PETROBEL

SETH ONSHORE DEVELOPMENT

4187-440

MONTHLY PROGRESS REPORT NO.2

EGYPT

Rev. 0

4187-440 SETH ONSHORE DEVELOPMENT

MONTHLY PROGRESS REPORT NO.2


AS OF 30 APRIL 2011

REV

18/05/2011

DATE

ISSUED FOR IMPLEMENTATION

REVISIONS

If/'
v

BY

/-,1'.- ....rI

CH'D

APPR

Enpp:l.
PTB

SETH ONSHORE DEVELOPMENT

PAGE 1 OF5

4187-440

Rev. (0
Egypt

MONTHLY PROGRESS REPORT No.2

Contents
I.

Project Description

2.

Parties Involved and Relevant Scope

3.

Schednle Milestones

4.

Major Activities Completed

5.

Major Activities in Progress

6.

Major Activities To Be Started During Next Reporting Period

7.

Area of concern

7.1. Progress summary Sheets With Relevant S-Curves


7.2.

Progress Control Sheets

7.3. Updated Schedule


7.4. Critical and Near Critical Activities
7.5. One Month Look Ahead Report
7. 6. Procurement Status.

7.7. Equipment and material status report


7.8. Alert report

18-MAY-2011

PAGE20F5
4187-440

SETH ONSHORE DEVELOPMENT

PTB

Rev. (0)
18-MAY-20II

MONTHLY PROGRESS REPORT No.2

Egypt

1.0 Project Description:


The Temsah Pliocene Gas Gathering Network is in operation to collect the gas production from several Pliocene
fields located in the Temsah area.
Actually the only Denise A and Tuna productions are gathered by the new sealine, and in the following months also
Denise B and Seth Fields.
The whole new production is transported to the onshore El Gamil plant via a new 32" export pipeline.
Denise A reservoir production (Pliocene "heavier" gas) is separated on TNW2 platform. The gas phase is conveyed
to El Gamil plant through the new 32" trunk-line.
Tuna and Denise B productions will be collected into a common subsea PLEM and conveyed via a new 24" sealine
to the Denise A SSIV; Seth production will be routed via 16" sealines to the Tuna PLEM, Km 10.5 approximately.
During the EI Gamil Upgrading Project Phase (I)a dedicated Slug Catcher for the Denise A Production has been
foreseen and installed.
With Seth Onshore Development Project, the installation of a new slug catcher operating in parallel with the
existing Denise Slug Catcher has been foreseen.

2.0 Parties Involved and Relevant Scope:


PTB:

Owner

ENPPI:

Contractor shall perfonn basic, detailed engineering and procurement services.

3.0 Schedule Milestones:


Milestone

Planned

Actual

Expected

Project Coming Into Force

22-DEC-1O

22-DEC-IO

Complete Engineering Services

22-SEP-11

22-SEP-ll

Complete Procurement Services

20-JAN-12

20-JAN-12

4.0Major Activities Completed During the Current Reporting Period:


4.1. Engineering
Basic engineering review completion
-/ Process

Hazardous Area Classification Schedule IFD


HSE philosophy IFD
Detection And Alarm Layout Drawings IFD
Fire Fighting Layout Drawings IFD

E:n.pp.l.
PTB

PAGE30F5

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

MONTHLY PROGRESS REPORT No.2

Egypt

if

18-MAY-201I

Piping

Under Ground Composite Drawing IFD


Under Ground Piping Standard Details IFD
piping specification classes IFD
Standard Piping Support Details IFD

if

Electrical
Earthing Layout IFD
Hazardous Area Classification Layout IFD

if

Civil

Standard Drawings IFA

4.2. Procurement

Piping Bulk Bidding

5.0Major Activities in Progress During the Current Reporting Period:


5.1. Engineering
if

Process

Fire Fighting System Technical Evaluation


Detection and Alarm system Technical Evaluation

5.2. Procurement
Piping bulk Bidding

6.0Major Activities To Be Started / Completed During Next Reporting Period:


6.1. Engineering
if

Process
Cause and effect IFD
Process cause and effect matrix IFD
Fire and gas cause and effect IFD
Fire and gas cable routing drawings IFD
Fire protection system TER

if

Piping

Piping Bulk TER

Enpp1
PTB

SETH ONSHORE DEVELOPMENT

PAGE 4 OF 5

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

.{

Instrumentation

.{

.{

Field Instrument Cable Routing IFD


Junction Box Interconnections IFD
Field Instrument Layouts IFD
Loop Diagrams IFD
Instrument Index IFD
Instrument Cable Schedule IFD
Instrument Hook Up And Supporting Drawings IFD
I/O list IFD
Instrument Bulk Material MRQ's
Instrument Cable Trays MRQ's

Electrical

Electrical Bulk MTO

Standard Drawings IFC


Miscellaneous pipe support Foundation Drawings IFA

Civil

6.2. Procurement

Instrument Bulk Material Bidding


Electrical Bulk Bidding
Piping bulk Bidding

18-MAY-2011

Enppa.
PTB

SETH ONSHORE DEVELOPMENT

PAGE50F5

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.ATTACHMENTS

18-MAY-2011

I
I

E:n.pp.l.
PTB

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.l.Progress summary Sheets With Relevant S-Curves

18-MAY-2011

Project No.: 4187-440

Summary Report

SETH ONSHORE PROJECT

As Of:

30-Apr-11

Overall
Relative
Weight

Item Description

Planned
%

76.55%

"Engineering

39.98

";;:c-;;r~m:n~ ~

Total

During
%

27.26

10.26

"

- - - - - - - - - - - - - -

Actual
%

r---;:::--- ~ -- -275""; - - - t - - - ~.;; - - :

100.00%

35.66

-i - - - - : . ; - - _

25.25

8.86

Layout No.1

Monday, May 16. 2011

Page 1 of 1

Data'Nes Systems, Release 2.21

Project No.:

EDppt

4187.440

Progress Curve

SETH ONSHORE PROJECT


Overall

As Of:

100
90

lp'a~ned % =

35.66

%=

25.25

IActual

80

....

I
I

.;

. - -:

30Apr-11

70
;
~
III
III

"0
~

60
50

Cl
~

0..

40
30

20

10

;.
0

..."

",'

~o

"

c:...

Qe

......
')"C-<$

......
",'

~e

......
~~/

......

.,.q.:

......

..

,,'"... .,.",<$......

......

)'"

)'"

......

G.;P"

......

"

0"

......

.J:

~o

......
c:

Qe

...'l":J'lJ.<$

...'l-

",'

~e

...'l-

~~.

Time I Date
Actual
---"'-_.---

..._ . - - ..

Planned

- - - - - - - - - ._--

. _ - - - - - - - - - ...- - - _...

Layout NO.1
Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Ellppl

Summary Report

SETH ONSHORE PROJECT

AsOf:

30-Apr-11

Overall
Enaineerina
Relative
Weight

Item Description

Planned
%

Actual
%

During
%

...----------------------,...----------.-----------....,.-------------.--------
. . . .
i Process

17.92%

45.98

34.09

12.38

: .
: .
: .
:
:
.
---i~--------------------~--------~--------~--------~----Piping
i
42.73%
i
31.76
i
30.25
i
7.03

~--------------------~--------~--------~--------~----i Instrumentation
i
12.40%
i
38.27
i
5.19
i

5.19

40.00

~--------------------~--------~--------~--------~----Electrical
i
5.51%
i
73.33
i
40.00
1

Pressure Vessels

. . . .
i

4.90%

65.00

65.00

~--------------------~--------~--------~--------~----i Civil
i
16.54%
i
37.50
i
13.24
i
L

Total

39.98

100.00%

Tuesday, May 17, 2011

----

----

- - __

0.00

----

13.24

27.26

10.26

Layout No.1
Page 1 of 2

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Progress Curve

SETH ONSHORE PROJECT


Proffesional Services
Engineering
100
90

,""
(Planned % =
IActual

%=

39. 98
27.26

....

80
70
60

"
~

..

50

':

'" 40
30

20

10

o-l--~~=------i--~-~----:--~-~-~-:------i-------i----i-----i---i---1
Nov-10

Dec-10

Jan-11

Feb11

Mar-11

Apr-11

May-11

Jun-11

Jul-11

Aug-11

Sep-11

Oct-11

Nov-11

Dec-11

Jan-12

Feb-12

Mar-12

Time I Date
Actual

Planned

Layout No.1
Data'Nes Systems, Release 2.21

Project No.: 4187-440

Summary Report

SETH ONSHORE PROJECT

As Of:

30-Apr-11

Overall
Procurement
Relative
Weight

Item Description

Purchasing

'i
~

42.00%
~

Expediting

Planned
%

42.86
~

34.00%

10.44

During
%

Actual
%

38.57

7.35

8.57

----

~--------------------~--------~--------~--------~----i Inspection
!
24.00%
!
0.00
!
0.00
!
L
L
L
l
J
Total

21.55

100.00%

Tuesday, May 17, 2011

18.70

2.06

----

0.00

4.30

Layout No.1
Page 20f2

Data'Nes Systems, Release 2.21

Project No,: 4187.440

Enppl

Progress Curve

SETH ONSHORE PROJECT


As Of

Proffesional Services

30-Apr~11

Procurement
100
90

Iplanned %
IActual

%=

,:
,
,

21,551
18,70

80

70

.
0
0

60

o!l

'.

, -,

-;

50

Cl

0-

40
30

.'

:,

20
10

.. ,- ......

