Documente Academic
Documente Profesional
Documente Cultură
Projects
Batching plant
Galle
Control workshop
Rajagriya
Project
Gampola
Leasing structure
Katunayake
Industrial Training
Sin
Hotel Kalutara
As a sub contractor
QEQ project Port-Authority
AES Kelaanitissa
Gampola Bridge
85 million Rupees
Industrial Training
Maga Engineering (pte)Ltd
All these projects are massive projects; mainly massive projects are done by mga.
This give a clear idea about mga engineering (pte) ltd is one of the leading construction firms
in Srilanka,
Finance
director
Director
operation
Director
administration
Dir, engineering
(planning & dev)
Dir.eng
design&con
Assistant
accountant
Coordinating
engineering
Estimating
dept, planning
General Manager
Administration
Finance
department
Driver orators
General administer
Stores
Industrial Training
Industrial Training
3000 m3
Hapugalla reservoir
12000m3
Kowulhena
reservoir
7000m3
Halloluwagada reservoir
7000 m3
Mahagoda reservoir
3000 m3
Industrial Training
GING GANGA
800mm
INTAKE
600mm
AREATOR
600mm
FLASH MIXTURE
450mm
(2 line)
450mm
CLARIFIER
FOCCULATOR
450mm
(2 line)
450mm
SAND FILTER
150mm
SLDGE DRYING
BEDS
RECOVERYPIT
600mm
400mm
CLEARWATER RESERVOIR
3000M3
350mm
Back wash
800mm
HAPUGALA RESERVOIR
12000M3
THROUGH
SALINITY BARRIER
400mm
MAGAGODA
RESERVOIR 3000M3
600mm
KOWLHENA RESERVOIR
7000M3
500mm
HALLOLUWAGODA RESERVOIR
7000M3
Industrial Training
PROJECT DETAILS
Project
Client
Main contractor
:-KOLON-SAMSUNG CONSORTIUM
Kolon Eng. & const.co.Ltd
SAMSUNG Coporation
Consultant
Sub Contractor
Source of water
:- Gin-ganga
Design Demand
Type of contract
Contract No.
:-P&D/GREATER GALLE/W/DBT/2000/01
Total cost
:-Rs.96, 163,190.96
:- 01 July 2002
Industrial Training
EXCAVATION
Before a foundation can be laid it is necessary to excavate a trench of the required
depth and width. Initially survey was done to establish the level in the whole area to quantify
the excavation. Level was measured for each and every square of grid on middle and edges of
square. Bulk-excavation need to be done up to bottom of the screed of basement slab.
Excavation quantify was calculated from the existing levels and excavation bottom level.
Excavation was done 1m below the ground level. Excavation was difficult and time
consuming using man power
For small area excavation, man power was used. Excavation areas were kept under moist
conditions to minimize dust pollution in the site.
Machinery & Equipment used for bulk excavation
Excavator
Tractor
Disposal of earth
All excavated bad soils were disposed off site by using tractor. Sometime excavated
soil was reused for back filling work. Disposal area was kept wet while spreading of earth.
Blondish stone removing
First tried to remove the blondish stone by manual but, could not remove. After that
drilling hammer and air compressor were used to remove but, whole stone could not remove.
Then large bucket excavator and breaker were used to remove that stone. This excavator was
brought by low bed transport.
Backfilling
Over excavated areas were back filled with suitable materials selected from the
excavation. Those approval fill material was deposited in layers of max.300mm or less, as can
be thoroughly compacted with rollers, vibrator. No layers were deposited until the previous
layer has been compacted to the satisfaction of the engineer, and also no filling of excavation
were commenced until these had been approved and measured by the engineer. Compaction
Department of Civil Engineering
Industrial Training
Maga Engineering (pte)Ltd
was done until the soil gets its required properties (dry density, etc).proctor compaction test
was done
Machinery & Equipment used for backfilling & compacting
Tractors
Excavator
Roller
Vibrating rammer
Industrial Training
Degree of Compaction
Procedure
A hole about 6 wide and 6 deep was dug into the compacted soil.
A cone and jar apparatus containing special fine-grained uniform sand was placed over
the hole, and hole was filled with sand.
Then completely dried and weighted again (the amount of water lost, divided by the
dry weight gives the moisture in the soil)
Calculation
Weight of can +sand 1
=W1
Weight of sand
=W1 W2
= D (Known)
Volume of funnel
= V1 (known)
Volume of hole
= M1
Weight of can
= M2
= (M1 M2)
Bulk density
Weight of can
=w1
=w2
10
Industrial Training
Weight of can+ dry soil
=w2-w1
=w3-w1
Weight of water
=w2-w3
Moisture content
= (w2-w3)/( w3-w1)
Dry density
11
Industrial Training
Waterproofing
Water proofing member was fixed above the screed concrete top. It is fixed to prevent
water movement towards the structural inside. There is different kind of water proofing
system.In my site polythene was used for water proofing membrane.
FOUNDATION
Foundation is the lowest part of a structure .which a building rests and its purpose
is to safely the load of a building to a suitable sub soil. Generally, foundations are placed
below the ground level to increase the stability of a structure or a building.
The objectives of providing foundation
To distribute and transmit the total load acting on the structure to a larger are of
underlying support.
1. Strip foundation
2. Isolated or pad foundation
3. Raft foundation
4. Combined foundation
5. Piled foundation
Strip foundation
Reinforced concrete strip foundations are used to support and transmit the loads from
heavy walls. Tensile reinforcement is therefore required in the lowest face of the strip with
distribution bars in the second layer running longitudinally.
Normally, weak concrete (grade 15 (1:3:6)/40 mm agg) is used for blinding concrete
but, in my site grade 20 concrete (1:2:4/20 mm agg) was used for blinding concrete.
Normally, grade 20 concrete (1:2:4/20 mm agg) is used for reinforcement concrete. But, in my
Department of Civil Engineering
12
Industrial Training
Maga Engineering (pte)Ltd
site grade 35 (1:1:1) concrete was used because water pressure is most. 600 mm height
concrete layer was placed. 16 mm rebar is used in 2 layers with 100 mm space in each
other. The rebar should not to touch the water bar.
Isolated or pad foundation
This type of foundation is used to support and transmit the loads from piers and
columns. The most economic plan shape is a square but if the columns are close to the site
boundary it may be necessary to use a rectangular plan shape of equivalent area. In my site
every pad foundation was square.
Normally, weak concrete (grade 15 (1:3:6)/40 mm agg) is used for blinding concrete
but, in my site grade 20 concrete (1:2:4/20 mm agg) was used for blinding concrete.
Normally, grade 20 concrete (1:2:4/20 mm agg) is used for reinforcement concrete. But, in my
site grade 35 (1:1:1) concrete was used because water pressure is most. 450 mm height
concrete layer was placed. 25 mm rebar is used in 2 layers with 210 mm space in each
other. The rebar should not to touch the water bar.
Combined foundation
Having a square base is not always possible. If the structure has a wall on the
boundary of the site the columns would be located eccentrically, if conventional isolated bases
were employed. One method of overcoming this problem is to place the perimeter columns on
a reinforced concrete continuous column foundation in the form of a strip. The strip is
designed as a beam with the columns acting as point loads which will result in a negative
bending moment occurring between the columns requiring top tensile reinforcement in strip.
Normally, weak concrete (grade 15 (1:3:6)/40 mm agg) is used for blinding concrete.
but, in my site grade 20 concrete (1:2:4/20 mm agg) was used for blinding concrete.
Normally, grade 20 concrete (1:2:4/20 mm agg) is used for reinforcement concrete. But, in my
site grade 35 (1:1:1) concrete was used because water pressure is most. 450 mm height
concrete layer was placed. 25 mm rebar is used in 2 layers with 210 mm space in each
other. The rebar should not to touch the water bar.
Raft foundation
The principle of any raft foundation is to spread the load over the entire area of the site.
This method is particularly useful where the column loads are heavy and thus requiring large
bases or where the bearing capacity is low , again resulting in the need for large bases, there
are three type of raft foundation such as
13
Industrial Training
Beam and slab Raft foundation
Solid slab Raft foundations are constructed of uniform thickness over the whole raft
area, which can be sometimes wasteful since the design must be based on the situation
existing where the heaviest load occurs.
Normally, weak concrete (grade 15 (1:3:6)/40 mm agg) is used for blinding concrete.
but, in my site grade 20 concrete (1:2:4/20 mm agg) was used for blinding concrete.
Normally, grade 20 concrete (1:2:4/20 mm agg) is used for reinforcement concrete. But, in my
site grade 35 (1:1:1) concrete was used because water pressure is most. 600 mm height
concrete layer was placed. 16 mm rebar is used in 2 layers with 100 mm space in each
other. The rebar should not to touch the water bar.
REINFORCED CONCRETE
Concrete and steel expand and contract at the same rate under temperature changes.
Concrete has a high resistance to damage by fire and thus protects the steel, which is
easily damaged by fire.
Types of stresses
The following are the principal type of stress, which develop in structural members:
(1)Compression
Compressive stresses tend to cause concrete to crush.
(2)Tension
Tensile stresses tend to cause concrete to stretch and crack
(3)Shear
Shear stresses tend to cause sliding between adjacent sections of concrete
Department of Civil Engineering
14
Industrial Training
Clean bar
Deformed bars
Reinforcing steel has to be extended beyond the region of tensile stress to develop satisfactory
bond strength. If there is not enough room to extend a bar, a bend or hook is used to develop
bond with the concrete.
