Documente Academic
Documente Profesional
Documente Cultură
S. No.
PARTICULARS
SCOPE
STANDARDS
MANUFACTURING PROCESS
QUALITY ASSURANCE
TESTING
10
11
12
13
14
15
16
ABSOLUTE GUARANTEES
Annexure-I
1.0 SCOPE
1.1
Scope includes manufacture, testing before dispatch and delivery FOR destination of
66 KV XLPE Power cable of size 1200mm2 as per BOQ conforming to IS 7098 for
66kV cable work of LILO of one circuit of 66kV Sector 23- Dhundahera line at
proposed 220kV s/stn. Sector 20 enroute proposed 66kV s/stn. HSIDC Udhog Vihar
(3.91kms) and LILO of one circuit of Daultabad- Sector 9 line at proposed 66kV s/stn.
Sector 4 Gurgaon (3.47kms).
2.0 STANDARDS:
2.1 Unless otherwise stated hereafter, rating, characteristics, test and procedures etc.
concerning the 66kV XLPE cable shall be preferably as per IS, IEC standards given
below and shall be in compliance with the latest edition or revisions thereof and
meeting the constructional details and testing requirement as stipulated in foregoing
also.
IEC-60228
IEC-60229
IEC-60230
IEC-60270
IEC-60287-1-1
IEC-60502
IEC- 60840
IEC-62067
BIS: 7098 (Part-3)
IEEE:48
2.2 The 66 KV XLPE cable may conform to any other authorities standards, which
ensures an equal or better quality than the standard mentioned above. The bidder
must specifically indicate the standards to which the cable conforms and indicate all
deviations (if any) from the preferred IS/ IEC codes that affect performance and rating.
2.3 Compliance of the 66 KV XLPE cable manufactured with the provisions of this
specification does not relieve him of the responsibility of furnishing 66 KV XLPE cable
and accessories of proper design, electrically and mechanically suited to meet the
operating guarantees at the specified service conditions.
2.4 If there are, in the opinion of the bidder, any conflicts between these codes and this
specification, these contradictions shall be brought to the attention of the owner.
3.0 CLIMATIC CONDITIONS AND LAYING CONDITIONS
The XLPE Power cable shall be suitable for continuous & satisfactory operation under
following conditions:Page-1
50oC
40oC.
(-) 5 oC.
55 oC
100%
10%
40
100
10 to 100 cm
4 months
100 kg/Sq.mm
1000 M
35o C
ii)
90o C
iii)
Air temperature
50o C
iv)
1.5 m. approx.
v)
Formation
vi)
vii)
viii)
5.1.2 The minimum number of wires in conductor and D.C. resistance shall be as per tableII of IEC-60228 / IS: 8130. The grade and quality of the Aluminium used for the
conductor shall be as per IEC/IS standard.
5.1.3 The material & nominal area of conductor shall be as per BOQ.
5.2
Conductor Screen:
5.2.1 The conductor screen consisting of semi conducting compound layer shall be
provided over the conductor by extrusion which will not only eliminate the risk of
electric discharge at the interface between conductor and insulation but will also
present a very smooth protrusion free interface with the insulation to eliminate any
localized stress concentration. The screen shall be firmly bonded to XLPE
insulation.
5.2.2 The minimum thickness of extruded conductor screen shall be 1.0 mm. The outer
surface of the conductor screen shall be circular and free from irregularities. A nonhygroscopic semi-conducting tape, if required, shall be applied to the conductor
under extruded layer to prevent penetration of compound in to the conductor
interstices.
5.3
Insulation:-
5.3.1 The insulation composed of a special super clean grade layer of cross linked
polyethylene (XLPE) shall comply with the requirement of IS-7098(Part-III)/ IEC. The
insulation shall be applied by extrusion over the conductor screen and vulcanized
using dry curing process to form a compact homogeneous body free from micro
voids and contaminants.
5.3.2 The eccentricity of insulation should not be more than 10%.
5.4
Insulation Screening:
5.4.1 The insulation screening shall consist of two parts, namely, non-metallic and
metallic.
5.4.2 Non-Metallic Part (extrusion):5.4.2.1 A non-metallic insulation screen of semi-conducting compound similar to conductor
screen (clause 5.2) for similar purpose shall be applied directly over the insulation
core by extrusion and shall be continuous and cover whole surface area of
insulation. It shall be firmly bonded to the insulation.