':

,;-"--~

o .jo....:.=--T..c.'-----;---;--~'---;_--;_--;_--.;_--.;_--..;_--..;_--.;..--.;..--..;..--_:_--_/
Nov~10

o.c-10

Feb-11

Mar-11

Apr-11

May-11

Jun-11

Jut-11

Aug-11

Sep-11

Ocl11

Nov~11

o.c-11

Jan-12

Feb12

Mar-12

Time I Date

,,__, '

"

,,

Actual

Planned

",

J
Layout No, 1

Data'Nes Systems, Release 2.21

4187470 PTB, SETH ONSHORE PROJECT

Enppl

DELAY ANALYSIS
AS OF 30-Apr11

Process CaUse and effect matrix


11.89

1.54

fire & gas I/O IIsl


Halardous area c1asslflcotion

s~hedule

Firefightlng system layout drawing

24-Mar-ll

26May-l1

27-Febll

20-May-ll

30Mar-1l

26-M"y-U

24Mar-ll

24-May-ll

24-M.r-ll

i6-Aprn

Detection and alarm layout draWing

1.51

0.52

Pplping Valves Vendor prints review


Instrument Index

33.0&

3.59

I/o list
Instrument Hook Up And Supporting Drawings
Field Instrumenllayouts
Field Instrument Cable Routing
Instrument Bulk MRQ

Instrument Cable T,a s MRQ


33.33

1.66

24.26

3.10

Electrical Bulk MTO


Civil standard drawings IFe

Misc. Steel supports found"tion plan & details IFD

Instrument I Fire & gas cables RFQ


4.29

0.47

3.09

0.24

Electrical bulk material RFQ


I....trument Bulk RFQ
Instrument I Fire & gas Cable Trays RFQ

The delay of MRQ's issuance


13Apr-ll

26-May-ll

17Febll

18Mayll

In progress
Piping Valves start fabrication

Enpp1
PTB

SETH ONSHORE DEVELOPMENT

4187-440

Rev. (0
Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7.2.Progress Control Sheets

I
I

Project No.: 4187440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

Expected

As Of : 30-Apr-11

Milestone

* Relative

Value

Weight

Process cause and effect matrix

Start

:ZO-Feb-11

. "De~i~~
'i24~Feb-;; . ~
............. .,
.
T

Construction

Fire and

cause and effect

: 07-Apr-11

.
19-May-11

.. Co'n~lr'ucti~~ . -. -!24~Au~~11' . "

23-Au"g:11 .

." 11-Apr-11 .
81art
- - - - - :13-Mar-11
- ..
Design
: 17-Mar-11
. -- -,
','
- ,- - 18-Apr-11
-Finish

: 17-Aug-11

08-Apr-11

Start

~e.si~~
Finish

16-Aug-11

22-May-11

20

31-Jul-11

40

27-Jul-11

20

02-Aug-11

40

:~~Jo6~De~-;1'

"

:,~~:~8-AUi~~':_:_~.~ 40' ~

Commissioning procedure

:28-Nov-11
"

..............!, OS-Dec-11 .
Design

Finish

4.27%

60.00%

0.00%

4.27%

0.00%

0.00%

4.27%

0.00%

0.00%

4.27%

60.00%

60.00%

. - - .... - .. - ....
40
. 2S-May-11
.

: 13-Nov-11

60.00%

40

,20-Nov-11

60.00%

20

Design

4.27%

40

Start

Start

20.00%

Pre-commissioning procedure

60.00%

....40- _.

Fire & gas 110 list

4.27%

. ... - - 40
_ ... _.-

"

20.00%

20

Hazardous area classification schedule

Fi~is"h'

60.00%

: 27-Jul-11

Design

"

4.27%

Start
:03-Apr-11
. 25-Apr-11
..........
- -' "0"

Actual
Progress%

20

29-Mar-11

Planned
Progress%

:21-Dec-11

11-Aug-11
.....
- ..
17-Aug-11
. .. ...

40

02-Sep-11

40

20

""

HSE philosophy specification

20
40
40

29.91%

I 42.86%

22.86%

Drawin s
3.42%

Fire fighting system layout drawing

Start

: 13-Mar-11

40

~o.n~tr.u:ti?~ _ ~ .:!7:~u~-~~

40

',' "

"

Layout NO.1

* Weights of Activities are calculated relative to (Process)


Tuesday, May 17, 2011

60.00%

20

.. ..
Design
: 17-Mar-11
..............
,
.
"

60.00%

Page 1 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Milestone

I Milestone

Dates

Expected

Actual

Planned

Value

As Of : 30-Apr-11

* Relative
Weight

Planned
Progress%

4.27%

60.00%

0.00%

4.27%

60.00%

60.00%

4.27%

60.00%

0.00%

Actual
Progress%

Overall

Design

12-May-11

:27-Mar-11

Start

','

",'

"

01-Sep-11

:04-Sep-11

Start
"

','

16.May-11

.... _.
. . _. ... .. _.

:03-Apr-11
-

Design

18-May-11
.......
.

:31-Mar-11

: 07-Apr-11

-.. C;n~t;ucti~~ ... '!11~Se~-11' .

20
.......
. .. 40
... .

19-May-11

08-Sep-11

40

Detection and alarm layout drawing

Start

,'OS-Mar-lt
-

','

Design

!to-Mar-tt

Construction

:10-Aug-11

20

13-Apr-11

20-Apr-11

, -'. c -

Fire fighting, safety equipment and safety signs

.,

- Start
-.-

Design
~

:20-Mar-11
','

!24-Mar-11

C;n~t;ucti~~ i24~Au;.;1

15-May-11

;-

;
a

"

20

26-May-11,
23-Aug:11

40
40

20.51%

I 60.00% I 22.50%

20
40
10

30

Start

i27-Jan-11

Construction

: 20-Jul-11

20

10-Mar-11

40
19-Jul-11

40

Layout NO.1

... Weights of Activities are calculated relative to (Process)


Tuesday, May 17, 2011

Page 2 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Milestone

I Milestone

Dates

II--'p"":-.-nn-e-d""'---A7"c:-t:-U-.:-,---:E:-x-p-e-ct:-e""'d-lI

Value

As Of : 30-Apr-11

I'"

Relative
Weight

Planned
Progress%

Actual
Progress%

4.27%

Start

27-Jan-11

10-Mar-11

Design

17-Feb--11

17~Mar-11

Construction

20-Jul-11

. . . . . . . . . . . . . . . . . . . ..

Total

20

.
19-Jul-11

40

34.09%

Process

"" Weights of Activities are calculated relative to (Process)


Tuesday, May 17, 2011

40

Layout No.1
Page 3 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Milestone
Value

Expected

Actual

As Of : 30-Apr-11

* Relative
Weight

Planned
Progress%

Actual
Progress%

Overall

Specification for ins. Of UlG system.

Start

.. .21-Jul-11

"

"

Finish

ZQ-Jul-11

2.87%

0.00%

0.00%

2.87%

0.00%

0.00%

2.87%

60.00%

60.00%

30

27-Jul-11

Specification for field test of U/G system.

Start

28-Jul-11

"

Finish

Piping Material Classes specification

:27-feb-11

Start

-.'

DesIgn
"

:03-Mar-11

20

31-Mar-11

.:.

20-Apr-11

Finish

..

..._.... ......__,'24-Aug-11
......__..._..._._........-"-.....
~_

....

',' " "

~~~~~~~ _-~

~-"-.-

......

23~Aug-11

40

:20-Feb-11

Start

Design

',"

< ,

10-Mar-11
<

",

:24-Feb-11

Co<n;t:Udi~~

28-Mar-11
'!28~AU;-11' ." ,. 25-Au9:11"

:03-Mar-11

Start

<

"

<

',"

3.58%

60.00%

40

" " "

40

60.00%

20

15-Mar-11

--_._._------_._-_.
60.00%
60.00%

20
....
.

Table

3.58%

~~~.~~~~~~""'''''''-'--_._~~.~~-~~----------------

Tie-In List

,40,
"

".

40

- - 40
---38.18%

:20-Feb-11
-,' ..

Start

Construction

..Start

.
..

..

20
40

:10-Aug-11

..
09--Aug-11

~~n~t~u:ti?~

,'

':~1.-~e~;~ _

"

5.02%

60.00%

60.00%

40

__

<

08-Sep-11

40

Layout NO.1

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17, 2011

60.00%

20

Start
: 03-Apr-11
31-Mar-11
- - De~i;~' ~ ~ ~ ~ !Oi-Ap~-11 -:- - 07=A~;-11

60.00%

40

Underground composite drawing

4.30%

40

02-Aug-11

:27-Feb-11

-,'

Construction

60.00%

40

: 10-Mar-11

. . , 15-Mar-11
20-Mar-11
...
- . .

60.00%

20

15--Mar~11

:03-Mar-11
.. .. 20-Mar-11
.. - .
',":03-Aug-11

. Design
.
.-

_ ~~si~~

4.30%

Page4of19

Data'Nes Systems, Release 2.21

Issuance Status Report

Project No.: 4187440

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

As Of : 30-Apr-11

Milestone
Value

Expected

'It

Relative
Weight

Planned
Progress%

Actual
Progress%

4.30%

60.00%

60.00%

4.30%

0.00%

0.00%

3.58%

60.00%

60.00%

3.58%

0.00%

0.00%

3.58%

0.00%

0.00%

Overall
Engineering

Underground piping standard details


20
......
.
40
...... .

Start
: 05-Apr-11
08-Apr-11
De~i;~ . " 09-Ap~-:;1' :. '14:A~;-1"1' .. - "

'i

','

"

Construction

. -

"

:06Sep-.11

40

03-Sep-11

Hydrostatic test loops.


Start
:19-5ep-11
18-Sep-11
, co'n~t;ucti~n' .. i25~Se~11 ~ . - :. 22-S~~11'
.......................

~~_4~~_"__~_~'_

"-"_""_

_<..~~

__

___"__~

?_~

20

80 .. :

~L_~~~_~~~_~_

details

Standard

~.~

__

_ _" _ . _

~"_"_.~._.

20

Start
: 14-Apr-11
31-Mar-11
~ De~i~; '::;O~Ap;-11' " 21:A~:-1-1'
- co'n~t;ucti~~ - - .

_"'"--~-'-

40

-i 03-0ct~:; 1" , .

02-0ct-11

40

Special piping support


Start
: 02-0ct-11
29-Sep-11
- Co'n~t;u~i~n'
1" " .
l'

20
.
'OS-Oct-; . ......
80

-i os-octo:;

Standard steel structure

list
20
.......
80

32.97%

39.13%

39.13%

Commodities
Piping Bulk

MRO

:17-Mar-11

22-Mar-11

3.58%

15.00%

15.00%

7.89%

65.00%

55.00%

....15.. .

. ... 30...
"." -MRp i09-Ju~-11-" .......
09-Jun-11
1S
1. Evaluation

;.

~~~~

19-May-11

:19-May-11.

VPR start

-::26-Jun-11

VPR finish

:04-Aug-11

~~~

"

26-Jun-11

. .. . . ...
. . .. 10
- ...
30

Ppiping Valves
MRQ

: 04-Jan-11

1S

04-Jan-11

I :" .. --r. E~alu~ti'o~ 'io2~Feb-;1' - ~ 08~F~b.11


...
-

~J

VPR's~art'

-:;7~Feb-;1'

40

16-May-11
"" .....
mml ... VPR'fi~i;h' '!05-0ct-11" " ...
13-Dec-11

11..

