Lesson 03
Project Tasks
Objectives
By the end of this lesson, you will be able to:
Rearrange tasks
Indicators
Task Mode
Task Name
Duration
Duration column indicates the total working time required for a task.
Start
Finish
Predecessors
Resource Names
Predecessors column indicates the task that precedes the given task.
Resource Names column contains details of materials or human resource
needed for the task.
In case of manually scheduled tasks, you need to enter the duration and start date of the task. The finish date is
calculated according to the duration entered.
In case of auto scheduled tasks, you need to enter the duration of the task. The start and finish date is calculated
automatically. The start date of the first task is by default set to the project start date.
Manually Scheduled
Auto Scheduled
Project Outline
While creating a Task List, the Project Manager can create a project outline by grouping tasks.
Tasks are grouped as summary tasks and subtasks.
In Microsoft Project 2013, the summary tasks are easily recognized as they are in bold. The summary task
encapsulates details of all subtasks.
Expand or collapse arrow next to the summary task can be used to collapse and expand the outline.
Start-to-Start
P
Finish-to-Finish
P
Start-to-Finish
Milestones can be recognized in Microsoft Project 2013 as tasks that have zero duration.
10
Rearranging Tasks
Tasks and subtasks can be rearranged in the project plan using the cut and paste commands.
Select row
Cut
1
Paste
3
11
When tasks with dependencies are rearranged, the links will be lost, unless the
dependent tasks are shifted along with the main tasks.
12
Inactive Tasks
All tasks added in Microsoft Project 2013 are entered as Active Tasks. Tasks that are on hold or are not a part of active
tasks can be set as Inactivate Tasks.
13
Timeline View
Timeline View allows a Project Manager to view all the project related information at a glance.
14
Project Summary
Project Summary summarizes the timeline of the entire project. Project summary is automatically created by Microsoft
Project 2013, however, it is hidden by default.
1
15
16
Knowledge Check 1
a.
b.
c.
d.
17
Knowledge Check 1
a.
b.
c.
d.
18
Knowledge Check 2
While creating a Task List, how can a Project Manager create a project outline?
Select the answer.
a.
b.
c.
d.
As summary tasks
As active tasks
By grouping tasks
By creating subtasks
19
Knowledge Check 2
While creating a Task List, how can a Project Manager create a project outline?
Select the answer.
a.
b.
c.
d.
As summary tasks
As active tasks
By grouping tasks
By creating subtasks
20
Knowledge Check 3
Ideally, which of the following is needed while auto scheduling the task?
Select the answer.
a.
b.
c.
d.
21
Knowledge Check 3
Ideally, which of the following is needed while auto scheduling the task?
Select the answer.
a.
b.
c.
d.
22
Knowledge Check 4
When tasks are linked in a project, which of the following dependency is created by default?
Select the answer.
a.
b.
c.
d.
Finish-to-Start
Start-to-Start
Finish-to-Finish
Start-to-Finish
23
Knowledge Check 4
When tasks are linked in a project, which of the following dependency is created by default?
Select the answer.
a.
b.
c.
d.
Finish-to-Start
Start-to-Start
Finish-to-Finish
Start-to-Finish
Answer: a. Finish-to-Start
Explanation: When tasks are linked, finish-to-start dependency is created by default.
24
Knowledge Check 5
a.
b.
c.
d.
Project tasks
Project milestone
Project outline
Project summary
25
Knowledge Check 5
a.
b.
c.
d.
Project tasks
Project milestone
Project outline
Project summary
26
Summary
Here is a quick recap of what was covered in this lesson:
Tasks are added by entering appropriate task name in the task Sheet, available in
the Gantt Chart view.
A project is outlined as summary tasks and subtasks.
27
Thank You