REINFORCING STEEL
Types of Reinforcing Steel
Hard-drawn wire,
In our site hot rolled plain round bar (mild steel) and hot rolled deformed bar (Tor
steel) were used.It is important to be aware of the different types of reinforcing steel, how to
identify them and where to use them. In schedules, R for round is mild steel in the form of
plain smooth bars.
T or Y denotes steel, which has a ribbed appearance and may be twisted. This is
used to be known as high tensile steel, which is called as tor steel or yield steel.
Tor steel
Tor steel is produced in the form of cold hoisted deformed bars for concrete
reinforcement and available almost all standard diameters, ranging from 6mm to 50mm.but in
15
Industrial Training
Maga Engineering (pte)Ltd
our site we used (10-32) mm bars. For all reinforcement work tor steel was used and its
strength is 460N/mm2.
Mild steel
Mild steel is soft carbon steel and it contains (0.2-0.5) percentage of carbon. This can
be easily cut and bend. In addition, its strength is 250N/mm2. Therefore, it is mostly used for
column stirrups and beam stirrups. In our site the 6 and 10 mm diameters bars were used.
Naming reinforcement bars
Reinforcement on details drawings is described by a coding system to simplify
preparation and reading of the details.
For example: - 25T20-65-125B1
25
- No of bars
20
-Bar diameter in mm
65
-Bar mark
125
-Spacing
B1
- Bottom (position)
Abbreviations used
B1
- Bottom reinforcement
B2
T1
- Top reinforcement
T2
C/C
- Center to center
ALT -Alternatively
Weight of tor steel
1m tor steel weight is calculated approximately below the equation.
Weight = diameter / 162.162
Diameter is in mm
Department of Civil Engineering
16
Industrial Training
Weight is in kg/m
Bar type
Weight (kg/m)
T10
0.616
T12
0.888
T16
1.579
T20
2.466
T25
3.854
T32
6.313
T40
9.864
Lapping
T20
T20
Lapping length = 50 *
= 50* 20
= 1000 mm
(2.)
T32
Lapping
T20
Department of Civil Engineering
17
Industrial Training
Lapping length =50 *
Y
X
Y: X =1:10
Before accepting deliveries of reinforcing steel, always check the following:
Loose, flakey or soft rust must be removed, as it will prevent the concrete bonding to
the steel.
Heavy corrosion reduces the effective size of reinforcement, and an engineers advice
should be sought before using it.
Very light rust causes no problems and it can even improve the bond between steel and
concrete.
Stacking Reinforcement
The following points should be remembered when stacking reinforcing steel on a job site
18
Industrial Training
Stack it conveniently according to size and length.
Bending reinforcement
Probably the simplest device for beading bars up to 12mm in diameter is a 3m
length of pipe whose internal diameter is slightly greater than the diameter of the bar. This
method can be used when the bends are simple and the quantity is not great.
For general work up to 20 mm diameter bar, simple hand, operated machines are
available. These machines consist of a flat sleet plate on which is fixed a bending pin around
which the bar is bent.
When bar is bended, the following point should be noted
Bar must be bent accurately to the dimensions shown on the bending schedule.
Otherwise, the cover may not be obtained when the steel is positioned in the structure
fixed.
If steel has been bent and then straightened, it should not be bent again at the same
point or near the same point.
Fixing Reinforcement
Reinforcement must be securely fined in the formwork so that the bars tire not
displaced by workers walking on them or by the placement of concrete. It is essential for the
safety of a structure to ensure that the correct size, shape and grade of reinforcement is used,
and that the reinforcement is fixed accurately and securely in the position specified. It is
essential that the concrete cover specified in the drawing is obtained in the order to protect the
reinforcement from rusting or chemical attack.
Where bars cross or where there is a lapped splice, bars should be tied together with
either soft iron wire (tie wire) or specially made wire ties( bag ties).The most suitable size of
Department of Civil Engineering
19
Industrial Training
Maga Engineering (pte)Ltd
wire is 1.6 mm diameter (do not use wire less than 1. 25 mm diameter). Bag ties can be
obtained in various lengths, but 150 mm is suitable for most purposes.
In our site, 1.6 mm diameter tie wire was used. This tie wire one roll was 25 kg .this
wire was cut four pieces for 10, 12,16 mm and three pieces for 20, 25,25mm. Bars were tied
double.
In the case of double net , (such as in the case of a base) stools are used between the
two nets to get required space between them.
Under the bottom net cover blocks were used in required density to maintain the
bottom cover.
20
Industrial Training
Maga Engineering (pte)Ltd
distribution bars (secondary bars).In bottom, main bars should be below the distribution bars.
In top, main bars should be above the distribution bars.
(top)
Main bar
Main bar
distribution bar
distribution
(bottom)
When main bars or distributions lap, crank is not necessary. we should not lap more
than 50 % of the bars at the same cross section.
First line bar (FF)
Second line bar (NF)
Stools
Stools are used to separate the top reinforcement mesh and bottom reinforcement
mesh. Those should strength enough to bear the load without changing the gap of two layers.
12 mm or 16 mm bars are used to make the stools.
Stool height
21
Industrial Training
Maga Engineering (pte)Ltd
Stool height = slab thickness-(top (main bar diameter +distribution bar diameter) +
bottom (main bar diameter +distribution bar diameter) + (2*cover))
(2) Column
A column is a vertical member carrying the beam and floor loading to the foundation
and is a compression member. Since concrete is strong in compression it may be concluded
that provided the compressive strength of concrete is not exceeded no reinforcement will be
required. For this conditions must exist:
Column must be short, which can be defined as a column where the ratio of its
The minimum number of main bars in column should not be less than four for
construction.
Stirrups for column
To prevent the slender main bars from buckling and hence causing spalling of the
concrete, links or binder are used as a restraint.
These should be at least one quarter of the largest main bar diameter.
Pitch or spacing not greater than twelve times the smallest main bar diameter.
All bars in compression should be tied by a link passing around the bar in such away
that it tends to move the bar towards the centre of the column.
Main bar
Binder
Binder
Main bar
Column with 4 main bars
22
Industrial Training
Circular column
Strater bar
anchorage
Base slab
Column Elevation
Column plan
In column bar schedule, crank is important . The slope of the inclined portion of a
cranked bar should be 1 in 10. crank the upper bars to extend the lowest bars. Starter bar
should be bended inside base slab. This anchorage length is 50 *.
e.g. column bar diameter 32 mm
crank
crank length=10*32=320 mm
anchorage length= 50 *
=50*32
=1600 mm
(3) Beam
400
23
Industrial Training
Maga Engineering (pte)Ltd
In beam bar schedule, crank is important . The slope of the inclined portion of a
cranked bar should be 1 in 10. Anchorage length of beam depend on the beam height. E.g. if
beam height is 400 mm and cover 50 mm , anchorage length is 250 mm. This anchorage
length may be different. This anchorage length is no specific limitation.
*
*
*
*
Hogging moment
Sagging moment
24
Industrial Training
Compression
Compression
Tension
Hogging moment
sagging moment
In continuous beam, hogging moment and sagging moment are due to loads. In top of
the beam, tension is in hogging moment point and compression is in sagging moment point.
In bottom of the beam, tension is in sagging moment point and compression is in hogging
moment point. Tension bars are used in tension points in top of the beam. such as Tension
bars are used in top of the beam in support point .Tension bars are not used in bottom of the
beam. When beam main bars spacing is greater than 250 mm, tension bar is used.
(4)Wall
Vertical bars
Horizontal bars
25
Industrial Training
L - Shaped bars are used in T junction and corner of the wall to avoid bursting or
cracking. Reinforcement in inner face should extend to outer face.
Nominal diagonal reinforcement should be provided in both faces around all openings
in a wall. If the walls are opening as shown above, the above detail can transmit only about
25% of the walls flexural capacity. Then, it is better to use hair pins .which has a higher
moment carrying capacity.
COVER BLOCKS
Reinforcement work cover block is very important part. Cover block is used to maintain the
space between shuttering and bottom of the reinforcement. Using grade 25 concrete with
6mm chips cover blocks (spacer) will be made as the given sizes. They are made up cement
:sand : chips = 1:1:1.
All formwork of reinforcement were supported on cover blocks. So that the
reinforcement can be completely enclosed by concrete and thus protected against corrosion
cover blocks may also be needed at the sides of the reinforcement to maintain the correct
distance from the side shuttering.
Covering sizes were specified in the drawings. Covering sizes are depend on,
1. Weather condition
Department of Civil Engineering
26
Industrial Training
2. Fire resistance
3. Grade of concrete
A part of binding wire was placed inside the cover block at construct level to tie with
reinforcement, otherwise it may move away from the exact location.
In our site 50 mm cover block was used in all places.