10

"

....

35

I_

Layout No.1

* Weights of Activities are calculated relative to (Piping)

Tuesday, May 17,2011

_%_,_

-!._1_1_.4_7.;.%_,_.I. 4_9_._38_'_Y'_.l.-4_2_.5_O

Page 5 of 19

Data'Nes Systems, Release 2_21

Project No.: 4187440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

* Relative
Weight

Milestone
Value

Expected

As Of : 30-Apr-11

Planned
Progress%

Actual
Progress%

Overall

....Start
"."""

2B.Sep-11

Finish

09-0ct-11

.......

27-Sep-11

20

"

-.'

OS-Oct-11

0.00%

0.00%

3.58%

100.00%

80,00%

3.58%

100.00%

100.00%

0.00%

0.00%

0.00%

0.00%

0.00%

0.00%

80

3.58%

--".-"-'--'~'.~""""~~--""~.""""'''---<''-''---''-''''''''''''"------

:27-Feb-11

:03-Mar~11

Start

20

27-Dec-11

15-Mar-11

20

. _._. _

L_:~_~ FI~I;h - .. ~_:~~M~'r-11'-~_~_~~~M~i~~_~:~:_: ~~~_: ~~~~_~~~_~


Piping bulk final MTO

~~_._._

Start
Finish

Piping valves final MTO

Finish

........ ,

o
o

19-Jul-11

--

29-Jun-11

66.67%

10.75%

60.00%

GA~

Piping GA drawing area

','

Design

-.-

-,

Construction

..

9.68%

0.00%

0.00%

_.

-,_

19-5ep-.11

:20-Sep-11

Existing piping GA drawing area

20-Jul-11

Start

0.00%

10-Aug-11

: 28-Jul-11
-

0.00%

28-Aug-11

: 20-Jul-11

Start

8.60%

~""---"~'.''---'--

..28-Aug-11
- _ ..... ..28-Jul-11

20

0
I ~. ~ .~e.si~~
~~-~u~-~1
......
19-5ep-.11
80
~I
Construction
20-Sep-11
1lI1d==~~~~~==~~'='='===~::::==;==:=:=~~
18.28%
0.00%
0.00%
iii

[ti~----------------------------------"'-----"'----"'---Ij!j-F~;='==;===:='=================:::::::==;:=;=~::::=:::::::===='"
ili~
i2ill
Piping isometrics
10.75%
0.00%
0.00%
ffJii/SO's

II

Bh "

~::;r~cti;~

----:~:~~:;~{ ~ ~

- -~~~;:f~~ ~ ~ ~ ~ .~~ ..

i;;lIIF====~='===~~~~~='=====r~::==F~==;=:===

1lI1------------------------------J-------J------..I,------10.75%

5.

., Weights of Activities are calculated relative to (Piping)


Tuesday, May 17, 2011

0.00%

0.00%

Layout No.1
Page 6 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

Expected

Milestone
Value

As Of : 30-Apr-11

* Relative
Weight

Planned
Progress%

Actual
Progress%

Overall

* Weights of Activities are calculated relative to (Piping)


Tuesday, May 17, 2011

Layout NO.1
Page 7 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone
Planned

Actual

Expected

Value

* Relative
Weight

Finish

18-May-11

.. ~e.si~~ . . . ~4.-~e~~ 1. .

26-Jul-11

27-JuJ-11

40
40

Loose Instrument data sheets

:27-Feb-11

.--

.. ~e.sj~~

3.70%
20

:?3:'~a:-~1..
!03:AU~-~1

Finish

Instrument Cable Schedule

. - _.

Start
~'-'--'.'

"

:30-Mar-11
__

"

",

"

3.70%

60.00%

60.00%

20

__

- .. ,

"

14-Apr-11

_,

,40,
T

_J.---,--_,,---,-.?~~~~~~~:~P-11....>.-.~-"-"-'-...~~._~~"---"---,,_,,_~.~,,-.-<-.,

.__..._ .._.

.__.

3.70%

Sand probes data sheets

: 60.00%

20.00%

20

Start

Start

i 10-Mar-11

Design

: 16-Mar-11

18-May-11

.......... - - - -, - . - ....

20

24-May-11

40

16-Aug-11

40

layout NO.1

* Weights of Activities are calculated relative to (Instrumentation)


Tuesday, May 17, 2011

0.00%

"-19-M~Y~1;'

, 10-Apr-11
.. " - ' .:24-Mar-11
""-'-'--"'"

Design

60.00%

...... ',' 23-Au"9:11 .

:24-Aug-11

Finish

3.70%
16-May-11

. _ . __ .. !~7.-~a!-~1..

__ ~e.si~~ .... __ .!~3:~a!-~1. _

Actual
Progress%

20

15-May-11

20-Feb-11

Start

Start

Planned
Progress%

7.41%

Instrument Index

Start

As Of: 30-Apr-11

Page 8 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone

Milestone

Actual

Planned

Expected

Value

As Of : 30-Apr-11

'" Relative
Weight

Planned
Progress%

4.94%

60.00%

Actual
Progress%

Overall

Junction Box Interconnections

;.

25-May-11

: 17-Mar-11

Start
~

.. - Design

','

:23-Mar-11

",'

20

:23:-AU~-11

Construction

0.00%

26-May-11

40

22-Aug-11

40

23.46%

60.00%

0.00%

Commodities
Instrument I Fire &

19.75%

cables

MRQ
......
- . - - - - - : -07-Apr-11
- - - - ..
T. Evaluation
............. ' ,:29-May-11
'
.
s1art
.. _.VPR
- -'
_
..,: 14-Jul-11 .
"

19-May-11

20

26-Jun-11

40

1B-Jul-11

10

"

VPR finish

17.28%

Instrument Bulk

20.00%

0.00%

20
40

10

30

Total

Instrumentation

5.19%

'" Weights of Activities are calculated relative to (Instrumentation)


Tuesday, May 17, 2011

Layout No.1
Page 9 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Milestone

Dates
Planned

Actual

Expected

Milestone
Value

As Of : 30-Apr-11

* Relative
Weight

Planned
Progress%

Actual
Progress%

Overall

22.22%

60.00%

60.00%

22.22%

60.00%

60.00%

22.22%

60.00%

60.00%

20
...

40

.. .......
28-Apr-11

~~si~~ . . . ~0:~a!-!1
Construction
10-Aug-11

09-Aug-11

40

Electrical grounding layout

13-Apr-11
.......
17-Apr-11
!~7:~a:-!1.. ....
- --

Start
"

20

: 13-Mar-11

',"'""

.... I?e.si~~ _
Construction
- - - .....

:17-Aug-11

40
16-Aug-11

40

Hazardous area classification layout

Construction

14-Apr-11
....
- - - -.- - - - - - --

20-Mar-11

Start

. . . l?e.si~~ __ .. __ . ~4:~a!-~ i.

. ~S:A?~-1.1

.
23-Aug-11

. ~4-Aug-11

20

40
40

60.00%

33.33%

Electrical Lighting MRQ

Start

20-Mar-11

Finish

24-Mar-11

.. ""

~: ~ ~~-~~Y:1~ .
24-May-11

20

, 100.00%

0.00%
40.00%

Electrical

Layout No.1

., Weights of Activities are calculated relative to (Electrical)


Tuesday, May 17, 2011

0.00%

80

33.33%

Total

100.00%

Page 10 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone
Planned

Actual

Expected

Value

As Of : 30Apr11

I..

Relative
Weight

Planned
Progress%

Actual

Progress%

Overall

100.00%

MRO

04-Jan-11

04-Jan-11

15

T. Evaluation

02-Feb-11

13-Feb-11

40

VPR start

20-Mar-11

28-Mar-11

VPR finish

28-Jun-11

65.00%

65.00%

10
21-Jul-11

35

65.00%
Total

65.00%

Pressure Vessels

Layout No.1

.. Weights of Activities are calculated relative to (Pressure Vessels)


Tuesday, May 17, 2011

Page 11 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

As Of : 30-Apr-11

SETH ONSHORE PROJECT


Dates

Milestone
Planned

* Relative

Milestone
Value

Expected

Actual

Weight

Planned
Progress%

Actual
Progress%

Overall
Engineering

Concrete Specification

~t~rt . . . 9~-~p~-!1

... 9,:Si~~ ...

Finish

Start
-

.......

"

50.00%

50.00%

10

"

40

17-Apr~11

: 18-Apr-11
-

1.85%

50

: 06-Apr-11
. ~O:Ap~-~1 .' ....
...... - ",'"
"" ...

50.00%

40

17-Apr-11

Shim and grouting Specification

Design

50.00%

10

" :O:Ap~-~1 . . .......

!~-~P~-!1
13-May-11

1.85%

. ..

Fi~is_h _ _ :~3-May-11

50

:~-~aY-11

hqyF='::'=~~=c=~~==~===!==~====:=:::o:;===c:::~==::~=
..r.~.,.; structural st1fabrication Sp.cification
1.85%
50.00% 50.00%

.-;:;\

III

_. Start

: 06-Apr-11

_.

-,-

Design

_.

, 1D-Apr-11
-
-.- - _. - - - -

: 18-Apr-11

II

.. -

1m
i.~.J.
".,~.:.~~

~t~rt_ _ _

10

17-Apr-11:

-';

40

- .... _. >j3~Ma~'11' - -' ;8-M~Y~1;' . - - 50 -';


gl="S=ite::=p"r."p"'a"'ra=t:Oio"n"',"'e=a=rt:Oh"W"O"'rk:;=;&""ba"'ckfi"":~IiI"S"P"""'C:Cifi"'lc"a'"ti"'on""'=:=:====:=:""====::=o=======1"."8"5'''~===;5::0:=.0:=0:=%;;=="5::0:=.0:'0"'::~=

it

Fi~is-h

~ ?~si~~

T'

_.-

~O:A?~-1.1_

1. ~ ~
_ , __ " .

~7:Ap~-1.1 . .... ~ ..

