Sunteți pe pagina 1din 209

DETAILED CUM ABSTRACT ESTIMATE

NAME OF WORK: Construction of


School building under R&R Centre
to MPUPS In Various components
at
Chinnayakkaluru
(V)
of
Peddapappur
(M)
in
Ananthapuramu (Dist)

Estimate Cost

Rs.178.00 Lakhs

EXECUTING AGENCY
EXECUTIVE ENGINEER (APEWIDC)
KADAPA

DETAILED - ESTIMATE
NAME OF WORK :Construction of Thahasildhar Office
at Rapthadu(V) of Rapthadu(M) in
Ananthapuramu (Dist)

Estimate Cost : Rs. 50.00Lakhs

SPECIFICATION REPORT
Estimate cost Rs. 38.50 Lkhs
Name of work: Construction of School building under R&R Centre to MPUPS In Various
components at Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu (Dist)

The Detailed Estimate for the work Construction of School building under R&R
Centre to MPUPS In Various components at Chinnayakkaluru (V) of Peddapappur
(M) in Ananthapuramu (Dist)". was prepared vide Letter Rc. No.
G2/8818/2009,Date 28/09/2015 of theDistrict joint Collector Ananthapuramu.
with a unit cost of Rs.38.50 lakhs ,

Provisions:
A Foundations and Sub-Structure:
1. Earth work excavation in all types of soils for open foundations
2. P.C.C (1:5:10) prop: nominal mix for levelling course in foundations and as bed concrete
for flooring.
3. P.C.C (1:4:8) prop: nominal mix for foundations for columns.
4. VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Footings, Pedestals, Plinth beams and Columns up to plinth level.
5. Random Rubble Stone masonry in CM(1:8) prop, for basement.
6. Filling with gravel in trenches, sides of foundations and for basement.
B Superstructure:
1.

VRCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
graded metal for Columns, Roof Beams, Roof Slabs.

2. Providing HYSD bars Fe 415 for VRCC Items .


RCC (1:2:4) prop. M20 grade design mix using 20 mm HBG machine crushed graded
metal for Lintels, 50mm thick platforms.
RCC M 20 grade design mix ( by weigh batching), using 20mm HBG machine crushed
4. graded metal for sun shades, 7.5cm thick at fixed end and 5.0 cm thick at free end, of
any width as per approved plan .
PCC M20 grade Design Mix ( by weigh batching), using 20mm HBG machine crushed
5.
gradedmetal for steps .
3.

6. Brick masonry in CM(1:8) prop. using Fly Ash traditional bricks for Superstructure.
7. Reinforced Brick masonry 115mm thick in CM(1:4) prop. using Fly Ash traditional bricks
for Partition walls.
8. Plastering 12 mm thick in two coats, base coat 8mm thick in CM(1:6) and top coat 4mm
thick in CM(1:4) for even face of walls.
9. Ornamental Plastering to ceiling, 12 mm thick in two coats, base coat 8mm thick in
CM(1:6) and top coat 4mm thick in CM(1:4).
10. Providing impervious coat over RCC roof slab, in side of septic tank to required slopes
with CM (1:3) prop. 20 mm thick (average) mixed with water proofing compound.
11. Flooring with Polished Black Kadapa slabs minimum of 15 mm thick (0.457M x 0.457M)
set over a base coat of CM (1:8), 12mm thick over already laid C.C. bed or R.C.C. roof
slabs.
12. Flooring with Ceramic non-skid tiles of 7.3 mm thick 1st. quality of any shade set over a
base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C. slab.
13. Providing Skirting to internal walls to 12.5 cm height with Rough Kadapa slabs of
minimum 40 mm thick, size not less than (0.457 x 457M) slabs 15mm to 18mm thick.
Dadooing to walls with coloured glazed tiles 1st. quality of size not less than 300mm x
17.
200mm.

Providing Green Chalk Board of size 3.00 x 1.2 mm including border with palstering in
19. CM (1:2) 12 mm thick as base coat and 3 mm thick top coat with cement green oxide
powder in (1:1) prop.
Whiting to new walls and ceiling in two coats with Birla white or equavalent quality for
20.
internal walls .
21.

Painting with Plastic emulsion grade -1 paint to exterior faces of new walls with 3 coats
of approved make shade and colour For External Walls.

22. Painting two coats with synthetic enamel paint 1st grade to new iron work.
Supply and fixing of MS Door (Double shutter) and Windows by using alround frame of
23. MS 'L' angle 35x35x5mm, for shutter by using 25x25x4mm covered by 18gauge MS
sheet.
AMENITIES:
1) Sub-Estimate is prepared for Water supply and Sanitary Arrangements as per the
requirements based on approved plan.
2) Sub-Estimate is prepared for Internal Electrification as per the requirements based on
approved plan.
DATAS & RATES:
The Data of all the items are adopted as per the Revised Standard Data Part-III
(Buildings) and the rates are worked out based on current SSR i.e Building SSR 20152016. Cement and Steel rates are adopted as approved by the Committee of the Chief
Engineers for July - 2015
SPECIFICATIONS:
The Standard specifications as per APSS are adopted and the work will be carried out
true to the relevant standard specification of APSS and as per the agreement
conditions.
Quarries:
The nearest leads, quarries are adopted while preparing the Datas, and as per the
location of the site No Area allowance on labour is proposed.
Overhead Charges & Contractors Profit:
14% towards overhead charges and contractors profit put together has been proposed
in the estimates which is as per the Revised Standard Data - Part-III (Buildings), ordered
by the Government of A.P vide G.O.Ms.No.49, IRRIGATION & CAD (PW-REFORMS)
DEPARTMENT Dated: 2-3-2009, for adoption by all Engineering /Public Works
Departments and other organizations.
Lump sum amounts at the rate of 5% towards VAT has been added in the Abstracts of
all the estimates by the SE APEWIDC,Kadapa, which is as per the Revised Standard
Data - Part-III (Buildings), and the same will be provided at 5% of ECV.
The estimate is submitted for according Administrative sanction.

,Executive Engineer
APEWIDC, Ananthapuramu

,Dy.Executive Engineer
APEWIDC,
Ananthapuramu

,Assistant Engineer
APEWIDC, Tadipatri
.

Page 8 of 209

GENARAL ABSTRACT
Name of work : Construction of School building under R&R Centre to MPUPS In
Various components at Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu
(Dist)
S.no
Description
Amount
1 Construction of 2 Rooms and Eletrification

5369245

2 Provision for Compound Wall Sub - Estimate(200.00 Mtrs)

#REF!

3 Provision for Toilets Sub - Estimate(2 Units)

#REF!

4 Provision Kitchen Sub - Estimate

#REF!

5 Water supply arrangements and Bore well

#REF!
TOTAL

#REF!

6 Add for VAT @ 5 %

#REF!

7 Add for PS Charges @ 7 %

#REF!

8 Add for Labour chess @ 1 %

#REF!

9 Add for Q.C Charges @ 0.50 %

#REF!

10 Unforseen Item

#REF!
#REF!

,Executive Engineer
APEWIDC,
ANANTAPURAMU

,Dy.Executive Engineer
APEWIDC, ANANTAPURAMU

,Assistant Engineer
APEWIDC, TADIPATRI

DETAILED ESTIMATE

Name of work : Construction of Thahasildhar Office at Rapthadu(V) of Rapthadu(M) in


Ananthapuramu (Dist)
S.
Measurement
Per
Description of work
No
Contents Rate
No
L
B
D
1
2
3
4.00 5.00
6.00
7.00
8
9
1 Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Loamy
Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) including all operational incident
labour charges such as shoring, strutting, sheeting, planking and dewatering including cost of hire charg
of T & P, labour charges etc., complete for finished item of work excluding seignerage charges excludin
dewatering charges etc., complete for Foundation of Building.
FT1
FT2
FT3
Al Round Building
Al Round Open Yard
Dedact Footings
-do-do-

1
1
1
1
1
-1
-1
-1

x
x
x
x
x
x
x
x

36 1.95
16 1.90
4
1.45
1 80.60
1 33.00
22 1.95
16 1.90
4
1.75

1.95
1.90
1.45
0.60
0.60
0.60
0.60
0.60

1.50
1.50
1.50
0.60
0.60
0.60
0.60
0.60

205.34
86.64
12.62
29.02
11.88
-15.44
-10.94
-2.52
316.60
317.00

289.50 1 Cum

2 Filling with useful available excavated earth (excluding rock) in trenches, sides of foundations an
basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited layer b
watering and ramming including cost and conveyence of water to work site and all operational, incidenta
labour charges, hire charges of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
Earth Work QTY
Allowed 90%

317.00
285.30
285.30
285.50

34.15 1 Cum

3 Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nomin
mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) met
from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregat
water etc. to site, including sales & other taxes on all materials, all operational, incidental, and labo
charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishin
top surface, curing concrete, etc., complete for finished item of work for Foundations (APSS No. 402)
FT1
FT2
FT3

1 x 36
1 x 16
1 x 4

1.95
1.90
1.45

1.95
1.90
1.45

0.10
0.10
0.10

13.69
5.78
0.84
20.31
20.50

3727.75 1 Cum

3 Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5:10) proportion nomin
mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Blasted Granite (IS383, 1970) met
from approved quarry including cost and conveyance of all materials like cement, sand, coarse aggregat
water etc. to site, including sales & other taxes on all materials, all operational, incidental, and labo
charges such as mixing, laying and ramming concrete in layers in position not exceeding 15cm, finishin
top surface, curing concrete, etc., complete for finished item of work for Foundations and Flooring Be
(APSS No. 402)
Al Round Building
1 x 1 80.60 0.60
0.10
4.84
Al Round Open Yard
1 x 1 33.00 0.60
0.10
1.98
Dedact columns
-1 x 22 0.23
0.38
0.10
-0.19
-do-1 x 16 0.23
0.23
0.10
-0.08

Under plinth
-do-do-doFlooring Bed
Deduct Open Yard
Steps

1
1
1
1
1
-1
1

x
x
x
x
x
x
x

2
8
5
7
1
2
1

22.30 0.45
4.75
0.45
2.00
0.45
3.00
0.45
22.30 18.00
8.20
8.30
3.25
1.43

0.10
0.10
0.10
0.10
0.10
0.10
0.10

2.01
1.71
0.45
0.95
40.14
-13.61
0.46
38.66
39.00

3524.45 1 Cum

4 Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) ha
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimu
quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance of all materials lik
cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost on all materials includin
centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross membe
etc., shuttering , machine mixing, laying concrete, vibrating,lift charges, curing etc., complete but excludin
cost of steel and its fabrication charges for finished item of work
A FOOTINGS:
FT1
1 x 36 1.80
1.80
0.45
52.49
FT2
1 x 16 1.75
1.75
0.38
18.62
FT3
1 x 4
1.30
1.30
0.30
2.03
73.14
73.50 8427.00 1 Cum
B PEDESTALS:
FT1,FT2
FT3

1 x 36
1 x 20

0.45
0.45

0.60
0.45

0.60
0.60

5.83
2.43
8.26
8.50

8867.80 1 Cum

C COLUMNS:
Up to bottom of plinth beam
C1
1 x 36
C2
1 x 16
C3
1 x 4
Above plinth beam
C1
1 x 36
C2
1 x 16
C3
2 x 4

0.23
0.23
0.30

0.38
0.23
0.30

1.50
1.50
1.50

4.72
1.27
0.54

0.23
0.23
0.30

0.38
0.23
0.30

3.60
3.60
3.60

11.33
3.05
2.59
23.50
23.50 10022.40 1 Cum
6.15
3.93
0.69
2.17
2.26
0.58
0.72
16.50
16.50 10577.75 1 Cum

D PLINTH BEAMS:
Long wall
short wall
-do-doOpen Yard Ver Beam
Portico

1
1
1
1
1
1
1

x
x
x
x
x
x
x

4
8
5
7
4
2
1

22.30
4.75
2.00
3.00
8.20
4.20
10.50

0.23
0.23
0.23
0.23
0.23
0.23
0.23

0.30
0.45
0.30
0.45
0.30
0.30
0.30

1 x

22.30

0.23

0.30

E BEAMS:
Long wall

6.15

short wall
-do-doOpen Yard Ver Beam
Portico

1
1
1
1
1
1

x
x
x
x
x
x

F FOR ROOF SLAB 125 MM THICK:


1 x
Roof
-1 x
Deduct Open Yard
1 x
Portico

G FOR WAIST SLAB 175 MM THICK:


1 x
Midlanding
1 x
1st Flight
1 x
2nd Flight

8
5
7
4
2
1

1
1
1

1
1
1

4.75
2.00
3.00
8.20
4.20
10.50

0.23
0.23
0.23
0.23
0.23
0.23

22.30 18.00
8.20
8.30
10.50 4.20

3.00
3.40
3.40

1.50
1.50
1.50

0.45
0.30
0.45
0.30
0.45
0.45

3.93
0.69
2.17
2.26
0.87
1.09
17.16
17.50

8844.80 1 Cum

401.40
-68.06
44.10
377.44
377.50

1068.90 1 Sqm

4.50
5.10
5.10
14.70
15.00

1365.45 1 Sqm

5 Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones fro
approved quarry including cost and conveyance of all materials like Granite stones, cement, sand, wate
etc., to site including sales & other taxes on all materials, all operational, incidental, and labour charge
such as cutting stones to required size and shape, mixing of cement mortar, constructing masonry, curin
etc., complete for finished item of work for foundation and basement (APSS No. 601 & 615)
Al Round Building
Al Round Open Yard
Dedact columns
-doFor step

1
1
-1
-1
1

x 1 80.60
x 1 33.00
x 22 0.23
x 16 0.23
x 6
3.25

0.45
0.45
0.38
0.23
1.25

1.20
1.20
1.20
1.20
0.15

43.52
17.82
-2.34
-1.02
3.66
61.64
62.00

2980.95 1 Cum

6 Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers not exceedin
15cm thick, consolidating each deposited layer by watering and ramming including cost and conveyence
water to the work site and all operational, incidental, labour charges,hire charges of T & P etc., complete f
finished item of work. (APSS NO. 309 & 310)
In side building(Including
1 x 1 22.00 17.70
1.50
584.10
Plinth)
Deduct Open Yard
-1 x 1
8.20
8.30
1.50
-102.09
Dedact Columns
-1 x 22 0.23
0.38
1.50
-2.92
-1 x 16 0.23
0.23
1.50
-1.27
477.82
478.00
178.05 1 Cum

7 Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard blaste
granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minimu
quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance of all materials lik
cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost on all materials includin
centering using Cashewrina Ballies and Wooden runners & staging including all bracings, cross membe
etc., shuttering , machine mixing, laying concrete, lift charges, curing etc., complete but excluding cost
steel and its fabrication charges for finished item of work (APSS No. 402 & 403)

A For SUNSHADE 0.60 M, 75 MM THICK @ FIXED END ,50 MM THICK @


FREE END @averag 50 mm thick
Open Court Yard
Front
Out Side Over Windows

1 x 2
1 x 2
1 x 17

8.20
8.20
1.50

0.60
0.60
0.60

9.84
9.84
15.30
34.98
35.00

731.65 1 Sqm

B LINTELS
Over Door
Over Window

1 x 12
1 x 17

1.80
1.80

0.23
0.23

0.15
0.15

0.75
1.06
1.81
2.00

9796.70 1 Cum

8 Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm wi
compressive of 50 Kgs / Sqcm from approved source including cost and conveyance of all materials lik
cement, sand, fly ash bricks, water etc., to site, including sales & other taxes on all materials, a
operational, incidental and labour charges such as mixing cement mortar, constructing masonr
scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS No. 501 & 504).
Long wall
short wall
-do-doDeduct Main Door
Deduct door D
Deduct door D1
Deduct door D2
Deduct Windows
Deduct Ventilaters
Deduct Lintel Over Door
Deduct Lintel Over Window

1
1
1
1
-1
-1
-1
-1
-1
1
-1
-1

x
x
x
x
x
x
x
x
x
x
x
x

4
4
5
5
1
2
1
13
17
6
12
17

22.30
18.00
4.75
3.00
2.40
1.22
1.22
0.90
1.22
1.22
1.80
1.80

0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23
0.23

2.80
2.80
2.80
2.80
2.13
2.13
2.13
2.13
1.22
0.3
0.15
0.15

57.44
46.37
15.30
9.66
-1.18
-1.20
-0.60
-5.73
-5.82
0.51
-0.75
-1.06
112.94
113.00

5800.70 1 Cum

9 Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm thick (averag
mixed with water proofing compound manufactured by reputed manufacturers as approved by Engineer-i
charge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth with a floating coat
neat cement and thread lining at regular intervals of 45cmx45cm including cost and conveyance of a
materials like cement, sand, water proofing compound, water etc., to site,sales & other taxes on a
materials, all operational, incidental and labour charges such as mixing mortar, laying, rounding off
junctions of wall and slab, rendering smooth with thread lining, curing, lift charges, etc., complete f
finished item of work (APSS No. 901 & 903).
Roof
Deduct Open Yard
Portico

1 x
-1 x
1 x

1
1
1

22.30 18.00
8.20
8.30
10.50 4.20

401.40
-68.06
44.10
377.44
377.50

390.50 1 Sqm

10 Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top coat
4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials like cemen
sand, water etc., to site, sales & other taxes on all materials,all operational, incidental and labour charge
such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherever necessary
directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wall for finishe
item of work. (APSS 901,903 & 904)
Thasiladhar Room
Toilets
Beams
Conference Hall
Beams
Mialanding
1st Flight
2nd Flight
VRO's and RI's Rooms
Entrance
Portico
Beams
Office Room
Toilets
Beams
Computer,Dy Thasildhar and
Record Room
Sunshades

Ver

1
1
2
1
2
1
1
1
1
1
1
4
1
1
1

x
x
x
x
x
x
x
x
x
x
x
x
x
x
x

1
1
2
1
3
1
1
4
4
1
1
2
1
2
2

4.75
1.50
4.75
4.75
4.75
3.00
3.40
3.40
2.90
3.50
10.50
4.20
4.75
2.30
4.75

4.75
3.00
9.20
1.50
1.50
1.50
3.00
1.50
4.20
7.07
4.75
-

0.45
0.45
0.45
0.45

22.56
4.50
8.55
43.70
12.83
4.50
5.10
20.40
34.80
5.25
44.10
15.12
33.58
21.85
4.28

1 x

3.30

4.75

47.03

8.20
8.20
1.50
8.30
8.20

0.60
0.60
0.60
2.00
2.00

9.84
9.84
15.30
33.20
32.80
429.13
429.50

1
1
1
1
1

x 2
x 2
x 17
x 2
x 2

360.51 1 Sqm

11 Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick
CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, sand, water etc
to site, seigniorage charges, sales & other taxes on all materials,all operational, incidental and labo
charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wherev
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfaces of Wa
for finished item of work. (APSS 901,903 & 904)
Thasiladhar Room
1 x 4
4.75
3.25
61.75
Toilets
1 x 2
1.50
1.80
5.40
-do1 x 2
3.00
1.80
10.80
Conference Hall
1 x 2
4.75
3.25
30.88
-do1 x 2
9.20
3.25
59.80
Stair Case
1 x 2
4.75
3.40
32.30
-do1 x 1
3.00
3.40
10.20
VRO's and RI's Rooms
2 x 4
2.90
3.25
75.40
-do2 x 4
3.00
3.25
78.00
Entrance
1 x 2
3.50
3.25
22.75
-do1 x 2
3.00
3.25
19.50
Office Room
1 x 2
4.75
3.25
30.88
-do1 x 2
7.07
3.25
45.96
Toilets
2 x 2
2.30
1.80
16.56
-do2 x 2
4.75
1.80
34.20

Computer,Dy Thasildhar and


Record Room
-doOut Side
Deduct
Deduct
Deduct
Deduct
Deduct
Deduct

Main Door
door D
door D1
door D2
Windows
Ventilaters

2 x
2
1
1
-2
-2
-2
-2
-2
-2

3.30

x 3
4.75
x 2 22.30
x 2 18.00
x 1
2.40
x 2
1.22
x 1
1.22
x 13
0.90
x 17
1.22
x 6
1.22

3.25

64.35

3.25
3.40
3.40

92.63
151.64
122.40
-10.22
-10.39
-5.20
-49.84
-50.61
-4.39
834.75
835.00

2.13
2.13
2.13
2.13
1.22
0.3

347.15 1 Sqm

11 Supply and Fixing of Door with Double leaf shutter, Door Size 2.4x2.13 mtrs with MediumTeak wood Fram
of sections size 125mm x 100mm with Flush Door Shutter Solid Bond Wood black board type wi
commercial ply on both faces of 35mm thick including cost of fixtures such as Aluminium Tower Bol
250mm long 2 Nos, Aluminium Handles 150mm long 2 Nos, 300mm long Aluminium Aldrops 1No, 125m
long M.S. But hinges 6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fas
6Nos, Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixin
of Door Frame and shutter Fixing in position , with Hardware fixtures etc., complete for finsihed utem
work.
Main Door
1 x 1
1.00
1.00 19166.55 1 Nos

12 Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13 mtrs with Medium teak woo
Frame of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood black board type wi
commercial ply on both faces of 35mm thick including cost of fixtures such as Aluminium Tower Bol
300mm long 2 Nos, Alluminimum Handles 150mm long 2 Nos, 300mm long Aluminium Aldrops 1N
125mm long M.S. But hinges 6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Ho
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such
Fixing of Door Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed ute
of work.
D,D1 Doors
1 x 3
3.00
3.00 11868.00 1 Nos

13 Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13 mtrs with Medium Teak Wood Fram
of sections size 75mm x 100mm with Flush Door Shutter Solid Bond Wood black board type wi
commercial ply on both faces of 35mm thick including cost of fixtures such as Aluminium Tower Bol
300mm long 2 Nos, Aluminium Handels 150mm long 1 No, 300mm long Aluminium Aldrops 1No, 125m
long M.S. But hinges 3 Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fas
6Nos, Sales and Other Taxes cost and convenyance of all materials to site all Labour charges such as Fixin
of Door Frame on shutter Fixing in position , with Hardware fixtures etc., complete for finsihed utem
work.
D2 Doors
1 x 13
13.00
13.00 9631.25 1 Nos

14 Providing & Fixing of Openable Windows with Fly-mesh made of pre-painted steel (Base Steel as per IS 51
of 0.6mm thick galvanized as per IS 277 with zinc of 150 GSM) primer coated with epoxy primer of 5
microns thick, finish painted with a polyester paint of 12-16 microns thick and back coated with 5-7 micron
thick alkyd backer and the section for outer frame of 72 x 55mm, centre mullion of 72 x 50mm, section f
fixed glass beading section of 12 x 12 mm and section for shutters of 47 x 20 mm and outer frame
mullion sections with rebate for glazed shutters, fly mesh and a 20 mm provision for guard bars/grills an
fly mesh shutter section of 20 x 40 mm and the sections cut to length metre joined with corner bracke
centre mullions fixed with mullion cap, stay, handles, latch 2 Nos of heavy duty stainless steel pivot hinge
per shutter and panelled with 5mm thick plain float glass and S.S. Mesh for fly mesh shutter (304 grade
fitted using rubber gaskets.
Windows
1 x 17 1.22
1.22
25.34

25.34

8192.05 1 Sqm

15 Supply and fixing of Fixed Louvered Ventilators with sections made of pre - painted steel (base steel as p
IS 513 of 'D" quality, galvanized as per IS 277 with zinc of 120 GSM) primer coated with epoxy primer of
7 microns thick, finish painted with a polyester paint of 12-16 microns thick and back coated with 5
microns thick alkyd backer with total coated thickness of 0.6mm. Section for louvered ventilator fram
should be of 33x57mm. All the above closed and seamed sections should be made out of single sheet an
with stitch at a single place as per enclosed drawings; The ventilators should be paneled with 4 m
pinhead glass with Ethyl propylene Diamine monomer Gasket (EPDM). The sections are to be cut to leng
mitre joined with corner bracket. Gaskets are to be made of Ethyl propylene Diamine monomer(EPDM
Corner brackets made of CRCA with Zinc Phosphate. The above frames should be fixed to the concre
/masonry wall by means of self expanding brackets & screws including 10 mm square guard bars with
pitch and all taxes complete for finished item of work.
Ventilaters
1 x 6
1.22
0.30
2.20
2.20 5400.20 1 Sqm

15 Flooring with 15 to 18 mm thick polished block Kadapa slabs set over a base coat of CM (1:8), 12mm thi
(joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof slab only after it is properl
cured, cleaned, moistered and where necessary treated with neat grey cement slurry of honey lik
consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to full dept
including cost and conveyance of all materials like cement, sand, water, flooring stones etc. to site, sale
and other taxes on all materials, all operational, incidental and labour charges such as dressing of floorin
stones to the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete f
finished item of work.(APSS No.703 & 701)
Thasiladhar Room
Conference Hall
Mialanding
VRO's and RI's Rooms
Entrance
Portico
Office Room
Computer,Dy Thasildhar and
Record Room
Ver

1
1
1
1
1
1
1

x
x
x
x
x
x
x

1
1
1
4
1
1
1

4.75
4.75
3.00
2.90
3.50
10.50
4.75

4.75
9.20
1.50
3.00
1.50
4.20
7.07

22.56
43.70
4.50
34.80
5.25
44.10
33.58

1 x

3.30

4.75

47.03

1 x
1 x

2
2

8.30
8.20

2.00
2.00

33.20
32.80
301.52
302.00

537.20 1 Sqm

16 Providing Skirting to internal walls to 12.5 Cm height with Polished black kadapa slabs of minimum 15
18 mm thick (0.457x0.457M) with length equal to flooring stones set over a base coat of CM (1:5), 12m
thick and jointed with neat cement paste to full depth (joints of stone should be flushed), including c/c of a
m/ls like cement, sand, water, flooring stones etc. to site, seigniorage charges, sales and other taxes on a
materials, all operational, incidental l/c such as dressing of flooring stones to the required sizes, mixing
cement mortar, laying, jointing, curing, lift charges etc., complete for finished item of work.(APSS No.701
707)
Thasiladhar Room
Conference Hall
Mialanding
VRO's and RI's Rooms
Entrance
Portico
Office Room
Computer,Dy Thasildhar and
Record Room
Ver

1
1
1
1
1
1
1

x
x
x
x
x
x
x

4
4
4
4
2
2
4

4.75
4.75
3.00
2.90
3.50
10.50
4.75

0.10
0.10
0.10
0.10
0.10
0.10
0.10

1.90
1.90
1.20
1.16
0.70
2.10
1.90

4 x

3.30

0.10

3.96

1 x
1 x

2
2

8.30
8.20

0.10
0.10

1.66
1.64

18.12
18.50
582.45 1 Sqm
17 Providing high yield strength deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of differe
diameters, cutting, bending, to required sizes and shapes placing in position with cover blocks of approve
size and binding wire of 20SWG, forming grills for reinforcement work as per approved designs an
drawings including cost and conveyance of bars from approved sources to site of work, including cost an
conveyance of binding wire, cover blocks and all operational, incidental, and labour charges such
cutting, bending, placing in position, tying etc., and sales & other taxes,on cost of all materials complete f
finished item of work (APSS No.126) in all floors.

6615.00
3290.00
1980.00
1020.00
2100.00
4077.00
200.00
236.25
19.518
19.600 61180.65 1 MT
18 Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give an even shad
after thoroughly brushing the surface to remove all loose powdered materials including cost an
conveyance of all materials and water to site, sales & other taxes, all operational, incidental and labo
charges such as cleaning the surface, painting, curing etc., complete for finished item of work for intern
walls. (APSS No.901 & 908)
COLUMN FOOTINGS
COLUMNS
PLINTH BEAM
PEDASTAL
BEAM
SLAB 120MM THICK
LINTEL
SUNSHADE

73.50
23.50
16.50
8.50
17.50
45.30
2.00
2.63

cum@
cum@
cum@
cum@
cum@
cum@
cum@
cum@

90.00
140.00
120.00
120.00
120.00
90.00
100.00
90.00

Ornamental Plastering
Plastering

429.50
835.00
429.50
32.15 1 Sqm
19 Painting to New walls with two coats of Emalsatoin or equavalent quality of approved shade over base co
of cement primer grade I making three coats in all to give an even shade after thoroughly brushing th
surface to remove all loose powdered materials, including cost and conveyance of all materials, includin
cost and conveyance of all materials, cost of brushes, water to site, etc., sales & other taxes, a
operational, incidental and labour charges such as scaffolding charges, lift charges, curing etc., complete
Building
Out Side
Deduct Windows
Deduct Ventilaters

1
1
-1
-1

x 2 22.30
x 2 18.00
x 17
1.22
x 6
1.22

3.40
3.40
1.22
0.3

151.64
122.40
-25.30
-2.20
246.54
247.00

148.50 1 Sqm

TOTAL

,Executive Engineer
APEWIDC, ANANTAPURAMU

,Dy.Executive Engineer
APEWIDC, ANANTAPURAMU

,Assistant Engineer
APEWIDC, TADIPATRI

AILED ESTIMATE

Thahasildhar Office at Rapthadu(V) of Rapthadu(M) in


Ananthapuramu (Dist)

Amount

10
on bank with initial lead of 10m and initial lift of 3m in Loamy &
Ordinary Gravelly Soils ( SS 20-B) including all operational incidental
ng, sheeting, planking and dewatering including cost of hire charges
for finished item of work excluding seignerage charges excluding
oundation of Building.

91656

d earth (excluding rock) in trenches, sides of foundations and


ot exceeding 15cm thick, consolidating each deposited layer by
nd conveyence of water to work site and all operational, incidental,
c., complete for finished item of work. (APSS NO. 309 & 310)

9743

o M7.5 grade as per IS 456 equivalent to (1:4:8) proportion nominal


gregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal
d conveyance of all materials like cement, sand, coarse aggregate,
ther taxes on all materials, all operational, incidental, and labour
mming concrete in layers in position not exceeding 15cm, finishing
plete for finished item of work for Foundations (APSS No. 402)

75711

o M5 grade as per IS 456 equivalent to (1:5:10) proportion nominal


gregate) using 40mm size Hard Blasted Granite (IS383, 1970) metal
d conveyance of all materials like cement, sand, coarse aggregate,
her taxes on all materials, all operational, incidental, and labour
mming concrete in layers in position not exceeding 15cm, finishing
mplete for finished item of work for Foundations and Flooring Bed

136255

M 20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard


d metal (Coarse aggregate) from approved quarry, using a minimum
um of concreteincluding cost and conveyance of all materials like
aggregate, water etc., to site and cost on all materials including
d Wooden runners & staging including all bracings, cross members
concrete, vibrating,lift charges, curing etc., complete but excluding
for finished item of work

616351

73248

235526

174533

151777

403446

20072

1:8) prop: (Cement: Sand) using Hard blasted Granite stones from
veyance of all materials like Granite stones, cement, sand, water,
xes on all materials, all operational, incidental, and labour charges
and shape, mixing of cement mortar, constructing masonry, curing
for foundation and basement (APSS No. 601 & 615)

183746

foundations and basement with initial lead in layers not exceeding


d layer by watering and ramming including cost and conveyence of
al, incidental, labour charges,hire charges of T & P etc., complete for
310)

85076

gn Mix ( by weigh batching ) using 20mm size (SS5) hard blasted


al (Coarse aggregate) from approved quarry, using a minimum
um of concrete including cost and conveyance of all materials like
aggregate, water etc., to site and cost on all materials including
d Wooden runners & staging including all bracings, cross members
g concrete, lift charges, curing etc., complete but excluding cost of
shed item of work (APSS No. 402 & 403)

25608

17732

M (1:8) prop: using Fly ASH Bricks of size 290x225x140mm with


proved source including cost and conveyance of all materials like
etc., to site, including sales & other taxes on all materials, all
harges such as mixing cement mortar, constructing masonry,
etc., complete for finished item of work. (APSS No. 501 & 504).

655131

f slab to required slopes with CM (1:3) prop. 20mm thick (average)


anufactured by reputed manufacturers as approved by Engineer-inroof slab when it is green, finished smooth with a floating coat of
lar intervals of 45cmx45cm including cost and conveyance of all
oofing compound, water etc., to site,sales & other taxes on all
nd labour charges such as mixing mortar, laying, rounding off at
mooth with thread lining, curing, lift charges, etc., complete for
03).

