Sunteți pe pagina 1din 14

National Institute of Construction Management and Research,

Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT

ASSIGNMENT
COURSE NO

PGCM 13

COURSE TITLE

MATERIALS & EQUIPMENT MANAGEMENT

ASSIGNMENT NO

DATE OF DISPATCH

25/11/2014

LAST OF ASSIGNMENT
AT CODE OFFICE

05/12/2014

SUBMITTED BY:

K UDHAYA SANKER
REG NO: 214-08-11-50127-2161

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT

ASSIGNMENT
1. Your company has been awarded a contract of developing and construction a new
International air port 30 KM from a city. You have been appointed as Planning Engineer.
Project is to be implemented in phases. In phase I, one strip of landing 100 m width is to be
constructed in 100 days.
The scope of work is as follows:
(a) Cutting and dozing of 1, 00,000 cum of earth. Average height is 0.75 m.
(b) Transportation of 20,000 cum of surplus earth from site to dumping ground 3 KM
away from site. Filling of 80,000cum of earth.
(c) Bringing of 20,000 cum of sand from 20 KM (including of spreading and
leveling).
(d) Procurement of 1,50,000 liters of bitumen. Duration of work 30 days from the
60th day of starting work. Lead time for the procurement of bitumen is 45 days.
Storage facility of 50,000 litres at site.
2. Estimate total cost of work and your plan of:
(a) Equipment planning procurement and development.
(b) Ordering and replenishing of Bitumen.

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT

INTRODUCTION of Construction equipments


Construction equipments are one of the very important resources of modern-day
construction, especially in infrastructure projects. Such projects utilize equipments for most
of the works including earthmoving operations, aggregate production, concrete production
and its placement, and so on. In fact, one cannot think of any major construction activity
without the involvement of construction equipment. There are different types of construction
equipments suitable for different activities in a construction project. The choice of
construction equipment defines the construction method, which in a way leads to the
determination of time and cost for the project. In order to select the right equipment to
perform a specific task at the least cost, it is essential to know the features of construction
equipment including its rate of production and the associated cost to operate the equipment.
For a contractor, the decision to employ a particular type of equipment is influenced by the
contract he enters with the owners, the site condition and the location of the project site.
Specifications indicating the capabilities and the different features of construction equipments
are provided by manufacturers.
The factors to be considered for the selection of some important construction
equipment have been discussed. An effort has also been made in here to cover topics such as
financial issues involved in purchase of equipment, issues involved in choosing an
equipment, accounting for assets generated, and considerations in computation of
depreciation of equipment. Certain aspects of implications of the above factors on tax
calculation are also covered.

FACTORS BEHIND THE SELECTION OF CONSTRUCTION


EQUIPMENTS

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
The selection of the appropriate construction equipment is an important part of job
planning. The contractor has many different options to choose from, which makes the
selection even more complicated. A planner has to choose the alternative that provides the
best value from a cost and schedule perspective.
Selection of equipment for construction projects generally involves two classes of
factors or considerations-hard factors and soft factors. Examples of hard factors include
technical specifications of the equipment, physical dimensions of the site and constructed
facility, and cost calculations. As can be noticed, hard factors are tangible in nature. On the
other hand, soft factors are mostly intangible, qualitative and informal in nature. Some
examples of soft factors are safety considerations, company policies regarding purchase/
rental, market fluctuations and environmental constraints. The soft factors influence decisionmaking to a large extent.
In the following paragraphs, we discuss some of the factors that govern the
equipment-selection decision. It may be difficult to come up with a set of decision variables
that are applicable for the selection of all types of equipments used in construction, and
hence, only a few common decision variables are discussed.
Economic Considerations
The economic considerations such as owning costs, operating labour costs and
operating fuel costs of equipment are most important in selection of equipment. Besides, the
resale value, the replacement costs of existing equipment, and the salvage value associated
with the equipment are also important.
Company-specific
The selection of Equipment by a company may be governed by its policy on owning'
or renting': While emphasis on 'owning' may result in purchase of equipment keeping in
mind the future requirement of projects. The emphasis on 'renting' may lead to putting too
much focus on short-term benefits. This may explain the situation of a construction company
opting for two 30 m3/h batching plant owned by the company and currently idle, instead of

