Documente Academic
Documente Profesional
Documente Cultură
ABSTRACT
INTRODUCTION
This work presents an experimental investigation that correlates the stiffness changes of reinforced concrete beams with
the amount of steel cross section loss and concrete covercracking morphology due to localized corrosion of the embedded steel. Ten concrete beams (100 by 150 by 1,500 mm) with
the central portion contaminated by chlorides placed during
mixing of the concrete were used in this investigation. In addition, two beams without chloride contamination were used as
controls. Corrosion was further accelerated in the chloridecontaminated beams by impressing an anodic current to the
single no. 3 steel reinforcement bar (10 mm diameter). During
corrosion acceleration, the beams were tested under flexure
by a cyclic loading-unloading procedure. The changes on the
stiffness (slope of the force-displacement diagram) and crack
morphology of the concrete cover were recorded periodically
while the specimens were corroded. The results obtained
showed a decrease in the flexure stiffness as much as 32%
for a 14% reduction in the rebar radius.
862
0010-9312/04/000149/$5.00+$0.50/0
2004, NACE International
CORROSIONSEPTEMBER 2004
TABLE 1
Experimental Parameters and Results from Previous Investigations 2-10
Exposure
Time
Corroded
Area
(cm2)
% Cross
Section
Loss
Crack
Width
(mm)
3, 20, 100
A/cm2
70 to 120 days
70 to 190
0.8 to 1.2
0.05 to 2.0
Reported 3 V
Reported 3 V
1 to 28 days
28 days
170 to 280
390
3.6 to 19.2
0.8 to 9.2
0.06 to 0.46
Not reported
Almusallam, et al.
(Slabs), (Pullout)4
3 mA/cm2
1 to 2.5 days
670
1 to 75
Not reported
5 A/mm2
126 h
408
<1
Not reported
1 to 4 mA/cm2
3 mA/cm2
15 to 18 days
16 to 64 h
540 to 2,300
540
2.5 to 10
1.25 to 5
Not reported
Not reported
100 A/cm2
100 A/cm2
4,100 to 7,700
4,700 to 8,200
10.1 to 26.3
9.1 to 17.8
0.2 to 0.6
0.8 to 4.0
0.5 mA/cm2
3 to 15 days
2,010
2.5 to 12
0.1 to 0.75
Natural
corrosion
12 to 60 months
33.0 to 47.7
2.3 to 15.8
0.08 to 1.25
Author
Andrade, et al.
(Prisms)2
Cabrera
(Pullout)3
(Beams)3
Accelerated
Corrosion
Procedure
EXPERIMENTAL PROCEDURES
Specimen Fabrication
In the present study, twelve 100 by 150 by
1,500-mm concrete beams reinforced longitudinally
with one no. 3 reinforcing bar (rebar) were made. To
eliminate the need to use wet/dry cycles using salt
water, chlorides were introduced in ten beams at the
location where the damage was intended. Three different chloride-contaminated length sections located
at the middle of the beam (LC in Figure 1) were used:
25 mm (in V07 and V08), 250 mm (in V04, V05, V06,
V10, V11, and V12), and 1,000 mm (in V03 and V09).
The chloride ion contamination of 3 wt% of cement
(~12 kg/m3) was obtained by adding NaCl (table
salt) during concrete mixing, as used in earlier studies.2,7-8,11,13-14 Beams with LC values of 1,000, 250, and
25 mm were defined as specimens with generalized
corrosion (GC), localized corrosion (LC), and highly
localized corrosion (HLC), respectively. Two control
beams (V01 and V02) were included in which there
was no chloride-added zone, and no accelerated corrosion technique was performed on them both.
The beams were cast in wood molds at a concrete
factory. The fabrication of all the test beams required
two separate pours. First, a free-chloride concrete
864
CORROSIONSEPTEMBER 2004
current density with similar results as studies performed with half this current density.15 Therefore, the
chosen anodic current density used in this investigation was 200 A/cm2. A custom-made multi-channel
galvanostat provided a regulated current source
for each specimen. More details may be found elsewhere.14-15 When the targeted RRL was reached, the
applied current was stopped and each beam then was
disconnected from the galvanostat system and was
kept positioned in their respective metallic supports
for further evaluation.
(1)
x AVER =
WG 103
Fe L C
(2)
(a)
(b)
FIGURE 2. Typical crack pattern observed for (a) LC beam (V10) and (b) GC beam (V03) at Day 42 and Day 80 of the
corrosion stage. The photographs were taken from the bottom face, after rotating it, during crack survey.