EXAMPLE:
T20-1-210
T20-2-210
450mm
T20-3-210
T20-4-210
Column footing
Length = 27450 mm
Width = 2750 mm
Height = 450 mm
Cover = 50 mm
2650 mm
Main bar
200
200
12000
11800
200
27
Industrial Training
11800
12000
200
200
No of distribution bars
(2750-2*cover)/210= (2750-2*50)/210= 12.62=13
Therefore no of distribution bars = 14 (13+1)
Bars are in top and bottom
2/132/ T20
2650
200
200
2/14/ T20
12000
2/14/ T20
5550
200
2/14/ T20
11800
200
column
Cutting
Total
Total
of
length
length
weight
T20
210
bar
264
(mm)
3050
(m)
799.1
(kg)
1970.58
T20
210
28
12000
336.0
828.58
T20
210
28
5750
161.0
397.03
T20
210
28
12000
336.0
828.58
footing
28
shape
Industrial Training
Formwork
Introduction
This is temporary structural system, which provides casing to enable wet concrete to
attain the shape required. Formwork provides
1. Strength
2. Smoothness
3. Stiffness
4. Good shape at the concrete face
There are many objectives to be considered in selection of formwork
Concrete finish
Cost
Reuse
Logistics
Productivity
The concrete formwork and its labours are one of the highest profit risk area for the
contractor.
Additional requirements for good formwork
1. Joint should be simple
2. Must be easy to strip after concreting
3. Timber should not be too dry/ too wet (moisture content 15- 20%) with the surface
coated with mould oil
4. formwork economy in the design of structures
At the formwork erect, consider the materials and methods will be required to
make and the removal
The formwork shall withstand and worst combination of the following loads
29
Industrial Training
Maga Engineering (pte)Ltd
Construction loads including dynamic effects of placing , compacting and
Construction traffic
Wind loads
coupler
Procedure
4 * 8, 12 mm thick plywood decking across 48.6 diameter * 2.4 mm thick pipes at
200 mm centers and spacing 1200 mm is placed across 100 mm * 100 mm timber bearers, is
supported by height adjustable vertical shores by Nppon Beatty. these shores are located in
rows at 1200 mm centers and 750 mm spacing , in each row . they are braced for lateral
stability in two directions at right angles, using 48.6 mm diameter GI pipes placed diagonally
and fixed together using GI pipe clamps. After erecting this arrangement, they are properly
leveled.
Details about shores
Type VS- 2
Closed height 2110 mm
Fully extended height 3480 mm
The safe working loads for axial loading are 20 KN in closed position and 15 KN in the fully
extended position
Total weight of the unit 13 16 kg
Material High-tension steel
Lowest tube diameter 60.5 mm
Upper tube diameter 48.6 mm
Top plate fork and flat
First, all the shores are adjusted roughly to required level, which is measured from off
lines. Then 100 mm* 100 mm bearers and 50 mm * 50 mm timber, 50 mm diameter GI pipe
are put after plywood is placed on that. Finally, they are properly leveled.
Department of Civil Engineering
30
Industrial Training
Coupler
To brace the shores for lateral stability in two directions at right angles, using 48.6 mm
diameter GI pipes fixed together with GI pipe couplers. Swivel, rectangular couplers are used.
The key factors concreting the workman ship of false work
The false work is used in accordance with the design , in particular as regards quality
of components, and setting out
Tolerances ( 3 mm)
The vertical member of the structure should be located centrally on the sole plates on
base plates and fork head if size 100 mm
High tensile pin is commonly used but in some pins replaced by reinforce bars
Over extension of the screw, supporting the fork head must be avoided ( 300 mm)
Provide edge protection to all open side and holes in the decking as well as properly
constructed access to the working area to be prevent accidents
When concreting
On the slab, materials should only be stored in areas designed by the engineer
200-300 mm
600 mm
31
Industrial Training
Maga Engineering (pte)Ltd
Space between slap and first GI horizontal support 200 mm
Column formworks are subjected to greater lateral pressure. Because of, its small cross
section area compared with the height. So column boxes must have tight joint to withstand
that high pressure. And also blowhole is made at the bottom to clean the inside surface before
concreting.
Baffle wall with column
Formwork for this component also similarly erected up to 600 mm from upper surface
of base slab, so that the height of kicker for wall will be 600 mm throughout from the upper
surface of the slab
It is to be noted that the portion of the baffle wall directly connected with the main
periphery wall will not be constructed at this stage, which will be done along with the
construction of main periphery wall. Inner lengths of baffle walls, which are commencing
from expansion joints, are erected under the present stage.
32
Industrial Training
Industrial Training
P- Cones
This is the old model Japanese system formwork arrangement and P-Cones types. 40
mm and 50 mm size P-Cones used according to load carrying capacity required. i.e. 50 mm is
used to bear where the high force occur.
34
Industrial Training
50 mm pee cone
Preparation of formwork
Before concrete is placed, the formwork should be cleaned of all dirt and construction
debris. All surfaces are coated with approved mineral mould oil.
12 mm plywood
50 mm*50 mm timber
Form tie
225 mm
48 mm Gi pipe
500 mm
Pipe support
(Adjustable)
500 mm
500 mm
100 mm*100 mm
Hard wood
500 mm
400 mm
Expansion joint
300 mm
35
Industrial Training
Wall formwork
For the key concreting vertical surfaces are prepared with the sharp cut of the original
ground. RRM was arranged places where ground condition is disturbed.
Formwork of the wall foundation was provided at the outer face of the foundation slab
that is inner face was covered by the previous concreted base surface. Along the wall line ,
wall kicker was arranged supporting the formwork with rebar .the kicker height is 150 mm
and at the wall center water bar was kept in positions by using water bar chips and wires so
that it was centered on concrete surface.
The formwork material is 12 mm marine coated plywood sheets for water structure
and supporting system is shown the sketch. To maintain the wall thickness separator were
used with 50 mm pee cone.
For our safe side, and to avoid water leaks through pee cones, rubber washer or
welded metal plate was used whenever fixing reservoir wall formworks. formwork for
reservoir walls was arranged as follows
1. 2.4 m 1st step
2. 2.4 m 2nd step
3. 3rd step with roof corbel
Removal of formworks
Formwork should not be removed until the concrete a sufficient strength to supports
its self weight and any other load transferred. Form should be eased out carefully in order to
prevent the load being transferred suddenly to the partly hardened concrete.
Walls and columns (unloaded)
Department of Civil Engineering
12-18 hrs
36
Industrial Training
Tie beams (not load transfer)
Slap
21 days
CONCRETE
Concrete is a mixture of cement, fine aggregate, coarse aggregate and water. Two
essential properties of the hardened concrete are durability and strength. Both properties are
affected by the voids or capillaries in the concrete which are caused by incomplete
compaction or by excessive water in the mix.
According to the code BS 8110 the concretes are divided in to two classifications. The
first consists designed mixes, where strength is the main criterion specified, the design of
the mix is left to the supplier and compliance is judged on the basis of strength testing. The
second classification is that of prescribed mixes, where the cement content or mix
proportions are specified and it is the duty of the specifier to ensure that the mix specified will
give the required properties, including strength. With prescribed mixes, strength tests are not
used to judge compliance width the specification.
Transporting
Transporting of concrete will be done by 5m3 capacity concrete trucks from batching
plant number of concrete trucks will be increased by considering the volumes to be placed.
Concrete Placing
Placing of concrete will be done by using the concrete pump car and crane and bucket
considering the volume arid site conditions. Requited site test (slump test) will be arranged
for each trust to maintain the quality and cube will be casted for checking the strength of
concrete. Concreting will be started at one corner of the formwork and proceeded diagonally
without creating hardened edges.
Curing will be arranged for 7 days by using the gunny cloths and sprinkling of water.
Important things before concreting
37
Industrial Training
Check the levels of formwork, reinforcement
Check the reinforcement at all intersection whether the bars, links should securely tie
together with 1.6 mm soft iron wire .whether end of the wires must not point towards
the face
Check the support of the form work and construction joint key
Check the surface (roughened joint surfaced which has to concreting) using
compressor
38
Industrial Training
Maga Engineering (pte)Ltd
practical minimum. The necessity for such precautions will be determined by the Engineer in
relation to the other factors affecting the heat of hydration, such as the characteristics of the
mix constituents, the nature of the particular pour and the method of curing to be adopted.
HANDLING CONCRETE
When handling concrete the following are to be avoided:
Delay
Drying Out
Segregation
As soon as the cement and water are mixed and concrete begins to harden and it does so more
quickly with:
High concrete temperature (so keep the concrete cool in hot weather)
forms, Throw the batch, out rather than try to doctor it. Never add water to hardened concrete.
There must be no delays in transporting, placing and compacting
Form B I 9(M) requires that t h e concrete be placed and compacted within the following
times from charging the mixer
Temperature32 C or less
Mixed on Site
45 mins
30mins.
Ready-mixed
I hour
45 mins.
39
Industrial Training
Maga Engineering (pte)Ltd
However, the supervisor should appreciate that from time to time specifications are
altered. So on each new job he should check the Job Document to ensure himself that there
have been alteration of which he is unaware
Compacting
The object of compacting concrete is to ensure that maximum density is obtained,
and that no gaps are left between the concrete and the surfaces of the reinforcing steel and
formwork. A5% loss of compaction can result in a 30% loss of strength.
Proper compaction results
Maximum strength
Spinning (used only for concrete pipes and hollow circular piles)
Hand compaction
Rodding or tamping by hand can only be used for very small quantities of concrete
with a slump of 50-100mm. it may be used only for compacting minor works such as pipe
heads and not on bridges or culverts.
