct one on one session with
departments

Analyse trends and report on 13


departments and finalise business plans

Collect baseline data

Analyse data and compile report on


baseline information to inform audit

Facilitate Employee Wellness


Programme implementation

Facilitate Employee Wellness


Programme implementation

Facilitate Employee Wellness


Programme implementation

Facilitate Employee Wellness


Programme implementation

Collect and analyse data from Persal


and Vulindlela on Leave Management
with special emphasis on employees
number of sick leave days taken, sick
leave pending applications, employees
who never took vacations with special
attention given to DOE,DOH,DSRAC
and OTP

Collect and analyse data from Persal


and Vulindlela on Leave Management
with special emphasis on employees
number of sick leave days taken, sick
leave pending applications, employees
who never took vacation focusing on
DOE,DOH,DSRAC and OTP

Collect and analyse data from Persal


and Vulindlela on Leave Management
with special emphasis on employees
number of sick leave days taken, sick
leave pending applications, employees
who never took vacation focusing on
DOE,DOH,DSRAC and OTP

Collect and analyse annual data from


Persal and Vulindlela on Leave
Management with special emphasis on
employees number of sick leave days
taken, sick leave pending applications,
employees who never took vacation
focusing on DOE,DOH,DSRAC and
OTP

54

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: HUMAN RESOURCE STRATEGY AND POLICY SERVICES

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON EMPLOYEE AND ORGANISATIONAL WELLNESS

BUDGET ALLOCATION: R475 000

STRATEGIC OBJECTIVE
Build a people focussed organisation
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATORS
2.9 Number of departments implementing employee wellness programmes; and
2.10 Number of departments implementing Policy and Procedure on Incapacity Leave and Ill-health Retirement (PILIR) Framework effectively.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Facilitate appointment of new Health


Risk Manager, the setting up of new
HRM (signing of contract, Introductions
to depts), Monitor handover and
submission of applications and facilitate
PILIR Steering committee meeting

Facilitate steering committee meeting


and submission of reports, Analyse data
per department, submit report and
formulate feedback to departments.

Facilitate steering committee meeting


and submission of reports, Analyse data
per department, submit report and
formulate feedback to departments

Facilitate steering committee meeting


and submission of reports, Analyse data
per department, submit report and
formulate feedback to departments

55

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: EMPLOYMENT RELATIONS MANAGEMENT

PROJECT NAME: FACILITATION, MONITORING AND SUPPORTING


DEPARTMENTS ON EMPLOYMENT RELATIONS MANAGEMENT

BUDGET ALLOCATION: R475 000

STRATEGIC OBJECTIVES
Build a people focussed organisation
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
2.11 Number of departments implementing employment relations strategies.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Misconduct data collected, analysed and


reports developed.

Misconduct data collected, analysed and


reports developed.

Misconduct data collected, analysed and


reports developed.

Collect, analyse and report on


misconduct data.

Leadership seminar for HR Heads


organised.

Leadership seminar for Executive


Management organised.

Leadership seminar for HR Heads


organised.

IDLRF held.

IDLRF held.

IDLRF held.

IDLRF held.

Benchmarking session for LR


practitioners is held.

Benchmarking session for LR


practitioners.

1st annual LR dialogue session held and


decisions of the session formed into a
PoA.

Facilitate structured engagement


between labour and government to
create and sustain labour peace within
the Provincial Administration.

Facilitate structured engagement


between labour and government to
create and sustain labour peace within
the Provincial Administration.

Facilitate structured engagement


between labour and government to
create and sustain labour peace within
the Provincial Administration.

Preparatory processes for Chamber


finalised

Preparatory processes for Chamber


finalised

Preparatory processes for Chamber


finalised

Preparatory processes for Chamber


finalised

Meetings of the Provincial Chambers of


the PSCBC and GPSSBC take place
and OTP takes part in ELRC and
PH&SDSBC.

Meetings of the Provincial Chambers of


the PSCBC and GPSSBC take place
and OTP takes part in ELRC and
PH&SDSBC.

Meetings of the Provincial Chambers of


the PSCBC and GPSSBC take place
and OTP takes part in ELRC and
PH&SDSBC.

Meetings of the Provincial Chambers of


the PSCBC and GPSSBC take place
and OTP takes part in ELRC and
PH&SDSBC.

Seek Mandate, Participate in, and


communicate the outcomes of the
PSCBC and GPSSBC processes

Seek Mandate, Participate in, and


communicate the outcomes of the
PSCBC and GPSSBC processes

Seek Mandate, Participate in, and


communicate the outcomes of the
PSCBC and GPSSBC processes

Seek Mandate, Participate in, and


communicate the outcomes of the
PSCBC and GPSSBC processes

56

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Dialogue session PoA KRAs factored


into the OPS of departments.

CHIEF DIRECTORATE NAME: HUMAN CAPITAL & TALENT MANAGEMENT


SUPPORT SERVICES (HCTMSS)

SECTION NAME: PERFORMANCE MANAGEMENT AND DEVELOPMENT


SERVICES

PROJECT NAME: FACILITATE THE IMPLEMENTATION OF PMDS IN


DEPARTMENTS

BUDGET ALLOCATION: R380 000

STRATEGIC OBJECTIVES
Build a people focussed organisation
Effectively coordinate and build capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATORS
2.7 Number of departments with credible HoDs performance agreements by 31 May 2013; and
2.8 Number of departments conducting credible performance reviews and evaluations for their Heads of Departments.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Support HoDs with performance


contracting.

Validation report on HoDs PAs done.

Support the process of conducting the


2nd HoD performance reviews

Support the process setting up of


evaluation panels to evaluate the
previous financial year performance

Support the process of conducting the


1st HoD performance reviews

Monitor, support and report on the


implementation of the Employee PMDS:
Employee performance contracting
for 2013/14
Quarter 4 Reviews (2012/13)
Annual employee performance
assessments (2012/13)
Annual state of PMDS report for
2012/13 done

Monitor, support and report on the


implementation of the Employee PMDS:
Sample of employee performance
contracts validated and report done.
Implementation of employee
performance incentives monitored
Quarter 1 employee performance
reviews monitored

Monitor, support and report on the


implementation of the Employee PMDS:
Sample of employee performance
reviews validated and report done.
Quarter 2 employee performance
reviews monitored

Revised PMDS manual approved and


EPMDS policy integrated into the book.

500 Revised PMDS manual printed and


distributed to H/O and 6 districts

500 Revised PMDS manual printed and


distributed to 2 districts

57

Support finalization of HoDs


performance appraisal of the
previous financial year.
Develop an annual report on the
state of HOD PMDS
Monitor, support and report on the
implementation of the Employee PMDS:
Provide readiness support to
departments for 2014/15 PMDS
Planning and contracting for the
new financial year
Quarter 3 employee performance
reviews monitored

CHIEF DIRECTORATE NAME: HUMAN RESOURCE DEVELOPMENT SUPPORT

SECTION NAME: HRD STRATEGY DEVELOPMENT MONITORING AND


SUPPORT

PROJECT NAMES

BUDGET ALLOCATION

TRANSVERSAL TRAINING
LEADERSHIP DEVELOPMENT
WOMEN IN LEADERSHIP

R10 741 000


R10 741 000
R500 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATORS
2.18 Number of middle and senior managers trained through the leadership development programme;
2.19 Number of women participating in the Women in Leadership Development Programme; and
2.20 Number of public servants trained in specific key areas in line with the Public Sector Transformation Strategy.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

TRANSVERSAL TRAINING
Train at least 150 officials on key areas
in line with the Public Sector
transformation Strategy (Financial and
Business Management, Human
Resource Management, Organisational
Development, Communication,
Compulsory Induction Training, ICT)

Train at least 150 officials on key areas


in line with the Public Sector
transformation Strategy (Financial and
Business Management, Human
Resource Management, Organisational
Development, Communication,
Compulsory Induction Training, ICT)

Train at least 150 officials on key areas


in line with the Public Sector
transformation Strategy (Financial and
Business Management, Human
Resource Management, Organisational
Development, Communication,
Compulsory Induction Training, ICT)

Train at least 150 officials on key areas


in line with the Public Sector
transformation Strategy (Financial and
Business Management, Human
Resource Management, Organisational
Development, Communication,
Compulsory Induction Training, ICT)

Train at least 80 officials on key areas in


line with the Public Sector
Transformation Strategy
Advanced Leadership Programme
ALP

Train at least 80 officials on key areas in


line with the Public Sector
Transformation Strategy
ALP continues
Executive Development Programme
(EDP) commences in September
2013

Train at least 80 officials on key areas in


line with the Public Sector
Transformation Strategy
ALP ends end December 2013
Advanced Management Programme
(AMDP) commences in November
2013
EDP continues

Train at least 80 officials on key areas in


line with the Public Sector
Transformation Strategy
EDP continues

Prepare for Leadership Seminar

Conduct Leadership Seminar

Conduct Leadership Seminar

Conduct Leadership Seminar

LEADERSHIP DEVELOPMENT

58

CHIEF DIRECTORATE NAME: HUMAN RESOURCE DEVELOPMENT SUPPORT

SECTION NAME: HRD STRATEGY DEVELOPMENT MONITORING AND


SUPPORT

PROJECT NAMES

BUDGET ALLOCATION

TRANSVERSAL TRAINING
LEADERSHIP DEVELOPMENT
WOMEN IN LEADERSHIP

R10 741 000


R10 741 000
R500 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATORS
2.18 Number of middle and senior managers trained through the leadership development programme;
2.19 Number of women participating in the Women in Leadership Development Programme; and
2.20 Number of public servants trained in specific key areas in line with the Public Sector Transformation Strategy.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

WOMEN IN LEADERSHIP
Finalise Concept And Develop
Programme

30 Women participate in a Women in


Leadership Programme

Continuation with the Women in


Leadership Programme

59

Continuation with the Women in


Leadership Programme
Compilation of a summative report
on the Programme

SECTION NAME: HRD STRATEGY DEVELOPMENT MONITORING AND


SUPPORT

CHIEF DIRECTORATE NAME: HUMAN RESOURCE DEVELOPMENT SUPPORT


PROJECT NAMES

BUDGET ALLOCATION: R20 476 000

SKILLS DEVELOPMENT
FINANCIAL ASSISTANCE

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATORS
2.20 Number of public servants trained in specific key areas in line with the Public Sector Transformation Strategy; and
2.21 Number of unemployed young people trained in specific skill areas as part of the strategic skills development initiative
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

SKILLS DEVELOPMENT
Support Government Departments to
develop HRD Implementation Plans in
line with the PSDS

Consolidate the Annual Plans of


Provincial Departments and monitor
implementation

Consolidate and present half-yearly


implementation reports to Provincial
Management

Consolidate and present the Annual


HRD implementation report to Provincial
Management

Consolidate the Annual Reports of


PSDF Stakeholders against the PSDS;

Work with Stakeholders on the


Provincial Management Information
System;

Present the half-yearly report to the


Provincial and National HRD Council
and to Provincial Management

Quarterly reports consolidated;

Coordinate the placement of at least 600


unemployed youth in Learnerships,
Apprenticeships or Skills Programmes

Coordinate the placement of at least 600


unemployed youth in Learnerships,
Apprenticeships or Skills Programmes

Coordinate the placement of at least 600


unemployed youth in Learnerships,
Apprenticeships or Skills Programmes

Coordinate the placement of at least 600


unemployed youth in Learnerships,
Apprenticeships or Skills Programmes

Facilitate, coordinate and monitor the


placement of FET College students with
Provincial Departments, Municipalities
and Public Entities

Facilitate, coordinate and monitor the


placement of FET College students with
Provincial Departments, Municipalities
and Public Entities

Facilitate, coordinate and monitor the


placement of FET College students with
Provincial Departments, Municipalities
and Public Entities

Facilitate, coordinate and monitor the


placement of FET College students with
Provincial Departments, Municipalities
and Public Entities

Coordinate the provision of Financial


Assistance to at least 3,000 full-time
students in critical fields of study

Coordinate the provision of Financial


Assistance to at least 3,000 full-time
students in critical fields of study

Coordinate the provision of Financial


Assistance to at least 3,000 full-time
students in critical fields of study

Coordinate the provision of Financial


Assistance to at least 3,000 full-time
students in critical fields of study

Annual report on financial assistance


provided by provincial government in
2012/13 including student progress

Conduct an extensive Career Exhibition


Programme

Half year report on the financial support


provided in 2013/14.