5.4.2.2 The minimum thickness of extruded insulation screen layer shall be 0.8 mm, the
ovality of the core shall be not more than 5%.
5.4.3
5.4.3.2
The semi conducting compound and the semi conducting tape shall be
compatible with the insulating material and suitable for the operating
temperature of the cable.
5.4.4
Metallic Part Radial Water Barrier:The metallic sheath of Aluminium sheath or Lead alloy E shall be provided over
the non-metallic part of the insulation screening. Metallic sheath, together with
copper screen (if required) shall be able to withstand short circuit current of
31.5 kA for duration of 1 second for 66 kV system. The details of metallic
sheaths are as under:
5.4.4.1
i)
The lead alloy sheath shall have composition as per IS: 692. The lead alloy E
Sheath shall be extruded using a continuous screw press and shall be free from
all extrusion defects. The nominal thickness of lead alloy E sheath shall be as
per IEC-60502-2 / IS: 7098 (Part-3).
The bedding over the Metallic sheath shall be of semi-conducting tape(s)
Copper wire screen of annealed plain copper wires with gap shall be Helically
applied over the Radial Water Barrier lead alloy metallic sheath.
ii)
An open helix copper tape binder shall be applied over the copper wire screen.
The nominal thickness of the tape shall not be less than 0.1 mm. The minimum
thickness shall not fall below the nominal value by more than 10%. Suitable
non-metallic binder tape may also be applied over the copper screen to prevent
the penetration of the outer sheath in to the screen.
5.4.4.2
ii)
5.5
Outer Sheath:-
5.5.1
The outer sheath shall consist of an extruded layer of black, PE or PVC type
ST-2 as per IEC/IS-7098 (Part-3)
5.5.2
The nominal thickness of outer sheath shall not be less than the value
calculated as per the recommendation of IEC 60502-2/IS-7098 (Part-3). The
outer sheath shall be of sufficient hardness to discourage termite and rodent
attack.
Page-5
5.5.3
6.0
6.1
The cable jointing accessories shall include the end terminating kits, straight
through joints. These shall be rated for 31.5KA for 66 kV system. The sheath
voltage under full load conditions shall not exceed 65V specified / allowed in
relevant standards for safety of personal as well satisfactory working of cable.
The sheath shall be solidly grounded.
6.2
The cable terminations shall be fire resistant. The components of kits shall have
flame retardant property.
6.3
All the cable sealing end/end termination kits and straight through joints shall be
either pre-molded or Heat shrinkable type upto 66kV level complete with
accessories from reputed manufacturer of proven design which has already
been extensively used and fully type tested. The make of termination kits and
straight through joints shall be got approved from HVPNL before bringing in
use.
6.4
The joint shall preferably be built up from the same material as the main cable
and shall have electrical and mechanical withstand capabilities same as or
better than the main cable. The joints shall be suitable for tropical climatic
conditions. The straight through joints shall be suitable for underground buried
installation with incorporated back fill and chances of flooding by water. The
straight through joints should be absolutely impervious to the entry of water.
The manufacturer shall use the proven technology and design to prevent entry
of water or any other liquid inside the straight through joints and cables.
6.5
The end termination shall be outdoor anti-fog type and shall be of porcelain
type with accessories. The outdoor terminal should be suitable for heavily
polluted atmospheric conditions with minimum creepage distance of 25 mm/kV
and protected creepage distance of not more than 50% of the total creepage
distance. The cable end terminals for terminating the cables shall be fully
compatible with the cables to be supplied. Field tests of sealing end terminals
shall be made in conjunction with the cables after installation of the cables and
terminals.
6.6
The testing of cable termination, sealing ends and straight through joints shall
be as per IEC-62067. All the type tests, sample tests and routine tests shall be
as per IEC-62067.
6.7
The cable termination and straight through joints shall bear guarantee for five
(5) years from the date of commissioning. Any defect noticed in the kit shall be
attended by the bidder immediately but not later than 24 hours on getting the
complaints and if required shall be replaced and installed free of cost, otherwise
the same will be arranged at the bidders risk and cost.
