15 December 2009
Davis Langdon LLP, London
Project Support
− Risk issues, HSEQ, audit, due diligence
− Consents, Permits & Planning Issues
− Environmental Management Plans
• Project Scope
– 220km submarine cable
– coastal converter stations
– grid connections
• Metoc Scope
– project manager marine aspects
– feasibility studies
– route investigations
– route selection
– risk assessment and burial
– EIAs
– support for EPC contract
– consent monitoring