Documente Academic
Documente Profesional
Documente Cultură
together in a contract
environment
IMCA
ublications
Global experience
The International Association of Oil & Gas Producers (formerly the E&P Forum) has
access to a wealth of technical knowledge and experience with its members operating
around the world in many different terrains. We collate and distil this valuable knowledge for the industry to use as guidelines for good practice by individual members.
Disclaimer
Whilst every effort has been made to ensure the accuracy of the information contained in this
publication, neither the OGP nor any of its members will assume liability for any use made
thereof.
Copyright OGP
Material may not be copied, reproduced, republished, downloaded, posted, broadcast or
transmitted in any way except for your own personal non-commercial home use. Any other
use requires the prior written permission of the OGP.
These Terms and Conditions shall be governed by and construed in accordance with the laws
of England and Wales. Disputes arising here from shall be exclusively subject to the jurisdiction of the courts of England and Wales.
Authors
These guidelines have been prepared for OGP by the Safety, Health and Personnel Competence
Committee, SHAPCC, through its Contractor HSE Task Force, in consultation with the International
Association of Geophysical Contractors, IAGC, and the International Marine Contractors Association,
IMCA, who both endorse the use of these Guidelines.
Arco
Arco
Baker Hughes
BG Plc
BP Amoco
BP Amoco
BP Amoco
Chevron
Conoco
Elf E&P
Esso
IADC
IAGC
PDVSA
SagaPetroleum
Saga Petroleum
Schlumberger
Shell
Shell
Shell
Statoil
Total
Total
E&P Forum
Chairman
Chairman
Secretary
Following the Task Force work on developing the guidelines, Bob Moschetta undertook the role of
Technical Editor to review and address comments and suggested amendments.
The International Association of Oil & Gas Producers is the international association of oil companies
and petroleum organisations formed in 1974. It was established to represent its members interests at the
International Maritime Organisation and other specialist agencies of the United Nations, and to
governmental and other international bodies concerned with regulating exploration and production of oil
and gas. While maintaining this activity, OGP now concerns itself with all aspects of exploration and
production operations, with particular emphasis on safety of personnel and protection of the
environment, and seeks to establish industry positions with regard to such matters.
As of mid 1999, OGP has 57 members made up of 47 oil companies and 10 national and international
oil industry associations operating in more than 60 different countries. The Safety & Health and
Personnel Competence Committee (SHAPCC) of OGP has observers from IADC, IAGC and IMCA in
its membership.
Contents
Purpose/Intent...................................................................................................................iii
Description........................................................................................................................iii
1.
Introduction ................................................................................................................1
1.1 Background........................................................................................................................ 1
1.2 Interrelationship with other systems ................................................................................... 2
2.
3.
Planning ......................................................................................................................5
3.1
3.2
3.3
3.4
3.5
4.
Pre-qualification ..........................................................................................................9
4.1
4.2
4.3
4.4
4.5
5.
Objective............................................................................................................................ 9
Purpose and responsibilities ............................................................................................... 9
Standard pre-qualification documents ................................................................................ 9
Screening............................................................................................................................ 9
From pre-qualification to selection................................................................................... 10
Selection ....................................................................................................................11
5.1
5.2
5.3
5.4
5.5
5.6
6.
Objectives .......................................................................................................................... 5
Description of work ........................................................................................................... 5
Risk identification .............................................................................................................. 5
Contracting strategy ........................................................................................................... 6
Contract schedule............................................................................................................... 7
Objective.......................................................................................................................... 11
Bid documentation prepared by company ........................................................................ 11
Bid preparation by contractor .......................................................................................... 12
Pre-award meetings .......................................................................................................... 12
Incentive schemes for HSE............................................................................................... 12
Contract award ................................................................................................................ 13
Pre-mobilisation activities..........................................................................................15
6.1 Objectives ........................................................................................................................ 15
6.2 Kick-off meeting .............................................................................................................. 15
6.3 Pre-job audits ................................................................................................................... 16
7.
Mobilisation ..............................................................................................................17
7.1 Objectives ........................................................................................................................ 17
7.2 General ............................................................................................................................ 17
7.3 Mobilisation audit............................................................................................................ 17
8.
Execution ..................................................................................................................19
8.1
8.2
8.3
8.4
8.5
9.
Objectives ........................................................................................................................ 19
Responsibilities ................................................................................................................ 19
Contractor compliance..................................................................................................... 19
Competence assurance...................................................................................................... 19
Inspection and HSE auditing/reviews............................................................................... 20
De-mobilisation.........................................................................................................21
9.1 Objectives ........................................................................................................................ 21
9.2 Responsibilities ................................................................................................................ 21
ii
Purpose/Intent
The overall objective of this guideline is to improve the company and contractor health, safety and
environmental (HSE) performance regarding exploration and production activities. Active and ongoing
participation by both the company and contractors are essential to achieve this goal. While each has a
distinct role to play in ensuring the ongoing safety of all involved, there is an opportunity to further
enhance the company/contractor relationship by clearly defining roles and responsibilities, establishing
expectations and maintaining communication throughout the relationship. For example, one role of the
company is to review and assess the contractors HSE Management System and Programmes, while one
role of the contractor is to provide HSE information as requested by the company. Often the information
requests vary from company to company. By establishing a standard format, which streamlines the
bidding process, company and contractor resources can be devoted to improving specific HSE issues.
This guideline is designed to:
1. improve workplace safety, health and environmental performance by assisting the company and
contractors in administering an effective HSE program for the contract;
2. assist contractors in administering programs which are consistent with the clients expectations;
3. facilitate the interface of contractors activities with those of the company, other contractors and subcontractors.
These programs should be designed to protect both company and contractor personnel from workplace
injuries and illness as well as from losses associated with the incidents, while preserving the independent
contractor relationship.
This information is provided to assist company and contractor management to visualise the process of
managing contractor HSE programs. This document is not intended to replace the necessary professional
judgement needed to recommend the specific strategy to follow. Each reader must analyse their particular
situation, tailor the information in this document and obtain the appropriate technical support.