Page-6
7.0
MANUFACTURING PROCESS:
7.1
7.2
The conductor screen, insulation and insulation screen shall be extruded in one
simultaneous triple extrusion process (Clause 14.2.1 of IS: 7098-3) through
common triple crosshead. The extruders and triple crosshead shall be
designed to prevent stagnation of materials to eliminate hot spots and ensure
smoothness of the conductor screen and screen surfaces. Insulation thickness
should be controlled on-line using X-ray monitoring system.
7.3
The cross linking, curing and cooling shall be carried out in one operation and
shall be a dry curing process under high pressure to eliminate the formation of
voids in the insulation and contaminations in the dielectric.
7.4
7.5
7.6
8.0
QUALITY ASSURANCE:-
8.1
Raw materials used for manufacture of cable shall be of highest quality and
material received by manufacturer should be checked / tested to ensure that it
meets manufacturers material specification. The materials shall be clean and
packed in moisture and dust proof packing.
8.2
As the Quality control of EHV XLPE cables while manufacturing is very critical
so expert supervision is required for raw material testing, in process checks and
also for final testing. A specially trained quality assurance team should be in
place for maintenance of the quality at an optimum level at the plant. Complete
details of manufacturing process along with details of automatic manufacturing
plant, shall be furnished by bidder in the bid.
8.3
Page-7
9.0
9.1
9.1.1
TESTING:GENERAL:This schedule gives tests to be carried out on 66 KV, single core XLPE type
cables. The schedule of tests to be followed shall be generally as per IS7098(Part-3)/ IEC 62067/ IEC-60840 (For 66 KV cable).
9.1.2
The facilities available for site tests shall be clearly and implicitly brought out in
the Bid. The site tests shall be carried out during and after laying/installation by
the supplier.
9.1.3
This test schedule can be modified at the discretion of the purchaser to omit or
to include additional tests. Power frequency test shall be carried out at a
frequency of 50 Hz.
10.0
10.1
TESTS AT MANUFACTURES WORKS:The tests shall be carried out in accordance with IS-7098(Part-3)/ IEC62067/
IEC-60840 (For 66 KV cable).
10.2
10.3
10.4
10.4.1
TYPE TEST(s):The cables offered should be fully type tested. Type test reports (not more than
seven years old reckoned from the date of bid opening in respect of all the type
tests carried out as per relevant IEC/ IS standards from Govt./ Govt. approved
reputed test house shall be submitted along with the bid.
10.4.2
The bidder must have all testing facilities available at their works for testing the
material as per clause 8 above. Detailed list of testing equipment along with
relevant tests must be furnished with the tender other wise offers is likely to be
ignored.
11.0
11.1
MARKING ON OUTER SHEATH:The following particulars shall be marked on cable outer sheath:
Manufacturers name/ or trade name
Voltage grade viz. 38/66 KV.
Cable size ( no. of core x conductor cross section)
Year of manufacture.
Purchasers name i.e. HVPNL
Page-8
11.2
The spacing between one set of marking and the beginning of the next on the
legend shall not exceed 150 mm.
11.3
12.0
12.1
Immediately after the works tests, both ends of every length of cable shall be
sealed by means of heat shrinkable end caps.
12.2
Cables shall be wound on metallic drums. All the drums shall be arranged to
take a round spindle and be legged with strong closely fitting wooden battens
so as to prevent damage in the cable. Each drum shall bear an identification
number permanently stenciled or branded on the outside of the flange.
12.3
12.4
13.1
14.0
14.1
15.0
15.1
The bidder shall furnish guaranteed technical particulars of cable in the relevant
schedule enclosed
16.0
ABSOLUTE GUARANTEES:-
16.1
16.2
Annexure - I
DESIRED TECHNICAL PARTICULARS OF 66 KV XLPE CABLE
S. No.
Particulars
Technical Details
Cable
Applicable standard
1.
2.
3.
4.
5.
i)
ii)
iii)
iv)
v)
Page-10
6.
i)
CONDUCTOR SCREENING
Material & type
ii)
iii)
7.
i)
Grade
Thickness
INSULATION
Material
ii)
8.
A
INSULATION SCREENING
Non-metallic part(extruded)
Material
i)
ii)
iii)
i)
ii)
C
i)
ii)
iii)
D
E
Grade
Min. thickness.
Non-metallic part (taped)
longitudinal water barrier over
insulation screen.