Conduct an extensive Career Exhibition


Programme.

Conduct an extensive Career Exhibition


Programme

Host the Annual Top Achievers Award


Ceremony for the top Grade 12 learners

FINANCIAL ASSISTANCE

60

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: ORGANISATIONAL DESIGN AND SYSTEMS SUPPORT

PROJECT NAME: RENDER ORGANISATIONAL DESIGN AND SYSTEMS


SUPPORT TO THE PROVINCIAL ADMINISTRATION

BUDGET ALLOCATION: R203 640

STRATEGIC OBJECTIVE
Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATORS
2.12 Number of departments with approved organizational Structures for the current Medium Term Strategic Framework; and
2.13 Number of departments with credible human resource planning, recruitment and selection and leave management business processes.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

ASSESSMENT & SUPPORT ON DEVELOPMENT OF ORGANISATIONAL STRUCTURE


Three (3) organogram analysed which
include:
Pre-consultation sessions held with
the departments during
restructuring
Organogram consulted with OTP
and DPSA before approval by the
relevant EA

Four (4) organogram analysed which


include:

Four (4) organogram analysed which


include:

Pre-consultation sessions held with


the departments during
restructuring
Organogram consulted with OTP
and DPSA before approval by the
relevant EA

Pre-consultation sessions held with


the departments during
restructuring

Two (2) organograms analysed.


Validate service delivery models and
departmental organograms and develop
Annual report with recommendations for
improvements

Organogram consulted with OTP


and DPSA before approval by the
relevant EA

ASSESSMENT AND SUPPORT ON IMPLEMENTATION OF JOB EVALUATION POLICY


Three (3) departments implement JE
structures, co-ordinated and supported
which include:
Analysis of existing JE capacity
Trained JE Analysts and Panellists

Four (4) departments implement JE


structures, co-ordinated and supported
which include:

Four (4) departments implement JE


structures, co-ordinated and supported
which include:

JE structures fully functional


Evaluated posts in terms of the
Public Service Regulations.
JE results captured on Persal

JE structures fully functional


Evaluated posts in terms of the
Public Service Regulations.
JE results captured on Persal

61

Two (2 ) departments implement JE


structures, co-ordinated and supported
and JE report developed

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: ORGANISATIONAL DESIGN AND SYSTEMS SUPPORT

PROJECT NAME: RENDER ORGANISATIONAL DESIGN AND SYSTEMS


SUPPORT TO THE PROVINCIAL ADMINISTRATION

BUDGET ALLOCATION: R203 640

STRATEGIC OBJECTIVE
Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
Ensure sound organisational integrity inclusive of human resource, financial, risk and supply chain managerial practices and systems
PERFORMANCE INDICATORS
2.12 Number of departments with approved organizational Structures for the current Medium Term Strategic Framework; and
2.13 Number of departments with credible human resource planning, recruitment and selection and leave management business processes.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

BUSINESS PROCESS RE-ENGINEERING


Formalize BPM task teams which
include:
Appointment of members to serve in
the provincial BPM task team
At least one (1) task team meeting
held

1 As-is process mapped for recruitment


and selection process and develop are
report.

1 As-is process mapped for leave


management process and develop a
report

1 As-is process mapped for HR planning


and a report for all mapped processes
with recommendations.

Development of a BPM project plan

DOCUMENT MANAGEMENT SUPPORT TO DEPARTMENT OF EDUCATION


OD intervention plan for documents
management developed for the
Department of Education

Conduct Joint Action Planning with


Department of Education relevant
business unit/s

Conduct group sessions on


organisational diagnosis with
relevant business unit/s
Conduct feedback sessions as a
results of diagnosis made with the
relevant business unit/s

62

Ensure implementation of
recommendations and follow through

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: CULTURE CHANGE

PROJECT NAME: FACILITATE IMPLEMENTATION OF CULTURE CHANGE


PROJECTS

BUDGET ALLOCATION: : R763 650

STRATEGIC OBJECTIVES
Build a people focussed organisation; and
Effectively coordinate and build the capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
2.14 Number of departments implementing culture change strategies
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Feedback to departments on the DI
Analysis and findings

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Monitor and support implementation of


Departmental Culture Change Quick
Win Projects that are aligned to
Departmental Programmes

Monitor and support implementation of


Departmental Culture Change Quick
Win Projects that are aligned to
Departmental Programmes

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Monitor and support implementation of
Departmental Culture Change Quick
Win Projects that are aligned to
Departmental Programmes

Monitor and support implementation of


Departmental Culture Change Quick
Win Projects that are aligned to
Departmental Programmes

Skills enhancement, Refresher and Reorientation sessions for Departmental


Change Agents and OTP Technical
Advisors

Skills enhancement, Refresher and Reorientation sessions for Departmental


Change Agents and OTP Technical
Advisors

Skills enhancement, Refresher and Reorientation sessions for Departmental


Change Agents and OTP Technical
Advisors

Skills enhancement, Refresher and Reorientation sessions for Departmental


Change Agents and OTP Technical
Advisors

Leadership Change Engagement


Programme (Premier and MECs, DG,
HoDs and DDGs)

Leadership Change Engagement


Programme (Premier and MECs, DG,
HoDs and DDGs)

Leadership Change Engagement


Programme (Premier and MECs, DG,
HoDs and DDGs)

Leadership Change Engagement


Programme (Premier and MECs, DG,
HoDs and DDGs)

Orientation of Batho Pele coordinators of


13 departments on the Batho
Revitalization strategy implementation
plan.

Monitor and support the implementation


of the Batho Pele Revitalization Strategy
implementation plan

Monitor and support the implementation


of the Batho Pele Revitalization Strategy
implementation plan

Batho Pele Audits / Front Line


Service Audits
Khaedu

Support development of Departmental


Annual Culture Change Programmes

Batho Pele Audits / Front Line


Service Audits feedback
Khaedu

Comprehensive report on progress on


Provincial and Departmental Cultures
Change Programmes

63

Report on the Batho Pele


Revitalization Strategy
implementation plan
Annual Plan for 2014/15 Batho Pele
Revitalization Strategy
Comprehensive report on progress on
Provincial and Departmental Cultures
Change Programmes

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: CULTURE CHANGE

PROJECT NAME: FACILITATE IMPLEMENTATION OF CULTURE CHANGE


PROJECTS

BUDGET ALLOCATION: : R763 650

STRATEGIC OBJECTIVES
Build a people focussed organisation; and
Effectively coordinate and build the capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
2.14 Number of departments implementing culture change strategies
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Preparations for the Public Service
Month
APSD Activities held on 23 June
2013 (Part of EXCO Outreach)
Preparation for the EXCO outreach
Report on progress on 2012 HoD
Deployments, feedback and followup
HoD Deployments to Service
Delivery Sites
Public Servants Policy and Culture
Change Sessions

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Public Service Month activities


implemented

Report of the Public Service Month

Logistics
Feed -back to Ikhwezi
Feedback to Elliotdale
Preparation for the EXCO outreach

EXCO Outreach Report

Feedback and follow up on HoD


deployments

Monitor implementation of EXCO


Outreach Resolutions in respect of HoD
Deployments

HoD Deployments to Service


Delivery Sites
Public Servants Policy and Culture
Change Sessions

64

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Monitor the implementation of the
PSM recommendation
Annual report on the PSM 2013/14
Public Service Month Concept for
2014 developed
Monitor implementation of EXCO
Outreach Resolutions in respect of HoD
Deployments

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: SERVICE DELIVERY INTERVENTIONS

PROJECT NAME: DEVELOPMENT AND PILOTING OF AN INTEGRATED


ORGANISATIONAL ASSESSMENT TOOL

BUDGET ALLOCATION: R80 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
2.15 Integrated organizational performance assessment framework and tool developed.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Research and development on the
integration of organizational
performance diagnostic tools done:
Research on integrated hybrid
organizational assessment tools
done
Benchmarking of hybrid tools and
organizational maturity models
Integrated model for organizational
performance assessment and
reporting developed

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Concept document for the integration of


diagnostic tools developed and
approved
Concept document with a case for
change developed
Blue print for organizational
performance diagnostics developed
Concept document consulted with
all relevant stakeholders

65

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of a web-based
organizational diagnostic tool done:
Blue print for a web- based tool
done
User needs analysis done
Web-based tool piloted to users
Web-based toll signed off

Pilot the web-based diagnostics tool in


additional 1 department:
Departmental orientation done
Users in department trained
Users conduct assessment
Pilot sight signed off to test tool for
reliability and reliability

Pilot the web-based diagnostics tool in 1


identified department.
Departmental orientation done
Users in department trained
Users conduct assessment
Pilot sight signed off

Organizational Performance
Assessment Policy Updated:
Organizational Assessment policy
revision workshop conducted
Revised policy communicated to all
stakeholders
Updated policy approved by EXCO

Training of 50 designated IDOS and


OTP transversal (prg 3 & 4) staff done

Training of 100 provincial M& E and


Balasela champions done

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: SERVICE DELIVERY INTERVENTIONS

PROJECT NAME: REVISION OF SDIPS AND MONITORING IMPLEMENTATION

BUDGET ALLOCATION: R225 460

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation.
PERFORMANCE INDICATOR
2.16 Number of departments implementing revised Service Delivery Improvement Plans
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

REVISION OF SDIPS AND MONITORING IMPLEMENTATION


Feedback reports provided and
presented to 13 Departments on the
revised SDIPs submitted.

Audits done to track SDIP


implementation at head office and in 3
districts of 4 identified Departments.

Audits done to track SDIP


implementation at head office and in
additional 3 districts of the 4 identified
Departments.

Progress report on the departmental


feedback sessions done

Audit report done

Audit report done

Integrated audit report on SDIP


implementation with recommendations
for improvement shared with 4
departments across six districts

Updated PSDC distributed and


communicated to Departments in 3
districts

Report on PSDC implementation with


recommendations for improvement
shared with 13 departments

MARKETING THE PROVINCIAL SERVICE DELIVERY CHARTER


2000 copies of the updated Provincial
Service Delivery Charter(PSDC) printed

PSDC loaded on the provincial web-site

Updated PSDC distributed and


communicated to 13 Departments at
Head Office (Bhisho & King Williams
Town)

Updated PSDC distributed and


communicated to Departments in 3
districts.

66

CHIEF DIRECTORATE NAME: INSTITUTIONAL SUPPORT SERVICES

SECTION NAME: INNOVATION AND KNOWLEDGE MANAGEMENT

PROJECT NAME: COORDINATION OF KNOWLEDGE MANAGEMENT

BUDGET ALLOCATION: R295 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.17 Number of departments implementing Innovation and Knowledge Management strategies.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Provide Support to 13 Departments to


be trained to upload information /
documents in the Provincial Knowledge
Hub

Departments supported to Identify,


Collect, and Package the Provincial Best
Practices and Facilitate the Replication
of Existing Best Practices

Coordinate Knowledge Exchange in


Cross Functional Teams for Information
Sharing in 3 Departments by Focusing in
Finance Section

Facilitate the implementation of Learning


and Sharing Practices in Departments

Provide Support to 6 Departmental


Districts to upload information /
documents in the Provincial Knowledge
Hub

Facilitate the Replication of Existing Best


Practices in Departments

Coordinate Knowledge Exchange in


Cross Functional Teams for Information
Sharing in 3 Departments by Focusing in
HR Section

Coordinate Knowledge Exchange in


Cross Functional Teams for Information
Sharing in 3 Departments by Focusing in
SCM Section

67

Sub-Programme 2.3: Information Technology Management


CHIEF DIRECTORATE NAME: PROVINCIAL INFORMATION MANAGEMENT
UNIT

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF ICT GOVERNANCE

BUDGET ALLOCATION: R200 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.22 Number of departments implementing ICT Governance in accordance with the Provincial Framework.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Maturity Level Assessment for the 13


Departments produced

GAP Analysis based on the assessment


and Policy creation

Business Processes and ICT Goals


Mapping

Alignment of Business Processes with


ICT / COBIT Processes

Provincial ICT Strategy Planning


Session with PGITOC members

Provincial ICT Strategy review

Provincial ICT Strategy review and


presentation to the Provincial ICT
Steering Committee

Approved Provincial ICT Strategy


document for 2014-2019

68

CHIEF DIRECTORATE NAME: PROVINCIAL INFORMATION MANAGEMENT


UNIT

SECTION NAME: N/A

PROJECT NAME: MONITORING OF SITA SERVICE LEVEL AGREEMENT

BUDGET ALLOCATION: R87.737m

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.23 Level of compliance of SITA with the Service Level Agreements
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Business Agreement kick-off sessions

Business Agreement review and


engagement inputs

An approved final Business Agreement


document

Approved Report on SITA accountability


matrix

Approved Report on SITA accountability


matrix

Approved Report on SITA accountability


matrix

Approved Report on SITA accountability


matrix

Quarterly Performance reports (ALL


SLAs)

Quarterly Performance reports (ALL


SLAs)

Quarterly Performance reports (ALL


SLAs)

Quarterly Performance reports (ALL


SLAs)

Submission of
Renewal/Termination/Amendment of
reviewed SLAs for approval

Assessment for in-house Provincial


Hosting of the SITA historical data

Review of SITA and ICT related SLAs


(Managed Desktop, Hosted Printing, etc)

A Developed implementation plan for inhouse Provincial Hosting of SITA


historical data.