Due to the rapid change that is occurring in the oil and gas industry, together with the various companycontractor interface systems and management practices that are evolving, this guideline will be reviewed
every 2 years. The Safety Health and Personnel Competency Committee will make updates and
modifications based upon review.
Description
The main section of the document covers various phases of the contracting process and the associated
HSE tasks and responsibilities of the company and contractors. This is an eight-phase process, which
begins with planning, and ends in final evaluation and close out. The objectives, roles and responsibilities
are defined for each phase.
A key part of the planning phase is risk identification. It is also the prime factor in determining
contracting strategy. During this step the level of risk is assessed and the most appropriate measures are
identified to prevent incidents from occurring. Included in the appendices are additional tools such as
checklists for HSE Plan development, severity of risk definitions, and guidelines for small and large
contracts.
iii
iv
1.
Introduction
1. Introduction
1.1 Background
Within the oil and gas exploration and production industry, the pattern of use of contractors has changed
significantly over the last ten years. Figure 1 shows the pattern of company and contractor hours reported
to E&P Forum for the period
1985-1998.
Figure 1. Company contractor hours worked
Prior to 1985 the work force
was predominately company
employees. Since 1990 there
has been a significant increase
in the use of contractor staff,
with a resulting shift in
responsibility and risk from
the company to the contractor
population.
It can be seen from Figure 2
that
there
have
been
significant improvements in
the safety performance of both
the Companies and their
contractors during this period.
(millions of hours)
1200
1000
800
Manhours
contractor
600
400
Manhours
company
200
0
1985
1987
1989
1991
1993
1995
1997
Figure 2.
10
Overall
8.1
Company
6.6
Contractor
6.1
5.2
4.7
4.1
4
3.4
2.5
1989
1990
2.8
1991
3.3
1992
3.9
3.1
3.0
1993
2.5
1994
2.6
1995
3.0
2.0
1996
2.7
2.0
1997
1.9
1998
2.
Overview of process
2. Overview of process
Management of HSE in a business environment where two or more companies work together requires cooperation between them and a clear definition of the tasks and responsibilities of each of the parties.
The typical phases of a contracting process are shown in Figure 3. The sectional headings addressing the
phases are shown on the right. Each section describes the tasks and responsibilities showing a clear
distinction between the company and contractor(s). An overview of responsibilities is given in Appendix I.
Company
Description of work &
risk identification
Planning
Contracting strategy
Contractor responds to
questionnaire and
provides HSE information
Shortlist and
screen contractors
Contractor prepares
bid and HSE plan
Bid evaluation
and clarification
Establish bid
evaluation criteria
Pre-qualification
Contractor
database
Selection
Contract award
Pre-mob audits
Kick-off meeting
Mobilisation
Pre-execution audit
Execution, supervision
and reporting
Monitoring, audits
and inspection
M obilisation
Execution
De-mobilisation
Acceptance of work
and restored site
De-mobilisation
Close-out
Review
Report
Pre-mobilisation
3.
Planning
3. Planning
3.1 Objectives
The objectives of this phase are to describe the work and to assess the HSE risks associated with the work.
The contracting strategy is to be selected on the nature and size of the work, and the risk involved.
Increasing probability
Reputation
Environment
Assets
People
Severity
Consequence
No
health No
effect/injury
damage
No effect
Minor
effect
Considerable
impact
Single fatality
Major
damage
National impact
Multiple
fatalities
Extensive Massive
damage effect
3.4
Major
effect
Never heard
of in E&P
industry
Heard of in
E&P
industry
Incident has
occurred in
our
Company
Happens
several
times per
year in our
Company
Happens
several
times per
year in a
location
No impact
Limited impact
International
impact
Incorporate risk
reduction measures
Intolerable
Contracting strategy
One of the most important strategic contract management decisions to be made by the company is on the
way in which the contractor, or alliance of contractors, is held responsible for the management of HSE.
Two distinctly different modes are described below.
Mode 1. The contractor provides people and tools for the execution of work under the supervision,
instructions and HSE-MS of the company. The contractor has a management system to provide
assurance that the personnel for whom he is responsible are qualified and healthy for the job and
that the tools and machinery he is providing are properly maintained and suitable for the job.
Mode 2. The contractor executes all aspects of the job under its own HSE Management System, provides
the necessary instructions and supervision and verifies the proper functioning of its HSE
Management System. The company is responsible for verifying the overall effectiveness of the
HSE management controls put in place by the contractor, and assuring that both the
companys and the contractors HSE-MS are appropriately compatible.
Selection of one of these modes is preferred. However, in certain situations it may be necessary to adopt a
mixture of the two modes. This can be accomplished by following Section 3.5 of the E&P Forum
Guideline for the Development and Application of Health, Safety and Environmental Management
Systems, Report No. 6.36/210. This section outlines the interfacing of contractors activities with those of
the company and with those of other contractors as appropriate. This may be accomplished by means of a
specific interface document between the company and the contractor so that differences may be resolved
and procedures agreed before work commences. Examples of such situations are given below.
3.
Planning
Operations in an area where there is a limited selection of contractors able to meet the evaluation
criteria. For example an alliance may have to be formed between the company and available
contractors with the objective to develop, improve and implement an HSE Management System for
the contractor while executing work under the management system of the company. The management
system will initially aim at working under Mode 1.
Operations too large or diverse for a single contractor may require a number of contractors and
subcontractors (a consortium) to work together under the supervision of one main contractor working
for the company under Mode 2.
The work is intimately associated with the activities of the company, or presents such a high risk to the
company that the work is to be executed using the company's management system under Mode 1.
The contractor executes most aspects of the job under its own HSE Management System; however,
certain support activities such as transportation and emergency response are provided by the company.
A Drilling Contractor is responsible for identifying and supplying personal protective equipment to its
personnel. A Fluids Contractor designs the mud program for the Operator, with new additives
included in the well plan. In this case the company has an interface procedure that details the
responsibilities of the drilling contractor and requires the fluid contractor to provide chemical hazard
information to the Operator and drilling contractor before shipping the materials. The interface
procedure further requires the on-site fluids engineer to communicate chemical hazards during the prespud meeting.