Immersion vibrators
This type of vibrator may be
40
Industrial Training
Withdraw the vibrator immediately motor begins to collect on the surface. This can
Withdraw tile vibrator slowly (not faster than 100 rout per second) to allow the hole
Work systematically, inserting tile vibrator at points about 500 poor apart (this will
vary with different consistencies of concrete and different sizes of vibrating head).
(g)
Avoid using the vibrator to push tile concrete along the forms. the concrete should be
Do not allow the vibrator to touch the forms as a sand streak may result or the form
may be damaged.
(i)
Normally the vibrator will be operating for about two thirds of the concrete is being
placed, though this time varies depending on the Characteristics of the mix and the
dimensions of the section being poured.
(j)
When placing concrete in floors or deck slabs, it may be necessary to tilt the vibrator
41
Industrial Training
Previous layer
Previous layer
Incorrect
Still plastic
Correct
Previous layer
Incorrect
Incorrect
Incorrect
42
Correct
Industrial Training
Correct
Incorrect
Poker using method
CURING
Reasons for curing
Correct curing is very important in order to get the maximum strength, water tightness and
wear resistance. The two things needed to provide conditions favorable for continued
hydration are
Adequate moisture
A favorable temperature
Loss of water from the surface of the concrete can cause hydration to cease, thus
preventing strength development. It can also cause shrinkage, which results in surface
cracking.
Low temperatures also cause hydration to slow down, and it is necessary to keep the
temperature well above freezing.
Advantage of curing
Continuous curing from the time the concrete is placed helps to ensure a hard, dence
surface and the risk of crazing and dusting
Curing methods
Concrete can be kept moist by a number of curing methods. in our site gunny cloths
were used for water curing.
Length of Curing Period
Form B19 (M) states that slabs shall be kept moist for at least 14 days, and other
concrete surfaces for at least 7 days.
Preventing plastic shrinkage cracks
Department of Civil Engineering
43
Industrial Training
Maga Engineering (pte)Ltd
This type of cracking comes times occurs soon after the concrete has placed. Plastic shrinkage
cracking is usually associated with hot-weather concreting. The following will increase
evaporation of surface moisture and therefore the possibility of plastic shrinkage cracking:
Low humidity
High winds
To minimize the possibility of shrinkage cracking the following simple precautions should be
taken:
Dampen the aggregates if they are very dry (but don't forget to allow for this
additional moisture
Cover the concrete with wet covers or curing compound as soon as possible.
If cracking does occur before initial set, it should be rectified by hand working
followed by proper Curing.
Placing will be executed in accordance with the drawing on which the water bar profile and
the position required is marked level differences, bends, junctions, etc should be carefully
considered before placing.
44
Industrial Training
Maga Engineering (pte)Ltd
Fixing clips are attached to the ends of the water bar. The fixing clips simplify the fixing of
water bars to the reinforcing steel by means of tying wires and thus ensure the water bars are
not displaced during concreting.
(b). Fixing to formwork
Formwork may be used. In this method allow one half of the water bar out and other half will
be casted. Water bars clamped between formwork.
PLACING THE CONCRETE
The water bar performs its function only if both sides are well embedded in the
concrete. The accumulation of coarse aggregates (honey combs) should be avoided around the
water bar to be fixed firmly.
Placing of fresh concrete near the water bar requires core, as otherwise it will be
forced from its position by the pressure of the fresh concrete that is ends will fold up. To
present this the same concrete pressure must be present on both sides of the water bar.
CONCRETING THE SECOND STAGE
The water bar end will be checked for honeycombing and repaired if necessary. Bounding
agent will be wed for the concrete surface.
WELDING
Water bars are made form thermoplastic PVC and therefore allow an easy on site
welding. The ends are heated with welding blade mail the PVC melts (without burning or
charring). The welding blade is removed and molten ends are immediately pressed together.
The welded joint will be inspected after it has cooled.
VIBRATING OF CONCRETE EAR THE WATER BAR
Care will be taken to ensue that concrete is well placed and compacted around the
water bar area.
45
Industrial Training
Wall Kickers
Proposed Details of the Kicker
(1)Height of the Kicker
According to section 5.7 of BS 8007: 1987, the height of the kicker should be at least 75
mm.
R.D. Anchor suggests on pages 17 & 82 of his well known book entitled, Design of Liquid
retaining Concrete Structures , that the height of wall kicker should be between 100 to 150
mm.
In view of providing firm grip to wall formwork, we propose, the height of wall kicker should
be 100 mm.
(2)Shape of Kicker
R.D. Anchor states in his aforementioned textbook, if rebates are provided at construction
joints, cracks are formed invariably.
According to him, the most appropriate kicker is only a rectangular up stand without any
fillet and the free surface of the concrete must be finished to a compacted level surface.
We also prefer to introduce a rectangular up stand without any fillet as the wall kicker.
(3)Width of Kicker
Since the outer face of the external wall is inclined inwards, the width of the kicker at the upper
surface is slightly less than that at the lower end. The inner angle of inclination of the outer face
of the wall is 86.70 and the width at the upper surface of the kicker is 5.8 mm less than that at
the bottom therefore the width of the kicker at the bottom is 750 mm [wall thickness]. But the
width at the upper end of the kicker is 385 mm.
46
Industrial Training
47
Industrial Training
White cement mixed with water and applied above the motor (this is applied for
colour)
Water proofing membranes are used to prevent water movement towards the inside of
the structure. There are different kinds of the water proofing membrane
(e.g.
Xypex).
Roof slab concrete was grade 35 and benching concrete was grade 20. benching
concrete is used to protect the water proofing membrane from its failure by external
activities.
Leakage checking
48
Industrial Training
Maga Engineering (pte)Ltd
First, that area was chipped after that water plug (one type of cement) mixed with
water .then applied in that area.
Slump test
Cube test
Slump test
The workability of concrete is the ease with which it may be placed and
compacted. The slump test is used to indicate the likely workability of a concrete mix.
Concrete is tested to control workability (consistency). The consistency of the concrete is
checked by means of slump cone. The slump test measures the consistency of concrete. It is a
simple means of ensuring that the concrete on site is uniform.
Once the slump of a particular concrete mix has been determined, the slump test
indicates whether or not the materials in different batches are still being mixed in their correct
proportions. If the slump alters from batch to batch, it is most probable that the water content
is varying from batch to batch. However, variation in slump can also be caused by alterations
in aggregate grading or cement content.
200mm
The mould shall be of a metal other than brass and aluminum of at least 1.6 mm.
(or 16BG) thicknesses. The top and bottom shall be open and at right angle to the axis of the
cons. The mould shall have a smooth internal surface. It shall be provided with suitable foot
piece and handles to facilitate lifting it from the moulded concrete test specimen in a vertical
direction as required by the test. A mould provided with a suitable guide attachment may be
used.
Department of Civil Engineering
49
Industrial Training
Maga Engineering (pte)Ltd
Pointed steel rod: (The tamping rod shall be of steel or other suitable material, 16 mm
in diameter 600 mm long and rounded at one end
Scoop
Smooth flat plate: The base plate shall be of steel or other suitable material, smooth
rigid and with non-absorbent surface.
The test must be carried out on a level non-absorbent surface. The inside surface of
Note: if the concrete collapses sideways when the cone is lift, repeat the test.
Allowable slump range is different to every grade of concrete.
Grade of concrete
Department of Civil Engineering
Industrial Training
Grade 15
Grade 20
120+/-10
Grade 25
120+/-10
Grade 30
120+/-25
Grade 35
120+/-25
Grade 35A
120+/-25
Grade 50
120+/-25
Cube Test
a) Size of Test cubes
The standard size of cube shall be 150 mm*150 mm *150 mm, but may be 100 mm*100
mm* 100 mm. cubes may be used, if the minimal maximum aggregate size does not
exceed 25 mm
b) Compacting test cubes
The test specimen shall be made as soon as practicable after sampling, in such a way as to
produce full compaction of the concrete with neither segregation nor excessive laitance.
The mould shall be filled in layers approximately 50 mm depth and each layer shall be
compacted. After the top layer has been compacted the surface of the concrete shall be
finished level with the top of the mould by means of a trowel.
When compacting by hand, the standard compacting bar shall be used and the storks of
the bar shall be distributed in a uniform manner, over the cross sections of the mould.
The number of strokes per layer, required to produce the specified condition will vary
according to the type of concrete, but in no case shall the concrete be subjected to less than 35
storks per layer for 150 mm.
c) Curing Test cubes
Specimens made on site.
Immediately after they are made, the test specimens shall be stored in a place free from
vibration, under damp matting or other suitable damp material, completely covered with
polythene or other impervious sheeting, at temperature of 20 +- 5 C, for 16 to 24 hours, form
the time of adding water.
If the concrete has not achieved sufficient strength, to enable remoulding to be carried out
within the stated period, the remoulding shall be delayed for a further 24 hours, but this fact
Department of Civil Engineering
51
Industrial Training
Maga Engineering (pte)Ltd
shall be stated in the text report. During this further period, the specimens shall be stored in
the moist air conditions stated
After moist curing, the specimens shall be marked for later identification, removed form
the moulds and unless required for test within 24 hours, immediately submerged in a water
tank until they are transported to the testing laboratory.