Quarterly Performance report on Web


Applications Development &
Maintenance

Quarterly Performance report on Web


Applications Development &
Maintenance.

Development of the implementation


plan for in-house Provincial Hosting of
SITA historical data

Quarterly Performance report on Web


Applications Development &
Maintenance.

Quarterly Performance report on Web


Applications Development &
Maintenance.

Approval of the Project Plan for Service


Improvement.

Develop Project Plan for Service


Improvement.

Assessment for in-house Provincial


Hosting of the SITA historical data

69

CHIEF DIRECTORATE NAME: PROVINCIAL INFORMATION MANAGEMENT


UNIT

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF THE PROVINCIAL ICT


INFRASTRUCTURE PLAN

BUDGET ALLOCATION: R7.27m

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.23 Level of implementation of the Provincial ICT Infrastructure Plan
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Approved Infrastructure and


Maintenance Plans based on Asset
verification

Provisioning and Maintenance of


Provincial ICT Network Infrastructure
services as per the Maintenance and
Infrastructure Plans

Provisioning and Maintenance of


Provincial ICT Network Infrastructure
services as per the Maintenance and
Infrastructure Plans

Provisioning and Maintenance of


Provincial ICT Network Infrastructure
services as per the Maintenance and
Infrastructure Plans

Continuous update of the OTP Asset


register

Continuous update of the OTP Asset


register

Continuous update of the OTP Asset


register

Report on Asset verification and updated


Asset Register

Monitoring of the Microsoft EA and


ESET NOD32 Licenses

Approved Microsoft EA and ESET


NOD32 upgrade

Installed base for Microsoft EA and


ESET NOD32

Maintenance of Provincial Server Room


equipment

Final Technical Specifications for the


implementation of the Provincial VPN

Implemented Phase 1 (Data) of the


Provincial VPN

Phase 2 (Voice and Video) of the


Provincial VPN RFQ

Awarded Tender for the Phase 2 (video


and Voice) of the VPN

70

CHIEF DIRECTORATE NAME: PROVINCIAL INFORMATION MANAGEMENT


UNIT

SECTION NAME: N/A

PROJECT NAME: GIS SERVICE PROVISION

BUDGET ALLOCATION: R250 000

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.25 Level of implementation of spatial referencing of government information through Geographical Information System (GIS)
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Report on Spatial Referencing of


Provincial Departments

Report on Spatial Referencing of


Provincial Departments

Report on Spatial Referencing of


Provincial Departments

Report on Spatial Referencing of


Provincial Departments

80 Employees trained in the usage of


GIS

80 Employees trained in the usage of


GIS

40 Employees trained in the usage of


GIS

An approved GIS Training Plan

Number of mapping request completed

Number of mapping request completed

Number of mapping request completed

Number of mapping request completed

71

CHIEF DIRECTORATE NAME: PROVINCIAL INFORMATION MANAGEMENT


UNIT

SECTION NAME: N/A

PROJECT NAME: IT DISASTER RECOVERY PLAN FOR OFFICE OF THE


PREMIER

BUDGET ALLOCATION: R4m

STRATEGIC OBJECTIVE: Effectively coordinate and build the capacity of the public sector towards social and institutional transformation
PERFORMANCE INDICATOR
2.26 Level of implementation of phase two of the IT Disaster Recovery Plan for Office of the Premier
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Performance Assessment and
Procurement of hardware for the DRP
solution

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED QUARTER 2


ACTIVITIES
DRP Solution (Virtualization and
Replication) implementation

DRP Solution (Virtualization and


Replication) implementation

72

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Development of procedure manuals to
restore services and testing of Disaster
Recovery Solution

Programme 3: Policy and Governance


Sub-Programme 3.1: Office of the Deputy Director General
DIRECTORATE: DDGS OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R354 000

STRATEGIC OBJECTIVES: All strategic objectives applicable to Programme 3


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 3
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate the Programme Executive


Management meetings for the
programme and follow up on the
decisions thereof

Coordinate the Programme Executive


Management meetings for the
programme and follow up on the
decisions thereof

Coordinate the Programme Executive


Management meetings for the
programme and follow up on the
decisions thereof

Coordinate the Programme Executive


Management meetings for the
programme and follow up on the
decisions thereof

Compile monthly, quarterly, mid-year


and annual reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement

Compile monthly, quarterly, mid-year


and annual reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement

Compile monthly, quarterly, mid-year


and annual reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement

Compile monthly, quarterly, mid-year


and annual reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate general programme


meetings and follow up decisions thereof

Coordinate all planning activities for the


Programme and resulting in the
submission of draft Programme APP
and budget.

Coordinate all planning activities for the


Programme and resulting in the
submission of the draft Programme APP
and budget

Coordinate all planning activities for the


Programme and resulting in the
finalisation of the Programme Plans
(APP, Operational Plan, Monthly Activity
Plans, Cash flows, Procurement Plans)

Ensure all managers and staff in the


programme are evaluated through the
PMDS

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the first quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the second quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the third quarter)

Ensure that all staff in the programme


have valid performance contracts for

Ensure that all staff members have valid


performance agreements for the next

73

DIRECTORATE: DDGS OFFICE

SECTION NAME: N/A

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R354 000

STRATEGIC OBJECTIVES: All strategic objectives applicable to Programme 3


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 3
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

2013/14 financial year

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
financial year

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Correspondence Administration

Correspondence Administration

Correspondence Administration

Correspondence Administration

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor expenditure patterns of the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

Monitor Risk Management in the


Programme

74

Sub-Programme 3.2: Performance Monitoring and Evaluation


CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: COORDINATION OF PERFORMANCE REPORTING

BUDGET ALLOCATION: R300 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.1 Number of departments submitting credible quarterly performance reports
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of the concept document,


Standard Operating Procedure (SOP)
and Annual Schedule for Reporting

Implementation of the SOP

Implementation of the SOP

Implementation of the SOP

Development of a Framework and


Criteria for analysing Quarterly
Performance Reports

Collection of Departmental Quarterly


Performance Reports as per SOP and
Schedule

Collection of Departmental Quarterly


Performance Reports as per SOP and
Schedule

Collection of Departmental Quarterly


Performance Reports as per SOP and
Schedule

Consultations on the (SOP) and Annual


Schedule for Reporting with
departments

Analysis of Departmental Quarterly


Reports

Analysis of Departmental Quarterly


Reports

Analysis of Departmental Quarterly


Reports

Submitting the draft SOP and Schedule


for approval to the OTP and Provincial
Management structures
Finalisation of the SOP and Schedule

Production of Draft Analysis Report

Production of Draft Analysis Report

Production of Draft Analysis Report

Consultation with stakeholders on the


Draft Analysis report

Consultation with stakeholders on the


Draft Analysis report

Consultation with stakeholders on the


Draft Analysis report

Advocating the SOP with relevant


stakeholders

Updating and finalisation of the Analysis


report

Updating and finalisation of the Analysis


report

Updating and finalisation of the Analysis


report

Presentation of the final Analysis Report


to Provincial Management Structures for
endorsement

Presentation of the final Analysis Report


to Provincial Management Structures for
endorsement

Presentation of the final Analysis Report


to Provincial Management Structures for
endorsement

Produce an annual report on the


implementation of the SOP

75

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: IMPROVING MANAGEMENT PERFORMANCE INFORMATION

BUDGET ALLOCATION: R150 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.1 Number of departments submitting credible quarterly performance reports
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of the concept document


for analysing departmental frameworks
for managing performance information

Development of an Assessment
Framework for analysing the quality of
departmental Frameworks for managing
performance information

Development of an Assessment
Framework for analysing the quality of
departmental Frameworks for managing
performance information

Development of an Assessment
Framework for analysing the quality of
departmental Frameworks for managing
performance information

Development of draft provincial


guidelines for managing performance
information in provincial departments

Setting up of an Analysis Team


(ECSECC and Provincial Treasury)

Assessment of the quality of frameworks


and guidelines for improving the
management of performance information
in the province in 4 departments

Assessment of the quality of frameworks


and guidelines for improving the
management of performance information
in the province in 4 departments

Collection of departmental Frameworks


for managing performance information

Assessment of the quality of frameworks


and guidelines for improving the
management of performance information
in the province in 5 departments

Produce a draft report

Produce a draft report

Produce a draft report

Engage with relevant departments on


the draft report

Engage with relevant departments on


the draft report

Engage with relevant departments on


the draft report

Update and finalise the report

Update and finalise the report

Update and finalise the report

Present the report to OTP Management


Structures

Develop a consolidated report for 13


Departments

Present the report to OTP and Provincial


Management Structures for
endorsement

Present the report to OTP Management


Structures

76

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: COORDINATION OF OVERSIGHT OF THE PROVINCIAL


PRESIDENTIAL SCHOOLS AND ASIDI PROGRAMME

BUDGET ALLOCATION: R50 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.1 Number of departments submitting credible quarterly performance reports
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of the concept document


Standard Operating Procedure (SOP)
and Schedule for Presidential Schools
and ASIDI Reporting

Engagement of stakeholders on the


Draft report on Presidential Schools and
ASIDI schools

Collection of Quarter 2 ASIDI and


Presidential Schools Performance
Reports as per SOP

Collection of Quarter 3 ASIDI and


Presidential Schools Performance
Reports as per SOP

Endorsement of SOPs and Schedule by


Programme Head

Finalisation of the Presidential Schools


and ASIDI schools report

ASIDI and Presidential Schools Site


Visits (49 schools second phase)

Production of Progress Report on the


Presidential Schools and ASIDI schools

Collection of Quarter 4 (for the 12/13


financial year) ASIDI and Presidential
Schools Performance Reports as per
SOP

Presentation of Presidential Schools and


ASIDI schools report to Provincial
Management structures for endorsement

Production of Progress Report on the


Presidential Schools and ASIDI schools

Engagement of stakeholders on the


Draft report on Presidential Schools and
ASIDI schools

ASIDI (49 schools first phase) and


Presidential Schools Site Visits

Presentation of the final reports to


EXCO

Engagement of stakeholders on the


Draft report on Presidential Schools and
ASIDI schools

Finalisation of the Presidential Schools


and ASIDI schools report

Production of Progress Report on the


Presidential Schools and ASIDI schools

Collection of Quarter 1 ASIDI and


Presidential Schools Performance
Reports

Finalisation of the Presidential Schools


and ASIDI schools report

Presentation of Presidential Schools and


ASIDI schools report to Provincial
Management structures for endorsement

Production of Progress Report on the


Presidential Schools and ASIDI schools

Presentation of Presidential Schools and


ASIDI schools report to Provincial
Management structures for endorsement

Presentation of the final reports to


EXCO

77

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME : N/A

PROJECT NAME: DEVELOPMENT OF PERFORMANCE MONITORING &


KNOWLEDGE MANAGEMENT SYSTEM IN PARTNERSHIP WITH DPME

BUDGET ALLOCATION: R1 500 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.1 Number of departments submitting credible quarterly performance reports
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Endorsement of the Concept Document


by OTP Management Structures

Presentation of the system at Provincial


Top Management meeting

Advocate the Performance Monitoring


and Knowledge Management System to
the relevant stakeholders

Formulation of the work group that will


spearhead implementation of the system

Approval of the System

Training of all departmental M& E


officers.

Formulate a business case to guide the


system

Testing of the system

Piloting of the system

Development of the System

Hands on support from DPME to OTP


M&E officials.

