Stay ring
G.
Spiral Casing.
H.
I.
J.
Pressure Testing & Dismantling Test Cone & Cylinder Runner envelop & Matching Piece.
(Make up piece)
K.
Concreting
L.
M.
N.
O.
Runner assembly runner & shaft assembly pr. test. Trial assembly of G.V with pivoting &
outer Top Cover.
R.
Lowering of Runner & Shaft assembly with Inner top cover final assy, of Guide apparatus.
S.
T.
U.
V.
W.
X.
Y.
Z.
The instructions given here are to serve as compendium for Storage and handling of the
Hydro Turbine components.
The technology of packing and also design of components are constantly being improved
and hence the instructions given here are subject to modifications. Effort has beer, made to
cover as many aspects as can be foreseen at the moment. The aim of proper storing and
handling is to ensure trouble free erection and operation. It has been pre-supposed that the
operators and supervisors who will handle these are conversant with general engineering
practices and sufficiently skilled in material handling.
1.1.2
1.2
1.2.1
ii)
1.2.2
Before unloading a packing case from the carrier the following instructions painted on the
packing case should be noted.
1.2.3
(i)
(ii)
(iii)
For all major components, lifting arrangement drawings are supplied. These should be
consulted while lifting these components.
1.2.4
Suitable lifting gear should be selected. The lifting tackles which are properly certified by
appropriate authority about load carrying capacity should only be used. All tackles should
be properly maintained. If the sling marks are not provided on any of the packing for
lifting, the sling should preferably make an angle not more than 30 deg. to the vertical,
and in no case more than 45 deg., while lifting the packing.
1.2.5
1.2.6
While handling the packing, the warnings indicated by markings and inscriptions on the
packing boxes such as "HANDLE WITH CARE". "THIS SIDE TOP" "NOT TO PUT LOAD
ON THE TOP", "SLING HERE" etc. shall be strictly observed.
1.2.7
On receipt of the equipment check them with the shipping list. Any omission and damages
should be reported back to SUPPLIER immediately. This checking should be preferably
done in the presence of SUPPLIER's representative posted at site. At the time of
inspection the case should be opened carefully so as not to destroy the packing material
in the process to that it can re re-used.
1.2.8
Protective coating applied on machined surfaces should not be disturbed. The plastic
covering should be put back carefully after inspection of the component. Some packing
cases may contain VCI (Volatile Corrosion Inhibitor) coated paper, which lets off the
vapour that prevents corrosion of the parts inside the packing case. This should not be
thrown away as long at it is effective. Absence of odour from the paper indicates loss of
effectiveness. Silica Gel and such other chemicals kept in the box as desiccants and
indicators should also be left in the box. The case should be restored to its original state
as -far as possible.
1.3
STORAGE
The equipment should be accommodated in permanent place of storage within a week after
arrival at destination.
1.3.1
The warehouse or the covered area where the equipment is to be stored should be clean,
dry and well ventilated. It must have been pretreated with pesticides insecticides against
growth of fungus and other micro-organism.
1.3.2
The cases should be arranged in neat stacks away from walls and at least 100 mm above
floor level preferably on rail sections, and also so far as possible in the sequence of
requirement of the parts for erection. Adequate gangways are to be left for inspection and
cleaning. It is also recommended to repaint weight, upright position indication etc. on the
side exposed for inspection.
1.3.3
To prevent distortion the heavy part and other large assemblies should be kept on even
platform. The articles weighing 10,000 kg and above should be arranged in a single tier.
Parts weighting up to 5,000 kg may be piled up to a height of 2.5 meters. Small and
medium size- components are recommend recommended to be stored on shelves.
1.4
GUIDE PADS
1.4.1
Guide pads supplied by SUPPLIER have thin lining (2 to 3 mm) of tin base babbit metal
chemically bonded to a steel backing. The pads are polished to high surface finish.
1.4.2
The babbit metal is quite soft and can be easily scored by ferrous material. These pads
should be stored in such a way as to prevent abrasion, scoring etc. These pads must not
be stacked one over another.
1 .5
FABRICATED COMPONENTS
1.5.1
All these items are generally fabricated from mild steel shot blasted and painted. The
machined surfaces however are treated with corrosion protective chemicals. As these
chemicals are to be removed before assembly, they are necessarily of temporary nature
and can be easily removed. Sometimes, in addition to this, aluminum foils or plywood is
used to protect against mechanical damage.
1.5.2
As soon as the components are received at side they should be examined for rupture of
preventive (TRP) film given at works. It is recommended that either a touch up work is done
or complete new film of TRP is applied.
1.5.3
It is recommended that films are replaced twice a year, preferably before and after
prolonged rainy periods.
Oil and grease do not protect surface adequately. SUPPLIER do not recommend their use
as rust preventives.
1.6
PIPE WORK
Before the pipes and pipe works are sent to site, the pipes are pickled and coated with rust
preventive coatings. Small bore pipes are plugged and large bore pipes are covered with
flanges.
1.7
INSTRUMENTS
Packing cases containing instruments, relays, motors, etc., are marked 'fragile'. Jerks and
impacts should be avoided in handling these. These cases should be fully opened and
inspected for any damage on arrival. The repair and replacement of instruments takes a
long time. It is recommended that all the instruments are checked for calibration. The
instruments should be repacked giving adequate cushioning. The instruments could also be
stored individually without the packing cases, but on properly cushioned bases and with
adequate protection against falling objects, accidental impacts etc. All instruments should
be stored in a vibration free area.
2.0
INTRODUCTION:
All components dispatched from SUPPLIER Bhopal would have been given
protection against rust by application of one of the following points. However
if any site application is necessary due to long storage, following guidelines
should be kept in mind.
2.1
Materials
2.1.1. For site use SUPPLIER recommends the following Temporary Rust Preventives (TRP).
a) Non-drying Type (Pigmented) BP 55191
b) Drying Type (Pigmented) AA 55155
c) Drying Type (Black) AA 55154
2.1.2
2.1.3
spirit Xylol or Toluol. It would provide protection for a period not exceeding six months.
2.1.4
2.2
3. 0
SURFACE CLEANING
Before any TRP is applied on any metal surface the surface should be free from old TRP,
rust, grease, moisture etc. It may be emphasized that the effectiveness of the TRP is
reduced or even nullified if the surface is left contaminated.
3.1
3.2
Remove the rust spots using sufficient quantity of derust solution rubbing with clean cloth.
Clean the surface with cloth soaked in water. In case the surface is still not clean, repeat
the process. Finally remove the residual acid from the surface with the help of wet cotton
otherwise it may cause further Corrosion.
3.3
3.4
Wipe off the surface with clean cloth having small quantity of uncontaminated white spirit.
Allow the solvent to evaporate. The surface is now ready for TRP application.
4.0
TRP APPLICATION
The application has been classified into four categories viz., A, B, C&D keeping in view the
status of finish and extent of protection desired.
4.1
Category A
Journal faces, highly finished surfaces (better than 0.8 microns) such as thrust face,
bearing surfaces of Shafts.
4.2
Category 'B'
Large fabricated items having machined surfaces such as Guide Bearing Support Ring,
Vapour Seal Assy, Oil Retaining Sleeve, mating surfaces, shaft flanges.
4.3
Category 'C'
All fasteners and threaded portions excepting in such cases where the job has already a
protective film each as plating, galvanizing etc.
4.4
Category 'D'
Small machined components & other components not defined above.
5.0
5.1
Jobs classified in Category 'A' and B' will have 3-coat system as detailed below.
5.1.1
After cleaning, apply one coat of TRP AA 55155 and allow it to air dry for 12 hours inside
the store.
5.1.2
Clean dust from the surface and apply a coat of TRP AA 55154 and allow it to air dry for
about 12 hours.
5.1.3
5.2
Jobs classified as Category 'C' will have 2-coat system as detailed below.
5.2.1
After cleaning apply one coat of AA 55154 on non-threaded portion and a liberal coat of BP
55191 on threaded portion. Allow if to air dry for 12 hours.
5.2.2
5.2.3
Fasteners of small size, having no other protective film such as plating, galvanizing etc.
after cleaning, shall be given a liberal coat of BP 55191 TRP on threaded and non-threaded
portion.
5.3
Jobs classified, as Category D will have two-coat system of TRP as detailed below.
5.3.1
After cleaning apply one coat of AA 55155 and allow it to air dry for 12 hours.
5.3.2
6.0
PRECAUTIONS
6.1
TRP should be stirred well in the original container so as to make a homogeneous mixture
of its constituents.
6.2
Container and brush must be cleaned after application with white spirit before keeping for
next operation.
6.3
During the drying period, the wet film should be protected from, deposition of dust particles
by providing an umbrella of polythene sheet.
