Documente Academic
Documente Profesional
Documente Cultură
2.
DECISION
The appeal was dismissed on the ground that the appellants have the
constructive knowledge regarding the mistake done by the respondent.
Besides that, the fact that the appellants have a very credible background
provide better support to say that this factor should be take into account.
Plus, the appellants intention to seek profit from purchasing the printer is
another additional factor to show the appellants have a good constructive
knowledge regarding the mistake done by the respondent and took an
opportunity over it.
3.
PRINCIPLE
Constructive knowledge is sufficient to render the contract void on the
ground of unilateral mistake. But, it is important to mention that additional
factors such as credibility of the person and other surrounding
circumstances must also be taken into account as constructive knowledge
alone cannot render the contract to be void
4.
CRITICAL ANALYSIS
a)
30
Interesting point to be noted that this court distinguished itself from the
case of Great Peace Shipping Ltd v Tsavliris Salvage (International) Ltd
[2003] QB 679. This distinguished case was regarding one vessel which
was in distress in its journey. In the Court Of Appeal, the trial judge
mentioned it is unquestionable that there is no room for rescission in
equity of a contract which is void. It is distinguishable that both case are
different. It is because the referred case is a common mistakes case
whereas the present case is related to unilateral case. But, the judge
agreed that actually the law itself is already came with an equitable
jurisdiction. Hence, instead of applying separate doctrine of law and
doctrine of equity, the learned judge inclined to find the equity in the law
itself. the learned judge was in an opinion to rationalise the legislation so
that it can be applied in this present case and later provides just and fair
judgement for the parties involved.
In discussing on unilateral mistake, the learned judge agreed with
exception of the principle that the contract will binding when a party made
a mistake in that particular contract. the exception mentioned that the
contract will not be binding if the non-mistaken party already knew that
there is mistake committed by the mistaken party. It is because there is no
It is also must be noted that this court also distinguished itself from the
when suggestion made by the majority judgement in case of Taylor v
Johnson [1983] 151 CLR 422 tend to suggest that the contract would not
be void even where the non-mistaken party knew of a fundamental
mistake. The present court in an opinion that when a non-mistaken party
who knew that there must be something wrong with the contract continues
to affirm such transactions and act as nothing happened, the conduct itself
is already against the concept of equity which came along with the law. It
is a point to stress out that the party involves in such commercial dealings
should act with sincere conduct and did not perform any act which may
cause the other party to suffer loss which is not due to their lack of care.
Although mistake usually come along with carelessness, but it is not the
argument in this case as the mistake sometimes may happened in a
technical manner.
Something that is crucial to be noted that this court has departured itself
from the judgement by Denning LJ in case of Solle v Butcher [1950] 1 KB
671. In this reported case, the learned Denning LJ seemed to have
conflated the law with equity. Lord Denning also suggested the application
of equitable jurisdiction in the case of mistake. However, the court in the
present case believe that there is no jurisdiction in equity to grant a
rescission of a contract on the ground of common mistake where the
contract was valid and enforceable on ordinary principles of contract law.
As mentioned earlier, the learned judges in present case tried to rationalise
the legislation as they strongly believe that the law is already came with
the equitable principles.
b)
PRESENT CASE
In present case, the trial judge was inclined to prove that a constructive
knowledge may render a contract to be void under unilateral mistake
subjected to circumstancial evidences. Despite of using the doctrine of
equitable jurisdiction which they believe already covered by the law itself,
the learned judges managed to prove that constructive knowledge may be
affirmed as actual knowledge which the appellants had subject to the
surrounding evidence. This constructive knowledge made the state of a
persons mind as the question of fact. Thus, to prove the existence of this
actual knowledge, the learned judges went for a reasoning process where
it may considered what a reasonable man will be think of as he/she is in
similar position. Court went for Nelsonian Knowledge which meant
shutting ones eyes to the obvious. The learned judge also applied what is
mentioned in the case of OT Africa Line Ltd v Vickers Plc [1996] 1 Lloyds
Rep 700, that there must be a real reason to suppose the existence of a
mistake. But, it still depend on the circumstances of the present case.
After evaluating all appellants, courts came into conclusion that all the
appellants knew about the mistake or at least they have the constructive
knowledge regarding the mistake. The presence of surrounding evidences
later strengthen that there is existence of real knowledge regarding the
mistake committed by the mistaken party. The elements of opportunistic
and profit-seeking is manifested in the appellants which drive them to
proceed with such contract although they apparently knew that there is
something wrong or mistake happened in the transaction.
5.
CONCLUSION
All three learned judges in the Court of Appeal were in the same position as
they agreed unanimously to dismiss the plaintiffs appeal except in the
issue related to the cost of trial where they will bear 90% from the actual
cost, different with the previous judgement. The three learned judges came
into conclusion by finding and utilising the available evidence to suit with
the law as they believe that the law is already came with equity to provide
the best outcome for any parties.
The plaintiff (Statoil ASA) is the seller for 32,000 tons of liquid propane gas (LPG).
The defendant (Louis Dreyfus Energy Services LP) is the buyer of the said items.