Also, when working with an alliance of contractor(s) or a consortium, it should be made clear in advance
whether the alliance or the lead contractor is fully responsible for all instructions and supervision or
whether that is the responsibility of the company. If the alliance or consortium is responsible, it should be
made clear in the contract how this is organised. In addition, the person responsible for critical activities
has to be clearly identified. Joint responsibilities should be avoided by breaking down the work into
smaller identifiable activities, each with a party assigned to it with responsibility for the HSE aspects.
Usually Mode 2 is preferred except in "High Risk" situations where the work is highly interactive with
companys activities.
Example:
Example:
A consortium of contractors with one lead contractor is responsible for the construction of a
new onshore production facility. Construction activities are always "High Risk". However,
until the moment that hydrocarbons are introduced, the lead contractor can be held
accountable for managing all aspects of the job provided the construction contractor can
demonstrate its capability to manage all HSE aspects. Typically Mode 2 would be used.
"Low Risk" contracted operations, e.g., deliveries of non-critical materials, food, stationery, etc., are
usually covered by Mode 2 whereby the contractor provides the HSE controls. Usually the company
controls on such low risk activities are minimal and Mode 2 is typical. However, contractors working on
company premises are normally under the control of company personnel and should follow company
instructions.
Issues in setting a contract strategy might include: number of contracts, contract schedule, rules and
regulations, and the use of company HSE standards and/or relevant national HSE legislation and
international conventions.
4.
Pre-qualification
4. Pre-qualification
4.1 Objective
The objective of the Pre-qualification phase is to screen potential contractors to establish that they have
the necessary experience, capability and financial viability to undertake the activities in question safely and
in an environmentally sound manner.
4.2
The general practice in Companies for selecting contractors is through competitive tendering. In the prequalification stage, potential contractors are screened to establish that they have the necessary experience
and capability to undertake the activities in question. Only those being able to demonstrate that they can
manage in a fully satisfactory manner the HSE risks of the work, should be included on the pre-qualified
list. A formal historical record of the HSE performance, including findings of audits and inspections, of
all contractors previously employed, should be maintained by the company for use during the prequalification process.
The pre-qualification process is a crucial step in which assurance is sought that the risks of the work will
be managed. The purpose of the pre-qualification stage is for the company to agree on a list of contractors
that will be invited to bid, and a list of HSE bid evaluation criteria to be met. Pre-qualification is one of
the last safeguards in identifying suitable contractors. Once contractors are qualified to bid, they are
eligible for award of a contract.
The company contract manager is responsible for pre-qualification and providing assurance that the
contractors invited to bid can manage the HSE risks associated with the work.
4.3
Pre-qualification is usually achieved by issuing a standard format document for the contractor to
complete, supported where necessary by historical performance records. It may be necessary to review the
content before issue and to add, remove or emphasise requirements specific to the activity.
As a means to streamline the pre-qualification process, the E&P Forum recommends that companies
adopt the pre-qualification questionnaire, located in Appendix III. Requests for additional or company
specific information that is not included in the questionnaire can be inserted into Section 9. By
implementing this standard format, both the company and contractors can devote their resources to
improving HSE performance rather than reformatting existing information into a variety of formats.
Of special importance is the management by contractors of their subcontractors and the need for the main
contractor to demonstrate understanding and commitment to having full responsibility in this area.
Similarly, when contractors are working in an alliance or consortium, it is of special importance to
demonstrate that each entity fully understands, and is committed to, the HSE management of the
assigned HSE critical activities.
A points system method, which minimises subjective judgement, may be used to evaluate contractors
submissions. Contractors who achieve a pre-defined acceptable score will then be judged to have met the
HSE pre-contract requirements. Appendix IV provides guidelines for such a rating system.
4.4
Screening
The screening process should be designed to assure that the contractors invited to bid can perform the
work to the required HSE criteria.
The general approach is to send a uniform questionnaire to all potential contractors, initially assess their
HSE capabilities based on the questionnaire using an equitable measuring system (see Appendix III) and
supplementing this with site inspections of current contractor work sites.
Contractors which have been used by the company previously can be assessed through the use of close out
reports and other historical records. A review of any potential changes to the contractor's organisation,
programmes and systems should also be conducted.
During pre-qualification of large contractors, especially those with many divisions in numerous countries,
the use of the record of the Corporation may not be appropriate. In such a case, the focus should be on
the division bidding for the work.
For those contractors not qualifying, a feedback mechanism should be in place to inform them why they
did not qualify and that by correcting the identified deficiencies; they may qualify for future work.
Where there is a policy to encourage selected contractors to develop an HSE management Plan, and these
contractors have little or no background in HSE management, then a plan to overcome the shortcomings
should be developed. Such a plan may require additional company supervision, more explicit procedures
or additional training. The HSE requirements should be met before work commences. The scale of the
contract and the exposure must be matched accordingly. Again, the details of the program and
performance of such contractors should be recorded and retained for future reference.
4.5
Before entering the selection phase the company should document the pre-qualified contractors and the
rationale for the selection. At this time, the company specifies the minimum evidence to be produced
during the selection phase by the potential contractors demonstrating that a sound Plan exists for
implementing HSE management during the potential contract work to control risks to as low as
reasonably practicable. This information should be prepared by the contractor as part of the HSE Plan.
Appendices V and VI provide requirements for an HSE Plan for major and small contracts, respectively.
Dependent on the level of risk involved in the contracted work, the company should establish yardsticks
to measure the quality of the contractors HSE Plan and criteria to be met. These measuring methods and
criteria should be documented prior to the selection process in the form of "Bid Evaluation Criteria".
10
5.
Selection
5. Selection
Pre-qualification is the most important screening tool for the selection of contractors. All contractors that
are pre-qualified should be fully capable of managing all HSE aspects of the job.
5.1 Objective
The objective of the selection phase is to assess whether the HSE Plan and the Bid Evaluation Criteria
have been met and to select, where necessary on the basis of clarification meetings, the successful bidder.