6.4
Protections, given for TRP film, such as Aluminum sheet, plywood etc. should be replaced
after application of the TRP. The surface coming in contact with the job should be given a
Normally after an interval of six months, the surface of TRP coated jobs shall be examined
for any damage, corrosion spots etc. the repair should be done and TRP System applied.
6.6
any damage / shortage, suitable action in line with QAM/SP shall be initiated to inform
concerned agencies. Storage and preservation of materials shall be ensured as per
manufacturer instructions.
4.2 All rubber products eg. Cup seals, O-rings etc. are preserved till their use, in chalk
powder / water container with water replacement every week / water soaked saw dust.
5. WELDING
5.1 Welding is carried out by a qualified welder.
5.2 Recommended electrodes are used wherever specified.
5.3 Edge preparation is checked / prepared wherever required as per drawing.
5.4 Surfaces are cleaned thoroughly before starting welding, surfaces must be free from
foreign materials such as grease, oil, paints etc. for a distance of at least 20 mm from weld
joint on either side.
5.5 Electrodes are suitably baked in oven prior to their use to 300 C at least for two hours / as
per manufacturers guidelines.
5.6 Proper root gap is maintained for welding to avoid undercut, over laps, abrupt ridges and
valleys.
If the gap is more than 5 mm packing strips are provided to minimize shrinking and
welding deformation. These shall be removed before starting seal welding from other side.
Preheating / post-heating of surfaces / stress relieving of weld joints is carried out
wherever necessary as per technical requirements.
5.7 After root run completion of welding dye penetrant testing is carried out and corrective
action taken.
5.8 Wherever circumferential welding is involved, welding as per sketch no. 1 is followed for
making root run.
5.8.1
.8.2
.8.3
After this, welding may done starting from two or four points and proceed
continuously. In other joints skip / step welding as shown in sketch no. 2 may be followed to
minimize deformation of equipments.
5.9 Before starting seal welding on the other side, gouging / or grinding is done and dye
penetrant is carried out.
5.10All site weld joints of stayring and spiral casing are radiographed or UT done as per
9. ASSEMBLY OF EQUIPMENTS
9.1 Before taking up any assembly, check all items of the concerned drawing are available.
Check for any damaged components and rectify if possible after obtaining concurrence
from concerned manufacturing unit.
9.2 Check for all technical requirements of drawings to be satisfied at site and ensure their
compliance.
9.3 Check for all concessions /deviations raised at shop if any to be taken care at site and
ensure compliance.
9.4 Check for all test results of shop wherever necessary.
9.5 Check for PO number, assembly match mark and axis marking for each assembly.
9.6 Ensure that individual components are cleaned & are free from burrs and scratches.
9.7 Check for special lifting arrangements of assembly / sub assembly, if any and ensure its
availability.
9.8 Check for shop dowels.
9.9 Temporary plugs / protections provided should be retained till final assembly.
9.10Blow compressed air to oil and grease ports, load grease ports with grease and plug
them temporarily.
10. CONFIRMATION BEFORE STARTING ERECTION / ASSEMBLY WORK
10.1Confirm availability of all tools and tackles required for erection works.
10.2Confirm availability of reference drawings and technical documentation related to the
project.
10.3Confirm customers certified centre line and established datum available on embedded
plates on the concrete nearest to the pit.
10.4Confirm availability of all connected equipments, instruments required for erection.
10.5Ensure installation of generator assemblies with reference to Radial line of assembly.
11. PREPARATION OF FOUNDATION BLOCK OUTS
11.1 Check the foundation block outs dimension and locations, if necessary carry out chipping
of foundations to required dimension and elevation.
B.
1.
Use proper protective clothings, welding glass to avoid burn injuries due to welding
spatters, hot welding slag arc flashes etc.
2.
Ensure proper earthing of work & welding machine to avoid electric shock.
3.
4.
Welding area should be properly ventilated to minimize air pollution in the surrounding area.
5.
6.
Store gas cylinders away from "Sources of Heat" Over Furnace, direct sun rays.
7.
8.
9.
10.
Ensure against leakage of gas from torch, hose valves Regulators etc. Use proper pipe
clips. Periodical checking of pressure gauges of regulator to be done.
11.
No flammable material like Petrol, Oils Dyes Acids Enamel paints and Varnishes etc, be
lying in the area where cutting or welding is being done.
(c)
Lifting Tackles
1.
2.
3.
4.
Periodic greasing of ropes should be done to avoid rusting and decrease friction.
5.
Periodic testing of 'D' shackles, turn buckles, Pull lifts and chain pulley blocks be done.
6.
Avoid wire ropes coming in contact with sharp edges while lifting.
(D)
Cranes
1.
2.
Do not keep the load suspended for more time than absolutely required. For this, plan your
activity well in advance.
3.
4.
5.
6.
While giving signals to crane operator standard signals with which operator is conversant
be given by one man.
7.
(E)
1.
2.
3.
4.
5.
6.
7.
8.
F.
1.
Never add water to Acid for making dilute solution. Always add Acid to water.
2.
Never handle any acid or alkali with bare hands and without protection to eyes.
3.
Use acid proof rubber gloves, gum boots, rubber aprons and goggles as per Job
requirements.
4.
Whenever there is any acid or alkali burn, wash off as quickly as possible with a large
quantity of clear water and then rush to doctor.
Embedded Parts
Embedded Pipe in First Stage
(A)
Pre-Erection Checks.
(i)
Check for availability of all the items as per relevant drgs & bill of material and clean
them.
(ii)
Check that all the necessary tools, equipment & material required are available at
site.
(B)
Erection.
(i)
(iii)
Pipes to be erected.
(a)
(b)
(iv)
(v)
Ensure proper clamping of pipes so that they remain in the same position during
concreting.
(vi)
Field efficiency and discharge measurements are to be made for all units as per drg.
2.
3.
4.
5.
6.
7.
8.
9.
Pier Nose
1.
Lower Pier nose assembly using winches wire ropes or suitable crane then check level and
elevation.
2.
3.
4.
5.
Fixing of Anchors.
6.
7.
(a)
Vertically 1 .mm/metre.
(b)
2.
3.
4.
5.
Arrange all bottom, top, left side, right side segments and assemble them complying with
elevation w.r.t. relevant drgs.
6.
7.
Check dimension elevation, matching and then clear for full weld.
8.
9.
10.
Flush grind final run, align, tighten, H.D. Bolts and Turn buckles lock, erect drain box
assembly & connect DT drain pipe & weld.
11.
Lower two bottom cone segments, align with DT liner and Tack weld.
2.
3.
4.
Check alignment of cone w.r.t. X & Y axis within 2 mm. Top center of D.T. cone to be in line
with D.T. liner center within 2 mm.
5.
Measure the inner diameter of cone at the top. If it is not as per drg. correct it.
6.
7.
Weld the joints as per relevant standards and dye test the root run.
8.
Release for concreting up to casing of piers for spiral casing and stay ring.
SL.NO
DESCRIPTION
PAGE NO
STAY RING
29
2.
SPIRAL CASING
30
3.
RUNNER ENVELOP
4.
PIT LINER
31
32
STAY RING
(ii)
(iii)
(iv)
(v)
Establish center line (x, y Axis) & Datum elevation given by the civil wing.
(vi)
(B) ERECTION
(i)
(ii)
Assemble in service bay and heat and tighten the Joint bolts to achieve elongation as per
drawing.
(iii)
(iv)
Lower the Stay ring on stools, so that stay ring pedestal are resting on the stool. Align
center & level with respect to station, Center Line, using hydraulic Jacks/Mechanical
Jacking screws.
(v)
(vi)
No step at joints on top & bottom machined surfaced after joining. Check radius at top &
bottom machined bores.
(vii)
(viii)
Seal welding of Joints to be done as per drawing requirement. Conduct NDT tests as per
drawing requirement.
SPIRAL CASING
(A) PRE-ERECTION CHECKS.
(i)
(ii)
(iii)
Check and prove threads on holding down, bolts & jacking bolts & other hardware.
(iv)
(B) ERECTION
(i)
Assemble the spiral segments as per drawing & ensure that gap at joints in axial or
radial direction is 2 to 5m.m
(ii)
Match the spiral members with top & bottom contour of stay ring & center line
marked on spiral member with reference to center line of stay ring ( 2mm).
(iii)
Weld the spiral segments as per technical requirements given in the drawing.
(iv)
Dye check the weld seams for any surface defects in the plate.
(v)
Back gouge, grind & dye check for seal run, complete the sealing run.
(vi)
Radiograph and ultrasonic Test for all butt Joints to be carried out as per drawing
requirement.
(vii)
(viii)
(ix)
Carry out the Hydraulic testing of spiral casing at pre test pressure and time as
given in drawing.
(x)
After successful completion of Hyd. Test, remove test cone & test cylinder.
(xi)
Complete the installation of holding down bolts, anchors, wedges, & lock all the
hardware.