"

~o

11=""==:"",F=;n";~'h==:=:====:.=:=."",,,,,,,,,,~,,,,,,,,,,::=,,,,,,,,,,=,,,,8=.,,M,,a,,,Y'=',,,,,,,,,,,,,,,,,,,,,,,,5,,0=='========7':0=:':='==:=:::=:'=:==0=::=:'",,="
Concrete paving Specification
1.85%
50.00%
50.00%

linE

:s2&
""lW

,[g~~. ~.c

___.:

~:g

10
~. ~,~t~rt :?6"-~P~-!1 ~. ~O:Ap~-1.1:.. YTY.,.
;
Design

: 18-Apr-11

17-Apr-11

40

r.i.F.-~,='""",~F=;"~",i;,,h=:~:~.~~:.,,.=,,,,,:,,~j1",3~:M,,'a~~~'-~"='"'='=='"'~',,,,,'
"'",'",,,'".~.'='8-",'=M",a~'y=:,=;",'~'"',,,'='
-...............
........ "5",0'", ,',,'=========:=::'::===='0=:0:7===':':':C:==

::::::t

II
II

r.: t.,: ~

...; "

:::

-"---'-~-"-----"-"-"-..;,-"-

_,~_.......:.._."-

Soil & foundation investigation Specification

: : :

~::~~~

: : : : : : :

Finish.

~~:~:;:;::

:~3-May-11

----~-

2.78%

50.00%

50.00%

10

~0:Ap~.~1.
:7:Ap~.~1.

40
18--May-11

50

1l=='=Ex==:is"'t=in=g"p=/~RO=V"''''ri~fi''ca''ti~'o=n-2r''''p'''o'''rt=====:=:'''''-2==::=="""""============~2~3~.~15~'~l\===~0~.0~0~%C===0:'.=0~0~%,:=,=

30
;1 ~::'h - :~~1~;~;; .
70
f~1
I
11l------------------.
. .-------------..I.----...l----..I.---02-Jun-11
15Jun11

35.19%

17.11%

17.11%

!;D~r.~.s~~~~~:~:~:~1g=.=n".=ra"l=n=ot:='='========================="3:=.7='0"%;;===;1=00='.:::0"0':=~==::60='.:::0=0'?~=

IZi
i
!l1j

a
ej
@ill.'i

_I

Start

. --De~i;~

.............
Construction

!20-Feb-11
'!24~Feb-l1-
','

10

~3:A'p~-1.1.
14-Apr-11

: 17-Mar-11

50
24May11

40

Layout NO.1

* Weights of Activities are calculated relative to (Civil)


Tuesday, May 17, 2011

Page 12 of 19

Data'Nes Systems, Release 2.21

Project No.:

4187-440

Issuance Status Report

As Of:30-Apr-11

SETH ONSHORE PROJECT


Dates

Milestone

Milestone
Expected

Actual

Planned

Value

* Relative
Weight

Planned
Progress%

Actual
Progress%

Drawings
2.76%

Anchor bolts standard details

:20-Feb-11

Start

Design

:24-Feb-11

','

03-Apr-11
......
.

10

~4:A?~-~1

50

40

24-MaY-11

Construction

2.78%

standard details

". - Start
_

-' .,;20-Feb-11

Design

:24-Feb-11
"

, -

Construction

Start

: 17-Mar-11

:20-Feb-11

03-Apr-11
....
- - - .,,
14-Apr-11
~ ~ ~ ~e:Si~~ : :: : :: :!~4:~e~-~1~ ~ ....... ' , "
Construction

: 17-Mar-11

.
.
24-May-11

:12-MaY-11

91 ~

",

;.

19-May-11,

60.00%

0.00%

11.11%

0.00%

0.00%

10

12.96%

: 60.00%

New slug catcher foundation plan & details

8.33%

40

~e.si9~ . :~o:~ay-}~
~:-~~Y:1~ ~ : ~ ~ :0..
Con:tr~~~~ ..".,"-,,-1~~~~~,,~.->--"-'C-,-~~:~~~-, __~~~4~~~: __ ~

;1_-...

60.00%

10

Valves foundation plan & details


Start

100.00%

50

Misc. Steel supports foundation plan & details

~'"'_ "*'*:_""'H~""'.'

2.78%

.__.

._

0.00%

ii!E

4QWf

1m

Start

05-Jun-11

: 19-Jan-11

til .--De'si~~ ~ - -i;6-J-a~-11"

II .

-i18~Au~-;1 ..

-,

23-M~y~1;
09-Au9:11 .

10

50
40

fjfF==;;;;=====":~=='==="'===~==='=======c===~o=====o====
~
steel details
11.11 %
60.00%

"Wi

I ,

ill

St~rt

Design

!"Ap~.~,

'
.. ,
,: 26-Apr-1l ,

:~"~~Y:'~

26-May-11.

10
50

1I1==',=='"'"'=c"o,,'n,,;t,,;"=ct=i~=n,,",,',,'='=',,,!2,,'0,,:,,se,,;""",""'"',,'=',,,,,""',,'='=',,,,'" "='=9,,.A, U, g, :,=', , ,"',,',,'='=4,,'0, ',,'='''''=====r======r=====r=====

1I:...
II

55.56%

56.67%

...l_;.;,~.;,;,_..l....;.:......;;.....l

.....,;,;,;.;.;;.,_
13.00%

=MTO
~--

iliili

~I

9.26%

Civil MTO
Start

:OS-May-11

19-May-11

20

'_.: ~ ~i~jS~: :: .. :: >o~~ar-}~':::::: ~~-~~y~1; r 80"

;~l:::::::::::::::::::::::::::::::::::::::::::::::::::::::::::~:::9.:2:6:%:::~1::0:.0:0:'/.:'::~::0:.0:0:'/.:.::
Layout No.1

* Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011

Page 13 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

Expected

Milestone
Value

As Of : 30-Apr-11

, * Relative
Weight

Planned
Progress%

Actual

Progress%

Overall

Weights of Activities are calculated relative to (Civil)


Tuesday, May 17, 2011

Layout NO.1
Page 14 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Actual

Planned

I Milestone

Dates

Milestone

* Relative

Value

Expected

As Of : 30-Apr-11

Weight

Planned
Progress%

Actual
Progress%

Overall
Procurement

Fire detection

24-Feb-11

RFQ
11-Apr-11
.....................

I
I
I

Rec.Bids

.-

OZMay-11

23-Mar-11

.-

C. Evaluation

13-Jun-11

F.OA

20-Jun-11

-"fi

fi

RFQ

40.00%

9.52%

40.00%

40.00%

9.52%

10.00%

0.00%

11.90%

40.00%

40.00%

9.52%

100.00%

100.00%

9.52%

40.00%

0.00%

10

10-Jul-11

---

---17-Jul-11

10

- .... - , -24-Mar-11
- ... .
11-Apr-11
18-Apr-11
...
- .. - " ..... "

10.00%

30

Piping Bulk

Rec.Bids

9.52%

C. Evaluation

02-Jun-11

30

F.GA

09-Jun-11

30

16.67%

Catcher

30

20-Jan-11

Rec.Bids

22-Dec-10

RFQ

OS-Feb-11

03-Jan-11

10

17-Feb-11

10-Mar-11

30

15-Mar-11

30

-. - - -

---

"

C. Evaluation

F.OA

Instrument I Fire & gas cables

RFQ

11-Apr-11

02-Jun-11
-

Rec.Bids

- ...

.. - - - -

"

c. Evaluation

12-Jun~11

F.OA

19-Jun-11

...

"

"

<

10
-

29-May-11

30

10-Jul-11

30

- ..... ".. . ...

---

30

Fire protection system

.. RFQ
- " . - ... ,

"

!-04-Apr-11
... .. -24-Feb-11
. -. .

.,

"

"

........... ". ",."


C Evaluation

:17-May-11,
10-Jun-11
!;5-Ju~-11 ~ " ,' 15-ju~-;1

:22-Dec-10

Rec.Bids

"

"

28-Mar-11

30

: 07-Apr-11

~ ~ F.O.A." ....

10

"

Rec.Bids

"

RFQ

"

"

-,

:OS-Feb-11

"

18-Jan-11
"

"

"

30
30

30

"

05-Jan-11

-:

10

. .. - . - - - ... .... - ...- - - - - - .. .... - - - -,- - - - _ ...


"

- RFQ
... - . .. - :28-Mar-11
--- - .
Rec.Bids
18-Apr-11
- .. - ... - - .. - -,: ....
-. C. Evaluation
:OS-May-11
- .. - - . ' , ' .. - - - .....
. "~''?~
__ . __:~2~~ar-}: .
"

"

02-Jun-11

10

02-Jun-11

30

,
,'

"

"

_.

..28-May11
- - . . ..
04-Jun-11

30
....
-.
30

., Weights of Activities are calculated relative to (Purchasing)


Tuesday, May 17, 2011

layout No.1
Page 15 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone

Actual

Planned

Milestone
Value

Expected

As Of : 30-Apr-11

,., Relative

Planned
Progress%

Weight

Actual
Progress%

Overall

11.90%

Instrument Bulk

RFQ

11-Apr-11

Rec.Bids

26--Jun-11

01-MaY-11

10

05-Jun-11

"

C. Evaluation

12-Jun-11

17-Jul-11

F.G.A.

19-Jun-11

24-Jul-11

Instrument I Fire & gas Cable Trays

~~I

RFQ
"

11.90%

: 13-Apr-11
-

Rec.Bids

C.E~u~t;o~

".'

:03-May-11

- "i 14-jU~-11-

30

0.00%

10

25-MaYc11

---

10.00%

07-Jun-11

30

19-Jul-11

30

IIill=",'===~,:~.o"."A,,.=======.:i";='~,;,JU,,;=-;~,'==',='"'='=-='='=='='='2=6='J=~='-=;'='=-,,,='='='=3=0='='='~====r=======T=======;=======
...--..-- ......
100.00%

Total

38.57%

38.57%

Purchasing

Layout No.1

"Weights of Activities are calculated relative to (Purchasing)


Tuesday, May 17, 2011

42.86%

Page 16 of 19

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT


Dates

Milestone

Actual

Planned

Expected

Milestone
Value

As Of :30-Apr-11

* Relative
Weight

Planned
Progress%

Actual

Progress%

20

24-Dec~11

30

16-Jan-12
16-Jan-12

12-Feb-12

20

10

Start

09-Jun-l1

VPR start

26-Jun-11

..

10

VPR finish

04-Aug-11

20

SID.Award

16-Nov-l1

20

Fab. Finish

26-Dec-11

30

Fab. Start

17-Mar-l1

10

VPR start

2a-Mar-It

10

VPR finish

21-Jul-l1

S/D.Award

14-0ct-l1

20

23-Dec-l1

30

20

17-Jul-l1

10

03-Jan-12

20

12-feb-12

30

18-Jul-!1

17Jul-l1

Fab. Finish

....... ,
16-Jan-12
....
- ..

10

28-Jul-1!