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
the required one 45 m3/h batching plant that it can get on rent. It is clear that the company
wants to deal with the 30 m3/h batching plant keeping future projects in mind, even though
going for the 45 m3/h batching plant option at present may have been economical.
Further, if the company project forecast says that there will be considerable number of
projects involving a particular type of construction equipment, say X, for the next couple of
years, then the decision would be to buy only this type of equipment. Construction Company
specializing in a particular type of construction, such as tunneling, will have a tendency to
procure only those equipments that are used in tunnel construction. The equipment-selection
decision also depends on the amount of outsourcing the company does to execute its projects.
A company opting to subcontract a majority of their project work will tend to keep low
equipment asset.
Site-specific
Site conditions-both ground conditions as well as climatic conditions may affect the
equipment selection decision. For example, the soil and profile of a site may dictate whether
to go for crawler-mounted equipment or wheel-mounted equipment. If there is a power line at
or in the vicinity of site, one may go for a fixed-base kind of equipment rather than a mobile
kind of equipment. Similarly, climatic conditions such as the presence of strong winds,
visibility level and noise level may affect equipment-selection decision. Further, the access
leading to the site may also affect the decision. Heavy traffic congestion near a site may lead
to a decision to produce the concrete at site and, hence, selecting a concrete batching plant
rather than relying on ready mix concrete. Similarly, if there is only a narrow road leading to
the site, it may have a bearing on type of transportation equipment selected for the site.
Equipment-specific
Construction equipments conic with high price tags. While it may be tempting to go
for the equipment with low initial price, it is preferable to opt for standard equipments. Such
equipments are manufactured in large numbers by the manufacturers, and their spare parts are

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
easily available, which would ensure minimum downtime. Besides, they can also fetch good
salvage money at the time of their disposal.
It is a general tendency to go for such equipments that can bring in 'uniformity' in the
type of equipments that are already available with the company. For example, a company
would like to go for a uniform type of engines for different machines such as excavators,
dumpers and tractors.
The size of equipment selected is also an important consideration. Although the unit
production cost may be cheaper for equipments of large size, it is also true that large
equipments require correspondingly larger sizes of matching equipments. Thus, downtime in
one primary unit may lead to downtime in dependent equipments also trade-off between unit
production costs versus size must be obtained and as far as possible, equipments of similar
sizes should be selected for the project.
Besides the above factors, the versatility (whether it can perform more than one
function) of equipment, the adaptability for future use, the past experience with the
equipment, and the interaction with other equipments are also to he noted.
Client and Project-specific
The owner/client in a certain project may have certain preferences that are not in line
with the construction company's preferred policies as far as equipment procurement is
concerned. The schedule, quality and safety requirements demanded of a particular project
may in some cases force the company to yield to the demands of the client.
Manufacturer-specific
A construction company may prefer to buy equipment from the same manufacturer
again and again and that too from a specific dealer. This may be to bring in uniformity in the
equipment fleet possessed by the company or because the company is familiar with the
working style of the manufacturer and the dealer. Long association may not only result in

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
cheaper price, but it also ensures prompt services by the manufacturer with regard to the
company.
Labour Consideration
Shortage of manpower in some situations may lead to a decision in favour of
procuring equipment that is highly automated. Further, the selection of equipment may be
governed by the availability or non-availability of trained manpower. The company may not
be inclined to select some sophisticated equipment if it finds that there is limited availability
of manpower to operate the same.

Assumptions
(a) Type of equipment:

Excavator: for cutting/ excavation


Dozer for dozing
Grader: for spreading of material
Dumper: For shifting/ Hauling of material
Roller and water tanker: for compaction

(b) Working Hours

10 hours per day and max of 60 per week.