866
CORROSIONSEPTEMBER 2004
TABLE 2
Experimental Results
Beam
(H)
V01
V02(H)
V03
V04
V05
V06
V07
V08
V09
V10
V11
V12
(A)
(B)
(C)
(D)
(E)
(F)
(G)
(H)
LC(A)
(mm)
CWMAX(B)
(mm)
WG(C)
(gm)
100
25
25
25
2.5
2.5
100
25
25
25
7.0
4.0
4.0
8.0
0.3
0.4
11.0
8.0
2.0
0.8
85.1
19.9
21.0
40.1
3.2
2.7
83.3
37.1
12.9
12.6
WF(D)
(gm)
104.6
29.8
29.2
56.9
2.88
2.88
103.4
50.5
14.4
13.5
ACOREFF(E)
(%)
xAVER(F)
(mm)
xAVER/r0(G)
81.4
66.8
71.9
70.5
111.1
93.7
80.6
73.8
89.6
93.3
0.363
0.339
0.358
0.684
0.546
0.460
0.355
0.633
0.220
0.215
0.076
0.071
0.075
0.144
0.115
0.097
0.0747
0.133
0.046
0.045
K (8)EQ K ( t )
K (8)EQ
100
(3)
( I dt ) A W
nF
(4)
867
(a)
(b)
The use of Equation (4) to estimate the metal loss implies that the transformation of the impressed current
to metal loss is 100% efficient. Studies conducted by
previous investigations indicated that calculated losses could overestimate actual losses.2,7-8,13-15 Therefore,
a combination of predictive and gravimetric methods
was used, whereby initial estimates of mass loss and
RRL were calculated based on current measured and
elapsed time.
As mentioned before, a constant current (I) was
impressed through the system to accelerate the rebar
corrosion. The applied current was controlled automatically and monitored periodically (at least three
times per week) during the entire applied current
stage until reaching the target RRL. When reaching
the target RRL, the beam was disconnected and the
experiment ended. Figure 4 shows typical current
monitoring results (applied current in amp vs time in
days) for two beams (GC, V03 and V09). The theoretical (Faradaic) steel mass loss (WF) values were calculated from Equation (4). The results of WF for each
beam are presented in Table 2.
After reaching the target RRL, the rebar was retrieved from the concrete and the corrosion products
were cleaned using an inhibited HCl solution. The
mass loss of the steel rebar (WG) was estimated afterward by subtracting the post- from the pre-corrosion
masses. The results are also listed in Table 2.
The apparent corrosion efficiency, ACOREFF, of the
accelerated corrosion system is estimated by the following equation:
WG
ACOR EFF =
100
WF
(5)
(c)
FIGURE 3. Typical force-displacement diagrams for (a) a control
beam (V02), (b) a generalized corrosion beam (V03), and (c) a
localized corrosion (V04) at 8, 29, 57, and 98 days of the corrosion
acceleration stage (no corrosion was applied to the control beam
V02). Day 8 is the test performed at the 8th day.
868
The xAVER values for the rebar were estimated using Equation (2). The estimated values of WG, xAVER,
and xAVER/r0 are presented in Table 2 (r0 = original
rebar radius, mm). This calculation assumes that the
corrosion is uniform at the anodic region of the rebar.
In general, this is not essentially true. Steel corrodes
in concrete due to the presence of chlorides (marine
environment scenario) by forming localized anodic
regions called pits. In most of the cases, these pits
are formed uniformly on the surface of the bar (when
the chloride content is large and/or the concrete is
highly porous), giving some effect of uniform corrosion. In reality, if the bar surface is observed by using
a magnifying lens, many pits cover the surface. In
addition, the average corrosion penetration at time t,
CORROSIONSEPTEMBER 2004
TABLE 3
Experimental Values of K(t)EQ in KN/mm(A)
Time
(days)
V01(B)
V02(B)
V03
V04
V05
V06
V07
V08
V09
V10
V11
V12
4.57
4.19
4.45
4.52
4.56
4.56
4.30
3.99
4.03
4.23
4.30
4.15
4.01
4.52
7.04
5.94
7.05
7.16
6.73
6.27
5.88
6.27
6.30
6.56
6.46
6.46
6.38
6.46
5.96
5.58
5.71
5.81
5.88
5.35
4.73
5.24
5.21
4.75
4.87
4.76
4.91
4.36
5.97
4.97
5.78
5.01
5.23
5.39
4.51
4.96
4.90
4.38
4.20
3.91
4.36
5.98
5.22
5.46
5.39
5.24
5.41
4.81
5.33
5.22
5.36
5.06
5.43
4.65
6.94
6.46
6.76
5.85
6.22
6.06
6.91
5.83
5.79
5.88
5.96
5.48
5.17
4.65
4.87
4.47
4.47
1.41
4.24
3.82
7.29
6.80
6.75
6.52
7.25
7.54
5.85
5.74
5.83
5.56
5.86
6.91
6.64
6.59
6.07
6.01
6.40
5.65
6.22
6.10
5.95
5.56
6.03
5.54
6.18
5.59
5.27
5.39
4.72
5.21
5.20
5.85
6.20
5.26
4.74
4.40
4.89
5.14
5.80
4.74
4.77
5.13
4.99
4.89
4.85
4.95
4.94
4.52
4.49
4.43
4.40
4.24
4.15
3.99
3.99
3.99
5.72
5.55
5.53
5.41
5.53
5.23
5.71
5.56
5.74
5.39
5.39
5.21
SLEND(%)(C) 1.09
8.24
26.84
26.97
22.24
44.96
19.62
19.53
27.03
18.4
8.57
8.76
8
15
22
29
36
42
50
57
64
71
77
88
92
98
114
128
142
156
172
181
(A)
(B)
(C)
K(t)EQ = equivalent stiffness (slope obtained from the load-displacement experimental results) at time t.