Material
Min. thickness
METALLIC SHEATH
Material
Min. Thickness(mm)
Short Circuit Current Withstand
[Metallic sheath, together with
copper screen (if required)]
Bedding over lead sheath
CONCENTRIC COPPER WIRE
SCREEN (IF REQUIRED)
Material and type
i)
Min. area (Sq. mm)
ii)
9.
OUTER SHEATH
Material
i)
ii)
10.
11.
12.
13.
14.
15.
16.
i)
ii)
17.
18.
19.
20.
21.
Recommended minimum
installation radius.
Maximum D.C. Resistance of
conductor at 90 deg C in ohm/km.
Continuous current rating for each
circuit when laid in ground in trefoil
formation and other condition
given in specification.
Maximum allowable temperature
for cable and accessories.
At rated full load and at site
conditions.
The conductor temperature after a
short circuit for one second shall
not exceed (with conductor
temperature at start of short
circuits as 900 C).
Basic impulse insulation level
(1.2/50 micro second wave)
Power frequency withstand voltage
Symmetrical Short circuit rating for
one second duration for lead
sheath and copper screened
combined/ Aluminium Sheath
Drum Length
Expected cable life.
To be indicated
As per standard
To be indicated
90 Deg C
250 Deg C
As per Standard
As per Standard
31.5 kA for 1 Sec.
Page-12
PARTICULARS
SCOPE
ROUTE SURVEY
STATUTORY CLEARANCES
CABLE HANDLING
DAMAGE TO PROPERTY
SAND BEDDING
10
BACK FILLING
11
WARNING TAPE
12
13
14
15
JOINTING BAY
16
17
BENDING RADIUS
18
19
SUMPHOLES
20
TENTS/ COVERS
21
22
23
IDENTIFICATION
24
MAKING A JOINT
25
CABLE TERMINATIONS
26
27
EARTHING
28
ERECTION PART
Scope: Complete installation, laying, testing and commissioning of the cable of the D/C lines shall
be the responsibility of the bidder. Four runs of the cable per circuit shall be laid as per
the tentative route plan enclosed. The scope for installation work shall, therefore include,
but not limiting to: 1. Route survey for the entire route length under the scope of work.
2. Clearances from relevant Local Authorities for laying of cables. All the protective
measures for laying, protection and for smooth working of all the cables as per statuary
norms/standards to be followed/ensured by the bidder for its safe and smooth operation
in future.
3. Laying of cables under scope as per specification. At most of the route length, the
cables shall be laid through Trench-less technology at depth of 2.5m to 3.0m.
4. Measurement of Thermal resistivity of soil. The value of thermal resistivity will be
intimated to field office.
5. Transportation of cable drums & other material.
6. All civil works required for laying of the cables, which shall include design, construction
materials and labours. Manholes shall be provided at every proposed joint location for
jointing bays. The bidder shall identify the location of the joint bays after carrying out
detailed survey of the cable route and excavation of the trial pits. The delivery lengths of
the cables shall match the location.
7. Laying & installation of cables in ducts, in HDPE pipes and through Trench less method of
required strength for various crossings, in air at terminations at the tower, at varying
depths due to obstructions, construction of cable jointing bays.
8. Supply of HDPE pipe of required strength of ISI mark shall be 1.5 times of Cable. The
HDPE pipes are required for crossing of roads/ Bridge/Railways/culverts/water courses/
Nala/ Sewerage pipe lines/Oil /Gas pipe lines and for Trench-less system. The pipes to be
filled with sand/suitable material after cabling in Road crossing .
9. Supply & Erection of terminal structures including foundations between the line for
supporting cable end terminations, it shall include the supply of Earthing material,
Earthing of each cable, post insulators for cable support, civil foundation design,
construction material and labours etc.
Page-1
10.
The cables will be terminated on the cable termination structures in the s/stn. premises
and the cable will be terminated on the tower at the point of connection with Overhead line.
Where the cable is to be terminated on the tower (tower will be erected
departmentally), the LAs will have to be mounted on the tower by making suitable
arrangement and the independent earthing of LAs mounted on the tower and of each
cable shall be got done to the satisfaction of Engineer-incharge. The size of
galvanised flat to be used for earthing of LAs shall be 75X12mm.
11.
Termination of cables at both ends. Suitable loops shall be provided at both ends.
12.