(xii)
(xiii)
Carry out erection, welding and NDT of inlet pipe as per drawing.
(xiv)
Recheck the alignment leveling of stay ring before handing over for concreting
Runner Envelopes
A. Pre Erection Checks.
1.
2.
Check diameter.
B. Erection.
i.
Runner Envelope to be lowered, after lowering for Ist out before stay ring.
ii.
iii.
iv.
v.
vi.
vii.
ERECTION
A. LOWER THE PIT LINER SEGMENTS
1. The mechanical surfaces for fixing the servo motors are equidistant from X & Y axis (with
tolerance as per drawing) & are vertical. 1 mm. per meter
2. Top dia of pit liner ( 5 mm)
3. Welding to requirements as per drawing.
4. Welding of anchor plates.
5. Installation of pipes / Pipes sleeves for routing of air, water and other pipe lines. Also check that
embedded pipe carrying in this state of concreting are installed and the free ends are blanked
off by welding metal plate. Ensure placement of sufficient sleeves for routing cables etc also.
SL. NO
1.
DESCRIPTION
2.
3.
4.
5.
6.
PAGE NO.
7.
8.
9.
Installation. of G V. servomotor
10.
Guide Bearing
11.
Shaft seal
12.
Oil-Header
13.
Governing Equipment
14.
RUNNER ASSEMBLY
1.
2.
Perform visual inspection for any damages, report to unit if any abnormality is noticed.
3.
Check the match markings during dismantling (if the runner is received at site in assembled
condition).
4.
5.
Check correct joining and assembly of rubber cords and other seals.
Check that the pre stressing of fasteners is done as per drawing reference.
j)
Check that the locking on laterships, washers, plugs and valves are as per technical
requirements/details of drawing.
k) Assemble runner shaft and servo tube with runner as per drawing
l)
m) Measure and record the clearance between runner hubs & blade, it should be as per
drawing value.
n) Perform testing of the Runner as per test procedure technical data provided in the drawings
supplied by manufacturing unit.
Drawing to be referred
1. Tools tackless for runner shaft
2. Runner assembly
3. Shaft arrangement
4. Arrangement of all tubes of runner servomotor
5. Testing devices for runner & shaft
RUNNER ASSEMBLY
Overhauling, Shaft assembly, Hyd. Testing
A. RUNNER
1.
Runner of a Francis turbine is dispatched to site, fully assembled or partly assembled and
partly loose depending on its overall size / transport limitations. Partly assembled runner
comprise of hub, turning mechanism, piston, runner blades, bottom cover etc. The loose
components may be runner servo tubes, piston rod, cone and other hardware.
2.
Check all the materials as per drg & all tools available for carry out overhauling.
3.
4.
Carry out trial lowering of assembled runner in to the runner chamber if called up before its
assembly with shaft to check and ensure clearances between runner blades and runner
chamber with runner blades pulled out. In the event of clearances being less than those
specified in the drawing, correction is done either by grinding the tip of runner blades / runner
chamber in the complete zone of runner blades operation (i.e. close to open & open to close).
B. OVERHAULING ASSEMBLY
1. Runner received in site in dismantled condition, runner blade received at site separately.
2. Place runner on pedestal.
3. Remove bottom cone & perform through checking inside. While remaining bottom cone
ensure match mark is there.
4. Assemble any loose components & carry out tightening of fastener, locking called in drg.
5. Fix bottom cone as per match mark & perform tightening & locking.
6. Turn the portion of the runner & lower it over the platform made for runner blade fixing.
7. Carry out assembly of runner blade with cup seals as per instruction given in drg.
C. ASSEMBLY OF TURBINE SHAFT WITH RUNNER
1. Place the runner leveled on stools / wooden sleepers.
2. Check the mating surface of turbine shaft & runner for trueness.
3. Check & ensure the holes of coupling bolts in runner & shaft and coupling bolts are as per
drg.
4. Prepare shaft in line with general guidelines and check trueness of all machined surfaces.
5. Check and prove bedding of guide bearing pads with guide bearing journal of shaft, with
shaft in horizontal position (Ref. Instructions for bedding of pads) before runner shaft assy
start.
6. Carry out cleaning, acid pickling, neutralization and oil rinsing interiors of oil servo tubes.
Insert the lower part of servo tube in shaft bore before runner shaft assy start.
7. Turn the shaft to make it vertical along with servo tube (runner servo tube is suspended with
chain pulley blocked to the same crane hook connected to shaft).
8. Transfer and lower the shaft on to runner. Maintaining accessibility with shaft suspended,
lower and assemble servo tube with piston rod coinciding match marks and using dowels.
Carry out locking of fasteners and dowels as called for.
9. Install O-seal, lower the shaft and carry out assembly of shaft with runner, coinciding the
match marks. Install all coupling bolts, tighten to required stress / elongation as per technical
requirement & lock the nut.
10. Check soundness of runner shaft assembly joint with the help of 0.03 feeler gauge. In the
event of correct assembly, feeler gauge will not pass.
11. Cover the open end of servo tube temporarily to avoid entry of foreign materials in to the
system.
12. Prepare FQA log sheet for elongation tightening & completion of runner shaft assy.
D. HYDRAULIC TESTING OF RUNNER & CHECKING LEAKAGES
1.
2.
Carry out laying and connection of pipes as per the scheme of testing supplied by the
manufacturer.
3.
Carry out testing of runner in the manner stipulated in drawing and check leakages through
sliding mechanisms.
Note : Oil leakage is not permitted, through the cup seals of runner blades.
4.
5.
After successful testing, carry out locking of all fasteners as called in drawing.
Note : Oil leakage is not permitted, through the cup seals of runner blades.
Runner shaft assembly is lowered along with turbine top cover. Runner shaft assembly is
supported on top cover with a suitable supporting bracket fitted at the seat of turbine guide
bearing. Turbine guide bearing skirt rests over this bracket.
2)
Lower the complete assembly in to runner chamber and carry out assembly of top cover using
seals dowels and fasteners etc. Lower runner shaft assembly further to make GB skirt rest
over the bracket.
3)
Carry out leveling at turbine shaft flange and centering of runner with runner chamber.
Check the leveling of speed ring top flanges and groove area. Grind them if necessary to
achieve drg. Value.
ERECTION OF GUIDE APPRATUS
PRE-ERECTION CHECKS
1)
lower bracket
foundations completed.
2)
Generator barrel is painted except stator, lower bracket, and upper bracket foundations.
3)
4)
All flanges and threaded holes of stay-ring are cleaned and surfaces deburred.
5)
Horizontality of stay-ring flanges checked and corrective action executed wherever required.
6)
All components of guide apparatus and erection devices as per drawing are received.
Even through the guide apparatus assembly is proved in the manufacturers unit, trial
clearances and free turning movements of guide vanes are as per technical requirements
and to establish, lower ring, top cover positioning and dowelling.
2)
Remove preservatives and clean all the components of guide apparatus and prepare the
components for assembly as per general guidelines.
3)
Depending on type of design, lower ring may be assembled finally with seals.
4)
5)
6)
Install all holding down bolts of lower ring and complete tightening.
7)
8)
Assemble four upper guide vane bush housings, 90 degree apart on top cover. Lift the top
cover precisely leveled with the help of turn buckles and crane and lower it on stay-ring.
9)
Position the top cover using dowels and reference match marks.
10)
Install alternate holding down studs of top cover and install all upper guide vane bush
housing (thin layer of grease on guide vane journals and bush housing before installation).
11)
Check and ensure free turning of all guide vanes. While tightening the nuts of holding down
studs till tightening of all nuts of top cover is finally completed.
12)
Bring all guide vanes to close position, to check and ensure the clearances of guide vanes
with top cover at leading and trailing edges are as per drawing requirements. In case of
deviation from the drawing requirements, corrective action is taken wherever required.
13)
14)
15)
Complete reaming, doweling of lower ring and inner top cover & outer top cover.
2) Check the rubber cup seals and O-seals do not carry any cracks and are not de-shaped.
3) Install cup seals and retaining rings on lower bush bearing of guide vane and ensure that
retaining ring does not interfere with lower collar of the guide vane. In case of interference,
the retaining ring shall be suitably machined.
4) Lower guide vane in position.
5) Install rubber seal of top cover on stay-ring & complete the assembly of top cover with stay
ring using dowers pins & fasteners ( to ensure proper assembly of top cover stay ring ,check
gap between top cover & stay ring flange by 0.03 mm feeler gauge ,which should not pass).
6) Assemble guide vane bush houses with seals and check free turning movement of each
guide vane. (ensure bush house installation with reference to grease port for pipe connection)
7) Guide vane should move freely when turned by one person by using spiral spanner supplied
as erection device by the manufacturer. After installation of bush.
8) Lower runner assembly with inner top cover runner shaft assembly.
Note : Allowable tolerance in centering 0.1 mm Leveling with 0.03 mm/met.