147390

wo coats with base coat of 8mm thick in CM (1:5) and top coat of
finish including cost and conveyance of all materials like cement,
taxes on all materials,all operational, incidental and labour charges
ges, lift charges, including cutting of Grooves wherever necessary as
hing, curing, etc., complete for Even Surfaces of Wall for finished

154706

h base coat of 8mm thick in CM (1:6) and top coat of 4mm thick in
cost and conveyance of all materials like cement, sand, water etc.,
other taxes on all materials,all operational, incidental and labour
lding charges, lift charges, including cutting of Grooves wherever
charge, finishing, curing, etc., complete for Even Surfaces of Wall
& 904)

289783

eaf shutter, Door Size 2.4x2.13 mtrs with MediumTeak wood Frame
th Flush Door Shutter Solid Bond Wood black board type with
m thick including cost of fixtures such as Aluminium Tower Bolts
150mm long 2 Nos, 300mm long Aluminium Aldrops 1No, 125mm
ng Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts
onvenyance of all materials to site all Labour charges such as Fixing
sition , with Hardware fixtures etc., complete for finsihed utem of
19167

e leaf shutter, Door Size 1.22x2.13 mtrs with Medium teak wood
m with Flush Door Shutter Solid Bond Wood black board type with
m thick including cost of fixtures such as Aluminium Tower Bolts
ndles 150mm long 2 Nos, 300mm long Aluminium Aldrops 1No,
mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
and convenyance of all materials to site all Labour charges such as
n position , with Hardware fixtures etc., complete for finsihed utem

35604

af shutter, Door Size 0.90x2.13 mtrs with Medium Teak Wood Frame
h Flush Door Shutter Solid Bond Wood black board type with
m thick including cost of fixtures such as Aluminium Tower Bolts
s 150mm long 1 No, 300mm long Aluminium Aldrops 1No, 125mm
ong Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold fasts
onvenyance of all materials to site all Labour charges such as Fixing
sition , with Hardware fixtures etc., complete for finsihed utem of

125206

with Fly-mesh made of pre-painted steel (Base Steel as per IS 513


77 with zinc of 150 GSM) primer coated with epoxy primer of 5-7
ester paint of 12-16 microns thick and back coated with 5-7 microns
uter frame of 72 x 55mm, centre mullion of 72 x 50mm, section for
mm and section for shutters of 47 x 20 mm and outer frame &
shutters, fly mesh and a 20 mm provision for guard bars/grills and
m and the sections cut to length metre joined with corner bracket,
stay, handles, latch 2 Nos of heavy duty stainless steel pivot hinges
ck plain float glass and S.S. Mesh for fly mesh shutter (304 grade),

207587

ntilators with sections made of pre - painted steel (base steel as per
IS 277 with zinc of 120 GSM) primer coated with epoxy primer of 5polyester paint of 12-16 microns thick and back coated with 5-7
coated thickness of 0.6mm. Section for louvered ventilator frame
osed and seamed sections should be made out of single sheet and
nclosed drawings; The ventilators should be paneled with 4 mm
mine monomer Gasket (EPDM). The sections are to be cut to length
ets are to be made of Ethyl propylene Diamine monomer(EPDM).
nc Phosphate. The above frames should be fixed to the concrete
ing brackets & screws including 10 mm square guard bars with 6"
item of work.
11880

d block Kadapa slabs set over a base coat of CM (1:8), 12mm thick
C.C. bed already laid or R.C.C. roof slab only after it is properly
necessary treated with neat grey cement slurry of honey like
t for 1 sqm. and jointed with neat cement paste to full depth,
aterials like cement, sand, water, flooring stones etc. to site, sales
erational, incidental and labour charges such as dressing of flooring
ement mortar, laying, jointing, curing, lift charges etc., complete for
01)

161977

2.5 Cm height with Polished black kadapa slabs of minimum 15 to


h equal to flooring stones set over a base coat of CM (1:5), 12mm
e to full depth (joints of stone should be flushed), including c/c of all
tones etc. to site, seigniorage charges, sales and other taxes on all
such as dressing of flooring stones to the required sizes, mixing of
lift charges etc., complete for finished item of work.(APSS No.701 &

10775
(HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of different
sizes and shapes placing in position with cover blocks of approved
ming grills for reinforcement work as per approved designs and
e of bars from approved sources to site of work, including cost and
ocks and all operational, incidental, and labour charges such as
ng etc., and sales & other taxes,on cost of all materials complete for
ll floors.

1199141
coats with Surya cem or equavalent quality to give an even shade
to remove all loose powdered materials including cost and
to site, sales & other taxes, all operational, incidental and labour
ainting, curing etc., complete for finished item of work for internal

13808
Emalsatoin or equavalent quality of approved shade over base coat
e coats in all to give an even shade after thoroughly brushing the
materials, including cost and conveyance of all materials, including
, cost of brushes, water to site, etc., sales & other taxes, all
es such as scaffolding charges, lift charges, curing etc., complete

36611

###

,Assistant Engineer
APEWIDC, TADIPATRI

LEAD CHART

NAME OF WORK: Construction of School building under R&R Centre to MPUPS In Various components at Chinnayakkaluru (V)
Ananthapuramu (Dist)

RATES AS PER COMMON SSR OF 2015-16 with cement and steel rates of July 2015

Sl.
No.

Description

(1)

(2)

Add
Convence Initial
Differe
1%
Charges
Cost
nc in toward
Loading
including including Seignio
s
charges
Total Stacking Stacking - rage storag
Charges Charges Charge
e
s

Lead in KM

SSR
Sl.No.

Avg.
Thick
ness
in
mm

Source of Material

(3)

(4)

(5)

MR

CT

(6)

(7)

(8)

0.00

40.00

409.49

610.00

0.00

0.00

0.00

(9)

(10)

(11)

(12)

(13)

Sand for Mortar

M-005

Ullikallu

40.00

Sand for Plastering

M-006

Ullikallu

40.00

0.00

40.00

409.49

677.00

0.00

0.00

0.00

Sand for filling& blindage

M-004

Local

3.00

0.00

3.00

23.65

460.00

0.00

0.00

0.00

Gravel

M-008

Local

3.00

0.00

3.00

23.65

103.00

0.00

0.00

0.00

R.R. Stone(Granite, Dolamite


&Trap variety)

M-148

K.R.Palli

10.00

0.00

10.00

100.09

252.00

0.00

0.00

0.00

C.R. Stone(Granite, Dolamite


&Trap variety)

CSSR-A.14

K.R.Palli

10.00

0.00

10.00

100.09

288.00

0.00

0.00

0.00

trough stones25 x25x45 to 60


CSSR-A.76
cms

K.R.Palli

10.00

0.00

10.00

100.09

1040.00

0.00

0.00

0.00

40mm
1970)

M-055

K.R.Palli

10.00

0.00

10.00

100.09

845.00

0.00

0.00

0.00

20mm M/c chips (IS383-1970)

M-053

K.R.Palli

10.00

0.00

10.00

100.09

1365.00

0.00

0.00

0.00

13.2/12.5
mm
(IS383-1970)

M-052

K.R.Palli

10.00

0.00

10.00

100.09

1097.00

0.00

0.00

0.00

M-051

K.R.Palli

10.00

0.00

10.00

100.09

935.00

0.00

0.00

0.00

10

HBG

Metal

M/c

(IS383-

chips

11 10mm M/c chips (IS383-1970)

Sl.
No.

SSR
Sl.No.

Description

12 6mm M/c chips (IS383-1970)

Avg.
Thick
ness
in
mm

Add
Convence Initial
Differe
1%
Charges
Cost
nc in toward
Loading
including including Seignio
s
charges
Total Stacking Stacking - rage storag
Charges Charges Charge
e
s

Lead in KM
Source of Material
MR

CT

10.00

0.00

10.00

100.09

735.00

0.00

0.00

0.00

5200.00

0.00

0.00

41.88

96.01

M-050

K.R.Palli

BMT-A.01

Ananthapuramu

6.00

0.00

6.00

90.63

Fly Ash Bricks of size 290 x100


13 x140 mm with compressive BMT-A.13 2.292
strength of 50 Kg /sq.cm

Ananthapuramu

6.00

0.00

6.00

207.77

###

0.00

0.00

Fly Ash Bricks of size 290 x225


14 x 140 mm with compressive BMT-A.10 5.158
strength of 50 Kg/sq .cm

Ananthapuramu

6.00

0.00

6.00

467.48

###

0.00

0.00 216.02

13

2nd Class
23x11x7cm

Bricks

of

size

15

Polished Black Kadapa Slabs of


BMT-B.06
15 mm thick

15

Tadipatri

66.00

0.00

66.00

14.25

137.90

0.00

0.00

0.46

16

Rough Kadapa slabs of 40 mm


BMT-B.01
thick (0.457 x 457M)

40

Tadipatri

66.00

0.00

66.00

37.99

96.00

0.00

0.00

1.22

High polished Granite 16 to 18


17 mm thick up to 8' 00" (2.43M) BMT-B.11
black

17

Tadipatri

66.00

0.00

5.00

0.00

2352.00

0.00

0.00

0.00

Local

0.50

0.00

5.00

0.00

77.00

0.00

0.00

0.00

CSSR-A.05

At Site

0.00

0.00

0.00

0.00

5460.00

0.00

0.00

0.00

M-126

At Site

0.00

0.00

0.00

0.00

###

0.00

0.00

0.00

CSSR-A.62

At Site

0.00

0.00

0.00

0.00

###

0.00

0.00

0.00

18 water
19 Cement
Mild Steel Bars (Fe 250) for
6mm
High Yield Strength Deformed
21 Bars (Fe 415) for 8mm to
40mm dia
20

Sl.
No.

22

Description

SSR
Sl.No.

Mild Steel, Structural steel, I,e,


CSSR-A.68
Angles, Channels & I-Sections

23 M.S. Plates

CSSR-A.69

Avg.
Thick
ness
in
mm

Add
Convence Initial
Differe
1%
Charges
Cost
nc in toward
Loading
including including Seignio
s
charges
Total Stacking Stacking - rage storag
Charges Charges Charge
e
s

Lead in KM
Source of Material
MR

CT

At Site

0.00

0.00

0.00

0.00

###

0.00

0.00

0.00

At Site

0.00

0.00

0.00

0.00

###

0.00

0.00

0.00

CERTIFICATES:1

Certified that the above leads are true and correct to the best of my knowledge

Certified that the quarry requries blasting for RR, CRS, 6mm, 10mm, 12mm, 20mm & 40mm Metal

Certified that the 20mm, 12mm, 10mm, 6mm Metal requires Machine Crushing

Certified that the work site falls within 12 Kms belt of any Municipality/ Corporation.Hence extra on labour charges is allowed

,Executive Engineer
APEWIDC,
ANANTAPURAMU

,Dy.Executive Engineer
APEWIDC, ANANTAPURAMU

,Assistant En

APEWIDC, TA

EAD CHART

to MPUPS In Various components at Chinnayakkaluru (V) of Peddapappur (M) in


thapuramu (Dist)

5-16 with cement and steel rates of July 2015


Area
allowenc
unload
e on
ing loading &
charge unloadin
s
g
charges
@ 25 %
(14)
(15)

Total

Unit
per

(16)

(17)

0.00

0.00

1019.49

Cum.

0.00

0.00

1086.49

Cum.

0.00

0.00

483.65

Cum.

0.00

0.00

126.65

Cum.

0.00

0.00

352.09

Cum.

0.00

0.00

388.09

Cum.

0.00

0.00

1140.09

Cum.

0.00

0.00

945.09

Cum.

0.00

0.00

1465.09

Cum.

0.00

0.00

1197.09

Cum.

0.00

0.00

1035.09

Cum.

Area
allowenc
unload
e on
ing loading &
charge unloadin
s
g
charges
@ 25 %

Total

Unit
per

0.00

0.00

835.09

Cum.

41.88

10.47

5384.86

1000
Nos

96.01

24.00 11423.79

1000
Nos

54.01 24953.53

1000
Nos

###

0.23

0.06

152.89

1Sqm.

0.61

0.15

135.97

1Sqm.

0.00

0.00

2352.00

1Sqm.

0.00

0.00

77.00

50.25

12.56

5522.81

M.T

60.23

15.06 45075.29

M.T

60.23

15.06 42075.29

M.T

KL

Area
allowenc
unload
e on
ing loading &
charge unloadin
s
g
charges
@ 25 %

Total

Unit
per

60.23

15.06 45075.29

M.T

60.23

15.06 44075.29

M.T

40mm Metal

ence extra on labour charges is allowed

,Assistant Engineer
APEWIDC, TADIPATRI

STANDARD DATAS (SSR 2015-16)

Name of work :Construction of School building under R&R Centre to MPUPS In Variou
components at Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu (Dist)
Qty
CEMENT MORTAR (1:2)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
CEMENT MORTAR (1:3)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
CEMENT MORTAR (1:4)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
CEMENT MORTAR (1:5)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
CEMENT MORTAR (1:6)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
CEMENT MORTAR (1:8)
Material
Cost of Sand
Cost of Cement
Man Power
Light Mazdoor
Rate per cu.m.
Cost andConvenyance of 20mm to
6mm HBG Graded Metal / (Trap
20mm
Metal)
12mm
10mm
6mm
Rate per 1 cu.m.

C-Data

1.05 Cum
720 Kgs
0.20 Nos

1.05 Cum
480 Kgs
0.20 Nos

1.05 Cum
360 Kgs
0.20 Nos

1.05 Cum
288 Kgs

Rate

1019.49
5522.81
400.00

1019.49
5522.81
400.00

1019.49
5522.81
400.00

1019.49
5522.81

0.20 Nos

1.05 Cum
240 Kgs
0.20 Nos

1.05 Cum
180 Kgs
0.20 Nos

0.6 Cum
0.15 Cum
0.15 Cum
0.10 Cum

31 of 209

Per

1 Cum
1000 Kgs
1 Day

1 Cum
1000 Kgs
1 Day

1 Cum
1000 Kgs
1 Day

1 Cum
1000 Kgs
1 Day

1019.49
5522.81
400.00

1019.49
5522.81
400.00

1465.09
1197.09
1035.09
835.09

1 Cum
1000 Kgs
1 Day

1 Cum
1000 Kgs
1 Day

1 Cum
1 Cum
1 Cum
1 Cum
Total

D DATAS (SSR 2015-16)

ool building under R&R Centre to MPUPS In Various


(V) of Peddapappur (M) in Ananthapuramu (Dist)
Amount

1070.46
3976.43
80.00
5126.89

1070.46
2650.95
80.00
3801.41

1070.46
1988.21
80.00
3138.68

1070.46
1590.57
0.00
2661.03

1070.46
1325.48
80.00
2475.94

1070.46
994.11
80.00
2144.57

879.05
179.56
155.26
83.51
1297.39

C-Data

32 of 209

Hire charges of machinery


SL.
No

Description of machinery

Units

1 concrete mixer300/200 (diesel)

Hour

2 Batchingplant 0.5 cum

Hour

3 needle vibrator 40 mm (petrol)

Hour

Hire
charges

53.50
114.60
8.00

fuel charges

85.30
114.10
7.60

crew
charges

total

189.80
293.80
136.60

328.60
522.50
152.20

0.00

Sl. No.
Description
Quantity
Rate (Rs.)
Per Unit
1
Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Lo
& Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) includin
operational incidental labour charges such as shoring, strutting, sheeting, planking and dewate
including cost of hire charges of T & P, labour charges etc., complete for finished item of w
excluding seignerage charges excluding dewatering charges etc., complete for Foundation
Building.(APSS No. 308)
Light Mazdoor
0.364 Nos
400.00
1 Day
Add 75% for excavation of foundation
1 cu.m.
109.200
1 cu.m.
of
building
add
seigniorage charges
1 cum
0.00
1 cum
Add 14% over heads
254.80 cu.m.
0.14
1 cu.m.
Rate per 1 cu.m.
Total

a) Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Lo
& Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) includin
operational incidental labour charges such as shoring, strutting, sheeting, planking and dewate
including cost of hire charges of T & P, labour charges etc., complete for finished item of w
excluding seignerage charges excluding dewatering charges etc., complete for Pipe line where
depth is more than 1.5 times width.(APSS No. 308)
Light Mazdoor
0.364 Nos
Add 120 % for excavation of Pipe line
1 cu.m.
add seigniorage charges
1 cum
Add 14% over heads
320.32 cu.m.
Rate per 1 cu.m.

400.00
174.720
0.00
0.14

1 Day
1 cu.m.
1 cum
1 cu.m.
Total

C) Earth work excavation and depositing on bank with initial lead of 10m and initial lift of 3m in Lo
& Clayey Soils like BC Soils, Red Earth & Ordinary Gravelly Soils ( SS 20-B) includin
operational incidental labour charges such as shoring, strutting, sheeting, planking and dewate
including cost of hire charges of T & P, labour charges etc., complete for finished item of w
excluding seignerage charges excluding dewatering charges etc., complete for Septic tank soak
and sump.(APSS No. 308)
Light Mazdoor
0.364 nos
400.00
1 nos
add seigniorage charges
1 cum
0.00
1 cum
Add 14% over heads
145.60
Rate per 1 cu.m.
2

C-Data

0.14

1
Total

Earth work excavation for foundations (Mechanical Means) for buildings in ordinary s
and depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth inclu
all operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
overheads & contractors profit complete for finished item of work excluding dewatering charges
as per SS 20 B(APSS 308)
(BLKD-CSTN-2-2)
Ordinary Soil - Mechanical Means up to 3m depth
Unit : 1 cum
Taking output :
240.00 cum
a) Labour
Mazdoor ( Unskilled)
8.32 Nos.
400.00
1 No.
b) Machinery
Shovel 0.85 cum 110hp
6.00 hours
2791.00
1 Hour
6.00 hours
222.30
1 Hour
Crew charges
Add MA on crew charges
0.00
0.00

33 of 209

Amount
iting on bank with initial lead of 10m and initial lift of 3m in(Rs.)
Loamy
ed Earth & Ordinary Gravelly Soils ( SS 20-B) including all
es such as shoring, strutting, sheeting, planking and dewatering
T & P, labour charges etc., complete for finished item of work
uding dewatering charges etc., complete for Foundation of
145.60
109.20
0.00
34.69
289.50

iting on bank with initial lead of 10m and initial lift of 3m in Loamy
ed Earth & Ordinary Gravelly Soils ( SS 20-B) including all
es such as shoring, strutting, sheeting, planking and dewatering
T & P, labour charges etc., complete for finished item of work
ding dewatering charges etc., complete for Pipe line where the
dth.(APSS No. 308)
145.60
174.72
0.00
43.61
363.95

iting on bank with initial lead of 10m and initial lift of 3m in Loamy
ed Earth & Ordinary Gravelly Soils ( SS 20-B) including all
es such as shoring, strutting, sheeting, planking and dewatering
T & P, labour charges etc., complete for finished item of work
ding dewatering charges etc., complete for Septic tank soak pit
145.60
0.00
145.60
19.82
165.45

dations (Mechanical Means) for buildings in ordinary soils


nd with an initial lead of 10m and up to 3m depth including
harges such as shoring, sheeting, planking, strutting etc., and
plete for finished item of work excluding dewatering charges etc.,

3328.00
16746.00
1333.80
0.00

C-Data

34 of 209

c&d)
Overheads&Contractors Profit @1
Cost for 240 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 240

0.14

21407.80

Say
3

Filling with useful available excavated earth (excluding rock) in trenches, sides of foundat
and basement with initial lead in layers not exceeding 15cm thick, consolidating each deposited l
by watering and ramming including cost and conveyence of water to work site and all operatio
incidental, labour charges, hire charges of T & P etc., complete for finished item of work. (APSS
309 & 310)
Light Mazdoor
0.052 Nos
400.00
1 Nos
Water
0.12 Kl
77.00
1 Kl
Add 14% over heads
Rate per 1 cu.m.

30.04

Total

1 cu.m.
0.052 Nos
0.12 Kl

Add 14% over heads


156.69 cu.m.
Rate per Cu.m.

1 cu.m.
0.31 Nos
0.1 Kl

Add 14% over heads


615.35 cu.m.
Rate per Cu.m.

0.14

1 cu.m.
1 Nos
1 Kl
1 cu.m.
Total

483.65
400.00
77.00
0.14

1 cu.m.
1 Nos
1 Kl
1 cu.m.
Total

Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5


proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Bla
Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes on all materials
operational, incidental, and labour charges such as mixing, laying and ramming concrete in laye
position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished ite
work for Foundations and Flooring Bed (APSS No. 402)
material
Metal 40mm
0.9 cu.m.
945.09
1 cu.m.
Sand
0.45 cu.m.
1019.49
1 cu.m.
Cement
129.6 Kgs.
5522.81
1000 Kgs.
Water
1.2 KL
77.00
1 KL
Machinery
concrete mixer300/200 (diesel)
1 Hour
328.60
1 Hour
LA oncrew charges
25%
189.80
1
Labour
1st class mason
0.1 Nos.
525.00
1 Each
Light Mazdoor
1.39 Nos.
400.00
1 Each
Add 14% over heads

C-Data

126.65
400.00
77.00

Filling with Sand Cushion under footings with initial lead in layers not exceeding 15cm t
consolidating each deposited layer by watering and ramming including cost and conveyence of w
to the work site and all operational & incidental charges, labour charges, hire and opertaional cha
of T & P etc., complete for finished item of work. (APSS NO. 309 & 310)
Cost of Sand
Light Mazdoor
Water

Filling with Gravel in trenches, sides of foundations and basement with initial lead in layers
exceeding 15cm thick, consolidating each deposited layer by watering and ramming including cost
conveyence of water to the work site and all operational, incidental, labour charges,hire charges of
P etc., complete for finished item of work. (APSS NO. 309 & 310)
Cost of Gravel
Light Mazdoor
Water

0.14

3102.06 cu.m.

35 of 209

0.14

1 cu.m.

21407.80
89.20
2997.09
24494.09
102.06
102.10

avated earth (excluding rock) in trenches, sides of foundations


yers not exceeding 15cm thick, consolidating each deposited layer
g cost and conveyence of water to work site and all operational,
ges of T & P etc., complete for finished item of work. (APSS NO.
20.80
9.24
30.04
4.09
34.15

ides of foundations and basement with initial lead in layers not


each deposited layer by watering and ramming including cost and
e and all operational, incidental, labour charges,hire charges of T &
work. (APSS NO. 309 & 310)
126.65
20.80
9.24
156.69
21.33
178.05

r footings with initial lead in layers not exceeding 15cm thick,


by watering and ramming including cost and conveyence of water
& incidental charges, labour charges, hire and opertaional charges
em of work. (APSS NO. 309 & 310)
483.65
124.00
7.70
615.35
83.78
699.15

onding to M5 grade as per IS 456 equivalent to (1:5:10)


fine aggregate: Coarse aggregate) using 40mm size Hard Blasted
pproved quarry including cost and conveyance of all materials like
ater etc. to site, including sales & other taxes on all materials, all
charges such as mixing, laying and ramming concrete in layers in
ng top surface, curing concrete, etc., complete for finished item of
g Bed (APSS No. 402)
850.58
458.77
715.76
92.40
328.60
47.45
52.50
556.00
422.35

C-Data

36 of 209

Rate per Cu.m.

Total

Plain Cement Concrete corresponding to M7.5 grade as per IS 456 equivalent to (1:
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 40mm size Hard Bla
Granite (IS383, 1970) metal from approved quarry including cost and conveyance of all materials
cement, sand, coarse aggregate, water etc. to site, including sales & other taxes on all materials
operational, incidental, and labour charges such as mixing, laying and ramming concrete in laye
position not exceeding 15cm, finishing top surface, curing concrete, etc., complete for finished
of work for Foundations (APSS No. 402)
material
Metal 40mm
0.9 cu.m.
945.09
1 cu.m.
Sand
0.45 cu.m.
1019.49
1 cu.m.
Cement
162 Kgs.
5522.81
1000 Kgs.
Water
1.2 KL
77.00
1 KL
Machinery
concrete mixer300/200 (diesel)
1 Hour
328.60
1 Hour
LA oncrew charges
25%
189.80
1
Labour
1st class mason
0.1 cu.m.
525.00
1 cu.m.
Light Mazdoor
1.39 Nos.
400.00
1 Each
Add 14% over heads
3281.00 cu.m.
0.14
1 cu.m.
Rate per Cu.m.
Total

Plain Cement Concrete corresponding to M5 grade as per IS 456 equivalent to (1:5


proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Bla
Granite (IS383, 1970) Machine Crushed graded metal from approved quarry including cost
conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including sal
other taxes on all materials, all operational, incidental, and labour charges such as mixing, la
concrete, finishing top surface, curing concrete, etc., complete for finished item of work for Dum
Columns. (APSS No. 402)
materal
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor

0.9 cu.m.
0.45 cu.m.
129.6 Kgs.
1.2 KL

Rate for other Floors


Basic Rate of P.C.C(1:5:10) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Add 14% over heads
Rate per cu.m.
9

1 cu.m.
1 cu.m.
1000 Kgs.
1 KL

1 Hour
25%

328.60
189.80

1 Hour
1

0.1 cu.m.
1.39 Nos.

525.00
400.00

1 cu.m.
1 Each

GF
3419.13
229.00
1338.00
25%
334.50
0.00
5320.63
0.14
724.40
Total 6045.05

FF
SF
3419.13 3419.13
229.00 229.00
1471.80 1605.60
367.95 401.40
60.85 121.70
5548.73 5776.83
755.46 786.52
6304.20 6563.35

Total
TF
3419.13
229.00
1739.40
434.85
182.55
6004.93
817.57
6822.50

Plain Cement Concrete corresponding to M10 grade as per IS 456 equivalent to (1:
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Bla
Granite (IS383, 1970) Machine Crushed graded metal from from approved quarry including cost
conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including sal
other taxes on all materials, all operational, incidental and labour charges such as mixing, lay
curing concrete, etc., complete for finished item of work for Bed Blocks and Hold Fasts (APSS
402)
Material

C-Data

1297.39
1019.49
5522.81
77.00

37 of 209

3524.45

onding to M7.5 grade as per IS 456 equivalent to (1:4:8)


ne aggregate: Coarse aggregate) using 40mm size Hard Blasted
pproved quarry including cost and conveyance of all materials like
ater etc. to site, including sales & other taxes on all materials, all
charges such as mixing, laying and ramming concrete in layers in
ng top surface, curing concrete, etc., complete for finished item
402)
850.58
458.77
894.70
92.40
328.60
47.45
52.50
556.00
446.71
3727.75

onding to M5 grade as per IS 456 equivalent to (1:5:10)


ne aggregate: Coarse aggregate) using 20mm size Hard Blasted
ushed graded metal from approved quarry including cost and
ment, sand, coarse aggregate, water etc. to site, including sales &
erational, incidental, and labour charges such as mixing, laying
ng concrete, etc., complete for finished item of work for Dummy

1167.65
458.77
715.76
92.40
328.60
47.45
52.50
556.00
3419.13
FF
3419.13
229.00
1873.20
468.30
243.40
6233.03
848.63
7081.70

onding to M10 grade as per IS 456 equivalent to (1:3:6)


ne aggregate: Coarse aggregate) using 20mm size Hard Blasted
shed graded metal from from approved quarry including cost and
ment, sand, coarse aggregate, water etc. to site, including sales &
erational, incidental and labour charges such as mixing, laying,
finished item of work for Bed Blocks and Hold Fasts (APSS No.

C-Data

38 of 209

Graded Metal 20 to 6 mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
Light Mazdoor
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:3:6) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Add 14% over heads
Rate per cu.m.
10

Add 14% over heads


Rate per cu.m.

1 Hour
25%

328.60
189.80

0.1 cu.m.
1.39 Nos.

525.00
400.00

GF
3918.39
61.00
244.00
25%
61.00
0.00
4284.39
0.14
583.32
Total 4867.75

1 cu.m.
1 cu.m.
1000 Kgs.
1 KL
1 Hour
1

1 Each
1 Each
Total
FF
SF
TF
3918.39 3918.39
3918.39
61.00
61.00
61.00
268.40 292.80
317.20
67.10
73.20
79.30
60.85 121.70
182.55
4375.74 4467.09
4558.44
595.76 608.19
620.63
4971.55 5075.30 5179.10

0.9 cu.m.
0.45 cu.m.
331.2 Kgs.
1.2 KL

1297.39
1019.49
5522.81
77.00

1 Hour
25%

328.60
189.80

0.1 cu.m.
1.39 Nos.

525.00
400.00

GF
4532.53
277.00
473.00
25%
118.25
0.00
5400.78
0.14
735.32
Total 6136.10

1 cu.m.
1 cu.m.
1000 Kgs.
1 KL
1 Hour
1

1 cu.m.
1 Each
Total
FF
SF
TF
4532.53 4532.53
4532.53
277.00 277.00
277.00
520.30 567.60
614.90
130.08 141.90
153.73
60.85 121.70
182.55
5520.76 5640.73
5760.71
751.65 767.98
784.32
6272.45 6408.75 6545.05

Plain Cement Concrete M20 Design Mix ( by weigh batching ) using 20mm size (SS5) hard bla
granite machine crushed graded metal (Coarse aggregate) from approved quarry, using a minim
quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance of all mater
like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost on all mate
including steel centering, shuttering, machine mixing, laying concrete, lift charges, curing
complete for finished item of work for steps (APSS No. 402 )
Material
Graded Metal 20mm to 6mm
Sand
Cement

C-Data

1297.39
1019.49
5522.81
77.00

Plain Cement Concrete corresponding to M15 grade as per IS 456 equivalent to (1:
proportion nominal mix (cement: fine aggregate: Coarse aggregate) using 20mm size Hard Bla
Granite (IS383, 1970) Machine Crushed graded metal from approved quarry including cost
conveyance of all materials like cement, sand, coarse aggregate, water etc. to site, including sal
other taxes on all materials, all operational, incidental and labour charges such as mixing, lay
curing concrete, etc., complete for finished item of work (APSS No. 402)
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
concrete mixer300/200 (diesel)
LA oncrew charges
Labour
1st class mason
men &women Mazdoor
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:2:4) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.

11

0.9 cu.m.
0.45 cu.m.
220 Kgs.
1.2 KL

0.8 cu.m.
0.4 cu.m.
350 kgs

39 of 209

1297.39
1019.49
5522.81

1 cu.m.
1 cu.m.
1000 kgs

1167.65
458.77
1215.02
92.40
328.60
47.45
52.50
556.00
3918.39
FF
3918.39
61.00
341.60
85.40
243.40
4649.79
633.07
5282.90

onding to M15 grade as per IS 456 equivalent to (1:2:4)


ne aggregate: Coarse aggregate) using 20mm size Hard Blasted
ushed graded metal from approved quarry including cost and
ment, sand, coarse aggregate, water etc. to site, including sales &
erational, incidental and labour charges such as mixing, laying,
finished item of work (APSS No. 402)
1167.65
458.77
1829.16
92.40
328.60
47.45
52.50
556.00
4532.53
FF
4532.53
277.00
662.20
165.55
243.40
5880.68
800.65
6681.35

n Mix ( by weigh batching ) using 20mm size (SS5) hard blasted


etal (Coarse aggregate) from approved quarry, using a minimum
1 cum of concrete including cost and conveyance of all materials
), coarse aggregate, water etc., to site and cost on all materials
ng, machine mixing, laying concrete, lift charges, curing etc.,
or steps (APSS No. 402 )

1037.91
407.80
1932.98

C-Data

40 of 209

Water
Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
Labour
1st class Masons
Man and Mazdoor
Basic rate per Cum.
Rate for other Floors
Basic Rate of P.C.C(1:1.5:3) per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift Charges per Cum.
Add 14% over heads
Rate per cu.m.
12

1.2 KL
1.333 Hour
1.333 Hour
25%

522.50
152.20
573.72

1 Hour
1 Hour
1

0.1 Nos.
1.39 Nos.

525.00
400.00

1 Each
1 Each

GF
5122.40
61.00
244.00
25%
61.00
0.00
5488.40
0.14
747.25
Total 6235.65

59.4 Kgs
0.5 Cum
0.44 Cum
0.16 Cum
0.33 cu.m.
1.2 Nos
2.0 Nos

Add 14% over heads


2623.71 cu.m.
Rate per cu.m.

C-Data

FF
SF
5122.40 5122.40
61.00
61.00
268.40 292.80
67.10
73.20
60.85 121.70
5579.75 5671.10
759.68 772.12
6339.45 6443.25

TF
5122.40
61.00
317.20
79.30
182.55
5762.45
784.56
6547.05

5522.81
352.09
388.09
1140.09
1019.49
525.00
400.00
0.14

1000 Kgs
1 Cum
1 Cum
1 Cum
1 cu.m.
1 Each
1 Each
1 cu.m.

Coursed Rubble stone masonry 2nd sort, in CM (1:6) prop: (Cement: Sand) using hard blasted gra
stones from approved quarry including cost and conveyance of all materials like Granite sto
cement, sand, water, etc., to site including seigniorage charges, sales & other taxes on all mater
all operational, incidental, and labour charges such as cutting stones to required size and sh
mixing of cement mortar, constructing masonry, curing etc., complete for finished item of work
foundation and basement (APSS No. 601 & 612)
cost of cement
76.8 Kgs
5522.81
1000 Kgs
CR Stone
0.94 Cum
388.09
1 Cum
Through stones 25 x 25x 45 to 60 cms
0.16 Cum
1140.09
1 Cum
Sand
0.32 cu.m.
1019.49
1 cu.m.
1st Class Mason
1.5 Nos
525.00
1 Each
Light Mazdoor
2.32 Nos
400.00
1 Each
Add 14% over heads
3013.11 cu.m.
Rate per cu.m.

14

1 KL

Random Rubble stone masonry, in CM (1:8) prop: (Cement: Sand) using Hard blasted Granite st
from approved quarry including cost and conveyance of all materials like Granite stones, cem
sand, water, etc., to site including sales & other taxes on all materials, all operational, incidental,
labour charges such as cutting stones to required size and shape, mixing of cement mo
constructing masonry, curing etc., complete for finished item of work for foundation and basem
(APSS No. 601 & 615)
cost of cement
RR Stone
CR
Through stones 25 x 25x 45 to 60 cms
Sand
1st Class Mason
Light Mazdoor

13

77.00

0.14

1 cu.m.

Flush Pointing to CRS Masonry in CM(1:3) Prop: including cost and conveyance of all materials
cement, sand, water etc., to site, including sales & other taxes on all materials, all operatio
incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete
finished item of work. (APSS 901,906)
cost of cement
1.44 Kgs
5522.81
1000 Kgs
Sand
0.003 cu.m.
1019.49
1 cu.m.
1st Class Mason
0.05 Nos.
525.00
1 Each
Man mazdoor
0.074 Nos.
400.00
1 Each

41 of 209

92.40
696.49
202.88
143.43
52.50
556.00
5122.40
FF
5122.40
61.00
341.60
85.40
243.40
5853.80
796.99
6650.80

CM (1:8) prop: (Cement: Sand) using Hard blasted Granite stones


st and conveyance of all materials like Granite stones, cement,
sales & other taxes on all materials, all operational, incidental, and
tones to required size and shape, mixing of cement mortar,
omplete for finished item of work for foundation and basement
328.06
176.05
170.76
182.41
336.43
630.00
800.00
2623.71
357.22
2980.95

sort, in CM (1:6) prop: (Cement: Sand) using hard blasted granite


ding cost and conveyance of all materials like Granite stones,
ncluding seigniorage charges, sales & other taxes on all materials,
our charges such as cutting stones to required size and shape,
ting masonry, curing etc., complete for finished item of work for
No. 601 & 612)
424.15
364.80
182.41
326.24
787.50
928.00
3013.11
410.23
3423.35

CM(1:3) Prop: including cost and conveyance of all materials like


including sales & other taxes on all materials, all operational,
ges such as mixing mortar, finishing, curing, etc., complete for
06)
7.95
3.06
26.25
29.60

C-Data

42 of 209

Add 14% over heads


Rate per 1 Sqmt.
15

66.86 cu.m.