Hands on support from DPME to the


departmental M&E officials.

78

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Launch of the system

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: PREPARATION OF THE PERFORMANCE REPORTS TO


BUDGET ALLOCATION: R50 000
MAKGOTLA
STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.2 Number of provincial performance oversight reports processed
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of Standard operating


Procedures (SOPS) for Makgotla
reporting

Collection of performance progress as


per PCMT and Quarterly Performance
Reporting SOPS

Collection of performance progress as


per PCMT and Quarterly Performance
Reporting SOPS

Draft Consolidated Report produced

Draft Consolidated Report produced

Draft Powerpoint Presentations


Produced

Draft Powerpoint Presentations


Produced

Presentation of Draft Report and


Powerpoint in Clusters, Provincial
Management and EXCO for verification
and endorsement

Presentation of Draft Report and


Powerpoint in Clusters, Provincial
Management and EXCO for verification
and endorsement

Printing and Distribution of reports to


Cabinet Secretariat

Printing and Distribution of reports to


Cabinet Secretariat

79

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: PCMT OVERSIGHT ENGAGEMENTS AND REPORTING

BUDGET ALLOCATION: R50 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.2 Number of provincial performance oversight reports processed
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Develop Standard Operating Procedures


and an annual schedule of the PCMT

Collection of performance reports as per


SOPS

Collection of performance reports as per


SOPS

Collection of performance reports as per


SOPS

Development and approval of the format


of the PCMT report to EXCO and
Provincial Management

Verification of information

Verification of information

Verification of information

Development of a plan to support


departments post-PCMT

Development and submission of prePCMT reports (analysis of departmental


performance for consideration by PCMT)

Development and submission of prePCMT reports (analysis of departmental


performance for consideration by PCMT)

Development and submission of prePCMT reports (analysis of departmental


performance for consideration by PCMT)

Engagement with stakeholders on the


SOPS, annual schedule and format of
the PCMT report for endorsement

PCMT engagements take place (first


Quarter Report and Annual Reports)

PCMT engagements take place (Quarter


2 Reports)

PCMT engagements take place (Quarter


3 Reports)

Compilation of post-PCMT reports

Compilation of post-PCMT reports

Compilation of post-PCMT reports

Implementation of the plan to support


departments post-PCMT (including
feedback/correspondence to HODs)
Submission of post-PCMT reports for
consideration by Provincial Management
Structures and endorsement by EXCO

Implementation of the plan to support


departments post-PCMT (including
feedback/correspondence to HODs)
Submission of post-PCMT reports for
consideration by Provincial Management
Structures and endorsement by EXCO

Implementation of the plan to support


departments post-PCMT (including
feedback/correspondence to HODs)
Submission of post-PCMT reports for
consideration by Provincial Management
Structures and endorsement by EXCO

Collection of performance reports as per


SOPS
-

80

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: END OF TERM REPORT

BUDGET ALLOCATION: R500 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.3 Number of evaluations/impact assessment conducted to evaluate the impact of government policies and programmes on the lives of people in the province
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Preparation of a Concept Document on


the End of Term Report (2009-2014)

Submit Final Report to EXCO for


endorsement

Engagement of stakeholders (Clusters,


on the findings of the report

Engagement of stakeholders on the


findings of the report

Approval of the evaluation by EXCO


(before the end of March 2013)

Printing and distribution of the report

Preparation of Terms of Reference for


the End of Term Report

Initiation of procurement of capacity to


support the Evaluation

Appointment of the Service Provider to


support the evaluation

Setting up of the Project Steering


Committee for the Evaluation

Desk-top Data collection and Data


Analysis

Site visits for verification (see separate


Project Plan)

Management of the Service Provider


(weekly Project Steering Committee
reports)

Produce draft Evaluation Report

Engage stakeholders on the findings of


the Report

Update report as per inputs from


stakeholders produce final report

81

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: SITE VISITS - CONTRACT EIGHT (8) SERVICE DELIVERY


BUDGET ALLOCATION: R1500 000
VERIFICATION OFFICERS FOR 5 MONTHS
STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.3 Number of evaluations/impact assessment conducted to evaluate the impact of government policies and programmes on the lives of people in the province
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

Concept document approved (by 31


March 2013)
Posts approved by Premier (by 31
March 2013)
Verification Team and one Team Leader
reports for duty at Office of the Premier
(PME Unit)
Orientation of the team (including
Communication Officers, Community
Development Workers and Service
Delivery Facilitators), planning the visits
and review of annual reports and APPs
of departments.
Development of a draft service delivery
report
Development of a site verification tool
and framework for capturing and
reporting
Verification Team reports for duty in 6
District Municipalities and 2 Metros.
Site Visits and capturing of data as per
reporting framework

Site Visits and capturing of data as per


reporting framework
Mopping up visits and compilation of the
draft consolidated report.

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Engagement with stakeholders on draft


report

Update and produce final report.

Table report to EXCO for endorsement


Printing and distribution of report

82

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: EVALUATION OF TRANSVERSAL TRAINING IN THE


PROVINCE

BUDGET ALLOCATION: R350 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.3 Number of evaluations/impact assessment conducted to evaluate the impact of government policies and programmes on the lives of people in the province
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Preparation of a Concept Document on


the Evaluation of Transversal Training,
in collaboration with IDOS

Appointment of the Service Provider to


support the evaluation

Produce draft Evaluation Report

Printing and distribution of the report

Approval of the evaluation by EXCO


(before the end of March 2013)

Setting up of the Project Steering


Committee for the Evaluation

Engage stakeholders on the findings of


the Report

Engage stakeholders on the findings of


the final report

Preparation of Terms of Reference for


the Evaluation of Transversal Training in
the Province, in collaboration with IDOS

Data collection and Data Analysis

Update report as per inputs from


stakeholders produce final report

Procurement of capacity to support the


Evaluation

Management of the Service Provider


(weekly Project Steering Committee
reports)

Submit Final Report to EXCO for


endorsement

83

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: EVALUATION OF COORDINATION OF INFRASTRUCTURE


DELIVERY

BUDGET ALLOCATION: R350 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.3 Number of evaluations/impact assessment conducted to evaluate the impact of government policies and programmes on the lives of people in the province
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Preparation of a Concept Document on


the Evaluation of the coordination of
infrastructure delivery

Appointment of the Service Provider to


support the evaluation

Data collection and Data Analysis

Update report as per inputs from


stakeholders produce final report

Approval of the evaluation by EXCO


(before the end of March 2013)

Setting up of the Project Steering


Committee for the Evaluation

Management of the Service Provider


(weekly Project Steering Committee
reports)

Submit Final Report to EXCO for


endorsement

Preparation of Terms of Reference for


the Evaluation of the coordination of
infrastructure delivery in the Province

Produce draft Evaluation Report

Printing and distribution of the report

Procurement of capacity to support the


Evaluation

Engage stakeholders on the findings of


the Report

Engage stakeholders on the findings of


the final report

84

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF MPAT

BUDGET ALLOCATION: R20 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.11 Number of departments conducting effective management performance assessments
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of a draft Provincial MPAT


concept document and implementation
plan for 2013/14 (including the
production of improvement plans), in
collaboration with IDOS

Endorsement of Provincial MPAT


implementation plan by Provincial
Management

Implementation of the Provincial MPAT


Plan for 2013/14, in collaboration with
IDOS

Compilation of the Provincial MPAT


Report, in collaboration with IDOS

Consultation with relevant stakeholders


on the draft implementation plan 13/14,
in collaboration with IDOS

Monitor and report on the production of


improvement plans by departments (in
collaboration with IDOS)

Provide support to ensure that all 13


Departments conduct MPAT
Assessments, in collaboration with IDOS

Engagement with stakeholders on the


2013/14 MPAT report, in collaboration
with IDOS

Consultation with all Provincial


Departments on the 2012/13 MPAT
results, in collaboration with IDOS

Endorsement of the 2013/14 MPAT


report by Provincial Management

Develop a support plan for all


Departments for the production of
improvement plans (in collaboration
with IDOS)

85

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: PROVINCIAL MANAGEMENT OVERSIGHT PLAN/ FOSAD


PLAN APPROVED AND REPORTING

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.12 Number of monitoring reports on the provincial management oversight plan (FOSAD plan)
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Finalise the Provincial Management


Plan/FOSAD plan

Collection of data on finalised plan

Collection of data on finalised plan

Collection of data on finalised plan

Present the Provincial Management


Plan/FOSAD plan to Provincial
Management for endorsement

Analysis of data received

Analysis of data received

Analysis of data received

Produce First Quarter report on the


Provincial Management Plan/FOSAD
plan

Produce Second Quarter Report on the


Provincial Management Plan/FOSAD
plan

Produce Third Quarter Report on the


Provincial Management Plan/FOSAD
plan

Presentation of report to management


structures

Presentation of report to management


structures

Presentation of report to management


structures

Presentation of report to EXCO

Presentation of report to EXCO

Presentation of report to EXCO

86

CHIEF DIRECTORATE NAME: PERFORMANCE MONITORING & EVALUATION

SECTION NAME: N/A

PROJECT NAME: IMPLEMENTATION OF FRONT LINE SERVICE DELIVERY

BUDGET ALLOCATION: R100 000

STRATEGIC OBJECTIVE: Provincial monitoring, reporting and evaluation framework fully implemented
PERFORMANCE INDICATOR
3.13 Number of monitoring reports on frontline service delivery
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Formulation of a concept document and
the Annual FSD Plan 2013/14

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Annual FSD Plan implemented and


monitored

Annual FSD Plan implemented and


monitored

Draft Annual Report on the


implementation of the Annual FSD Plan
is produced

Site visits conducted

Site visits conducted

Engagement with stakeholders on the


Draft Annual Report

Identification and approval of the Annual


FSD sites

Draft Report produced

Draft Report produced

Updating and finalisation of Annual


Report

Stakeholder and Public Awareness of


the Annual FSD Plan

Engagement with stakeholders on the


Draft Monitoring Report

Engagement with stakeholders on the


Draft Monitoring Report

Endorsement of the Annual FSD Report


by EXCO

Updating and finalisation of Monitoring


Report

Updating and finalisation of Monitoring


Report

FSD concept document approved

87

Sub-Programme 3.3: Service Delivery Intervention and Co-ordination Support


CHIEF DIRECTORATE NAME: SERVICE DELIVERY INTERVENTION & COORDINATION SUPPORT

SECTION NAME: N/A

PROJECT NAME: PREMIERS SERVICE DELIVERY INTERVENTION

BUDGET ALLOCATION: R400 000

STRATEGIC OBJECTIVE: To co-ordinate and facilitate service delivery intervention


PERFORMANCE INDICATOR
3.4 Quarterly monitoring of the implementation of the Presidents and Premiers service delivery initiatives
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Project identification

Establish Project Committees

Project management and monitoring

Project management and monitoring

Project assessments

Draft and facilitate signing of


Memorandum of Agreements (MOAs)

Coordinate and attend Project


Committee Meetings

Stakeholder management

Stakeholder mobilisation and


management

Resource mobilisation and Management

Support implementation of projects

Coordinate and attend Project


Committee Meetings

Develop projects business plans

Procurement of Professional Services

Stakeholder management

Support implementation of projects

Establish Institutional arrangements

Coordinate and attend Project


Committee Meetings

Reporting

Project evaluation and close out

Coordinate and attend Project


Committee Meetings

Support implementation of projects

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

Progress reporting

Progress reporting

Progress reporting

Progress reporting

88

CHIEF DIRECTORATE NAME: SERVICE DELIVERY INTERVENTION & COORDINATION SUPPORT

SECTION NAME: N/A

PROJECT NAME: PRESIDENTIAL SERVICE DELIVERY INTERVENTIONS

BUDGET ALLOCATION: R250 000

STRATEGIC OBJECTIVE: To co-ordinate and facilitate service delivery intervention


PERFORMANCE INDICATOR
3.4 Quarterly monitoring of the implementation of the Presidents and Premiers service delivery initiatives
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Establish / support Institutional


arrangements

Stakeholder coordination and


management

Stakeholder coordination and


management

Stakeholder coordination and


management

Stakeholder coordination and


management

Coordinate and attend meetings

Coordinate and attend meetings

Coordinate and attend meetings

Coordinate and attend meetings

Site inspections

Site inspections

Site inspections

Site inspections

Provide strategic reports

Provide strategic reports

Provide strategic reports

Provide strategic reports

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

Development of pre and post service


delivery visit reports

89

CHIEF DIRECTORATE NAME: SERVICE DELIVERY INTERVENTION & COORDINATION SUPPORT

SECTION NAME: N/A

PROJECT NAME: EXCO OUTREACH

BUDGET ALLOCATION: R600 000

STRATEGIC OBJECTIVE: To co-ordinate and facilitate service delivery intervention


PERFORMANCE INDICATOR
3.5 Percentage of EXCO outreach commitments implemented
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of the Previous years


