SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)

SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


Pressure Testing of Pressure Vessels and Fin Fan Coolers

SATIP-A-004-04

PROJECT TITLE:

ITEM
NO.

1.0

APPROVED DATE

TASK / ACTIVITY

QUALITY
PROCEDURE

QUALITY
RECORD

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

SAUDI
ARAMCO

Pressure Testing Procedure


a) Test Procedure
b) Pressure Test Diagram

SAIC-A-2001

RH1

RH1

1.2

Review of Test Package Preparation

SAIC-A-2003

RH1

R2

1.3

Lay-Up Procedure

SAIC-A-2007

RH1

RH1

Verification of test medium

SAIC-A-2008

SATR-A-2014

RH1

R2

Pre-Test Inspection of Pressure Vessels

SAIC-A-2025

SATR-A-2007

H1

H1

* See Note 1 (General Notes)

APPLICATION

3.1

3.2

Test Preparation & Verification of


Testing equipment (including safety
requirements)

3.3

Filling and Pressurization

SAIC-A-2013
or
SAIC-A-2020

3.4

Visual Inspection at Test Pressure

SAIC-A-2015

4.1

De-Pressurization & Water Disposal

SAIC-A-2017

4.2

Lay-up

SATR-A-2009

4.0

* See Note 1 (General Notes)

MATERIAL RECEIVING

2.1
3.0

REMARKS

DOCUMENT REVIEW

1.1

2.0

MECHANICAL

25-May-05
CONTRACTOR/SUBCONTRACTOR

WBS/BI/JO/NO.

PROJECT PHASE &


Activity Code

DISCIPLINE:

SAIC-A-2009

SATR-A-2002
SATR-A-2003
SATR-A-2004
SATR-A-2005
SATR-A-2006
SATR-A-2001
for test
Manifold)
SAIC-A-2009

SATR-A-2001

H1

W1

W1

H1

H1

W1

H1

W1

POST- TEST

SATR-A-2009

Page 1 of 2

Forms SATR-A-2003 & SATR-A-2004 shall be


used for 24-hr recorded hydrostatic test, Ie;
underground piping or piping whose joints are
covered before pressure testing.

Use:
a) SAIC-A-2013 for hydro testing
b) SAIC-A-2020 for pneumatic testing

SAUDI ARAMCO ID/PID - REV 1 - 5/18/05 (Standards Cutoff - August 2004)


SATIP No.

SAUDI ARAMCO TYPICAL INSPECTION PLAN


Pressure Testing of Pressure Vessels and Fin Fan Coolers

SATIP-A-004-04

PROJECT TITLE:

ITEM
NO.

APPROVED DATE

WBS/BI/JO/NO.

PROJECT PHASE &


Activity Code

QUALITY
PROCEDURE

TASK / ACTIVITY

QUALITY
RECORD

DISCIPLINE:

25-May-05

MECHANICAL

CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ASSIGNMENTS
CNTRCTR

REMARKS

SAUDI
ARAMCO

GENERAL NOTES
1

The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may
adjust the levels of Saudi Aramco participation based upon the Contractors performance.

Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization.

Witness:
QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC
organization representative is not present.

Hold:
attendance.

If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in

LEGEND
W1

100% Witness Inspection/Test

H2

Sample Hold Point for QC Inspection or Test

RH1 100% Review and Approval of Documents

W2

Sample Witness Inspection/Test

R1

100% Review of Documents

RH2 Sample Review and Approval of Documents

H1

100% Hold Point for QC Inspection or Test

R2

sample Review of Documents

Page 2 of 2