20

03-Jan-12

20

12-Feb-12
'

10

17-Jul-l1

30

." Weights of Activities are calculated relative to (Expediting)


Tuesday, May 17, 2011

Layout NO.1
Page 17 of 19

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Issuance Status Report

SETH ONSHORE PROJECT

Planned

I Milestone

Dates

Milestone

Expected!

Actual

Value

As Of : 30-Apr-11

* Relative

Planned
Progress%

Weight

Actual
Progress%

Overall
Procurement

10.29%
Fab. Start

",'

"

.......

10

18-Apr-11

: 17-Feb-11

10

24-Apr-11
.......

: 17-Feb-11

Start

VPR start
.......
- - , - - . ' ,:06-Mar-11
' .. - ...

18-MaY-11,

10

22-Ju~-11 "- .. 20' - . ;


"-. -SjO.A~rd .. -. '!06~AU~-11- ~ ..... _. . "14-0d-11- ~ ... 20' . ,
~

VPR finish

" 14-Apr-11

I ~~~~~a~ !~n~~~~~i~-~i~~~~_~~~_~~~~ ~_~_;;1~:_~~~_L_~


Electrical bulk material

- .. ',':12-May-11 .

Start

05-Jun-11

Fab.
. Start
_." -, ..,:12-May-11
.. "

,~ ~~R"s!a~

,.

S/O.Award

"

.. ..
"

VPR finish

','

........ :

: 09-0c1-11

"

10
10

10.29%

0.00%

0.00%

10.29%

0.00%

0.00%

10
,.""."."

22-Sep-11:

:30-Aug-11

09-0ct-11- -

05-Jun-11

)~2:~ay-.1~.

Fab"Finish - " ":

....... "

05-Jun-11

"

01-Nov-11

20

,. i

01-Nov-11

30

20'

100.00%

Total

Expediting

7.35%
7.35%

* Weights of Activities are calculated relative to (Expediting)


Tuesday, May 17, 2011

1 10 .44 %

layout NO.1
Page 18 of 19

Data'Nes Systems, Release 2_21

Project No.: 4187-440

Issuance Status Report

As Of : 30-Apr-11

SETH ONSHORE PROJECT


Dates

Milestone
Planned

Actual

Expected

Milestone
Value

* Relative

Planned

Weight

Progress%

Actual
Progress%

Overall
Procurement

Fire detection system

NFl
RFS
Bulk

OS-Feb-12
. .......

..

....

RFS'

!19-Dec-11

NFl
RFS

0.00%

8.33%

0.00%

0.00%

16.67%

0.00%

0.00%

12.50%

0.00%

0.00%

12.50%

0.00%

0.00%

v.

60

19-Dec-11,

40

._"

~ ~~J.~~~~~_~~_~:~~~_~_:_~_~2i~~:~~~_~_~.~~?~~:

Slug Catcher

0.00%

40

12-Feb-12

NFl

8.33%

v.

__

Instrument I Fire & gas cables

NFl

RFS

Fire protection system

NFl

!!11=;;;::;~RF~Sc====d~~~=====~~~=~====~==;;o:~==;=~===;;o:===;
Piping valves
8.33%
0.00%
0.00%
~

1'=

!6W

III
~

NFl

til ~ .. -RFS' --

: 08-0ct-11

-j15-o~-;1"

PiF~~'''-~,,-=,-=-=,,-:==::;.-=~=-'''--,,~'C--,,-'''=-==-=-'-=--'~~"-=.-=.,-=,.=

II=
""""

Electrical bulk material

16-Dec-11

...

40

60' -:
.=-.=.-=",-='=,'".,,.= . -..-=.-='
,, =.=-.~=-="".-='-=."-=.=. ,"-="-=.--=--=-,,-.,,--=.-=--=-'~-.~~=-~-==-~"'~~--~--~-,,-'=-'::c_:=-~-c;-=-=c-~--,,-~--=-~-=-~--=c=",,-:==

-:-

23-6~c~1; - ~- -

8.33%

0.00%

0.00%

illtH

""

NFl

: 02-0ct-11

25-0cl-11

40

RFS ~. '09-0ct-11"'
60
01-Nov-11
IFCI"n"st:=ru=m~e"n:=t;:;B=U;;.lk====~~~~<====""======'====='=======':1"2".5"0:::%""==0"."0"0:::%""==:0
0".0"0:::.."',=

I,-

II
iii

~ ... ~~I . _

RFS

.:

~O.-?~-~1_

" ...

.1~-~~V-.1~.

~Oy

60

21-Nov-11

: 17-0ct11

,Fo\:'='===:7:==:=;;'7==!:::~~=~=========='====='=====;==';;;:;;;:::f===;::;;;:::f==::'::::::""=;
Ii
Instrument I Fire & gas Cable Trays
12.50%
0.00%
0.00%

n
$Wi
II

. " .

~~I . . . . . . . . : ~2..C?C:-~1. . ~ ...

1~-~~V~1~ _

.'.

~o.. _

IIF=,==R=F=s==-=.=-=-=-=-=.,=:~~9.=-O=.ct=:='='.=-<'=.=_=.=.=.=.=.=.=.=2=3-=N=~=V'=.'='=.====6=0=""'=====;=1~O~O~.O~O~,~y,,==r=O~.O~O~'''y,,==;=O~.~O~O~'I.~,=
Total

_:

0.00%

Inspection

layout No.1

* Weights of Activities are calculated relative to (Inspection)


Tuesday, May 17, 2011

Page 190f19

Data'Nes Systems, Release 2.21

E:n.PP1
PTB

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.3. Updated Schedule

18-MAY-2011

4187.440, PETROBEL

Enppl

04-Jan-11

Slug Catcher Data Sheets

Evaluation (Slug Catcher)


VPR (Slug Catcher)

. . . Actual Work
1_00:';'/";;>:1 Remaining Work

I!iBIIIIIIIl Critical Remaining Work:

Milestone

Page 1 of10

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30Apr-11

Summary

30

02-Feb-11

70 20-Mar-11

28-Jun-11

Start Date: 22..Dec-10


Finish Date : 26Feb~12
Data Date: 30Ap....11

Date
18-May-11

Rav.O

By: Haytham A.Rahman


Revision
Checked
A.Fathy

Approved
M. Abushanab

Print Date: 16-May-11

'~~-"'-'---

4187-440, PETROBEL

Enppl

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

HSE philosophy IFD

18 06 Mar-11

03-Apr-11 A

cause and effect

5 20-Feb-11

31-Mar 11 A

Fire

5 03-Apr-11

09-May-11

cause and effect IFC

5 21-Jul-11

Com missioning

20 Nov-11
M

IFF

27 Jul 11
28 Jul 11
M

-Aug-11
Hazardous Area Classification

02 May 11

03-Aug-11
10-Aug-11

17-Aug-11

11-Aug-11

17-Aug-11

Page 2 of 10

Enppl

4187.440, PETROBEL
SETH ONSHORE DEVELOPMENT PRO~ECT UPDATED SCHEDULE AS OF 30-Apr-11

10 06 Mar11
M

10 Mar-11
M

5
A2200

0 20-Mar-11

24-Mar-11

02-May-11

02-May-11

A2240

5 27-Mar-11

31-Mar-11

02-May-11

08-May-11

5 03-Apr-11

07-Apr-11

09-May-11

15-May-11

20-Jul-11

07-Jul-11

20-Jul-11

10-Aug-11

04-Aug-11

A2260

Junction Box Interconnecting Wiring Diagram IFD

A1560

P&ID's IFC

A2230
A1570

And Alarm Layout DraVllings IFe


Fire Fighting

Drawings IFe

11-Aug-11
24-Aug-11

A2250

5 25-Aug-11

A2270

5 05-Sep-11

Fighting System MRQ


A1990
A1590

Technical
Fire Fighting System VPR

DETECTION AND GAS SYSTEM

18-Aug-1.1

11-Sep-11

24-Aug-11

11-Sep-11

24-Mar-11

18-Feb-11 A

24-Feb-11 A

10-May-11

28-Mar-11 A

15-May-11
01-Aug-11

Page 3 of 10

4187-440, PETROBEL

Enppl

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

20

23-Mar-11 A

03-Aug-ll

A3180
A3200

Under Ground Piping Standard Details IFD

l4-Apr-1l

A1630
A3290

03-Aug-11

Under Ground Composite Drawing IFe (Header)

6
25 04-Aug-l
5 05-Sep-ll

ll-Aug-ll

04-Aug-ll

ep-ll

04-Aug-ll

ll-Sep-ll

05-Sep-ll

ll-Sep-ll

24-Feb-ll
A2330

piping specification

IFD

03-Mar-11

Page 4 of 10

Enppl
A3220

Under Ground Specification

A2340

piping specification dasses IFe

4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

A2380
A2360

Line Designation Tables JFC

A3250
A2400

IFe
Standard Steel Structure Support List IFC

A3230
A3260

Cable Routing IFD

16-Mar-11

,J'7~"~;:,:i-------- i2;;3':_'Mi~a;r:_;1-11 --I n09Q'-'M,ia~;Y;:-:'1 11 -I-,;;:"i~;;:;


A2450

Loop Diagrams

30-Mar-11

16-May-11

Page 5 of 10

Enpp l

4187.440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30.Apr-11

A2410
A2440

Aug-11

A2460

11-Aug-11

17-Aug-11

17-Aug-11

23-Aug-11

24-Aug-11

Instrument Hook Up And Supporting Drawings


IFD

--CO"~,:: ------- 'Instrument Index IFD

"."

5 27-Feb-11

03 Mar 11

02-May-11

08-May-11

17~Mar~11

23-Mar~11

09-May-11

15-MaY-11

27-Jul-11

21-Jul-11

A2510

Instrument Cable Schedule IFD

A1970

Instrument Index [Fe

5 21-Jul-11

A2500

~.,~,~-~~"~"

24~FebM11

A2490

..