9) To facilitate alignment of generator, the runner shaft assembly is installed in a lower position
from designed level by an amount 3-4 mm more than the spigot height of the generator shaft
flange.
10) Check and ensure centering of runner w.r.t. Lower labyrinth on lower ring is within the
specified limits.
11) Install regulating ring and servo motors (refer instructions for installation of servo motors of
different variants, described separately).
12) Install link mechanism and adjust guide vane end clearances, bedding clearance and
clearance between lever and lever stopper / collar.
13) Check free turning movement of all guides vanes from full close to full open position.
14) Position regulating ring to close of guides apparatus complete centering and provisional
locking.
15) Install connecting rods of servomotors with regulating ring and carry out pre-stressing of
guide apparatus mechanism (refer instructions described separately).
Note : After final assembly of guide apparatus, grease and lubricate all bearings and check
for easy turning movement of guide apparatus mechanism by applying oil under pressure in
the servo motors. The complete mechanism should turn freely at oil pressure not more than 5
kg/sq. cm or as indicated in drawing. In case guide apparatus fails to turn at this pressure, its
Tightness in guide vanes is determined in the following manner upon the readiness of oil
pressure system, governor and completion of working mechanism in all respects.
2.
In closed position of guide vanes, bring the piston of servomotor with stopper, forward by 15
mm by adjusting the length of connecting rod with turnbuckle. While doing this, check that
regulating ring is not disturbed and remains in the closed position of guide apparatus.
3.
Take the piston of servomotors without stopper, back by same amount i.e. 15 mm in the similar
way.
4.
5.
Apply oil pressure, according to drawing instructions on servo motor piston for closing and
measure the amount of movement of piston. Movement of piston so measured is the tightness
required in the guide vanes.
6.
Release the oil pressure and install the piston of both the servomotors from the end support at
a distance of tightness value measured. Complete locking of turn buckles with lock nuts.
7.
between
adjacent
guide
vanes
all
along
their
height
is
00,
apparatus
servomotor
opens
to
its
full
stroke,
when
the
oil
Dismantle the servomotor after proper match marking of all components / joints.
2)
Check the cup seal O rings of servomotors for any cracks or damage. Check the
interference of cup seals I. D. with sleeve.
3)
Clean thoroughly all parts and inside surface of piston and cylinder with solvents like
diesel / petrol check the surfaces of piston, cylinder, piston rings, bushes etc. for any
scratches.
4)
Use new cup seals and prepare O ring if assembled ones are worn out and if replacement
is necessary.
5)
Assemble the covers using O ring. Fasten the covers by tightening the studs and nuts.
6)
Insert the piston assembly in the cylinder in vertical position, taking care to keep the slot
portion of piston towards oil ports. Lubricate cylinder surface profusely with turbine oil as
soon as piston rings have entered the cylinder remove clamp, used for pressing the piston
rings.
7)
Assemble the cylinder cover using cup seals. Fasten the cover with stud nut. Locking of
nuts to be carried out only after satisfactory hydraulic testing, & after checking the opening
and closing of servomotor and checking the seals are intact.
B) INSTALLATION
1. Check and clean the base plates mounted on pit liner. Check vertically.
2. Push / pull the servomotor piston fully in/out. Lower servomotor stopper in position to lock
the movement of piston.
3. Lower both the servomotors in their respective position. Couple mounting plates with
servomotors using studs & nuts.
4. Align both the servomotors to drg. Dimension. Keep the piston rods of both servomotors in
fully closed position (i.e. piston touching the respective cylinders ends).
5. Check the threads of piston rod. If necessary clean and dress with triangular smooth file.
6. Level the servomotor precisely (horizontal) check level by precision block level (accuracy 1
Div = 0.02 mm/m) on piston sleeve level should be achieved with 1 division.
7. Assemble the piston rod and connected rod initially, keep 25 mm gap between piston rod
and connecting rod.
8. The connecting rods of servomotors to be assembled with regulating ring keeping the
guide apparatus fully closed.
9. Maintain the distance 1985 of G.V. servo cylinder (Not of piston rods / connecting rods)
and level the servomotor.
10. Now if the gap between mounting plate and plate of pit liner is less than 3mm weld
mounting plates directly to pit liner without using strip, otherwise they are to be welded
using strip as shown in the drawing no.
11. Check the guide vane bedding its nut as per drg value correct it with both the servomotor
operation.
12. Also check and set if necessary the G. V. servo stroke indicator scale.
TOLERANCE:
1. Center line servomotor is parallel to Y axis and at a distance as specified in the drawing (within
1 mm).
2. Elevation of servomotor w.r.t. regulating ring (within 1 mm).
6.0 GUIDE BEARING.
A)
i)
Pre-erection.
Thoroughly clean all parts and joint faces of bearing oil sump. Use engineers blue on one
face, tighten the joint faces and check the bedding. If necessary scrap the face. Filler gauge
can be used to find out the gap.
ii)
Clean the bearing pads with solvent like petrol and white spirit. Check their bedding with the
bearing journal of the shaft. If necessary Scrapping can be done. Also check the bedding of
Disc. Check that stud has spherical curvature where it is pressing the disc.
iii)
iv)
v)
Check the working of oil level indicator in Separate oil container out side.
vi)
Apply liquid sealing compound (hold tight at joint faces of the Bearing oil sump. Bottom
ring)
(i)
Fix. studs called in guide apparatus drg. Assemble bearing housing with dowel and pins,
bolts nuts washer, O-seal respectively, taking care that no step at any joint.
(ii)
Install the rubber o" rings and position the bearing housing matching with unit axis marked
on the top cover and bearing housing.
Center the center piece with respect to turbine shaft journal (with runner at centre) Tighten nuts
and washer.
(iii)
Assemble the pipe assembly in their respective position. Suitably blank it for testing with
kerosene for any leakage through O rings. Remove the kerosene after testing.
(iv)
Fix studs with holdtite. Assemble the two halves of bearing housing, Match with axis and
complete the assembly of bearing housing. Bearing housing should be checked for any
leakage.
(v)
The runner feed back system & the indicator showing the position of runner blades are also
mounted on the oil header. Oil header is assembled with runner shaft logged after alignment
& center of runner.
4. PRE ASSEMBLY
4.1 Check individual component of oil header is prepared to technical instruction.
4.2 Check surface finish of pipe line assembly as per drawing requirement and there is no ovality
on diameter at location where it passes through the oil header bush.
4.3 Place oil header assembly upside down and ensure the movement of pipe line assembly, in
the oil header bush is smooth.
4.4 Check and record the diameters of bush and pipe line assembly. Check oil deflector items
machined surfaces are true and check level and surface finish exciter shaft for trueness
(where oil deflector is assembled).
5. ERECTION OF OIL TUBES & OIL HEADER
Following sequence of activities to be followed for erection of oil tubes and oil header:
5.1 After assembly of runner, shaft and inner top cover in erection bay check horizontality of the
upper flange of oil tube (lower). Upper flange of oil tube (lower) should be parallel to turbine
shaft coupling face.
5.2 Lower the assembly of runner, shaft and inner top cover along with oil tube (lower) in the
turbine pit (preferably after testing of runner on erection bay).
5.3 Insert middle tube inside generator shaft in erection bay and then lower in the pit keeping
oil tube projected by 200 mm approx. below generator shaft to facilitate coupling of tubes.
5.4 After connecting middle tube to lower tube and assembly of generator shaft with turbine
shaft, check the horizontality of flange of middle tube and throw of its spigot.
5.5 Assembly oil tube (upper), check the horizontality of its top flange and throw of spigot.
5.6 Lower and assemble generator tubular shaft with generator shaft, check throw of spigot in
generator tubular shaft and horizontality of top flange.
5.7 Lower the assembly of central pipe and pressure box. After assembly with upper tube,
check throw of central pipe and pressure box.
5.8 The allowable value of throw for point no. 4, 5, 6 and pressure box is preferably 75% of the
diametral clearance at pressure box bearing, and in no case it should exceed the value of
diametral clearance.
5.9 The allowable value of throw for central pipe is preferably 75% of the diametral clearance at
central pipe bearing, and in no case it should exceed the value of diametral clearance.
5.10
If the throw is more than the value mentioned in Para 8 & 9 above, correction to be
done in respective flange face by suitability scraping or using shims taking care of O seal
grooves.
5.11
Assembly oil bath and oil guide as per drawing, centralize oil bath to get the uniform
labyrinth clearances.
5.12
Lower oil header body carefully in balanced condition taking guide from central pipe
in such a way that there is no radial pressure or bending effect on central pipe. If the spigot
between body and oil bath does not match, loosen the spigot suitably by grinding and
assembly body to oil bath.
5.13
After checking free rotation and stroking of oil tubes, dowelling of oil header body
In extreme position of runner blade stroke (fully open and fully close), rotate the
machine at very slow speed for checking any fouling between stationary and rotating
components.