It shall be the responsibility of the contractor to terminate the fourth (spare) run of the
cable at the terminal structures in such a way that it shall be possible to connect it to
all the three phases of conductor by changing jumpers only. However this spare cable
shall be connected to nearest conductor to avoid theft/moisture in-gress. Necessary
bonding of the cable screen shall be done by the supplier.
13.
Tentative Quantity of LAs shall be as per BOQ attached. The drawings of LAs shall be
got approved from HVPNL .
14.
Cable markers as per statutory requirements shall be provided all along the route at a
maximum distance of 100 meters and other important locations. Also the location of
the underground cable shall be clearly indicated on the marker.
15.
The bidder shall make his own arrangement for boarding & lodging of his men
engaged in the work.
16.
17.
18.
Erection portion. After award of contract, its Design/Drawings will be got approved
before execution of work.
19.
The design of all type of crossings is in the scope of the bidder and work
shall
be
started only after getting the design / Drawings approved from HVPNL.
2.0
Route Survey
The bidder shall fully familiarize himself with the site and route conditions etc. The
complete design and detailed engineering shall be done by the contractor. The survey
shall be conducted for underground routes to finalize the route and paths for the
underground cable. Contractor shall arrange information about existing under ground
facilities for the proposed routes. To do so as built drawings or route index diagram
for various services viz water works, electric supply utilities, telecom services, public
health, Gas/oil authorities etc. may be collected from the concerned authorities. In
case details are not available, the contractor shall assess suitably by conducting
enquiries and surveys. The contractor shall prepare and submit the final survey report
showing all the details enroute for HVPNL approval.
3.0
Statutory Clearances
The contractor shall coordinate on behalf of owner, for obtaining necessary clearances
for laying of cable and carrying out excavation/ digging work from the authorities on
behalf of the Employer and provide requisite copies of information maps, survey report
etc. to the authorities. The employer shall assist the contractor in obtaining such
clearances by providing the authority letter or any other relevant document. The
contractor shall ensure quick and speedy clearances in order to implement the project
within stipulated schedule. In case the authorities have some objections on certain
sections of routes proposed and are unwilling to provide clearances, the contractor
shall propose an alternate route, promptly carrying out the survey and submit specific
survey report for that and reapply for clearance after taking into account the
comments/objections of the authority. The clearance of the Chief Electrical inspector
under Electricity laws shall solely be in contractors scope.
4.0
CABLE HANDLING
The inspection of cable on receipt, handling of cables, paying out, flaking, cushioning
with sand or sieved compacted soil, back-filling, providing and fixing joint markers,
route indicators, and all necessary precautions that are required shall be carefully
planned and in general conform to IS 1255-1983 or its equivalent.
5.0
DAMAGE TO PROPERTY
The contractor shall take all precautions while excavation of trench, trial pits & drill for
trench-less laying etc., to protect the public and private properties and to avoid
accidental damage. Any damage so caused shall be immediately repaired and brought
to the notice of the Employer.
The contractor shall bear all responsibilities and liabilities and shall bear all costs of
the damages so caused by him or by his workman or agents.
Page-3
6.0
7.0
8.0
9.0
SAND BEDDING:
The cable shall be completely surrounded by well-compacted sand (River bed sand) to
such a thickness and of such size that the cable is protected against damage.
Precast RCC slabs in M-20 of size 500X300X65mm for 66kV and shall be provided for
protection of the cable by covering the cable as per drawing enclosed. Every pre-cast
slab shall carry the engraved words as- HVPNL 66kV.
Page-4
10.0
BACK FILLING:
Normally back filling shall consist of the material earlier excavated. However, bigger
stones or pieces of rock should be removed & shifted at approved locations of Local
Authority. The compaction of Earth filling shall be ensured by the contractor 95% of
the Proctor density.
11.0
WARNING TAPE:
A pre-warning, Red colour plastic/PVC tape, 250 mm wide 100 microns thick shall
be laid at approx. 0.4 m above the cable specified depth, throughout the cable route.
The tape shall carry the legend printed in black continuously as under CAUTION
HVPNL, 66000 V CABLES.
12.0
13.0
14.0
15.0
JOINTING BAY
Manholes shall be provided at every proposed joint location for jointing bays. The
bidder shall identify the location of the joint bays after carrying out detailed survey of
the cable route and excavation of the trial pits. The delivery lengths of the cables shall
match the location.
