Documente Academic
Documente Profesional
Documente Cultură
LUZON
SUPPLY-DEMAND OUTLOOK
2012-2030
Critical Periods
21000
19000
17000
15000
13000
11000
9000
Existing Capacity
Existing + Committed
Notes
a. Demand curve as plotted includes total of peak demand and required Reserve Margin (RM)
i.e. 4% regulating reserve and contingency and dispatchable reserve requirement
b. 4.12% peak demand growth rate resulted from aggregated demand submitted by the utilities
to DOE
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
3
Critical Periods
At 4.12% Peak Demand Growth
Rate
2013 on existing capacity
2014 on existing capacity with
committed capacities
At 5.28% Peak Demand Growth Rate
2013 both on existing capacity
and with committed capacities
Notes
a. Demand curve as plotted includes total of peak demand and required Reserve Margin (RM)
i.e. 4% regulating reserve and contingency and dispatchable reserve requirement
b. 4.12% peak demand growth rate resulted from aggregated demand submitted by the utilities
to DOE
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
Critical Periods
21000
19000
17000
15000
13000
11000
9000
Existing Capacity
Existing + Committed
With Indicative
Notes
a. Demand curve as plotted includes total of peak demand and required Reserve Margin (RM)
i.e. 4% regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.12% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
Critical Periods
At 4.12% Peak Demand Growth Rate
2013 on existing capacity
2014 on existing capacity with
committed capacities
2019 if with indicative capacities
At 5.28% Peak Demand Growth Rate
2013 both for existing capacity
and with committed
capacities
2017 if with indicative capacities
Notes
a. Demand curve as plotted includes total of peak demand and required Reserve Margin (RM)
i.e. 4% regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.12% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
2013
2014
2015
2016
2017
2018
2019
2020
2021
10,744
11,587
12,180
9,900
3.84%
3.32%
10,019
5.28%
4.57%
10,744
11,612
13,274
10,212
3.62%
3.15%
10,480
5.28%
4.60%
10,744
11,763
13,425
10,542
3.70%
3.23%
10,965
5.28%
4.63%
10,744
11,763
13,425
10,880
3.66%
3.21%
11,475
5.28%
4.66%
10,744
11,763
13,425
11,244
3.79%
3.34%
12,013
5.28%
4.68%
10,744
11,763
13,425
11,620
3.79%
3.35%
12,579
5.28%
4.71%
10,744
11,763
13,425
12,010
3.78%
3.36%
13,175
5.28%
4.74%
10,744
11,763
13,425
12,415
3.77%
3.36%
13,802
5.28%
4.76%
10,744
11,763
13,425
12,906
4.42%
3.96%
14,463
5.28%
4.78%
2022
2023
2024
2025
2026
2027
2028
2029
2030
10,744
11,763
13,425
13,419
4.42%
3.98%
15,158
5.28%
4.81%
10,744
11,763
13,425
13,955
4.42%
3.99%
15,890
5.28%
4.83%
10,744
11,763
13,425
14,514
4.42%
4.01%
16,661
5.28%
4.85%
10,744
11,763
13,425
15,099
4.42%
4.02%
17,472
5.28%
4.87%
10,744
11,763
13,425
15,709
4.42%
4.04%
18,326
5.28%
4.89%
10,744
11,763
13,425
16,346
4.42%
4.05%
19,225
5.28%
4.91%
10,744
11,763
13,425
17,011
4.42%
4.07%
20,172
5.28%
4.92%
10,744
11,763
13,425
17,705
4.42%
4.08%
21,169
5.28%
4.94%
10,744
11,763
13,425
18,430
4.42%
4.10%
22,218
5.28%
4.96%