(ii)
(iii)
Prepare all the "0" seals and check for damage/crack, if required replace it.
GUIDE LINES FOR ERECTION OF OIL TUBES AND OIL HEADER OF VERTICAL FRANCIS
TURBINES
1. After assembly of Runner, Shaft and Inner top cover in erection bay check horizontality of the
upper flange of oil tube (lower). Upper flange of oil tubs (lower) should be parallel to turbine
shaft coupling face.
2. Lower the assembly of Runner, shaft and Inner top cover along with oil tube (lower) in the
turbine pit (Preferably after testing of Runner on erection bay).
3. Insert Middle tube inside Generator shaft in erection bay and then lower in the pit keeping oil
tube projected by 200mm approx. below generator shaft to facilitate coupling of tubes.
4. After connecting middle tube to lower tube and assembly of generator shaft with Turbine shaft
check the horizontality of top flange of middle tube and throw of its spigot.
5. Assemble oil tube (upper), check the horizontality of its top flange and throw of the spigot.
6. Lower and assemble generator tubular shaft with Generator shaft, check throw of spigot in
generator tubular shaft and horizontality of top flange.
7. Lower the assembly of central pipe and pressure box. After assembly with upper tube, check
throw of central pipe and pressure box. .
8. The allowable value of throw for point no. 4,5,6 and pressure box is preferably 75%. of the
diametral clearance at pressure bob bearing , and in no case it should exceed the value of
diametral clearance.
9. The allowable, value of throw for central pipe is preferably 75%. of the diametral clearance at
central pipe bearing, and in no case it should exceed the value diametral clearances.
10. If the throw is more than the value mentioned in Para 8 & 9 above, correction to be done in
Respective flange face by suitably scraping or using shims taking care of "O seal grooves.
11. Assemble oil bath and oil guide as per drawing, centralize oil bath to get the uniform labyrinth
clearances.
12. Lower oil header body carefully in balanced condition taking guide from central pipe in such a
way that there is no radial pressure or bending effect on central pipe. If the spigot between
body and oil bath does not match, loosen the spigot suitably by grinding and assemble body
to oil bath. Grinding can be carried out since there are 4 Dowels of 16mm in addition to 16
studs of nuts of M20 for holding the body with oil bath which keep the joint tight even in
running condition job the Machine.
13. After checking free rotation and stroking of oil tubes, dowelling of oil header body and oil bath
to be carried out.
14. In extreme positions of Runner blade stroke (fully open and fully close), rotate the machine at
very slow speed for checking any fouling between stationary and rotating components.
15. CHANGES DUE TO REVISION: NIL
16. ENCLOSURES: Sketch No. HTE/SK/001 & HTE/SK/002
GOVERNING EQUIPMENT
(i)
(ii)
Pressure Receiver.
(iii)
(iv)
Check all the pockets of foundation are as per drawing. Ensure sides of these pockets are
slightly rough for proper bondage of concrete.
(ii)
(iii)
(B) Erection.
(i)
Lift the complete P.P. Set assembly on 4 equal wire Ropes, using eye bolts in fairly levelled
condition
(ii)
Install the P.P. Set as per drawing dimensions. Check the elevation at 4 places. Ensure no
gap exists between supporting brackets and concrete.
(iii)
(iv)
(v)
(vi)
(ii)
Remove manhole door and inspect for any rusting from inside surface or foreign material
during Transportation. Check the paint condition from inside.
(iii)
Place the manhole door in the position if required replace the gasket.
(B) Erection.
(i)
Lift the pressure receiver in balance condition and assemble it on the foundation bolts. Align
the pressure receiver as per drawing dimension. Care to be taken that angular position of
the mountings are as per drawing.
(ii)
(iii)
Mount all the fittings on receiver and prevent them from any damage (Glass parts/pressure
gauges).
(iv)
Pressure test the receiver with air and check leakage through any fittings.
(B) Erection.
(i)
Install the hydro mechanical and electrical cabinet as per the drawing.
(ii)
Use leveling screws to leveling screws to level and achieve elevation as per drawing.
(iii)
Check the verticality of the cabinets by plum bob and also check level, with precision level,
of the rod for free movement of kinematics.
Note :After installation of above panels dust/ moisture in this area should not be allowed. As such, all
precautions like chipping/cleaning in the surrounding are to be taken prior to installation of these
cabinets.
Arrangement of PP set
02210114201
02200114201
02085014101
02083614101
Check that all items are available and are in sound condition.
(ii)
Wire rope be pre-stressed to 300 kg. . Force, for 24 hrs. before installation or as called in
drg.
(iii)
(iv)
Touching of wire rope with any bracket, tube etc. is not allowed. Movement of wire rope
should be free.
(v)
(vi)
(vii)
Wire rope after installation should be in tension (not loose, to avoid any back lash)
(viii)
ii)
Install metering instrument panel and assemble all instruments as per layout drawing.
Carryout laying, welding of pipes and install supports, clamping etc.
iii)
iv)
v)
Install pressure gauges on draft tube cone, penstock, spiral case and other instruments
as per layout drawing.
Note :
1. Carry out hydraulic testing of pipelines wherever called for.
2. Ensure calibration of all metering instruments prior to putting them in service.
Shear pin is a weak link between strap and guide vane lever and fails in the event of
blocking or jamming of guide vanes. With the failure of shear pin guide vane becomes
free of its turning movement and strap alone moves and opens the contacts of the limit
switch to initiate a warning signal of shear pin failure at UCB. The limit switches are
connected in series with normally closed contact.
C) ERECTION
i)
Install all base plates of unit switches, strikers and clamps as per layout details.
ii)
Assemble limit switches and strikers with their respective base plates such that the limit
switch remains pressed with striker and the contacts are closed.
iii)
Carryout laying, clamping and connecting of cables with guide apparatus open,
providing a little additional allowances in the cable for flexibility.
iv)
AUXILIARIES
1
TRANSFORMERS
RECEIPT OF TRANSFORMER AT SITE
To ensure that a Transformer will function satisfactorily it is important that handling, lifting, storing
and assembling are carried out with great care and cleanliness by experienced personnel who are
thorough with various working operations.
This section gives instructions how handling, lifting, storing and assembling should be carried out.
For large Transformers it is recommended that the work is done by TARIL or is under supervision
by experts from TARIL.
INSPECTION
In connection with receiving and unloading at site, and at the final storing place before assembling,
the transformers
shall be inspected carefully for external visible damages as dents, paint damages etc. After the
arrival of the material at receiving points, the customer should, in case of possible damage/loss of
any component, make the necessary claims with the contractors representatives under intimation
to supplier so that such claims can be registered with the transport agents. Before unloading, the
condition of packing and of the visible parts should be checked and possible traces of leaks
verified (condenser bushings). If necessary, appropriate statements and claims should be made.
Drums containing oil which have been dispatched separately should be examined carefully for
leaks or any sign of tampering. All drums are dispatched filled up to their capacity and any
shortage should be reported. As a principle we never supply partly filled drums.
In order to protect the active part against moisture, the transformer tank is filled with nitrogen
during transport at an
over pressure of 0.2kg/cm2 approximately at room temperature. Check immediately the gas
pressure at the arrival. A positive pressure indicates that the tank and the transformer components
respectively are tight, and that the active part including the insulation materials is dry.
If there is no positive gas-pressure, transformer should be immediately filled with dry Nitrogen gas
at pressure of 2 PSI without loss of time.
DAMAGE/LOSS
Damage or loss of any component should be reported to Supplier immediately. Photographs or
other useful evident
should be submitted wherever possible. When the transformer is dispatched filled with oil, level in
transformer main tank should be checked & if the level is below the indicated level in main tank the
same should be reported to the supplier immediately & also the same should be mentioned in LR
copy. When the transformer is dispatched filled with oil, a sample of oil should be taken from
bottom of the tank and tested to IS: 1866. If the dielectric strength is below 50KV, when tested on
standard IS: 1866, the matter should be reported to supplier along with insulation resistance values
of the various windings to earth.
Drums containing transformer oil which have been dispatched separately should be examined
carefully for leaks or any signs of tempering. All drums are dispatched filled up to their capacity and
any shortage should be reported to us immediately.
UNLOADING
The transformer should be unloaded by means of crane or suitable device of sufficient capacity
(Please refer rating
plate for weight detail). For lifting purpose lifting lugs are provided on the top cover & on the sides
of tank. Lifting lugs on the sided of tank are lifting the complete transformer, whereas the lugs
provided on the tank cover should be used only for lifting the cover. Lifting lugs for transformer
lifting are painted red. Check at lifting of complete transformer that the lifting wires/ropes are not in
contact with bushing or other components on the cover.
Four jacking pads are also provided for lifting the transformer with the help of jacks.
