Documente Academic
Documente Profesional
Documente Cultură
Estimation,
and Critical Path
9-1
Project Scheduling
Project scheduling requires us to follow some
carefully laid-out steps, in order, for the schedule to
take shape.
Project planning, as it relates to the scheduling
process, has been defined by the PMBoK as:
The identification of the project objectives and the
ordered activity necessary to complete the project
including the identification of resource types and
quantities required to carry out each activity or task.
09-02
Time
A M J
Deplaning
Baggage claim
Container offload
Pumping
Engine injection water
Container offload
Main cabin door
Aft cabin door
Aft, center, forward
Loading
First-class section
Economy section
Container/bulk loading
Galley/cabin check
Receive passengers
Aircraft check
Loading
Boarding
0
Figure 3.4
10
20
Time, Minutes
30
40
A
C
09-09
A
C
09-010
Network Diagrams
F
C
D
B
F
C
09-012
Node Labels
Early Start
Activity Float
Late Start
09-13
ID Number
Early Finish
Activity Descriptor
Activity Duration
Late Finish
Serial Activities
Serial activities are those that flow from one to
the next, in sequence.
FIGURE 9.5
09-14
FIGURE 9.6
09-15
Merge Activity
FIGURE 9.7
09-16
Burst Activity
FIGURE 9.8
09-17
AON Example
Activities and Predecessors
Activity
A
Description
Build internal components
Immediate
Predecessors
A, B
D, E
F, G
Table 3.1
AON Network
F
A
Start
Preceding activities
A
B, C
B
C, D
E
F
G, H
9-20
F
H
D
B
E
9-21
Node Labels
Early
Start
Activity
Float
Late
Start
ID
Number
Early
Finish
Activity Descriptor
Activity
Duration
Late
Finish
9-22
ba
Activity Variance = =
a + 4m + b
Activity Duration = TE =
6
9-23
Table 9.2
Description
Optimistic
Likely
Pessimistic
Contract signing
11
Questionnaire design
Target market ID
Survey sample
12
20
Develop presentation
12
Analyze results
Demographic analysis
14
Presentation to client
09-24
Task Predecessor
Z
-Y
Z
X
Z
W
Y, X
V
W
T
W
S
T, V
a
7
13
14
12
1
6
11
m
8
16
18
14
4
10
14
b
15
19
22
16
13
14
19
9-25
9-26
Table 9.4
Project Delta
Activity
Description
Predecessors
Estimated Duration
None
Contract signing
Questionnaire design
Target market ID
Survey sample
B, C
13
Develop presentation
Analyze results
Demographic analysis
Presentation to client
E, F, G
09-28
09-30
FIGURE 9.20 Project Network with Activity Slack and Critical Path
Note: Critical path is indicated with bold arrows.
09-32
-A
A
B
B
C
D, F
E, G
H
4
9
11
5
3
7
3
2
1
Laddering Activities
It may be possible to begin a portion of one activity while work continues on
other elements of the task, particularly in lengthy or complex projects.
Create a visual basic code composed of several subroutines to cover the
systems of multiple departments.
Under sever time pressure to use our resources efficiently, however, we
might want to find a method for streamlining, or making the development
sequence more efficient.
9-34
Laddering Activities
Project ABC can be completed more efficiently if
subtasks are used
A(3)
A1(1)
B(6)
A2(1)
B1(2)
Laddered
ABC=12 days
C(9)
ABC=18 days
A3(1)
B2(2)
C1(3)
B3(2)
C2(3)
C3(3)
9-35
Hammock Activities
Summaries for some subsets of activities identified in
the overall project network.
Hangs below the network path for consultant tasks
and serves as an aggregation of task durations for the
activities it ROLLS UP
Duration first identifying all tasks to be included and
then subtracting the ES or the first task from the EF
from the EF of the latest successor.
9-36
Hammock Activities
Used as summaries for subsets of activities
0 A 5
5 B 15
15 C 18
0 5
5 10 15
15 3 18
0 Hammock 18
0
18
18
Exercise:
Calculate the ES, LS, EF, LF and slack time in a table format.
Find the critical path.