Existing Capacity
10,744
Existing + Committed
10,749
With Indicative
Peak Demand @ 4.12 GR + RM 9,582
GR Peak Demand
GR Peak Demand + RM
Peak Demand @ 5.28 GR+ RM 9,582
GR Peak Demand
GR Peak Demand + RM
-
Existing Capacity
Existing + Committed
With Indicative
Peak Demand @ 4.12 GR + RM
GR Peak Demand
GR Peak Demand + RM
Peak Demand @ 5.28 GR+ RM
GR Peak Demand
GR Peak Demand + RM
Average
GR
4.12%
3.70%
5.28%
4.78%
7
Installed Capacity
(MW)
2012
Difference
(MW)
2011
Dependable Capacity
Difference
(MW)
(MW)
2012
2011
Coal
3,879
3,849
30
3,664
3,531
133
Oil Based
1,757
1,984
-227
1,633
1,586
48
Natural Gas
2,861
2,861
2,770
2,756
14
Geothermal
751
899
-148
587
500
87
Hydro
2,440
2,346
94
2,124
2,101
23
Wind
33
33
33
20
13
Biomass
17
13
11,981
-242
10,824
10,498
326
TOTAL
11,739
Location
GN Power (2x300
Mariveles Project)
Green Future Biomass
Mariveles, Bataan
Bacnotan, La Union
Pililia Wind
Pililia Rizal,
Payatas LFG
Quezon City
Isabela
Proponent
Fuel
Type
Coal
Capacity
M/Q/Year
(MW)
600.0
Jan. 2013
13.0
Jan. 2013
21.0
4Q 2013
Wind
68.0
Dec. 2013
Biomass
1.0
Dec. 2013
703.0
Location
Proponent
Maibarara Geothermal
Inc.
Fuel
Type
Geo
Capacity
M/Q/Year
(MW)
20.0
Oct. 2014
20.0
10
Location
Calaca, Batangas
Proponent
Fuel
Type
Coal
Biomass
Capacity
M/Q/Year
(MW)
135.0 Sept. 2015
11.0
Dec. 2015
146.0
11
Location
Proponent
Aero Derivative
Combined Cycle Power
Plant
Calamba, Laguna
Nagsurot-Saoit, Burgos,
Ilocos Norte
Unisan, Quezon
Province
Isabela
Fuel
Type
Oil
Wind
48.0
June 2013
LNG
300.0
Dec. 2013
86.0
Dec. 2013
5.6
Dec. 2013
3.6
Dec. 2013
Capacity
M/Q/Year
(MW)
150.0 June 2013
593.2
12
Location
Proponent
Fuel
Type
Coal
Capacity
M/Q/Year
(MW)
300.0
2014
72.0
Feb. 2014
80.0
1Q 2014
300.0
3Q 2014
300.0
4Q 2014
17.5
Dec. 2014
1,069.5
13
Location
Mabitac, Rizal
Proponent
Fuel
Type
Wind
Alternergy Sembrano
Wind Corporation
Sitio Naglatore, Cawag, Redondo Peninsula
Coal
Subic
Energy, Inc.
San Gabriel, Batangas
First Gas Power
Natural
City
Corporation
Gas
Bacman Geothermal
Energy Development
Geo
Field, Sorsogon
Corporation
Bacman Geothermal
Energy Development
Geo
Field, Sorsogon
Corporation
Mariveles, Bataan
GN Power Mariveles Coal
Coal
Plant Ltd., Co.
Brgy. Puting Bato, West South Luzon Thermal
Coal
Calaca, Batangas
Energy Corporation
(formerly TAOil)
Unisan Biogas Project Unisan, Quezon Province Unisan Biogen Corporation Biogas
Phase II
Capacity
M/Q/Year
(MW)
56.0
2015
300.0
2Q/2015
550.0
3Q 2015
40.0
Sept. 2015
40.0
Sept. 2015
600.0
4Q 2015
135.0
4Q 2015
5.6
Dec. 2015
1,726.6
14
Location
Proponent
Fuel
Type
Capacity
M/Q/Year
(MW)
Cavinti, Laguna
Wind
50.0
2016
Camarines Sur
Coal
40.0
1Q 2016
Coal
500.0
2Q 2016
Coal
300.0
3Q 2016
Coal
300.0
3Q 2016
1,190.0
15
Location
Proponent
Manito-Kayabon
Geothermal Project
Bacman Geothermal
Field, Sorsogon
Energy Development
Corporation
Fuel
Type
Coal
Geo
Capacity
M/Q/Year
(MW)
300.0
2017
40.0
Mar. 2017
340.0
16
Location
Atimonan, Quezon
Proponent
MERALCO
Fuel
Type
LNG
Capacity
M/Q/Year
(MW)
1,750.0
2018
1,750.0
17
Location
Gen. Nakar, Quezon
Province
Proponent
Kanan Hydro Electric
Power Corp.