One or more tanks can be used, containing clean water, renewed at least once a month and
maintained at a temperature of 20 +- 2 C on site.While the specimens remain on site, records
of the daily maximum and minimum air and water storage temperatures shall be kept with
maximum and minimum thermometers or with continuous recording instruments.
The specimens, well packed in damp sand or wet sacks and enclosed when necessary
in a polythene bag or sealed container, shall be sent to the testing laboratory, when they are
not less than 3 days, nor more than 7 days old, to arrive there in a damp condition not less
than 24 hours, before the time of test.
On arrival at the testing laboratory, the specimens shall be stored in water, maintained
at a temperature of 20 +- 1 C, until the time of test. The specimens shall not be allowed to
become dry at any time, until they are tested.
Specimens to be tested at 24 hours, shall be stored for this period in the moist air
conditions stated and remoulded just before test
d)General
The characteristic strength of concrete, on which the structural design is based is that, 28
day cube strength below which, not more than 5% of the test results may be expected to fall
In order to get an idea of the quality of the concrete sooner, compressive strength test at 7
days may be used, to test compliance with the specified characteristic strength.
For this purpose, the 7 days strength may be taken to be 2/3 of the 28 day cube strength.
The rate of sampling shall generally be as given below, unless other-wise decided by
the officer In charge.
One sample shall be taken from any one batch, selected randomly to represent an average
volume of not more than 20 cubic meters, 20 batches or of the total quantity of concrete
under consideration for testing, whichever is the lesser volume, but not at a rate less than 1
sample per day per grade.
d) Testing Plan
52
Industrial Training
Maga Engineering (pte)Ltd
Each cube shall be made from a single sample taken from a randomly selected batch of
concrete. The samples shall be taken at the point of discharge from the mixer or in the
case of ready mixed concrete, at a point of discharge from the delivery vehicle.
Number of cubes needed
In site number of cubes is varied according to the main contractor or client
requirement.
0-10 m3 3 cubes in which, 1 cube for 7 day testing and 1 cube for 28 day
10-25 m3 6 cubes in which, 2 cubes for 7 day testing and 2 cubes for 28 day
over 25 m3 9 cubes in which, 3 cube for 7 day testing and3 cube for 28 day
53
Industrial Training
5. Pump car
6. Breaker
7. Bar bending, cutting machines
8. Compressors
9. Lorries and trucks (wagon)
Backhoe (Excavator)
Hydraulically operated backhoe is used to have the shape of the excavation curve varied
to suit the situation and allows the limit of the excavation to approach much nearer to the
tracks of the machine due to both arm the bucket are indecently controlled by means of
separated hydraulic rams and also additionally the variable force available with hydraulic
powering gives the machine a much increased capacity.
Used situations
To place the concrete when absence of crane, pump car but to small area
Etc
Etc
Bulldozer
This is very versatile machine and was used frequently. The dozer is normally
operated with a straight blade fixed perpendicular to the line of movement to push the
Department of Civil Engineering
54
Industrial Training
Maga Engineering (pte)Ltd
material forward or angled to move the soil to the side. Crawler type dozer was used in our
site due to
Give low pressure to the base
Not stability problem then wheel type(uneven surface)
Etc
Used situation
Shallow excavation
Ripping
Concrete trucks
In which fully mixed concrete is loaded into the truck mixer at the batching plant.
During transportation to the site the drum revolving at1-2 revolutions per minute agitates the
mix. On arrival the mix is finally mixed by increasing the drums revolutions to between 10 to
15 revolutions per minute for a few minutes before being discharged. 3-5 m 3 trucks are used.
Mixture drum is inclined 16o.
Lorries and trucks (wagon)
Earth moving trucks are used to transport material not only longer distance but also
within the site. They are usually loaded by an excavator, but sometimes, in exceptional cases
by the JCB also. Actually the choice of system in transporting material form the loading point
depends on many factors including.
a) Site conditions
b) Volume of material to be moved
c) Type of material
d) Time available
e) Road condition
f) Distance
g) Etc
Pump car
The transport and placing of concrete by pump car is an increasingly popular method
because
Department of Civil Engineering
55
Industrial Training
a) It is very fast
b) Efficient
c) Little waste of concrete
d) Can prevent the segregation
Etc
Considering points
The speed of the pumping(10-90m3/h)
Should be pump able concrete where slump and sand grading is important
Supply of concrete to the pump should be adequate for the pumps capacity
Maintaining continuously flow of concrete
Breaker
The most common pneumatic tools used in building are the breaker. Which is used
basically for breaking up hard surfaces. This tool needs a supply of compressed air as their
power source.
Steel bending, cutting machine
which is used to bend , cut the reinforce bars. This is one of management planning.
steel yard is in another place and near the site . if the yard is out of the site then we should
have transport facility, time wasting, etc.
58 metric tones
Water tank
150 letters
Cement
Procedure
First sand is conveying belt to the scale which is controlled automatically by lever
principal.then metal is passing to that it scale after sand conveyer stopped. Automatically
calculatethe total weight (sand +metal) and stop when the required weight passed. Both sand
and metal mix together and pass it to the pan/drum mixture. At the same time cement and
water also come to this pan and stop when the required weight collected . at once 1 m can
able to mix . I.e. for 5m3 concrete preparation, five times is necessary.
Department of Civil Engineering
56
Industrial Training
Mixing speed
-20 rpm
-min
Fully prepared mix is then transported to site using concrete trucks. In plant , one
cube is casted per 30m3 concrete to checking strength and also checked the slump from every
truck concrete mixture . G15, G20 ,G25 ,G30,G35,G50 concrete is prepared to supply . if any
cube fails from its required strength then core test should be done
Grade of concrete
The standard recommended compositions are as follows and Concrete grade was
decided according to the requirement of the structure. The basis and the method of
proportioning of concrete are depending on the grade of concrete and the structural
importance of the members. In this concretes Pozzolith300R, AEA303A and Rheobuild 561
are used as admixtures. Pozzolith300R is to change porosity, AEA303A is to change air voids
and Rheobuild 561 is to change rigidity.
SAFETY PROCEDURE
Which is the important consideration point in construction sites where dangerous
accidents take place ,such as handling of huge machines, electrical works, working at higher
elevation, etc.before happen accident , we should be aware of it . some of those are given
below.
Not allow to work underneath when working is going on at higher elevation directly
Etc
57
Industrial Training
-1.0 INTRODUCTION
I have been appointed to do the training in Tudawe Brothers Limited and I have been
working first 13 weeks at the site Little Sisters of the Poor at Maradana. The site is located
next to St.Josephs College. Then after 9 weeks, I have been working at the site Godagama to
Malamba road project which site office is in Aturugiriya. Head office of the organization is
located at 505/2, Elvitigala Mawatha, Colombo 05.
58
Industrial Training
59
Industrial Training
Maga Engineering (pte)Ltd
4. Ascon Appartments ( Project Cost is Rs. 247 Million )
Client
60
Industrial Training
Architect
Arch. H.M.R.B.Herath
Consultants
Contractor
Project Cost
Period
15 months.
Table : 2.1 About the building site details
Project Director
Project Co-Ordinator
Department of Civil Engineering
61
Project Engineer
Site
Technical
Supervisor
Engineer
Officer
Planning Engineer
Site Project
Manager
Site Quantity
Quantity
Surveyor
Surveyor
Assistant
SiteSurveyor
Surveyor
Surveyor AssistantStore
StoreKeeper
Keeper
Industrial Training
Figure :2.1
62
Industrial Training
Site manager
1. Reports to project coordinator.
2. Plans and co-ordinates site activities and with the site staff.
3. Monitors work programme and quality control.
4. Liaises with client, consultants and local authorities
5. Attends all client or consultant meetings.
6. Liaises with sub-contractors.
7. Implementation of safety measures.
8. Liaises with nominated sub-contractors.
9. Liaises with manager planning ad development and prepares micro programmes.
10. Preparation of three monthly programme and monitors programme.
63
Industrial Training
Technical officer
1. Sets out alignment and levels.
2. Checks discrepancies between structural drawings and issues RFI.
3. Counter checks alignment or levels by surveyor.
4. Monitors work progress and quality control by using inspection and test plans.
5. Records daily works and submits to R.E for certification at the end of the day.
6. Act as a member of the site safety committee.
7. Submits of materials for approval from consultants.
8. Maintains concrete cube testing reports.
Supervisor
1. Reports to site engineer or technical officer.
2. Sets out alignment and levels.
3. Labourer supervision and ensuring the quality of works.
4. Counter checks alignments or levels by surveyor.
5. Monitor work progress and quality assurance by using inspection and test plans.
6. Records daily works.
7. Act as a member of the site safety committee.
Site surveyor
1. Counter check setting out or level done surveyors.
2. Monitor progress and quality control by inspection and test plan.
64
Industrial Training
Store keeper
1. Maintaining stock controls (consumables and nonconsumables).
2. Controls or checks quantity and quality of materials delivered.
3. Ensures adequate inventories and stocks are available to meet the sites planned
activities.
4. Prepares daily and monthly records for materials received at site.
5. Inventory control of plant, machinery and equipment, their usage at site and
maintaining records of repairs and services.
