Documente Academic
Documente Profesional
Documente Cultură
INTRODUCTION
After the end of WWII, sources of sulfur for manufacture of
superphosphate were limited and with the prospect of limited
supplies in the future, prices were high. This, together with a
guarantee by the Commonwealth Government to pay a subsidy if
the price of sulfur fell below a certain fixed price, the savings of
foreign exchange and the opportunity to establish a local
industry, led the South Australian Government to encourage and
sponsor the formation of Nairne Pyrites Pty Ltd (Doherty, 1978).
The company was formed in August 1951 and comprised
Wallaroo Mt Lyell Fertilizers Ltd, Adelaide Chemical and
1.
2.
6th ICARD
93
Creek and a much smaller dump on the eastern side (Figure 1).
Material containing more than five per cent sulfide was regarded
as ore and processed on site. The concentrates were transported
by road to Nairne and thence by rail to Port Adelaide where they
were converted to sulfuric acid and then superphosphate for SAs
agriculture industry. Tailings were deposited in a valley-fill
94
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
6th ICARD
seepage
rainfall
80000
1000
900
800
700
600
60000
500
400
40000
20000
300
rainfall (mm/yr)
200
100
19
7
19 5
8
19 8
8
19 9
9
19 0
9
19 1
9
19 2
9
19 3
9
19 4
9
19 5
9
19 6
9
19 7
9
19 8
9
20 9
0
20 0
0
20 1
02
seepage (kilolitres)
ENVIRONMENTAL ISSUES
95
Cover materials
Both neutralisation sludge from the plant and biosolids from
waste water treatment plants are used as part of the on-going
rehabilitation of the minesite. Both contain elevated levels of a
variety of heavy metals and concern was raised that they may act
as additional sources of contamination of water in Dawesley
Creek. PIRSA engaged Australian Water Technologies to
undertake an investigation of the use of biosolids and
neutralisation sludge to determine the potential for heavy metals
and nutrients to move off-site.
Municipal impact
Not all contamination of Dawesley Creek is attributable to the
Brukunga Mine. The headwaters of Dawesley Creek are adjacent
to the township of Woodside with discharge from its Septic
Treatment Ponds being released to the catchment. An antiquated
common septic system, built at Brukunga in 1956, enabled
effluent to overflow into Dawesley Creek leading to odour and
turbidity and surface frothing. From 2000 the town sewage was
TABLE 1
Representative water quality from mine sources (range of values shown).
Parameter
(mg/L) except pH
Mine cuts
Tailings
Dawesleys u/s
Peggy Buxton
Dawesley d/s
(KAN 2)
Waste dump
R/O and Seep
2.5
3.0
2.3
7.5
3.0
4.5
2.5
3.0
4000
8000
7000
200
1000
4000
6000
SO4
5000
10 000
8000
80
100
1000
2000
6000
9000
Fe
1000
2500
4000
1.5
10
30
200
600
Al
400
800
50
<1
25
200
700
1000
Cl
300
1500
250
400
500
100
200
Ca
200
500
450
50
60
100
300
200
300
Mg
200
500
300
40
60
50
100
200
300
Na
200
1200
200
450
300
100
400
Mn
20
40
150
0.1
5
20
30
50
Zn
30
50
15
0.005
15
20
50
pH
Acidity
96
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
Summary
An annual Environment Protection Authority site licence
established the accepted monitoring requirements in 1996 and
requires regular water monitoring and reporting, and the
development and revision of an Environmental Improvement
Program for remediation work conducted on the site. These are
discussed separately below.
MONITORING
Monitoring of various parameters falls into two categories:
ongoing and short-term/information gathering. The objectives of
an on-going water monitoring program, contained in Condition
100-1 of the EPA Site Licence No 10577, are:
1.
2.
3.
Water quality
Ecology
6th ICARD
Groundwater hydrology
The groundwater hydrology of the quarry, areas to the west and
waste rock dumps has been assessed on several occasions (AGC,
1989; EGi, 1995). Hydrology is controlled by the structural
geology of the area, which consists of competent quartzites and
metasiltstones dipping to the east at 60. There is some fracturing
and jointing at a different orientation. EGi (1995) concluded that:
97
FIG 3 - Calculated annual load of contaminants in Dawesley Creek. Note: chromium, copper and lead were not graphed because a high
number of samples are recorded as being below the detection limit of the analysis technique. Using this data can result in high calculated
loads that are not real.
98
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
7.0
6.0
5.0
M ax i mum
Lower l i mi t A NZE CC gui del i ne f or i r r i gat i on pH 4. 5
pH
4.0
A v er age
3.0
2.0
M i ni mum
Wi nt e r
Summe r
1.0
0.0
Jan
Concentration (mg/litre)
10,000
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000
0
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Nov
Dec
Summe r
Maxi mum
Aver age
Mi ni mum
Wi nt e r
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Concentration (mg/litre)
0.25
0.20
Summer
Maximum
0.15
Average
0.10
Winter
0.05
0.00
Minimum
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
FIG 4 - 2002 results against four year average Dawesley Creek as it leaves the Brukunga Mine site (a) pH, (b) sulfate and (c) cadmium.