0 20 Feb 11

02 MaY 11
w

03-Aug-11

03-Aug-11

Drawings
18-Aug-11

Page 6 of 10

Enppl
A2850

Instrument Cable Trays MRQ's

AZ860

Instrument

AZ870

Instrument Cable Trays VPR

A2570

Trays

4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

30 Mar-11
R

Evaluation

HazardousArea Classification Layout IFD

31-May-11

16-May-1

31-0CI-11

16-May

16-May-11

9-Jun-11

06-Ju~11

8-Aug-11

31-0cl-11

0 20-Mar-11

28-Apr-l1 A

0 06-Mar-11

10-Mar-11

5 20Mar-11

24-Mar-11

5 04-Aug-11

10-Aug-11

02-May-11
02-May-11

08-May-11

04-Aug-11

10-Aug-11

w , ' n n n n n m m " , _ ,

IFe
AZ580
A3310

AZ050

11-Aug-11

Layout [Fe

18-Aug-11

11-Aug-11

17-Aug-11

24-Aug-11

18-Aug-11

24-Aug-11

24-Aug-l1

18-Aug-11

30-Apr-11

Page 7 of 10

Enppl

AZ670

4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Ap....11

Drawings

A1740

Drawings

A1750

Slug catcher Foundation Drawings IFe

AZ6S0

Valves Foundation Drawings JFC

support Foundation Drawings

A17S0
A1790
..... :A;;'l"S:OOOO

A2730

.. !F~i;;i~,;ti~~lu:Pt:o" 'R"F"S

Bidding

...............

~;~f;,;., ;~:;; ................ ;Z'O"-';D~'e"c'-'1"1 i 'Z'Z-'M'a"'y'- ;1;1

20 1ZApr11

02-May11

24-Feb-11 A

;1 'S-;D'e'c'-';1';1

Page 8 of 10

Enppl

A1860
A1870
A1880
A3280

4187-440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr-11

Page 9 of 10

Enppt

4187.440, PETROBEL

Page 10 of 10

SETH ONSHORE DEVELOPMENT PROJECT UPDATED SCHEDULE AS OF 30-Apr11

A1940

21

A1950

Electrical Bulk Commercial Evaluation Upto PO


Issuance By PTS

A1960

Electrical Bulk Fabrication Upto RFS

15 19Apr-11

12-May-11

12-May-11

09-0cl-11

23-May-11
03~Nov-11

I:

E:n.PP1
PTB

SETH ONSHORE DEVELOPMENT

4187-440

Rev. (0
Egypt

MONTHLY PROGRESS REPORT No.2

7A.Critical and Near Critical Activities

18-MAY-2011

E.nppl

4187-440, PETROBEL

Page 1 of 2

SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30Apr-11

Commercial Evaluation Upto PO Issuance By

PTS

. . . . Actual Work
!.;",,+ x,',;, ! Remaining Work

Critical Remaining Work

Milestone

Summary

Start Date: 22Dec-10


Finish Date: 26-Feb-12
Data Date: 30-Apr..11
Print Date: 16-May-11

By: Haytham A.Rahman


Date
1SMay-11

Revision

Rev.O

Checked
A.Fathy

Approved
M. Abushanab

Enppl

4187.440, PETROBEL
SETH ONSHORE DEVELOPMENT PROJECT CRITICAL ACTIVITIES AS OF 30Apr11

Page 2 of 2

PTB

SETII ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7. S. One Month Look Ahead Report

18-MAY-2011

Project No.: 4187-440

Lookahead Report
As Of:

SETH ONSHORE PROJECT

Forecast Date:
Dates
Milestone

Expected

Planned

" Relative
Weight

Milestone
Value

Planned
Progress%

30-Apr-11
28-May~11

Actual
Progress%

Overall

Process cause and effect matrix

Design

Fire and gas cause and effect

07-Apr-11

Design

19-May-11

Start
D';Sig~

08-Apr-11

22-May-11

20.00%

4.27%

: 60.00%

0.00%

4.27%

60.00%

0.00%

4.27%

60.00%

0.00%

4.27%

60.00%

0.00%

11.11%

20.00%

20.00%

20

- - - - ~ -,' . ;2-AP~-11- -: - 25-M~Y=11- . - . -40 - - -

Fire and gas cable routing drawings

.. -

: 60.00%

40

Fire & gas 110 list

r - - -

4.27%

27-Mar-11

Start
','

Design

12-May-11

20

18-May-11

40

','

31-Mar-11

Fire and gas cable wiring diagram

Start

03Apr-11

... ~ De~ig~ ..... ',' . Oi-Apr.11

16-May-11

20

-i- "19-M~Y:1; - ... '40' ..

Fire fighting, safety equipment and safety signs

- - . - Start

Design

20-Mar-11

_.

24-Mar-11

."15-May-11- - . - - -2026-May-11

40

1. Evaluation

"Weights of Activities are calculated relative to (Process)


Tuesday, May 17, 2011

Layout No.1
Page 1 ofS

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

Expected

Milestone
Value

* Relative

Planned

Weight

Progress%

As Of:

30-Apr-11

Forecast Date:

28-May-11

Actual
Progress%

Overall

Bulk

II

T. Evaluation

7.89%

Ppiping Valves
VPR start

27-Feb-11

16-May-11

65.00%

55.00%

10

II

layout No.1

* Weights of Activities are calculated relative to (Piping)


Tuesday, May 17, 2011

Page 2 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report
As Of:
Forecast Date:

SETH ONSHORE PROJECT

I Milestone

Dates

Milestone

Planned

Expected!

* Relative
Weight

Value

II

Planned
Progress%

7.41%

Instrument Index

30-Apr-11
28-May-11

Actual
Progress%

0.00%

Start

Design

Instrument Cable Schedule

3.70%

60.00%

0.00%

3.70%

60.00%

9.88%

60.00%

0.00%

4.94%

60.00%

0.00%

3.70%

60.00%

0.00%

Start

Design

data sheets

03-Mar-11

Design

22-MaY-11

40

Instrument Hook Up And Supporting Drawings

Start

06-Mar-11

22-May-11

.. 6e"Si9~' <, 10-M~r-l1 .:.


H

25~M~Y~11

20
H'"

"40' --

Field Instrument Layouts

Start

06-Mar-11

... 6;Si9~' .:.

'10'-M~r-;1'

19-May-11

.:.

20

26~M~Y~1;

"40"-

Field Instrument Cable Routing

Star!

t 6e"sig~

10-Mar-11

- ...

>

":'

;6-Ma~r-;1

18-May~11

i 24.M~y~1;

Junction Box Interconnections


Start

17-Mar11

Design

23-Mar11

IIl~c~o~m~m~O~d~1~'t~ie~S~====::;======================:=:3:::::===:=:3:::::===::=::='='======
Instrument! Fire & gas cables

19.75%

20.00%

0.00%

ilif@

mill
MRQ
07-Apr11
19May-11
20
IF=':oln"s"'tru=m"e=n':t"BC'U"lk"'===~"'========"":==:==~==="'='======:=C;=;';;;='='=7~';;;='='=::;==;:';;;='='======;

IF
iiliili

1illti
'B3E-

M~~~~: ~"--:~~~

24-May-11

x.'-,,-_,-~~~~_.__ ~,_,_.

,_.

=':oln"sO'tru=m"e"n':t7t"'F;'ir:'e';&C'e9caC'S=;:cC'a"bC'le"T;:ra=ys==============='=======:="1:;7".2"8"0/<7,=0=';;2"0".0"0"0/<7,=::;==;:0".0"0"%;=::;======:
MRQ
_

30Mar-11

'

..24-May-11

20

Layout No.1

* Weights of Activities are calculated relative to (Instrumentation)


Tuesday, May 17, 2011

Page 3 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

* Relative

Milestone
Value

Expected

Weight

Planned
Progress%

As Of:

30~Apr~11

Forecast Date:

28~May~11

Actual
Progress%

Overall

33.33%

Electrical Lighting MRQ

Start

Finish

2Q...Mar~11

.. i4-M;r~; 1" "i'

80

layout NO.1

* Weights of Activities are calculated relative to (Electrical)


Tuesday, May 17, 2011

0.00%

20

2Q...May~11

24-M~Y:1;

100.00%

Page 4 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187440

Lookahead Report

SETH ONSHORE PROJECT

Milestone

Dates

Planned

Milestone
Value

Expected

* Relative
Weight

Planned
Progress%

As Of:

30-Apr-11

Forecast Date:

28-May-11

Actual
Progress%

1.85%

50.00%

50.00%

1.85%

50.00%

50.00%

Structural steel fabrication Specification

1.85%

50.00%

50.00%

Site preparation, earth work & backfill Specification

1.85%

50.00%

: 50.00%

1.85%

50.00%

50.00%

2.78%

50.00%

50.00%

2.76%

100.00%

60.00%

2.78%

100.00%

60.00%

8.33%

60.00%

0.00%

Shim and grouting Specification

Finish

Finish

Concrete paving Specification

18-May-11

13-MaY-11

Finish

50

Soil & foundation investigation Specification

13-MaY-11

Finish

18-May-11

50

notes
Construction

Anchor bolts standard details

Construction

17-Mar-11

40

24-May-11

Paving standard details

Construction

17-Mar-11

40

24-May-11

Standard connections details

40

Construction

Misc. Steel supports foundation plan & details

Start
20-Mar-11
- De'sig~ . - . . 24.M~r-;1

18-May-11
25-M~Y:1;'

