Documente Academic
Documente Profesional
Documente Cultură
DOC: CTG-PWHT/PETROSTEEL/008
REV 0
ISSUED ON: 05 December 2011
SREERAM METHIL
Operations Manager
This document is issued for use by CORE TEAM GLOBAL GENERAL CONTRACTING EST.
Neither the whole nor any part of this document may be reproduced in any form without prior
written consent of CORE TEAM GLOBAL CONTRACTING EST.
1 of 9
CORE TEAM
25.09.2014 08:27
TABLE OF CONTENTS
1.
SCOPE
2.
GENERAL REQUIREMENTS
3.
4.
5.
PROCEDURE
6.
HARDNESS TEST
7.
DOCUMENTATION
ATTACHMENT
1.
2.
3.
4.
PWHT REPORT
5.
TIME SHEET
6.
CALIBRATION CERTIFICATE
2 of 9
CORE TEAM
25.09.2014 08:27
1.
SCOPE
1.1.
This procedure outlines the minimum requirement for the external local post weld heat treatment
requirements associated with welded joints of pipe, nozzles, vessels and related components using
electrical resistance methods. The work shall be carried out in accordance with the codes and
specifications described in section 3.0 below.
1.2.
Post weld heat treatment shall be performed after all welding and repairs but shall be performed
prior to any hydro test.
2.
GENERAL REQUIREMENTS
2.1. This procedure shall be used to determine post weld heat treatment requirement including
equipment, heating methods and inspection techniques.
2.2. The following definitions are applicable to this procedure.
2.2.1.
2.2.2.
Stress Relief
Uniform heating to a specified temperature below the lower critical temperature for a sufficient
period of time to relieve the major portion of residual stresses, followed by uniform cooling.
3.
3.1. The edition of the code and specifications described during the execution of the job requirements will
be applicable.
3.1.1. ASME Boiler and Pressure vessel code section VIII Div. 1 (2010 Ed.)
3.1.2. ASME B 31.3 chemical plant and petroleum refinery piping (2010 Ed.)
3.1.3. API- 650 welded steel tanks for oil storage (10
th
Edition, 1998)
4.
The equipment used by CORE TEAM GLOBAL is purpose built having proven ability in the field.
4.1. POWER SOURCE
Power source will be 380/440 three phase primary supply and gives 3 ph output voltage of
either 60 V to 80 V AC between phase and neutral .The unit is fitted with circuit breaker and panel mounted
cam lock output terminals
4.2 TEMPERATURE CONTROLLER
3 of 9
CORE TEAM
25.09.2014 08:27
C to 800
All thermocouples to have initial calibration check and thermocouple wire conformance certificate
1996
Description:
2 X 13/0.2 mm Copper Constantan compensating cable type VX, PVC/PVC laid flat BS 1843 color code Positive
white negative blue and sheath cover red
Copper Constantan compensating cables shall be used with the following conditions:
1. The junction between the copperconstantan compensating cable and the type K thermocouple lead shall
be a minimum of 0.5 m outside the insulated area
2. The acceptable temperature range of the junction between the compensating cable and thermocouple lead
0
is from 0 to 80
3. Attachment of thermocouple shall be capacitance discharged direct wire, the gap between not to exceed
6mm .Actual junction to be insulated using thermocouple high temperature Putty to protect from direct heat
source
4 of 9
CORE TEAM
25.09.2014 08:27
Heating elements used for PWHT shall be flexible ceramic mat heaters of 60 V, 2.7 KW. Standard sizes are 205
X250 mm, 255X205 mm, 305X165 mm, 380X145 mm and 1220X45 mm. Flexible ceramic mat heaters are
o
C. End of the heaters are provided with cam lock plug and socket connections and
the elements are attached by black annealed iron wire and mild steel 12 mm wide banding strap Flexible
ceramic mat heaters can be easily wrapped around the pipes with the following conditions
1.
The width of the circumferential band to be heated shall be at least SIX (6) times the thickness of shell
material being welded from both edge of weld ,and should not be less than 25 mm
2.
Centre line circumferential gap between two band of elements shall not exceed 30 mm or t
whichever is lesser and the longitudinal gap between elements shall not exceed the wall thickness or
50 mm whichever is less ,care shall be taken to ensure that there is no gap in the 6 oclock position
3.
In case if the welding is of two separate wall thickness then the thickness of the thicker pipe will be
considered
4.6 INSULATION
Ceramic fiber mats of thickness 25 mm and size 300 x 600, 600x 600,900x 600, 1200x 600, 1800x600 with SS
3
wire mesh cover shall be used as thermal insulation .Density of the ceramic fiber shall be 128 kg /m
.The
insulation shall extend a minimum distance of 300 mm either side of the weld joint to heat treated .The
o
insulation shall not be removed until the heat treatment is completed and the temperature is below 150
C.
Open end of the pipe shall be closed off to stop air flow through pipe that will lower the temperature of the
inside surface unless the internal surface is insulated .
The number of the layers and extent of insulation will depend on the wall thickness, pipe or fitting diameter,
gradient requirements and the site conditions and the minimum requirement shall be 2 layers of density
3
128 kg /m
5 PROCEDURE
5.1. PREPARATION
5.1.1. Prior to the start of heat treatment the piping shall be inspected to ensure that all restraints have
been removed so it is free to expand and contract.