5.2
The selection criteria used should consider significant aspects such as costs, technical ability, reputation,
and the ability to meet schedules. The overall risk of contract and HSE management should be given
appropriate weighting along with other considerations when selection criteria are evaluated. This section
outlines some key considerations specific to the HSE portion of the selection process.
Contractors should be given copies of the companys HSE documentation relevant to the contract.
Documentation in the tender package may include:
company HSE goals and objectives.
company HSE-MS.
definition of the scope of the HSE Plan and the known hazards to be addressed.
list of HSE controls procedures and compliance issues for the contract.
definition of the company/contractor anticipated interfaces, the company supervision strategy and
interaction with company operations, interaction with specific company plans such as emergency
response.
type and schedule of company and contractor training requirements and competencies.
specification of the minimum pre-execution requirements.
The HSE tender documentation should be compiled, with due attention to the following:
It is the company's responsibility to assure that the tender documents address the HSE requirements
for the contract and that knowledge about hazards already identified by the company are passed on to
the contractor. The company should not assume that the contractor knows of the hazards in the
workplace, which are associated with the execution of contracted activities.
The contractor has independent responsibility for his own HSE Plan, but documents should make
clear provision for the company to perform HSE audits on the contractor in order to assess
compliance.
The documents should include provision for the company to suspend work if the contractor does not
observe the HSE criteria spelled out in the contract HSE Plan or HSE Case and, in particular at
mobilisation, to withhold permission to start execution and hold payments until a satisfactory preexecution audit has been achieved. Before any work is suspended, the company should liaise with the
contractor to allow them the opportunity to rectify any non-conformances.
Where special HSE provisions are to be provided, the documents should specify these clearly and
identify who is to pay for them. Any constraints on the methods of working should also be specified.
In preparing their bid, the contractor should demonstrate compliance with such requirements and
illustrate their process for preparing their own HSE Plan within the required framework. The actual plan
will be developed after the contract is awarded. This may be accomplished by developing a system which
facilitates the interfacing of company, contractor and sub-contractor activities, as described in Section 3.5
of OGP's Guidelines for the Development & Application of Health, Safety and Management Systems.
11
12
5.
Selection
The need for additional incentives should be carefully considered. To be effective a scheme should:
not discourage or suppress the reporting of incidents.
be proactive and reward effort, e.g., audits and follow-up rather than 'after the event' statistics.
ensure that incentives are valued by the personnel who are in a position to influence the performance
and maintain the systems.
be culturally sensitive to the local environment.
motivate personnel to change those behaviours that detract from HSE performance.
appreciate the HSE culture of the contractor
13
14
6.
Pre-mobilisation activities
6. Pre-mobilisation activities
6.1 Objectives
The objectives here are to ensure that the relevant aspects of the contract risk assessment and any other
HSE aspects of the contract are communicated and understood by all parties prior to implementation of
the contract. Several activities such as reviews, meetings and audits can be used. The amount of detail and
effort for pre-job activities should be commensurate with the level of risk.
15
16
7.
Mobilisation
7. Mobilisation
7.1 Objectives
The objectives of this phase are to assure that the HSE Plan is modified, if warranted, and communicated
to all relevant personnel, both company and contractor.
7.2 General
Prior to mobilisation, it is likely that the full HSE Plan is known only to the principal members of the
company's and contractor's project management teams. During mobilisation, the HSE Plan should be
communicated by the management of both the company and the contractor to all relevant personnel.
In the mobilisation phase some of the principal activities are:
local kick-off meeting(s)
mobilisation of contract staff and equipment
finalise the contractor's HSE Plan
commence induction and site-specific training
hold mobilisation HSE audit.
During mobilisation the company and contractor assure that each sets up a method of operation that is in
accordance with the agreed HSE Plan. It is at this stage that implementation of the HSE Plan by the
contractor formally begins. For contracts under "Mode 1" strategy, the contractor's operations should be
fully compatible with the company's HSE-MS. For contracts under a "Mode 2" strategy, any HSE Plan
requirements should be integrated into the contractor's HSE-MS.
The company and contractor should confirm that each has deployed his supervisory staff and is
implementing the agreed-upon briefing and training for his supervisors and employees.
Depending on the circumstances, additional supervisory staff from the contractor may be required to
allow rapid set-up and implementation of the HSE Plan. The company and contractor may want to have
additional staff available to verify that the HSE Plans are fully implemented. This can be accomplished by
a joint company/contractor HSE field review or audit.
During the initial part of the mobilisation phase all key personnel assigned to the project should attend an
HSE orientation program that should be used to communicate the HSE Plan and any other significant
HSE aspects of the contract.
Progress meetings should then be used as a formal method of reviewing HSE implementation, along with
frequent walk-throughs by company personnel.
Aligning the various interests and areas of responsibility requires good working relationships between the
company and contractors, among contractors and between contractors and sub-contractors. This is
particularly true if the subcontractor activities are difficult to monitor (e.g. distributed work groups,
transportation).
Once mobilisation activities have commenced, the company should begin monitoring of the contractor's
pre-execution activities to assure the HSE Plan is implemented.
17
and whether mobilisation can be considered complete. This can be accomplished by a joint
company/contractor HSE field review or audit.
Achievement of HSE Plan targets for this stage should represent the first milestone of the project.
Usually, the extent of the audit depends on the level of risk associated with the activity. For a relatively
low risk contract, an audit may be conducted by means of a simple checklist. For high-risk contracts, a
more analytical approach may be used.
If the audit proves to be unsatisfactory, then the status of the contractor's progress should be carefully
reviewed. The options available at this stage are:
Minor deficiencies: the contractor should be requested to implement corrective action and the audit
repeated. It may be possible to allow this to take place in parallel with initiating the execution phase.
Serious omissions: the option of withholding permission to proceed or even terminating the contract
may be necessary.
To minimise the possibility that the company could be perceived as assuming responsibility for HSE
supervision, the results of the mobilisation audit are documented and processed through the contractor's
HSE-MS.
The mobilisation audit usually is structured against the elements of the HSE-MS or, more specifically
against the HSE Plan elements (as outlined in Appendix V).