Bidirectional skids are also provided on the bottom of the transformer, in the form of channels
having towing holes on both the sided & also holes for foundation of transformer. Transformer
should be jacked up using the projections specially provided for that purpose. Jack should never
be placed
under any valves. To avoid undue mechanical stresses the transformers must be
kept on reasonably level foundation.
ASSEMBLY OF WHEELS
Whenever wheels are supplied with transformer, movement of transformer at site is carried out by
mounting these wheels.
Mounting of wheels under transformer is to be done as per roller arrangement drawing. In power
transformer wheels are designed such a way that conservator side wheels are of slight higher in
height fin the view of keeping transformer shortly inclined to release trapped air from main tank and
to avoid accumulating rain water on the tank top cover. While fixing the rollers, the flange should
come on the inner side of the rails.
Transformer placement can be with or without rollers as per applicable GA/foundation drawing.
When the transformer is in the final position, the wheels shall be locked to prevent accidental
movement of the transformer.
STORAGE
After arrival at site, it is desirable to erect and commission the transformer with minimum
delay. In case this is not possible the transformer shall be erected at its permanent location
with conservator and breather fitted and dry oil filled to the correct level. Whether storage or
in use, the dehydrating breather must be fitted on all the transformers which are oil filled.
The breather incorporates an oil sealing device which must be filled with oil, to the level
marked, to be effective. The condition of silica gel must be checked periodically, particularly
during monsoons.
Dismantled equipment and components are packed to be protected against normal
handling and transport stresses.
All other accessories should be stored in a covered dry place. It should be ensured that
there is no damage to the gasketted joints and that all the blanked joints are tight.
Goods stored outdoors must not be placed directly on the ground, and should be covered
carefully with tarpaulin or similar material.
The tap changer, if provided, should be operated at 6 monthly intervals. Two of three runs
from one end of the range to the other and back are sufficient.
Heaters on Marshalling kiosks, etc. should be kept energized. If for this purpose, power
supply at the appropriate voltage to suit the heater is not available, temporary heaters
should then be installed to suit the site voltage. The provision of heaters is important and
failure to provide them may result in extensive damage to the contents of the kiosk because
of condensation.
If oil received in drums is not likely to be used immediately the drums should be stored in a
covered space where the temperature variation is minimum. If it is necessary to store the oil
outside, adequate protection must be provided at all times. Oil drums should be stored in
horizontal (lying) position with both the bungs also in horizontal position.
INDOOR STORAGE
The following items shall be stored indoor.
Oil Drums: To be kept Horizontal and over two wooden planks. Care is taken that the caps
shall be at 45 deg. from Vertical
Radiators & Conservator.
Frames, Pipes & Pipe supports.
Rollers, Cable Box.
INSTALLATION
LOCATION AND SITE PREPARATION
Transformer should be placed on the foundation so that easy access is available all around
and diagram plates, thermometers, valves, oil gauges, etc. can be easily reached or read.
Adequate electrical clearances are also to be provided from various live points of the
transformer to earthed parts.
ONAN type transformers depend entirely upon the surrounding air for carrying away the
heat generated due to losses. For indoor installation, therefore, the room must be well
ventilated so that the heated air can escape readily and be replaced by cool air. Air inlets
and outlets should be of sufficient size and number to pass adequate air to cool the
transformer. The inlets should be as near the floor as possible and outlets as high as the
building will allow. Where necessary, exhaust fans can be installed for the purpose.
The transformers should always be separated from one another and from all walls and
partitions to permit free circulation of air. Where walls are provided, it should be ensured
that the transformer gets good ventilation as mentioned above for indoor transformers.
Provision should be made for the emergency drainage of the oil from the transformers
(e.g. in case of fire in neighboring apparatus or bushing or the transformer tank), by
surrounding the transformer plinth with sump filled with small pebbles.
ASSEMBLING THE TRANSFORMER
By means of the Part list and the Transformer GA Drawing, the assembling of a fully
completed transformer is carried out according to the following Instructions. The following
precautions are to be taken:
GASKETS
The sealing system normally used against oil and gas in transformers and belonging components
has rubber bonded
cork gaskets at joints. Whenever the blanking plates are removed to fix detached parts such as
bushing turrets, etc., a new gasket shall be used while fixing the same. A set of new unused
gaskets of correct size and thickness is supplied with every transformer for this purpose.
Gaskets are best stored in such a way, that they must be protected from damp, oil and grease To
make a gasket joint, first clean the metal surfaces ensuring that they are free from oil, rust, scale
etc. Using one of the flanges as a template, punch the necessary bolt holes. Insert the bolts and
tighten the bolts sequentially,
a little every time so that uniform pressure is exerted on the gasket until the gasket is compressed
to about 2/3 of its
original thickness. Joints should not be subjected to pressure until tightening is complete. If care is
taken in making joints, and in handling the gasket, it is possible to break and remake a joint several
times, using the same gasket.
Bolts/studs should be tightened lightly and diagonally in the sequence. Do not over tighten,
otherwise gasket will get crushed.
OIL FILLING
Before filling oil in the tank, it should be tested to meet the requirements as per IS:1866. In case oil
does not meet the
requirement, it should be processed and shall only be used when meets the requirements. For
transformers dispatched gas filled, remove N2 gas from the tank by means of a vacuum pump and
take full vacuum and check & rectify if any leakage is there & keep the transformer under vacuum
for 12:00 HRS. The filling of oil inside the tank should be done under vacuum & fill the transformer
main tank up to top cover. Do not open any blank flange for erection without filling oil up to top
cover. Transformer of high voltage rating (66KV and above) have their tanks designed to withstand
full vacuum. Below 66KV class transformer, full or partial vacuum should not be applied without
consulting manufacturer.
When filling a transformer with oil it is preferable that the oil be pumped into the bottom of the tank
through filtration
machine. It should also be ensured that the tap changer board, relief vent diaphragm, conservator,
etc. are not subjected to full vacuum as these may not designed for the same.
In case the transformer is provided with OLTC of in-tank type, while evacuating the main
transformer tank, the diverter switch compartment must also be evacuated simultaneously so that
no undue pressure is allowed on the Tap Changer Chamber. While releasing vacuum, the Tap
Changer vacuum should also be released simultaneously. For this, one equalizer pipe should be
connected between main tank and tap changer.
DRYING OF TRANSFORMER USING FILTER MACHINE
Before the drying out is started all fittings coolers and associated accessories shall be fitted. Drying
out process of transformer is requiring care and good judgment. If the drying out process is
carelessly or improperly performed, great damage may result to the transformer insulation through
overheating etc.
Transformer should not be left unattended during any part of drying out period. Transformer should
be carefully
watched throughout the dry out process and also observations shall be carefully recorded. The
most practical method of drying out is by circulation of hot oil through a high vacuum filter machine
incorporating oil heater and vacuum chamber. The vacuum pump of the filter machine should have
capacity of creating vacuum as high as possible but not less than 710 mm of mercury. Where
possible, a vacuum pump can be connected to the tank top cover to keep the oil in tank under
vacuum consistent with tank suitability. This may speed up the drying out process. Oil should be
filled in tank under vacuum.
Coolers and Tap Changers are filled with clean dry oil. Oil samples are taken out from them and
tested. Further
circulation of oil is carried out till the oil results are satisfactory. The oil temperature as measured
by the oil temperature indicator should be of the order of 60C. In no case temperature of oil inside
the filter machine should exceeds 70C. The circulation is continued till insulation resistance and oil
samples test are satisfactory.
Plot IR values taken at regular intervals against temperature readings. It will be observed that in
the beginning IR values drop down as the temperature goes up. The IR values will be low till
moisture is coming out of the insulation and start rising before steadying.
EARTHING
Tank should be permanently and effectively earthed by means of connection to the earthing
terminals provided for the
purpose at the bottom of the tank. A good low-resistance earth is essential for adequate protection.
The earthing connection should be of sufficient cross-section to carry the LV line current for 30
seconds. Other accessories such as fan motors, oil pump motors, winding neutrals etc. should also
be earthed.
Earthing terminals are provided on tank for earthing of tank mentioned in General Arrangement
Drawing. Ensure that paint on the earthing terminal is removed before connecting the earthing
strips. Earth resistance should be measured and it should be within acceptable limit.
COMPLETION OF ERECTION WORK
Final topping up is now done up to a level in conservator commensurate with filled oil temperature.
Other such as wiring of various alarm/trip contacts, fan motors, pumps motors and other
apparatus, earthing of neutral and tank is also to be completed. The interposing valves between
the radiators and the tank are opened. The transformer and its equipment are cleaned carefully
from dirt, oil, lubricating grease etc. If the paint work has been damaged during transit or erection,
touching-up should be carried out with the least delay. The surface to be repainted should be
cleaned and free from rust and grease. If rust has begun to form, the surrounding area should also
be cleaned thoroughly as rust tends to spread beneath paint work. Failure to maintain the paint
work in good condition will result in considerable deterioration of the apparatus during storage or
service. After completion of erection work it should be checked thoroughly that there should be not
leakage. If any leakage found, it should be immediately arrested.