Fuel Capacity
M/Q/Year
Type
(MW)
Hydro 150.0 Dec. 2020
150.0
18
VISAYAS
SUPPLY-DEMAND OUTLOOK
2012-2030
19
Critical Periods
4000
3500
3000
2500
2000
1500
Existing Capacity
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.45% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE.
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
20
Critical Periods
At 4.45% and 5.28% Peak Demand
Growth Rate
2013 in all cases (on existing
capacity, on existing
capacity with committed
capacities, and on existing
with committed and
indicative capacities
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.45% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE.
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
21
4500
4000
3500
3000
2500
2000
1500
Existing Capacity
With Indicative
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.45% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE.
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
22
Critical Periods
At 4.45% and 5.28% Peak Demand
Growth Rate
2013 in all cases (on existing
capacity, on existing capacity with
committed capacities, and on
existing with committed and
indicative capacities)
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.45% peak demand growth rate resulted from aggregated demand submitted by the
utilities to DOE.
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
23
Existing Capacity
Existing + Committed
With Indicative
Peak Demand @ 4.45 GR + RM
GR Peak Demand
GR Peak Demand + RM
Peak Demand @ 5.28 GR+ RM
GR Peak Demand
GR Peak Demand + RM
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2,037
2,037
2,037
1,831
1,831
-
2,037
2,045
2,095
1,909
4.78%
4.26%
1,917
5.28%
4.70%
2,037
2,065
2,217
1,992
4.90%
4.39%
2,007
5.28%
4.73%
2,037
2,208
2,360
2,070
4.36%
3.93%
2,103
5.28%
4.75%
2,037
2,212
2,364
2,160
4.78%
4.31%
2,203
5.28%
4.78%
2,037
2,347
2,499
2,255
4.87%
4.41%
2,309
5.28%
4.80%
2,037
2,347
2,499
2,342
4.24%
3.86%
2,420
5.28%
4.82%
2,037
2,347
2,499
2,433
4.23%
3.87%
2,538
5.28%
4.84%
2,037
2,347
2,499
2,526
4.18%
3.83%
2,661
5.28%
4.86%
2,037
2,347
2,499
2,624
4.22%
3.88%
2,791
5.28%
4.88%
2022
2023
2024
2025
2026
2027
2028
2029
2030
2,037
2,347
2,499
2,727
4.25%
3.93%
2,928
5.28%
4.90%
2,037
2,347
2,499
2,836
4.29%
3.98%
3,072
5.28%
4.92%
2,037
2,347
2,499
2,950
4.33%
4.02%
3,223
5.28%
4.94%
2,037
2,347
2,499
3,070
4.36%
4.06%
3,383
5.28%
4.95%
2,037
2,347
2,499
3,196
4.39%
4.11%
3,551
5.28%
4.97%
2,037
2,347
2,499
3,328
4.43%
4.15%
3,728
5.28%
4.98%
2,037
2,347
2,499
3,468
4.46%
4.19%
3,914
5.28%
5.00%
2,037
2,347
2,499
3,614
4.49%
4.23%
4,110
5.28%
5.01%
2,037
2,347
2,499
3,769
4.52%
4.27%
4,317
5.28%
5.02%
Average
GR
4.45%
4.09%
5.28%
4.88%
24
Installed Capacity
(MW)
2012
2011
Difference
(MW)
Dependable Capacity
(MW)
2012
2011
Difference
(MW)
Coal
806
786
20
777
501
275
Oil Based
615
615
476
464
12
Geothermal
923
964
-40
745
751
-6
Hydro
13
13
13
13
Biomass
44
29
15
26
15
11
2,402
2,407
-5
1,745
292
TOTAL
2,037
25
Location
Sibalom, Antique
Proponent
Sunwest Water & Electric
Co., Inc.