In case of underground portion, the joint bays should have a flat and level surface
lined with bricks and properly plastered. The retaining walls on all sides to the required
height shall be of brick/stone masonry. The top of the wall shall have a cement
concrete band 1:2:4 with 20mm size aggregate all-round. The top shall be covered
with pre-fabricated RCC slabs and with an inspection cover. Al the bottom in a corner,
a sump-pit shall be made for bailing out water.
The contractor shall submit design and drawing of Jointing bay for HVPNL approval.
All works shall be carried out under supervision of the engineer in charge or his
representative.
16.0
17.0
BENDING RADIUS:
The minimum bending radius of XLPE insulated cables are as follows:
Cable
Bending radius
Single Core
20 x D
19.0
SUMPHOLES
When jointing cables in water logged ground or under unforeseen rainy conditions, a
sumphole should be made at one end of the joint bay, in such a position so that the
accumulated water can be pumped or baled out by buckets, without causing
interference to the jointing operation.
20.0
TENTS/ COVERS
An enclosure or suitable protection cover shall be used in all circumstances wherever
jointing work is carried out in the open irrespective of the weather conditions. The joint
shall be made in dust free, moisture free and clean atmosphere.
21.0
22.0
23.0
IDENTIFICATION
The identification of each phase shall be clearly and properly noted. The cable shall be
jointed as per the approved design. Each cable shall have identification for phase at
joint bays.
24.0
MAKING A JOINT
Comprehensive jointing instructions should be obtained from the manufacturer of
jointing kits and meticulously followed.
The materials used in the joints like ferrules, screen/sheath continuity bonds, lugs etc.,
shall be of good quality and conform to standards. The jointing tools shall be
appropriate and as per the requirement of jointing HV XLPE cables.
25.0
CABLE TERMINATIONS
The preparation of the cable end for installing the terminations and the precautions to
be taken before fixing the terminations shall be followed as in the case of the cable
jointing procedures.
The instructions furnished by the termination manufacturer shall be strictly followed:
At cable terminating end, the following provisions for supply and erections are to be
included:
A sufficient length of spare cable shall be left in the ground, for future needs.
Page-7
27.0
Earthing:Bidder shall carry out the earthing of sheath/ screen at the cross bonding points as
well as at the ends of cable using insulation sheath bonding (earthing) cable of
required size through link boxes with/ without surge voltage limiter at cross-bonding
points and terminal substations. Earthing shall be as per relevant standards. The
sheath /screen shall bound in the earth station through disconnecting type link boxes.
Screen continuity by using tinned copper mesh and earth continuity by tinned copper
braids of appropriate size shall be provided for transfer of screen/earth in straight
through joints.
All the LAs to erected on the towers shall be properly earthed through 75X12mm GI
strip to the satisfaction of field office.
28.0
of
Page-8
The specification covers excavation for cable trenches, ducts, structural foundation,
jointing bays.
1.2
The contractor shall control the grading in the vicinity of all excavations so that the
surface of the ground will be properly sloped or diked to prevent surface water from
running in to the excavated area during construction.
1.3
The excavation shall include the removal of all materials required to excute the work
properly and shall be made with sufficient clearance to permit the placing, inspection
and setting of forms and completion of all works for which the excavation was done.
1.4
The sides and bottoms of excavation shall be cut sharp and true. Under cutting shall
not be permitted. Earth sides of excavations shall not be used in lieu of form work for
replacement of concrete unless authorized by the Engineer where the limititations of
space for large excavation necessitate such decision.
1.5
When machines are used for excavation th last 300 m,m before reaching the required
level shall be excavated by hand or by such equipment that will leave the soil at
required final level in its natural condition.
1.6
The bottom of the excavation shall be trimmed to the required level and when carried
below such level by error, shall be brought to level, by filling with lean concrete of 1:4:8
Mix at contractors cost.
1.7
1.8
The excavations for foundation where specified shall be carried out at least 75 mm or
as specified in relevant drawing below the bottom of the structure concrete and then
be brought to the required level by placing lean concrete of 1:4:8 mix or as specified
with aggregate of 40 mm nominal size.
1.9
When the excavation requires tracing, sheeting, shoring strutting etc. the contractor
shall submit to the Engineer in charge drawings showing arrangement and details of
proposed installation and shall obtain the approval from the Engineer in charge before
proceeding with the work.