Control beam: beam in which there was no chloride added and no externally applied anodic current.
SLEND = 100 [K(181)EQ K(8)EQ] / K(8)EQ.
(6)
where tFIN is the time (in days) of the accelerated corrosion application stage. A linear approximation of
xAVER(t) is considered in this investigation based on
the accelerated experimental procedure used. For the
natural corrosion procedure, this may vary based on
the corrosion rate fluctuations.
FIGURE 5. Maximum crack width, CWMAX, vs RRL, xAVER /r0, for data
from previous studies110 and this investigation.
(a)
(b)
870
(c)
FIGURE 6. Stiffness Loss, SL(t), vs RRL, xAVER(t)/r0, for: (a) GC,
(b) LC, and (c) HLC. The plots show regression lines for each beam
data, where y = SL(t) and x = xAVER(t)/r0.
CORROSIONSEPTEMBER 2004
CONCLUSIONS
The effect of corrosion on flexure stiffness changes was investigated experimentally for reinforced
concrete beams with corroding steel zones of various
lengths. This work attempts also to obtain information
contributing to the development of an empirical relation to predict flexure stiffness loss based on the rebar
radius loss due to corrosion. Based on the experimental results obtained with this investigation, the following conclusions were drawn.
For a GC process, the cracks evolve more rapidly
than for LC and HLC, supporting the findings of previous investigations with localized corrosion effects on
concrete cracking development.
The efficiency of the accelerated corrosion system
was adequate, giving efficiency estimates between
66.8% and 111.1% (with 83.2% efficiency as the
average).
ACKNOWLEDGMENTS
The authors acknowledge the Instituto Mexicano
del Transporte (Mexican Transport Research Institute)
Quertaro, Mxico, and APASCO SA de CV (Holcim
Group), Quertaros Concrete Factory for the support
of this investigation.
REFERENCES
1. A.A. Torres-Acosta, M. Martnez-Madrid, J. Mater. Civil Eng. 15,
4 (2003): p. 344-353.
2. C. Andrade, C. Alonso, F.J. Molina, Mater. Struct. 26 (1993): p.
453-464.
3. J.G. Cabrera, Cem. Concr. Compos. 18 (1996): p. 47-59.
4. A.A. Almusallam, A.S. Al-Gahtani, M. Maslehuddin, M.M. Khan,
A.R. Aziz, Proc. Inst. Civ. Eng. Struct. Build. 122 (1997): p. 27-34.
5. R. Huang, C.C. Yang, Cem. Concr. Compos. 19 (1997): p. 131137.
6. P.S. Mangat, M.S. Elgarf, ACI Struct. J. 96, 1 (1999): p. 149-158.
7. J. Rodriguez, L.M. Ortega, J. Casal, Constr. Build. Mater. 11, 4
(1997): p. 239-248.
8. J. Rodriguez, L.M. Ortega, J. Casal, Load Bearing Capacity of
Concrete Columns with Corroded Reinforcement, Proc. 4th SCI
Int. Symp. on Corrosion of Reinforcement in Concrete Construction, eds. C.L. Page, P.B. Bamforth, J.W. Figg (Cambridge, U.K.:
E&FN Spon, 1996), p. 220-230.
9. Y. Tachibana, K. Maeda, Y. Kajikawa, M. Kawuamura, Mechanical Behaviour of RC Beams Damaged by Corrosion of Reinforcement, in Corrosion of Reinforcement in Concrete, eds. C.L. Page,
871
10.
11.
12.
13.
872
14.
15.
16.
17.
CORROSIONSEPTEMBER 2004