18
8.
Execution
8. Execution
8.1 Objectives
The objectives of this phase are to assure that the work to be performed is conducted according to the
agreed-upon HSE Plan, and that additional HSE needs, identified during the work, are properly
addressed.
8.2 Responsibilities
The nature of the work determines the level of supervision necessary. For example, within or in close
proximity to operating plant, hazardous area zones or acknowledged high risk operations, more direct
company supervision may be required than on a new construction site or the contractors own premises,
i.e. MODU, lay barge, etc. Only in particular circumstances should contractors be directly supervised
because too much instruction/direction from the client tends to relieve the contractor of the
responsibilities stipulated in the contract.
Where responsibility for supervision rests with the contractor, the companys role should be to monitor
compliance to contractual terms and systems defined within the contract. Unless the contract holder has a
permanent presence on site, it is usual to appoint representatives from line management to monitor and
verify that contract HSE obligations are being met. The contract holder and representative should have
access to specialist HSE advice where needed, but accountability for contract HSE lies with the contract
holder. Responsibility may be delegated to the representative, but accountability needs to remain with the
contract holder.
8.4
Competence assurance
During execution of the work, the company contract holder must monitor the continued competence of
the contractor. This refers to any associated training commitment undertaken. Where necessary, the
company should also determine if any additional competence assurance is needed as a result of local
circumstances. Monitoring should include a verification that the contractor complies with his
management system that may include:
19
20
9.
De-mobilisation
9. De-mobilisation
9.1 Objectives
The objectives of this phase are to identify the hazards associated with demobilisation and identify and
implement controls to minimise the risks. The HSE Plan should be modified, if need be, to address new
or unexpected hazards.
9.2 Responsibilities
The contractor's HSE Plan should continue to be the vehicle for managing the HSE activities in this
phase.
Demobilisation often is a phase of the project having an increased chance of incidents as the project
infrastructure and contractor HSE management structures are being dismantled with people moving off
the project to new assignments. Assurance should be sought that the appropriate organisational structures
remain intact until associated activities have been completed. These should include:
emergency response
site restoration
waste management and disposal.
Due consideration should be taken of any learning points from mobilisation, the problems encountered
and solutions found.
The company and contractor should continue to monitor performance against the Plan, including
attention to incident reporting. It is important to maintain vigilance on HSE matters to the very end of
the contract. The close out report should be made after all activities have been completed.
21
22
10.
10.
10.1 Objectives
The objectives of this phase are to conduct a joint evaluation of the contractors and companys HSE
performance and to provide feedback to the contractor(s) and company which can be a reference for
future work.
10.2
Contracts should be closed out with a report of HSE performance, providing feedback for future
knowledge and learning.
Ideally, HSE performance should be tracked on a regular basis throughout the contract with the final
report being the distillation of the regular monitoring process and the end of contract review. This may
take the form of a close-out meeting where all parties are represented. Thus, throughout the contract,
contractor performance should be monitored against Plan and any deviations, positive or negative,
annotated for reference in the close-out report/summary.
The format of the close-out report should reflect the agreed Plan and contractual obligations between the
company and the contractor(s). However, there should be sufficient flexibility to take account of mutually
agreed changes to the contract.
The analysis and summary of conclusions should address:
quality of the original HSE Plan and its relevance to the overall contractor(s) performance, stipulating
what was learned and how future contracts should be structured.
highlighting positive aspects of learning and how they can be applied in the future. This learning
should be shared with the contractor.
incorporation of any new hazards identified into the hazard identification and evaluation process for
future contracts.
analysis of both the client and contractors HSE performance for mutual improvement.
information on the contractor to be added as a reference for the client bid list and which may provide
advice for improvements in assessing future tenders.
The HSE close-out data should be recorded and made accessible for future reference. A documented
record of HSE Performance should be kept on each contractor.
The contractor will again be advised that his overall performance and HSE record will be taken into
account when being considered for future work.
23
24
25
Contractor
Contractor Manager should:
prepare and assure quality of contractor's HSE Plan
define competencies required for HSE critical positions
assign appropriate personnel to HSE critical positions
assure adequate resources and time in the schedule to manage the contract in accordance with the
contractor's HSE Plan
notify the Contract Holder in writing of his nominated contractor representative(s) and contractor Site
Representative(s)
provide resources to implement remedial actions following audits in an expeditious manner.
Contractor Representative should:
fulfil the pre-execution HSE requirements
implement the contractor's HSE Plan
seek formal approval from the Contract Holder for any proposed deviations from or amendments to
the contractor's HSE Plan
implement additional requirements as agreed upon with the Contract Holder.
Contractor Site Representative:
Where a contractor may be working in a number of areas it is common for the contractor to appoint a
person or persons to assume responsibility on behalf of the contractor representative to supervise the work
being executed under the contract in the specific area. The HSE responsibilities are as for the contractor
representative but with responsibility for a specific site.
26
Assets*, Equipment
Potential
Definition
Impact
Zero
No damage to
equipment.
Slight
injury/illness
Slight
damage
Minor
injury/illness
Minor
damage
Major
injury/illness
Local
damage
Plant partly
down; process
can (possibly) be
restarted.
(estimated cost
of repair below
$1,000,000).
Single
fatality/
permanent
total
disability or
unfitness for
work (small
exposed
population)
Major
damage
Partial loss of
plant; plant shut
down (for at
most two weeks
and/or estimated
repair costs
below
$10,000,000)
Multiple
fatalities
Extensive
damage
Severity
Rating
0
No disruption to
the process,
minimum cost of
repair (below
$10,000).
Possible brief
disruption of the
process; isolation
of equipment for
repair (estimated
cost below
$100,000)
*Assets are understood as referring to: the oil and gas reservoirs, production facilities, pipelines, money,
capital, and other company, contractor and third party property.