6. Inventory control of nonconsumables.
7. Prepares Good Received Note (GRN).
8. Prepares goods issued note.
9. Prepares transfer notes for materials transferred out from the site.
10. Prepares material reconciliation report.
11. Liaises with purchasing department.
65
Industrial Training
66
Industrial Training
Maga Engineering (pte)Ltd
Forms shall be eased out carefully in order to prevent the load being transferred suddenly to
the partly hardened concrete.
The most common fault with release agents is for too much to be put on: this can stain
the concrete. On the other hand, if not enough is applied, striking is made difficult and both
the concrete and form face can be damaged.
The right amount is thin film applied uniformly by brush, roller or best of all spray. if
by mistake too mush is applied wipe off the excess with a clean rag. Never dilute or mix
different release agents together.
Part of structure
Period
for
ordinary
Portland
24 hrs
7 days
14 days
21 days
67
Industrial Training
Y
15
staff
4200
Level Machine
Figure : 3.1
Floor level
68
Industrial Training
4.0 REINFORCEMENT
Reinforcement is used to carry tensile stress as well as compressive stress.
Reinforcement bars carry tensile stress only, where as compressive stress will be carried by
both reinforcement bars and concrete, which is depending on the situation of carrying.
Normally steel bar is used as reinforcement because it has enough strength and both steel and
concrete has nearly the same thermal coefficient. In early days wooden bar was also used for
this purpose.
The reinforcement detail are mentioned in the reinforcement drawing. After that the
following checks have to be done.
1. Spacing
2. No of strips
3. Lap length
4. Starter bars for columns
5. Cover blocks
If there are any construction joints, they should be chipped to bond properly.
- No of bars
16
07
125
Industrial Training
Reinforcement work cover block is very important part. Cover block is used to maintain the
space between shuttering and bottom of the reinforcement. They are made up to 1:2 cement
mortar.
All formwork of reinforcement were supported on cover blocks. So that the reinforcement can
be completely enclosed by concrete and thus protected against corrosion cover blocks may
also be needed at the sides of the reinforcement to maintain the correct distance from the side
shuttering.
Covering sizes were specified in the drawings. Covering sizes are depend on,
1. Weather condition.
2. Fire resistance
3. Grade of concrete.
A part of binding wire was placed inside the cover block at construct level to tie with
reinforcement otherwise it may move away from the exact location.
In our site 30mm cover block was used in all places.
Size of bar
No of bars
Dimensions
Bending length
70
Industrial Training
5.0 CONCRETE
Concrete is a mixture of cement, fine aggregate, coarse aggregate and water. Two
essential properties of the hardened concrete are durability and strength. Both properties are
affected by the voids or capillaries in the concrete which are caused by incomplete
compaction or by excessive water in the mix.
According to the code BS 8110 the concretes are divided in to two classifications. The
first consists designed mixes, where strength is the main criterion specified, the design of
the mix is left to the supplier and compliance is judged on the basis of strength testing. The
second classification is that of prescribed mixes, where the cement content or mix
proportions are specified and it is the duty of the specifier to ensure that the mix specified will
give the required properties, including strength. With prescribed mixes, strength tests are not
used to judge compliance width the specification.
Grade 10 mix
aggregate=1:4:8
Water added (roughly)=32 liters Expected strength= 10 N/mm2
2)
Grade 15 mix
aggregate=1:3:6
Water added (roughly)=32 liters
Expected strength=15 N/mm2
Mainly used for screed but not used for reinforcement concrete.
3)
Grade 20 mix
The following proportion obtains grade 20 mix
Industrial Training
Water added (roughly)= 25 liters
Grade 25 mix
The following proportion obtains grade 25 mix,
aggregate: 1:1.5:3
Water added (roughly)=23 liters
Expected strength=25 N/mm2
5)
Grade 30 mix
72
Industrial Training
o Is the formwork is correctly aligned and levelled?
73
Industrial Training
74
Industrial Training
Next day moulds were removed and all the cubes were fully submerged in water.
After 7 days, cubes were taken from water and 4 cubes were tested for strength After
28 days, the rest of 4 cubes were tested for their strength to find the compressive
strength of
Compressive force is applied to each test cubes separately by hydraulic mechanism. The
crushing strength is taken as the compressive strength, which can be directly red from the dial
gauge. Finally the average strength is taken as the compressive strength of the test cubes.
5.4 CONCRETING
Some experienced in the construction of formwork, preferably a tradesman, should
always be standing by when the concrete is being placed. He should have a supply of suitable
materials such as props, bolts etc. to handle dangerous situations. Check cracking, excessive
deflection, level and plump and any movement. Concrete should be deposited at, or as near as
possible to, its final position.
The concrete should be placed in uniform layers. Avoid placing it in large heaps or
sloping layers because there is always a danger of segregation, especially with mixes tending
to be uncohesive.
In walls and columns no layer should be more than about 450 mm thick. With layers
thicker than 450 mm, the weight of concrete on top makes it almost impossible-even with
vibration-to get the air out from the bottom of the layer. In thin slabs compacted by a vibrating
beam, restrict the layers to 150-200 mm. With greater thickness, vibrators have to be used.
Place the concrete as quickly as possible but not faster than the compacting method and
equipment can cope with.
Where a good finish is required on columns and walls, fill the forms at a rate greater
than two metres height per hour. Also avoid delays and interruptions because these will cause
colour variations on the surface.
Make sure that each layer of concrete has been fully compacted before placing the
next one, and that each new layer is placed while the underlying layer is still responsive to
vibration. This will make the layers "knits" together.
Department of Civil Engineering
75
Industrial Training
Maga Engineering (pte)Ltd
In columns and walls, the placing must be done in such a way that the concrete does
not strike the face of the formwork; similarly, avoid heavy impact against reinforcement, as
the force could displace it.
5.4.1 PLACING OF CONCRETE
The main objective in placing is to deposit the concrete as close as possible to its final
position as quickly and efficiently as you can, so that segregation is avoided and it can be
fully compacted.
Concrete can be transported by a variety of different methods ranging from
wheelbarrows, dumpers and ready-mix trucks to skips and pumps, and though it is obviously
desirable to place the concrete directly into position this is not always possible: for example, it
will seldom be practical to discharge from a dumper or ready-mix truck directly into the top
of a column or wall.
COMPACTION OF CONCRETE
After concrete has been mixed, transported and placed, it contains entrapped air in the
form or voids. The object of compaction is to get rid of as much as possible for this unwanted
entrapped air; down to less than 1% is usually the aim.
The amount of entrapped air is related to the workability: concrete with a 75 mm
slump contains about 5 % air, while concrete of 25 mm slump contains about 20 %. This is
why a low-slump concrete requires more compactive effort-either a longer time or more
vibrators compared with a concrete with a higher slump.
Department of Civil Engineering
76
Industrial Training
77
Industrial Training
78
Industrial Training
5.5 Curing
When water is added to cement chemical reaction takes place (Hydration of cement),
which results setting and hardening of cement. Mixing water is usually sufficient for the
initial hydration of cement. If however, there is insufficient water in the concrete during
its setting period, concrete cant develop its full strength.
It is generally believed that the cement keeps on hardening for at least one
year. When concrete is laid, its water content is rapidly loss, if insufficient precautions are
not taken. This is due to evaporation occurs in the action of sun, wind and heat generated
during setting of cement. The prevention of such process is known as CURING.
But in sites normally curing will be done for 10 14 days. This is sufficient for
concrete to reach the required strength. It is found that concrete will get strength at an
increasing rate. The percentage increase of strength with respect to duration is listed
below,
Duration
Percentage
3 days
40%
7 days
65%
28 days
100%
3 months
115%
6 months
120%
1 year
130%
Climate conditions and the type of cement used will also affect the curing practice.
Concrete will get more strength at high temperature and low at low temperature. Concrete
should be protected from harmful natural conditions. If proper curing is not taken place,
there will occur shrinkage initially and it leads crack.
There are two methods of curing is available. One is supplying moisture to
concrete and the other is preventing moisture from concrete. But in our site we normally
used the first method.
Department of Civil Engineering
79
Industrial Training
Width
Brick shape
Length
Bed face
Height
Stretcher face
Header face
Width of the brick is governed by the fact that it should be of such a size that a brick
can be easily geld by one hand. Height is governed by firing considerations during
burning.
Department of Civil Engineering
80
Industrial Training
6.1.1.2
Blocks
It is a walling unit exceeding in length, with or height the dimensions specified for a
brick. The height of a block work should not exceed either its length or six times its width,
to avoid confusion with slabs and panels.
In solid blocks small holes passing through or nearly through the block do not exceed
25% of its volume. In hollow blocks, holes passing through the unit exceed 25% of its
volume. In cellular blocks do not pass through entirely.
Types of blocks
Front view
Plan view
Solid block
Figure: 6.2
Hollow block
Cellular block
Types of blocks
In our site they have used hollow blocks for the construction of wall (Figure: 5.1). The
sizes that were found in our site are 390*190*200 mm and 390*190*100 mm. As the
strength of the wall increase with size of unit and since there are no practical difficulties in
making a bigger unit. Blocks are made as large as possible. Only restriction is that those
should not be heavier than about 25 kg to facilitate two handed laying.
6.1.2. MORTAR
Mortar generally mixed on volume basis with the help of a gauge box. The mix
proportion of the mortar may vary with the type of individual component whether brickwork
Department of Civil Engineering
81
Industrial Training
Maga Engineering (pte)Ltd
or block work and with the thickness of the wall ( Table: 6.1 & Table: 6.2 ). In practice the
mixing can be done manually or using a tilting drum.