The plaintiff chatered a vessel called Harriette N to carry the 32,000 tons of LPG
bought by the defendant to several possible ranges of discharge ports. The
negotiation regarding the sale and purchase of the said items is done under the
cif contract (cost, insurance and freight). This negotiation is done by the plaintiff
and the defendant through a middle-man named Mr. Andersen who is also a
broker. Upon finalising the contract, the defendant issued a condition under the
heading of Demurrage which mentioned that the demurrage claim shall be
submitted by the seller within 90 days after the completion of discharge. This
conditions issued that the claim will be barred if the seller brought it after the
expiration of 90 days. However, this condition later is excluded from the real
agreement without any parties mentioning to reinsert this condition. This
agreement is agreed by both parties. The vessel which carried 32,000 tons of LPG
started to discharge first parcel (23-25 September 2006), second parcel (11-13
October 2006) and lastly third parcel (23-24 October 2006). The owner of the
vessels sent a first demurrage statement to the plaintiff after discharging second
parcel. Erroneously, one Mr. Rostrup calculated the demurrage claim that Statoil
was to make on Louis Dreyfus Energy Services LP up to 16 October 2006 only. His
conduct actually caused him to neglect the discharge of the last parcel. On 13
November 2006, the demurrage claim was sent to one Mr Hodge of Louis Dreyfus
Energy Services LP together with supporting documents. This Mr Hodge managed
to figure out this error committed regarding the calculation in demurrage claim.
He later decided to keep silent regarding this issue and just waiting for the other
party who submitted this demurrage claim to realise it on his own. As for this
reason, the demurrage claim which amount to US$137,694.50 is agreed by both
parties on 26 January 2007 and was paid on later date, 2 February 2007. Upon
receiving information regarding the real date of completion of discharge from the
vessels owner on the date of payment, one Mr. Rostrup wrote a letter to Mr.
Hodge to clarify this issue of mistake happened between them and asked for the
revision on the demurrage claim (actual sum is US$549,360.96). Mr. Hodge
reluctant to agree on the revision. Later, Mr. Rostrup had a telephone
conversation with Mr. Hodge who later agreed to pay remaining sum
(US$435,833.12) if the plaintiff considered to do the adjustment and reduction for
six hours which related to the laytime. Later, Mr. Rostrup managed to concede
the six hours but Mr. Hodge suddenly refused to do so and contended that there
is no oral agreement between him and on Mr. Rostrup. He also argued that the
demurrage claim brought by the plaintiffs representatives is barred by the time
limitation. The plaintiff brought a claim before the court against the defendant to
claim the remaining balance (US$435,833.12) of the demurrage as it alleged to
be due.
2.
DECISION
The learned judge allowed the plaintiffs claim for the remaining balance based
on the real existence of the oral agreement between one Mr. Rostrup and Mr.
Hodge made on 19 March 2007 which actually has superseded that agreement
made on 26 January 2007.
3.
PRINCIPLE
The court does not recognised the existence of such equitable jurisdiction that
allowed an agreement to be voidable in equity for unilateral mistake as to a fact
or state of affairs which the basis upon which the terms of the contracts are
agreed. The learned judge succeeded in the best way to evaluate all the available
evidences provided by both parties in order to reach to a just and fair conclusion.
Instead of granting rescission based on equity principle, available evidences was
used optimumly. Also stressing on the fact of negligence on the claimants party,
court expressly mentioned that equitable principles are not applicable in the
present case as it may render the justice and truth to be vitiated.
4.
CRITICAL ANALYSIS
a)
In the judgement, the learned judge Mr Justice Aikens has discussed a few
cases in an extensive manner. For example, the learned judge did so when
he was discussing the statement made by Andrew Smith J in Huyton SA v
Distribuidora Internacional De Productos Agricolas SA de CV [2003] 2
Lloyds Rep 780. This case is about the Plaintiff (Huyton) who entered into
a contract on the mistaken belief that the goods were stored at
warehouses owned or leased by particular party and not in the factory. As
the common law will refuse to hold that the contract is not binding, the
learned judge in this mentioned case inclined to accept that there is an
equitable jurisdiction of the court to set aside a contract on grounds of
unilateral mistake. However, he mentioned that this jurisdiction was
limited by and subject to a number of considerations. Mr. Justice Aikens
expressly mentioned that he had disagree with the conclusion in the
mentioned case. It is because he believe that when a party did a mistake
related to the fact or state of affairs which is the basis upon which the
terms of the contract are agreed, but the assumption is not part of terms of
contract, hence there is no room for such equitable jurisdiction to be
applied.
The learned judge Mr. Justice Aikens also mentioned the case of Great
Peace Shipping Ltd v Tsavliris Salvage (International) Ltd [2002] Lloyds
Rep 653 in his judgement. Based on his statement, he was inclined to
follow this case which expressly stated that there is no such equitable
jurisdiction in the case of a unilateral mistake.
The learned judge has followed one of the case, Smith v Hughes (1871) LR
6 QB 597 which the finding of this case proved that when one party made
a mistake of fact of which he relied on it to enter into the contract, but the
fact itself is not a part of the contract, the contract will be binding
eventhough the other party knows about the mistake in the contract.
b)
PRESENT CASE
Based on this present case, few issues managed to be answered by the
learned judge. They are :
I.
II.
III.
IV.
5.
CONCLUSION
Equitable jurisdiction is not the best solution to grant a rescission of a
contract where one party has made unilateral mistake as to the facts or
state of affairs which is the basis upon which the terms of the contract are
agreed. In addition, this facts are not the term of contract. Due to the
presence of negligence which constituted the mistake done by the said
party, it is obvious that the application of equitable jurisdiction will deny
the real objectives of law which is to help to restitute or give compensation
the party who is not in any false action. If it is applied, the law is deemed
to be a protection for such stupidity act and carelessness conduct by a
party who are not aware and really concerned in managing his/her
conduct. However, in this case the learned judge allowed the claimants
claim not based on the equitable jurisdiction. It is rather be done by the
maximum utilisation of available evidence which later save the party from
his own negligence conduct.