27
Severity
Environment
Potential
Definition
Impact
Contamination
(litres)
Sensitive
areas
Offshore
Several
Zero
effect
No financial
consequences; no
environmental risk
Slight
effect
Negligible financial
consequences; local
environmental risk;
within the fence and
within systems
<10
Minor
effect
Contamination;
damage sufficiently
large to attack the
environment; single
excedence of statutory
or prescribed criteria;
single complaint; no
permanent effect on
the environment
Local
effect
Reputation
Potential
Definition
Impact
Zero
impact
No public awareness
0-100
Slight
impact
Public awareness of
the incident may
exist; there is no
public concern
<100
100-1,000
Limited
impact
Limited loss of
discharges of known
toxicity; repeated
excedence of statutory
or prescribed limit and
beyond
fence/neighbourhood
1001,000
1,00010,000
Considerable
impact
Regional public
concern. Extensive
negative attention in
local media; slight
national media
and/or local/regional
political attention
with possibly
negative stance of
local government
and/or action groups
Major
effect
Severe environmental
damage; the company
is required to take
extensive measures to
restore the
contaminated
environment to its
original state. Extended
excedence of statutory
or prescribed limit
1,00010,000
10,000100,000
Major
national
impact
National public
concern. Extensive
negative attention in
national media
and/or regional
national policies
with potentially
restrictive measures
and/or impact on
grant of licences,
mobilisation of
action groups.
Massive
effect
Persistent severe
environmental damage
or severe nuisance
extending over a large
area. In terms of
commercial or
recreational use or
nature conservancy, a
major economic loss for
the company. Constant
high excedence of
statutory or prescribed
limit.
>10,000
>100,000
Major
international
impact
International public
attention. Extensive
negative attention in
international media
and
national/internation
al policies with
potentially severe
impact on access to
new areas, grants of
licences and/or tax
legislation
*Incidents relating to air, noise, smell, light and soil vibrations should be addressed on the
basis of expert judgement and, in the case of uncertainty, local expertise may be called in.
28
Table III
Questionnaire items
Section 1: Leadership and Commitment
(i) Commitment to
HSE through
leadership
Responses
29
Table III
Questionnaire items
Responses
Section 3: Organisation, Responsibilities, Resources, Standards and Documentation
(i) Organisation commitment and
communication
30
Table III
Questionnaire items
Responses
Section 3: Organisation, Responsibilities, Resources, Standards and Documentation (cont.)
(vi) Assessment of
suitability of
subcontractors/
other companies
(vii) Standards
(iii) Handling of
chemicals
(iv) Personal
protective
equipment
(v) Waste
management
31
Table III
Questionnaire items
Section 5: Planning and Procedures
(i) HSE or
operations
manuals
(ii) HSE
performance
achievement
awards
(iii) Statutory
notifiable
incidents
/dangerous
occurrences
(iv) Improvement
requirement and
prohibition
notices
32
Responses
Table III
Questionnaire items
Section 6: Implementation and Performance Monitoring (cont.)
(v) HSE
a) Have you maintained records of your incidents
performance
and HSE performance for the last five years?
records
(If YES, please provide the following: Number of
Fatalities, Lost Time Injuries, Lost Workday
Cases, Medical Treatment Cases and Restricted
Work Day Cases. Also include the Fatal Accident
Rate, Lost Time Injury Frequency and Total
Recordable Incident Rate for each year. (NOTE:
Please include your company definitions of a the
above mentioned terms - for clarification refer to
the E&P Forum Safety Performance Accident
Data Report.)
Responses
(ii) Additional
features of your
HSE
management
33
34
10
14
20
Elements scoring 0 should normally disqualify a contractor from being included in a pre-qualification list.
Any elements rated so must be highlighted as a qualification on the tender if it is still to be considered.
Table IV
A
B
Section 1: Leadership and Commitment
Evidence of a positive
HSE culture in senior
management and at all
levels
35
Table IV
A
B
C
Section 3: Organisation, Responsibilities, Resources, Standards and Documentation
In addition to C,
employees are assigned
topics to discuss on a
rotational basis
Employee handbook
provided and supervisor
outlines, explains and
demonstrates new
employee's job
No HSE training
established
HSE arrangements
incorporated in HSE
manual but not in a
format which is
distributed to all
employees
No formal programme
Written arrangements in
place for basic HSE
matters only
36
Table IV
A
B
Section 4: Hazards and Effects Management
Company makes no
special provision for
advising the workforce
about properties of
potential hazards
Company provides
information to workforce
in the workplace on
properties of potential
hazards but has no active
follow-up
Company distributes
information to individuals
in the workforce at start
of their involvement onsite
Company maintains a
database of the
properties of all potential
hazards encountered in
its contracts and has
formal methods of
information distribution
to all personnel and
trains its workforce in
handling, etc.