Fuel
Type
Hydro
Capacity
M/Q/Year
(MW)
8.0
Dec. 2013
8.0
26
Location
Nasuji, Valencia,
Negros Oriental
Proponent
Energy Development
Corporation
Fuel
Type
Geo
Capacity
M/Q/Year
(MW)
20.0
Dec. 2014
20.0
27
Location
Proponent
Concepcion, Iloilo
Palm Thermal
Consolidated Holdings
Corp.
Cantakoy HEP
Danao, Bohol
Cantakoy Hydroelectric
Power Project
Fuel
Type
Coal
Hydro
Capacity
M/Q/Year
(MW)
135.0
3Q 2015
8.0
4Q 2015
143.0
28
Location
Cebu
Proponent
Fuel
Type
Biomass
Capacity
M/Q/Year
(MW)
4.0
Dec. 2016
4.0
29
Location
Concepcion, Iloilo
Proponent
Palm Thermal
Consolidated Holdings
Corp.
Fuel
Type
Coal
Capacity
M/Q/Year
(MW)
135.0
Sept. 2017
135.0
30
Location
Bgy. Pawa, Nabas, Aklan
Proponent
Trans-Asia Oil and
Energy Development
Corporation
Fuel
Type
Wind
Capacity
M/Q/Year
(MW)
50.0
2013
50.0
31
Location
Proponent
54 MW San Lorenzo
Wind Power Project
Bgy. Cabalabaguan,
Mina, Iloilo
Fuel
Type
Wind
Capacity
M/Q/Year
(MW)
54.0
Jan. 2014
Biomass
18.0
June 2014
Biomass
17.5
Dec. 2014
Biomass
12.0
Dec. 2014
101.5
32
Location
Proponent
Fuel
Type
Capacity
M/Q/Year
(MW)
Panay Energy
Development
Corporation
Coal
82.0
2015
Brgy. Daanlungsod,
Toledo City, Cebu
Cebu Energy
Development
Corporation (CEDC)
Coal
82.0
2015
Coal
20.0
4Q 2015
Biomass
17.5
Dec. 2015
201.5
33
Location
Proponent
Fuel
Type
Geo
Capacity
M/Q/Year
(MW)
40.0
2017
40.0
34
Location
Southern Leyte
Proponent
Energy Development
Corporation
Fuel
Type
Geo
Capacity
M/Q/Year
(MW)
40.0
2019
40.0
35
LUZON-VISAYAS
SUPPLY-DEMAND OUTLOOK
2012-2030
36
25000
23000
21000
19000
17000
15000
13000
11000
9000
Existing
With Indicative
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.17% peak demand growth rate resulted from aggregated demand of Luzon and Visayas
submitted to DOE by the utilities
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
37
Critical Periods
At 4.17% Peak Demand Growth Rate
2013 on both existing capacity
and committed apacities
2018 if with indicative capacities
At 5.28% Peak Demand Growth Rate
2013 on both existing capacity
and committed capacities
2017 if with indicative capacities
Actual transfer may be constrained
by Luzon-Visayas import-export lines
Notes
a. Demand curve represents total of peak demand and required Reserve Margin (RM) i.e. 4%
regulating reserve and contingency and dispatchable reserve requirement (RM).
b. 4.17% peak demand growth rate resulted from aggregated demand of Luzon and Visayas
submitted to DOE by the utilities
c. 5.28% peak demand growth rate resulted from observed 0.8 elasticity ratio of demand for
electric power with national economic growth applied to 6.6 percent GDP growth rate (GR)
for 2012.