Type of mortar
Cement
Sand
Location
Table: 6.1
Type of mortar
Cement
Sand
Location
1
Table: 6.2
6.2 BOND
6.2.1 NEEDS FOR PROPER BONDING
force
oforce
To account for variations in brick dimensions so that verticality and horizontally of
a wall can maintained
o Provide uniform contact force
between adjacent bricks/blocks.
o Exclude rain and dust which may pass through the wall
force
82
Industrial Training
Figure : 6.3
Bond is the interlacement of bricks produced when they lap those immediately above or
below them. An unbounded wall with its continuous joints has little strength and stability
since load is not distributed evenly (Figure: 6.3). Strength of such a wall is also not
uniform and exceedingly weak at a continuously vertical joint.
6.2.2
Stretching bond
A
B
A
B
Plan of A
Plan of B
83
Industrial Training
1 brick walls only = 225 mm
A
B
A
B
Plan of A
Plan of
B
Figure : 6.5
Heading bond
A
B
A
Plan view of A
Plan view of B
Figure : 6.6
English bond
84
Industrial Training
Maga Engineering (pte)Ltd
This consists of alternate stretchers and headers in every course. This
considered to more attractive than English bond and is used to limited extent in
Srilanka(Figure : 6.7).
A
B
A
B
A
B
Plan view of
A
Plan view of
B
Figure : 6.7
Flemish bond
A
B
A
C
B
A
Plan view of
A
Plan view of
B
Plan view of
C
Figure : 5.7
Flemish bond
Figure : 6.8
85
Industrial Training
String
Gauge box
Figure : 6.9
Construction of wall
86
Industrial Training
6.4
Lintel
The lintel work means that a reinforcement beam kept between the block (or brick) work
where the opening will be provided.
The lintel is provided to take the bearing load affected by the overlaying block (or
brick) work. Generally it will be pre-casted at the site and then will place in the correct
position if the opening is small. Otherwise by using the shuttering work it will be casted. In
my site litel was casted by using shuttering works. The structural arrangement of lintel is
shown as follows,
Lintel
Opening
Figure: 6.10
Lintel arrangement
Size of bricks and blocks are different. That was hard to construct the block or brick
wall with design thickness. When select the bricks must considered the sizes.
2.
Before using any bricks or blocks for any construction work those should be soaked
into the water. Because if those are too dry they will absorb the water from the mortar
and then the water content of on the mortar will reduce and then we could not be able
to get proper bond between the blocks or bricks.
3.
For constructing the wall vertically our site engineer suggested to tie a string between
the soffit and the floor ( Figure : 6.9 ). Because checking the plump line using a plump
bob for each and every block is really a time consuming procedure. To increase the
work speed the site engineer suggested that procedure. But some of the masons are not
quite happy with that. Because they do not like to change the procedure for their work.
87
Industrial Training
7.0 PLASTERING
The function of plastering is protection of wall and the appearance of the building.
Various types of plasters are used. In our site cement plaster was used. Ratio of mixture of the
cement plaster is 1:5 cement, sand. Thickness of plastering is 15mm.
Plastering was the art of covering to surfaces with a plastic material to
obtain an even, smooth, regular, clean and durable surface.
The principle objects of plastering were,
To provide a true, even, smooth and finished surface to the work and improve the
appearance.
To protect the surfaces from harmful effects of atmospheric influences
To cover defective workmanship.
To cover up unsound and porous materials.
To give suitable ground for white wash, co lour wash, distemper or paint.
Plastering conceals defective workmanship and covers up unsound and cheap quality
material. Often, plastering was required to provide a satisfactory base for decorating the
surface by whitewashing, color washing, distempering or painting. External plastering also
termed as rendering was done with the object of improving the resistance of the surface to
rain water penetration and other atmospheric influences.
The following factors affected the selection of the type of plaster to be used:
1. Availability of binding materials.
2. Desired durability and finish.
3. Atmospheric conditions to which the plaster would subjected.
4. The place where the plaster is going to be used lime whether on exterior surfaces or interior
surfaces.
The plastic material or plaster was made by working together a mixture of building material,
which was cement, lime or clay, fine aggregates (usually sand) and water. Certain additives
were sometimes added to improve its adhesiveness, durability and luster. When cement was
used as the binding material, the plaster was termed as cement plaster and when lime was
used as the binding material, it was called lime plaster. Sand normally forms the greatest
proportion of the constituents of a plaster. Sand controls the shrinkage, porosity, strength and
adhesive properties of plaster. Fine sand was often recommended for plastering and it should
be so graded that it has not pass by more than 5% through a sieve of 100 mesh ( b.s. sieve ).
Used sand were clean, sharp and free from deleterious matter. Normal tap water was used to
Department of Civil Engineering
88
Industrial Training
Maga Engineering (pte)Ltd
add. Depending upon the availability of the materials, the choice of plaster for any particular
location, was governed by the rainfall, weather conditions and the finish desired.
1.
Before plastering wall has to curing by the water. Because avoid present voids
between wall surface and motor. But our site they did not consider about that.
2.
In corridor walls, plaster tags have to put together. Otherwise after finishing work
sometimes walls were not same line. That is not good appearance. But our site several
times they did not consider about that.
89
Industrial Training
8.0 TILING
Tiling is generally done to get a nice appearance to the internal part of a building. Tiling
work can be divided into mainly three types. There are wall tiling, floor tiling, and staircase
tiling. They are available in different sizes. For our site tiles were brought from Lanka wall
tiles and Royal ceramic. During in our training period they were doing only wall tiles work.
= 152mm
Wide
= 152mm
Thickness = 6mm
90
Industrial Training
LOCATION
CLIENT
CONSULTANT
CONTRACTOR
COMMENCEMENT
01 02 2002
COMPLETION
30 04 - 2004
PROJECT COST
FUNDED
ROAD LENGTH
11.3 km
Table : 9.1 About road site details
91
Industrial Training
Quality control
Project
Quantity
Surveyor
Surveyor
Site
Manager
Laboratory
Assistant
Accountant
Project
Enginee
r
Assistant Surveyor
Quantity
Surveyor
Store
Keeper
Assistant Engineer
Lab
Technician
Assist store
Keeper
Technical Officer
Trainees
Figure : 9.1
Draught person
Supervisor
92
Industrial Training
10.2.2 RE-CONSTRUCTIONS
Any improvements or constructions works done in already made highway
constructions.
93
Industrial Training
Stage3
10.3 ALIGNMENT
Marking the position of the highway on the ground is known as alignment.
Alignment or
1. Horizontal components:
It includes the straight path, curves and horizontal deviations
2. Vertical components:
It includes verticals curves, verticals gradients and etc.
Both these components play a vital role in determining the alignment of a road. After
careful study of the area. Except in flat areas due consideration has to be given to the grade as
it will be difficult to use a road having very high grades. Once the road is aligned and
constructed. It becomes it, due to high cost of construction and increases in value of ad joints
land.
94
Industrial Training
95
Industrial Training
VII. Approximate cost per km of the route
96
Industrial Training
Maga Engineering (pte)Ltd
Information regarding existing hydraulic structures such as culverts, bridges should be
gathered.
SBST
GB
GS
GC
S.S.G
C/W
A/C
Thickness
Type
50
A/C
20
SBST
150
GB
200
GB
250
GS
130
GC
Table : 12.1 Introduction about the materials
3%
0.3
1.8
3.7
Invert level
5.5
6.7
97
0.6
Industrial Training
Cross section
98
Industrial Training
Maga Engineering (pte)Ltd
Materials used for selected sub grade shall be naturally occurring soils or gravels
and shall not include highly plastic clays, silts, peat or other organic soils or any soil that is
contaminated with topsoil, vegetable or other deleterious matter.
SL properties No.
Test method
AASHTO
T90
T90
40
15
Exceed
Maximum dry density
T180/BS1377 test 14
1650
T193
15
Inadequate stability
The inadequate stability of the sub grade may be attributed due to the following factors,
Inherent weakness of the soil itself.
Excessive moisture in the sub grade.
Inadequate compaction of the sub grade.
12.4SUB BASE
The materials used for sub base shall be naturally occurring or blended gravels and sands
or mixtures there have and shall not include highly plastic clays, peat or other organic soils or
any soil that is contaminated with top soil vegetable and other deleterious matter.
The completed sub base shall contain no aggregate.
Degree of compaction > 98% of MDD.
MDD is indicated Maximum Dry Density.
99
Industrial Training
Test method
SL properties No.
Sub base
AASHTO
T90
40
T90
12
T180/BS1377 Test 14
1750
T193
30
MDD not less than (%)
Table : 12.3 Requirements of sub base materials.
Grading Requirements for Sub Base Materials
Sieve size (mm)
50
37.5
20
5
1.18
0.3
0.075
% Passing
100
80-100
60-100
30-100
17-75
9-50
5-25
Table :12.4 Grading requirements for sub base materials
100
Industrial Training
Following are the main reasons for the inadequate strength or stability of the sub base
Improper mix proportion
Inadequate thickness of the sub base
Use of soft variety of stone aggregates
Poor quality control during construction period
101
Industrial Training
102
Industrial Training
Sieve Size
4.75
2.36
1.18
0.6
0.3
0.075
103
Industrial Training
Maga Engineering (pte)Ltd
This work shall consist of an application of a tack coat to an existing pavement
prior to construction of a surfacing, so as to provide a bond between the two layers.