6th ICARD
99
12.0
10.0
pH
Summe r
8.0
M axi mum
Wi nt e r
A v er age
6.0
M i ni mum
4.0
Concentration (mg/litre)
Jan
10,000
9,000
8,000
7,000
6,000
5,000
4,000
3,000
2,000
1,000
0
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Sep
Oct
Nov
Sep
Oct
Nov
Dec
Summe r
Maxi mum
Aver age
Mi ni mum
Wi nt e r
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Dec
Concentration (mg/litre)
0.25
0.20
Summer
Maximum
0.15
Average
0.10
Winter
0.05
0.00
Minimum
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Dec
FIG 5 - 2002 results against four year average Mt Barker water downstream of the Brukunga Mine site (a) pH, (b) sulfate and (c) cadmium.
100
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
FIG 6 - Dawsley Creek system-mean and standard deviation species richness six sites: 1996 - 2001.
ENVIRONMENTAL MANAGEMENT
Oxidation rates
The oxidation rates within the waste rock dumps and TSF were
determined by ANSTO (Bennett, 1994) using temperature and
pore gas oxygen concentration profiles. The results show that the
waste rock dumps are well aerated and oxidation is occurring
throughout the dumps. The calculated sulfate generation rate is
400 tonnes per annum for each dump and that this will occur for
at least another 300 years. Oxygen measurements in the tailings
indicate that oxidation is occurring in the top 3 m and the
oxidation rate is limited by the oxygen supply rate.
6th ICARD
Water collection
Acid seepage was originally collected at the toe of the TSF and
returned to a 15 ha acid lake at the top of the tailings dam, for
evaporation. The lake added to the seepage from the foot of the
dam wall and increased contaminant load. Seepage from the
mine site is collected at the base of the rock dumps, in eight
sumps along the west bank of Dawesley Creek and surface
run-off from the quarry is collected and pumped to the retention
dams. Calculations show that approximately 60 per cent of the
seepage from the minesite is collected for treatment in the
neutralisation plant, the remainder enters Dawesley Creek. To
improve interception of acid seepage, the sumps were deepened
in 2001 and probes reset to keep collection points nearer to dry.
The tweaking of seepage collection wells is ongoing and is
thought to be the main factor in the decreasing contamination
levels monitored in water leaving the mine site.
Neutralisation plant
A neutralisation plant was commissioned in September 1980 to
treat the acid seepage and to eliminate the 15 ha acid lake located
on the tailings. The design capacity of the plant is 20 kL/hour but
during periods of high flow it is operated at 30 kL/hour with a
consequent reduction in efficiency of the thickener tank. This
means that more water is pumped to the sludge holding ponds,
and more unsettled particles go the clarifying pond. Lime sludge
is obtained as a waste product from the production of industrial
acetylene gas. Lime is added at a rate to achieve a pH = 9 in the
thickener to ensure precipitation of the majority of dissolved
metals, particularly cadmium and manganese.
101
102
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
6th ICARD
erosion and to improve the aesthetics of the site. The trees have
established well in the gypsum sludge and will form a partial
screen for the exposed high foot wall of the quarry.
In May 2001, the old metallurgical plant site was spread with
imported soils, horse manure and sown to pasture grasses. In
June 2001, Urrbrae High School students planted out the area
with tube stock. Results to date have been encouraging.
An area on the east side of Dawesley Creek affected by
seepage from the retention pond was rehabilitated by installation
of a French drain and planting with eucalyptus tube-stock. A
recent application of pea-straw resulted in surrounding grass
cover and provided a boost in growth of the trees, which had
been stagnant for several years.
RESEARCH
The Brukunga minesite has been the focus of a variety of
research by post-graduate students from local universities and
ANSTO, CSIRO, AWT, and AWQC. Four major studies were
undertaken to assess the environmental impacts of the mine and
rehabilitation measures (McLaughlin and White, 1999; Schultze,
2000; Australian Water Technologies, 2000, Burtt and Gum,
2000a and b, 2001) each of which is referred to above. The study
by McLaughlin and White (1999) was in response to alleged
infertility in livestock on pasture downstream to the mine.
Because of concerns raised by some local residents for the use
of biosolids and neutralisation sludge around the site, Australian
Water Technologies were commissioned by PIRSA to examine
their impact on the environment. In particular, they were
requested to examine their erodibility, solubility and potential as
a source of heavy metals. AWT (2000) found that there is
minimal risk of any heavy metals contained in the sediments
used in rehabilitation contaminating water in Dawesley Creek.
Over time the water holding capacity of biosolids may decrease
as organic matter decomposes, which may lead to greater
erodibility.