PPE requirements
formally assessed with
spot checks on usage
Procedures in place to
assess all PPE
requirements, monitor
and enforce usage and
replacement needs. Stock
inventories monitored,
kept above demand
levels. Training in use
provided where needed
PPE requirements
formally assessed but
little effort made to
ensure correct usage
37
Table IV
A
B
Section 5: Planning and Procedures
HSE or operations manuals : Item 5(I) (a) and (b)
No HSE procedures
available
Contractor has
procedures to cover all
HSE precautions, typical
contractor HSE Plan
requirements with a
system of updating and
dissemination to
employees
In addition to C, periodic
inspections conducted by
top management or by
teams of specialists
Company has a
comprehensive system for
monitoring performance
in all areas with feedback
to employers for
improvement and has
received awards for
achievement
Statutory notifiable incidents, dangerous occurrences, improvement requirements and prohibition notices:
Items 6(iii) and 6(iv)
More than one
One occurrence of a
Occurrences relate to
No occurrences in the
occurrence of major
major incident in the last minor incident(s) only
last five years
incident in last five years
five years
HSE Performance records (Latest year injury rate comparison to contractors three preceding years
average) : Item 6(v) (a) - (d)
Rate is not improving
Shows only minor rate
Rate steadily improving
Contractor supplied
improvement
by more than 20 per cent
insufficient information to
per year
establish rate or rate
increases
Criteria for absolute performance
Rate over 200 per cent
Rate under 200 per cent
Rate under 120 per cent
Rate better than that of
that of company
that of company
that of company
company
Incident Investigation and reporting : Item 6(vi) (a) - (c)
Findings communicated
As in C but with the
Findings not generally
Findings communicated
to all employees via
addition of details of
communicated
to key personnel only via
specific company notice
implication for improving
limited company internal
HSE performance
memo or similar media
38
Performance monitoring
in a few areas carried out
Table IV
A
Section 7: Auditing and Review
Auditing: Item 7(i) (a) - (c)
Company HSE
documents include
reference to auditing but
there are no specific
details about scheduling
and coverage
Section 8: HSE Management - Additional Features
Audit process is cursory
only - HSE documents
are not explicit about
auditing
Company HSE
documents include
details of how auditing is
to be implemented with
schedules/coverage for
the key areas
As in C but additionally
specifies management's
role in audit and followup on action items
Company is a member of
at least one HSE
association
Company is an active
participant in at least one
HSE association
Company has
membership of at least
one association but with
no prominence given to
HSE
39
40
41
HSE legislation
HSE standards
Section 4 Evaluation and risk management
Methods and procedures for hazards and effects management
Assessment of exposure of the workforce to hazards and effects
Material data sheets for safe handling of chemicals
Hazards and effects management and the assessment of PPE requirements
Methods and procedures for waste management
Section 5 Planning and procedures
HSE procedures
Basic HSE rules
Emergency response procedures
HSE equipment and equipment HSE inspection
Occupational health
Environmental
Road transport
Section 6 Implementation and performance monitoring
HSE performance - general
Incident investigation
Section 7 Auditing and review
HSE auditing
42
Checked
Table V.2 Checklist for HSE Plan: Section 2 Policy and Strategic Objectives
Checklist items
HSE policy statement
General
Written HSE policy
Dated and signed by Chief Executive
Policy statements:
specific to individual parts of the contract (e.g.
locations/sites/plants)
cover specialised aspects (e.g. alcohol and drugs)
consistent with company guidelines
clear, concise and motivating
Content
Importance of HSE as a contract objective
Checked
Discussion
43
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation
Checklist items
HSE organisation
Key personnel
Contract
objectives/
accountability
Manning/
communications
Manpower philosophy
Manpower level to be defined correctly so as not to compromise
HSE
Effective means to communicate HSE issues to the company,
contractor and subcontractors
Organisation staffed by competent personnel with sufficient
appreciation of HSE where necessary with specific training in the
issues involved
Corporate
structure/
responsibility
44
Checked
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
HSE professionals
Job definition
Checked
Reporting/
follow-up
HSE department
Subcontractors
Management
Identification/
vetting
45
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
HSE communications
Coverage/
Set up appropriate lines of communication to handle HSE issues,
awareness
e.g. such items as:
direct access to emergency services
nearest hospital
helicopter availability
air ambulance, etc.
Authorisation and implementation procedures fully
understood
Emergency services: those organisations that would be expected
to provide support in a major incident aware of requirements briefed as to their likely role
External links
Lines established to communicate externally incidents that may
endanger those on a site
Individual responsibilities and procedures for the company and
contractor(s) to make government agency reports have been
agreed upon and clearly defined
Contractor able to communicate with all his workforce in an
emergency
Communications take into account the diversity of languages
amongst the workforce
Ability of base to mobilise in an emergency, e.g. doctors, hospital
facilities
Emergency
communications
Meeting structure
46
Checked
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
HSE meeting programme (cont.)
Follow-up actions
Meeting actions
Checked
Performance
Promotional
methods
Possibilities include:
small 'give-aways' with the HSE message
competitions
suggestion schemes
Part of business
HSE activities seen as an intrinsic part of running an efficient
business rather than a costly and time-consuming 'extra'
HSE competence requirements
Fitness of
Confirmation of medical fitness from a recognised and approved
personnel
medical facility of all proposed employees for contract
Employee orientation programme
Approach
Provision of a comprehensive handbook for all new employees
On-the-job orientation for supervisory staff
Established procedure in relation to follow-up of all new
employees at the worksite
New employees
Accountability
47
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
Employee orientation programme (cont.)
Procedures
Required for new employee orientation consistent with existing
company guidelines
Reappraisal
Supervisory
training
Including:
HSE management
job procedures
road safety
health (first-aid health hazards, medical services, alcohol and
drugs, health promotion, use of PPE)
auditing
incident investigation and reporting
HSE adviser skills
supervisory development
HSE meetings
environmental protection
Supervisory development training promotes man-management
skills and communication skills
Formalised
programme
Coverage
Supervisors'
participation
Course content
48
Checked
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
HSE training (general) (cont.)
Specialised
Relevant training given to personnel prior to the execution of
training
hazardous operations
Checked
HSE content in
other courses
Qualifications
HSE legislation
Coverage
Waivers
49
Table V.3 Checklist for HSE Plan: Section 3 Organisation, Responsibilities, Resources, Standards
and Documentation (cont.)
Checklist items
HSE standards.
Availability
Control/
authorisation
Coverage
50
Checked
Table V.4 Checklist for HSE Plan: Section 4 Evaluation and Risk Management
Checklist items
Methods and procedures for hazards and effects management
Coverage
Company assessment used as a starting point with additional
hazards identified by the contractor
Checked
Renewal/
replacement
51
Table V.5 Checklist for HSE Plan: Section 5 Planning and procedures
Checklist items
HSE procedures
Availability/control
Deviations
Written procedures:
familiar to all employees including subcontractors
available in their working language..
contents related to individual job descriptions..
Procedure for obtaining
Responsibility and level
Recording of authorised deviations
Omissions
Permit to work
(PTW)..
System in place
Training/
qualification
Production/
updating
52
Checked
Table V.5 Checklist for HSE Plan: Section 5 Planning and procedures (cont.)