Penetration grade bitumen:
The penetration grade bitumen used for road construction and refining petroleum
shall derive maintenance work.
104
Industrial Training
Maga Engineering (pte)Ltd
The bituminous mix, after spreading, finishing, and initial compaction by the
paver, shall have a smooth surface free of irregularities causes by dragging, tearing or
gouging.
In narrow widths and in restricted areas where the paver cannot operate, the mix
may be manually laid. In which case, care shall be taken avoid segregation. Manually laid
strips shall be rolled at the same time as the paver laid work.
Breakdown
Intermediate speed
Finish speed
speed (km/hr)
3
5
5
(km/hr)
5
5
5
(km/hr)
5
8
-
105
Industrial Training
13.2 BACKHOE
This type of machine is the one that is most commonly used machine by the
contractors for excavating basements, pits and trenches. This is also called the backhoe.
Discharge is by raising the bucket in a tucked position and emptying the spoil through the
open front end into the attendant haul unit or alongside the trench. Output varies from 60
bucket loads per hour, and this depends on the nature of the excavation area.
106
Industrial Training
107
Industrial Training
The paver can easily handle asphalt and all asphalt mixes, coated and uncoated materials,
crushed stones and dry lean concrete, in fact all road making materials other than wet
concrete.
This is the equipment used for paving road surface with asphalt. The paver should
be capable of spreading finishing and providing initial compaction of the asphalt mix. It
should be able spread the mix to correct lines, grades levels, dimensions and cross section
intended, either over the entire width or part of widths as case may be.
108
Industrial Training
Selected material sample was mixed with distilled water on the glass plate until it can
be rolled and it shall be rolled between the hand and the glass plate.
When it comes to a thread with a diameter less than 3mm the soil shall be kneaded
together and was rolled again. This should be done until the thread shows signs of
cracks and further could not be rolled.
109
Industrial Training
Maga Engineering (pte)Ltd
The cracked threads were put in to a container and weighted.
Test was being carried out for two samples and moisture content can be determined.
The average moisture content of the two samples is the plastic limit.
From the results of the above two tests plasticity index can be acquired.
Plasticity Index = L.L P.L
Take the sample and pass through the sieves (Starting from the largest
one)
110
Industrial Training
From this curve we can find Maximum Dry Density & Optimum Moisture Content.
111
Industrial Training
Degree of Compaction
112
Industrial Training
113
Industrial Training
16.0 SAFETY
Unaccepted accident causes pain, permanent disabilities, human suffering or
death. This affects the victim and other working resulting in loss of morale and even a fear of
performing certain tasks. Therefore accident in construction competent, safetyconscious,
supervision, education, discipline, job safety organization, safety device and equipment.
All persons must wear safety helmets before enter the site works.
Do not though any heavy things on high level that may cause injuries.
Ensure that there is no danger from live electrical cables or equipment near to work is
carried out.
Goggles and screens must be used when doing the work that might cause damage to
eyes.
Power tools were not exposed to rain. They were not used in damp or wet location.
Do not force tools (it will do the job better and safer at rate for which it was intended)
Dress properly
Use safety glasses; also use face or dusk mask if cutting operating is dusty.
114
Industrial Training
17.0 CONCLUSION
After finishing the Level 3 examination we have to go into the industry as civil
engineers. Without knowing about the industry and practical knowledge we could not be able
to survive as real engineers in future. By considering this University of Moratuwa and NAITA
decided to have an Industrial Training programme for undergraduates after finishing their
Level 3 examination.
While we are in the university we are studying many theories. Even though we are
doing a lot of practicals during the academic year to understand the concepts clearly, certain
things can not be found or can not be learnt as concepts such as labourer management.
Therefore it is necessary to take the Industrial Training as serious and we have to do it
properly. Labourer management is very important for civil engineers because most of the time
they have to deal with the labourers directly or through subcontractors.
Civil engineer should have the ability to coordinate the other labourers or subcontractors to
finish a construction within the limited valuable time period. They must have the ability to
work as a team otherwise they could not meet the target within the allocated time. There may
be conflicts between the different subcontractors about the construction work those should be
solved by engineers to finish the construction within the limited period. These things can be
easily learnt from the industrial training period.
Twenty-two weeks were allocated for our Industrial Training programme. Within that duration
learning everything about the construction was not possible. Because of this reason a trainee
might got the chance only to learn a part of the construction. Normally one particular work is
repeated even for several months .Hence just increase the training period will not be the
solution for the above problem. Therefore it is better if the trainees can be changed
themselves to the other sites of the same organization where other part of the construction is
going on with the aid of the University and NAITA.
The Department of Civil Engineering from University of Moratuwa allocated a staff member
for each and every student during the training period. Therefore the trainee gets supervised by
Department of Civil Engineering
115
Industrial Training
Maga Engineering (pte)Ltd
that staff member every month and he/she has the chance to speak about their problems
related to their training programme with the staff member.
This type of supervision really motivated us to finish the training successfully.
I feel sad to say ,that in our site mainly road site, most of the staffs were not really
worried about the trainees whether the trainees have got or learnt anything from their training
period. They only aimed on the work that we were done for them and they only wanted to
finish those work in time. In our sites they have not any special programme for trainees we
have to work as a technical officer or sometimes even as a labourer. If the organisation have a
defined programme for trainees, that really will guide the trainees in their learning procedure.
During our training period we were work with several trainees from other institutions.
Their training period is more than two years. But our training period is only twenty-two
weeks. Therefore we have to learn everything within twenty-two weeks. Therefore we have to
work hard in our training period. Otherwise they will defeat us.
Finally I wish to thank the whole staff of University of Moratuwa and
to the staff of NAITA.
116
CONTENTS
1.0 INTRODUCTION...............................................................................................................1
1.1 ABOUT THE ORGANIZATION..................................................................................59
1.2 ON GOING PROJECTS................................................................................................59
2.0 ABOUT THE LSP (BUILDING SITE) ORGANIZATION..............................................60
2.1 ABOUT THE SITE DETAILS.......................................................................................60
2.2 THE ORGANIZATION CHART...................................................................................61
2.3
JOB FUNCTIONS....................................................................................................63
3.2
TIME OF REMOVAL..............................................................................................66
4.0 REINFORCEMENT.........................................................................................................69
4.1 INDICATION OF REINFORCEMENT IN DRAWING..............................................69
4.2 COVER BLOCKS........................................................................................................70
4.3 BAR BENDING WORK..............................................................................................70
4.4 PLACING OF REINFORCEMENT.............................................................................70
5.0 CONCRETE......................................................................................................................71
5.1 GRADE OF CONCRETE..............................................................................................71
5.2 CHECKS BEFORE CONCRETING.............................................................................72
5.3 TEST FOR CONCRTE..................................................................................................73
5.3.1 SLUMP TEST..........................................................................................................73
5.3.2 CUBE TEST............................................................................................................74
5.4 CONCRETING..............................................................................................................75
5.4.1 PLACING OF CONCRETE....................................................................................76
5.4.2 TRANSPORTATION OF CONCRETE...................................................................76
5.4.3
COMPACTION OF CONCRETE....................................................................76
5.5 Curing.............................................................................................................................79
6.0 MASONRY WORK...........................................................................................................80
6.1
6.1.1
MASONRY ITEMS.................................................................................................80
BRICKS AND BLOCKS..................................................................................80
II
6.1.2.
MORTAR..........................................................................................................81
6.2 BOND.............................................................................................................................82
6.2.1 NEEDS FOR PROPER BONDING........................................................................82
6.2.2
6.3
WALL CONSTRUCTION........................................................................................86
6.4
Lintel............................................................................................................................87
8.0 TILING...............................................................................................................................90
8.1 WALL TILES..................................................................................................................90
8.2
TILE CUTTING.......................................................................................................90
MAP STUDY............................................................................................................95
11.2
RECONNAISSANCE SURVEYS............................................................................95
12.3
SUB GRADE............................................................................................................98
III
SUB BASE................................................................................................................99
PRIME COAT.........................................................................................................102
BACKHOE.............................................................................................................106
13.3
FACE SHOVEL......................................................................................................106
13.4
MOTOR GRADER.................................................................................................107
13.5
SAFETY PROCEDURES.......................................................................................114
17.0 CONCLUSION..............................................................................................................115
IV
LIST OF FIGURES
Figure :2.1
Figure : 3.1
Figure : 6.1
Brick shape........................................................................................................80
Figure: 6.2
Types of blocks...................................................................................................81
Figure : 6.3
Figure : 6.4
Stretching bond..................................................................................................83
Figure : 6.5
Heading bond...................................................................................................84
Figure : 6.6
English bond......................................................................................................84
Figure : 6.7
Flemish bond.....................................................................................................85
Figure : 5.7
Flemish bond....................................................................................................85
Figure : 6.8
Figure : 6.9
Construction of wall..........................................................................................86
Figure: 6.10
Lintel arrangement...........................................................................................87
Figure : 9.1
Figure :12.1
Cross section.....................................................................................................97
Figure : 14.1
LIST OF TABLES
Table: 6.2
VI