EXCO outreach baseline data (issues
and commitments)

Production of pre EXCO outreach


service delivery reports

Production of pre EXCO outreach


service delivery reports

Production of pre EXCO outreach


service delivery reports

Interface with government institutions


and relevant stakeholders on service
delivery matters

Interface with government institutions


and relevant stakeholders on service
delivery matters

Interface with government institutions


and relevant stakeholders on service
delivery matters

Interface with government institutions


and relevant stakeholders on service
delivery matters

Production of pre EXCO outreach


service delivery reports

Stakeholder coordination and


management

Stakeholder coordination and


management

Stakeholder coordination and


management

Stakeholder coordination and


management

Production of post EXCO outreach


service delivery reports

Production of post EXCO outreach


service delivery reports

Production of post EXCO outreach


service delivery reports

Quarterly reporting

Conduct service delivery site


verifications

Conduct service delivery site


verifications

Conduct service delivery site


verifications

Quarterly reporting

Quarterly reporting

Quarterly reporting

Redevelopment and maintenance


(update) of service delivery database

Redevelopment and maintenance


(update) of service delivery database

Redevelopment and maintenance


(update) of service delivery database

Production of annual report on


implementation of EXCO outreach
matters

90

CHIEF DIRECTORATE NAME: SERVICE DELIVERY INTERVENTION & COORDINATION SUPPORT

SECTION NAME: N/A

PROJECT NAME: SERVICE DELIVERY INTERVENTIONS AND SUPPORT

BUDGET ALLOCATION: R300 000

STRATEGIC OBJECTIVE: To co-ordinate and facilitate service delivery intervention


PERFORMANCE INDICATOR
3.14 Level of implementation of service delivery intervention initiatives
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Conduct investigations on service


delivery requests for intervention

Conduct investigations on service


delivery requests for intervention

Conduct investigations on service


delivery requests for intervention

Conduct investigations on service


delivery requests for intervention

Coordination and management of


government institutions and
stakeholders

Coordination and management of


government institutions and
stakeholders

Coordination and management of


government institutions and
stakeholders

Coordination and management of


government institutions and
stakeholders

Interface with communities and


appealing stakeholders

Interface with communities and


appealing stakeholders

Interface with communities and


appealing stakeholders

Interface with communities and


appealing stakeholders

Production of preliminary reports

Production of preliminary reports

Production of preliminary reports

Production of preliminary reports

Develop action plans with catalytic


projects

Develop action plans with catalytic


projects

Develop action plans with catalytic


projects

Develop action plans with catalytic


projects

Manage and monitor implementation

Manage and monitor implementation

Manage and monitor implementation

Manage and monitor implementation

Conduct site verifications

Conduct site verifications

Conduct site verifications

Conduct site verifications

Production of progress reports and


update

Production of progress reports and


update

Production of progress reports and


update

Production of progress reports and


update

Develop support mechanism and close


out

Develop support mechanism and close


out

Develop support mechanism and close


out

Develop support mechanism and close


out

Develop annual analysis report on


Service Delivery Intervention initiatives

91

Sub-Programme 3.4: Policy Planning and Research Co-ordination


CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH
COORDINATION

SECTION NAME: N/A

PROJECT NAME: GOVERNMENT CLUSTER SYSTEM

BUDGET ALLOCATION: R250 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the Province
PERFORMANCE INDICATOR
3.6 Level of functionality of the government cluster system
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of the Cluster Schedule as


per the POA

Review of the Cluster Schedule

Review of the Cluster Schedule

Review of the Cluster Schedule

Develop the cluster status quo report


and a review concept

Production of the Lekgotla concept and


report

Implementation of the review plan

Development and approval of the POA

Production of the cluster review plan

Implementation of the review plan

Production of the cluster monthly and


quarterly reports

Evaluation of the review plan

Production of the cluster monthly and


quarterly reports

Production of the cluster monthly and


quarterly reports

Coordination of departmental priority


activities

Production of the cluster monthly and


quarterly reports

Coordination of departmental priority


activities

Coordination of the POA implementation

Assessment of Cluster performance

Production of annual cluster


performance/review report

Assessment of Cluster performance

Follow-up on departmental priority


activities

Coordination of departmental priority


activities

Assessment of Cluster performance

Assessment of Cluster performance

Development and approval of the


concept for the assessment of APPs

Analysis of APPs

Production of a detailed assessment


report for 2013/14 APPs

Final analysis of the 2014/15 APPs

Development of the assessment criteria


and finalisation of the tools

Production of departmental specific


findings based on the analysis

Analysis of 2014/15 draft APPs

Production of a detailed report for


2014/15 draft 3 APPs

Interface with departments on the


concept and criteria

Conduct one on one engagements and


workshops with departments to table
criteria and approach for assessment.

Conduct one on one engagements and


workshops with departments to provide
feedback

Reporting

Collation of departmental APPs

Reporting

Production of report on the assessment


of the draft APPs

Reporting

Reporting

92

CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH


COORDINATION

SECTION NAME: : N/A

PROJECT NAME: ASSESSMENT OF PROVINCIAL DEPARTMENTS APPs

BUDGET ALLOCATION: R50 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the Province
PERFORMANCE INDICATOR
3.7 Number departments with credible APPs that are aligned to the Provincial priorities
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development and approval of the


concept for the assessment of APPs

Analysis of APPs

Production of a detailed assessment


report for 2013/14 APPs

Final analysis of the 2014/15 APPs

Development of the assessment criteria


and finalisation of the tools

Production of departmental specific


findings based on the analysis

Analysis of 2014/15 draft APPs

Production of a detailed report for


2014/15 draft 3 APPs

Interface with departments on the


concept and criteria

Conduct one on one engagements and


workshops with departments to table
criteria and approach for assessment.

Conduct one on one engagements and


workshops with departments to provide
feedback

Reporting

Collation of departmental APPs

Reporting

Production of report on the assessment


of the draft APPs

93

CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH


COORDINATION

SECTION NAME: : N/A

PROJECT NAME: PROVINCIAL INFRASTRUCTURE SERVICE DELIVERY PLAN

BUDGET ALLOCATION: R389 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the Province
PERFORMANCE INDICATOR
3.8 Number of Departments with approved Infrastructure Delivery Plans
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Identification and assessment of all


infrastructure delivery in the province

Develop a Diagnostic report on


infrastructure delivery in the Province
per sector

Consult with stakeholders

Collation of the data

Procure service provider

Consult with sector partners

Establish institutional arrangements

94

Service Delivery plans for the following


departments complete on time: Health;
Education; Human Settlements;
DSRAC; and Roads and Public Works

CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH


COORDINATION

SECTION NAME: : N/A

PROJECT NAME: NDP IMPLEMENTATION FACILITATION

BUDGET ALLOCATION: R600 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the Province
PERFORMANCE INDICATOR
3.9 Level of readiness to implement the National Development Plan in the Province
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Create awareness about the NDP in the


Province (advertisement, printing,
translation, marketing)

Create awareness about the NDP in the


Province (advertisement, printing,
translation, marketing)

Create awareness about the NDP in the


Province (advertisement, printing,
translation, marketing)

Create awareness about the NDP in the


Province (advertisement, printing,
translation, marketing)

Provide support to the ECPC in


government and municipal participation
in the development of the plan

Provide support to the ECPC in


government and municipal participation
in the development of the plan

Provide support to the ECPC in


government and municipal participation
in the development of the plan

Provide support to the ECPC in


government and municipal participation
in the development of the plan

Facilitate regular quarterly engagements


between the ECPC and the Premier and
the DG

Facilitate regular quarterly engagements


between the ECPC and the Premier and
the DG

Facilitate regular quarterly engagements


between the ECPC and the Premier and
the DG

Development of the NDP


implementation plan for the Province

95

CHIEF DIRECTORATE NAME: POLICY PLANNING AND RESEARCH


COORDINATION

SECTION NAME: : N/A

PROJECT NAME: DEVELOPMENT AND APPROVAL OF THE YOUTH


STRATEGY

BUDGET ALLOCATION: R547 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the Province
PERFORMANCE INDICATOR
3.10 Youth Development Strategy Approved
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Assessment youth initiatives in the


departmental programmes

Production of youth initiatives status quo


report

Procurement of a service provider

Development and approval of


conceptual framework

Consultation of stakeholders to present


the report

Development of a draft strategy

Approved youth strategy

Project scoping

Consultation of stakeholders

96

CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH


COORDINATION

SECTION NAME: : N/A

PROJECT NAME: PROVINCIAL POLICY AND RESEARCH AGENDA

BUDGET ALLOCATION: R950 000

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the province
PERFORMANCE INDICATOR
Number of provincial policy research programmes conducted
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Conduct assessment and scope of the


provincial policy and research agenda

Review the plan

Management of research projects

Production of final research reports

Consultations with departments and


policy forums.

Initiate research projects (review of rural


development strategy, Review of the
Urban Renewal Programme)

Production of draft research reports

Presentation of the research reports to


stakeholders

Develop Process Mapping for planning,


policy development and research

Reporting

Reporting

Reporting

97

Approval of research reports


Reporting

CHIEF DIRECTORATE NAME: POLICY PLANNING & RESEARCH


COORDINATION

SECTION NAME: N/A

PROJECT NAME: PROVISION OF OVERSIGHT TO SURUDEC AND ECSECC

BUDGET ALLOCATION: N/A

STRATEGIC OBJECTIVE: To lead the coordination of policy, planning and research in the province
PERFORMANCE INDICATOR
3.15 Quarterly Review of ECSECC performance
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Production of oversight guidelines and


plan

Oversight engagements on quarterly


performance with SURUDEC and
ECSECC

Oversight engagements on quarterly


performance with SURUDEC and
ECSECC

Development and approval of SLAs for


the next financial year

Management of SLA

Facilitate flow of funds as per the SLA

Facilitate flow of funds as per the SLA

Oversight engagements on quarterly


performance with SURUDEC and
ECSECC

Facilitate flow of funds as per the SLA

Facilitate flow of funds as per the SLA

98

Programme 4: Executive Support Services


Sub-Programme 4.1: Office of the Deputy Director General
DIRECTORATE: DDGs OFFICE

SECTION NAME: EXECUTIVE SUPPORT SERVICES

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R387 000

STRATEGIC OBJECTIVE: All strategic objectives applicable to Programme 4


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 4
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate Branch management


meetings and follow up decisions
thereof: DDGs Office and Subdirectorates

Coordinate Branch management


meetings and follow up decisions
thereof: DDGs Office and Subdirectorates

Coordinate Branch management


meetings and follow up decisions thereof
: DDGs Office and Sub-directorates

Coordinate Branch management


meetings and follow up decisions
thereof: DDGs Office and Subdirectorates

Compile monthly performance reports


and quarterly reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement:
Monitor Sub-branch POE
Escalate areas of decision making
and advise thereof

Compile monthly performance reports


and quarterly reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement:
Monitor Sub-branch POE
Escalate areas of decision making
and advise thereof

Compile monthly performance reports


and quarterly reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement:
Monitor Sub-branch POE
Escalate areas of decision making
and advise thereof

Compile monthly performance reports


and quarterly reports for the programme
and ensure that there is credible
evidence associated with all reported
achievement:
Monitor Sub-branch POE
Escalate areas of decision making
and advise thereof

Provide support to sub-branches on


high-level Projects and Executive
decisions, include:-

Provide support to sub-branches on


high-level Projects and Executive
decisions, include:-

Provide support to sub-branches on


high-level Projects and Executive
decisions, include:-

Provide support to sub-branches on


high-level Projects and Executive
decisions, include:-

Coordination of EXCO Outreach


Steering Committee
Monitor progress on High Level
projects, such as HoL
Facilitate and monitor Internal and
External intervention projects or

Coordination of EXCO Outreach


Steering Committee
Monitor progress on High Level
projects, such as HoL

Coordination of EXCO Outreach


Steering Committee
Monitor progress on High Level
projects, such as HoL

Facilitate and monitor Internal and


External intervention projects or

Facilitate and monitor Internal and


External intervention projects or

99

Coordination of EXCO Outreach


Steering Committee
Monitor progress on High Level
projects, such as HoL
Facilitate and monitor Internal and
External intervention projects or

DIRECTORATE: DDGs OFFICE

SECTION NAME: EXECUTIVE SUPPORT SERVICES

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R387 000

STRATEGIC OBJECTIVE: All strategic objectives applicable to Programme 4


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 4
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
requests from DDG and Sub-branches,
include SATMA, Ex-mine Workers PSC
and/or any other intervention deemed
necessary for DDGs Office.