5.1.2. The work shall be properly supported during heat treatment to prevent sagging and distortion.
5.1.3. Pipe ends shall be blanked off prior to PWHT to prevent the effects of drafts inside the pipe, free
venting shall be observed in the preparation.
5.1.4. The work being heat treated shall be protected from impingement of wind and other types of
inclement weather. It shall be supported (restrained as needed) to prevent war page and other distortion.
5.1.5. Protect flanges faces and threaded connections to prevent damage from scaling during the heat
treatment by a suitable paint or compound (anti-sieze compound/ deoxaluminite). Material shall be heat
resistant and shall be applied by brush and properly covered with ceramics mats during the post weld heat
treatment.
5 of 9
CORE TEAM
25.09.2014 08:27
5.2.1. It shall be ensured that there shall be at least one Thermocouple for each separately controlled
zone of heating elements for every 450 mm (24 inch) length of weld seams being heat treated.
If localized PWHT of piping or nozzle welds in used, the following number of equally spaced recording
thermocouples (T/C) shall be used.
A.
B.
C.
D.
E.
Type A
Type B
Type C
Type D
6 of 9
CORE TEAM
25.09.2014 08:27
If localized PWHT of the vessel shall is used, it shall be monitored used at least 4 sets of thermocouples,
with each set consisting of one thermocouple each on the inside and outside surfaces. Each set shall be
placed at 90 intervals around the vessel circumference.
Additional T/C are required if multiple heat control zones are used, in which a control zone is not
monitored by any of the primary T/Cs.
5.4. ALARM SCANNER
The equipment used is incorporated with an alarm scanner which can scan 6 thermocouples
at one time. If one or more gets out of step with other and starts to fall behind an alarm will sound. Similarly if
it exceeds the High alarm setting the alarm will sound. If either fault is not cleared within 5 minutes, a second
relay operates which may be used to switch off the faulty circuits. If an alarm sounds, the operator shall stop
wrapping and connecting other welds and returns to the machine.
5.5. POST WELD HEAT TREATMENT
o
C/hour
divided by the material thickness in inches, but in no case shall be more than 222
and alloy steel respectively. Heating and cooling rates are regardless of wall thickness and shall conform to the
PWHT requirement in the individual approved welding procedure.
5.6.2. Soak temperature to be set at a mean difference between the upper and lower limits and the maximum
o
temperature
Carbon Steel
C-649
Alloy Steel
C-746
the material thickness in inches, but in no case shall it be more than 222
C / hour divided by
C/ hour). At
316
C the power shall be turned off and the weld will be allowed to cool naturally with the insulation in place.
The insulation shall not be removed before the temperature has cooled to below 150
C.
After PWHT the TCs shall be removed and the areas of attachment filled or ground to clean metal. After
thermocouples are removed, the areas shall be visually examined or liquid penetrant inspected. PT report
chart.
7 of 9
CORE TEAM
25.09.2014 08:27
6. HARDNES TEST
6.1. GENERAL
6.1.1. This test method covers the determination of the hardness of the materials, parent metal and the
weldments after PWHT is completed. Acceptable methods for verifying hardness of materials shall conform to
ASTM standard.
6.2. Hardness test shall be carried out with strict compliance set forth in project specification/standards and in
accordance with Brinell Hardness Examination Procedure No: Core Team Global 800-003, Rev. 04.
7. DOCUMENTATION
7.1. Prior to the start of work Core Team Global or fabricator shall prepare a table listing each joint or
component requiring heat treatment, which shall be submitted to Saudi Aramco Inspection for review. The
table shall include the following for each joint or component: location, drawing number, diameter, wall
thickness, material, heating rate, soak temperature, soak time, and cooling rate.
7.2. The post weld heat treatment strip chart shall have a unique identifying number that can be tied back in to
the inspection report.
7.3. The chart speed shall be calculated and noted on the strip a chart at the start of heat treatment.
7.4. The start and end of the soak period shall be clearly mark on each strip chart
7.5. The simple sketch of the element/ heat zone TC layout shall be drawn on the strip chart or attached to it
on a separate sheet of paper.
7.6. Temperature recorders shall be calibrated every three months and a current calibration sticker shall be
maintained on the recorder.
7.7. Hardness test on heat affected zone and weld metals shall be recorded and shall be submitted along with
PWHT reports, sketch or isometric drawing.
7.8. The contractor shall verify the actual thickness of the job and the heating rate and cooling rate shall be
reduced if the thickness exceed the drawing requirement in the actual job as per Para 13.4 of SAES-W-011 and
Para 5.6 of this procedure.
8 of 9
CORE TEAM
25.09.2014 08:27
Report No :
Project
Date :
Job No :
Order No :
Chart No :
oC
o
Soaking Temparature
Signature (Technician )
Hrs Min
Soaking Period (Min)
Name :
o
C/HR
Signature (Client )
o
C
APPROVALS
Tc Color
Joint
Diameter Sch/W.T
Number
TC Nos
Type
Remarks
Code
YES
YES
NONE
NO
INSPECTED BY
Name:_________________________________________________Signature ____________________________Date :_____________________________
FOR CLIENT
Technician's Name
NAME
Reviewed &Approved By
SIGNATURE
Date
DATE
9 of 9
CORE TEAM
25.09.2014 08:27