Checklist items
Emergency response procedures
Coverage
Identification of potential major emergency scenarios, and
procedures to use in such scenarios, e.g.
fire
abandon rig/location
storm
oil/chemical.. Spill
aircraft incident
emergency communications
Medevac
blow-out
diving emergency
search and rescue (SAR)
explosions
H2S
well control
man overboard
evacuation
terrorism
Potential use of company guidelines
Awareness
By employees of procedures
Orientation
Schedule of drills and testing
Medical contingency.. Plan included
Review frequency
Responsibility of employees for own and colleagues' HSE
Monitoring mechanism
Drills to be carried out without warning
Plans
Contingency plans allowed for in emergency situations
Checked
53
Table V.5 Checklist for HSE Plan: Section 5 Planning and procedures (cont.)
Checklist items
HSE equipment and equipment HSE inspection (cont.)
Schedule
HSE equipment inspection schedule established for the duration
of the project
Inspection frequency clearly identified for critical items of plant
Occupational Health
Facilities available
Facilities defined as part of contract
Occupational health programme established to:
identify hazards
assess hazards
control hazards, e.g. engineering controls, procedural
controls, PPE, vaccinations, etc.
maintain emergency procedures
Appropriate for the site conditions
Welfare programme meets the needs of isolated sites
Local medical facilities evaluated in detail to assess:
range and quality of equipment and supplies
hygiene standards
administration procedures and standards
transportation and communication
Sufficient for day-to-day needs and consistent with relevant health
programmes
Adequate provision for supply of drugs, antidotes, etc.
Staffing
Contingency.. plans
Accommodation
and catering
facilities
Promotion
Hygiene and
housekeeping
54
Checked
Table V.5 Checklist for HSE Plan: Section 5 Planning and procedures (cont.)
Checklist items
Environmental
Awareness
Control
Checked
Aims
Monitoring/
restoration
Audits
Road Transport.
Drivers :
competence and
selection
Driving Permits
Driver induction
Driver training
Driver
improvement
55
Table V.5 Checklist for HSE Plan: Section 5 Planning and procedures (cont.)
Checklist items
Road Transport (cont.)
Vehicle:
selection
Vehicle
specification
Passengers
Freight
Vehicle
maintenance
Ops management:
need and approval
journey routing
and scheduling
Journey
management
Roles and
responsibilities
Logging of actions
Contracting
Realistic schedules
Emergency
services
56
Checked
Table V.6 Checklist for HSE Plan: Section 6 Implementation and Performance Monitoring
Checklist items
HSE performance General
Measurement
Proposed plan to measure performance, i.e.
performance indicators
progress against targets..
HSE initiatives/incentive schemes..
achievement of milestones..
numbers and types of training courses
numbers and results of audits
clearance of action items
Use will be made of reactive statistical indicators, e.g.
Lost Time Injury Frequency/Total Recordable Incident Rate
numbers of first-aid and minor injuries..
material losses
vehicle incidents
spillages
occupational illnesses
sickness absenteeism
Feedback/analysis
Availability and use of performance records
Checked
Comparison of performance:
With other similar contract work
Frequency specified
Involvement of company personnel
Incident Investigation
Coverage
Reporting procedure for the contract
Methods
Covering not only injuries to and time lost by personnel but also:
health incidents (diseases, exposures to hazardous
substances, near misses, etc.)
environmental incidents (spillages, releases, contamination,
etc.)
other safety incidents (safety equipment failures, loss of
capital equipment)
material loss
Incident investigation method established to determine and
correct causes
Incidents first reported to the direct supervisor
Incident investigation teams led by the relevant managers
Differentiation made between numbers of first-aid treatments and
other minor injuries
Procedure in place on vehicle incidents
Methods to be used for collecting incident statistics
57
Table V.7 Checklist for HSE Plan: Section 7 Auditing and Review
Checklist items
HSE auditing
Availability
Scope
Coverage
Effectiveness
How verified
Involvement of the contractor's corporate management in review
of findings
Intention to publish findings
Discussion with personnel on contract and at HSE meetings..
Lessons used to improve operations across the contract
Follow-up
58
Checked
Checklist items
Senior management should reinforce the importance of HSE at
all levels in the organisation and should be seen to be setting a
personal example.
Policy and
Strategic
Objectives
Organisation,
Responsibilities,
Resources,
Standards and
Documentation
Checked
59
Hazards and
Effects
Management
Planning and
Procedures
Checklist items
A statement of how HSE competence is assessed for personnel
with HSE-critical activities to perform.
Statement of requirements for employees to indicate that they
have the necessary appreciation of the HSE issues in the
contractor's business activities. This should include reference to
potential client HSE induction sessions and HSE training. Such
training could include items from the following list (as relevant to
the contract):
fire and explosion hazards
road transport/driving
first-aid
work procedures/PTW
hazard awareness and reporting
security
basic HSE rules
legislative requirements
occupational health
environmental protection
Implementation
and Performance
Monitoring
Auditing and
Review
60
Checked
Item
Details
Company
Project
Contract Title/Number
Contractor details
Site location
Company Contract Holder/Representative(s)
Company Representative(s)
Contract Manager/contractor Representative(s)
Hazard assessment
Contract scope description
Expected hazards identified (including adjacent operations, etc.)
Alternatives considered
Procedures to be followed for hazard control (list documents or
describe details here)
Access/escape provisions (alarms, muster stations, etc.)
Emergency service provisions (including first-aid, nearest medical
treatment, emergency phone numbers, etc.)
Competence standards for contractor's personnel
Standards for contractor's equipment
Training requirements (including site HSE induction )
Job/services description
Contractor's personnel assigned
Contractor's equipment/ consumables/services assigned
Company's personnel assigned
Company's equipment/consumables/services assigned
Subcontractor details
Responsibilities/interfaces defined
PPE and any special HSE equipment to be used
Working hours/job duration
Site description/limits
PTW provisions applicable
Conditions for suspending work (e.g. weather, adjacent site
operations, etc.)
61
62
What is OGP?
The International Association of Oil & Gas Producers represents the worlds oil and gas
industry. Our members include private and state-owned oil and gas companies, national
associations and petroleum institutes.
What do we do?
Our purpose is to:
provide information about the oil and gas exploration and production industry;
represent our members interests at global and regional regulatory bodies; and
develop operating guidelines.