10

~~~_".....>.--L-"---"-~,,:,,,,--,--~

50' ..
~"-""""-"-'-

Start

12-May-11

19-May-11

~ - - -Desi~~ -' _ : 2o:.Ma~-;1- - 25-M~Y:1; .:. -

.~.

0.00%

0.00%

rf

10

-50-"

* Weights of Activities are calculated relative to (Civil)


Tuesday, May 17, 2011

..

11.11%

Valves foundation plan & details

Layout No.1

Page 5 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report
As Of:
Forecast Date:

SETH ONSHORE PROJECT


Dates

Milestone

Planned

Expected

Milestone
Value

* Relative
Weight

Planned
Progress%

30-Apr-11
28-May~11

Actual
Progress%

Overall
Engineering
Drawings
New slug catcher foundation plan & details

Design

26-Jan-11

23-May-11

18-Apr-11

Start

Start

__

26-Apr-11

05-May-11

Finish

;0

1Q..MaY-11

18-May-11

26-May-11

19-May-11
T

11.11%

60.00%

0.00%

"

50

20
__

80

Weights of Activities are calculated relative to (Civil)

Tuesday, May 17, 2011

0.00%

10

26-May-11

60.00%

50

Misc. Steel supports steel details

Design

12.96%

Layout No.1
Page 6 of 8

Data'Nes Systems. Release 2.21

Project No.: 4187440

Lookahead Report

SETH ONSHORE PROJECT


Dates

Milestone

Planned

Expected

Milestone

* Relative

Value

Weight

Electrical bulk material

Instrument I Fire & gas Cable Trays


RFQ

13.Apr-11

25-May-11

30~Apr-11

28-May-11

Actual

Progress%

9.52%

40.00%

0.00%

11.90%

10.00%

0.00%

10

* Weights of Activities are calculated relative to (Purchasing)


Tuesday, May 17,2011

Planned
Progress%

As Of :
Forecast Date:

Layout No.1
Page 7 of 8

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Lookahead Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

Expected

,., Relative
Weight

Milestone
Value

As Of:

30-Apr-11

Forecast Date:

28-May-11

Planned

Actual

Progress%

Progress'%

Overall
Procurement
Commodities
10.29%

Valves
VPR start

06-Mar-11

10

Layout NO.1

Weights of Activities are calculated relative to (Expediting)


Tuesday, May 17, 2011

50.00%

Page 8 of8

Data'Nes Systems, Release 2.21

Enpp.J.
PTB

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

7.6.Procurement Status.

18-MAY-2011

As of:

18 Mav 2011

PROCUREMENT DIVISION
FOREIGN PURCHASING SECTION
PTB, SETH OFFSHORE DEVELOPMENT PROJECT
PROJECT NO.: 4187-440

Serial
no.

Commodity

SLUG CATCHER

No. of
invited
bidders
I

Bid due date


and its
extensions
lOll 112010

No. of
bidders
quoted
1

Technical
opening date

1111112010

MANUAL VALVES

20112/2010

21/12/2010

FIRE & GAS


DETECTION

6/3/2011

23/03/2011

6/3/2011
EXT TILL
14/03/2011
EXT TILL
24/03/2011

28/03/2011

13

5/4/2011
EXT TILL
12/04/2011

12

17/04/2011

FIRE FIGHTING
SYSTEM

PIPING BULK

Technical
report date

14/02/2011

10/2/2011

Revised
commercial
bid due
date

F.O.ADATE

21102/2011

AWARDED TO
PTJ
IN 17/03/2011

LCM
05B Awarded to
17/0212011
LVF
05C Awarded to

PTB, SETH ONSHORE DEVELOPMENT PROJECT


Project no.: 4187-440
R.F.Q 4187-440
Commodity: SLUG CATCHER SETH - 03
R.F.Q issuance date: 02/11/2010

Serial Supplier name

PTJ

Country

EGYPT

Technical
Technical
Technical
Technical clarification
clarification
Bidder
clarification
Bid due date
actual reply
response opening date issuance
due date
date
date

11/10/2010

6/1/2011
26/01/2011

16/01/2011
01/02/2011

16/01/2011
06/02/2011

Technical
report date

14/02/2011

Revised
commercial bid
due date

Remarks

21102/2011

AWARDED IN
17/03/2011 WITH
DELIVERY 9.5 - 11
MONTHS F.O.T

PTB, SETH ONSHORE DEVELOPMENT PROJECT


Project no.: 4187-440
R.F.Q no. 4187-440-SETH - 05
Commodity: MANUAL VALVES
R.F.Q issuance date: 01112/2010

Bid due date

Bidder
response

Technical
opening date

Technical
clarification
issuance date

Technical
Technical
Revised
Technical report
clarification due
clarification
commercial
date
actual reply date
bid due date
date

Serial

Supplier name

Country

THARWA
BREDA

EGYPT

9/1/2011

12/1/2011

TLPR

ITALY

13/01/2011
26101/2011

16101/2011
29/01/2011

23/01/2011
06102/2011

TRP-PERAR

ITALY

9/112011

12/1/201 I

23/01/2011

DAFRAM

ITALY

13/01/2011

16101/2011

19/01/2011

LVF

ITALY

1211/2011
26101/2011

1610112011
29/0112011

26101/2011
07/02/2011

DRV

U.S.A

1211/2011

16101/2011

LCM

ITALY

11/1/2011
20101/2011

15/0112011
23/0112011

16101/2011
23/01/2011

QUALIVAL

EGYPT

6/1/2011

101112011

101112011

20/12/2010

21/12/2010

10/212011

17/02/2011

Remarks

FOROSA
AWARDED TO
LCMIN
20104/2011 WITH
DELIVERY 1826wksEXW
FOROSB
AWARDED TO
LVFIN
20/04/2011 WITH
DELIVERY 2426wks FOB
FOROSC
AWARDED TO
QUALIVALIN
20/04/2011 WITH
DELIVERY 2426 EXFACTORY IN
10th of Ramadan
city, Egypt

PTB, SETH ONSHORE DEVELOPMENT PROJECT


Project No.: 4187-440
SPEC NO.: 00192700 - BMSF - 13205
Commodity: SETH - 21 /PIPING BULK MATERIALS
R F Q Issuance Date' 22/03/2011

Serial

Supplier name

Country

Bid due date Bidder response

Technical
opening date

Technical

Technical

Technical

clarification

clarification

issuance date

clarification due
date

actual reply date

AR
TECHNOLOGY

ITALY

Quoted

2/5/2011

5/5/2011

3/5/2011

HPF

UK

Quoted

2/5/2011

5/5/2011

10/5/2011

FAD

ITALY

Quoted

2/5/2011

5/5/2011

10/5/2011

DYLAN

NL

Quoted

2/5/2011
8/5/2011

5/5/2011
9/5/2011

3/5/2011
9/5/2011

CHEROP1PING

ITALY

Quoted

2/5/2011

5/5/2011

4/5/2011

IPS

ITALY

Quoted

2/5/2011

5/5/2011

8/5/2011

IGAMM

ITALY

2/5/2011

5/5/2011

4/5/2011

TLPR

ITALY

Quoted

2/5/2011

5/5/2011

5/5/2011

EJSW

EGYPT

Quoted

2/5/2011

5/512011

8/5/2011

10

TUXOR

ITALY

Regret

11

MINTA

EGYPT

Quoted

2/5/2011

5/5/2011

9/5/2011

12

FERRARI

ITALY

Quoted

2/5/2011

5/5/2011

5/5/2011

13

STEEL TRADE

ITALY

Quoted

2/5/2011

5/5/2011

4/5/2011

05/04/2011
EXT TILL
12/04/2011
EXT. TILL
14/04/2011

Quoted

17/04/2011

Technical
report date

Revised
commercial
opening date

Remarks

PTB, SETH ONSHORE DEVELOPMENT PROJECT


Project No.: 4187440
SPEC NO.: 00192700BISF24204
Commodity: FIRE & GAS DETECTION / SETH 27
R.F.Q Issuance Date: 24/0212011
Serial

Supplier name

FORESENG

Country

ITALY

Bid due date

06/03/2011

Bidder
response

Technical
opening date

Technical
clarification
issuance date

Technical
clarification due

Technical
clarification

date

actual reply date

23/03/2011

3/4/2011
ll/5/2011

6/4/2011
12/5/2011

11/4/2011

Technical
report date

Revised
commercial

opening date

Remarks

PTB, SETH ONSHORE DEVELOPMENT PROJECT


Project No.: 4187-440
SPEC NO.:00192700-BMSF-13206
Commodity: FIRE FIGHTING SYSTEM SETH - 28
R F Q Issuance Date' 24/02/2011

..

Technical
clarification
issuance date

Technical
clarification due
date

Technical
clarification
actual reply date

5/4/2011
10/5/2011

9/4/20 II
12/5/2011

10/4/2011

REGRET

10/5/2011

12/5/2011

5/4/2011
10/5/2011

9/4/20 II
12/5/2011

5/4/2011
10/5/2011
5/4/2011
10/5/201 I

9/4/2011
10/5/2011
9/4/20 II
10/5/2011

5/4/2011

9/4/2011

Serial

Supplier name

Country

SAFCO

ITALY

REGRET

DETRONICS

UAE

REGRET

EUSEBI

ITALY

FORESENG

ITALY

GENERAL
MONITORS

U.S.A

SILVANI

ITALY

SANCO

ITALY

MINTA

EGYPT

FAS

ITALY

Bid dne date

06/03/2011
EXTENDED
TILL
14/03/2011
EXTENDED
TILL
24/03/2011

Bidder response

REGRET

Technical
opening date

28/03/2011
11/4/2011
10/4/2011
12/4/201 I
10/4/2011

Technical
report date

Revised
commercial
opening date

Remarks

E:n.pp.J.
PTB

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7. 7.Equipment and material status report

PROJE.CT COMMITME.NTS STATISTICAL OVERVIEW

STATISTII

COMMITMENTS COUNT:

A.

TOTAL NO. OF ISSUED COMMITMENTS:


F.D.C ISSUED.

B.
C.

P.Oo'S COMPLETED/RELEASED FOR SHIPMENT


P.Oo'S FOR SERVICES.

D.

P.Oo'S FABRICATION IN PROGRESS.

P.Oo'S ISSUED.

o
o
4

I
i

r,

- ...
;

<

...

----

..-

,
,

1---.-

-'

..

,~

'"
i--'-.

"
"
... ~

"
"

"

,I

Enpp!

;nu

~'i~.... r,,1bo~Uw..,

SETH DEVElOPMENT PROJECT RA5!EL.BAR CONCESSION

REPORT NO. 1

AS Of 28/4/2011

FROM 9.S MONTH TO


11 MONTHS

'"

SlUG CATCHERPAcKAG,

,ETHOSA

EXWORKS/ITAlV
MANUAL VALVES

20-4-2011

lB-26WEEKS ,PLUS ONt


WEEK FO~ AUGUST
SHUTDOWN

FDA WAS ISSUEOTO PTJ ON 17/3 fOR THE SUPPLY OF ONE SLUG
CATCHER PACKAGES, COMPLETE WITllTHE INST~UMENTS, VALVES,
INTERCONNECTING PiPiNG SKID AND lOCAL CONTROL PANEl.
KOM WAS CONDUCTED ON 4/4/l0U.
PTJ suaCONTRACTED I.M.S. Indu,lric MCe<'ni'he ON ~3/3 S'''doliato
S.p,A.FORTHE OESIGN,SUPPLYOF lOOSE MATERIALS AND MECHANICAL
GARANTEE FOR THE SLUG CATCHER WITH INTE~PIPING SKID AND LDOSE
INSTRUEMENTS AND VALVES ON S SHIPMENTS fROM 21/7 fOR FLANGES
,PI PIES AND flnlNGS TILL 20/2/1.012 fOR All VALVES AND CONTROL
PANEl.,
ENGINEERING DOCUMENTS STARETDTD B, RECEIVED FROM 29/3 ANQ
20/4 FoRTHE; VESSElCAlCUAtTlON, PFo, QUAtlT'I PLAN. VDeF.OATA
SHEET.
PROCUREMENT SU~ORDERING IS SCH,OUlEO FROM l/4 Tlll29/4
IWAITING FO~ CONFIRMIITIONI
FAe~leATION IS EXPECTED fROM 14/9 Fo~ NOULE wonKS TILL
1/l/l0U.

FoA WAS ISlum TO SUPPLIER ON 1.0/4/2011 FOR lllTEMS OF MANUAL


VALVES ITOTAllB VALVE).
DRAWINGS APPROVAL IS 10 DAYS
EMAIL WAS SENT TO SUPPlIfR ON ~8/4 TO SUBMIT THE
ACKNOWLEDGMENT AND ,NGINEE;RING DOCUMENTS AND ORDER
SCHEDULE

l~-~6

WEEKS,PLUS ONE
WEEHORAUGUST
SHUTDOWN

LVF/ITALV

fDA WA5ISSUED TOSUPPUER ON


VALVES ITOTAL 36 VAlVEI.
SETH 058

FOB ITALY

MANUAL VALVES

24l6 WEEKS FROM

24-l6 WEI'K5 FROM

'"

'"

"

"

:!OI~/2011

FOR U ITEMS OF MANUAL

,-MAil WAS SENT TO SUPPlIER ON 28/4 TO SUBMIT THE

ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORDER


SCHeDULE

204-2011

QUAUVAl/,GYPT
FOA WAS ISSUED

TOSU~PtlER

ON 20/4/Z011 FORS ITEMS OF MANUAL

VAlVES{TOTAL ,VALVE)
E~WORKS

sF;THOSC

MANUAL VAlVES

jlOTH Of

RAMADAN (;YPT

241.6 WEEKS fROM

2426 WEEKS fROM

'"

'"

"

"

"

E'MAll WAS SENTlO SUPPLIER ON 28/4 TO SUBMITrHE


ACKNOWLEDGMENT AND ENGINEERING DOCUMENTS AND ORD,R

SCHEDULE.

Enppa
PTB

SETH ONSHORE DEVELOPMENT

4187-440
Rev. (0

Egypt

MONTHLY PROGRESS REPORT No.2

18-MAY-2011

7. 8.Alert report

rI

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT

Milestone

I Milestone

Dates

Expected!

Planned

Value

* Relative

I i Planned. 1

Weight

Progress%

3.70%

Structural general notes

Construction

24-May-11
-"--

As Of :

100.00%

Actual
Progress%

60.00%

30-Apr-11

Weighted
Delay

1.48%

40

..--........--'---"-~-"---"---"---"-------------_._----_._-------------_._----

2.78%

100.00%

60.00%

1.11%

Paving standard details

2.78%

100.00%

60.00%

1.11%

Standard connections details

2.78%

100.00%

60.00%

1.11%

8.33%

60.00%

0.00%

5.00%

12.96%

60.00%

0.00%

7.78%

11.11%

60.00%

0.00% :

6.67%

Anchor bolts standard details

Construction

Construction

17-Mar-11

24-May-11

40

17-Mar-11

Misc. steel supports foundation plan & details

.. Start
. - . . . . . ..

. 19..May-11

20-Mar-11

Design

~.

24-Mar-11

10

25-May-11

50

New slug catcher foundation plan & details


OS-Jun-11

Start

10

Misc. steel supports steel details

Start
-

18~Apr-11

Design

26-Apr-11

18-May-11

<

26-May-11

10
"

"

50

Layout No.1

* Weights of Activities are calculated relative to (Civil)


Tuesday, May 17, 2011

Page 5 of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT

Milestone

I Milestone

Dates
Planned

Expected

Value

Instrument I Fire & gas cables

RFQ

11-Apr-11

02-Jun-11

RFQ

- ..........

02-Jun-11

11-Apr-11

..

26-Jun-11

Weighted
Delay

9.52%

10.00%

0.00%

0.95%

9.52%

40.00%

0.00%

3.81%

11.90%

10.00%

0.00%

1.19%

11.90%

10.00%

0.00%

1.19%

10

13-Apr-11

25-May-11

10

layout No.1

Weights of Activities are calculated relative to (Purchasing)


Tuesday, May 17, 2011

Actual

Progress%

30

Instrument I Fire & gas Cable Trays

RFQ

Instrument Bulk

RFQ

OZ-Jun-11
10
- - - 28-Mar-11
- - . - . .....
- - - - - ......

18-Apr-11

Ree.Bids

Planned

Progress%

30-Apr-11

10

Electrical bulk material

"

* Relative
Weight

As Of :

Page6of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT


Dates

Milestone

Planned

Expected

* Relative

Milestone
Value

Weight

As Of : 30Apr11

Planned

Progress%

Actual
Progress%

Weighted
Delay

Overall
Procurement

10.29%
VPR start

06-Mar-11

18-May-11

10

VPR finish

14-Apr-11

22-Jun-11

20

50.00%

20.00%

3.09%

I
.. Weights of Activities are calculated relative to (Expediting)
Tuesday, May 17, 2011

Layout No.1
Page 7 of 7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

Expected

Milestone
Value

Process cause and effect matrix

24-Feb-11

Design

---"--"----"_"-".'-.....L ......."'-..... _ ......

16-MaY-11

Fire &

07-Apr-11

27-Mar-11

20.00%

1.71%

60.00%

20.00%:

1.71 %

4.27%

60.00%

0.00%

2.56%

4.27%

60.00%

0.00%

2.56%

4.27%

60.00%

0.00%

2_56%

4.27%

60.00%

0.00% :

2.56%

?~-~P!-~1 i. ;~~~Y:1~.

" " :

'07-Apr-11 '

19-May-11

Fire fighting, safety equipment and safety signs

Start

20-Mar-11

Design

24-Mar-11

15-May-11

..

"".

--

26-May-11

20

40

Layout NO.1

* Weights of Activities are calculated relative to (Process)


Tuesday, May 17, 2011

4.27%

20

12-May-11

Fire and gas cable wiring diagram

Design

60.00%

Weighted
Delay

20
"40""

Fire and gas cable routing drawings

:t~rt".

4.27%

Actual
Progress%

40

Start
08-Apr-11 ,22-May-11
"_. De~ig~ ', 1i-Ap'r-11- -,- 25-M~Y~1;

Planned
Progress%

40

1/0 list

Start

'" Relative
Weight

-"-,~'~_"--'-"-,"--'-"......:... ..................

Fire and gas cause and effect

Design

As Of : 30-Apr-11

Page 1 of7

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

Expected

* Relative

Milestone
Value

Weight

As Of : 30-Apr-11

Planned
Progress%

Actual
Progress%

Weighted
Delay

Overall
Engineering

7.89%

Ppiping Valves
VPR start

27-Feb-11

16-May-11

55.00%

0.79%

10

layout NO.1

* Weights of Activities are calculated relative to {Piping)


Tuesday, May 17, 2011

65.00%

Page 2 of?

Data'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT


Dates
Milestone

Expected

Planned

* Relative

Milestone
Value

Weight

As Of : 30-Apr-11

Planned
Progress%

Start

,20-Feb-11