0.8 cu.m.
0.4 cu.m.
350 kgs

Water

1.2 KL

Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
Manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Basic rate per Cum.

C-Data

1 cu.m.
Or say

Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (S
hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, usi
minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance o
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost o
materials including centering using Cashewrina Ballies and Wooden runners & stag
including all bracings, cross members etc., shuttering , machine mixing, laying conc
vibrating,lift charges, curing etc., complete but excluding cost of steel and its fabrication charge
finished item of work for foundation, plinth , pedastals(below plinth)(APSS No. 402 & 403)
Material
Graded Metal 20mm to 6mm
Sand
Cement

16

0.14

1297.39
1019.49
5522.81
77.00

1 cu.m.
1 cu.m.
1000 kgs
1 KL

1.333 Hour
1.333 Hour
25%

522.50
152.20
573.72

1 Hour
1 Hour
1

0.133 Nos.
0.267 Nos.
4.6 Nos.

525.00
468.75
400.00

1 Each
1 Each
1 Each
Total

a) VRCC M20 grade design mix for fo


Basic Rate per Cum.
1 cu.m.
Centering Charges per Cum.
1 cu.m.
Add La charges on labour on centering
25%
Add 14% over heads
7417.13 cu.m.
Rate per cu.m.

6548.88
750.00
473.00
0.14

1 cu.m.
1 cu.m.

b) VRCC M20 design mix for plinth b


Basic Rate per Cum.
1 cu.m.
Centering Charges per Cum.
1 cu.m.
Add La charges on labour on centering
25%
Add 14% over heads
9310.13 cu.m.
Rate per cu.m.

6548.88
2476.00
1141.00
0.14

c) VRCC M20 for pedestals


Basic Rate per Cum.
1 cu.m.
Centering Charges per Cum.
1 cu.m.
Add La charges on labour on centering
25%
Add 14% over heads
7805.13 cu.m.
Rate per cu.m.

6548.88
1068.00
753.00
0.14

1 cu.m.

1 cu.m.
1 cu.m.
1 cu.m.

1 cu.m.
1 cu.m.
1 cu.m.

Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching / Mixer ) using 20mm
(SS5) hard granite machine crushed graded metal (Coarse aggregate) from approved quarry, usi
minimum quantity of 350 kgs. of cement per 1 cum of concreteincluding cost and conveyance o
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost o
materials including centering using Cashewrina Ballies and Wooden runners & stag
including all bracings, cross members etc., shuttering , machine mixing, laying conc
vibrating,lift charges, curing etc., complete but excluding cost of steel and its fabrication charge
finished item of work (APSS No. 402 & 403) For coloumns , Lintels, Water tanks, Rcc wall
building
Material
Graded Metal 20mm to 6mm
0.8 cu.m.
1297.39
1 cu.m.
Sand
0.4 cu.m.
1019.49
1 cu.m.

43 of 209

66.86
9.10
76.00

e M 20 Design Mix ( by weigh batching ) using 20mm size (SS5)


ed graded metal (Coarse aggregate) from approved quarry, using a
ment per 1 cum of concreteincluding cost and conveyance of all
gate (Sand), coarse aggregate, water etc., to site and cost on all
sing Cashewrina Ballies and Wooden runners & staging
members etc., shuttering , machine mixing, laying concrete,
mplete but excluding cost of steel and its fabrication charges for
n, plinth , pedastals(below plinth)(APSS No. 402 & 403)
1037.91
407.80
1932.98
92.40
696.49
202.88
143.43
69.83
125.16
1840.00
6548.88

6548.88
750.00
118.25
1009.84
8427.00

6548.88
2476.00
285.25
1267.57
10577.75

6548.88
1068.00
188.25
1062.67
8867.80

e M 20 Design Mix ( by weigh batching / Mixer ) using 20mm size


d graded metal (Coarse aggregate) from approved quarry, using a
ment per 1 cum of concreteincluding cost and conveyance of all
gate (Sand), coarse aggregate, water etc., to site and cost on all
sing Cashewrina Ballies and Wooden runners & staging
members etc., shuttering , machine mixing, laying concrete,
mplete but excluding cost of steel and its fabrication charges for
2 & 403) For coloumns , Lintels, Water tanks, Rcc walls in

1037.91
407.80

C-Data

44 of 209

Cement
Water
Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
Manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Basic rate per Cum.

1000 kgs
1 KL

522.50
152.20
573.72

1 Hour
1 Hour
1

0.167 Nos.
0.167 Nos.
5.6 Nos.

525.00
468.75
400.00

1 Each
1 Each
1 Each
Total

8821.35
0.14 1201.03

Rate per cu.m.

Total 10022.40

b) For Lintels
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each

GF
6919.85
760.00
953.00
25%
238.25

GF
6919.85
229.00
1338.00
25%
334.50

8871.10
0.14 1207.80
Total 10078.95

FF
6919.85
229.00
1471.80
367.95
240.60
9229.20
1256.56

SF
6919.85
229.00
1605.60
401.40
481.19
9637.04
1312.08

TF
6919.85
229.00
1739.40
434.85
721.79
10044.89
1367.61

10485.80 0949.15 11412.55

FF
6919.85
760.00
1048.30
262.08
240.60
9230.83
1256.78
10487.65

SF
6919.85
760.00
1143.60
285.90
481.19
9590.54
1305.75

TF
6919.85
760.00
1238.90
309.73
721.79
9950.27
1354.73
0896.30 11305.05

Vibrated Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (S
hard blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, usi
minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance o
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost o
materials including centering using Cashewrina Ballies and Wooden runners & stag
including all bracings, cross members etc., shuttering , machine mixing, laying conc
vibrating,lift charges, curing etc., complete but excluding cost of steel and its fabrication charge
finished item of work (APSS No. 402 & 403) For beams and slabs
Material
Graded Metal 20mm to 6mm
Sand
Cement
Water
Machinery
Batchingplant 0.5 cum
needle vibrator 40 mm (petrol)
LA on crew charges
Manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Basic rate per Cum.

0.8 cu.m.
0.4 cu.m.
350 kgs
1.2 KL

1297.39
1019.49
5522.81
77.00

1 cu.m.
1 cu.m.
1000 kgs
1 KL

0.308 Hour
0.308 Hour
25%

522.50
152.20
132.56

1 Hour
1 Hour
1

0.067 Nos.
0.133 Nos.
3.077 Nos.

525.00
468.75
400.00

1 Each
1 Each
1 Each
Total

a) For Roof beams

C-Data

5522.81
77.00

1.333 Hour
1.333 Hour
25%

a) For columns / RCC walls and Wate


Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads

Add 14% over heads


Rate per cu.m.
17

350 kgs
1.2 KL

45 of 209

1932.98
92.40
696.49
202.88
143.43
87.68
78.28
2240.00
6919.85

FF
6919.85
229.00
1873.20
468.30
962.38
10452.73
1423.14
11875.90

e M 20 Design Mix ( by weigh batching ) using 20mm size (SS5)


ed graded metal (Coarse aggregate) from approved quarry, using a
ment per 1 cum of concrete including cost and conveyance of all
gate (Sand), coarse aggregate, water etc., to site and cost on all
sing Cashewrina Ballies and Wooden runners & staging
members etc., shuttering , machine mixing, laying concrete,
mplete but excluding cost of steel and its fabrication charges for
& 403) For beams and slabs
1037.91
407.80
1932.98
92.40
160.93
46.88
33.14
35.18
62.34
1230.80
5040.36

C-Data

46 of 209

Rate for other Floors


Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per cu.m.

GF
5040.36
1342.00
1122.00
25%
280.50
7784.86
0.14 1059.91
Total 8844.80

b) VRCC M20 design mix for Slabs 75mm


thick
Cost of VRCC for 75 mm thick slab
0.075 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
378.03
152.00
127.00
31.75

0.14
Total

688.78
93.78
782.60

c) VRCC M20 design mix for Slabs 100mm


thick
Cost of VRCC for 100 mm thick slab
0.10 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
504.04
152.00
127.00
31.75

0.14
Total

814.79
110.93
925.75

d) VRCC M20 design mix for Slabs of 110mm


Cost of VRCC for 110 mm thick slab
0.11 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
554.44
152.00
127.00
31.75

0.14
Total

865.19
117.80
983.00

e) VRCC M20 design mix for Slabs of 115mm


Cost of VRCC for 115 mm thick slab
0.115 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads

C-Data

25%

GF
579.64
152.00
127.00
31.75

0.14

890.39
121.23

47 of 209

FF
SF
5040.36 5040.36
1342.00 1342.00
1234.20 1346.40
308.55 336.60
132.83 265.66
8057.94 8331.02
1097.09 1134.27
9155.05 9465.30

5040.36

1 cu.m.

FF
SF
378.03 378.03
152.00 152.00
139.70 152.40
34.93
38.10
9.96
19.92
714.62 740.45
97.30 100.81
811.95 841.30

5040.36

FF
579.64
152.00
139.70
34.93
15.28
921.55
125.47

TF
504.04
152.00
165.10
41.28
39.85
902.27
122.84
1025.15

1 cu.m.

FF
SF
554.44 554.44
152.00 152.00
139.70 152.40
34.93
38.10
14.61
29.22
895.68 926.16
121.95 126.10
1017.65 1052.30

5040.36

TF
378.03
152.00
165.10
41.28
29.89
766.30
104.33
870.65

1 cu.m.

FF
SF
504.04 504.04
152.00 152.00
139.70 152.40
34.93
38.10
13.28
26.57
843.95 873.11
114.90 118.87
958.85 992.00

5040.36

TF
5040.36
1342.00
1458.60
364.65
398.50
8604.11
1171.45
9775.60

TF
554.44
152.00
165.10
41.28
43.83
956.65
130.25
1086.90

1 cu.m.
SF
579.64
152.00
152.40
38.10
30.55
952.69
129.71

TF
579.64
152.00
165.10
41.28
45.83
983.85
133.95

FF
5040.36
1342.00
1570.80
392.70
531.33
8877.19
1208.63
10085.85

378.03
FF
378.03
152.00
177.80
44.45
39.85
792.13
107.85
900.00

504.04
FF
504.04
152.00
177.80
44.45
53.13
931.42
126.81
1058.25

554.44

579.64

C-Data

48 of 209

Rate per 1 Sqmts.


Total 1011.65
f) VRCC M20 design mix for Slabs of 120mm
Cost of VRCC for 120 mm thick slab
0.12 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
604.84
152.00
127.00
31.75

915.59
0.14
124.66
Total 1040.30

g) VRCC M20 design mix for Slabs of 125mm


thick
Cost of VRCC for 125 mm thick slab
0.125 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
630.04
152.00
127.00
31.75

940.79
0.14
128.09
Total 1068.90

h) VRCC M20 design mix for Slabs of 130mm


thick
Cost of VRCC for 130 mm thick slab
0.130 cu.m.
Rate for other Floors
GF
Rate as worked out above per Cum.
655.25
Hire charges on centering material
152.00
Labour charges for centering
127.00
LA on centering labour charges
25%
31.75
Lift charges @ 10% extra on each
floor
966.00
Add 14% over heads
0.14
131.52
Rate per 1 Sqmts.
Total 1097.55
h) VRCC M20 design mix for Slabs of 140mm
thick
Cost of VRCC for 140 mm thick slab
0.14 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
705.65
152.00
127.00
31.75

1016.40
0.14
138.38
Total 1154.80

i) VRCC M20 design mix for Slabs of 150mm


thick
Cost of VRCC for 150 mm thick slab
0.15 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering

C-Data

GF
756.05
152.00
127.00

49 of 209

1047.05 1082.45
5040.36

1 cu.m.

FF
SF
604.84 604.84
152.00 152.00
139.70 152.40
34.93
38.10
15.94
31.88
947.41 979.22
128.99 133.32
1076.45 1112.55

5040.36

FF
756.05
152.00
139.70

TF
655.25
152.00
165.10
41.28
51.80
1065.43
145.06
1210.50

1 cu.m.

FF
SF
705.65 705.65
152.00 152.00
139.70 152.40
34.93
38.10
18.60
37.19
1050.88 1085.34
143.08 147.77
1194.00 1233.15

5040.36

TF
630.04
152.00
165.10
41.28
49.81
1038.23
141.36
1179.60

1 cu.m.

FF
SF
655.25 655.25
152.00 152.00
139.70 152.40
34.93
38.10
17.27
34.54
999.15 1032.29
136.03 140.55
1135.20 1172.85
5040.36

TF
604.84
152.00
165.10
41.28
47.82
1011.04
137.65
1148.70

1 cu.m.

FF
SF
630.04 630.04
152.00 152.00
139.70 152.40
34.93
38.10
16.60
33.21
973.27 1005.75
132.51 136.93
1105.80 1142.70

5040.36

1117.85

TF
705.65
152.00
165.10
41.28
55.79
1119.82
152.46
1272.30

1 cu.m.
SF
756.05
152.00
152.40

TF
756.05
152.00
165.10

604.84

630.04
FF
630.04
152.00
177.80
44.45
66.42
1070.71
145.78
1216.50

655.25
FF
655.25
152.00
177.80
44.45
69.07
1098.57
149.57
1248.15
705.65

756.05

C-Data

50 of 209

LA on centering labour charges


Lift charges @ 10% extra on each
Add 14% over heads
Rate per 1 Sqmts.

25%

31.75

1066.80
0.14
145.25
Total 1212.10

j) VRCC M20 design mix for Slabs of 165mm


thick
Cost of VRCC for 165 mm thick slab
0.165 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
831.66
156.00
131.00
32.75

1151.41
0.14
156.76
Total 1308.20

k) VRCC M20 design mix for Slabs of 175mm


thick
Cost of VRCC for 175 mm thick slab
0.175 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
882.06
156.00
131.00
32.75

1201.81
0.14
163.63
Total 1365.45

l) VRCC M20 design mix for Slabs of 180mm


thick
Cost of VRCC for 180 mm thick slab
0.18 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

25%

GF
907.26
156.00
131.00
32.75

1227.01
0.14
167.06
Total 1394.10

m) VRCC M20 design mix for Slabs of 200mm


Cost of VRCC for 200 mm thick slab
0.2 cu.m.
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmts.

GF
1008.07
156.00
131.00
25%
32.75
1327.82
0.14
180.78
Total 1508.65

n) VRCC M20 design mix for Slabs of 225mm


thick

C-Data

51 of 209

34.93
38.10
19.92
39.85
1102.60 1138.40
150.12 154.99
1252.75 1293.40

5040.36

1 cu.m.

FF
SF
831.66 831.66
156.00 156.00
144.10 157.20
36.03
39.30
21.92
43.83
1189.71 1227.99
161.98 167.19
1351.70 1395.20

5040.36

TF
882.06
156.00
170.30
42.58
69.74
1320.68
179.81
1500.50

1 cu.m.

FF
SF
907.26 907.26
156.00 156.00
144.10 157.20
36.03
39.30
23.91
47.82
1267.30 1307.58
172.54 178.03
1439.85 1485.65

5040.36

TF
831.66
156.00
170.30
42.58
65.75
1266.29
172.41
1438.70

1 cu.m.

FF
SF
882.06 882.06
156.00 156.00
144.10 157.20
36.03
39.30
23.25
46.49
1241.44 1281.05
169.02 174.42
1410.50 1455.50

5040.36

41.28
59.77
1174.20
159.87
1334.10

TF
907.26
156.00
170.30
42.58
71.73
1347.87
183.51
1531.40

1 cu.m.

FF
SF
1008.07 1008.07
156.00 156.00
144.10 157.20
36.03
39.30
26.57
53.13
1370.77 1413.70
186.63 192.48
1557.45 1606.20

TF
1008.07
156.00
170.30
42.58
79.70
1456.65
198.32
1655.00

831.66

882.06
FF
882.06
156.00
183.40
45.85
92.98
1360.29
185.20
1545.50

907.26

1008.07

C-Data

52 of 209

Cost of VRCC for 225 mm thick slab

0.225 cu.m.

Rate for other Floors


Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
LA on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 10 Sqmts.
18

FF
SF
1134.08 1134.08
156.00 156.00
144.10 157.20
36.03
39.30
29.89
59.77
1500.10 1546.35
204.24 210.54
1704.35 1756.90

TF
1134.08
156.00
170.30
42.58
89.66
1592.62
216.84
1809.50

GF
6671.45
760.00
953.00
25%
238.25
8622.70
0.14 1173.98
Total 9796.70

FF
6671.45
760.00
1048.30
262.08
240.60
8982.43
1222.96
10205.40

SF
6671.45
760.00
1143.60
285.90
481.19
9342.14
1271.93

TF
6671.45
760.00
1238.90
309.73
721.79
9701.87
1320.91
0614.10 11022.80

Reinforced cement concrete with M 20 grade Design mix ( by weigh batching ) using 20mm size (S
machine crushed hard blasted granite graded metal (coarse aggregate) from approved quarry u
a minimum quantity of 350 Kg of cement per 1 Cum of concrete including cost and conveyance o
materials like cement, fine aggregate (sand) ,coarse aggregate, water etc. to site and cost on
materials
including centering using Cashewrina Ballies and Wooden runners & stag
including all bracings, cross members etc., shuttering, machine mixing, laying concrete, 7.
thick at fixed end and 5cm thick at free end with an average thickness of 6.25cm includ
labour charges for mixing, laying, curing etc., complete but excluding cost of steel and
fabrication charges for finished item of work
for sun-shades of any width as
per
approved plan / design and of
Material
average
thickness
of 62.50mm
Graded Metal
20mm to 6mm
(Sand
thickness at support 75mm and
thickness
at edge 50mm) (APSS
Cement
No. 402, 403)
Water
Machinery

C-Data

1453.83
0.14
197.94
Total 1651.80

1 cu.m.

Reinforced Cement Concrete M 20 Design Mix ( by weigh batching ) using 20mm size (SS5)
blasted granite machine crushed graded metal (Coarse aggregate) from approved quarry, usin
minimum quantity of 350 kgs. of cement per 1 cum of concrete including cost and conveyance o
materials like cement, fine aggregate (Sand), coarse aggregate, water etc., to site and cost o
materials including centering using Cashewrina Ballies and Wooden runners & stag
including all bracings, cross members etc., shuttering , machine mixing, laying concrete
charges, curing etc., complete but excluding cost of steel and its fabrication charges for finished
of work (APSS No. 402 & 403)
Material
Graded Metal 20mm to 6mm
0.8 cu.m.
1297.39
1 cu.m.
Sand
0.4 cu.m.
1019.49
1 cu.m.
Cement
350 kgs
5522.81
1000 kgs
Water
1.2 KL
77.00
1 KL
Machinery
Batchingplant 0.5 cum
1.333 Hour
522.50
1 Hour
LA on crew charges
25%
391.64
1
Manpower
1st Class Mason
0.167 Nos.
525.00
1 Each
2nd Class Mason
0.167 Nos.
468.75
1 Each
Man Mazdoor
5.6 Nos.
400.00
1 Each
Basic rate per Cum
a) For Lintels
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Cum.

19

GF
1134.08
156.00
131.00
25%
32.75

5040.36

0.8 cu.m.
0.4 cu.m.
350 kgs
1.2 KL

53 of 209

1297.39
1019.49
5522.81
77.00

1 cu.m.
1 cu.m.
1000 kgs
1 KL

1134.08

Design Mix ( by weigh batching ) using 20mm size (SS5) hard


raded metal (Coarse aggregate) from approved quarry, using a
ment per 1 cum of concrete including cost and conveyance of all
gate (Sand), coarse aggregate, water etc., to site and cost on all
sing Cashewrina Ballies and Wooden runners & staging
embers etc., shuttering , machine mixing, laying concrete, lift
xcluding cost of steel and its fabrication charges for finished item

1037.91
407.80
1932.98
92.40
696.49
97.91
87.68
78.28
2240.00
6671.45

FF
6671.45
760.00
1334.20
333.55
962.38
10061.58
1369.88
11431.50

20 grade Design mix ( by weigh batching ) using 20mm size (SS 5)


te graded metal (coarse aggregate) from approved quarry using
ement per 1 Cum of concrete including cost and conveyance of all
e (sand) ,coarse aggregate, water etc. to site and cost on all
using Cashewrina Ballies and Wooden runners & staging
mbers etc., shuttering, machine mixing, laying concrete, 7.5cm
at free end with an average thickness of 6.25cm including
g, curing etc., complete but excluding cost of steel and its
of work

1037.91
407.80
1932.98
92.40

C-Data

54 of 209

Batchingplant 0.5 cum


LA on crew charges
Manpower
1st Class Mason
2nd Class Mason
Man Mazdoor
Basic rate per Cu.m
a) Chajja / Sunshade
Cost of RCC for 62.5 mm thick
sunshade
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
Add 14% over heads
Rate per Sqmt.
b) for platforms of 50 mm thick
Cost of RCC for 50 mm thick platform
Rate for other Floors
Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.
b) for shelves of 25 mm thick
Cost of RCC for 25 mm thick shelves

C-Data

522.50
90.49

1 Hour
1

0.067 Nos.
0.133 Nos.
3.077 Nos.

525.00
468.75
400.00

1 Each
1 Each
1 Each
Total

4982.96

1 cu.m.

0.0625 cu.m.

25%

GF
311.44
150.00
146.00
36.50

0.14
Total

643.94
87.67
731.65

0.05 cu.m.

25%

GF
249.15
152.00
127.00
31.75

0.14
Total

559.90
76.23
636.15

0.025 cu.m.

Rate for other Floors


Rate as worked out above per Cum.
Hire charges on centering material
Labour charges for centering
La on centering labour charges
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.
20

0.308 Hour
25%

25%

GF
124.57
152.00
127.00
31.75

0.14
Total

435.32
59.27
494.60

FF
SF
311.44 311.44
150.00 150.00
160.60 175.20
40.15
43.80
8.30
16.60
670.49 697.04
91.29
94.90
761.80 791.95

4982.96

1 cu.m.

FF
SF
249.15 249.15
152.00 152.00
139.70 152.40
34.93
38.10
6.64
13.28
582.42 604.93
79.30
82.36
661.75 687.30

4982.96

TF
311.44
150.00
189.80
47.45
24.91
723.60
98.52
822.15

TF
249.15
152.00
165.10
41.28
19.92
627.45
85.43
712.90

1 cu.m.

FF
SF
124.57 124.57
152.00 152.00
139.70 152.40
34.93
38.10
3.32
6.64
454.52 473.71
61.88
64.50
516.45 538.25

TF
124.57
152.00
165.10
41.28
9.96
492.91
67.11
560.05

Pointing to Cuddapah / Shahabad slabs in CM(1:3) Prop: including cost and conveyance of all mate
like cement, sand, water etc., to site, including sales & other taxes on all materials, all operatio
incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete
finished item of work. (APSS 901,906)
cost of cement for Cement Mortar
0.96 Kgs
5.52
1 Kgs
(1:3)
cost of sand for Cement Mortar (1:3)
0.002 cu.m.
1019.49
1 cu.m.
1st Class Mason
0.048 Nos.
525.00
1 Each
2nd Class Mason
0.112 Nos.
468.75
1 Each
Man mazdoor
0.05 Nos.
400.00
1 Each
Woman mazdoor
0.11 Nos.
400.00
1 Each
Rate per 1 Sqmt.
Total

55 of 209

160.93
22.62
35.18
62.34
1230.80
4982.96
311.44
FF
311.44
150.00
204.40
51.10
33.21
750.15
102.13
852.30

249.15
FF
249.15
152.00
177.80
44.45
26.57
649.97
88.49
738.50

124.57
FF
124.57
152.00
177.80
44.45
13.28
512.10
69.72
581.85

abs in CM(1:3) Prop: including cost and conveyance of all materials


e, including sales & other taxes on all materials, all operational,
ges such as mixing mortar, finishing, curing, etc., complete for
6)
5.30
25.20
52.50
20.00
44.00
147.00

C-Data

56 of 209

21

Brick Masonry in superstructure with CM (1:8) prop: using Fly ASH Bricks of size 290x225x140
with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance o
materials like cement, sand, fly ash bricks, water etc., to site, including sales & other taxes o
materials, all operational, incidental and labour charges such as mixing cement mortar, construc
masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work. (APSS
501 & 504).
Wall thickness
0.225
Material
Fly Ash Bricks 290x225x140mm
110 Nos
24953.53
1000 Nos
Cement for Cement Mortar (1:8)
18 Kgs
5.52
1 Kgs
Sand for Cement Mortar (1:8)
0.1 cu.m.
1019.49
1 cu.m.
Labour
1st class mason
0.42 cu.m.
525.00
1 cu.m.
2nd class mason
0.92 Nos.
468.75
1 Each
Man Mazdoor
0.7 Nos.
400.00
1 Each
Woman Mazdoor
2.1 Nos.
400.00
1 Each
Basic Rate per Cum.
Rate for other Floors
Basic rate per Cum
Hire charges of stage scafflding per
cum
Labour charges for stage scaffolding
per
Add cum
LA on Labour for scaffolding
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Cum.

22

TF
4717.95
44.13
620.89
155.22
531.53
6069.72
826.39
6896.15

0.225

total
Add 14% over heads
Basic Rate per Cum.

110 Nos
24 Kgs
0.1 cu.m.

24953.53
5.52
1019.49

1000 Nos
1 Kgs
1 cu.m.

0.42 cu.m.
0.92 Nos.
0.7 Nos.
2.1 Nos.

525.00
468.75
400.00
400.00

1 cu.m.
1 Each
1 Each
1 Each

0.14

Reinforced Fly Ash Brick Masonry 10cm thick for partition walls in CM (1:4) prop: Fly Bricks of
290x100x140mm with compressive of 50 Kgs / Sqcm from approved source and placing 2nos. of 6
dia MS bars embedded in every 3rd layer with free ends of reinforcement keyed into mortar join
the main brick work whereever applicable including cost and conveyance of all materials like cem
sand, bricks, water etc., to site, sales & other taxes on all materials, all operational, incidental
labour charges such as mixing cement mortar, constructing masonry, scaffolding charges, lift char
curing, etc., but excluding cost and conveyance of steel and its fabrication charges complete
finished item of work. (APSS No. 501 & 509).
Material
Fly Ash Bricks 290x100x140mm
Cement for Cement Mortar (1:4)
Sand for Cement Mortar (1:4)

C-Data

5105.58
0.14
695.12
Total 5800.70

FF
SF
4717.95 4717.95
44.13
44.13
390.13 505.33
97.53 126.33
177.18 354.35
5426.92 5748.09
738.87 782.60
6165.80 6530.70

Brick Masonry in superstructure with CM (1:6) prop: using Fly ASH Bricks of size 290x225x140
with compressive of 50 Kgs / Sqcm from approved source including cost and conveyance o
materials like cement, sand, fly ash bricks, water etc., to site, including sales & other taxes o
materials, all operational, incidental and labour charges such as mixing cement mortar, construc
masonry, scaffolding charges, lift charges, curing, etc., complete for finished item of work
basement (APSS No. 501 & 504).
Wall thickness
Material
Fly Ash Bricks 290x225x140mm
Cement for Cement Mortar (1:8)
Sand for Cement Mortar (1:8)
Labour
1st class mason
2nd class mason
Man Mazdoor
Woman Mazdoor

23

GF
4717.95
44.13
274.80
25%
68.70

24 Nos
7.2 Kgs
0.02 cu.m.

57 of 209

11423.79
5.52
1019.49

1000 Nos
Kgs
1 cu.m.

h CM (1:8) prop: using Fly ASH Bricks of size 290x225x140mm


m from approved source including cost and conveyance of all
h bricks, water etc., to site, including sales & other taxes on all
and labour charges such as mixing cement mortar, constructing
harges, curing, etc., complete for finished item of work. (APSS No.

2744.89
99.36
101.95
220.50
431.25
280.00
840.00
4717.95
FF
4717.95
44.13
736.00
184.00
708.70
6390.78
870.10
7260.90

h CM (1:6) prop: using Fly ASH Bricks of size 290x225x140mm


m from approved source including cost and conveyance of all
h bricks, water etc., to site, including sales & other taxes on all
and labour charges such as mixing cement mortar, constructing
charges, curing, etc., complete for finished item of work. for

2744.89
132.48
101.95
220.50
431.25
280.00
840.00
4751.07
646.86
5397.95

0cm thick for partition walls in CM (1:4) prop: Fly Bricks of size
of 50 Kgs / Sqcm from approved source and placing 2nos. of 6mm
layer with free ends of reinforcement keyed into mortar joints of
icable including cost and conveyance of all materials like cement,
es & other taxes on all materials, all operational, incidental and
ent mortar, constructing masonry, scaffolding charges, lift charges,
d conveyance of steel and its fabrication charges complete for
& 509).
274.17
39.74
20.39

C-Data

58 of 209

Labour
1st class mason
2nd class mason
Man Mazdoor
Basic Rate per One Sqmt.
Rate for other Floors
Basic rate per sqm
Hire charges of stage scafflding per
cum
Labour charges for stage scaffolding
per
Add cum
LA on Labour for scaffolding
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per One Sqmt.
24

0.06 cu.m.
0.06 Nos.
0.275 Nos.

25%

GF
503.93
9.93
61.83
15.46

0.14
Total

591.15
80.49
671.65

525.00
468.75
400.00

1 cu.m.
1 Each
1 Each

FF
SF
503.93 503.93
9.93
9.93
87.78 113.70
21.95
28.43
16.96
33.93
640.55 689.92
87.21
93.93
727.80 783.85

TF
503.93
9.93
139.70
34.93
50.89
739.38
100.67
840.05

Providing High Yield Strength Deformed (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8
to 40mm diameters, cutting, bending, to required sizes and shapes placing in position with c
blocks of approved size and binding wire of 20SWG, forming grills for reinforcement work as
approved designs and drawings including cost and conveyance of bars from approved sources to
of work, including cost and conveyance of binding wire, cover blocks, chairs, overlaps, spac
dowels, wastage etc., and all operational, incidental, and labour charges such as cutting, bend
placing in position, tying etc., and sales & other taxes,on cost of all materials complete for finis
item of work (APSS No.126) in all floors.
Material
Cost of steel including 5% wastage
and overlaps

1.05 MT

42075.29

1 MT

cost of binding wire


Labour
Blacksmith/Tin Smith/Rivetor
Light mazdoor
Rate per MT

6 Kg

70.00

1 Kg

10 Nos
10 Nos

25

GF
53849.05

53849.05
0.14 7331.55
Total 61180.65

FF
SF
53849.05 53849.05
925.00 1850.00

TF
53849.05
2775.00

54774.05 55699.05 56624.05


7457.49 7583.43
7709.36
62231.55 3282.50 64333.45

Providing Mild Steel Bars (Fe 250 grade as per IS 432) of 6mm diameter, cutting, bending, to requ
sizes and shapes placing in position with cover blocks of approved size and binding wire of 20S
forming grills for reinforcement work as per approved designs and drawings including cost
conveyance of bars from approved sources to site of work, including cost and conveyance of bin
wire, cover blocks, chairs, overlaps, spacers, dowels, wastage etc., and all operational, incidental,
labour charges such as cutting, bending, placing in position, tying etc., and sales & other taxes,on
of all materials complete for finished item of work (APSS No.126) in all floors.
Material
Cost of Mild steel

1.05 MT

45075.29

1 MT

6 Kg

70.00

1 Kg

cost of binding wire


Labour
Blacksmith/Tin Smith/Rivetor
Light mazdoor
Rate per MT
Rate for other Floors
Basic rate per MT
Lift Charges per MT @10% extra on
labour per floor

C-Data

1 Nos
1 Nos
Total

Rate for other Floors


Basic rate per MT
Lift Charges per MT @10% extra on
labour per floor
Add 14% over heads
Rate per One MT

525.00
400.00

59 of 209

10 Nos
10 Nos

525.00
400.00

1 Nos
1 Nos
Total

GF
56999.05

FF
SF
56999.05 56999.05
925.00 1850.00

TF
56999.05
2775.00

31.50
28.13
110.00
503.93
FF
503.93
9.93
165.60
41.40
67.85
788.71
107.38
896.10

med (HYSD) steel bars (Fe 415 grade as per IS 1786-1985) of 8mm
ng, to required sizes and shapes placing in position with cover
ng wire of 20SWG, forming grills for reinforcement work as per
uding cost and conveyance of bars from approved sources to site
yance of binding wire, cover blocks, chairs, overlaps, spacers,
ational, incidental, and labour charges such as cutting, bending,
sales & other taxes,on cost of all materials complete for finished
ors.
44179.05
420.00
5250.00
4000.00
53849.05
FF
53849.05
3700.00
57549.05
7835.30
65384.40

ade as per IS 432) of 6mm diameter, cutting, bending, to required


n with cover blocks of approved size and binding wire of 20SWG,
ork as per approved designs and drawings including cost and
sources to site of work, including cost and conveyance of binding
spacers, dowels, wastage etc., and all operational, incidental, and
ding, placing in position, tying etc., and sales & other taxes,on cost
item of work (APSS No.126) in all floors.
47329.05
420.00
5250.00
4000.00
56999.05
TF
56999.05
3700.00

C-Data

60 of 209

Add 14% over heads


Rate per One MT
26

56999.05
0.14 7760.42
Total 64759.50

Ornamental Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:5) and top
of 4mm thick in CM (1:3) dubara sponge finish including cost and conveyance of all materials
cement, sand, water etc., to site, sales & other taxes on all materials,all operational, incidental
labour charges such as mixing mortar, scaffolding charges, lift charges, including cutting of Gro
wherever necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for E
Surfaces of Wall for finished item of work. (APSS 901,903 & 904)
Material
Base coat 8mm thick in C.M. (1:5)
Cement
3.17 kgs
5522.81
1000 kgs
cost of sand for Plastering
0.011 cu.m.
1086.49
1 cu.m.
Top Coat 4mm thick in C.M. (1:3)
Cement
1.92 kgs
5522.81
1000 kgs
cost of sand for Plastering
0.004 cu.m.
1086.49
1 cu.m.
Labour
1st Class Mason
0.063 Nos.
525.00
1 Each
2nd Class Mason
0.147 Nos.
468.75
1 Each
Light mazdoor
0.39 Nos.
400.00
1 Each
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of stage scafflding per
sqm
Labour charges for stage scaffolding
per sqm
Add LA on Labour for scaffolding
Lift charges @ 10% extra on each
Add 14% over heads
Rate per 1 Sqmt.