1.10
The contractor shall have to constantly pump out the water collected in the pits,
trenches due to rain, sub soil, springs etc. and maintain dry working conditions at no
extra cost to the owner.
The contractor shall arrange to transport the surplus excavated earth by mechanical
transport. It shall however be ensured that no stacked/disposed shall be as directed
by the Engineer-in-charge.
Page-9
2.2
3.0
However the contractor shall take all precautions at the site of excavation for keeping
the free flow of vehicular and human traffic and to avoid inconvenience in general. The
soil transported for disposal shall be stacked, leveled and dressed neatly.
3.1. The backfilling of excavated trenches around foundation shall consist of one of the
following materials as the Engineer-in-charge may direct in each location.
i) Selected sieved earth from excavated soil.
ii) Selected sieved earth brought from borrows area.
iii) Sand filling (sieved).
3.2 Filling shall be done after the concrete or measonry work has fully set and its curing
completed.
3.3 The contractor shall fill in and around any work until it has been properly reinstated and
approved by the Engineer-in charge.
6.0
7.2
The concrete mix for the various types of pre-cast units shall confirm to IS: 456. The
aggregate shall be mixed by weight and water cement ratio shall be controlled to
obtain the dense concrete and the strength required. The reinforcement shall be as
per the design approved. The curing shall be carried out for the period of minimum
seven days from the date of casting and precast element shall be cured by flooding
with water of minimum 25 mm depth over the element for the period mentioned above.
All the pre-cast element shall be marked, appropriately as specified.
Page-10
8.0 FOUNDATION
Foundations for mounting structures in cement concrete shall be casted by bidder as
per approved drawings.
10.0 PAINTING
Outdoor Kisok for link boxes etc., shall be painted with anticorrovise paint and red
oxide as primer and two coats of enamel paint. The boxes should be appropriately
labeled as per installation at site regarding the S.No., location, type caution
board/danger.
13.3
Permanent and durable type, cable route markers/joint indicating blocks should be
provided as per the design approved by the purchaser.
The Reinforced cement concrete block should be made by the wet process and all the
concrete shall consists of one part cement, one and a half part sand, three parts
aggregates of size 20 mm and down.
The marking block should be given a smooth cover surface or cement mortar and shall
have the appropriate legends, 5 mm deep engraved on them as HVPNL 66 CABLE
Ckt.- I OR HVPNL 66 KV CABLE Ckt.- II, HVPNL 66 KV CABLE or as the case may
be.
Page-11
14.0 PIPES
14.1
14.2
HDPE pipes of ISI mark, of approved diameter and thickness, of good quality shall be
used for formation of cable ducts. All sundry materials like coupling, collars, and caps
to cover the pipe ends before cable is pulled in shall be provided.
The bidder shall furnish the design drawings of foundations, foundation anchor bolts,
and design calculations etc. of these structures.
15.0 SAND
15.1
15.2
Sand supplied for backfill shall be river sand, free from flakes, dust, earth, organic
matter and large pebbles and stones and should be free from any chemical
contaminats likely to have corrosive action on the cable coverings. The sand should
be sieved through a mesh to remove all large stones and pebbles. The sand shall be
properly graded and shall conform to IS:383 for concreting work.
The owner will decide on the requirement of the use of sand depending on the
availability of the excavated earth to be used for backfill. The sand should be used
with the approval of the owner as a backfill.
16.0 QUANTITIES
16.1
16.2
The quoted price shall also include supply of all material transportation charges, taxes,
duties, Octoroi and tole tax, labour, construction, plant and equipment and fixture,
fittings and all temporary and permanent works necessary for satisfactory completion
in all respects.
If the owner is directed by the Engineer in charge to excavate to a lower level than that
indicated in the drawing, such additional excavation shall not be paid for & will be
deemed to be included in the quoted rates.
Page-12
16.5
16.6
However, no extra claim shall be entertained for material not salvaged or any other
damage to contractors proper as the results of the collapse. He shall not be entitled to
any claim for redoing the excavations as a result of the same.
20.0 REINSTATEMENT
After the cables and pipes have been laid and before the trench is backfill all joints and
cable positions should be carefully plotted and preserved till such time the cable is
energized and taken over by the Engineer. The protective covers shall then be
provided, the excavated soil riddled, sieved and replaced. It is advisable to leave a
crown of earth not less than 50 mm and not more than 100 mm in the centre and
tapering towards the sides of the trench.