~~~~:~?~~~~~~Feb.;1

15-May11:

Weighted
Delay

60.00%

0.00%

4.44%

3.70%

60.00%

20.00%

1.48%

9.88%

60.00%

0.00%

5.93%

4.94%

60.00%

0.00%

2.96%

3.70%

60.00%

0.00%

2.22%

4.94%

60.00%

0.00%

2.96%

7.41%

Instrument Index

Actual
Progress%

20

":' ;8-0~Y:1~ ~ :i :_~:~~~~_: __~~ __~~. __."~._". _


3.70%

Instrument Cable Schedule

Start

Design

22May11

03-Mar-11

40

..

Instrument Hook Up And Supporting Drawings

Start

06~Mar11

" " - - De~i~~ ..

H H;'

10.Ma"r-11"

i 22-May-11
20
"i' i5-M~Y=1; .... "40 - - "

Field Instrument Layouts

Start

,06-Mar-11

r " - - 6e~i~~

...

":'

10-M';r-11"

r!

19-May-11
26-M~Y=1;

20

.... "40 - . "

Field Instrument Cable Routing


Start

Design

Junction Box Interconnections

_.

Design

_.".

23-Mar-11

20

25-May-11

17-Mar-11

Start

.,_

A,A

26-May-11

40

~l",c;o~m;m;;;O;d;i;ti~e~s=.=::;:===;:=;:===================::::==::::;===========:::==
;If

Instru:::tI Fire & gas ca:~_:P'_11

19.May-11

20

19.75%

20.00%

=::====:::==~:::::;;=.=:::;
0.00%

3.95%

F"I"n"'struO=m""e"n"t=B"'U:'lk=:="'=:-=~:=~""="""'=:=:=""'=~"~"~""C:C=:=""=c.=-=-="",,~~~=--~~~=-~~=:~1=7-=;.~2':'8"':'%:'-==-=-="':2"':'0-=.O:'0':%7==~~'--~0=.0='-;;-=""l\==~-==3-=.~4':'6"':'~l\""~-=;

$1

!=F""="",M"R=Q"""'=:""'""",7'""",~~,,,""=~=--3,,0=.M,,="',,-~,,,'...~,,,,,2=4-,,,M,,a=y,,-""="==",2"0",,,.~,,,,.~=_=_==~=_=_=-=-=-==:_::,:7'=.-=-=-=_=-=-7'._""'_7'~_=.~-'--=-=O-""'~~=-=7~"7,,"=-=;
__

Instrument! Fire & gas Cable Trays

17.28%

20.00%:

0.00%

3.46%

=
mm

MRQ

30-Mar-11

layout NO.1

* Weights of Activities are calculated relative to (Instrumentation)

Tuesday, May 17, 2011

Page30f7

Dala'Nes Systems, Release 2.21

Project No.: 4187-440

Alert I Delay Report

SETH ONSHORE PROJECT


Dates
Milestone

Planned

Expected

Milestone
Value

* Relative
Weight

As Of : 30-Apr-11

II

Planned D

Progress%

Actual

Progress%

Weighted

Delay

Overall

Electrical Lighting MRQ

Start

33.33%
20-Mar-11

..2o-May-11

20

24-May-11

80

"."

Finish

0.00%

33.33%

layout No.1

* Weights of Activities are calculated relative to (Electrical)


Tuesday, May 17, 2011

100.00%

Page 4 of?

Data'Nes Systems, Release 2.21

S-ar putea să vă placă și