TOUCH-UP PAINTING
A basic principle at touch-up painting should be to restore a damaged paint coat on a surface to
the same quality and finish as of the surrounding surface. The touch-up paint should be limited to a
surface as small as possible. If the paint work has been damaged during transit or erection,
touching-up should be carried out with the least delay. The surface to be repainted should be
cleaned and free from rust and grease. If rust has begun to form, the surrounding area should also
be cleaned thoroughly as rust tends to spread beneath paint work. Failure to maintain the paint
work in good condition will result in considerable deterioration of the apparatus during storage or
service.
Both damaged and surrounding surface should be cleaned so that all grease, dust and other
impurities will be removed. Damages on the primer paint and grinding down to the steel surface
should be painted with two coats anticorrosive primer paint.
COMMISSIONING
After completion of proper erection, transformer is to be kept ready for commissioning. Before
putting transformer in service, following check points and Testing should be done to ensure the
healthiness of the transformer.
4.1 GENERAL CHECK POINTS
1. After erection & oil filling, transformer should be checked for any oil leakages from each and
every part. If found necessary tighten, replacement of gasket and o ring should be done.
2. Valves between Conservator to main tank should be fully open. All radiator valves are also fully
opened and locked in proper position.
3. Buchholz relay is to be mounted in position inclined angle of 5 to 7 degree. Ensure arrow mark
of relay towards conservator.
4. Air release from all air release plug / screws on Main tank cover, radiators, bushings, buchholz
relay, OLTC and Bushing turret to make ensure that no air remains inside the transformer tank.
5. Check the level of oil in main tank and OLTC conservator. Check the MOG operation by
depressing the float.
6. Ensure that, all the thermometer pockets are filled with transformer oil.
7. Minimum clearance between live parts to earth should be checked as per drawing.
8. Check the various protective devices (i.e. Buchholz relay, PRV, OSR, OTI, WTI and MOG)
should give proper alarm and trip indication.
9. Check the Buchholz relay practically by injecting the air from test cock or by draining the oil from
buchholz relay by closing both side valves. Ensure that, buchholz relay floats are not locked and
the relay is set at the desired position.
10. Check the color of silica gel in breather is dark blue. Also the oil in oil seal to be filled up to the
level indicator. Check the air passage of breather is not blocked.
11. Check weather transformer is earthed properly by two independent earth connections. Paint
between earthing terminal and earthing strip should cleaned properly for better connectivity. Also
OLTC, Marshalling box, cable box should also earthed properly. Also check for earthing for neutral
bushings.
12. Check the incoming voltage and set the OLTC on the corresponding tap position. In case of off
circuit tap changer brought to desired position and locked with bolt in plate hole. AVR can also set
as per required voltage variation, if applicable.
13. Check terminal clamp on bushings and cable and termination on bus bars.
14. Check functions of the breakers with transformer actual tripping operation.
15. Check oil level in OIP bushing from glass or small MOG (Mounted on bushing). It should be in
required level.
16. Check Explosion vent assembly mounting.
17. Check OLTC Explosion diaphragm in healthy condition.
18. Check Transformer painting. Apply touch paint at required places.
19. Check Name plate provided properly.
20. Check Roller wheel stoppers provided.
21. Check Valve between OLTC conservator and OLTC surge relay open.
22. Check BCTs for protection and metering connected to respective circuits properly.
23. Check Bushing thimbles and terminal cops tightness.
24. Check Anchor bolts for roller frames and cooler frame provided.
mounting of the GIS from shipping units, which were fitted up and tested in the factory
before
7.3. Tests after erection on site After erection, before putting into service, the gas-insulated
metal-enclosed switchgear shall be tested to check the correct operation and the dielectric
strength.
To reduce the risk of moisture and dust entering enclosures so preventing correct operation of the
switchgear, no obligatory periodic inspections or pressure tests are specified or recommended
when the gas-insulated substation is in service.
7.3.1. Checks and verifications
After erection before the high voltage tests the GIS should have a final inspection. The followings
should be checked step by step:
Conformity of the primary switchgear with the manufacturer's drawings (single line diagram,
gas schematic diagram, layout, section drawings of the different bays)
Conformity of the secondary control and protection circuits with the manufacturer's drawings
(schematic diagrams, connection diagrams, cable plans)
Conformity of the earthing system with the manufacturer's drawings (earthing plans)
Proper function of the direct current (DC) and alternating current (AC) auxiliary supply systems
Proper operation, alarm and position indication of each circuit breaker drive according to the
manufacturer's instructions (operational tests).
Proper operation and position indication of each disconnector and earthing switch drive
according to the manufacturer's instructions (operational tests).
Proper function of the interlocks operated locally from the local control cubicles. (The remote
operation is to be checked together with the central control equipment.)
Proper function of the measuring, protective and regulating equipment including the internal
heating and lighting of drives and cubicles.
Proper condition of each gas insulated flange connection (wholeness, cleanness, tightness of
nuts and bolts, greasing if necessary)
specifications) shall be evenly distributed on the trench floor with minimum thickness of 150 mm or
to a thickness prescribed in the project specifications.
2) Prior to start of cable pulling, Ravin recommends to conduct the DC sheath test on the reel in
order to ensure that no damage has taken place during transporting and handling of the cable.
Upon completion of the test heat shrinkable end caps, to protect against ingress of water or foreign
particles, must immediately seal the exposed area. Whenever a cable is cut, the exposed end shall
be sealed to protect from rain, mist or dripping or splashed water by heat shrinkable caps.
The drum should be mounted on transport and laying trailer. For cable pulling, the cable drum shall
be set at the opposite direction to the arrow painted on the drum that indicates the direction of
rolling during transportation. Care should be taken not to damage the cable by battens when
removing them from the cable drum. The direction of pulling should be so chosen so as to require
the least pulling strength at the end of the cable path.
3) Reliable communication between the drum, the head of the cable, on curves, entrance to duct,
intermediate post and the winch has to be established to effectively coordinate the work process.
The equipment to be used should be of proven reliability and should be thoroughly tested before
cable installation begins. Ensure that the winch has a pulling recorder and a tension meter, to
continuously monitor the cable pulling force. It should not exceed the maximum pulling force of the
cable recommended by Ravin.
4) Essential words or signals for cable pulling, at least START and STOP, are fixed and understood
by all the associated staffs. The meeting prior to cable pulling is recommended to decide position
of watchmen with communicative equipment to guide cable pulling works. Watchmen shall be
positioned every 50 metres and at every corner.
5) It shall be confirmed that cable drum, drum brake, winch, rollers, wire rope, drum for wire rope
and any other necessary tools/equipment have been set properly. Swivel shall be installed
between wire rope and pulling eye to prevent the cable from twisting. At the entrance to the cable
trench, a cable guiding and bearer stand is positioned, over which the cable taken off the cable
drum is pulled into the trench. The rollers that are inclined towards the centre ensure that the cable
is fed centrally into the trench. The rule for curves in the trench is that under no circumstances
should they fall below the minimum prescribed bending radius of the cable (15 x D of cable). The
cable rollers in straight portions shall be set at approximately 2 metre intervals to avoid the slack of
the cable pulling. Whereas the cable rollers in bend portions shall be set as close as possible, so
as not to be subjected to the sidewall pressures partially. Sufficient numbers of corner cable rollers
are positioned on the curves in the trench, to prevent cable sliding off. In field practice anchor pins
have proved ideal for anchoring the corner rollers.
6) Final check of trench shall be carried out so as to eliminate the risks that may damage the cable.
And it shall be confirmed that trench will not collapse at any portion along the cable route.
Timbering/Shuttering shall be provided securely prior to cable pulling at positions where trench
may or is liable to collapse.
7) When the cable is pulled into shaft or inclined tunnel, sufficient capacity of brake facilities shall
be applied so that the cable may not slip down due to its weight.
HANDLING
Damage to cables can occur due to the incorrect handling to which the drums and cables may be
subjected, causing breakdown of the drum flanges and in exceptional cases, movement of the
drum barrel takes place. Once this breakdown of the drum occurs, the cable is immediately
exposed to damage.
For guidance on handling, please refer to the sketches and notes contained in this booklet, which
should be followed closely.
Under no circumstances should a drum be rolled off a vehicle on to a cushion of sand, tarpaulin,
etc. This action could crumple the flanges and barrel of the drum, driving splinters and/or nails into
the cable.
STORAGE
If any time the drums of cable are required to be stored for reasonably long periods, e.g. prior to
shipment or installation, the following points should be noted;
The site for storage of drums should be well drained, hard packed soil, or preferably a concrete
surface, which will not allow the drums to sink and so give rise to damage due to the extreme
difficulty in moving drums when they are sunk into the ground.