27

GF
302.39
2.37
12.55
0%

0.00

0.14
Total

317.31
43.20
360.51

FF
302.39
2.37
17.64

SF
302.39
2.37
22.73

TF
302.39
2.37
27.82

0.00
0.00
25.80
51.60
348.20 379.09
47.41
51.61
395.61 430.70

0.00
77.39
409.97
55.82
465.79

Plastering 12mm thick in two coats with base coat of 8mm thick in CM (1:6) and top coat of 4mm t
in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cement, s
water etc., to site, sales & other taxes on all materials,all operational, incidental and labour cha
such as mixing mortar, scaffolding charges, lift charges, including cutting of Grooves wher
necessary as directed by Engineer - in - charge, finishing, curing, etc., complete for Even Surfa
of Wall for finished item of work. (APSS 901,903 & 904)
Material
Base coat 8mm thick in C.M. (1:6)
Cement
cost of sand for Plastering
Top Coat 4mm thick in C.M. (1:4)
Cement
cost of sand for Plastering
Labour
1st Class Mason
2nd Class Mason
Light mazdoor
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of access scafflding pers
Labour charges for access scaffolding
per sqm
Add LA on Labour for scaffolding
Lift charges @ 10% extra on each

C-Data

58324.05 58850.05 59774.05


7940.82 8012.43
8138.24
66264.90 6862.50 67912.30

2.64 kgs
0.011 cu.m.

5522.81
1086.49

1000 kgs
1 cu.m.

1.44 kgs
0.004 cu.m.

5522.81
1086.49

1000 kgs
1 cu.m.

0.063 Nos.
0.147 Nos.
0.39 Nos.

25%

61 of 209

525.00
468.75
400.00

1 Each
1 Each
1 Each

GF
296.81
0.99
6.18

FF
296.81
0.99
8.78

SF
296.81
0.99
11.37

TF
296.81
0.99
13.97

1.55

2.20
25.80

2.84
51.60

3.49
77.39

60699.05
8264.18
68963.25

n two coats with base coat of 8mm thick in CM (1:5) and top coat
sponge finish including cost and conveyance of all materials like
ales & other taxes on all materials,all operational, incidental and
tar, scaffolding charges, lift charges, including cutting of Grooves
Engineer - in - charge, finishing, curing, etc., complete for Even
m of work. (APSS 901,903 & 904)

17.51
11.95
10.60
4.35
33.08
68.91
156.00
302.39
FF
302.39
2.37
32.91
0.00
103.19
440.86
60.02
500.88

with base coat of 8mm thick in CM (1:6) and top coat of 4mm thick
ncluding cost and conveyance of all materials like cement, sand,
xes on all materials,all operational, incidental and labour charges
g charges, lift charges, including cutting of Grooves wherever
in - charge, finishing, curing, etc., complete for Even Surfaces
k. (APSS 901,903 & 904)

14.58
11.95
7.95
4.35
33.08
68.91
156.00
296.81
FF
296.81
0.99
16.56
4.14
103.19

C-Data

62 of 209

Add 14% over heads


Rate per 1 Sqmt.
28

C-Data

334.58 363.61
45.55
49.51
380.15 413.15

392.65
53.46
446.15

GF
313.70
0.99
6.18
25%

1.55

0.14
Total

322.42
43.90
366.35

FF
313.70
0.99
8.78

SF
313.70
0.99
11.37

TF
313.70
0.99
13.97

2.20
2.84
25.80
51.60
351.47 380.50
47.85
51.80
399.35 432.30

3.49
77.39
409.54
55.76
465.30

Plastering with CM(1:5) Prop: 12mm thick in single coat including cost and conveyance of all mate
like cement, sand, water etc., to site, including sales & other taxes on all materials, all operatio
incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete
finished item of work. (APSS 901,906)
cost of cement for Cement Mortar
sand for Cement Plastering (1:5)
1st Class Mason
Man mazdoor

30

305.53
41.60
347.15

Plastering 20mm thick in two coats with base coat of 16mm thick in CM (1:6) and top coat of 4
thick in CM (1:4) dubara sponge finish including cost and conveyance of all materials like cem
sand, water etc., to site, sales & other taxes on all materials, all operational, incidental and la
charges such as mixing mortar,scaffolding charges, lift charges, finishing,including cutting of Gro
wherever necessary as directed by Engineer - in - charge, curing, etc., complete for Une
Surfaces of Brick Wall for finished item of work. (APSS 901,903 & 904)
Base coat 16 mm thick in C.M.
(1:6)
Cement
4.32 kgs
5522.81
1000 kgs
cost of sand for Plastering
0.018 cu.m.
1086.49
1 cu.m.
Top Coat 4mm thick in C.M. (1:4)
Cement
1.44 kgs
5522.81
1000 kgs
cost of sand for Plastering
0.004 cu.m.
1086.49
1 cu.m.
Labour
1st Class Mason
0.063 Nos.
525.00
1 Each
2nd Class Mason
0.147 Nos.
468.75
1 Each
Light mazdoor
0.39 Nos.
400.00
1 Each
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of access scafflding pers
Labour charges for access scaffolding
per sqm
Add LA on Labour for scaffolding
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmt.

29

0.14
Total

4.32 kg
0.015 cu.m.
0.06 Nos.
0.096 Nos.

5.52
1086.49
525.00
400.00

1 kg
1 cu.m.
1 Each
1 Each

Rate per 1 Sqmt.


Total
Rate for other Floors
GF
FF
SF
TF
Basic rate per 1 Sqmt.
110.05
110.05 110.05
110.05
Hire charges of access scafflding pers
0.99
0.99
0.99
0.99
qm
Labour charges for access scaffolding
6.18
8.78
11.37
13.97
per
Add sqm
LA on Labour for scaffolding
25%
1.55
2.20
2.84
3.49
Lift charges @ 10% extra on each
6.99
13.98
20.97
floor
118.77
129.01 139.23
149.47
Add 14% over heads
0.14
16.17
17.56
18.96
20.35
Rate per 1 Sqmt.
Total 134.95
146.60 158.20
169.85
Plastering with CM(1:4) Prop: 20mm thick in single coat including cost and conveyance of all mate
like cement, sand, water etc., to site, including sales & other taxes on all materials, all operatio
incidental charges and labour charges such as mixing mortar, finishing, curing, etc., complete
finished item of work. (APSS 901,906)
cost of cement for Cement Mortar
7.56 kg
5.52
1 kg
sand for Cement Plastering (1:4)
0.021 cu.m.
1086.49
1 cu.m.
1st Class Mason
0.094 Nos.
525.00
1 Each
Man mazdoor
0.16 Nos.
400.00
1 Each

63 of 209

421.69
57.41
479.15

with base coat of 16mm thick in CM (1:6) and top coat of 4mm
finish including cost and conveyance of all materials like cement,
other taxes on all materials, all operational, incidental and labour
ffolding charges, lift charges, finishing,including cutting of Grooves
y Engineer - in - charge, curing, etc., complete for Uneven
d item of work. (APSS 901,903 & 904)
23.86
19.56
7.95
4.35
33.08
68.91
156.00
313.70
TF
313.70
0.99
16.56
4.14
103.19
438.58
59.71
498.30

thick in single coat including cost and conveyance of all materials


te, including sales & other taxes on all materials, all operational,
ges such as mixing mortar, finishing, curing, etc., complete for
06)
23.85
16.30
31.50
38.40
110.05

thick in single coat including cost and conveyance of all materials


te, including sales & other taxes on all materials, all operational,
ges such as mixing mortar, finishing, curing, etc., complete for
06)
41.73
22.82
49.35
64.00

C-Data

64 of 209

Rate per 1 Sqmt.


Rate for other Floors
Basic rate per 1 Sqmt.
Hire charges of access scafflding pers
qm
Labour charges for access scaffolding
per
Add sqm
LA on Labour for scaffolding
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmt.
31

0.14
Total

186.62
25.41
212.05

Total
TF
177.90
0.99
13.97
3.49
34.01
230.36
31.36
261.75

GF
343.70

0.14
Say

343.70
46.79
390.50

FF
SF
343.70 343.70
22.02
44.04
365.72 387.74
49.79
52.79
415.55 440.55

TF
343.70
66.06
409.76
55.79
465.55

Flooring with Polished Black Kadapa Slabs of 15 mm thick set over a base coat of CM (1:8), 12
thick (joints of stone must be flushed) over C.C. bed already laid or R.C.C. roof slab only after i
properly cured, cleaned, moistered and where necessary treated with neat grey cement slurr
honey like consistency spred at3.3 kgs of cement for 1 sqm. and jointed with neat cement paste to
depth, including cost and conveyance of all materials like cement, sand, water, flooring stones et
site, sales and other taxes on all materials, all operational, incidental and labour charges suc
dressing of flooring stones to the required sizes, mixing of cement mortar, laying, jointing, curing
charges etc., complete for finished item of work.(APSS No.703 & 701)
Material
Cost of Polished Bethamcherla pure
white
stone
minimum
25 mm thick
Cement
for Morter
andof
slurry
(0.254M
x 0.254M)
Coarse sand
for mortor(C.M. 1:8)
Machinery
Machine
charges
for
rubbuing/polishing
floor
LA charges on crew charges
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Add water charges @1% on labour
Basic rate per 1 Sqmt.

1.1 Sqmt.
7.46 Kgs
0.012 cum
0.1 day
25%
0.31 Nos.
0.11 Nos.
0.086 Nos.
1%

Rate for other Floors


Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each

C-Data

FF
SF
177.90 177.90
0.99
0.99
8.78
11.37
2.20
2.84
11.34
22.67
201.21 215.77
27.39
29.38
228.60 245.15

Providing impervious coat over RCC roof slab to required slopes with CM (1:3) prop. 20mm t
(average) mixed with water proofing compound manufactured by reputed manufacturers as appro
by Engineer-in-charge at 1Kg/bag of cement, laid over roof slab when it is green, finished smooth
a floating coat of neat cement and thread lining at regular intervals of 45cmx45cm including cost
conveyance of all materials like cement, sand, water proofing compound, water etc., to site,sal
other taxes on all materials, all operational, incidental and labour charges such as mixing mo
laying, rounding off at junctions of wall and slab, rendering smooth with thread lining, curing
charges, etc., complete for finished item of work (APSS No. 901 & 903).
cost of cement for Cement Mortar
10.08 kg
5.52
1 kg
(1:3)
sand for Cement Plastering(1:3)
0.021 cu.m.
1086.49
1 cu.m.
Water proof compound
0.2 Kgs
52.00
1 Kgs
1st Class Mason
0.066 Nos.
525.00
1 Each
2nd Class Mason
0.154 Nos.
468.75
1 Each
Man Mazdoor
0.37 Nos.
400.00
1 Each
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmt.

32

25%

GF
177.90
0.99
6.18
1.55

65 of 209

GF
472.81

152.89
5522.81
1019.49
0.00

525.00
468.75
400.00
248.71

FF
472.81
25.12

1 Sqmt.
1000 Kgs
1 cum
1 day

1 Each
1 Each
1 Each

SF
472.81
50.24

TF
472.81
75.36

177.90

C roof slab to required slopes with CM (1:3) prop. 20mm thick


g compound manufactured by reputed manufacturers as approved
cement, laid over roof slab when it is green, finished smooth with
hread lining at regular intervals of 45cmx45cm including cost and
ment, sand, water proofing compound, water etc., to site,sales &
erational, incidental and labour charges such as mixing mortar,
wall and slab, rendering smooth with thread lining, curing, lift
item of work (APSS No. 901 & 903).
55.64
22.82
10.40
34.65
72.19
148.00
343.70
FF
343.70
88.08
431.78
58.79
490.60

pa Slabs of 15 mm thick set over a base coat of CM (1:8), 12mm


d) over C.C. bed already laid or R.C.C. roof slab only after it is
and where necessary treated with neat grey cement slurry of
gs of cement for 1 sqm. and jointed with neat cement paste to full
ce of all materials like cement, sand, water, flooring stones etc. to
materials, all operational, incidental and labour charges such as
quired sizes, mixing of cement mortar, laying, jointing, curing, lift
em of work.(APSS No.703 & 701)
168.18
41.20
12.23
0.00
0.00
162.75
51.56
34.40
2.49
472.81
FF
472.81
100.48

C-Data

66 of 209

Add 14% over heads


Rate per 1 Sqmt.
33

C-Data

472.81
64.37
537.20

497.93 523.05
67.79
71.21
565.75 594.30

548.17
74.63
622.85

Flooring with Rough Kadapa slabs of 40 mm thick (0.457 x 457M)laid over existing CC bed or
slab set over a base coat of CM (1:8), 12mm thick and pointing with CM(1:3) to full depth of floo
slabs dully filling joints neatly , including cost and conveyance of all materials like flooring sto
cement, sand, water, etc. to site, sales and other taxes on all materials, all operational, incidental
labour charges such as mixing of cement mortar, laying, pointing, curing, lift charges etc., comp
for finished item of work.(APSS No.703 & 701)
Rough Kadapa slab
cost of cement for Cement Mortar
sand for Cement Mortar (1:8)
Pointing with CM (1:3)

1.05 Sqmt.
2.16 kg
0.012 cu.m.
1 Sqmt.

1st Class Mason


2nd Class Mason
Man Mazdoor
Woman Mazdoor
Basic rate per 1 Sqmt.

0.096 Nos.
0.224 Nos.
0.22 Nos.
0.11 Nos.

Rate for other Floors


Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per 1 Sqmt.
34

0.14
Total

GF
601.33

0.14
Total

601.33
81.87
683.20

135.97
5.52
1019.49
147.00
525.00
468.75
400.00
400.00

1 Sqmt.
1 kg
1 cu.m.
1 Sqmt.
1 Each
1 Each
1 Each
1 Each

FF
SF
601.33 601.33
28.74
57.48
630.07 658.81
85.78
89.70
715.85 748.55

TF
601.33
86.22
687.55
93.61
781.20

Providing skirting to internal walls 12.5 Cm high withPolished Black Kadapa Slabs of 15 mm thick
length equal to flooring stones set over a base coat of CM (1:3), 12mm thick with cement slurr
honey like consistency spread @ 3.3 Kgs per sqm and jointed with neat cement paste mixed
pigment of matching shade to full depth (joints of stone should be flushed), including cost
conveyance of all materials like cement, sand, water, flooring stones etc. to site, sales and other t
on all materials, all operational, incidental and labour charges such as dressing of flooring stone
the required sizes, mixing of cement mortar, laying, jointing, curing, lift charges etc., complete
finished item of work.(APSS No.701 & 707)
Material
Cost of Polished Bethamcherla pure
1.1 Sqmt.
152.89
1 Sqmt.
white stone minimum of 25 mm thick
(0.254M x 0.254M)
sand for Cement Mortar (1:3)
0.012 cu.m.
1019.49
1 cu.m.
cement for Cement Mortar (1:3) base
5.76 Kgs
5522.81
1000 Kgs
coat
Cement for slurry
3.3 Kgs
5522.81
1000 Kgs
Labour
1st Class Mason
0.096 Nos.
525.00
1 Each
2nd Class Mason
0.224 Nos.
468.75
1 Each
Man Mazdoor
0.31 Nos.
400.00
1 Each
Add water charges @1% on labour
1%
279.40
Basic rate per 1 Sqmt.
Rate for other Floors
GF
FF
SF
TF
Basic rate per 1 Sqmt.
512.64
512.64 512.64
512.64
Lift charges @ 10% extra on each
28.22
56.44
84.66
floor
512.64
540.86 569.08
597.30
Add 14% over heads
0.14
69.80
73.64
77.48
81.32
Rate per 1 Sqmt.
Total 582.45
614.55 646.60
678.65

67 of 209

573.29
78.05
651.35

of 40 mm thick (0.457 x 457M)laid over existing CC bed or roof


8), 12mm thick and pointing with CM(1:3) to full depth of flooring
luding cost and conveyance of all materials like flooring stones,
ales and other taxes on all materials, all operational, incidental and
ement mortar, laying, pointing, curing, lift charges etc., complete
03 & 701)
142.77
11.92
12.23
147.00
50.40
105.00
88.00
44.00
601.33

2.5 Cm high withPolished Black Kadapa Slabs of 15 mm thick with


over a base coat of CM (1:3), 12mm thick with cement slurry of
.3 Kgs per sqm and jointed with neat cement paste mixed with
l depth (joints of stone should be flushed), including cost and
ent, sand, water, flooring stones etc. to site, sales and other taxes
idental and labour charges such as dressing of flooring stones to
nt mortar, laying, jointing, curing, lift charges etc., complete for
& 707)
168.18

12.23
31.81
18.23
50.40
105.00
124.00
2.79
512.64
FF
512.64
112.88
625.52
85.16
710.70

C-Data

68 of 209

35

Supplying and fixing of Polished Black Kadapa Slabs of 15 mm thick in Single piece with the edges
nosed and set over a base coat of CM (1:3), 12mm thick, and fixing in position with neat cement p
including cost and conveyance of all materials like cement, sand, water, stones etc. to site, sales
other taxes on all materials, all operational, incidental and labour charges such as dressing of stone
the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete
finished item of work For Raisers (APSS No.701 & 707)
For Raisers of 0.15 Mt. Height
Material
Cost of Polished Shahbad stone
sand for Cement Mortar (1:3)
cement for Cement Mortar (1:3) base
coat
Cement for slurry
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Flat nosing edges as per BMM-V.13
Add water charges @1% on labour
Basic rate per 1 Sqmt.

1.1 Sqmt.
0.012 cu.m.
5.76 Kgs
3.3 Kgs
0.096 Nos.
0.224 Nos.
0.31 Nos.
13.33 Rmt.
1%

Rate for other Floors

GF

Basic rate per 1 Sqmt.


Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.
36

0.14

672.60
91.57
764.17

1 Sqmt.
1 cu.m.
1000 Kgs
1000 Kgs

525.00
468.75
400.00
12.00
279.40

FF

1 Each
1 Each
1 Each
1 Rmt.

SF

TF

672.60 672.60
28.22
56.44
700.82 729.04
95.42
99.26
796.24 828.30

672.60
84.66
757.26
103.10
860.36

Supplying and fixing of Polished Black Kadapa Slabs of 15 mm thick in Single piece with the edges
nosed and set over a base coat of CM (1:8), 12mm thick, and fixing in position with neat cement p
including cost and conveyance of all materials like cement, sand, water, stones etc. to site, sales
other taxes on all materials, all operational, incidental and labour charges such as dressing of stone
the required sizes, mixing of cement mortar, fixing in position, curing, lift charges etc., complete
finished item of work for Treads (APSS No.701 & 707)
Treads of 0.30 Mt wide
Cost of Polished Shahbad stone
1.1 Sqmt.
152.89
1 Sqmt.
Cement for jointing
5.46 Kgs
5522.81
1000 Kgs
Coarse sand for mortor(C.M. 1:8)
0.012 cum
1019.49
1 cum
Machinery
Machine
charges
for
0.1 day
0.00
1 day
rubbuing/polishing
floor
LA charges on crew charges
25%
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Flat nosing edges
Basic rate per 1 Sqmt.
Rate for other Floors
Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.

C-Data

672.60

152.89
1019.49
5522.81
5522.81

0.31 Nos.
0.11 Nos.
0.086 Nos.
6.67 Rmt.

GF
539.32

0.14
Say

69 of 209

539.32
73.43
612.75

525.00
468.75
400.00
12.00

1 Each
1 Each
1 Each
1 Rmt.

FF
SF
539.32 539.32
24.87
49.74
564.19 589.06
76.81
80.20
641.00 669.26

TF
539.32
74.61
613.93
83.59
697.52

ck Kadapa Slabs of 15 mm thick in Single piece with the edges flat


M (1:3), 12mm thick, and fixing in position with neat cement paste
l materials like cement, sand, water, stones etc. to site, sales and
ational, incidental and labour charges such as dressing of stones to
nt mortar, fixing in position, curing, lift charges etc., complete for
SS No.701 & 707)

168.18
12.23
31.81
18.23
50.40
105.00
124.00
159.96
2.79
672.60
FF
672.60
112.88
785.48
106.94
892.42

ck Kadapa Slabs of 15 mm thick in Single piece with the edges flat


M (1:8), 12mm thick, and fixing in position with neat cement paste
materials like cement, sand, water, stones etc. to site, sales and
ational, incidental and labour charges such as dressing of stones to
nt mortar, fixing in position, curing, lift charges etc., complete for
S No.701 & 707)
168.18
30.15
12.23
0.00
0.00
162.75
51.56
34.40
80.04
539.32
FF
539.32
99.49
638.81
86.97
725.78

C-Data

70 of 209

37

In - situ - Granolithic Concrete Flooring 20mm thick with CC(1:1:2) Prop: using 6mm to 12mm size
machine crushed metal laid monolithically over 100mm thick CC flooring bed (1:5:10) with 40mm
metal in alternate panels of size not exceeding 1.50m x 1.50m and finishing the top surfac
required smoothness and slopes, thread lining as directed by the Engineer - in - charge including
and conveyance of all materials like cement, sand, water, etc. to site, sales and other taxes o
materials, all operational, incidental and labour charges such as mixing of cement concrete, lay
curing, lift charges etc., complete for finished item of work (APSS No.701 & 710)
6mm to 12mm HBG metal
Sand
Cement
PCC bed (1:5:10) 100mm thick
1st Class Mason
2nd Class Mason
Manand women Mazdoor

0.017 cum
0.0085 cum
12 Kgs
0.10 cum
0.125 Nos.
0.006 Nos.
0.3 Nos.

Add 14% over heads


Rate per 1 Sqmt.
38

Rate for other Floors


Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.

C-Data

1 cum
1 cum
1000 Kgs
1 cum
1 Each
1 Each
1 Each

590.96
Total

Flooring with Ceramic Tiles of 7.3mm thick 1st. quality of any shade as approved by Engineer charge set over a base coat of CM (1:8), 12mm thick laid over flooring bed / V.R.C.C. slab, with
cement slurry of honey like consistency spread at the rate of 3.3 Kgs of cement per Sq.m and joi
with neat white cement paste to full depth mixed with pigment of matching shade including cost
conveyance of all materials like cement, sand, water, ceramic tiles etc. to site, sales and other t
on all materials, all operational, incidental and labour charges such as mixing of cement mo
laying, curing, lift charges etc., complete for finished item of work.(APSS No.701 & 707) in
Floors
Material
Ceramic Tiles
1.05 Sqmt.
465.00
1 Sqmt.
Sand
0.012 cum
1019.49
1 cum
Cement
2.16 Kgs
5522.81
1000 Kgs
Grey Cement for slurry
3.3 Kgs
5522.81
1000 Kgs
White Cement for pointing
0.2 Kgs
29.00
1 Kgs
Labour
1st Class Mason
2nd Class Mason
Man Mazdoor
Add water charges @1% on labour
Basic rate per 1 Sqmt.

39

0.14

1022.42
1019.49
5522.81
3102.06
525.00
468.75
400.00

0.096 Nos.
0.224 Nos.
0.33 Nos.
1%

GF
826.71

0.14

826.71
112.56
939.30

525.00
468.75
400.00
287.40

1 Each
1 Each
1 Each

FF
SF
826.71 826.71
29.03
58.05
855.74 884.76
116.51 120.46
972.30 1005.25

TF
826.71
87.08
913.79
124.41
1038.25

Dadooing to walls with white glazed tiles 1st. quality of any size of brand as approved by Enginee
- charge and set over a base coat of CM (1:5), 12mm thick and neat cement paste at the rate o
Kg/Sqmt. and jointed with white cement paste mixed with pigment of matching shade including
and conveyance of all materials like cement, sand, water, tiles, etc. to site,sales and other taxes o
materials, C921 such as mixing of cement mortar, laying in position, curing, lift charges etc., comp
for finished item of work (APSS No.701 & 707) in All Floors
white glazed tiles
1.05 Sqmt
348.00
1 Sqmt
Grey cement
0.33 Kgs
5522.81
1000 Kgs
White cement
0.6 Kgs
29.00
1 Kgs
Cement for Cement Mortar CM (1:5)
3.45 Kgs
5.52
1 Kgs
Sand Mortar CM (1:5)
0.012 Cum
1019.49
1 Cum
Labour
1st Class Mason
0.077 Nos.
525.00
1 Each
Man Mazdoor
0.08 Nos.
400.00
1 Each
Basic rate per 1 Sqmt.

71 of 209

ng 20mm thick with CC(1:1:2) Prop: using 6mm to 12mm size HBG
hically over 100mm thick CC flooring bed (1:5:10) with 40mm HBG
not exceeding 1.50m x 1.50m and finishing the top surface to
read lining as directed by the Engineer - in - charge including cost
e cement, sand, water, etc. to site, sales and other taxes on all
l and labour charges such as mixing of cement concrete, laying,
r finished item of work (APSS No.701 & 710)
17.38
8.67
66.27
310.21
65.63
2.81
120.00
590.96
80.46
671.45

m thick 1st. quality of any shade as approved by Engineer - in (1:8), 12mm thick laid over flooring bed / V.R.C.C. slab, with neat
ncy spread at the rate of 3.3 Kgs of cement per Sq.m and jointed
ll depth mixed with pigment of matching shade including cost and
ment, sand, water, ceramic tiles etc. to site, sales and other taxes
cidental and labour charges such as mixing of cement mortar,
mplete for finished item of work.(APSS No.701 & 707) in All
488.25
12.23
11.93
18.23
5.80
50.40
105.00
132.00
2.87
826.71
FF
826.71
116.11
942.82
128.37
1071.20

tiles 1st. quality of any size of brand as approved by Engineer - in


f CM (1:5), 12mm thick and neat cement paste at the rate of 3.3
ment paste mixed with pigment of matching shade including cost
cement, sand, water, tiles, etc. to site,sales and other taxes on all
ement mortar, laying in position, curing, lift charges etc., complete
.701 & 707) in All Floors
365.40
1.82
17.40
19.04
12.23
40.43
32.00
488.33

C-Data

72 of 209

Rate for other Floors


Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
floor
Add 14% over heads
Rate per Sqmt.
40

488.33
66.49
554.85

TF
488.33
21.73
510.06
69.44
579.50

0.2 kgs
0.021 Nos.
0.032 Nos.
1%
0.14

25.00
485.63
400.00
28.00

1 kgs
1 Each
1 Each

28.28
Total

Painting to New Iron work with two coats of ready mixed synthetic enamel paint first quality all sh
over an existing steel primer including cost and conveyance of all materials to site, sales & o
taxes, incidental, operational and all labour charges etc., complete for finished item of work. (A
No. 1201, 1207 & 1212).in All Floors
Red oxide primer
0.07 Ltr
185.00
1 Ltr
Cost of Synthetic Enamel Paint
1st Class Painter
2nd Class Painter

0.11 Ltr
0.033 Nos.
0.077 Nos.

Add 14% over heads


Rater per 1 Sqmt. for all floors
42

0.14

FF
SF
488.33 488.33
7.24
14.49
495.57 502.82
67.47
68.46
563.05 571.30

Whiting to new walls and ceiling in two coats with Surya cem or equavalent quality to give an e
shade after thoroughly brushing the surface to remove all loose powdered materials including
and conveyance of all materials and water to site, sales & other taxes, all operational, incidental
labour charges such as cleaning the surface, painting, curing etc., complete for finished item of w
for internal walls. (APSS No.901 & 908) in All Floors
Surya Cem
Painter
Man Mazdoor
sundries including brushes,ladders,
etc.,
Add 14% over heads
Rater per 1 Sqmt. for all floors

41

GF
488.33

0.14

276.00
600.00
468.75

1 Ltr
1 Each
1 Each

99.20
Total

Supply and fixing of 110mm dia ISI mark PVC Rain water spouts of 4.0 Kg/cm2 pressure including
of necessary pvc bends, shoes and M.S.clamps and all other accessories and fixing in pos
including cost and conveyance of all materials to site , sales and other taxes on all materials
operational, incidental and labour cahrges such as fixing in alignment etc., complete for finished
of work.(APSS NO1328) in All Floors
Cost of 110mm dia PVC Pipe.BMW3.00 Rmt.
484.00
3 Rmt
G.13
Cost of P.V.C.Bend 391 BMW-G.57
1.00 No.
83.00
1 No
Cost PVC shoe 397 BMW-G.63
1.00 No.
70.00
1 No
Cost of Clips 440 BMW-G.106
3.00 Nos.
18.00
1 No
Plumber 1st Class
0.30 Nos.
480.00
1 Each
Plumber 2nd class
0.70 Nos.
420.00
1 Each
Man Mazdoor
1.00 No.
400.00
1 Each
Rate per 3 Rmt.
Add 14% over heads

0.14

509.67

Rate per Rmt.


43

Reinforced cement mortar Facia 5 cm thick in CM (1:3) for drop walls, Fins & staircase railing
rabbit wire mesh & nominal reinforcement as directed by Engineer-in-charge with dubara sp
finishing including cost & conveyence of all materials to site, including sales and other taxes on
materials and all operational, incidental charges such as labour charges, like mixing cement mo
scaffolding charges, lift charges, curing, for making 50 mm thick RCM Paradah walls (RCM Drop w
including tying Rabbit (chicken) wire mesh to the existing mild steel / HYSD Steel reinforcem
applying mortar lumps, finishing, plastering to both faces, sponge finishing etc complete for finis
item of work but excluding cost of steel and its fabrication charges in All Floors
Materials
Costof rabit wire mesh

C-Data

Total

1.33 Sqmt

73 of 209

17.00

1 Sqmt

FF
488.33
28.97
517.30
70.43
587.75

two coats with Surya cem or equavalent quality to give an even


e surface to remove all loose powdered materials including cost
d water to site, sales & other taxes, all operational, incidental and
surface, painting, curing etc., complete for finished item of work
& 908) in All Floors
5.00
10.20
12.80
0.28
28.28
3.85
32.15

coats of ready mixed synthetic enamel paint first quality all shades
ding cost and conveyance of all materials to site, sales & other
ll labour charges etc., complete for finished item of work. (APSS
oors
12.95
30.36
19.80
36.09
99.20
13.51
112.75

mark PVC Rain water spouts of 4.0 Kg/cm2 pressure including Cost
d M.S.clamps and all other accessories and fixing in position
all materials to site , sales and other taxes on all materials, all
ahrges such as fixing in alignment etc., complete for finished item
ors
484.00
83.00
70.00
54.00
144.00
294.00
400.00
1529.00
509.67
69.39
579.10

cm thick in CM (1:3) for drop walls, Fins & staircase railing with
orcement as directed by Engineer-in-charge with dubara spong
ce of all materials to site, including sales and other taxes on all
ental charges such as labour charges, like mixing cement mortar,
ing, for making 50 mm thick RCM Paradah walls (RCM Drop walls)
re mesh to the existing mild steel / HYSD Steel reinforcement
astering to both faces, sponge finishing etc complete for finished
eel and its fabrication charges in All Floors
22.61

C-Data

74 of 209

43 Grade cement
Cost of coarse sand
Labour
1st Class Mason
Miller operator
Man Mazdoor
Hire charges of miller
Basic rate per 1 Sqmt.

31.91 Kgs
0.06 Cum

5522.81
1019.49

1000 Kgs
1 Cum

0.80 Nos.
1.00 Nos.
1.00 Nos.
0.20 Hour

525.00
525.00
400.00
328.60

1 Each
1 Each
1 Each
1 Hour

Rate for other Floors


Basic rate per 1 Sqmt.
Lift charges @ 10% extra on each
Add 14% over heads
Rate per Sqmt.
44

0.14

1668.69
227.19
1895.90

FF
SF
1668.69 1668.69
141.07 282.14
1809.76 1950.83
246.40 265.61
2056.20 2216.45

TF
1668.69
423.22
2091.91
284.81
2376.75

Painting to New wood work with two coats of ready mixed synthetic enamel paint first qualit
shades to give an even shade over base coat Primer with Luppam finishing after thorou
brushing the surface to remove all remains including cost and conveyance of all materials to
sales & other taxes, all operational, incidental and labour charges etc., complete for finished ite
work.(3 coats) (APSS No. 1201 & 1212).in All Floors
PRIMARY COAT
Luppam finish BMT-J.07
0.1 Kg.
158.00
1 Kg
Ready mixed primer
0.07 lit
158.00
1 Lt
Ist class painter
0.021 Nos.
600.00
1 Each
2nd class painter
0.049 Nos.
468.75
1 Each
TWO COATS OF PAINTING
Synthetic enamel paint
0.12 lit
276.00
1 lit
1st class painter
0.036 Nos.
600.00
1 Each
2nd class painter
0.084 Nos.
468.75
1 Each
Add 14% over heads
Rate per 1 Sqmt. for all Floors

45

GF
1668.69

0.14

156.52
Total

Supply and Fixing of 50mm thick Jali including cost and conveyance of all materials to site, sal
other taxes, all operational, incidental and labour charges etc., complete for finished item of wor
All Floors.
Rate as per SSR
1 Sqmt
402.00
1 Sqmt
Add 14% over heads

0.14

402.00

Rate per Sqmt.