20.1
Page-13
20.2
After the subsidence has ceased the trench may be permanently reinstated and the
surface resorted to the best possible condition.
20.3
The road surface being cement concrete, asphalt or tarred macadam, resurfacing will
be done by the civic authorities at owners cost. The fixing of markers etc. shall be coordinated by bidder.
20.4
All works shall be carried out under supervision of the Engineer in Charge or his
representative.
Page-14
Bill of material of LILO of one circuit of 66kV Sector 23- Dhundahera line at proposed 220kV
s/stn. Sector 20 enroute proposed 66kV s/stn. HSIDC Udhog Vihar .
(Supply Portion only)
Sr. No.
Description
Unit
Total Quantity
1.
Mtrs.
3910X8
No.
16
3.
No.
No
No
Mtrs
200
No.
10
No.
Lot
11
Mtr.
3550X8
12
No.
64
12
No.
12
No.
Lot
2.
Note:1. It is specific for all the bidders to visit the office of SE/ TS, Gurgaon to see the site
constraints before finalising / submitting the bids.
2. The said work involves the route through residential area/Industrial area for which Trenchless digging shall be got done as per Technical specification.
3. The above mentioned length of cable involves the tentative loop of 100m for enrouting the
said line at proposed 66kV s/stn. HSIDC Udhog Vihar.
4. To lessen the no. of Straight through joints, the length of cable shall be judiciously
selected keeping in view the safety of the cable by the successful bidder during detailed
survey.
5. The route length / Quantities of 66kV line shown above is tentative & may vary.
Bill of material of LILO of one circuit of 66kV Sector 23- Dhundahera line at proposed 220kV
s/stn. Sector 20 enroute proposed 66kV s/stn. HSIDC Udhog Vihar .
( Erection Portion only)
Sr.
No.
1.
Description
Unit
Quantity
360
Lot
Lot
LS
Lot
3550
16
Note:1. It is specific for all the bidders to visit the office of SE/ TS, Gurgaon to see the site
constraints before finalising / submitting the bids.
2. The said work involves the route through residential area/Industrial area for which Trenchless digging shall be got done as per Technical specification.
3. The above mentioned length of cable involves the tentative loop of 100m for enrouting the
said line at proposed 66kV s/stn. HSIDC Udhog Vihar.
4. To lessen the no. of Straight through joints, the length of cable shall be judiciously
selected keeping in view the safety of the cable by the successful bidder during detailed
survey.
5. The route length / Quantities of 66kV line shown above is tentative & may vary.
Bill of material of LILO of one circuit of Daultabad- Sector 9 line at proposed 66kV s/stn.
Sector 4 Gurgaon.
(Supply Portion only)
Sr. No.
Description
Unit
Total Quantity
1.
Mtrs.
3470X8
No.
16
3.
No.
No
No
Mtrs
200
No.
10
No.
Lot
11
Mtr.
1000X8
12
No.
56
12
No.
12
No.
Lot
2.
Note:1. It is specific for all the bidders to visit the office of SE/ TS, Gurgaon to see the site
constraints before finalising / submitting the bids.
2. The said work involves the route through residential area for which Trench-less digging
shall be got done as per Technical specification.
3. To lessen the no. of Straight through joints, the length of cable shall be judiciously
selected keeping in view the safety of the cable by the successful bidder during detailed
survey.
4. The route length / Quantities of 66kV line shown above is tentative & may vary.
Bill of material of LILO of one circuit of Daultabad- Sector 9 line at proposed 66kV s/stn.
Sector 4 Gurgaon.
( Erection Portion only)
Sr.
No.
1.
Description
Unit
Quantity
2470
Lot
Lot
LS
Lot
1000
16
Note:1. It is specific for all the bidders to visit the office of SE/ TS, Gurgaon to see the site
constraints before finalising / submitting the bids.
2. The said work involves the route through residential area for which Trench-less digging
shall be got done as per Technical specification.
3. To lessen the no. of Straight through joints, the length of cable shall be judiciously
selected keeping in view the safety of the cable by the successful bidder during detailed
survey.
4. The route length / Quantities of 66kV line shown above is tentative & may vary.