38
Existing Capacity
Existing + Committed
With Indicative
Peak Demand @ 4.17 GR + RM
GR Peak Demand
GR Peak Demand + RM
Peak Demand @ 5.28 GR+ RM
GR Peak Demand
GR Peak Demand + RM
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
12,781
12,786
12,786
11,412
11,412
-
12,781
13,632
14,275
11,808
3.99%
3.47%
11,936
5.28%
4.59%
12,781
13,677
15,491
12,204
3.83%
3.35%
12,487
5.28%
4.62%
12,781
13,971
15,785
12,612
3.81%
3.35%
13,068
5.28%
4.65%
12,781
13,975
15,789
13,040
3.85%
3.39%
13,679
5.28%
4.68%
12,781
14,110
15,924
13,499
3.98%
3.52%
14,322
5.28%
4.70%
12,781
14,110
15,924
13,963
3.86%
3.44%
14,999
5.28%
4.73%
12,781
14,110
15,924
14,443
3.85%
3.44%
15,712
5.28%
4.75%
12,781
14,110
15,924
14,941
3.84%
3.44%
16,463
5.28%
4.78%
12,781
14,110
15,924
15,530
4.38%
3.95%
17,254
5.28%
4.80%
2022
2023
2024
2025
2026
2027
2028
2029
2030
12,781
14,110
15,924
16,146
4.39%
3.97%
18,086
5.28%
4.82%
12,781
14,110
15,924
16,791
4.40%
3.99%
18,962
5.28%
4.84%
12,781
14,110
15,924
17,464
4.40%
4.01%
19,884
5.28%
4.86%
12,781
14,110
15,924
18,168
4.41%
4.03%
20,855
5.28%
4.88%
12,781
14,110
15,924
18,904
4.41%
4.05%
21,877
5.28%
4.90%
12,781
14,110
15,924
19,674
4.42%
4.07%
22,953
5.28%
4.92%
12,781
14,110
15,924
20,478
4.43%
4.09%
24,087
5.28%
4.94%
12,781
14,110
15,924
21,320
4.43%
4.11%
25,279
5.28%
4.95%
12,781
14,110
15,924
22,199
4.44%
4.12%
26,535
5.28%
4.97%
Average
GR
4.17%
3.77%
5.28%
4.80%
39
40
Diesel
Natural gas/Combined Cycle
Geothermal
Hydro
Import from Visayas
Demand Forecast
System Gross Reserve
Req'd. Regulating Reserve
Req'd. Contingency Reserve
Req'd. Dispatchable Reserve
Jan
Feb
Mar
Apr
May
8512 8094 8652 8291 9168
0
0
0
150
260
3022 2961 3815 3012 3967
338
338
348
357
353
3007 2778 2757 2729 3158
396
373
375
412
499
1650 1450 1300 1528
781
99
194
57
103
150
7079 7335 7720 8007 8201
1433
759
932
284
967
283
293
309
320
328
647
647
647
647
647
647
647
647
647
647
Jun
9276
0
4267
353
3158
499
849
150
8163
1113
327
647
647
Jul
Aug
Sep
Oct
Nov
Dec
9791 9460 9379 9541 8931 9588
350
350
0
0
610
0
4032 3620 3897 3897 3897 3979
353
353
353
353
353
353
3158 3248 2992 2992 1792 2992
499
499
488
488
438
453
1299 1240 1499 1661 1841 1661
100
150
150
150
0
150
8012 7880 7951 7840 7880 7840
1779 1580 1428 1701 1051 1748
320
315
318
314
315
314
647
647
647
647
647
647
647
647
647
647
647
647
Sta Rita 1 PO
Low HEP Cap
Pagbilao 1 &
Sta Rita 4 PO
Sta Rita 1 FO
Sual 2 PO
Malaya 2 PO
41
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
1783
1698
1868
1766
1811
1717
1729
1737
1726
1728
1793
1833
Coal/Thermal
691
614
747
616
697
635
656
593
614
606
593
635
Diesel
355
373
381
357
375
383
383
377
377
387
383
381
Geothermal
710
682
719
719
720
623
664
741
709
709
741
741
27
29
21
24
19
26
26
26
26
26
26
26
50
50
50
50
1462
1445
1522
1534
1591
1518
1512
1551
1526
1560
1594
1643
321
253
346
232
220
199
217
186
200
168
199
190
58
58
61
61
64
61
60
62
61
62
64
66
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
100
Hydroelectric/Other RE
Import from Luzon
Demand Forecast
KSPC U2 S/D
CTPP U2 S/D
42
43
Source: NGCP
44
Source: NGCP
45
Electric Power
Supply-Demand Outlook for 2012-2030
Sec. Carlos Jericho L. Petilla
Department of Energy
Visayas Power Summit
Waterfront Hotel
26 April 2013