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES
requests from DDG and Sub-branches,
include SATMA, Ex-mine Workers PSC
and/or any other intervention deemed
necessary for DDGs Office.

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

requests from DDG and Sub-branches,


include SATMA, Ex-mine Workers PSC
and/or any other intervention deemed
necessary for DDGs Office.

requests from DDG and Sub-branches,


include SATMA, Ex-mine Workers PSC
and/or any other intervention deemed
necessary for DDGs Office.

Coordinate all planning activities for the


Programme and resulting in the
submission of the draft programme APP
and budget

Coordinate all planning activities for the


Programme and resulting in the
finalisation of the programme Plans
(APP, Operational Plan, Cash flows,
Procurement Plans)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the first quarter)

Ensure that performance review for all


staff in the programme are conducted
and moderated (for the second quarter)

Ensure that all SMS member have


valid performance agreements for
the next financial year
Ensure that performance review for
all staff in the programme are
conducted and moderated (for the
third quarter)

Compile Special Reports and responses


for Portfolio Committee, PCMT,

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Compile Portfolio Committee Reports

Correspondence Administration,
acknowledgements and responses

Correspondence Administration,
acknowledgements and responses

Correspondence Administration,
acknowledgements and responses

Correspondence Administration,
acknowledgements and responses

Coordinate/Facilitate/Monitor
functionality of Branch Monitoring
Committees:

Coordinate monthly Finance committee:


Monitor invoicing and Expenditure
patterns

Coordinate/Facilitate/Monitor
functionality of Branch Monitoring
Committees:

Coordinate monthly Finance committee:


Monitor invoicing and Expenditure
patterns

Coordinate all planning activities for the


Programme and resulting in the
submission of draft programme APP and
budget.
Ensure that all staff in the programme
have valid performance contracts for
2013/14 financial year
Ensure all managers and staff in the
programme are evaluated through the
PMDS; Ensure PMDS Programme
Committee functionality

Finance Committee - Monitor


expenditure patterns of the
Programme

Finance Committee - Monitor


expenditure patterns of the
Programme

100

DIRECTORATE: DDGs OFFICE

SECTION NAME: EXECUTIVE SUPPORT SERVICES

PROJECT NAME: OVERALL PROGRAMME MANAGEMENT

BUDGET ALLOCATION: R387 000

STRATEGIC OBJECTIVE: All strategic objectives applicable to Programme 4


PERFORMANCE INDICATORS
All performance indicators applicable to Programme 4
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Training Committee
PMDS Programme Committee
Monitor risk management indicators and
performance of Sub-branches

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Training Committee
PMDS Programme Committee
Monitor risk management indicators and
performance of Sub-branches

Monitor risk management indicators and


performance of Sub-branches

101

Monitor risk management indicators and


performance of Sub-branches

Sub-Programme 4.2: Cabinet Secretariat and Protocol Services


CHIEF DIRECTORATE NAME: CABINET SECRETARIAT & PROTOCOL
SERVICES

SECTION NAME: N/A

PROJECT NAME: RENDER CABINET SECRETARIAT & PROTOCOL SERVICES

BUDGET ALLOCATION: R1.3m

STRATEGIC OBJECTIVE: Lead and manage the provision of Executive support to the Premier, Executive Structures and Provincial Government
PERFORMANCE INDICATOR
4.1 Number of reports on secretariat and protocol services rendered to executive structures
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Provide Secretariat services to EXCO,


Cabinet Committees, Clusters and
Provincial Management

Provide Secretariat services to EXCO,


Cabinet Committees, Clusters and
Provincial Management

Provide Secretariat services to EXCO,


Cabinet Committees, Clusters and
Provincial Management

Provide Secretariat services to EXCO,


Cabinet Committees, Clusters and
Provincial Management

Coordinate verification and update


EXCO files and documents

Coordinate verification and update


EXCO files and documents

Coordinate verification and update


EXCO files and documents

Coordinate verification and update


EXCO files and documents

Track and report on the implementation


of EXCO resolutions

Track and report on the implementation


of EXCO resolutions

Track and report on the implementation


of EXCO resolutions

Track and report on the implementation


of EXCO resolutions

Facilitate and coordinate alignment


between the programmes of the
Legislature and EXCO

Facilitate and coordinate alignment


between the programmes of the
Legislature and EXCO

Facilitate and coordinate alignment


between the programmes of the
Legislature and EXCO

Facilitate and coordinate alignment


between the programmes of the
Legislature and EXCO

Render protocol services to the Premier


and Provincial events.

Render protocol services to the Premier


and Provincial events.

Render protocol services to the Premier


and Provincial events.

Render protocol services to the Premier


and Provincial events.

Facilitate and coordinate State functions


and visits of the President, Deputy
President, National Ministers, and
International Visits to the province.

Facilitate and coordinate State functions


and visits of the President, Deputy
President, National Ministers and
International Visits to the province.

Facilitate and coordinate State functions


and visits of the President, Deputy
President, National Ministers and
International Visits to the province.

Facilitate and coordinate State functions


and visits of the President, Deputy
President, National Ministers and
International Visits to the province.

102

Sub-Programme 4.3: Provincial Communication


CHIEF DIRECTORATET NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MARKETING & CORPORATE COMMUNICATIONS

PROGRAMME NAME: MARKETING OF THE PROVINCIAL GOVERNMENT &


BRAND THE PROVINCE

BUDGET ALLOCATION: R9 341

STRATEGIC OBJECTIVE: Enhance the Image of the provincial government and EC province
PERMANCE INDICATOR
4.2 Percentage of people rating the Provincial government and EC province positively
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Conduct public perception surveys

Conduct public perception surveys

Conduct public perception surveys

Conduct public perception surveys

Develop Draft communication plan for


the Province and OTP

Consultations on the draft plan

Implementation of plan

Implementation of plan

Manage implementation internal


communication platforms through
producing and distributing internal news
later

Manage implementation internal


communication platforms through
producing and distributing internal news
later

Manage implementation internal


communication platforms through
producing and distributing internal news
later

Manage implementation internal


communication platforms through
producing and distributing internal news
later

Manage implementation internal


communication platforms through
developing new design and content
layout and website management

Manage implementation internal


communication platforms through
developing new design and content
layout and website management

Manage implementation internal


communication platforms through
developing new design and content
layout and website management

Manage implementation internal


communication platforms through
developing new design and content
layout and website management

Communication forums facilitation (1 X


Economic and infrastructure cluster
meeting 1 X Eastern Cape Branding
and Marketing Forum meetings)

Communication forums facilitation (1 X


Cluster meeting; 1 x ECBMF Meeting)

Communication forums facilitation (1 X


Cluster meeting; 1 x ECBMF meeting)

Communication forums facilitation (1 x


Cluster meeting; 1 X ECBMF Meeting)

Develop and launch share point as an


integrated electronic communication
platform for the province

Establish a provincial networking


community in share point and Create
links with provincial websites

Create a provincial database for


communicators, Media, Stakeholder,
HOC and ICGF

Create an archiving system for press


releases, Photos, Images Campaigns,
Provincial CI Manual, Communication
Frameworks and policies

Develop and implement a new


Corporate ID for OTP through the
development of a CI manual, conducting
CI audits for OTP and the Province

Launch new CI and developing CI


compliance monitoring framework

Replace internal applications with new


CI and conduct first Quarterly audit

Replace external applications with new


CI and conduct second Quarterly Audit

Launch Home of legends (HoL)

Launch HoL national advertising

Launch HoL International competition;

Facilitate HOL Stakeholder workshop

103

CHIEF DIRECTORATET NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MARKETING & CORPORATE COMMUNICATIONS

PROGRAMME NAME: MARKETING OF THE PROVINCIAL GOVERNMENT &


BRAND THE PROVINCE

BUDGET ALLOCATION: R9 341

STRATEGIC OBJECTIVE: Enhance the Image of the provincial government and EC province
PERMANCE INDICATOR
4.2 Percentage of people rating the Provincial government and EC province positively
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Billboard campaign

campaign

Host International Media Tour; Launch


HoL public participation programme;
Launch HoL Website and Social Media
campaign

Develop creative concepts for the


promotional material and funding
proposals for HoL

Production of the HOL marketing and


promotional material

Distribute HOL Marketing and


promotional material to key stakeholders
and potential funders l

Distribute HOL Marketing and


promotional material to key stakeholders
and potential funders
Social media campaign
Billboard campaign

Launch marketing and Promotional


campaign 20 years of freedom through
publication of a Book; Booklets for
districts / metros; Interactive DVD;
Leaflets; Posters.

Provide communication support to the


EXCO Outreach program

Provide communication support to the


EXCO Outreach program

Provide communication support to the


EXCO Outreach program

Provide communication support to the


EXCO Outreach program

Provide graphic and design services to


the OTP (Design guidelines for the new
OTP CI; and Provide design services to
key events and marketing material)

Provide graphic and design services to


the OTP (Design guidelines for the new
OTP CI; and Provide design services to
key events and marketing material)

Provide graphic and design services to


the OTP (Design guidelines for the new
OTP CI; and Provide design services to
key events and marketing material)

Provide graphic and design services to


the OTP (Design guidelines for the new
OTP CI; and Provide design services to
key events and marketing material)

104

CHIEF DIRECTORATE NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MEDIA LIAISON

PROJECT NAME: MEDIA MANAGEMENT

BUDGET ALLOCATION: R6 709

STRATEGIC OBJECTIVE: Enhance the Image of the Provincial government and EC Province
PERFORMANCE INDICATOR
4.3 Percentage of net positive media representation of the provincial government in the media domain
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate quarterly communications


Cluster meetings with elements of
Media Engagement

Coordinate quarterly communications


Cluster meetings with elements of
Media Engagement meetings

Coordinate quarterly communications


Cluster meetings with elements of
Media Engagement meetings

Coordinate quarterly communications


Cluster meetings with elements of Media
Engagement meetings held

1 District /MCF Core team meeting

1 District/MCF Core Team meeting

1 District/MCF Core Team meeting

1 District/MCF Core Team meeting

1 DCF and 3 LCF meetings

1 DCF and 3 LCF meetings are held

1 DCF and 3 LCF meetings are held.

1 DCF and 3 LCF meetings are held

Celebrate information day in


SterkStroom

Celebrate information day in Great Kei


LM

Celebrate information day in Senqu LM

Celebrate information day in KSD

Information days in4 districts celebrating


20 years of freedom

Information days in 4 Districts


celebrating 20 years of freedom

Review the Communications Policy


Framework and adopt a new PCS
protocol PCS. The HoC led interdepartmental review committee to be
appointed to begin work with TOR

An IGCF led workshop is convened to


finalise a draft policy and protocol

Draft policy and protocol is tabled for


approval in the G&A Cluster, Cabinet
Committee & EXCO.

Execution of the Policy & Protocol and


Progress report submitted to leadership

Assist in the annual review of a


Communication strategy, programme of
action (POA) and execution plans.
Reviewed Provincial Communications
strategy approved by EXCO for
execution

A Reviewed draft comm. Strategy is


approved & executed

Progress report on the execution


submitted to governance structures.

Progress report on the execution


submitted to governance structures.

Coordinate the development & execution


of issue management framework
(position of government on key public
issues. Issue management framework
approved by EXCO for execution

A HoC led inter-departmental review


committee is appointed to begin work
with TOR

A service provider/partnership is
developed with research institutions or
higher learning institution for the
development if issue management
framework

Draft issue management framework is


tabled for approval in G&A Cluster,
Cabinet Committee & EXCO.