All drums should be stored with the battens intact, and in such a manner as to leave sufficient
space between them for air circulation. Check and tighten tie bolts on the drums at regular
intervals.
Tier stacking of drums is not recommended. In no circumstances must the drums be stored on the
flat, i.e., with flanges horizontal.
All drums, during installation (i.e. when the battens have been removed), should be scotched so
that there is no danger of the flanges of drums coming into accidental contact with unprotected
cable on other drums. The cables should not be left unprotected.
Cables should be protected from direct rays of the sun by leaving the battens on or covering the
cables with thick black polythene sheet.
3. INSTALLATION
3.1 Minimum Temperature during installation
To avoid risk of damage during handling, the cable should be installed only when both the cable
and ambient temperature are above 0C and precautions have been taken to maintain the cable
above this temperature. However, the cables are suitable for operating at temperatures between
below 0C and the specified maximum limit, provided that they are not bent or struck when at
temperatures below 0C.
3.2 Laying
Normally cables are supplied on wooden or steel drums and great care should be taken during
running off to ensure that the cable does not kink. The drum position should be chosen so that the
longest length of straight trench is at the pulling end, with any severe bends as close as possible to
the drum.
It is important that the rolling of the drum to this position should be in accordance with the arrow on
the flange to prevent loose turns from developing during unwinding. The distance of rolling
should be kept to a minimum.
Drums should be mounted so that the cable is pulled from the top of the drum, and for very heavy
cable, it may be
necessary to use a ramp to support the cable during the passage into the trench. As the cable is
run off, the drum will rotate in the opposite direction to the arrow on the ROLL THIS WAY
marking.
The excavated trench should be carefully examined to ensure that there are no sharp edged
stones, foundations,
reinforcing metalwork, etc. which could damage the cable, and riddled earth or sand should be
used as a bedding.
Preparation of the trench, prior to installing the cable, comprises the installation of skid plates,
rollers, etc. and paying out the winch rope, if using power assistance. Cable rollers are necessary
to prevent the cable from touching the ground, and should be spaced a maximum of 2m apart for
normal size cables. Correct positioning of rollers is important to keep friction to a minimum.
The cable should preferably be drawn to its final position in a continuous manner. During stops, the
cable will settle between rollers and may cause high strain on men and machines during restarting.
Whether the pulling is manual or with a winch, it is necessary for one man to be stationed at the
drum with a plank of wood wedged against the flange of the drum so that over-running of the drum
is prevented if the pulling stops. Otherwise, many loose turns can easily develop on the drum.
When pulling by a winch it is advantageous for the cable end to be taken by hand as far as
possible before attaching the winch rope. This allows the leading cable rollers, skid plates, etc to
take the load and settle under well-controlled conditions. The winch operator must, at all times,
carefully observe the dynamometer to prevent overloading. On long pulls, good communication is
essential, preferably by radio.
When pulling a power winch, more attention has to be given to the maximum pulling load which is
permissible. For such installations a pulling eye attached to the conductors is necessary, and for
copper conductors a pulling tension of 6 kg force per sq.mm of total conductor area can be applied
(with the proviso of 2000 kg force maximum).
Graphite paste should be used for lubrication when cables are being pulled into ducts. For open
trench and straight installations, a cable stocking can be used. It is advisable, however, to protect
the oversheath with a layer of bitumen tape applied with 50% overlap.
Cables should never be bent to a small radius. As large a radius as space permits should be
adopted. Under no
circumstances should the bending radius be less than the minimum permissible limits. It is
particularly important to have a generous bending radius when cables are to be pulled by a power
winch, so as to keep within the maximum permissible pulling tension and to prevent the cable
being flattened around bends or in ducts.
The floor should be marked out in accordance with the switchgear assembly drawings usually
provided by the manufacturer to ensure that the switchgear is correctly located with respect to cable
trenches, building walls and other equipment in the room.
A datum line requires to be established usually along the rear foundation bolts, and using normal
geometric methods the switchboard and foundation bolt holes can be located. The method of
positioning the switchgear is dependent on a number of factors such as switchgear size, building
location, site accessibility and lifting tackle available.
Lifting eyes are often either incorporated into switchboards or can be screwed into pre-machined
holes, but generally slinging is necessary and this should be done strictly in accordance with the
manufacturers recommendations.
Without the use of cranes, however, the traditional manual methods utilising jacks and roller
bars are effective.
Care must be taken not to exert pressure on weak parts such as control handles during this
manhandling. Positioning of the cubicles should start near to the centre of the switchboard,
installing as early as possible the enclosures associated with any special chambers or trunking.
The first enclosure should be positioned and checked to ensure the side sheets are plumb and that
any runner rails are level in both planes. When the first enclosure panel is correctly set the
remaining enclosures should be positioned successively on alternate sides of this panel to make the
front form an unbroken line.
Adjacent enclosures should be bolted together after they have been correctly aligned using whatever
shimming proves necessary to make sure that the cubicles are vertically and horizontally true. The
fixing bolts should be positioned in the foundation holes and cemented in leaving adequate time for
the cement to set before tightening up.
Si
emens metal clad switchgear SIMOSEC - Cable connection in cable panel
A further examination of all incoming and outgoing circuit and auxiliary cables, including a test of
the correctness of the connections at the remote ends, should be done; this should include measuring
the insulation resistance and continuity of all cables and wiring including internal and auxiliary
connections.
Where appropriate, phase rotation checks must be made before three-phase drives are energised. All
moving parts must be inspected to ensure they are all operative. Dashpots must be filled to the
correct level with the right grade of fluid, and the operation and accuracy of meters and relays by
secondary or primary injection tests should be checked.
All cable boxes must be properly topped up and compound filling spouts capped off. All insulators
and spouts must be clean and dry and cover plates securely bolted up with all screws in position and
tightened and breather vents clear of obstruction. Ensure that the top of the switchgear is free from
all dirt and rubbish.
A final check on all incoming and outgoing cable connections to terminals ensures that they are
tight and have adequate clearance. High voltage testing can then be carried out to the test figures
laid down in the appropriate BS switchgear specification or as specified by the clients engineers
who should witness the tests and sign the test results.
After testing, precautions must be taken to discharge any static and remove the test connections
before bolting up any covers removed for testing. Before energising, the operation of all circuit
breakers and relays should be confirmed manually and electrically to ensure that no sticking or
malfunction is present, particular attention being given to manual trip and close operations and to
the operation of overcurrent relays and residual current devices.
We should also ensure that the axes of the winch drum should be exactly at right angle to rope
direction.
LIFTING THE CRANE:Depending on the weight of the crane, the strength of the rope, trusses, the crane can be lifted
by one winch or two or four winches. If the weight of the crane is not very high the crane
structure can be assembled at the floor & the complete crane can be lifted. in case the crane is
very heavy we may lift different portions of the crane in sequence as follows:1. End carriages complete with L.T. wheels fitted in position.
2. Main girders.
3. Hoisting trolley or crab.
4. Drivers cabin & other electrical components.
To simplify the positioning of the different components the crane should be match marked at
every joint. Every joint should be bolted only by means of machine bolts.
For the safety of the people engaged in erection work, the following safety rules should be
observed:1. When lifting the crane structure the dangerous zone of assembly must be protected with
flags barriers etc. & no un-authorised person should be admitted in the area.
2. Do not lift the crane if the erection area is badly illuminated.
3. Although the lifted structures should not be allowed to suspend for a long time but in case of
exception we must see that:(a) The safety factors of the ropes & cross girders should be twice than the normal working.
(b) The last line of rope running off the blocked should be clamped near the block.
(c) In case the load is lifted by means of hand winch, remove the handles, apply & secure the
brakes.
(d) Post workers to ensure security.
4.
5.
It is strictly forbidden to stand or walk under the crane when the crane is being lifted.
The scaffolds must comply with the safety rules. the fitter working on top, must handle the
parts & tools carefully so as to prevent them to fall down.
The erection supervisor must ensure that all the components are assembled in accordance to
the sub assembly drawings. after the crane has been fully erected, we must do the electrical
connection exactly as per its wiring diagram. Before we actually do the load test we must run
all the motions in idle condition. during idle running of different motions we should particularly
observe the following:(a)
Eccentric running of moving parts.
(b)
Alignment of shafts.
(c)
Fauling of moving components.
(d)
Any un-usual noise.
(e)
Presence of lubricant at desired surfaces.
After the idle running of different motions & satisfactory performance of motors, limit switches,
brakes & controllers we may go ahead with load testing of the crane in accordance to relevant
Indian standards.
If the contract for erection & commissioning of the crane is not given to the manufacturer of
the crane, it will be desirable to seek their supervision during Erection & commissioning. This
will ascertain the alignments of components & thus longer life of the crane.
Page 96 of 96