46

Supplying & fixing collapsible steel shutters with vertical, double channel of 20 x10x2 mm of 100
centre ,Bracers with flat iron 40x40x6 mm with 38 mm dia steel pulleys, the top, bottom and
vertical frames of the collapsible gate with 65x65mmx8mm MS Angle and middle guide rail at
height with 65mmx8mm MS flat for the pulleys to guide and fixed with necessary hold fasts, b
nuts, rivets, locking arrangements, stoppers, handles, all accessories all fixtures and painted with
coat of approved steel primer etc., complete for finished item of work as per special spn 1105
Rate as per SSR BMT-F.30
Add 14% over heads
Rate per Sqmt.

47

C-Data

Total

1 Sqmt
0.14

2503.00
2503.00

1 Sqmt
Total

Supply and Fixing AC Sheet Corrugated 6mm thick including Labour Charges for fixing AC Sh
including cost of J bolts bitumen washers etc with or without ridges complete including cost
conveyance of all materials to site, sales and other taxes, all labour charges etc., complete for finis
item of work
Unit =
1 Sqmt
A ) material
cost of 6mm thick corregated AC
1.05 Sqmt
222.00
1 Sqmt
8mm dia G.I.J bolts & nuts
2.2 Nos.
10.00
1 Each

75 of 209

176.23
59.13
420.00
525.00
400.00
65.72
1668.69
FF
1668.69
564.29
2232.98
304.02
2537.05

wo coats of ready mixed synthetic enamel paint first quality all


er base coat Primer with Luppam finishing after thoroughly
remains including cost and conveyance of all materials to site,
, incidental and labour charges etc., complete for finished item of
1212).in All Floors
15.80
11.06
12.60
22.97
33.12
21.60
39.38
156.52
21.31
177.85

ali including cost and conveyance of all materials to site, sales &
tal and labour charges etc., complete for finished item of work in
402.00
54.73
456.75

shutters with vertical, double channel of 20 x10x2 mm of 100 mm


0x6 mm with 38 mm dia steel pulleys, the top, bottom and side
ate with 65x65mmx8mm MS Angle and middle guide rail at site
r the pulleys to guide and fixed with necessary hold fasts, bolts,
stoppers, handles, all accessories all fixtures and painted with one
omplete for finished item of work as per special spn 1105
2503.00
340.78
2843.80

gated 6mm thick including Labour Charges for fixing AC Sheets


washers etc with or without ridges complete including cost and
sales and other taxes, all labour charges etc., complete for finished

233.10
22.00

C-Data

76 of 209

G.I washersBitumen washers


Bitumen washers
B) labour
Carpenter II class
Man Mazdoor
Sundries including 50 x 6 mm Iron
wind ties and white lead etc.,
Rate per 1 Sqmt. for all Floors
Add 14% over heads
Rate per one Sqmt
48

2.2 Nos.
2.2 Nos.

1.00
1.00

1 Each
1 Each

0.043 Nos.
0.054 Nos.

525.00
400.00

1 Each
1 Each

0.14

Supply and Fixing MS Purlins 50mm dia including Labour Charges for fixing complete including
and conveyance of all materials to site, sales and other taxes, all labour charges etc., complete
finished item of work
Cost of MS Pipe 50mm dia asper (BMT5.1 Kgs.
61.00
1 Kgs.
F.04)
Fabrication,
Cutting
and
Fixing
5.1 Kgs.
21.00
1 Kgs.
charges
(BMM-V.16)
Add 14% over heads

0.14

418.20

Rate per Rmt.


49

Painting to New walls with two coats of Plastic Emulsion paint of superior quality of approved b
and shade over base coat of cement primer grade -I making three coats in all to give an e
shade after thoroughly brushing the surface to remove all loose powdered materials, including
and conveyance of all materials, including cost and conveyance of all materials, cost of brushes, w
to site, etc., sales & other taxes, all operational, incidental and labour charges such as scaffol
charges, lift charges, curing etc., complete for finished item of work in all floors for Walls.(APSS
912) in All Floors
Cement Primer Grade I
Plastic Emulsion Paint
Labour for Priming Coat
1st class painter
2nd class painter
Labour for Two Coats
1st class painter
2nd class painter
Add 14% over heads
Rater per 1 Sqmt. for all floors

50

165.00
196.00

1 Kgs
1 Ltr

0.021 Nos.
0.049 Nos.

600.00
468.75

1 Each
1 Each

0.036 Nos.
0.084 Nos.

600.00
468.75

1 Each
1 Each

0.14

130.68
Total

Making Green Chalk Board of size 3.00Mx1.20Mts including border with plastering in CM (1:2) 12
thick as base coat and 3mm thick top coat with cement green oxide powder in (1:1) prop. and ma
border of 50x20mm thick alround the chalk board over existing plastered surface and painting
chalk board surface with chalk board paint as per direction of Engineer-in-Charge including cost
conveyance of all materials, sales and other taxes on cost of materials and all operational, incide
and labour charges etc., complete for finished item of work (APSS No.1603)
base coat in cm 1:2
Cost of of sand for CM (1:2)
cost of cement for CM 1:2)
1st Class Mason
2nd Class Mason
Man mazdoor
Woman mazdoor
Basic rate per 10 Sqmt.
20mm thick plastering in CM(1:2)
Cost of of sand for CM (1:2)
cost of cement for CM 1:2)
1st Class Mason

C-Data

0.1 Kgs
0.09 Ltr

0.15 Cu.m.
108 Kgs
0.33 Nos.
0.77 Nos.
0.5 Nos.
1.1 Nos.

1086.49
5.52
525.00
468.75
400.00
400.00

1 Cu.m.
1 Kgs
1 Each
1 Each
1 Each
1 Each

0.21 Cu.m.
151.2 Kgs
0.66 Nos.

1086.49
5.52
525.00

1 Cu.m.
1 Kgs
1 Each

77 of 209

2.20
2.20
22.58
21.60
0.00
303.68
303.68
41.35
345.05

m dia including Labour Charges for fixing complete including cost


site, sales and other taxes, all labour charges etc., complete for
311.10
107.10
418.20
56.94
475.15

ts of Plastic Emulsion paint of superior quality of approved brand


nt primer grade -I making three coats in all to give an even
e surface to remove all loose powdered materials, including cost
uding cost and conveyance of all materials, cost of brushes, water
all operational, incidental and labour charges such as scaffolding
mplete for finished item of work in all floors for Walls.(APSS No.
16.50
17.64
12.60
22.97
21.60
39.38
130.68
17.79
148.50

.00Mx1.20Mts including border with plastering in CM (1:2) 12mm


op coat with cement green oxide powder in (1:1) prop. and making
he chalk board over existing plastered surface and painting the
rd paint as per direction of Engineer-in-Charge including cost and
nd other taxes on cost of materials and all operational, incidental
r finished item of work (APSS No.1603)
162.97
596.16
173.25
360.94
200
440
1933.32
228.16
834.62
346.5

C-Data

78 of 209

2nd Class Mason


Man mazdoor
Woman mazdoor
Basic rate per 10 Sqmt.
Top Coat in CM(1:1)
Cost of Cement
Cost of Black Oxide
1st Class Mason
2nd Class Mason
Man mazdoor
Woman mazdoor

51

1.54 Nos.
0.5 Nos.
3.2 Nos.

468.75
400.00
400.00

1 Each
1 Each
1 Each

3.15 Kgs
15 Kgs
0.33 Nos.
0.77 Nos.
0.5 Nos.
1.1 Nos.

5.52
88
525.00
468.75
400.00
400.00

1 Kgs
1 Kgs
1 Each
1 Each
1 Each
1 Each

DATA FOR GREEN BOARD


Cost of Base Coat in CM (1:2)
Cost of Top Coat
20mm thick Plastering in CM (1:2)
Cost of chalk Board paint

4.03 Sqmts.
3.6 Sqmts.
0.43 Sqmts.
4.03 Sqmts.

Rate per Each Board


rate per sqmt
Add 14% over heads

0.14

1933.32
2511.58
3611.16
384.4

10 Sqmts.
10 Sqmts.
10 Sqmts.
10 Sqmts.
Total
Say

553.75
rate per sqmt

Proviging plinth protection with a bed of 100mm thick PCC (1:5:10) using 40mm size HBG metal
on top of PCC, 20 mm thick granolithic concrete flooring with CC (1:1:2) prop; machine crushed m
of size 6mm to 12 mm laid monolithically already laid in alternate panels and finishing the top sur
to required smoothness and slopes inculing grooves, thread lining as cost and coveyance o
materials to site including , sales & other taxes and all materials and operatinal & incidental and la
charges like mixing of cement concrete, laying ,curing lift charges etc., complete including o
bedfor finished item of work (APSS No.701 & 710)
6MM To 12MM HBG metal
Sand
cement
PCC BED (1:5:10) 100mm thick
1 st class Mason
2 nd class mason
Man mazdoor
women mazdoor
Rate per 10 sqm
Rate per 1 sqm
Add 14% over heads

0.17 Cum
0.085 Cum
120 Kgs
1.0 Cum
1.25 Nos
0.06 Nos
2.5 Nos
0.5 Nos

1022.42 1 cum
1019.49 1 cum
5522.8125 1000 kgs
3102.06 1 cum
525.00 each
468.75 each
400.00 each
400.00 each

0.14
Rate per 1 sqm

52

C-Data

Construction of Rain water harvesting structure as per the approved drawing and design of size 2.
x 1.5 m x 2.0 m including earth work excavation of filling of 40 mm size HBG metal up to 50%
volume, filling of 20 mm size 15% of colume. construction of side walls in brickmasonry in CM (
230 mm thick and 450 mm height, plastering the side walls in (1:6) 16 mm thick base coat and
coat of 4 mm thick with dubara sponge tinish, providing coir mat to avoid spillage of water inclu
cost and conveyance of all materials to site and all albour charges etc., complete for finished ite
work.
Earth work excavation 375.00 each
6 Cum
145.60
1 Cum
2.0 x 1.50 x 2.00 = 6.00 Cum
Cost of 40 mm
3 Cum
945.09
1 Cum
2.00 x 1.50 x 1.00 = 3.00 Cum
Cost of 20 mm
1.2 Cum
1465.09
1 Cum
2.00 x 1.50 x 0.40 = 1.20 cum
Cost of sand filings
0.9 Cum
483.65
1 Cum
2.00 x 1.50 x 0.30 = 0.90 cum
B.W CM (1:6) Prop
0.63 Cum
4691.90
1 Cum
6.08 x 0.23 x 0.45 = 0.60 cum
Plastring 20 mm in two coats
1.61 sqm
322.42
1 sqm

79 of 209

721.88
200
1280
3611.16
17.39
1320
173.25
360.94
200
440
2511.58
779.13
904.17
155.28
154.91
1993.49
1993.5
553.75
75.39
629.15

ed of 100mm thick PCC (1:5:10) using 40mm size HBG metal and
hic concrete flooring with CC (1:1:2) prop; machine crushed metal
ically already laid in alternate panels and finishing the top surface
s inculing grooves, thread lining as cost and coveyance of all
other taxes and all materials and operatinal & incidental and labour
crete, laying ,curing lift charges etc., complete including of CC
o.701 & 710)
173.81
86.66
662.74
3102.06
656.25
28.13
1000
200
5909.65
590.97
80.46
671.45

g structure as per the approved drawing and design of size 2.0 m


ork excavation of filling of 40 mm size HBG metal up to 50% of
of colume. construction of side walls in brickmasonry in CM (1:6)
plastering the side walls in (1:6) 16 mm thick base coat and top
nge tinish, providing coir mat to avoid spillage of water including
s to site and all albour charges etc., complete for finished item of
873.6
2835.27
1758.11
435.29
2955.9
519.09

C-Data

80 of 209

7.00 x 0.23 = 1.61 Sqm


Add 14% over heads
Each

0.14

53

Supplying , laying , aligning & jointing of RCC Hume Pipes of 300mm dia NP2 class includin
necessary fixtures like collars of respective diameter including cost and convenyance of all mate
to site, sales and othe taxes on all materials , lifting, placing and fixing in position for finished ite
work.
As per SSR Item No : (page 238)
10 Rmt
397.00
1 Rmt
Add collars (page 239)
3 Nos
99.00
1 Nos
Labour charges for laying & jointing
10 Rmt
432.00
1 Rmt
(Rs. 36 per 25mm dia).page 225
Rate per 10 Rmt.
Rate per 1 Rmt.
Add 14% over heads
0.14
Rate per 1 Rmt.

54

Flooringwith 16 to 18mm thick high polished granite stone slabs of black colour approved by
engineer-incharge laid over RCC slab or bed alredy laid and set over base coat of CM (1:8) 20
thick including neat cement , slurry of honey like consistency spread at the rate of 3.30kg per
and joined with neat white cement paste mixed with pisment of matching shade to ful allmateria
work site depth including cost and conveyence of and all materials to work site and operatio
incidentallabour and lift charges etc., complete for finshed item of work for platform in kitchen/din
(SS 701 & special)
Materials
High polished granite 16 to 18mm
10.50 Sqm
2352 1 sqm
Sqm
corese sand for C.M. 1:8
0.20 Cum
1019.49 1 cum
Cum
Cement for CM1: 8 base coat
36.00 Kgs
5522.81 1000 kgs Kgs
Cement for slurry
33.00 Kgs
5522.81 1000 kgs Kgs
Cement for joining
6.00 Kgs
5522.81 1000 kgs Kgs
Labour
1 st class mason
3.00 Nos
525.00 each
Nos
2nd class mason
1.00 Nos
468.75 each
Nos
Man Mazdoor
8.00 Nos
400.00 each
Nos
Rete per 1 sqm
Add 14% over heads
Rete per 1 sqm

0.14

55

Half Rounding the edges of granite slab including polishing all labour charges, hire charegs of tools
plants All incidental charges etc., complete for finished item of work as directed by the engi
incharge
As per SSR BMM-V.10
1 RMT
289.00
1 RMT
Add 14% over heads
0.14
Rate per RM
total

56

Manufacture, supply, & delivery of 50mm outer dia HDPE pipes conforming to IS 4984 - 1995
6Kg/Sqcm. including cost and conveyance of all materials to site, all labour charges, sales and o
taxes on all materials etc., complete for finished item of work for All Floors.
Intial Cost
Add for Excise Duty at 10%
Add 14% over heads

1 RMT
10%
Total
0.14

67.00
67.00

1 RMT

Total rate per Rmt.


57

Laying jointing of HDPE pipes as per BIS No. 7634 part -II/75 and specials /fittings including excava
of trenches up to 0.5 mts depth in all soils except rock requires blasting and refilling trenches
laying and jointing of pipes as per ssr item no.12 (b) complete for finished item of work
Intial Cost
Add 14% over heads

C-Data

1 RMT
0.14

81 of 209

31.00

1 RMT

9377.26
1276.71
10654.00

nting of RCC Hume Pipes of 300mm dia NP2 class including all
pective diameter including cost and convenyance of all materilas
materials , lifting, placing and fixing in position for finished item of
3970.00
297.00
4320.00
8587.00
858.70
116.91
975.65

h polished granite stone slabs of black colour approved by the


b or bed alredy laid and set over base coat of CM (1:8) 20mm
of honey like consistency spread at the rate of 3.30kg per sqm
paste mixed with pisment of matching shade to ful allmaterials to
conveyence of and all materials to work site and operational ,
c., complete for finshed item of work for platform in kitchen/diniing
24696.00
203.90
198.82
182.25
33.14
1575.00
468.75
3200.00
30557.86
3055.79
416.05
3471.85

lab including polishing all labour charges, hire charegs of tools and
complete for finished item of work as directed by the engineer
289.00
39.35
328.35

50mm outer dia HDPE pipes conforming to IS 4984 - 1995 at


eyance of all materials to site, all labour charges, sales and other
for finished item of work for All Floors.
67.00
6.70
73.70
10.03
83.75

BIS No. 7634 part -II/75 and specials /fittings including excavation
all soils except rock requires blasting and refilling trenches after
r item no.12 (b) complete for finished item of work
31.00
4.22

C-Data

82 of 209

total rate per Rmt.


58

Drilling of 25 mm dia holes in hard rock by Pneumatic compressure including hire charges of too
plants etc complete for finished item of work.
1 Rmt
0.14

R&B SSR 2013-14 Sl. No.143(7b-II)


Add 14% over heads

293.00
293.00

1 Rmt

Rate per 1 Rmt


59

Pressure Grouting the drilled holes with neat cement slurry including cost and conveyencee o
materials and labour charges for finished item of work
1 Rmt
0.14

R&B SSR 2013-14Sl. No.146(8b-II)


Add 14% over heads
Rate per 1 Rmt
60

Add 14% over heads


Rate per 10 sqm
Rate per 1 sqm

C-Data

1 Rmt

Painting to new walls with 2 coats of Acrylic based Oil bound Washable Distemper having VOC con
less than 50 grams/litre over promer coat using white cemnt as approved by Engineer-In-Cha
making 3 coats in all to give an even shade after thourughly brushing the surface to remove all
and remains of loose powdered materials, including cost and conveyance of all materials to work
and all operational, incidental, labour charges etc., and overheads & contractors profit complete
finished item of work as per APSS 911 for internal walls in all floors.
(BLD-CSTN-12-1)
Unit = 10 Sqm
Cost of White Cement
Painter 1st class
Painter 2nd class
Cost of washable Oil Bound Distemper
Painter 1st class
Painter 2nd class
Sundries including brushes , ladders
etc., @ 1%

61

111.00
111.00

0.50 Kg
0.08 Nos.
0.19 Nos.
1.70 Ltrs
0.36 Nos.
0.84 Nos.
0.01

29.00
600.00
468.75
90.00
600.00
468.75
914.31

0.14

923.45

1 Kg
1 Each
1 Each
1 Ltr
1 Each
1 Each

Earth work excavation for foundations for buildings in hard rock (requiring blasting)
depositing on bank for all lifts and with an initial lead of 10m and up to 3m depth includin
operational,incidental, labour charges such as shoring, sheeting, planking, strutting etc.,
overheads & contractors profit complete for finished item of work excluding dewatering charges
as per SS 20 B(APSS 308)
(BLKD-CSTN-2-6)
Hard rock (requiring blasting)- up to 3m depth
Unit : 1 cum
Taking output :
10.00 cum
a) Labour
Driller
0.50 Nos.
525.00
1 No.
Blaster
0.25 Nos.
600.00
1 No.
Mazdoor ( Unskilled)
8.35 Nos.
400.00
1 No.
b) Machinery
1.00 hour
946.70
1 Hour
Air compressor 7cmm (diesel)
2.00 hours
19.80
1 Hour
Jack hammer/Pneumatic braker
Crew charges
1.00 Hours
198.40
1 Hour
Air compressor
2.00 Hours
310.10
1 Hour
Jack hammer/Pneumatic braker
Add MA on crew charges
0.00
818.60
c)Material
3.50 Kgs
73.00
1 Kg
Gelatin 80%
Detonator electric
14 Nos.
13.00
1 No.

83 of 209

35.25
rock by Pneumatic compressure including hire charges of tools &
of work.
293.00
39.89
332.89
332.90

with neat cement slurry including cost and conveyencee of all


shed item of work
111.00
15.11
126.11

f Acrylic based Oil bound Washable Distemper having VOC content


mer coat using white cemnt as approved by Engineer-In-Charge,
en shade after thourughly brushing the surface to remove all dirt
erials, including cost and conveyance of all materials to work site
ur charges etc., and overheads & contractors profit complete for
1 for internal walls in all floors.

14.5
48
89.06
153
216
393.75
9.14
923.45
125.73
1049.18
104.92

dations for buildings in hard rock (requiring blasting) and


with an initial lead of 10m and up to 3m depth including all
ges such as shoring, sheeting, planking, strutting etc., and
plete for finished item of work excluding dewatering charges etc.,

262.50
150.00
3340.00
946.70
39.60
198.40
620.20
0.00
255.50
182.00

C-Data

84 of 209

c&d)
Add 14% over heads
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum
62

0.14

5994.90

Earth work excavation for foundations for buildings in hard rock by benching and chisil
blasting Prohibited) and depositing on bank for all lifts and with an initial lead of 10m and u
3m depth including all operational,incidental, labour charges such as shoring, sheeting, plank
strutting etc., and overheads & contractors profit complete for finished item of work exclu
dewatering charges etc., as per SS 20 B(APSS 308)
(BLKD-CSTN-2-7)
Hard rock (blasting prohibited)- up to 3m depth
Unit : 1 cum
Taking output :
10.00 cum
a) Labour
Mazdoor ( Unskilled)
5.20 Nos.
b) Machinery
6.00 hour
Air compressor 7cmm (diesel)
12.00 hours
Jack hammer/Pneumatic braker
Crew charges
6.00 Hours
Air compressor
12.00
Hours
Jack hammer/Pneumatic braker
Add MA on crew charges
0.00
Add 14% over heads
Cost for 10 cum ( a+b+c+d)
Rate per 1 cum (a+b+c+d) / 10
Rate per 1 cum

63

1008.60
19.80

1 Hour
1 Hour

182.20
284.70
751.60

1 Hour
1 Hour

12878.80

Say

0.14

73.06

Roofing with Prepainted Galvalume profile roofing Sheet of 0.5mm thick Century wall or equiva
make fixed with G.I J bolts & nuts 8 mm dia with bitumen & G.I limpet washers filled with white le
including a coat of approved steel primer and two coats of approved paint on over lapping of sh
complete (upto a pitch of 600) and seigniorage charges, turnover tax etc., complete, excluding
cost of purlins, rafters, trusses & cost of conveyance of all materials for all floors
Basic rate ( BMS-W.45)
Add 14% over heads

,Executive Engineer
APEWIDC,
ANANTAPURAMU

C-Data

1 No.

Supply and fixing of M.S. Grills including cost and conveyance of all materials and all labour cha
etc.,
Rate complete
as per Circular
1 Kg
45.06
1 Kg
Fabrication charges (SSR.No.824)
1 Kg
24.00
1 Kg
Fixing charges (SSR No.825)
1 Kg
4.00
1 Kg
Add 14% over heads
Rate per 1 Kgs

64

0.14

400.00

0.14

,Dy.Executive Engineer
APEWIDC, ANANTAPURAMU

85 of 209

1 sqm
799.00

,Assistant Engineer
APEWIDC, TADIPATRI

5994.90
816.21
6811.11
681.11
681.10

ations for buildings in hard rock by benching and chisiling(


ng on bank for all lifts and with an initial lead of 10m and up to
al,incidental, labour charges such as shoring, sheeting, planking,
ontractors profit complete for finished item of work excluding
0 B(APSS 308)

2080.00
6051.60
237.60
1093.20
3416.40
0.00
12878.80
1753.45
14632.25
1463.23
1463.20

uding cost and conveyance of all materials and all labour charges
45.06
24.00
4.00
73.06
9.95
83.01

profile roofing Sheet of 0.5mm thick Century wall or equivalent


mm dia with bitumen & G.I limpet washers filled with white lead &
primer and two coats of approved paint on over lapping of sheets
seigniorage charges, turnover tax etc., complete, excluding the
t of conveyance of all materials for all floors
799.00
108.78
907.78

,Assistant Engineer
APEWIDC, TADIPATRI

C-Data

86 of 209

Standard Data - Electrical Items SSR 2015-16


3

Name of work :Construction of School building under R&R Centre to MPUPS In Various
1
components at Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu (Dist)
1

Inde Specific
Description
Unit Quanti Rate Rs. Amount Rs. 0Remar
- ks
x
ation
ty
2
-cod
No.
0
e
1
2
3
4
5
60 7
1.4.2
Supply and Fixing of 25mm dia 2.20 mm thick PVC pipe (ISI MARK) concealed in 6
Roof Slabs with all required accessories including masonary work and labour
(C)
charges etc., complete. Make : Sudhakar/ Maco Plast / Modi
Taking Output = 100 M
a) Material
elec-1.2.4 25mm dia 2.20 mm thick PVC pipe
100 M
ele-1.2.39 25mm dia 1,2,3 & 4 way deep Junction
Each
elec-1.2.44 Box
25mm PVC bends
Each
Add contr profit @14% on material
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 100 RM
Rate per Metre = C/100

1.00
12.00
12.00

3200.00
25.00
6.00

3200.00
300.00
72.00
3572.00
0.00
3572.00

2.00
2.00
2.00

480.00
375.00
375.00

960.00
750.00
750.00
0.00
0.00
6032.00
60.35

0.00

day
day
day
0%
0%

2460.00

Note : 1. If 25mm dia PVC / MS pipes are used


for light / fan point, add the cost of sheet metal /
1.4.2
(b)

Supply and Fixing of 25mm dia 1.80 mm thick P.V.C. pipe (ISI MARK) concealed in
wall with all required accessories including masonary work for light, fan and
separate plug point with well seasoned TW box including all labour charges etc.,
complete. Make : Sudhakar/ Maco Plast / Modi

Taking Output = 100 M


a) Material
elec-1.2.3 25mm dia 1.8mm thick PVC pipe
elec-8.1.7 U' Nails

100 M
100
Nos
elec-1.3.5 8"x10" Hot dip Galvanized Metal Boxes
Each
ele-1.2.39 25mm dia 1,2,3 & 4 way deep Junction
Each
elec-1.2.44 Box
25mm PVC bends
Each
elec-8.1.50 Cement
kg
Add contr profit @14% on material
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
elec-8.1.76 Mason Ist class
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 100 RM
Rate per Metre = C/100

87

1.00
2.00

2800.00
44.00

2800.00
88.00

2.00
12.00
12.00
50.00

179.00
25.00
6.00
7.00

358.00
300.00
72.00
350.00
3968.00
0.00
3968.00

2.00
2.00
2.00
2.00

480.00
375.00
375.00
420.00

960.00
750.00
750.00
840.00
0.00
0.00
7268.00
72.70

0.00

day
day
day
day
0%
0%

3300.00

2.1.1

Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant Low Smoke (FRLS) The
P.V.C. insulated flexible copper cable (ISI MARK) in existing pipe with 6A switch, R&B
Ceiling rose and 3mm thick hylam sheet covering to switch control box including Depart
all labour charges etc., complete for light, bell, fan and exhaust fan points in Non- ment
Residential Buildings
Propos
Makes of Wires : Finolex / R.R.Cable ,Makes of Switches : Anchor Penta ed
Cherry / Gold Madel Olive / Million Zoom / Great white omega
Labour,
for
Taking Output = 6 Points
Million
both
/piping
RPG/
a) Material
parag
elec-1.5.1 14/0.3mm (1.00 Sqmm)
FRLS PVC 100 M
1.00
1051.00
1051.00 &
on
wiring
insulated flexible copper wire
consid
elec-1.7.1 6A Switch @18/- each
each
6.00
18.00
108.00
ering
elec-1.7.13 6A 3 way Ceiling Rose@21/-each
each
6.00
21.00
126.00 40%
elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm Sq.in 100.00
0.61
61.00 Labour,
thick
1346.00 for
Add contr profit @14% on material
0.00
0.00 Wire
Total material cost
1346.00 draw.
Keepin
b) Labour charges :
g this,
elec-8.1.74 Skilled Electrician
day
0.60
480.00
288.00
the
elec-8.1.75 Semi skilled Electrician
day
1.20
375.00
450.00 labour
elec-8.1.81 Helpers
day
0.60
375.00
225.00 is
Add area allowence on labour
0%
0.00 propos
charges
Add contr@
profit @14% on Labour
0%
963.00
0.00 ed for
C) Cost for 6 Points
2309.00 wiring
100
Rate per Point = C/6
384.85
RM.
2.1.1 (1) Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant Low Smoke (FRLS)
P.V.C. insulated flexible copper cable (ISI MARK) in existing pipe with 6A 2 Way
flush type switch, Ceiling rose and 3mm thick hylam sheet covering to switch
control box including all labour charges etc., complete for Stair case and 2 way
light / fan points in Non-Residential Buildings
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton , Makes of Switches :
Anchor Penta Cherry / Gold Madel Olive / Million Zoom
Rate as per light point in Non Residental Building =384.85
For stair case
1.00
1.50
384.85
577.30
2.1.2

Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) P.V.C. insulated F.R.L.S. flexible
copper cable (ISI MARK) in existing pipe with 6A switch, Ceiling rose and 3mm
thick hylam sheet covering to switch control box including all labour charges etc.,
complete for light, bell, fan and exhaust fan points in Residential Buildings. Makes
of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon / HPL / L&T /
Power flex / RPG / Anchor / Bonton
Make of Switches : Anchor Penta
Cherry / Gold Madel Olive / Million Zoom

Taking Output = 7 Points


a) Material
elec-1.5.8 14/0.3mm (1.00 Sqmm)
FRLS PVC 100 M
insulated flexible copper wire
elec-1.7.1 6A Switch @18/- each
each
elec-1.7.13 6A 3 way Ceiling Rose@21/-each
each
elec.8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm
each
thick
Add contr profit @14% on material
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician

1.00

924.00

924.00

7.00
7.00
80.00

18.00
21.00
0.60

126.00
147.00
48.00
1245.00
0.00
1245.00

0.70

480.00

336.00

0.00

day

88

elec-8.1.75 Semi skilled Electrician


elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 6 Points
Rate per Point = C/7

day
day
0%
0%

1.40
0.70

375.00
375.00
1123.50

525.00
262.50
0.00
0.00
2368.50
338.40

2.1.1 (1) Wiring with 2 runs of 14/0.3mm (1.0 Sq.mm) Fire Retardant Low Smoke (FRLS)
P.V.C. insulated flexible copper cable (ISI MARK) in existing pipe with 6A 2 way
flush type switch, Ceiling rose and 3mm thick hylam sheet covering to switch
control box including all labour charges etc., complete for Stair case and 2 way
light/ fan points in Residential Buildings
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton ,Makes of Switches :
Anchor Penta Cherry / Gold Madel Olive / Million Zoom
Rate as per light point in Non Residental Building =338.4
For stair case
1.0
1.50
338.40
507.60
3.1.1

Supply and run of 2 of 14 /0.3mm (1.0 Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth continuity including all labour charges etc.,
complete.
Makes of Wires :
Polycab / Havells / SunCab / Fortune Art / Paragon / HPL / L&T / Power
flex / RPG / Anchor / Bonton

Taking Output = 100 M


a) Material
elec-1.5.8 14/0.3 mm(1.00 sq.mm) FRLS Copper
wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

100

2.00

924.00

1848.00
1848.00
0.00
1848.00

0.67
2.00
0.67

480.00
375.00
375.00

321.60
750.00
251.25
0.00
0.00
3170.85
31.75

0.00

day
day
day
0%
0%

1322.85

3.1.2

Supply and run of 1 of 14 /0.3mm (1.0 Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth continuity including all labour charges etc.,
complete.
Makes of Wires :
Polycab / Havells / SunCab / Fortune Art / Paragon / HPL / L&T / Power
flex / RPG / Anchor / Bonton
Taking Output = 100 M
a) Material
elec-1.5.8 14/0.3 mm (1.00 sq.mm) FRLS Copper
100
1.00
924.00
924.00
wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour

89

0.00

day
day
day
0%
0%

0.00
924.00
0.34
1.00
0.34

480.00
375.00
375.00
665.70

163.20
375.00
127.50
0.00
0.00

Cost per 100 Rmt


Rate per Meter= C/100

1589.70
15.90

3.1.3

Supply and run of 2 of 2 /0.3mm (1.50 Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for phase and neutral including all labour charges
etc., complete.
Makes of Wires :
Polycab / Havells / SunCab / Fortune Art / Paragon / HPL / L&T / Power
flex / RPG / Anchor / Bonton
Taking Output = 100 M
a) Material
elec-1.5.9 22/0.3 mm (1.50 sq.mm) FRLS Copper
100
2.0
1358.00
2716.00
wire
2716.00
Add contr profit @14% on material
0.00
0.00
Total material cost
2716.00
Labour Charges
elec-8.1.74 Skilled Electrician
day
0.67
480.00
321.60
elec-8.1.75 Semi skilled Electrician
day
2.00
375.00
750.00
elec-8.1.82 Helpers
day
0.67
375.00
251.25
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
1322.85
0.00
Cost per 100 Rmt
4038.85
Rate per Meter= C/100
40.40
3.1.3(1) Supply and run of 1 of 22 /0.3mm (1.50 Sq.mm) FRLS P.V.C. insulated flexible
copper cable in existing pipe for earth continuity including all labour charges etc.,
complete.
Makes of Wires : Polycab /
Havells / SunCab / Fortune Art / Paragon / HPL / L&T / Power flex / RPG /
Anchor / Bonton
Taking Output = 100 M
a) Material
elec-1.5.9 22/0.3 mm (1.50 sq.mm) FRLS Copper
wire

100

1.0

1358.00

1358.00
1358.00
0.00
1358.00

Add contr profit @14% on material


0.00
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
day
0.34
480.00
163.20
elec-8.1.75 Semi skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
0.34
375.00
127.50
Add area allowence on labour
0%
0.00
charges
@
Add contr profit @14% on Labour
0%
665.70
0.00
Cost per 100 Rmt
2023.70
Rate per Meter= C/100
20.25
3.1.4
Supply and run of 2 of 36/0.3 mm ( 2.5 sq.mm) FRLS / HFFR PVC insulated 1100 V
grade as per IS: 694 / 1990 specifications for flexible copper cable and one run of
14/0.3mm (1.0 sq.mm) flexible copper wire for earthing in existing PVC conduit
pipe for circuit mains including labour charges (phase neutral and earth) etc.,
complete as required for switch board circuit mains.
Makes of Wires : Finolex / RR Cabel
elec-1.5.3 36/0.3mm (2.5 sq.mm ) FRLS copper wire 100 M
2.00
2510.00
5020.00
elec-1.5.1 1 run of 1.00 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges

0.00

90

1.00

1051.00

1051.00

6071.00
0.00
6071.00

elec-8.1.74 Skilled Electrician


elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

day
day
day
0%
0%

1.01
3.00
1.01

480.00
375.00
375.00
1988.55

484.80
1125.00
378.75
0.00
0.00
8059.55
80.60

3.1.4 (a) Supply and run of 1 of 36/0.3 mm ( 2.50 sq.mm) FRLS PVC insulated flexible
copper cable in existing conduit pipe for circuit mains including labour charges (for
earth) etc., complete as required for switch board circuit mains.
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton
elec-1.5.10 36/0.3mm (2.5 sq.mm ) FRLS copper wire

100 M

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

0.00

day
day
day
0%
0%

1.00

2510.00

2510.00
2510.00
0.00
2510.00

0.34
1
0.34

480.00
375.00
375.00

163.20
375.00
127.50
0.00
0.00
3175.70
31.80

665.70

3.1.5

Supply and run of 2 of 56/0.3 mm ( 4 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (for phase
and neutral ) etc., complete as required for switch board circuit mains. Makes of
Wires : Finolex / RR Cabel
elec-1.5.4 56/0.3mm ( 4 sq.mm ) FRLS copper wire
100 M
2.00
3833.00
7666.00
elec-1.5.3 1 run of 2.50 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

1.00

2510.00

10176.00
0.00
10176.00

0.00

day
day
day
0%
0%

2510.00

1.34
4.00
1.34

480.00
375.00
375.00
2645.70

643.20
1500.00
502.50
0.00
0.00
12821.70
128.25

3.1.5 (1) Supply and run of 1 of 56/0.3 mm ( 4 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (for earth)
etc., complete as required for switch board circuit mains.
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton
elec-1.5.11 56/0.3mm ( 4 sq.mm ) FRLS copper wire
Add contr profit @14% on material

100 M
0.00

91

1.00

3833.00

3833.00
3833.00
0.00

Total material cost


Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

3833.00
day
day
day
0%
0%

0.50
1.50
0.50

480.00
375.00
375.00
990.00

240.00
562.50
187.50
0.00
0.00
4823.00
48.25

3.1.6

Supply and run of 2 of 84/0.3 mm ( 6 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (phase
and neutral ) etc., complete as required for switch board circuit mains. Makes of
Wires : Finolex / RR Cabel
elec-1.5.5 84/0.3mm ( 6 sq.mm ) FRLS copper wire
100 M
2.00
5828.00
11656.00
elec-1.5.3 1 run of 2.50 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

1.00

2510.00

14166.00
0.00
14166.00

0.00

day
day
day
0%
0%

2510.00

1.34
4.00
1.34

480.00
375.00
375.00
2645.70

643.20
1500.00
502.50
0.00
0.00
16811.70
168.15

3.1.6 (1) Supply and run of 4 of 84/0.3 mm ( 6 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (for earth)
etc., complete as required for switch board circuit mains. Makes of Wires :
Finolex / RR Cabel
4.00
5828.00
elec-1.5.5 84/0.3mm ( 6 sq.mm ) FRLS copper wire
100 M
23312.00
elec-1.5.3 1 run of 2.50 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

1.00

2510.00

25822.00
0.00
25822.00

0.00

day
day
day
0%
0%

2510.00

2.34
7.00
2.34

480.00
375.00
375.00
4625.70

1123.20
2625.00
877.50
0.00
0.00
30447.70
304.48

3.1.7

Supply and run of 2 of 140/0.3 mm ( 10 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (phase
and neutral ) etc., complete as required for switch board circuit mains. Makes of
Wires : Finolex / RR-Cable
elec-1.5.6 140/0.3mm ( 10 sq.mm ) FRLS copper
100 M
2.00
9030.00
18060.00
wire
18060.00
Add contr profit @14% on material
Total material cost

0.00

92

0.00
18060.00

Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

day
day
day
0%
0%

1.00
3.00
1.00

480.00
375.00
375.00
1980.00

480.00
1125.00
375.00
0.00
0.00
20040.00
200.40

3.1.7 (1) Supply and run of 1 of 140/0.3 mm ( 10 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (for earth)
etc., complete as required for switch board circuit mains. Makes of Wires :
Finolex / RR Cable
elec-1.5.6 140/0.3mm ( 10 sq.mm ) FRLS copper
100 M
1.00
9030.00
9030.00
wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100
3.1.8

9030.00
0.00
9030.00

0.00

day
day
day
0%
0%

0.50
1.50
0.50

480.00
375.00
375.00
990.00

240.00
562.50
187.50
0.00
0.00
10020.00
100.20

Supply and run of 2 of 126/0.4 mm ( 16 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (phase
and neutral ) etc., complete as required for switch board circuit mains.
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton

elec-1.5.14 126/0.4mm ( 16 sq.mm ) FRLS copper


wire
Add contr profit @14% on material
Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

100 M

2.00 13230.00

0.00

day
day
day
0%
0%

1.00
3.00
1.00

480.00
375.00
375.00
1980.00

26460.00
26460.00
0.00
26460.00
480.00
1125.00
375.00
0.00
0.00
28440.00
284.40

3.1.8 (1) Supply and run of 1 of 126/0.4 mm ( 16 sq.mm) FRLS PVC insulated flexible copper
cable in existing conduit pipe for circuit mains including labour charges (for earth)
etc., complete as required for switch board circuit mains.
Makes of Wires : Polycab / Havells / SunCab / Fortune Art / Paragon /
HPL / L&T / Power flex / RPG / Anchor / Bonton
elec-1.5.14 126/0.4mm ( 16 sq.mm ) FRLS copper
wire

93

100 M

1.00 13230.00

13230.00
13230.00

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

0.00

day
day
day
0%
0%

0.00
13230.00
0.50
1.50
0.50

480.00
375.00
375.00
990.00

240.00
562.50
187.50
0.00
0.00
14220.00

3.1.4 ( 1) Supply and run of 2 of 2.5 sq.mm FRLS PVC insulated flexible copper cable and one
run of 1.0 sq.mm flexible copper wire for earthing in existing PVC/ MS conduit pipe
for circuit mains including labour charges (phase neutral and earth) etc., complete
as required for switch board circuit mains. Makes of Wires : Finolex / RR Cable
elec-1.5.3 2 run of 2.5 sq.mm wire
elec-1.5.1 1 run of 1 sq.mm wire

1
1

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (0.67 + 0.34)
elec-8.1.75 Semi skilled Electrician (2 + 1)
elec-8.1.81 Helpers (0.67 + 0.34)
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

2.00
1.00

2510.00
1051.00

5020.00
1051.00
6071.00
0.00
6071.00

1.005
3.000
1.005

480.00
375.00
375.00

482.40
1125.00
376.88
0.00
0.00
8055.28
80.60

0.00

day
day
day
0%
0%

1984.28

3.1.5 (2) Supply and run of 2 of 4 sq.mm FRLS PVC insulated flexible copper cable and one
run of 2.5 sq.mm flexible copper wire for earthing in existing PVC/ MS conduit pipe
for circuit mains including labour charges (phase neutral and earth) etc., complete
as required for switch board circuit mains. Makes of Wires : Finolex / RR Cable
elec-1.5.14 2 run of 4.0 sq.mm wire
elec-1.5.3 1 run of 2.50 sq.mm wire

1
1

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (1.0 + 0.34)
elec-8.1.75 Semi skilled Electrician (3 + 1)
elec-8.1.81 Helpers (1.0 + 0.34)
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

2.00
1.00

3833.00
2510.00

1.34
4.00
1.34

.
480.00
375.00
375.00

0.00

day
day
day
0%
0%

2645.70

7666.00
2510.00
10176.00
0.00
10176.00
643.20
1500.00
502.50
0.00
0.00
12821.70
128.25

3.1.6 (2) Supply & run of 2 of 6.0 Sqmm(84/0.3mm) PVC insulated flexible copper cable and
one run of 2.5 Sqmm flexible PVC insulated copper cable for earthing in the
existing conduit pipe for AC points & SDB's etc as required. Makes of Wires
:Finolex / RR Cable
elec-1.5.5 2 run of 6.0 sq.mm wire
1
2.00
5828.00
11656.00

94

elec-1.5.3 1 run of 2.50 sq.mm wire

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (1.0 + 0.34)
elec-8.1.75 Semi skilled Electrician (3 + 1)
elec-8.1.81 Helpers (1.0 + 0.34)
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100

1.00

2510.00

2510.00
14166.00
0.00
14166.00

1.34
4.00
1.34

480.00
375.00
375.00

643.20
1500.00
502.50
0.00
0.00
16811.70
168.15

0.00

day
day
day
0%
0%

2645.70

3.1.6 (3) Supply and run of 4 of 6 Sq mm PVC insulated flexible copper cable and 1 run of
2.5 Sq mm flexible PVC insulated flexible copper cable in the existing conduit pipe
for run of mains from main panel board to TPN DB'S with pin type lugs and
connections etc.,complete for Lighting Distribution boards.
Makes of Wires : Finolex / RR Cable
elec-1.5.5 4 run of 6.0 sq.mm wire
elec-1.5.3 1 run of 2.50 sq.mm wire

1
1

Add contr profit @14% on material


Total material cost
Labour Charges
elec-8.1.74 Skilled Electrician (2.0 + 0.34)
elec-8.1.75 Semi skilled Electrician (6 + 1)
elec-8.1.81 Helpers (2.0 + 0.34)
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Cost per 100 Rmt
Rate per Meter= C/100
19

4.00
1.00

5828.00
2510.00

23312.00
2510.00
25822.00
0.00
25822.00

2.50
7.50
2.50

480.00
375.00
375.00

1200.00
2812.50
937.50
0.00
0.00
30772.00
307.75

0.00

day
day
day
0%
0%

4950.00

Supply and run of 4 of 10 Sq mm FRLS PVC insulated flexible copper cable with 1
No 4.00 Sq.mm PVC insulated flexible copper cable in the existing conduit pipe for
run of mains from main panel board to TPN DB'S with pin type lugs and
connections etc.,complete for PDB's and AC DBS. Makes of Wires :Finolex / RR
Cable
Taking Output = 100 M
a) Material
elec-1.5.6 126/0.4mm (10 Sq.mm) FRLS PVC flexible 100 M
4.00
9030.00
36120.00
copper cable
elec-1.5.4 56/0.3mm 4.00 sqmm) FRLS PVC copper 100 M
1.00
3383.00
3383.00
cable
39503.00
Add contr profit @14% on material
0.00
0.00
Total material cost
39503.00
b) Labour charges :
elec-8.1.74 Skilled Electrician (2.0 + 0.5)
day
2.00
480.00
960.00
elec-8.1.75 Semi skilled Electrician (6 + 1.5)
day
6.00
375.00
2250.00
elec-8.1.81 Helpers (2.0 + 0.5)
day
2.00
375.00
750.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
3960.00
0.00
Sundries
C) Cost for 100 RM
43463.00

95

Rate per Metre = C/100


Note : Labour Charges considered for 100 M / day

434.65

2.1.4

Supply and fixing of 6A 3/2 pin wall plug socket with 6A switch control on a
common switch board with earth continuity including wire leads, earth connections
along with all labour charges etc., complete. Makes : Anchor / Gold Medal Olive
/Million Zoom
Taking Output = each
a) Material
elec-1.7.4 6A 3 pin / 2 pin Socket
each
1.00
27.00
27.00
elec-1.7.1 6A 1 way flush type switch
each
1.00
18.00
18.00
45.00
Add contr profit @14% on material
0.00
0.00
Total material cost
45.00
b) Labour charges :
.
elec-8.1.74 Skilled Electrician
day 0.067
480.00
32.16
elec-8.1.81 Helpers
day 0.067
375.00
25.13
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
57.29
0.00
Rate per each
102.30
Note : Labour Charges proposed for 1point
considering 15 per day
2.1.4(a)

Supply and fixing of 3 Nos 6A 3 pin wall plug socket with 3 Nos. 6A switch control
on a common switch board with earth continuity including wire leads, earth
connections along with all labour charges etc., complete.
Makes : Anchor Penta Cherry / Gold Medal Olive / Million Zoom

Taking Output = each


a) Material
elec-1.7.4 6A 3 pin / 2 pin Socket
elec-1.7.1 6A 1 way flush type switch

each
each

3.00
3.00

27.00
18.00

81.00
54.00

elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm thick

Sq.in

100.00

0.61

61.00

196.00
0.00
196.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
.
elec-8.1.74 Skilled Electrician
day 0.201
480.00
96.48
elec-8.1.81 Helpers
day 0.201
375.00
75.38
Add area allowence on labour
0%
0.00
charges
@
Add contr profit @14% on Labour
0%
171.86
0.00
Rate per each
367.90
Note : Labour Charges proposed for 1point
considering
per14/0.3mm
day
2.1.3
Wiring with 15
2 of
(1.0 Sq.mm) P.V.C. insulated F.R.L.S flexible copper
cable (ISI MARK) in existing pipe with 6A switch control and 3/2 pin sockets fixing
on separate board including all labour charges etc., complete. Makes of Wires :
Finolex / RR Cable
Taking Output = 15 Points
a) Material
elec-1.5.1 14/0.3mm PVC FR flexible copper wire
100 M
1.00
1051.00
1051.00
elec-1.7.1 6Aswitches @18/- each
each 15.00
18.00
270.00
elec-1.7.4 6A 3 pin / 2 Pin Socket
each 15.00
27.00
405.00
1726.00
Add contr profit @14% on material
0.00
0.00
Total material cost
1726.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
1.50
480.00
720.00
elec-8.1.75 Semi skilled Electrician
day
1.50
375.00
562.50

96

elec-8.1.81 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
C) Cost for 15 Points
Rate per Points = C/15
12

day
0%
0%

1.50

375.00
1845.00

562.50
0.00
0.00
3571.00
238.10

Supply and Fixing of 16A 3pin and 6A 3pin plug socket with and 16A switch control
duly recessed in wall with MS switch deep box of 6" x8" x2 1/2" size covered with
hylam sheet including earth connections and all labour charges etc., complete.
Makes : Anchor Penta Cherry / Gold Medal /Million Zoom
Taking Output = each

a) Material
elec-1.3.4 6 Module Galvanized Metal Boxes Horizontal /
Verticle
elec-8.1.51 25 x 20 cms (10" x8") Hylam sheet 3mm thick
elec-1.7.10 16A 3 pin / 6A 3pin plug socket (2 in 1)
Elec1-7-8 16A flush type switch
Add contr profit @14% on material
Total material cost

each

1.00

137.00

137.00

Sq.in
each
each

50.00
1.00
1.00

0.61
102.00
65.00

30.50
102.00
65.00
334.50

0.00

0.00
334.50

b) Labour charges :
Skilled Electrician
elec-8.1.77 Semi Skilled Electrician
elec-8.1.81 Helpers

day
day
day

Add area allowence on labour


0%
charges
Add contr@
profit @14% on Labour
0%
Rate per each
Note : Labour Charges proposed for 10 jobs per
day
20

0.10
0.10
0.10

480.00
375.00
375.00
123.00

48.00
37.50
37.50
0.00
0.00
457.50

Supply and fixing Distribution board with 20A single phase plug and Socket, in
sheet steel enclosure with 10/16/20A SP MCB including internal connection and
labour charges for flush mounting etc., complete
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
a) Material
elec1 Phase Distribution board with 20A plug
Nos
1.00
590.00
590.00
2.12.67 and socket.
ele-2.9.9 10/16/20A SP MCB
Nos
1.00
162.00
162.00
752.00
Add contr profit @14% on material
0.00
0.00
Total material cost
752.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
Nos
0.25
480.00
120.00
elec-8.1.75 Semi skilled Electrician
Nos
0.25
375.00
93.75
elec-8.1.81 Helpers
Nos
0.25
375.00
93.75
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
307.50
0.00
Sundries such as Cement, Sand, T.W.
LS
130.00
Plugs, Screws etc.,
Rate per each
1189.50
Note : 1. Labour Charges considered for 4 jobs /
day
2. For concealing, add the following:
a
1No. Semi skilled mason
b
1/4 bag cement

97

21

Supply and fixing 4 Way TPN Distribution board with IP-43 protection (Metal Door)
suitable for 3 phase 40 A FP Isolator as incomer and 12 Nos 6-32 A 10kA SP MCBs
as outing goings including internal connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
A
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD)
each
1.00
2200.00
2200.00
2
suitable for 3 phase ELCB / RCCB / FP
Isolator as incommer.
elec40A, 4 Pole Isolator
each
1.00
678.00
678.00
2.10.14 10kA - 6-32A range SP MCBs
elec-2.9.9
each 12.00
162.00
1944.00
4822.00
Add contr profit @14% on material
0.00
0.00
Total material cost
4822.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.50
480.00
240.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
Add area allowence on labour
0%
0.00
charges
@
Add contr profit @14% on Labour
0%
990.00
0.00
Sundries such as TW Plugs, Screws
LS
15.00
15.00
Cement etc,
Rate per each
5827.00
Note : Labour Charges considered for 2 jobs / day
A

Supply and fixing 4 Way TPN Distribution board with IP-20 protection (Metal Door)
suitable for 3 phase 40 A FP Isolator as incomer and 12 Nos 6-32 A 10kA SP MCBs
as outing goings including internal connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
40A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.3 4way TPN, D.B with IP-20 Protection (MD)
each
1.00
2491.00
2491.00
9
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec40A, 4 Pole Isolator
each
1.00
890.00
890.00
2.10.14 10kA - 6-32A range SP MCBs
elec-2.9.9
each 12.00
201.00
2412.00
5793.00
Add contr profit @14% on material
0.00
0.00
Total material cost
5793.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.50
480.00
240.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
0%
0.00
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
0%
990.00
0.00
Sundries such as TW Plugs, Screws
LS
15.00
15.00
Cement etc,
Rate per each
6798.00
Note : Labour Charges considered for 2 jobs / day

98

Supply and fixing 4 Way TPN Distribution board with IP-43 protection (Metal Door)
suitable for 3 phase 63 A FP Isolator as incomer and 12 Nos 6-32 A 10kA SP MCBs
as outing goings including internal connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
63A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD)
each
1.00
2491.00
2491.00
2
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec63A, 4 Pole Isolator
each
1.00
890.00
890.00
2.10.15 10kA - 6-32A range SP MCBs
elec-2.9.9
each 12.00
201.00
2412.00
5793.00
Add contr profit @14% on material
0.00
0.00
Total material cost
5793.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.50
480.00
240.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
990.00
0.00
Sundries such as TW Plugs, Screws
LS
15.00
15.00
Cement etc,
Rate per each
6798.00
Note : Labour Charges considered for 2 jobs / day
Supply and fixing 4 Way TPN Distribution board with IP-43 protection (Metal Door)
suitable for 3 phase 80 A FP Isolator as incomer and 12 Nos 6-32 A 10kA SP MCBs
as outing goings including internal connection and labour charges for flush
mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B -2
80A FP Isolator - 1 No for incomer,
10kA-6-32A SP MCBs - 12Nos for
outgoing.
Taking Output = each
a) Material
elec.2.12.4 4way TPN, D.B with IP-43 Protection (MD)
each
1.00
2491.00
2491.00
2
suitable for 3 phase ELCB / RCCB/ FP
Isolator as incommer.
elec80A, 4 Pole Isolator
each
1.00
956.00
956.00
2.10.17
elec-2.9.9 10kA - 6-32A range SP MCBs
each 12.00
201.00
2412.00
5859.00
Add contr profit @14% on material
0.00
0.00
Total material cost
5859.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
1.00
480.00
480.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
1230.00
0.00
Sundries such as TW Plugs, Screws
LS
14.00
14.00
Cement etc,
Rate per each
7103.00
Note : Labour Charges considered for 2 jobs / day

99

22

Supply and fixing 8 way SPN Distribution board with IP-43 protection (Metal Door)
suitable for 1 No. 40A single phase DP Isolator as incomer and 6 Nos 6-32 A 10kA
SP MCBs as outing going including internal connection and labour charges for
surface / flush mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma

40A DP Isolator / RCCB / ELCB - 1 No


for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
elecSPN 8 way D.B with IP-43 Protection (MD)
2.12.11 suitable for single phase ECCB / RCCB/ DP
Isolator.
elec40A D.P.Isolator
2.10.10 10 kA - 6-32A range SP MCBs
elec-2.9.9

each

1.00

1245.00

1245.00

each
each

1.00
6.00

367.00
201.00

367.00
1206.00
2818.00
0.00
2818.00

0.50
0.50
1.00

480.00
375.00
375.00

240.00
187.50
375.00
0.00
0.00
9.50
3630.00

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as hardware, cement etc,
LS
Rate per each
Note : Labour Charges considered for 2 jobs / day

802.50
9.50

22

Supply and fixing 8 way SPN Distribution board with IP-20 protection (Metal Door)
suitable for 1 No. 40A single phase DP Isolator as incomer and 6 Nos 6-32 A 10kA
SP MCBs as outing going including internal connection and labour charges for
surface / flush mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B
40A DP Isolator / RCCB / ELCB - 1 No
for incomer, 6-32A SP MCBs - 6Nos
for outgoing.
Taking Output = each
a) Material
elec-2.12.8 SPN 8 way D.B with IP-20 Protection (MD)
each
1.00
606.00
606.00
suitable for single phase ECCB / RCCB/ DP
Isolator.
elec40A D.P.Isolator
2.10.10 10 kA - 6-32A range SP MCBs
elec-2.9.9

each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as hardware, cement etc,
LS
Rate per each
Note : Labour Charges considered for 2 jobs / day

100

1.00
6.00

367.00
201.00

367.00
1206.00
2179.00
0.00
2179.00

0.50
0.50
1.00

480.00
375.00
375.00

240.00
187.50
375.00
0.00
0.00
5.00
2986.50

802.50
5.00

23

Supply and fixing 8 way TPN - Vertical type Distribution board with IP -43
Protection with 125A, 4 Pole 25 kA MCCB as incomer with 8Nos 63A TP MCBs as
outgoing including internal connection and labour charges for flush mounting etc.,
complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B
8 way TPN Vertical DB
a) Material
elec.2.12.5 6 Way TPN Vertical DB with IP -43 (Metal
Nos
1.00
9823.00
9823.00
0
door) protection suitable for 125A, 4 Pole,
25kA MCCB as incomer.
elec-2.8.13 125 Amps, 4 Pole , 25 kA MCCB
Nos
1.00
7194.00
7194.00
elec-2.9.14 10 kA, 63A TP MCBs:
Nos
8.00
1477.00
11816.00
elec-2.9.9 10kA, 6 to 32A SP MCBs:
Nos
0.00
201.00
0.00
28833.00
Add contr profit @14% on material
0.00
0.00
Total material cost
28833.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
1.00
480.00
480.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
0%
0.00
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
0%
1230.00
0.00
Sundries such as T.W. Plugs, Screws,
LS
19.00
19.00
Cement etc.,
Rate per each
30082.00
Note : 1. Labour Charges considered for 1 jobs /
Say
30082.00
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilled for
mason
b

1/4 bag cement

23

Supply and fixing 8 way TPN - Vertical type Distribution board with IP -43
Protection with 125A, 4 Pole 25 kA MCCB as incomer with 4Nos 63A TP MCBs and
12 Nos. 10 kA SPMCBs as outgoing including internal connection and labour
charges for flush mounting etc., complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B
8 way TPN Vertical DB
a) Material
elec.2.12.5 8 Way TPN Vertical DB with IP -43 (Metal
Nos
1.00
9823.00
9823.00
0
door) protection suitable for 125A, 4 Pole,
25kA MCCB as incomer.
elec-2.8.13 125 Amps, 4 Pole , 25 kA MCCB
Nos
1.00
7194.00
7194.00
elec-2.9.14 10 kA, 63A TP MCBs:
Nos
4.00
1477.00
5908.00
elec-2.9.9 10kA, 6 to 32A SP MCBs:
Nos 12.00
201.00
2412.00
25337.00
Add contr profit @14% on material
0.00
0.00
Total material cost
25337.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
1.00
480.00
480.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
1230.00
0.00
Sundries such as T.W. Plugs, Screws,
LS
19.00
19.00
Cement etc.,
Rate per each
26586.00
Note : 1. Labour Charges considered for 1 jobs /
Say
26586.00
day

101

2. If the Distribution Boards from Item No. 4.4.1


to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilled for
mason
b
1/4 bag cement
23

Supply and fixing 8 way TPN - Vertical type Distribution board with IP -43
Protection with 1 No. 63A FP MCCB as incomer with 24 Nos. 10 kA SPMCBs as
outgoing including internal connection and labour charges for flush mounting etc.,
complete.
Makes : L&T Exora /Siemens / GE /ABB /Standard / Havells / HPL / Indo
Asain / Toyoma
B
8 way TPN Vertical DB
a) Material
elec.2.12.3 8 Way TPN Vertical DB with IP -43 (Metal
Nos
1.00
9823.00
9823.00
5
door) protection suitable for 125A, 4 Pole,
25kA MCCB as incomer.
elec-2.8.12 63 Amps, 4 Pole , 25 kA MCCB
Nos
1.00
5668.00
5668.00
elec-2.9.6 10 kA, 63A TP MCBs:
Nos
1477.00
0.00
elec-2.9.9 10kA, 6 to 32A SP MCBs:
Nos 24.00
162.00
3888.00
19379.00
Add contr profit @14% on material
0.00
0.00
Total material cost
19379.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
1.00
480.00
480.00
elec-8.1.75 Semi Skilled Electrician
day
1.00
375.00
375.00
elec-8.1.82 Helpers
day
1.00
375.00
375.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
1230.00
0.00
Sundries such as T.W. Plugs, Screws,
LS
19.00
19.00
Cement etc.,
Rate per each
20628.00
Note : 1. Labour Charges considered for 1 jobs /
Say
20628.00
day
2. If the Distribution Boards from Item No. 4.4.1
to
proposed
concealing, add the
a 4.4.8
1No. Semi
skilled for
mason
26

b
1/4 bag cement
Providing independent earthling by excavating a trench to a depth of 2.1 M in all
soils, as per size specified in the Data, using 40mm dia 'B' class GI pipe of 2.5 Mtrs
length with necessary accessories with hume pipe ring duly providing staggered
holes including filling with equal proportion of Salt and Charcoal in layers and all
labour charges etc., complete for small quarters.

a) Material
elec.8.1.52 Earth Work Excavation of Hard gravel Soil
with small boulder for trench 1st step of
size 1.5 x 0.6 x 0.9 m
Excavation of Hard disteggrated rocks
and boulders for trench 2nd Step of size
1.2 x 0.6 x 1.2 m (Civil SSR)
25% extra for narrow trench & pit and
back filling with Sand, Coke, Salt etc., and
elec.8.1.58 leveling
40mm dia 'B' Class G.I pipe
25 x 6 mm (1"X 1/4") G.I Flat duly drilled
12mm holes (4 Nos) of 200 mm (8")
elec.8.1.59 length
Drilling of 16 Nos through holes of 12mm
dia to G.I pipe
elec-8.1.12 G.I Nuts, Bolts an Washers
elec.8.1.61 18" dia hume pipe ring
elec-8.1.13 Hard Coke
elec-8.1.14 Salt

102

cum

0.85

0.00

0.00

cum

0.90

0.00

0.00

1.00

0.00

0.00

Mtr
Each

2.50
1.00

355.00
75.00

887.50
75.00

Each

16.00

6.00

96.00

Set
Each
Kg
Kg

4.00
1.00
40.00
20.00

13.00
220.00
9.00
4.00

52.00
220.00
360.00
80.00
1770.50

Add contr profit @14% on material


0.00
Total material cost
b) labour charges for fixing pipe ring and connections
elec-8.1.75 Semi skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries
Rate per each

Nos
Nos
0%
0%

0.50
0.50

0.00
1770.50
375.00
375.00
375.00

Say
27

187.50
187.50
0.00
0.00
2145.50
2145.50

Supply and Run of No.8 SWG G.I wire including cost of all accessories and labour
charges etc., complete.

a) Material
elec-8.1.45 No.8 SWG G.I wire 100 M Length (0.104
Kg
Kg / Mtr)
elec-8.1.07 U' Nails
100No
s
Add contr profit @14% on material
Total for material
b) labour charges
elec-8.1.82 Helpers

10.40

68.00

707.20

1.50

44.00

66.00
773.20
0.00
773.20

2.00

375.00

750.00

0.00

day

Add area allowence on labour


charges
Add contr@
profit @14% on Labour
C) Cost for 100 M
Rate per mtr c/100

0%
0%

750.00

0.00
0.00
1523.20
15.25

28

Supply, Transportation and fixing of 4' of 1x 36/ 40 Watt Box type Tube Light
luminaire powder coated CRCA sheet steel housing with
electronic ballast
suitable for 40 Watt tube including all labour charges for fixing fitting on varnished
teak wood round blocks with flexible 3 core wire etc.,, complete with all
connections including cost of 40W tube.
Makes: Surya / Havells / HPL / Fortune Art
a) Material
elec-3.6.5 4' x 40 watts box type flourscent light
each
1.00
1060.00
1060.00
elec-3.7.16 fitting.
Lamp cost of 40W
each
1.00
45.00
45.00
elec-8.1.31 Tw Round blocks
each
2.00
7.00
14.00
Elec-1.4.34 screws with rawal plugs
0.00
0
each
2.00
Elec-1.6.8 23/0060 twin core flexible copper cable
0.00
0
M
1.50
Rate per each
1119.00
Add contr profit @14% on material
0.00
0.00
Total for material
1119.00
a) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each
7.9.3

day
day
0%
0%

0.100
0.100

480.00
375.00
85.50

48.00
37.50
0.00
0.00
1204.50

Fixing of 40W tube light luminaire on wall / Ceiling with TW round blocks with
all accessories including giving connections and all labour charges etc., complete.