Develop and execute a mechanism for

Good news carried in government

Good news carried in government

Good news carried in government

105

CHIEF DIRECTORATE NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MEDIA LIAISON

PROJECT NAME: MEDIA MANAGEMENT

BUDGET ALLOCATION: R6 709

STRATEGIC OBJECTIVE: Enhance the Image of the Provincial government and EC Province
PERFORMANCE INDICATOR
4.3 Percentage of net positive media representation of the provincial government in the media domain
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
maximising generation and
dissemination of good news on ECPA.
Appointment of a service provider to
execute good news generation
Execution of a Public Relations
Campaign to profile the 20 years of
Freedom reporting period. Commission
writers/experts to draft pieces; and
Negotiate with print media owners to
avail leader page space.
Coordinate government efforts of
building good government media
relations. Convene a Seminar to
observe the World Press day jointly with
the media sector (03 May 2013)

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

strategic platforms/publications (All


media, Masincokole, Perspective,
website, e-mails, sms)

strategic platforms with a slant of


20years of freedom(All media,
Masincokole, Perspective, website, emails, sms)

strategic platforms (All media, with a


slant of 20years of freedom
Masincokole, Perspective, website, emails, sms)

Draft quarterly schedule with topics; and


4 x weekly Op pieces.

Draft quarterly schedule with topics; and


4 x weekly Op pieces.

Draft quarterly schedule with topics; and


4 x weekly Op pieces.

Convene an annual meeting between


Premier, EXCO and EC SANEF.

Convene Mcebisi Bata Memorial Lecture


as a platform appreciate relations
between the media & government

106

CHIEF DIRECTORATE NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MEDIA LIAISON

PROJECT NAME: MEDIA MANAGEMENT

BUDGET ALLOCATION: R6 709

STRATEGIC OBJECTIVE: Enhance the Image of the Provincial government and EC Province
PERFORMANCE INDICATOR
4.3 Percentage of net positive media representation of the provincial government in the media domain
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordinate the development and


execution of the Premiers Profiling
strategy. Appointment of the Premiers
MLO & PR advisor; development of
Strategy to profile the Premier &
approval by DG, Executive Management
& Premier; and provide Premiers PR
and content support to ensure all her
efforts and public engagements are well
publicized in the media

Execution of strategy to Profile the


Premier & progress report submitted

Execution of strategy to Profile the


Premier & progress report submitted,
linked to the Launch of 20 years of
Freedom

Execution of strategy to Profile the


Premier & progress report submitted.
linked to the celebration of 20 years of
Freedom

Participation in diary management;


drafting of speeches, backgrounders &
Op Eds; professional organisation of
media conferences; and writing of media
statements, opinion pieces & letters to
the editor.

Participation in diary management;


drafting of speeches, backgrounders &
Op Eds; professional organisation of
media conferences; and writing of media
statements, opinion pieces & letters to
the editor.

Participation in diary management;


drafting of speeches, backgrounders &
Op Eds; professional organisation of
media conferences; and writing of media
statements, opinion pieces & letters to
the editor.

Contract an independent media


monitoring agency to perform media
monitoring on behalf of govt. Advertise
tender for a period of two years

Appointment of service provider &


Service provider commences and
produces report that depicts the
coverage of the Provincial Government
and Eastern Cape

Media monitoring analyses and


continues and report produced

Media monitoring analyses and


continues report produce

Coordinate the execution of media


Rapid Response system.

Immediate responses to media enquiries


with stipulated deadlines with all affected
departments

Immediate responses to media enquiries


with stipulated deadlines with all affected
departments

Immediate responses to media enquiries


with stipulated deadlines with all affected
departments

Coordinate the execution of EXCO


quarterly Cluster M&E Media Briefings.
Submission to EXCO for the approval of
the schedule

2 quarter M&E Cluster Media Briefing


convened to reflect on progress

3 quarter M&E Cluster Media Briefing


convened to reflect on progress. To
coincide with the Premiers launch of
nd
progress report on the 2 decade of
Freedom.

4 quarter M&E Cluster Media Briefing


convened to reflect on progress to
nd
coincide with the celebration of the 2
decade of Freedom.

Coordinate the execution of Public


Information Campaigns. 10 Media slots
or features secured for the Principals/
Spokesperson to engage the public

10 Media slots or features secured for


the Principals/ Spokesperson to engage
the public

10 Media slots or features secured for


the Principals/ Spokesperson to engage
the public

10 Media slots or features secured for


the Principals/ Spokesperson to engage
the public

nd

rd

107

th

CHIEF DIRECTORATE NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MEDIA LIAISON

PROJECT NAME: MEDIA MANAGEMENT

BUDGET ALLOCATION: R6 709

STRATEGIC OBJECTIVE: Enhance the Image of the Provincial government and EC Province
PERFORMANCE INDICATOR
4.3 Percentage of net positive media representation of the provincial government in the media domain
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Strengthen cooperation with community
radio, print and TV media sector.
Organise and convene a community
media round table
Execution of the manual for maximizing
media liaison support for the EXCO
outreach programme: 80% increase of
profile of EXCO Outreach programme
Develop and Execute media liaison plan
during SOPA, Budget speech and Policy
speeches.

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

Development of scripts to profile


20years of freedom reporting period.

Execute radio adverts per cluster


reflecting progress 20 years of Freedom

80% increase of profile of EXCO


Outreach programme

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
Execute documentaries reflecting
progress 20 years of Freedom.

Develop media plan in collaboration with


Legislature & ensure approval by OTP
Executive Management

Execute media liaison support for


SOPA, Budget speech & policy
speeches (Media management, Live
Broadcast, PVAs screens,

Optimal Utilisation of ICTs to advance


the functioning of EC provincial
Communications System. Review of the
telemedia centre and related equipment
to determine resource needs

A plan for addressing the gaps, seeking


funding and training of requisite
personnel is in place

Rollout of the plan to departments and


municipal districts and the rolling out of
messaging reflecting 20 years of
Freedom reporting period

Rollout of the plan to departments and


municipal districts and the rolling out of
messaging reflecting 20 years of
Freedom reporting period

Production of video and audio visual


material (DVDs ,Internet video clips, TV
ads, and radio ads): 2 DVD packages for
different events and 4 Internet video
clips; and 2 radio ads be produced(as
required by media liaison)

DVD packages for different events and 2


Internet video clips2 radio ads be
produced(as required by media liaison)

DVD packages for different event sand 4


Internet video clips; and 2 radio ads be
produced(as required by media liaison)

DVD packages for focusing on Launch


of 20 years of Freedom Reporting period
per cluster; 3 Internet video clips
focusing on Launch of 20 years of
Freedom Reporting period per cluster; 3
radio ads be produced focusing on
Launch of 20 years of Freedom
Reporting period per cluster; and 20
years Review Documentary on the
performance of government and
distribution of DVDs across the

108

CHIEF DIRECTORATE NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: MEDIA LIAISON

PROJECT NAME: MEDIA MANAGEMENT

BUDGET ALLOCATION: R6 709

STRATEGIC OBJECTIVE: Enhance the Image of the Provincial government and EC Province
PERFORMANCE INDICATOR
4.3 Percentage of net positive media representation of the provincial government in the media domain
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
province.

Mobilization for various campaigns and


Institutionalized Days: Freedom Day
celebrations; Workers` Day; and June
16

Women`s month and Heritage Day

Day of the Disabled Persons; Launch of


20 years of Freedom reporting period;
Day of Elderly Persons; 16 Days of
Activism; and World AIDS Day

Back to school campaign; SONA;


SOPA; Celebrating 20 years of Freedom
reporting period; and Human Rights Day

Conduct environmental scanning in all


district/metros: Three reports on
environment are done with advisories &
district interventions

Three reports on environment are done


with advisories & district interventions

Three reports on environment are done


with advisories & district interventions

Three reports on environment are done


with advisories & district interventions

Record, develop a data base and track


issues raised by communities at
Thusong service centres: Generate 3
monthly status reports with analysis,
advisories for resolving outstanding
matters

Generate 3 monthly status reports with


analysis, advisories for resolving
outstanding matters

Generate 3 monthly status reports with


analysis, advisories for resolving
outstanding matters

Generate 3 monthly status reports with


analysis, advisories for resolving
outstanding matters

Ensure a rapid response system is in


place, executed, tracked and reports
generated on all EXCO outreach
undertakings: Three monthly reports are
given with demonstrable results

Three monthly reports are given with


demonstrable results

Three monthly reports are given with


demonstrable results

Three monthly reports are given with


demonstrable results

Promote the establishment of Thusong


Service Centres and Access points: 1
PISSC planning meeting ; and 1 monthly
Core Team meeting to mobilise and
coordinate establishment of Thusong
centres and Access point are held &
programme reports generated

1 PISSC planning meeting ; and 1


monthly Core Team meeting to mobilise
and coordinate establishment of
Thusong centres and Access point are
held & programme reports generated

1 PISSC planning meeting ; and 1


monthly Core Team meeting to mobilise
and coordinate establishment of
Thusong centres and Access point are
held & programme reports generated

1 PISSC planning meeting ; and 1


monthly Core Team meeting to mobilise
and coordinate establishment of
Thusong centres and Access point are
held & programme reports generated

109

CHIEF DIRECTORATET NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: CUSTOMER CARE & PRESIDENTIAL HOTLINE

PROGRAMME NAME: IMPROVE CUSTOMER CARE & MANAGEMENT OF THE


PRESIDENTIAL HOTLINE

BUDGET ALLOCATION: R268 480

STRATEGIC OBJECTIVE : Enhance the image of Provincial Government and the Eastern Cape
PERFORMANCE INDICATOR
4.4 Percentage of resolved public enquiries as registered and tracked on the Presidential Hotline
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Coordination of the Customer Care


workshop.

Presentation of the resolutions to the


Provincial Departments and
Municipalities

Implementation of the resolutions of the


Customer Care Strategic Planning

Monitoring and evaluation the


implementation of the resolution of the
strategic session

Presentation of the draft Customer Care


Policy to the Communications
Management

Presentation and approval of the draft


Customer Care Policy to the Executive
Management

Presentation of the approved Customer


Care Policy and its implementation by
Departments and Municipalities.

Implementation of the Customer Care


Policy and workshop resolutions around
Presidential Hotline.

Coordination of Road shows to


popularise Presidential Hotlines
objective and complaints handling
system: Proposed draft for the campaign

Consultation and planning with relevant


stakeholders

Road shows to District Municipalities


and Departments to present status

Utilisation of available platforms such as


Executive Management, IGCF,
MuniMec, HODs Retreat, Mayoral
Committee

Customer Care & Presidential Hotline


practitioners meetings convened and
reported.

Customer Care & Presidential Hotline


practitioners meetings convened and
reported.

Customer Care & Presidential Hotline


practitioners meetings convened and
reported.

Customer Care & Presidential Hotline


practitioners meetings convened and
reported.

Assist in developing and launching the


Business Intelligence Reporting Tool
with PIMU: Research and benchmarking
conducted on an Intelligence Reporting
Tool

Proposed reporting tool and presented


to the Communications and Executive
Management

Validation and implementation process

Implementation and Monitoring

Coordination of SOPA School Debates:


To do research on government
programmes and policies

Stakeholder coordination within OTP


and other relevant department

Identifying a suitable programme with


key role players.

Monthly Customer Care days

Coordination of Annual Presidential


Hotline and Provincial Customer Care
Indaba: To do the presentation to the
Management on issues lifted by the

Preparations of the Cabinet


Memorandum for the Executive Council

Approval of the identified District and


communication takes place

Liaising and preparations with the


identified District to host the Indaba

110

CHIEF DIRECTORATET NAME: PROVINCIAL COMMUNICATIONS

SECTION NAME: CUSTOMER CARE & PRESIDENTIAL HOTLINE

PROGRAMME NAME: IMPROVE CUSTOMER CARE & MANAGEMENT OF THE


PRESIDENTIAL HOTLINE

BUDGET ALLOCATION: R268 480

STRATEGIC OBJECTIVE : Enhance the image of Provincial Government and the Eastern Cape
PERFORMANCE INDICATOR
4.4 Percentage of resolved public enquiries as registered and tracked on the Presidential Hotline
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

communities
Participate and responding to customer
care queries during International,
National and Provincial Mandates: To
attend the institutionalised days and
document the issues raised and
analysed them.

Analysis of the raised issues and locate


then to various affected departments

Documenting all the issues rose in all


the Districts and coordinate responding
sessions such as information days

Summary of all the issues rose by the


communities and document them for the
Executive Council and affected District
for implementation purposes

Coordinate the training of PLOs on


Customer Care and Presidential Hotline
on quarterly basis.