Other research has been related to post-graduate studies or as a
contribution to larger studies such as oxidation rates in sulfidic
minewastes (Bennett, 1994) or the development of an ecological
risk assessment protocol for aquatic ecosystems (Twining, 1999,
2000). In addition to the work of ANSTO and CSIRO, there have
been numerous studies of the impact of contamination including
cadmium and zinc in soils (Nardecchia, 1997), aquatic fungi
(Wojcik, 1999; Edwards, 2000) algal esterase (Regal et al, 1999),
benthic diatoms (Sincock, 2000) and freshwater shrimp
(OBrien, 1999). Studies directed at the remediation of ARD and
minesite rehabilitation include the role of sewage sludge in
reducing ARD (Girdham, 1994), use of sulfate-reducing bacteria
to remediate ARD (Elliott, 1995), the use of a rotating biological
contactor to remediate ARD (Wilde, 1995) and the development
of hardpans/cement in mitigating ARD (Agnew, 1994, 1998).
One student (Haibo, 1994) examined the environmental
management practices at Brukunga and concluded that at the
time, they were unsatisfactory.
PIRSA is presently sponsoring three research projects: the
development of a porous reactive wall to remove contaminates
from acid water (Masters, Uni SA), ecotoxicology of the mine
site (PhD, Adelaide Uni) and the application of hyperspectral
remote sensing to AMD monitoring (PhD CSIRO).
103
2.
3.
Community consultation
The township of Brukunga is surrounded on three sides by the
123 ha minesite. Its present population is 220, most of who
commute to other centres of population for employment.
Agriculture and rural living is the main activity within the
catchment, few rely on Dawesley Creek with water sourced from
property bores and dams and roof catchment for household use.
A technical committee, the Brukunga Taskforce was
established in July 1999 in response to heightened public
concern following a directive issued by the EPA requiring
signposting, issue of notices to landowners and the publication of
warnings regarding contaminated water in Dawesley Creek. In
May 1999, the Deputy Premier and Minster for Primary
Industries, Natural Resources and Regional Development
established the Brukunga Mine Site Remediation Board
(BMSR). This Board superseded the Taskforce and is structured
to ensure strong community involvement and ownership in
decisions. Its first objective is to achieve a water quality in
Dawesley Creek that is suitable for domestic consumption, stock
and primary production purposes.
Informal liaison
104
6th ICARD
THE BRUKUNGA PYRITE MINE A FIELD LABORATORY FOR ACID ROCK DRAINAGE STUDIES
Aboriginal heritage
The mine site lies within the traditional lands of the Peramangk
Aboriginal people and Brukunga is an Aboriginal word meaning
place of hidden fire. Brukunga is highlighted in Aboriginal
mythology in the story of Tjirbrukes travels and on his death his
body became the hill of iron pyrites (Harris 2002).
COSTS
The cost for operating the plant (neutralisation plant, sumps, sump
pumps) and maintaining the 123 ha Brukunga site for 2001 - 2002
was $650 000. This included salaries of two site personnel and
engineering support ($150 000), EPA licence ($12 900), water
monitoring program ($67 300), power consumption ($25 200),
waste lime and flocculant ($77 800), neutralisation sludge
relocation ($85 700) and overall maintenance ($205 300).
CONCLUSIONS
The Brukunga Pyrite Mine operated when little was understood
about the environmental impacts of AMD. Consequently, mine
planning, operations and decommissioning resulted in a number
of environmental issues which contributed to acid generation and
contamination of Dawesley Creek. Over a period of nearly three
decades, State Government departments have undertaken a
variety of measures to reduce the impact of AMD on Dawesley
Creek, with apparent positive outcomes. Recently, with the
assistance of the community, more effective measures have been
developed and a diversion channel is under construction.
ACKNOWLEDGEMENTS
Primary Industries and Resources SA provided much of the
information for this paper and gave permission for its
publication. Peter Grindley has continued to collect and maintain
data about the mine, wastes and Dawesley Creek. His knowledge
has been invaluable to those responsible for the management of
the site and the many visitors to it.
REFERENCES
AGC, 1989. Brukunga Mine Rehabilitation. Conceptual plan. Report to
DME pp.
Agnew, M, 1994. Weathering products and geochemistry of wastes
residues at the Brukunga pyrite mine Adelaide Hills, SA, in relation
to environmental impacts. BSc (Hons) thesis. The University of
Adelaide.
Agnew, M, 1998. The formation of hardpan within tailings as a possible
inhibitor of acid mine drainage, contaminant release and dusting.
PhD thesis. The University of Adelaide.
ANZECC, 1992. Australian Water quality Guidelines for fresh and
marine waters. Australian and New Zealand Environment and
Conservation Council.
Armstrong, A and Betheras, F, 1952. Nairne pyrite deposit explanation.
SA Dept of Mines report, pp 98-107.
AWT, 2000. Environmental evaluation of municipal biosolids and
neutralisation plant precipitate for use on the Brukunga mine site.
Final Report to PIRSA.
Bennett, 1994. Oxidation rates in waste rock dumps and the tailings dam
at Brukunga. Report to Environmental Geochemistry International.
Blesing, N, Lackey, and Spry, A, 1974. Rehabilitation of an abandoned
minesite.
Both, R A, 1990. Kanmantoo Trough geology and mineral deposits, in
Geology of the Mineral Deposits of Australia and Papua New
Guinea (Ed: F E Hughes) pp 1195-1203 (The Australasian Institute
of Mining and Metallurgy: Melbourne).
6th ICARD
105
106
6th ICARD