Rate per each


a) Material
Elec-1.6.8 23/0060 twin core flexible copper cable

103

1.0

1040.00

10.4

Elec-1.4.34 screws with rawal plugs


Elec-8.1.35 T.W round blocks
Cement and sand etc.,

each
each
LS

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician/carpenter
day
elec-8.1.75 Semi skilled Electrician / Helper
day
Add area allowence on labour
0%
charges
@
Add contr profit @14% on Labour
0%
Rate per each
Note : 1. The Cost of Ceiling Rose may be
deducted in view of holder.
Note : Labour Charges considered for 10
fixtures / day .
29

54.00
7.00

1.08
14
2.11
27.59
0.00
29.70

0.10
0.10

480.00
375.00

48
37.5
0.00
0.00
115.20

85.50

Supply and fixing of batten holder / slanting holder in lieu of ceiling rose of light
point complete with all connections and all labour charges with 13w CFL lights (for
new installation).
Makes : Gold Medal Olive /Million Zoom / Anchor Penta Cherry
Taking Output = each

a) Material
elec-1.7.15 PVC batten holder
elec-3.7.1 13w CFL lights
elec-1.7.13 Deduct Cost of Ceiling Rose

each
each
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
@
Add contr profit @14% on Labour
0%
Rate per each
Note : 1. The Cost of Ceiling Rose may be
deducted in view of holder.
2. Labour Charges proposed for 20 jobs per day
30

2.0
2.0
5.6

1.00
1.00
1.00

20.00
110.00
21.00

20.00
110.00
-21.00
109.00
0.00
109.00

0.05
0.05

480.00
345.00

24.00
17.25
0.00
0.00
150.25

39.25

Supply and fixing of call bell on 6"x8" decolam block including giving connections,
cost of all accessories and labour charges etc., complete. Make :
Anchor/Goldmedal/Million / Million / Vimal / Maru

Taking Output = each


a) Material
elec-1.7.20 Call bell
elec-1.4.11 8"x6" decolam block

each
each

Add contr profit @14% on material


Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each

104

1.00
1.00

102.00
44.00

102.00
44.00
146.00
0.00
146.00

0.062
0.062

480.00
345.00

29.76
21.39
0.00
0.00
197.15

0.00

day
day
0%
0%

51.15

31

Supply and fixing of Ding dong on 6"x8" decolam block including giving
connections, cost of all accessories and labour charges etc., complete. Make :
Anchor/Goldmedal/Million / Million / Vimal / Maru

Taking Output = each


a) Material
elec-1.7.22 Ding dong bell
elec-1.4.11 6"x8" decolam block

each
each

Add contr profit @14% on material


Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Rate per each
32

1.00
1.00

102.00
39.60

102
39.6
141.6
0.00
141.6

0.062
0.062

480.00
345.00

29.76
21.39
0.00
0.00
192.75

0.00

day
day
0%
0%

51.15

Supply of 1200 mm (48") sweep ISI mark ceiling Fan as per IS 374- 1979 and
operating on 230V, A.C 50 Hz.Ceiling fan with 3 Blades and double ball bearings
with all standard accessories. Brown color
Makes: Crompton / Bajaj Kassels 50 / Usha Atom

a) Material
elec-5.1.1 1200 mm (48") Ceiling Fan
Transportation Charges on Unit Cost
Add contr profit @14% on material
Total material cost

each

0.00

1.00
1%

1600.00
16.00

1600.00
16.00
1616.00
0.00
1616.00

Supply of 1200 mm (48") sweep IS 374 -1979 and 5 Star rated ceiling Fan and
operating on 230V, A.C 50 Hz.Ceiling fan with 3 Blades and double ball bearings
with all standard accessories.
Makes: Crompton High Speed Plus / Bajaj Electra 50 / Orient Energy Star
/ Havells ES 50
a) Material
elec-5.1.2 1200 mm (48") Ceiling Fan
each
1.00
1825.00
1825.00
Transportation Charges on Unit Cost
1%
18.25
18.25
1843.25
Add contr profit @14% on material
0.00
0.00
Total material cost
1843.25
33

Supply and erecting Electronic type regulator for ceiling fans 1200 mm sweep
complete erected on existing board. Make : Anchor Penta Cherry / Gold
Medal Olive / Million Zoom
a) Material
elec-1.7.12 Steeped type Electronics type Regulator
M
1.00
220.00
220.00
Add contr profit @14% on material
0.00
0.00
Total material cost
220.00
b) Labour charges.
elec-8.1.75 Semi skilled Electrician
day
0.10
375.00
37.50
Sundries.
21.20
Add area allowence on labour
0%
0.00
charges
@
Add contr profit @14% on Labour
0%
58.70
0.00
Rate per Each
278.70

105

Note : Labour is Considered for 10


jobs / day
34

Labour Charges
Labour charges for Fixing of Ceiling fan and regulator including transportation and
giving connections with twin core wire etc., complete.

a) Material
elec-1.6.8 23/0060 Twin Core wire
100 M
Unforseen item works, such as painting
LS
to down rod, screws etc.,
Add contr profit @14% on material
Total for material
b) Labour charges.
elec-8.1.75 Skilled Electrician
elec-8.1.82 Helper
Add area allowence on labour
charges
Add contr@
profit @14% on Labour

1.00
1.00

1040.00
3.00

1043.00
0.00
1043.00

0.00

day
day
0%
0%

0.125
0.125

440.00
345.00
98.13

Rate per Each


Note : Labour is Considered for 8
fans / day
35

55.00
43.13
0.00
0.00
1141.13
142.64

Supply of fresh air exhaust fan of heavy duty 250V A.C.50Hz.. 300mm size (12")
900 R.P.M etc., complete.
Makes: CG / Almounard / Havells Turbo Force

a) Material
elec-5.1.11 300mm (12") 1350 RPM H.D. Exhaust
Fan
Transportation Charges on Unit Cost
Rate per Each
Add contr profit @14% on material
Total for material
36

1040.00
3.00

each

1.00
1%

2645.00
26.45

0.00

2645.00
26.45
2671.45
0.00
2671.45

Labour charges for fixing of Exhaust fan in wall with necessary connections and
masonary work of making hole, finishing etc., complete

a) Material
elec-1.6.8 23/0060 Twin flat wire
elec-8.1.50 Cement

100 M
kg

Add contr profit @14% on material


Total for material
b) Labour charges.
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helper
elec-8.1.76 Mason
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries such as Sand, Bolt, Nuts etc.,
Rate per Each
Note :1. Labour is Considered for 6
jobs / day

106

1.00
1.00

1040.00
6.60

1040.00
6.60
1046.60
0.00
1046.60

0.25
0.25
0.25

440.00
345.00
385.00

292.50
24.34

110.00
86.25
96.25
0.00
0.00
24.34
1363.44
227.24

0.00

day
day
day
0%
0%
LS

2. Cost of louver shutter may be added if


required.
3. If hole is already made available,
labour charges of Mason
shall be
deleted.
37

Supply of 1x40W weather proof flourescent streetlight fitting comprising canopy of


sheet Aluminium in stove enamel finish with copper / VPIT ballast, capacitor, tube
and starter etc., complete.
Makes: Phillips / GE / Wipro

a) Material
elec-3.1.1 1x40W WP flourscent street light fitting.
elec-3.7.7 Lamp cost of 40W
Add contr profit @14% on material
Total for material

each
each

1.00
1.00

1400.00
45.00

0.00

1400.00
45.00
1445.00
0.00
1445.00

38

Fixing of 40W street light luminaire to the wall with 1.0 Mtr., 25mm dia GI pipe
bracket and anti tilting MS flat etc., including giving connections and labour
charges etc., complete.
a) Material
elec-8.1.55 25mm dia G.I pipe light grade
M
1.00
226.00
226.00
elec-1.6.8 23/0060 twin core flexible copper cable
M 10.00
10.40
104.00
Pipe bending charges
LS
1.00
25.00
25.00
M.S flat and welding charges
LS
1.00
35.00
35.00
390.00
Add contr profit @14% on material
0.00
0.00
Total for material
390.00
b) Labour charges
elec-8.1.74 Skilled Electrician/carpenter
day
0.20
440.00
88.00
elec-8.1.76 Mason
day
0.20
385.00
77.00
elec-8.1.75 Semi skilled Electrician / Helper
day
0.20
345.00
69.00
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
234.00
0.00
Rate per each
624.00
Note : Labour Charges considered for 5
fixtures / day .
39

Supply of Integral street light luminaire of 150W HPSV lamp fitting comprises of
single piece die cast Aluminium body with copper wound ballast and capacitor,
Ignitor, with pot optics including 150W HPSV lamp etc., complete.
Makes: Phillips / GE /Wipro / Bajaj / Crompton

a) Material
elec-3.1.7 150W HPSV Lamp fitting single piece die
cast Aluminium body with copper wound
ballast and capacitor, Ignitor, with pot
elec-3.4.10 optics
150W HPSV lamp
Add contr profit @14% on material
Total for material
Rate per each
40

each

1.00

5327.00

5327.00

each

1.00

710.00

710.00
6037.00
0.00
6037.00
6037.00

0.00

Fixing of MV / SV/MH luminaire on wall with 1.0mt 40mm dia GI pipe bracket and
anti-tilting MS flat, 2.5 Sq.mm flexible copper cable etc.,including all labour
charges for mason work and giving connections etc., complete.
a) Material

107

elec.8.1.57 40mm G.I pipe for Bracket


elec.1.5.3 2.5 Sq.mm flexible copper cable

M
M

Add contr profit @14% on material

355.00
25.10

1.00

25.00

0.25
0.25
0.25
0.25

440.00
385.00
345.00
385.00

0.00

Pipe bending charges


b) Labour charges for Antitiling MS
flat / welding charges & fixing

LS

elec-8.1.74 Skilled Electrician


day
elec-8.1.83 Carpenter
day
elec-8.1.82 Helper
day
elec.8.1.78 Welder
day
0%
Add area allowence on labour
charges
@
Add contr profit @14% on Labour
0%
Rate per each
Note : Labour Charges considered for 4Nos MV / SV
41

1.00
4.00

278.75

355.00
100.40
455.40
0.00
455.40
25.00

110.00
96.25
86.25
96.25
0.00
0.00
869.15

Supply and laying of 2 pair telephone wire in the existing metallic/non metallic
conduit pipe withconnectionsetc.,complete
Makes: Million / Finolex /
Delton / Surabi / Polycab / Nakoda

Taking Output = 100 M


a) Material
elec-7.1.1 2 pair telephone wire
100 M
Add contr profit @14% on material
0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
0%
Add area allowence on labour
charges
@
Add contr profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
42

1.00

1010.00

1010.00
0.00
1010.00

0.34
1.00
0.34

440.00
375.00
345.00

149.60
375.00
117.30
0.00
0.00

641.90

1651.90
16.55

Supply and fixing of telephone jack type socket with top on MS box with modular
plate cover with screws connections etc., Makes: Gold Medal Olive / Million
zoom
Taking Output = 100 M
a) Material
elec-1.7.16 telephone jack type socket
1.00
48.00
48.00
elec-1.3.1 MS box
1.00
57.00
57.00
elec-1.4.1 4x4 sunglass delux board
1.00
14.00
14.00
119.00
Add contr profit @14% on material
0.00
0.00
Total for material
119.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.10
440.00
44.00
elec-8.1.75 Semi Skilled Electrician
day
0.10
375.00
37.50
elec-8.1.82 Helpers
day
0.10
345.00
34.50
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
116.00
0.00
Sundries
C) Cost for each
235.00

108

42 (a)
elec-7.1.9 Supply of 3 feet length patch cords of
make D link make / Beldan / Krone
43

1.00

1.00

2580.00

2580.00
0.00
2580.00

0.34
1.00
0.34

440.00
375.00
345.00

149.60
375.00
117.30
0.00
0.00

641.90

3221.90
32.25

Supply and fixing of cat-6 RJ-45information outlets including dual face plate with
MS box with modular plate cover with screws connections etc., Makes: Belden/D
link/Legrand

a) Material
elec-7.1.4 cat-6 RJ 45 information oulet
elec-1.3.1 MS box

Add contr profit @14% on material


Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
elec-8.1.75 Semi Skilled Electrician
elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries
C) Cost for each
45

200.00

Supply and laying of LAN cable Cat-6(A) UTP CABLE in the existing metallic/non
metallic conduit pipe with connections etc.,complete
Makes:D Link/ AMP /Molex

Taking Output = 100 M


a) Material
elec-7.1.3 cat-6 (A) UTP LAN cable
100 M
Add contr profit @14% on material
0.00
Total for material
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
@
Add contr profit @14% on Labour
0%
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M / day
44

200.00

1.00
1.00

340.00
57.00

340.00
57.00
0.00
397.00
0.00
397.00

0.20
0.20
0.12

440.00
375.00
345.00

88.00
75.00
41.40
0.00
0.00

0.00

day
day
day
0%
0%

204.40

601.40

Supply and laying of lan cable cat-6 UTP cable in the existing metallic/non metallic
conduit pipe with connections etc.,complete
Makes: AMP/DLINK/MOLEX/LEGRAND/KRONE.
Taking Output = 100 M
a) Material

ELEC-7.1.3 RG6 lan cable cat-6 UTP cable


Add contr profit @14% on material

100 M
0.00

1.0

2580.00

2580.00
0.00
2580.00

day

0.34

440.00

149.60

Total for material

b) Labour charges :
elec-8.1.74 Skilled Electrician

109

elec-8.1.75 Semi Skilled Electrician


elec-8.1.82 Helpers
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundries
C) Cost for 100 RM
Rate per Metre = C/100
Note : Labour Charges considered for 150 M /

day
day
0%
0%

1.00
0.34

375.00
345.00
641.90

375.00
117.30
0.00
0.00
3221.90
32.25

day

46

Supply and fixing of TV antenna outlet with MS box with cover with screws
connections etc., Makes: Goldmedal olive/Million zoom/Vimal opel/Maru
montero/Anchor
a) Material
elec1.7.17 TV socket outlet
1.00
26.00
26.00
elec-1.3.1 MS box
1.00
63.00
63.00
elec-1.4.3 6" X 6" sunglass delux board
1.00
25.00
25.00
114.00
Add contr profit @14% on material
0.00
0.00
Total for material
114.00
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
0.04
440.00
17.60
elec-8.1.75 Semi Skilled Electrician
day
0.04
375.00
15.00
elec-8.1.82 Helpers
day
0.04
345.00
13.80
Add area allowence on labour
0%
0.00
charges
Add contr@
profit @14% on Labour
0%
46.40
0.00
Sundries
C) Cost for each
160.40
21

Supply and fixing of 24 port switches of D link/ AMP/ Krone make including making
connections and etc., complete

24 switch
Taking Output = each
a) Material
elec-7.1.5 24 port switch

each
each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
Add contr@
profit @14% on Labour
0%
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day
21
A

1.00

5200.00

5200.00
0.00
0.00
5200.00
0.00
5200.00

1.00
1.00
1.00

440.00
375.00
345.00

440.00
375.00
345.00
0.00
0.00
14.00

1160.00
14.00

6374.00

Supply of 17U floor mounting net work rack with power spike including all
accessries of make HCL / Vall
24 switch
Taking Output = each

110

a) Material
elec-7.1.24 17U floor mounting rack

each
each
each

Add contr profit @14% on material


0.00
Total material cost
b) Labour charges :
elec-8.1.74 Skilled Electrician
day
elec-8.1.75 Semi Skilled Electrician
day
elec-8.1.82 Helpers
day
Add area allowence on labour
0%
charges
@
Add contr profit @14% on Labour
0%
Sundries such as TW Plugs, Screws
LS
Cement etc,
Rate per each
Note : Labour Charges considered for 2 jobs / day

1.00 10125.00

1.00
1.00
1.00

440.00
375.00
345.00
1160.00
14.00

10125.00
0.00
0.00
10125.00
0.00
10125.00
440.00
375.00
345.00
0.00
0.00
14.00
11299.00

Supply of 240 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.43 3.5 Core 240.00 Sq.mm.
Rmt
1.00
1023.00
1023.00
Add contr profit @14% on material
0.00
0.00
Total for material
1023.00
Supply of 185 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.40 3.5 Core 185.00 Sq.mm.
Rmt
1.00
806.00
806.00
Add contr profit @14% on material
0.00
0.00
Total for material
806.00
Supply of 150 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.38 3.5 Core 150.00 Sq.mm.
Rmt
1.00
658.00
658.00
Add contr profit @14% on material
0.00
0.00
Total for material
658.00
Supply of 120 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.35 3.5 Core 120.00 Sq.mm.
Rmt
1.00
579.00
579.00
Add contr profit @14% on material
0.00
0.00
Total for material
579.00
Supply of 95 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.32 3.5 Core 95.00 Sq.mm.
Rmt
1.00
547.00
547.00
Add contr profit @14% on material
0.00
0.00

111

Total for material

547.00

Supply of 95 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.32 3.5 Core 95.00 Sq.mm.
Rmt
1.00
547.00
547.00
Add contr profit @14% on material
0.00
0.00
Total for material
547.00
Supply of 50 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.26 3.5 Core 50.00 Sq.mm.
Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

326.00

326.00
0.00
326.00

Supply of 35 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.23 3.5 Core 35.00 Sq.mm.
Rmt
1.00
347.00
347.00
Add contr profit @14% on material
0.00
0.00
Total for material
347.00
Supply of 25 Sq. mm 3.5 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.20 3.5 Core 25.00 Sq.mm.
Rmt
1.00
207.00
207.00
Add contr profit @14% on material
0.00
0.00
Total for material
207.00
Supply of 16 Sq. mm 4 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.17 4.0 Core 16.00 Sq.mm.
Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

162.00

162.00
0.00
162.00

Supply of 10 Sq. mm 4 Core XLPE insulated 1100 Volts grade armoured


alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.14 4.0 Core 10.00 Sq.mm.
Rmt
1.00
128.00
128.00
Add contr profit @14% on material
0.00
0.00
Total for material
128.00
Supply of 6 Sq. mm 4 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab

112

elec-4.1.11 4.0 Core 6.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

112.00

112.00
0.00
112.00

Supply of 10 Sq. mm 2 Core XLPE insulated 1100 Volts grade armoured


alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.8 2.0 Core 10.00 Sq.mm.
Rmt
1.00
112.00
112.00
Add contr profit @14% on material
0.00
0.00
Total for material
112.00
Supply of 6 Sq. mm 2 Core XLPE insulated 1100 Volts grade armoured
alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.5 2.0 Core 6.00 Sq.mm.
Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

93.00

93.00
0.00
93.00

Supply of 4 Sq. mm 2 Core XLPE insulated 1100 Volts grade armoured


alluminium cable as per specification confirming of IS 7098 (Part - I) conductor
complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab
elec-4.1.2 2 Core 4.00 Sq.mm.
Rmt
1.00
78.00
78.00
Add contr profit @14% on material
0.00
0.00
Total for material
78.00
47

Supply of the following XLPE armoured cable 1100 V. Grade with ISI mark
stranded / solid, aluminimum conductor complete
Make: PolyCab / RPG / Finolex / Havells / Paragon / V- Guard / Fortune Art
/ Gloster / Suncab

elec-4.1.32 3.5 Core 95.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

472.00

472.00
0.00
472.00

elec-4.1.29 3.5 Core 70.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

363.00

363.00
0.00
363.00

elec-4.1.23 3.5 Core 50.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

280.00

280.00
0.00
280.00

elec-4.1.26 3.5 Core 35.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

212.00

212.00
0.00
212.00

elec-4.1.20 3.5 Core 25.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

180.00

180.00
0.00
180.00

elec-4.1.17 4.0 Core 16.00 Sq.mm.


Add contr profit @14% on material
Total for material

Rmt
0.00

1.00

140.00

140.00
0.00
140.00

113

48

Earth work excavation of Trench in hard ground soil, laying of U.G cables from 70 sqm to 400 Sq

a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)
elec-8.1.53 Cost of sand (Civil SSR)
elec-8.1.50 Cement (Civil SSR)
elec-8.1.27 Cost of cable route indicator

cum
1000
Nos
cum
Kg
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges for laying cable.
elec-8.1.84 Man Mazdoor for spreading the sand and
each
back filling the excavated soil.
elec-8.1.74 Skilled Electrician
day
elec-8.1.81 Helper
day
elec-8.1.84 Man Mazdoor for concreting and embedding ofday
cable
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts
Rate per Mtr
48

1.00
1.00

110.00
5427.01

110.00
5427.01

1.00
25.00
12.00

680.21
6.45
83.00

680.21
161.25
996.00
7374.47
0.00
7374.47

2.50

320.00

800.00

1.00
480.00
2.00
375.00
way
2.00indicators
320.00

480.00
750.00
640.00

1870.00

0.00
0.00

0%
0%

10044.47
100.45

Earth work excavation of Trench in hard ground soil, laying of U.G cables upto 50 Sq,mm on san

a) Material
elec-8.1.52 Excavation of earth 100 x 0.3 X 0.9 m
elec-8.1.54 Cost of bricks (Civil SSR)
elec-8.1.53 Cost of sand (Civil SSR)
elec-8.1.50 Cement (Civil SSR)
elec-8.1.27 Cost of cable route indicator

cum
1000
Nos
cum
Kg
each

Add contr profit @14% on material


0.00
Total for material
b) Labour charges for laying cable.
elec-8.1.84 Man Mazdoor for spreading the sand and
each
back filling the excavated soil.
elec-8.1.74 Skilled Electrician
day
elec-8.1.81 Helper
day
elec-8.1.85 Man Mazdoor for concreting and embedding ofday
cable
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundires and Rounding off
Rate per 100mts

114

0%
0%

1.00
1.00

110.00
5427.01

110.00
5427.01

1.00
25.00
12.00

680.21
6.45
83.00

680.21
161.25
996.00
7374.47
0.00
7374.47

2.50

320.00

800.00

1.00
480.00
2.00
375.00
way
2.00indicators
320.00

480.00
750.00
640.00

1870.00

0.00
0.00
10044.47

Rate per Mtr


49

100.45

Labour charges for run of U.G cable on wall / existing pipe with necessary fixing
arrangments such as saddles, clamps,wooden separators etc., (as directed by
departmental official) with No.10 SWG G.I wire for eath connections for the cables.

a) Material
elec-8.1.8 Wooden separators
elec-1.1.38 saddles of required size

each 100.00
100
2.00
nos
100
4.00
nos
kg
7.00

elec-1.4.34 12mm screws


elec-8.1.45 No.10 SWG GI wire
Add contr profit @14% on material
Total material cost
b) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helper
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundires such as Cement, Sand etc.,
Rate per Each
Note : Labour Charges Considered
for 100 Mts / day
50

165.00
446.00

16500.00
892.00

59.00

236.00

68.00

476.00
18104.00
0.00
18104.00

480.00
375.00

480.00
1500.00
0.00
0.00
21.00
20105.00
201.05

0.00

day
day
0%
0%

1.00
4.00

1980.00

Supply and Fixing of 3 phase meter Box, 3 Nos 100 A fuse units, Neutral link, on
T.W block with all accessaries etc., complete for finished items of work.

a) Material
elec-2.6.4 100 A Fuse units
100 A neutral links
elec-1.4.31 T.W blocks ( 12" x 15" )

each
each
each

Add contr profit @14% on material


Total for material
b) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helper
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundires such as Cement, Sand etc.,
Rate per Each
51

3.00
1.00
1.00

484.00
118.00
109.00

1452.00
118.00
109.00
1679.00
0.00
1679.00

1.00
4.00

480.00
375.00

480.00
1500.00
0.00
0.00
50.00
3709.00

0.00

day
day
0%
0%

1980.00

Supply and Fixing of Single phase Electronic energy meter of 40A rating in a M.S
Box,including 1 No 32 A fuse units, Neutral link etc. on T.W block with all
accessaries etc., complete for finished items of work. Make: HPL / Conzeru/AE
makes
a) Material
elec-6.3.11 Single phase energy meterof 40A rating
each
1.00
1050.00
1050.00
elec-2.6.1 32 A Fuse units
each
1.00
99.00
99.00
elec-1.3.12 MS box 300mmx250mm
each
1.00
236.00
236.00
1385.00
Add contr profit @14% on material
0.00
0.00

115

Total for material


b) Labour charges
elec-8.1.74 Skilled Electrician
elec-8.1.82 Helper
Add area allowence on labour
charges
Add contr@
profit @14% on Labour
Sundires such as Cement, Sand etc.,
Rate per Each

1385.00
day
day
0%
0%

1.00
0.33

480.00
375.00
603.75

480.00
123.75
0.00
0.00
50.00
2038.75

52

Supply and erecting ISI Mark 25 Ltrs Water heater with multiple safety system,
rust free ABS plastic body, 230V, 50Hz.., A.C. supply with inlet and outlet
connections with pvc/ nylon / metallic hose pipe, thermostat control and thermal
cutoff with 3 core P.V.C. flexible wire leads duly tested including cost of all
materials and all labour charges etc., complete.
Make: VENUS / RACOLD / BAJAJ / USHA
a) Material
elec-5.2.2 25 ltr water heater
each
1.00 10438.00
10438.00
transportation charges on unit cost
2%
208.76
elec-5.3.4 Hose pipe PVC/Nylon
nos
2.00
158.00
316.00
10962.76
Add contr profit @14% on material
0.00
0.00
Total for material
10962.76
b) Labour charges
elec-8.1.74 Skilled Electrician
day
0.25
480.00
120.00
elec-8.1.82 Helper
day
0.25
375.00
93.75
Add area allowence on labour
0%
0.00
charges
@
Add contr profit @14% on Labour
0%
213.75
0.00
Sundires such as anchor bolts ,gutties etc.,
25.00
11201.55
53

Supply,Transportation and erection of self contained drinking Water Cooler partial


stainless steel confirming to IS : 1475 / 78 with amendment No. 1 to 7 with 40 Lts
cooling capacity and 80 Lts of storage capacity for operation on 230V + 10%, 50
Hz.. single Phase A.C. Supply.
(Make: USHA/VOLTAS/BLUE STAR)
a) Material
As per MR
Rate per Each

each

54

Supply and fixing of concealed box PVC/MS with hook


A.Material
elec-8.1.25 Fan hook box
each
Add contr profit @14% on material
0.00
Total for material
b) Labour charges
elecSkilled Electrician
day
8.1.74
elecHelper
day
8.1.82 Add area allowence on labour
0%
charges
Add contr@
profit @14% on Labour
0%
Rate for each
, Executive Engineer
,A.P.E.W.I.D.Corporation
.NELLORE

Deputy Executive
, Engineer
A.P.E.W.I.D.Corpor
,ation
South Sub116
, Division
.N E L L O R E

1.00 34325.00

34325.00
34325.00

for fan
1.00

88.00

88.00
0.00
88.00

0.05
0.05

480.00
375.00

24.00
18.75
0.00
0.00
130.75

42.75

3
1
1
0
2

, Executive
Engineer
Deputy
Executive
Engineer
11.3.2
Supply
and erecting,
ISI mark
submersible 2.0 HP, 3, Assistant
Phase, 25
stages pumpset 3
,A.P.E.W.I.D.Corporation
, Engineer
,
A.P.E.W.I.D.Corporation
dia borewell with high quality water resistant and dynamically 1
. N Esuitable
L L O R Efor 156mmA.P.E.W.I.D.Corpor
.NELLORE
balanced bronze impeller
with stainless steel shaft sleeves, pump coupling and 1
,ation
pivot of 3 phase 415V South
, 50Hz..
Sub-A.C. power supply copper winding with water proof 0
, Division
insulation and high precision
strength not to be effected by chemical in water and .N E Lwith
L O Rnut
E and bolts etc., with necessary H-type clamp of 2
suitable bronze bearings
0
suitable size and strength.
0
a) Material
6
2HP, 1 Ph 3 stage submerisible pump set
each
1.00
including all taxes
23362.00
23362.00
80.00
160.00
Special M.S. clamps with bolts and nuts
each
2.00
467.24
Transportation Charges on Unit Cost
2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
400.00
400.00
Skilled Fitter
day
1.00
320.00
640.00
Helper
day
2.00
400.00
400.00
Plumber
day
1.00
Hire charges of tripod with winch 50% of
Labour charges
1440.00
720.00
Sundries and rouding off
LS
26149.24
Rate per Each

11.3.2

Supply and erecting, ISI mark submersible 2.0 HP, 3 Phase, 25 stages pumpset
suitable for 156mm dia borewell with high quality water resistant and dynamically
balanced bronze impeller with stainless steel shaft sleeves, pump coupling and
pivot of 3 phase 415V , 50Hz.. A.C. power supply copper winding with water proof
insulation and high precision strength not to be effected by chemical in water and
suitable bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
1.5HP, 1 Ph 3 stage submerisible pump
each
1.00
set including all taxes
18857.00
18857.00
80.00
160.00
Special M.S. clamps with bolts and nuts
each
2.00
377.14
Transportation Charges on Unit Cost
2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
400.00
400.00
Skilled Fitter
day
1.00
320.00
640.00
Helper
day
2.00
400.00
400.00
Plumber
day
1.00
Hire charges of tripod with winch 50% of
Labour charges
1440.00
720.00
Sundries and rouding off
LS
21554.14
Rate per Each

11.3.2

Supply and erecting, ISI mark submersible 3.0 HP, 3 Phase, 25 stages pumpset
suitable for 156mm dia borewell with high quality water resistant and dynamically
balanced bronze impeller with stainless steel shaft sleeves, pump coupling and
pivot of 3 phase 415V , 50Hz.. A.C. power supply copper winding with water proof
insulation and high precision strength not to be effected by chemical in water and
suitable bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
3 HP, 3 Ph 3 stage submerisible pump set
each
1.00 25724.00
including all taxes
25724.00
80.00
160.00
Special M.S. clamps with bolts and nuts
each
2.00
514.48
Transportation Charges on Unit Cost
2%

117

b) Labour charges for erection of


pump set including pipe connection
for suction & delivery
Skilled Fitter
Helper
Plumber
Hire charges of tripod with winch 50% of
Labour charges
Sundries and rouding off
Rate per Each
11.3.2

day
day
day

1.00
2.00
1.00

315.00
285.00
315.00

315.00
570.00
315.00

1200.00

600.00

LS
28198.48

Supply and erecting, ISI mark submersible 5.0 HP, 3 Phase, 25 stages pumpset
suitable for 156mm dia borewell with high quality water resistant and dynamically
balanced bronze impeller with stainless steel shaft sleeves, pump coupling and
pivot of 3 phase 415V , 50Hz.. A.C. power supply copper winding with water proof
insulation and high precision strength not to be effected by chemical in water and
suitable bronze bearings with nut and bolts etc., with necessary H-type clamp of
suitable size and strength.
a) Material
5 HP, 3 Ph 3 stage submerisible pump set
each
1.00 32373.00
32373.00
including all taxes
80.00
160.00
Special M.S. clamps with bolts and nuts
each
2.00
647.46
Transportation Charges on Unit Cost
2%
b) Labour charges for erection of
pump set including pipe connection
for suction & delivery
400.00
400.00
Skilled Fitter
day
1.00
320.00
640.00
Helper
day
2.00
400.00
400.00
Plumber
day
1.00
Hire charges of tripod with winch 50% of
Labour charges
1440.00
720.00
Sundries and rouding off
LS
35340.46
Rate per Each

,Executive Engineer
APEWIDC,
ANANTAPURAMU

,Dy.Executive Engineer
APEWIDC,
ANANTAPURAMU

118

,Assistant Engineer
APEWIDC, TADIPATRI

Name of work :Construction of School building under R&R Centre to MPUPS In Various co
Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu (Dist)

WATER SUPPLY AND SANITARY DATAS

25%
13.62%
ITEM
COEFFI
DESCRIPTION
UNIT
RATE
PER
CODE
CIENT
Supplying and laying, filling, jointing and testing SWG SP-1 pipes of ISI make confirming to IS
quality with air tight Cement joints in CM (1.5:1)prop. including excavation of trenches and socket pits in
rock requiring blasting) and refilling with watering and tamping to the required slope including cost and
materials to site and all labour charges for finished item of work (APSS NO 1301 & 1318)
AREA ALLOWENCE
ADD OVERHEADS

Sl.
No.
1

a) 101.60 mm dia SWG pipe upto 3' depth


Area allowence on labour charges
add overheads @

BMW-A.02
BMW-A.05

1.00
25%

Rmt

408.00
232.00

1.00
1.00

1.00
25%

Rmt

680.00
288.00

1.00
1.00

1.00
25%

Rmt

466.00
288.00

1.00
1.00

1.00
25%

Rmt

614.00
232.00

1.00
1.00

0.14

Total rate per 1 Rmt


b) 152.40mm dia SWG pipe upto 5' depth
Area allowence on labour charges
add overheads @

BMW-A.03
BMW-A.06
0.14

Total rate per 1 Rmt


c) 101.60 mm dia SWG pipe upto 5' depth
Area allowence on labour charges
add overheads @

BMW-A.01
BMW-A.06
0.14

Total rate per 1 Rmt


d) 152.40mm dia SWG pipe upto 3' depth
Area allowence on labour charges
add overheads @

BMW-A.04
BMW-A.05
0.14

Total rate per 1 Rmt


2

Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1
mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum
of 5 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted
manhole covers and frames including excavating pits up to a depth of 904 mm (3'-0") in all sorts
rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching
mm thick as per Standard specification and including cost and conveyance of all materials like cem
water etc., to site, cost of seigniorage charges on all materials and all incidental and operational, la
mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item of wor
specification.
BMW-B.03
1.00
Nos 6237.00 1.00
basic rate as per ssr item
Area allowence on labour charges
25%
0.00 1.00
add overheads @
Total rate per 1 Nos

WS-Data

119 of 209

0.14

Sl.
No.
3

ITEM
COEFFI
UNIT
RATE
PER
CODE
CIENT
Constructing 904.0 mm (30) dia brick masonry inspection chamber as per IS - 4111: Part-1:1
mortar (1:6) prop using 2nd Class Clay Bricks of 225 mm thick from approved source having a minimum
of 5 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted
manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in
(exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:
channel 100 mm thick as per Standard specification and including cost and conveyance of all materials l
bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operation
like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item
Standard specification.
DESCRIPTION

BMW-B.04

basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos 10181.00
0.00

1.00
1.00

0.14

Total rate per 1 Nos


4

Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per IS - 4111:
cement mortar (1:6) prop using fly ash blocks of 225mm thick from approved source having a minimum
of 10 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted
manhole covers and frames including excavating pits up to a depth of 1524 mm (5'-0") in
(exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:
channel 100 mm thick as per Standard specification and including cost and conveyance of all materials l
bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operation
like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item
Standard specification.
BMW-B.02
1.00
Nos 10590.00 1.00
basic rate as per ssr item
0.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 Nos


5

Constructing 904.0 mm (30) dia solid block masonry inspection chamber as per IS - 4111:
cement mortar (1:6) prop using fly ash blocks of 225mm thick from approved source having a minimum
of 10 N/sq.mm including plastering with cement mortar 1:3 prop; thick both inside and outside fitted
manhole covers and frames including excavating pits up to a depth of 1524 mm (3'-0") in
(exculding rock) and laying cement conrete (1:4:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:
channel 100 mm thick as per Standard specification and including cost and conveyance of all materials l
bricks, water etc., to site, cost of seigniorage charges on all materials and all incidental and operation
like mixing cement mortar, constructing masonry, lift charges, curing etc., complete for finished item
Standard specification.
BMW-B.01
1.00
Nos 6730.00 1.00
basic rate as per ssr item
0.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 Nos

Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 41
and constructing single brick masonry wall chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC
and fitted with 304.8 mm x 225.6 mm(12" x 9") CI frame and hinged cover and plastering 12mm thk.
both inside and outside surfaces and including cost and conveyance of all materials to site, labour charg
for finished item of work. SSR ITEM NO.527
BMW-A.72
1.00
Nos
568.00 1.00
Basic rate as per ssr item
BMW-A.74
30.00 1.00
Area allowence on labour charges
25%
add overheads @
Total rate per 1 Nos

WS-Data

120 of 209

0.14

Sl.
No.
7

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Supplying and fixing Indian make Flat Back Wash Hand Basin (HSW/Parryware/ Neycer) 1st qua
IS:2556-Part-4:1972 of size 550mm x 400mm with waste fittings like rubber plug, chain, 32 mm nomin
with parallel pipe thread conforming to IS:2963-1979 and fitted with 15 mm nominal bore Chromium P
1st quality Indian make 400 grams Seiko/ Esso or equivalent complete with standard CI brackets includin
No.12.70mm PVC connection with brass union nuts CP coated , 1 No.12.70mm NP bib tap 300 gms Se
including cost and conveyance of all materials to site, labour charges etc. complete for finished item of w
BMW-D24
BMW-D28

A Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

1782.00
377.00

1.00
1.00

1.00
25%

Nos

102.00
20.00

1.00
1.00

1.00
25%

Nos

474.00
43.00

1.00
1.00

1.00
25%

Nos

237.00
29.00

1.00
1.00

1.00
25%

Nos

26.00
0.00

1.00
1.00

0.14

Total rate per 1 Nos


B Basic rate as per ssr item 12.7MM DIA PVC
conection with brass union nut CP coated
Area allowence on labour charges
add overheads @

BMW-I48
BMW-I49
0.14

Total rate per 1 Nos


C Basic rate as per ssr item 12.7 MM ANGLE STOP
COCK first quality Indian make 400 gms Seiko
Area allowence on labour charges
add overheads @

BMW-E 05
BMW-E 06
0.14

Total rate per 1 Nos


D Basic rate as per ssr item 38.1 MM CP WASTE
COUPLING half or full thread 1st quality indian
make paryware or equivalent
Area allowence on labour charges

BMW-E31
BMW-E32

add overheads @

0.14

E Basic rate as per ssr item 31.75 MM dia PVC fleible


waste pipe of 914.4 mm length of first quality
Area allowence on labour charges

BMW-G05

add overheads @

0.14

Total rate per 1 Nos

Total rate per 1 Nos


TOTAL COST (A+B+C+D+E)
8

Supplying and fixing NP soap dish heavy type of approved make ISI quality with NP screws etc., c
cost and conveyance of all materials, labour charges for fixing etc., complete for finished item of work i
ssr item no 598
BMW-I28
1.00
Nos
243.00 1.00
Basic rate as per ssr item
BMW-I29
12.00 1.00
Area allowence on labour charges
25%
add overheads @
Total rate per 1 Nos

WS-Data

121 of 209

0.14

Sl.
No.
9

ITEM
COEFFI
UNIT
RATE
PER
CODE
CIENT
Supplying and fixing TV shape mirror with plastic frame of size 609.6mm x 457.2mm , plyw
screws 1st quality including cost and conveyance of all materials, labour charges etc., complete for finis
in all floors.
DESCRIPTION

BMW-I 105
BMW-I106

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

513.00
116.00

1.00
1.00

0.14

Total rate per 1 Nos


10

Supplying and fixing of 25.4mm dia , 609.6mm long aluminium anodized towel rods w
aluminium screws including cost and conveyance of all materials, labour charges etc., complete for finish
BMW-I 20
BMW-I 21

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

164.00
44.00

1.00
1.00

0.14

Total rate per 1 Nos


11

Supplying and fixing NP bib taps of size 12.70mm dia of Indian make Seiko or equivalent i
conveyance of all materials, labour charges etc., complete for finished item of work in all floors.
a) 300 grams
Basic rate as per ssr item
Area allowence on labour charges

BMW-E 09
BMW-E 10
add overheads @

1.00
25%

Nos

258.00
29.00

1.00
1.00

1.00
25%

Nos

407.00
29.00

1.00
1.00

0.14

Total rate per 1 Nos


b) 400 gms
Basic rate as per ssr item
Area allowence on labour charges

BMW-E 07
BMW-E 08
add overheads @

0.14

Total rate per 1 Nos


12

Supplying and fixing of SWR/ PVC pipes (as per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any IS
all special such as plain bends, off sets, door bends, single junctions, double junctions as per site require
PVC clamps if necessary with required number of Bombay nails including cost and conveyance of all
labour charges etc.complete for finished item of work at all floor levels. (APSS No. 1302 1319 & 1326)
(a) 90mm dia 3 Mts single socket
Basic rate as per ssr item
Area allowence on labour charges

BMW-G12
BMW
add overheads @

1.00 RM
25%

405.00
0.00

3.00
1.00

1.00 RM
25% RM

484.00
0.00

3.00
1.00

0.14

Total rate per 1 RMT


(b) 110mm dia 3 Mts single socket
BMW-G13
BMW

Basic rate as per ssr item


Area allowence on labour charges
add overheads @
Total rate per 1 RMT

WS-Data

122 of 209

0.14

Sl.
No.