(c) Maintenance

10 hours per week per plant (one day per week)

(d) Induction period :

Three working days (for dismantling, transport, reassembly,

testing) for a lead of 100 km.


(e) Break down period considered

Four days per equipment in a month.

(f) Adequate spares and sub assemblies are available with trained maintenance staff.
(g) Key plan of the area has been prepared and the plant operators are familiar with the task at
hand.
(h) Work is being executed as per the Key plan.

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
(i) Plant operators are experienced are capable of achieving the planned output.
(j) No disruptions have been considered for reasons of inclement weather / other factors.
(k) Plant/equipment as planned will be available.
(l) Will take equipments for rent. Then rent amount per hour includes the diesel consumption
and maintenance cost

COST ANALYSIS
1. Excavation of 100000 cum soil.
Consider 3 no. of excavators 0.9 cum bucket capacity @ 60 cum per Hour
Output 3 excavators (10 Hrs working)

= 1800 cum/day

Total duration required to excavate 100000 cum soil

= 56 days

Assume cost of operation of excavator @ Rs 1850 per Hour


Total cost for excavation of 100000 cum soil

= Rs 31.08 L

2. Dozing of excavated material


Consider 4 nos. of Dozer, 80HP @ 40 cum per Hour
Output 4 Dozers (10 Hrs working)

= 1600 cum/ day

Total duration required to excavate 100000 cum soil

= 63 working days

Assume cost of operation of Dozer @ Rs 1200 per Hour


Total cost for dozing 100000 cum soil

= Rs 30.24 L

3. Shifting of 20000 cum soil 3Kms away


Consider 8 no. of dumpers to execute this work
Capacity
Cycle time for a single trip

= 10 cum/ Trip

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
Loading of material

= 15 min.

Forward journey with loaded material

= 10 min

Unloading of material

= 5 min.

Return journey

= 10 min.

Total duration required for single trip

= 40 min

Total number of trip in a day (10 Hr working)

= 15 nos.

Total Output of 8 dumpers per day

= 1200 cum

Total duration required to shift 20000 cum

= 17 working days

Assume cost of operation of transportation of material @ Rs 650 per hour


Total cost of hauling of 20000 cum soil for 3 Km lead

= 80 x 17 x 650
= Rs 8.84 L

4. Shifting of 20000 cum sand from 20Km away


Consider 8 no. of dumpers to execute this work
Capacity

= 10 cum

Cycle time for a single trip


Loading of material

= 15 min.

Forward journey with loaded material

= 30 min

Unloading of material

= 5 min.

Return journey

= 30 min.

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
Total duration required for single trip

= 90 min

Total number of trip in a day (10 Hr working)

= 7 nos.

Total Output of 8 dumpers per day

= 560 cum

Total duration required to shift 20000 cum

= 36 working days

Assume cost of operation of transportation of material @ Rs 650 per hour


Total cost of hauling of 20000 cum sand for 20 Km lead= 80 x 36 x 650
= Rs 18.72 L
5. Spreading of 80000cum soil and 20000cum Sand
Consider 3 nos. Motor Grader110 HP, 80 cum per Hour
Output of 3 graders (10 Hrs working)

= 2400 cum per day

Total duration required

= 42 working days

Assume cost of operation of grader @ Rs 1100 per Hour


Total cost for spreading 100000 cum material

= Rs 13.86 L

6. Compaction
Consider 2 nos. Vibratory road roller 8-10 tonne capacity, 100 cum per Hour and
2 nos. water tanker 6 KL capacity
Output of 2 rollers (10 Hrs working)

= 2000 cum per day

Total duration required

= 50 working days

Assume cost of operation of roller @ Rs 1000 per Hour and operational cost for water
tanker @ Rs. 1600 per day
Total cost for compacting 100000 cum material (Roller + Water tanker)

10

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT

11

= Rs 10.80 L
SUMMARY OF EQUIPMENTS REQUIRED AND COST ESTIMATE
Sl.
No.
1

Activity

Dozing of 100000 cum soil

Shifting of 20000 cum

Excavation of 100000 cum


soil

Equipment
planned
Excavator 0.90
cum bucket- 3
nos.
Dozer, 80HP- 4
nos.
Dumper- 8 nos.