Coordinate the training of PLOs on


Customer Care and Presidential Hotline
in every quarter

Coordinate the training of PLOs on


Customer Care and Presidential Hotline
in every quarter

Coordinate the training of PLOs on


Customer Care and Presidential Hotline
in every quarter

111

Sub-Programme 4.4: Intergovernmental and Stakeholder Relations


CHIEF DIRECTORATE NAME: INTERGOVERNMENTAL RELATIONS &
STAKEHOLDER RELATIONS

SECTION: INTERGOVERNMENTAL RELATIONS

PROJECT NAME: IMPLEMENTATION OF IGR STRATEGY

BUDGET: R925 000

STRATEGIC OBJECTIVES
Strengthen Executive and IGR Structures of Provincial Government; and
Improve mechanisms for effective engagement with civil society
PERFORMANCE INDICATORS
4.5 Number of reports on participation of all provincial government departments in the development of Integrated Development Plans at local government level to improve
integrated planning and effectiveness in implementation of government programmes; and
4.6 Number of EXCO Outreach Programme organised to strengthen public participation and public engagements with stakeholders on service delivery commitments and
progress towards attaining coherence in service delivery.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Organise and convene a Provincial IGR


Workshop

Provincial IDP support evaluation


session

Convene Provincial engagement to


mobilise phase one IDP support

Convene Provincial engagement to


mobilise phase two IDP support

Convene Provincial engagement to


mobilise phase three IDP support

Convene engagement with National


departments and state owned
enterprises

Follow up on issues raised per


department

Convene engagement with National


departments and state owned
enterprises

Follow up on issues raised

Convene PCF

Convene PCF

Convene PCF

Convene PCF

Exco Outreach preparations

Coordinate NMBM, & CDM IGR Exco


Outreach session

Lift IGR issues for TSG & PCF agenda

Lift IGR issues TSG & PCF agenda

Coordinate ADM, ANDM, ORTDM,


CHDM & JGDM IGR Exco Outreach
session

Coordinate BCMM IGR Exco Outreach


session

Coordinate IGR engagements

Coordinate IGR engagements

112

CHIEF DIRECTORATE NAME: INTERGOVERNMENTAL RELATIONS &


STAKEHOLDER RELATIONS

SECTION: INTERNATIONAL RELATIONS

PROJECT NAME: IMPLEMENTATION OF INTERNATIONAL RELATIONS


STRATEGY

BUDGET: R1.477m

STRATEGIC OBJECTIVE: Strengthen Executive and IGR Structures of Provincial Government


PERFORMANCE INDICATOR
4.7 Number of international initiatives co-ordinated in Provincial Government to mobilise and attract resources for the implementation of government priorities
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Printing, distribution and roll out of the IR


strategy

Implementation of the Strategy to all


sector departments

Implementation of the Strategy to all


Municipalities

Report on the implementation of the IR


strategy

Coordinate Provincial International


Relations Steering Committee to update
the ODA Database.

Coordinate Provincial International


Relations Steering Committee to update
the ODA Database

Coordinate Provincial International


Relations Steering Committee to update
the ODA Database

Coordinate Provincial International


Relations Steering Committee to update
the ODA Database.

Produce ODA report

Produce ODA report

Produce ODA report

Produce ODA report

Update and report on the status of


provincial twinning

Update and report on the status of


provincial twinning

Update and report on the status of


provincial twinning

Update and report on the status of


provincial twinning

Conduct APRM in Districts/Metros and


province

Conduct APRM in Districts/Metros and


province

Conduct APRM in Districts/Metros and


province

Produce one provincial APRM report

Coordinate PGC meetings in the


province

Coordinate PGC meetings in the


province

Coordinate PGC meetings in the


province

113

CHIEF DIRECTORATE NAME: INTERGOVERNMENTAL RELATIONS &


STAKEHOLDER RELATIONS

SECTION: COMMUNITY AND STAKEHOLDER RELATIONS

PROJECT NAME: STAKEHOLDER ENGAGEMENTS

BUDGET: R2.19m

STRATEGIC OBJECTIVE: Improve mechanisms for effective engagement with civil society
PERFORMANCE INDICATOR
4.8 Number of engagement platforms facilitated for communities and stakeholders to participate in government programmes
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
Planning and preparations for
Community and Stakeholder
engagement during EXCO outreach

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Facilitate 4 district/metro stakeholder


engagement platforms for feedback on
policy and service delivery issues
emanated from EXCO outreach.

Facilitate 4 district/metro stakeholder


engagement platforms for feedback on
policy and service delivery issues
emanated from EXCO outreach.

Coordinate Community and District


Stakeholder engagement sessions in 5
districts through EXCO outreach

Coordinate Community and District


Stakeholder engagement sessions in 3
districts through EXCO outreach

Planning and preparations for Post


SOPA provincial stakeholder
engagement

Coordinate a Provincial POST SOPA


engagement

Plan for two sector specific engagement


sessions

Coordinate two sector specific


stakeholder engagement sessions

Review Stakeholder engagement


framework

Submit Stakeholder engagement


framework for approval

Printing of the Stakeholder engagement


framework.

Present to interdepartmental structures

114

Sub-Programme 4.5: Legal Services


CHIEF DIRECTORATE NAME: OFFICE OF THE CHIEF STATE LAW ADVISOR

SECTION NAME: CONTRACTS, CONSTITUTIONAL & LEGAL COMPLIANCE

PROJECT NAMES
BUDGET ALLOCATION: R207 000

MANAGEMENT OF PAIA
LEGAL MANAGEMENT

STRATEGIC OBJECTIVE: Enhance compliance with the Constitution and other prescripts
PERFORMANCE INDICATORS
4.9 Percentage of adverse court judgements against Provincial Government; and
4.10 Percentage of requests for legal advice and opinions provided.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Training on generic responsibilities of


DIO's and reporting by DIO's on
compliance with PAIA at one
Departmental Information Officer Forum
meeting

Training on new case law and legislative


developments of DIO's and reporting by
DIO's on compliance with PAIA at one
Departmental Information Officer Forum
meeting

Refresher course on DIO responsibilities


and training on new case law and
legislative developments of DIO's and
reporting by DIO's on compliance with
PAIA at one Departmental Information
Officer Forum meeting

Training on new case law and legislative


developments of DIO's and reporting by
DIO's on compliance with PAIA at one
Departmental Information Officer Forum
meeting

Receive information and collate report


on provincial compliance in previous
financial year with Section 32 of PAIA
and submit to Human Rights
Commission

Receive information and collate report


on provincial compliance in current
financial year with Section 32 of PAIA

Receive information and collate report


on provincial compliance in current
financial year with Section 32 of PAIA

Receive information and collate report


on provincial compliance in current
financial year with Section 32 of PAIA

Two training sessions for identified


officials on PAIA compliance

Two training sessions for identified


officials on PAIA compliance

Two training sessions for identified


officials on PAIA compliance

Two training sessions for identified


officials on PAIA compliance

Generate and maintain a contracts


register (legal management) for OTP (as
pilot)

Generate and maintain a contracts


register (legal management) for 4
departments

Generate and maintain a contracts


register (legal management) for 4
departments

Generate and maintain a contracts


register (legal management) for 4
departments

Obtain approval of the legislative


compliance framework

Roll-out of the legislative compliance


framework for 4 departments

Roll-out of the legislative compliance


framework for 4 departments

Roll-out of the legislative compliance


framework for 4 departments

Development and drafting of a guide on


best practices for the drafting and vetting
of contracts

Approval of guide

Roll-out of guide to departments

Roll-out of guide to departments

Provide legal advice and drafting of

Provide legal advice and drafting of

Provide legal advice and drafting of

Provide legal advice and drafting of

115

CHIEF DIRECTORATE NAME: OFFICE OF THE CHIEF STATE LAW ADVISOR

SECTION NAME: CONTRACTS, CONSTITUTIONAL & LEGAL COMPLIANCE

PROJECT NAMES
BUDGET ALLOCATION: R207 000

MANAGEMENT OF PAIA
LEGAL MANAGEMENT

STRATEGIC OBJECTIVE: Enhance compliance with the Constitution and other prescripts
PERFORMANCE INDICATORS
4.9 Percentage of adverse court judgements against Provincial Government; and
4.10 Percentage of requests for legal advice and opinions provided.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES
contracts on request

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES
contracts on request

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES
contracts on request

116

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES
contracts on request

CHIEF DIRECTORATE NAME: OFFICE OF THE CHIEF STATE LAW ADVISOR

SECTION NAME: LITIGATION SUPPORT AND LEGAL ADVICE

PROJECTS: (1). PROVINCIAL LITIGATION MANAGEMENT (2). FACILITATION


OF INTERVENTIONS

BUDGET ALLOCATION: R1 762 000

STRATEGIC OBJECTIVE: Enhance compliance with the Constitution and other prescripts
PERFORMANCE INDICATORS
4.9 Percentage of adverse court judgements against Provincial Government; and
4.10 Percentage of requests for legal advice and opinions provided.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Development of Provincial Litigation


Management Plan

Obtain approval of Provincial Litigation


Management Plan and commence rollout of plan

Roll-out of plan

Roll-out of plan

Collection and collation of litigation data


and conduct a trend analysis of all
Departments and submit 1 report to the
Director General

Collection and collation of litigation data


of all Departments and submit 1 report
and a trend analysis to the Director
General

Collection and collation of litigation data


of all Departments and submit 1 report
and a trend analysis to the Director
General

Collection and collation of litigation data


of all Departments and submit 1 report
and a trend analysis to the Director
General

Facilitate interventions as approved

Facilitate interventions as approved

Facilitate interventions as approved

Facilitate interventions as approved

Determine the need for intervention and


facilitate approved interventions

Determine the need for intervention and


facilitate approved interventions

Determine the need for intervention and


facilitate approved interventions

Determine the need for intervention and


facilitate approved interventions

Development of system and obtaining


reports on outstanding court orders and
submit 1 report thereon to the Director
General

Maintain the system on outstanding


court orders and submit 1 report thereon
to the Director General

Maintain the system on outstanding


court orders and submit 1 report thereon
to the Director General

Maintain the system on outstanding


court orders and submit 1 report thereon
to the Director General

100% of requests for legal advice and


opinions complied with

100% of requests for legal advice and


opinions complied with

100% of requests for legal advice and


opinions complied with

100% of requests for legal advice and


opinions complied with

Manage Office of the Premier's litigation

Manage Office of the Premier's litigation

Manage Office of the Premier's litigation

Manage Office of the Premier's litigation

117

DIRECTORATE NAME: OFFICE OF THE CHIEF STATE LAW ADVISOR

SECTION NAME: LEGISLATION

PROJECTS: (1). DRAFTING OF LEGISLATION (2). CAPACITATION OF


DEPARTMENTS ON DEVELOPMENT OF POLICIES AND LEGISLATION (3).
REVIEW OF LEGISLATION

BUDGET ALLOCATION: R428 000

STRATEGIC OBJECTIVE: Enhance compliance with the Constitution and other prescripts
PERFORMANCE INDICATORS
4.9 Percentage of adverse court judgements against Provincial Government;
4.10 Percentage of requests for legal advice and opinions provided; and
4.11 Percentage of Bills developed.
SUMMARY OF PLANNED
QUARTER 1 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 2 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 3 ACTIVITIES

SUMMARY OF PLANNED
QUARTER 4 ACTIVITIES

Obtain approval of the manual for


development, drafting, and submission
of policy and legislation

Roll-out of manual for 4 departments

Roll-out of the manual for 4 departments

Roll-out of the manual for 4 departments

Drafting of legislation as per requests


from departments

Drafting of legislation as per requests


from departments

Drafting of legislation as per requests


from departments

Drafting of legislation as per requests


from departments

Review existing legislation and make


recommendations thereon (at least 6
legislative instruments reviewed and
reports with recommendations
submitted)

Review existing legislation and make


recommendations thereon (at least 6
legislative instruments reviewed and
reports with recommendations
submitted)

Review existing legislation and make


recommendations thereon (at least 6
legislative instruments reviewed and
reports with recommendations
submitted)

Review existing legislation and make


recommendations thereon (at least 6
legislative instruments reviewed and
reports with recommendations
submitted)

All requests for legal advice and


opinions complied with

All requests for legal advice and


opinions complied with

All requests for legal advice and


opinions complied with

All requests for legal advice and


opinions complied with

118