Documente Academic
Documente Profesional
Documente Cultură
1. According to CESMM3, the BOQ item measured in number (nr) for trial pits (i.e. code B
11* or B 12*), does not involve any excavation activity and therefore it has no cost
significance related to the size of the pit. The rate constitutes the cost of setting-out/marking
the pit location, and shifting and setting up the excavating equipment/gang to the location,
which cost does not vary if the pit becomes larger.
2. The excavation itself should have been measured in the BOQ as a depth in metre (m)
item, also stating the plan area (as code B 13* and Rule A1). If the pit becomes larger (than
the stated plan area), then it is the rate of this item that would vary, and your method can be
used to calculate the new rate.
3. If however your BOQ is not measured strictly in accordance with the Rules of CESMM3,
then you need to first establish what the plan area of the pit that was fairly and reasonably
considered for the tender purpose and demonstrate that it is smaller than the required new
size before you apply your method. Remember to give a discount for the fixed costs of item 1
(if it is not measured as a separate item), as they do not increase when the pit becomes larger.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Respected Sir,
Hope this email finds you with good health. I'm one of the Alumni of SCA classes. I'm working for a
Contractor. Kindly advice me to calculate the penalty clause under a Procure and Construct (PC)
Contract which is as follows:
In the event the Contractor delays the performance, completion and delivery of the complete Work
within the time specified in the Contract, a delay penalty shall be imposed and assessed on the basis
of the project's daily average cost by dividing the Contract value by the performance period according
to the following:
a)
The penalty against the first period of delay shall be equivalent to 1/4 of the daily average cost for
each day of delay until it reaches either 15 days or 10% of the Contract Period whichever is longer.
b) The penalty against the second period of delay shall be equivalent to 1/2 of the daily average cost for
each day of delay until the delay for the two periods reaches either 30 days or 15% of the Contract
Period whichever is longer.
c) The penalty against the third period of delay shall be equivalent to full daily average cost for each day
of delay following the longer period mentioned in (b) above.
If a delay in performance prevents use of the Work then the total amount of the penalty shall not
exceed 10% of the total Contract Price.
d) If, in the judgment of the Employer, the delayed portion of the Work will neither prevent the full
utilization of the Work at the specified completion date, disrupt the use of other facilities, nor adversely
affect the use of that part of Work completed, then the penalty shall be applicable to value of delayed
Works in accordance with the method applied in computing the penalty applicable to original Work,
provided that total amount of penalty shall not exceed 10% of the value of delayed Work.
Project data:
Contract Price: Dhs 250,000,000/Final accounting will be on the basis of the actual quantities of the Work executed
Time for Completion: 130 weeks from Commencement date
Completion including testing and commissioning and ready for TOC: week 126*
Complete demobilization: week 130
* Delay penalty as specified above shall apply to Contract Milestone
Since there are no definitions given for the Contract value, performance period and
Contract Period there are likely to be disputes. For the purpose of the following
comments it is assumed that the Employer and Contractor would agree the Contract
value to be the Contract Price (excluding variations/claims) and performance
period/Contract Period to be the completion period (excluding delays and Defects
Liability Period)
Completion period
126 x 7
882 days
250,000,000 / 882
283,446.71
In both Type (a) penalties and Type (b) penalties stated above since 10% or 15% of 882
days amounts to periods longer than the stated 15 days or 30 days, the longer period is
taken into consideration
Type (a) penalty = 883rd day to 970th day
= 88 x 283,446.71 / 4 = 6,235,827.62
= 12,471,655.24
24,943,310.48
On the 1060th day penalties would reach the limit of Dhs. 25 Million.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
The correct way to administrate the contract is to wait until the TOC for the whole of the
Works is issued before dealing with the Statement at Completion. Payments can however
continue based on further interim payment certificates.
Now that the Engineer has incorrectly asked the Contractor to submit the Statement at
Completion, the following options could be considered:1. Issue immediately a TOC for the whole of the Works and then certify the Statement at
Completion, or
2. Inform the Contractor that an Interim Payment Certificate would be issued against the
submitted Statement at Completion, and the Contractor has to submit the Statement at
Completion again after the TOC for the whole of the Works is issued, or
3. Consider the issued TOC to be for the whole of the Works and the instruction to
complete the outstanding work as soon as possible to be read as as soon as
possible during the Defects Liability Period (which can be regularized by a letter)
and certify the Statement at Completion.
Whichever option is selected, the payment being certified should represent the value of work
completed to date and not to a date in the past. Also if 1 or 3 is selected, 50% of the Retention
Money too should be released.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Hi prof Sam,
I hope that all is well,
I have a question, I am preparing a Contract Agreement. After the agreement page, I
attached the "Appendix to Tender". Our Client commented to replace it with the
"Appendix to the Agreement".
Mostly, the contracts that I encountered, it is Appendix to Tender since the basis of
the Contract is the Tender, and there were some I've seen that consultants use as
"Appendix to Contract" or "Appendix to the Agreement"
Can you please enlighten me which one is the correct as per FIDIC?
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Thanks Prof.
yvette
Following Questions have been raised during recent classes:1. How can we claim cost reimbursement and EOT due to late shop
drawings approval by the Engineer if we did not show shop drawing
activity in clause 14 programme?
Introduce new activities with realistic durations, (compatible with other provisions in
the Contract) link them logically to amend the Clause 14 programme to include shop
drawing submission/approval, and use this amended programme as the base-line to
demonstrate the impact of late approvals. Remember to state in the claim that fair
and reasonable modifications have been made to the clause 14 programme, without
which it is not possible to demonstrate the impact.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
2. POM(I) requires net measurements to be used for all items, but when
measuring dry wall cladding above ceiling level (BOQ description refers to
full height), can the Engineer insist in measuring the height only up to
ceiling sofit and not beyond?
No. Net does not mean visible only. But, the Contractor is required to prove that
it is not physically possible to stop the dry wall cladding at the ceiling sofit, and that
it should extend above ceiling level (or that the design drawings require or Engineer
has instructed to extend it above ceiling level), for structural stability or other
reason, in order to get payment for full height.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
3. Where the pricing in the Contract is imbalanced, how can the Contractor
support his Claim?
The claim has to be based on actual additional costs incurred at site (and off site)
supported by contemporary records, which should show the actual (but fair &
reasonable) resources used when compared to the fair and reasonable resources that
could have been used, had the delay/disruption not occurred. Therefore it has no
connection with any imbalance in the pricing found in a BOQ.
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Regards,
Prof. Sam.
Prof. Indrawansa Samaratunga PhD, DSc
FRICS, FAIQS, FIQSSL, FCIArb, FCIOB, FCMI, FASI, FBEng
Chartered Surveyor, Chartered QS, Chartered Manager, Chartered Builder
Dear Alumni,
Media reports regarding the creation of 85 Million new jobs in the region by 2020, discussed
at the World Economic Forum, would make it necessary for you to decide where you want to
be at the beginning of the New Year 2012. With an influx of thousands of Contract
Administrators into the industry, you need to progress to more senior positions to make room
for the newcomers. Additionally you need to be competent in training the newcomers.
Both these needs would no doubt be a threat to those who are stagnant at their current
positions due to lack of advanced knowledge required for progression, whilst these could also
be the opportunity to move forward by deciding to gain the advanced knowledge required to
practice your discipline at senior / managerial / advisory positions as an Engineer, Quantity
Surveyor, Project Manager, Planner, Architect or other professional who is also required to
administrate contracts in addition to practising his or her own discipline.
Visit www.drsam.zzl.org