Unit cost of
Operation
Rs. 1850 per Hour

Total estimated
cost
Rs. 31.08 L

Rs. 1200 per Hour

Rs. 30.24 L

Rs 650 per hour

Rs. 8.84 L

Dumper- 8 nos.

Rs 650 per hour

Rs. 18.72 L

surplus soil 3Kms away


4
5
6

Shifting of 20000 cum sand


from 20Kms distance
Spreading of 80000 cum soil
and 20000 cum sand
Compaction of 100000 cum
material

Motor Grader,
Rs. 1100 per Hour
110 HP- 3 nos.
a)Vibratory roller,
a) Rs. 1000
8-10 T capacity-2
per Hour
nos.
b) Rs 1600
b) Water tanker- 2
per day
nos., 6 KL cap.
Total
estimated
cost

Rs. 13.86 L
Rs. 10.80 L

Rs. 113.54 L

PROCUREMENT OF BITUMEN
a. Lead time
As the name implies, it is the period elapses between the point of time when the need
for material is contemplated & the point of time the material actually available on the
site of construction for use.
It comprises time required for:-

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
1) Users intimation to the materials manage department regarding the time &
quantity of material required.
2) Materials management to decide that the materials purchased.
3) Selecting the source, fixing the price & ultimately placing the order.
4) To deliver the material.
5) Transportation & receiving the material including inspection & testing of material
if necessary.
b. Safety level
From the users point of view, the problem arises due to following factors1) The lead time in purchase is uncertain & if it delayed it will result in stoppage of
work.
2) There may be unexpected shortage due to scarcity (or total non-availability) of
material or some unexpected difficulties in transportation.
3) The continuously rising prices & small quantities purchased frequently may make
the Materials costlier.
So, if the user will overcome all these problems then & then only he will be in
safety level.

12

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT

13

In this case of bitumen, from the time the order is placed, it takes 45 days for the material to
reach the site. Hence, the order for the material is to be placed a minimum of 45 days before
the requirement for use actually comes up.

We will consider the case in detail:


i.
ii.
iii.
iv.
v.
vi.
vii.
viii.

Bitumen required from 60th day after work commencement.


Lead time 45 days.
Total Requirement 1, 50,000 liters.
Storage capacity 50,000 liters.
No of orders to be placed minimum three each of 50,000 liters bitumen.
First order to be placed on 15th day of work.
Material reaches site on 60th day of work.
Average rate of consumption of bitumen 5000 ltrs per day. Second order to be placed

ix.
x.

on 25th day of work.


Order materializes on 70th day of work.
Similarly third order to be placed on 35th day of work and order materialises on 80th

xi.

day of work.
Work is completed on 90th day after commencement.

Day from

Opening

Order

Order

Total

Consumed

Closing

beginning
15
25

stock
0
0

placed
50000
50000

stock
-

National Institute of Construction Management and Research,


Pune
SCHOOL OF DISTANCE
EDUCATION
ASSIGNMENT ON MATERIAL & EQUIPMENT
MANAGEMENT
35
60
69
70
79
80
89

0
0
5000
0
5000
0
5000

50000
-

50000
50000
50000
Work complete

50000
5000
50000
5000
50000
5000

5000
5000
5000
5000
5000
5000

45000
45000
45000
-

CONCLUSION
Thus the total cost of the project is calculated as per todays schedule of rates. It may vary
depends on time of execution. Planning and selection of equipments for the above project is
done exactly to achieve maximum results.

BIBLOGRAPHY/ READINGS
1. Dr. B. S. Patil, construction equipments & planning.
2. Lesson books, NICMAR, NCP 24 & NCP 25.

14

S-ar putea să vă placă și