13

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Supplying & fixing Ashirvad/Astral flow guard for equivalent CPVC Pipes with fittings in ground or on wall
tees, elbows, bends, reducers, couplings, running joints, union flanges, unions etc. with necessary exca
of soils except rock requiring blasting, refilling, chiselling masonry walls and making good the walls & flo
surface and fixing MS clamps on TW blocks on walls including cost and conveyance of all materials an
complete for finished item of work.

a) 15.90 mm dia CPVC SDR 13.50


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 220
BMW-I 415

add overheads @

1.00 Rmt
25% Rmt

141.00
31.00

1.00
1.00

1.00 Rmt
25% Rmt

160.00
31.00

1.00
1.00

1.00 Rmt
25% Rmt

212.00
31.00

1.00
1.00

1.00 Rmt
25% Rmt

360.00
31.00

1.00
1.00

1.00 Rmt
25% Rmt

525.00
31.00

1.00
1.00

0.14

Total rate per 1 RMT


b) 22.20 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 221
BMW-I 415

add overheads @

0.14

Total rate per 1 RMT


c) 28.60 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 222
BMW-I 415

add overheads @

0.14

Total rate per 1 RMT

D 41.30 mm dia CPVC SDR 13.50


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 224
BMW-I 415

add overheads @

0.14

Total rate per 1 RMT


E 54 mm dia CPVC SDR 13.50
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 225
BMW-I 415
add overheads @

0.14

Total rate per 1 RMT


14

Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make hea
cost and conveyance of all materials , labour charges etc. complete for finished item of work.
15 mm dia nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F21
BMW-F22
add overheads @

Total rate per 1 No

WS-Data

123 of 209

0.14

1.00
25%

Nos

636.00
44.00

1.00
1.00

Sl.
No.
15

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Supplying and fixing PPR Ball valve as per ISI Class - I , Indian make heavy type including cost and
materials , labour charges etc. complete for finished item of work.
a) 20mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 403
BMW-F20
add overheads @

Total rate per 1 No


b) 25mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

Nos

186.00
44.00

1.00
1.00

1.00
25%

Nos

245.00
44.00

1.00
1.00

1.00
25%

Nos

526.00
67.00

1.00
1.00

1.00
25%

Nos

613.00
90.00

1.00
1.00

1.00
25%

Nos

992.00
112.00

1.00
1.00

0.14

BMW-I 404
BMW-F18
add overheads @

1.00
25%

0.14

Total rate per 1 No

c) 40 mm PPR Ball valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 406
BMW-F26
add overheads @

0.14

Total rate per 1 No

d) 50 mm PPR Ball valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-I 407
BMW-F28
add overheads @

0.14

Total rate per 1 No


e) 63 mm PPR Ball valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-I 408
BMW-F30
add overheads @

0.14

Total rate per 1 No


16

Supply and fixing of white glazed flat back bowl urinals of size 440 mm x 265 mm x 315 mm with inte
mm fixied with screws complete inidan make (HS W/Parry/Neycer) conforming to IS 2556 -1995 as appro
in - charge 12.7 mm PVC connection with brass plumber union nuts CM Coated. including 12.70 mm pus
of approved make including supply & fixing 31.75 m dia PVC flexible waser pipe of 914.40 mm lenght of
and conveyance of all materials to site labour charges etc., complete for finished item of work for all floor
BMW-D33
BMW-D36

Basic rate as per ssr item


Area allowence on labour charges
add overheads @
Total rate per 1 No

WS-Data

124 of 209

0.14

1.00
25%

Nos

930.00
150.00

1.00
1.00

Sl.
No.
17

ITEM
COEFFI
UNIT
RATE
PER
CODE
CIENT
Construction of brick masonry support for GI pipe of size 304.80mm x 228.60mm x 228.60
prop including plastering and finishing with 12mm thick in CM (1:5) including cost and conveyance of al
labour charges etc. complete
BMW-i63
1.00
Nos
76.00 1.00
Basic rate as per ssr item
BMW-i64
22.00 1.00
Area allowence on labour charges
25%
DESCRIPTION

add overheads @

0.14

Total rate per 1 No


18

Supplying and fixing 150.00mmx100.00mm SWG gully trap 1st class confirming to ISI 651 & 4127wi
constructing single brick masonry wall chamber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:
plastering 12mm thk. in CM (1:4) prop. both inside and outside surfaces and fitted with 304.8MM X 288
frame and hinged cover as directed by Engineer-in-charge including cost and conveyance of all materi
charges etc., complete for finished item of work.
BMW-A72
1.00
Nos
568.00 1.00
Basic rate as per ssr item
BMW-A74
30.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 No


18

Supplying and fixing CI Nahani traps 100 mm dia Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI mar
IS:1729-1979 with C.P. Grating fixing with white cement as per site requirements with standard prac
including cost and conveyance of all materials to site, labour charges etc., complete for finished item of w
BMW-G
114
1.00
Nos
112.00 1.00
Basic rate as per ssr item Nahany trap
BMW-C42
59.00 1.00
Area allowence on labour charges
25%
add overheads @

Total rate per 1 No


Basic rate as per ssr item Nahany trap cover
Area allowence on labour charges
add overheads @

0.14
BMW-G
121
BMW-I13

1.00
25%

Nos

24.00
19.00

1.00
1.00

0.14

Total rate per 1 No


Total cost (A +B)
19

Supplying and fixing 580 mm x 440 mm long Orissa pan white glazed Water Closet 1st qualityISI mar
IS:2556-Part-3-1981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, CC sq
fixing 12.70mm dia NP Push cock 1st quality , P trap or S trap of Indian W.C. shall be encased on C
alround well above the joint to stop leakage at the joint etc., complete including cost and conveyance
site, cost of CC bed, labour charges and seigniorage charges etc., complete for finished item of work.
BMW-d04
BMW-d06

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

0.14

add overheads @

BMW-d09
0.14

Total rate per 1 No


Providing brick masonry seat
Total cost (A +B)

WS-Data

125 of 209

1.00
25%

Nos

1584.00
377.00

1.00
1.00

1.00

Nos

328.00

1.00

Sl.
No.
20

ITEM
COEFFI
UNIT
RATE
PER
CODE
CIENT
Supplying and fixing 584.20mm long Orissa pan white glazed Water Closet 1st qualityISI marked confi
Part-3-1981 with "P" or "S" trap Hindware / Parryware / Neycer with brick masonry seat, CC squatting
Fixing 10 Litres capacity Single Flush white PVC low level flushing system parryware, slimline with int
and short bend including cost and conveyance of all materials to site, all labour charges, sales and o
materials etc., complete for finished item of work for all floors.
DESCRIPTION

Basic rate as per ssr item


Area allowence on labour charges
Supply and Fixing 10 Litres capacity Single Flush
white PVC low level flushing system parryware,
slimline
Initial
cost SSR item
No 319
Area allowence
on labour
charges
Providing brick masonry seat
add overheads @
Total rate per 1 No including flush tank 10
21

BMW-d04
BMW-d06

1.00
25%

Nos

1584.00
377.00

1.00
1.00

BMW-G08

1.00

Nos

1455.00

1.00

BMW-d09

25%
1.00

Nos

0.00
328.00

1.00
1.00

0.14

Providing and placing on terrace (at all floor levels)polyetheylene water storage tank with double laye
and manufacture with cover and suitable locking arrangement and making necessary holes for inlet and
flow pipes but without fittings and base support for tanks
BMW-g01
BMW-g02

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Lit

6.00
1.00

1.00
1.00

0.14

Total rate per 1 Ltr


22

Supplying and fixing 609.6 mm x 457.2 mm x 254 mm RCC terrazo finished sink (or constructed at sit
thick) brass plug and chain incluiding CI cantilever brackets, 31.75 mm dia PVC flexible waste pipe 914
1st quality including cost and conveyance fo all materials labour charges etc., complete for finished item
BMW-D40
BMW-D41

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

791.00
255.00

1.00
1.00

0.14

Total rate per 1 No


23

Supply and fixing of stainless steel sink with drain board of size 914.4 mm x 457.2 mm 1 mm thick o
cantilever barackets with including 32 mm cP waste coupling supply & fixing 31.75 mm dia PVC flexi
914.4 mm longth of 1st quality incluidng chasing brick masonry wall and making good restoring to orig
complete for finished item of work in all floors SSR No.692
BMW-I119
1.00
Nos 7552.00 1.00
Basic rate as per ssr item
BMW-I120
506.00 1.00
Area allowence on labour charges
25%
add overheads @

24

Total rate per 1 No


Supply & Fixing of 22" dia RCC Cover for manhole with nominal reinforecement 3" thick with hookcs fo
cost and conveyance of all materials, labour charges etc., complete for finished tiem of work
BMW-I130
BMW-I120

Basic rate as per ssr item


Area allowence on labour charges
add overheads @
Total rate per 1 No

WS-Data

0.14

126 of 209

0.14

1.00
25%

Nos

734.00
506.00

1.00
1.00

Sl.
No.
25

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Construction of Perforated Dry Brick Masonry without using CM and keeping vertical dry joints of 15 to 2
by the Engineer in Charge including cost and conveyance of all amterials to site seignorage charge
taxes, all labour charges etc., complete item of work for Soak Pit.
Cost of Bricks

654 Nos.

Deduct 15% for perforation


Ist class Brick layer
Man Mazdoor
Women Mazdoor

98.10 Nos.
1.28 Each
0.64 Each
1.93 Each

5384.86

1000

5384.86 -1000
525.00
1
400.00
1
400.00
1

Rate per Cum


26

Supply and fixing of PVC pipes 110 mm Single socket ISI marked confirming to IS: 1729 - 1979 of re
cement caulked joints and paintaed black with japan paint and fixing with necessary woden blocks fixe
walls in CM (1.5:1) including fixing of MS clamps of necessary size and required no of Bombay nails
including cost and conveyance of all materials to site all labour charges sales and other taxes on a
complete for finished item of work all Floors
BMW-G 13
BMW-CO7

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

484.00
227.00

1.00
1.00

0.14

Total rate per 1 No


27

Supply and fixing of PVC pipes 75 mm Single socket ISI marked confirming to IS: 1729 - 1979 of rep
cement caulked joints and paintaed black with japan paint and fixing with necessary woden blocks fixe
walls in CM (1.5:1) including fixing of MS clamps of necessary size and required no of Bombay nails
including cost and conveyance of all materials to site all labour charges sales and other taxes on a
complete for finished item of work all Floors
BMW-G11
1.00
Nos
255.00 1.00
Basic rate as per ssr item
BMW-CO7
227.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 No


28

Constructing 457.2mm x 457.2mm (1'-6" x 1'-6") brick in CM (1:6) prop. Masonry inspection chamber u
0") and fitted with light weight 457.2mm x 457.2mm (1'-6" x 1"-6") frame and cover of 20kg., in
convenyance of all materials to site, all labour charges, sales and otehr taxes on all materials etc., com
item of work
BMW-B06
1.00
Nos 3825.00 1.00
Basic rate as per ssr item
0.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 No


29

Supply and fixing of 100 mm dia CI Vent pipe of 3 mts lenth fitted with AC cowl and mosquito proof wi
cost and conveyance of all materials to site complete for finished item of work.
BMW-H05
BMW-

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

2247.00
0.00

1.00
1.00

0.14

Total rate per 1 No


30

WS-Data

Supply and Fixing of Vent Cowls 90 mn dia with all necessary requirements including all operational , in
other taxes and all labour charges etc., complete including cost and convenyance of all materials com
item of work for all Floors.

127 of 209

Sl.
No.

ITEM
COEFFI
UNIT
CODE
CIENT
BMW-G 99
1.00
Nos
BMW-I37
25%

DESCRIPTION
Basic rate as per ssr item
Area allowence on labour charges

31

RATE
17.00
14.00

PER
1.00
1.00

0.14
add overheads @
Total rate per 1 No
Supply and Fixing of vent Cowls 63 mn dia with all necessary requirements including all operational , in
other taxes and all labour charges etc., complete including cost and convenyance of all materials com
item of work for all Floors.
BMW-G 97
BMW-I39

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

9.00
11.00

1.00
1.00

0.14

Total rate per 1 No


32

Construction of 50.8mm thick RCM Baffle wall with 2.267 Kg steel and rabit wire mesh in CM (1:3) prop: w
in neat cement in septic tank including cost and convenyance of all materials to site, seigonarage charg
taxes on all materials , and all labour charges etc., complete for finished item of work.
BMW-I95
BMW-I97

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

251.00
44.00

1.00
1.00

0.14

Total rate per 1 No


33

Supply and Fixing of C.I. (Spun ) Soil waste and ventilating pipe of 3.00 Mt length of 100mm dia with
vent over septic tank including cost and convenyance of all materials to site, all labour charges sales a
on all materials etc., complete for finished item of work.
BMW-H05

Basic rate as per ssr item


Area allowence on labour charges
Basic rate as per ssr item
Area allowence on labour charges

BMW-I36
BMW-I37
add overheads @

1.00
25%
1.00
25%

Nos
Nos

2247.00
0.00
71.00
14.00

1.00
1.00
1.00
1.00

0.14

Total rate per 1 No


34

Supply and Fixing of 914.4mm x 457.2mm Light Weight CI Manhole Frame and Cover (30 Kgs) complete
of work including cost and conveyance of all materials to site, all labour charges, sales and other taxes
etc., complete for finished item of work. Initial cost SSR item No 656
BMW-I86
BMW-I88

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

2020.00
140.00

1.00
1.00

0.14

Total rate per 1 No


35

Supply and Fixing of CI Steps for Septic Tank / Manhole complete for finished item of work including cos
of all materials to site, all labour charges, sales and other taxes on all materials etc., complete for finishe
BMW-I89
BMW-I90

Basic rate as per ssr item


Area allowence on labour charges
add overheads @
Total rate per 1 No

WS-Data

128 of 209

0.14

1.00
25%

Nos

65.00
11.00

1.00
1.00

Sl.
No.
36

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Supply and Fixing 10 Litres capacity Single Flush white PVC low level flushing system parryware, slim
components and short bend including cost and conveyance of all materials to site, all labour charges
taxes on all materials etc., complete for finished item of work for all floors. Initial cost SSR item No 342
BMW-G08

Basic rate as per ssr item


Area allowence on labour charges
add overheads @

1.00
25%

Nos

1455.00
0.00

1.00
1.00

0.14

Total rate per 1 No


37

Supply & Fixing 4" dia (110 mm) UPVC Plug (Door) bends 1st quality ISI marked conforming to IS : 1729caulked joints and fixing as per site requirements with standard practice including cost and conveyance
site, all labour charges, sales and other taxes on all materials etc., complete for finished item of work f
cost SSR item No 74
BMW-G 60
1.00
Nos
107.00 1.00
Basic rate as per ssr item
BMW-C14
72.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 No


38

Supply & Fixing 3" dia (75 mm) UPVC Plug (Door) bends 1st quality ISI marked conforming to IS with
joints and fixing as per site requirements with standard practice including cost and conveyance of all m
labour charges, sales and other taxes on all materials etc., complete for finished item of work for all floor
Initial cost SSR item No 73
BMW-C11
1.00
Nos
367.00 1.00
Basic rate as per ssr item
BMW-C14
72.00 1.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1 No


39

Manufacture, supply, & delivery of 50mm outer dia HDPE pipes conforming to IS 4984 - 1995 at 6Kg/Sq
and conveyance of all materials to site, all labour charges, sales and other taxes on all materials e
finished item of and ,Laying jointing of HDPE pipes as per BIS No. 7634 part -II/75 and specials
excavation of trenches up to 0.5 mts depth in all soils except rock requires blasting and refilling trenche
jointing of pipes as per ssr ite
Basic rate as per ssr item
TABLE
16(1) page
52
1.00
RMT
67.00 1.00
labour charges for laying and jointing
12
(b)
page 5 of
1 RMT
31.00
1
PH ssr
31.00
Area allowence on labour charges
25%
add overheads @

0.14

Total rate per 1Rmt


40

Supply and fixing of European Water Closet of 1st quality conforming to IS: 2556-Part-2-1973 of Hin
Parryware make white glazed with 'P' trap and Supply and fixing best indian make plastic seat and lid fo
closets with rubber or plastic buffers as per IS 2548 -1996 with 10 Litres capacity Single Flush white PVC
system parryware, slimline with internal components and short bend including cost and conveyance of al
all labour charges, sales and other taxes on all materials etc., complete for finished item of work for all fl
Basic rate as per ssr item
Plastic seat & lid as per IS 2548-1996
Supply and Fixing 10 Litres capacity Single Flush
white PVC low level flushing system parryware,
slimline

WS-Data

129 of 209

BMW-d14
BMW-d 16

1.00
1.00

Nos
Nos

1964.00
981.00

1.00
1.00

BMW-G08

1.00

Nos

1455.00

1.00

Sl.
No.

ITEM
CODE

DESCRIPTION
add overheads @

COEFFI
UNIT
CIENT

RATE

PER

0.14

Total rate per 1Nos


41

Supply and Fixing 12.7 mm dia NP push cock Ist quality including cost and conveyance of all materials
charges, sales and other taxes on all materials etc., complete for finished item of work for all floors.
Basic rate as per ssr item
add overheads @

BMW-E 29
0.14

1.00

Nos

271.00

1.00

Total rate per 1 Nos


42

Supply and Fixing angle stop cock 12.7 mm dia first quality Indian Make heavy duty Seiko/ Senior/ N
including cost and conveyance of all materials to site, labour charges etc., complete for finished item
BMW E.05
Basic rate as per ssr item
add overheads @

BMW-E 01
0.14

1.00

Nos

474.00

1.00

Total rate per 1Nos


43

44

Supply and FixingSupplying and fixing CP Jollys of approved make with complete including cost and
BMW-I 69
1.00
Nos
50.00 1.00
Basic rate as per ssr item
0.14
add overheads @
Total rate per 1Nos

Supplying & fixing GI pipe Medium Grade properties & weight as per IS 1239 ISI mark with GI fittin
on wall including cost of tees, elbows, bends, reducers, couplings, running joints, union flanges, unions e
necessary excavation in all types of soils except rock requiring blasting, refilling, chiselling masonry walls
good the walls & floors to the original surface and fixing MS clamps on TW blocks on walls including cost
of all materials and labour charges complete for finished item of work.
a) 15mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F79
BMW-F80

204.00
41.00

1.00
1.00

227.00
41.00

1.00
1.00

297.00
41.00

1.00
1.00

466.00
44.00

1.00
1.00

14.00%

add overheads @
Total rate per 1 RMT
b) 20mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

1.00 Rmt
25% Rmt

BMW-F81
BMW-F82

1.00 Rmt
25% Rmt
14.00%

add overheads @
Total rate per 1 RMT
c) 25mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F83
BMW-F84

1.00 Rmt
25% Rmt
14.00%

add overheads @
Total rate per 1 RMT
d) 32mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F87
BMW-F88
add overheads @

WS-Data

130 of 209

1.00 Rmt
25% Rmt
14.00%

Sl.
No.

ITEM
CODE

DESCRIPTION

COEFFI
UNIT
CIENT

RATE

PER

Total rate per 1 RMT


e) 40mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F87
BMW-F88

1.00 Rmt
25% Rmt

466.00
44.00

1.00
1.00

503.00
67.00

1.00
1.00

892.00
67.00

1.00
1.00

14.00%

add overheads @
Total rate per 1 RMT
f) 50mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F89
BMW-F90

1.00 Rmt
25% Rmt
14.00%

add overheads @
Total rate per 1 RMT
g) 65mm Nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F91
BMW-F90

1.00 Rmt
25% Rmt
14.00%

add overheads @
Total rate per 1 RMT
45

Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make hea
cost and conveyance of all materials , labour charges etc. complete for finished item of work.
15 mm dia nominal bore
Basic rate as per ssr item
Area allowence on labour charges

BMW-F21
BMW-F22
add overheads @

1.00
25%

Nos

636.00
44.00

1.00
1.00

0.14

Total rate per 1 No


46

Supplying and fixing Gunmetal Gate ( GM peet ) valve as per IS-778 Class - I , Indian make heavy type i
conveyance of all materials , labour charges etc. complete for finished item of work.
a) 20mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-F19
BMW-F20
add overheads @

1.00
25%

Nos

858.00
44.00

1.00
1.00

1.00
25%

Nos

1233.00
44.00

1.00
1.00

1.00
25%

Nos

2533.00
67.00

1.00
1.00

0.14

Total rate per 1 No


b) 25mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-F17
BMW-F18
add overheads @

0.14

Total rate per 1 No


c) 40mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

WS-Data

BMW-F25
BMW-F26

131 of 209

Sl.
No.

DESCRIPTION
add overheads @

ITEM
COEFFI
UNIT
CODE
CIENT
0.14

RATE

PER

Total rate per 1 No

d) 50mm GM peet valve


Basic rate as per ssr item
Area allowence on labour charges

BMW-F27
BMW-F28
add overheads @

1.00
25%

Nos

3711.00
90.00

1.00
1.00

1.00
25%

Nos

5730.00
112.00

1.00
1.00

0.14

Total rate per 1 No


e) 65 mm GM peet valve
Basic rate as per ssr item
Area allowence on labour charges

BMW-F29
BMW-F30
add overheads @

0.14

Total rate per 1 No

,Executive Engineer
APEWIDC,
ANANTAPURAMU

WS-Data

,Dy.Executive Engineer
APEWIDC, ANANTAPURAMU

132 of 209

,Assistan
APEWIDC,

ng under R&R Centre to MPUPS In Various components at


ddapappur (M) in Ananthapuramu (Dist)

PLY AND SANITARY DATAS

UNIT Amount (Rs.)

testing SWG SP-1 pipes of ISI make confirming to IS 1651 & 4127 1st
prop. including excavation of trenches and socket pits in any soil (except
ng and tamping to the required slope including cost and conveyance of all
ed item of work (APSS NO 1301 & 1318)
Rmt
0.00

408.00
58.00
466.00
63.45
529.45

Rmt
0.00

680.00
72.00
752.00
102.38
854.40

Rmt
0.00

466.00
72.00
538.00
73.25
611.25

Rmt
0.00

614.00
58.00
672.00
91.49
763.50

asonry inspection chamber as per IS - 4111: Part-1:1986 with cement


225 mm thick from approved source having a minimum crushing strength
mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
ing pits up to a depth of 904 mm (3'-0") in all sorts of soils (exculding
thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and channel 100
ncluding cost and conveyance of all materials like cement, sand, bricks,
on all materials and all incidental and operational, labour charges like
t charges, curing etc., complete for finished item of work as per Standard

WS-Data

Nos

6237.00

0.00

0.00
6237.00
849.17
7086.20

133 of 209

UNIT Amount (Rs.)

asonry inspection chamber as per IS - 4111: Part-1:1986 with cement


225 mm thick from approved source having a minimum crushing strength
mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
ating pits up to a depth of 1524 mm (5'-0") in all sorts of soils
:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
tion and including cost and conveyance of all materials like cement, sand,
harges on all materials and all incidental and operational, labour charges
nry, lift charges, curing etc., complete for finished item of work as per
Nos
0.00

10181.00
0.00
10181.00
1386.14
11567.15

ock masonry inspection chamber as per IS - 4111: Part-1:1986 with


225mm thick from approved source having a minimum crushing strength
t mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
ating pits up to a depth of 1524 mm (5'-0") in all sorts of soils
:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
tion and including cost and conveyance of all materials like cement, sand,
harges on all materials and all incidental and operational, labour charges
nry, lift charges, curing etc., complete for finished item of work as per
Nos
0.00

10590.00
0.00
10590.00
1441.83
12031.85

ock masonry inspection chamber as per IS - 4111: Part-1:1986 with


225mm thick from approved source having a minimum crushing strength
t mortar 1:3 prop; thick both inside and outside fitted with 20 dia RCC
ating pits up to a depth of 1524 mm (3'-0") in all sorts of soils
:8) 150 mm thick using 40 mm HBG Metal and P.C.C. 1:2:4 benching and
tion and including cost and conveyance of all materials like cement, sand,
harges on all materials and all incidental and operational, labour charges
nry, lift charges, curing etc., complete for finished item of work as per
Nos
0.00

6730.00
0.00
6730.00
916.29
7646.30

m SWG gully trap 1st class confirming to ISI 651 & 4127 with CI grating
mber of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed,
) CI frame and hinged cover and plastering 12mm thk. in CM (1:4) prop.
ost and conveyance of all materials to site, labour charges etc., complete
Nos
0.00

WS-Data

568.00
7.50
575.50
78.35
653.85

134 of 209

UNIT Amount (Rs.)

k Wash Hand Basin (HSW/Parryware/ Neycer) 1st quality conforming to


ith waste fittings like rubber plug, chain, 32 mm nominal size C.P. Fitting
-1979 and fitted with 15 mm nominal bore Chromium Plated Pillar Tap of
r equivalent complete with standard CI brackets including wooden block ,1
nuts CP coated , 1 No.12.70mm NP bib tap 300 gms Seiko or equivalent
site, labour charges etc. complete for finished item of work
Nos
0.00

1782.00
94.25
1876.25
255.45
2131.70

Nos
0.00

102.00
5.00
107.00
14.57
121.60

Nos
0.00

474.00
10.75
484.75
66.00
550.75

Nos
0.00

237.00
7.25
244.25
33.25
277.50

Nos
0.00

26.00
0.00
26.00
3.54
29.55
3111.10

Rs

ype of approved make ISI quality with NP screws etc., complete including
arges for fixing etc., complete for finished item of work in all floors as per
Nos
0.00

WS-Data

243.00
3.00
246.00
33.49
279.50

135 of 209

UNIT Amount (Rs.)

plastic frame of size 609.6mm x 457.2mm , plywood back with NP


e of all materials, labour charges etc., complete for finished item of work
Nos
0.00

513.00
29.00
542.00
73.79
615.80

609.6mm long aluminium anodized towel rods with brackets and


e of all materials, labour charges etc., complete for finished item of work.
Nos
0.00

164.00
11.00
175.00
23.83
198.85

2.70mm dia of Indian make Seiko or equivalent including cost and


complete for finished item of work in all floors.

Nos
0.00

258.00
7.25
265.25
36.11
301.40

Nos
0.00

407.00
7.25
414.25
56.40
470.65

per ISI standards) 4 Kg/Sq.cm. Prince/sudhakar or any ISI brand and fixing
nds, single junctions, double junctions as per site requirement, fixing with
of Bombay nails including cost and conveyance of all materials to site,
work at all floor levels. (APSS No. 1302 1319 & 1326)

WS-Data

RMT
0.00

135.00
0.00
135.00
18.38
153.40

RMT
RM

161.33
0.00
161.33
21.97
183.35

136 of 209

UNIT Amount (Rs.)

equivalent CPVC Pipes with fittings in ground or on wall including cost of


g joints, union flanges, unions etc. with necessary excavation in all types
hiselling masonry walls and making good the walls & floors to the original
walls including cost and conveyance of all materials and labour charges

Rmt

141.00
7.75
148.75
20.25
169.00

Rmt
Rmt

160.00
7.75
167.75
22.84
190.60

RMT
Rmt

212.00
7.75
219.75
29.92
249.70

RMT
Rmt

360.00
7.75
367.75
50.07
417.85

RMT
Rmt

525.00
7.75
532.75
72.53
605.30

peet ) valve as per IS-778 Class - I , Indian make heavy type including
arges etc. complete for finished item of work.
Nos
0.00

WS-Data

636.00
11.00
647.00
88.09
735.10

137 of 209

UNIT Amount (Rs.)

SI Class - I , Indian make heavy type including cost and conveyance of all
hed item of work.
Nos
0.00

186.00
11.00
197.00
26.82
223.85

Nos
0.00

245.00
11.00
256.00
34.85
290.85

Nos
0.00

526.00
16.75
542.75
73.90
616.65

Nos
0.00

613.00
22.50
635.50
86.52
722.05

Nos
0.00

992.00
28.00
1020.00
138.87
1158.90

l urinals of size 440 mm x 265 mm x 315 mm with internal rim flushing


S W/Parry/Neycer) conforming to IS 2556 -1995 as approved be Engineer plumber union nuts CM Coated. including 12.70 mm push cock 1st qulaity
5 m dia PVC flexible waser pipe of 914.40 mm lenght of 1st including cost
arges etc., complete for finished item of work for all floors
Nos
0.00

WS-Data

930.00
37.50
967.50
131.73
1099.25

138 of 209

UNIT Amount (Rs.)

GI pipe of size 304.80mm x 228.60mm x 228.60 mm in CM (1:8)


m thick in CM (1:5) including cost and conveyance of all materials and all
Nos
0.00

76.00
5.50
81.50
11.10
92.60

G gully trap 1st class confirming to ISI 651 & 4127with CI grating and
of size 20" x 14" x 12 in CM (1:6) prop. Over a CC (1:5:10)prop. bed, and
de and outside surfaces and fitted with 304.8MM X 288.6 MM (12"X9") CI
er-in-charge including cost and conveyance of all materials to site, labour
Nos
0.00

568.00
7.50
575.50
78.35
653.85

a Inlet- 75 mm (3") outlet pipe - 4 Kgs 1st quality ISI marked conforming to
e cement as per site requirements with standard practice for all floors
site, labour charges etc., complete for finished item of work.
Nos
0.00

Nos
0.00

112.00
14.75
126.75
17.26
144.05
24.00
4.75
28.75
3.91
32.70
176.75

Orissa pan white glazed Water Closet 1st qualityISI marked confirming to
are / Parryware / Neycer with brick masonry seat, CC squatting plate and
P trap or S trap of Indian W.C. shall be encased on CC (1:2:4) 150mm
the joint etc., complete including cost and conveyance of all materials to
age charges etc., complete for finished item of work.
Nos
0.00

Nos

WS-Data

1584.00
94.25
1678.25
228.49
1906.75
328.00
44.66
2279.41

139 of 209

UNIT Amount (Rs.)

n white glazed Water Closet 1st qualityISI marked confirming to IS:2556ryware / Neycer with brick masonry seat, CC squatting plate. Supply and
C low level flushing system parryware, slimline with internal components
of all materials to site, all labour charges, sales and other taxes on all
k for all floors.
Nos
0.00

1584.00
94.25

Nos

1455.00

0.00
Nos

0.00
328.00
3461.25
471.25
3932.50

vels)polyetheylene water storage tank with double layer approved brand


g arrangement and making necessary holes for inlet and outlets and over
for tanks
Lit
0.00

6.00
0.25
6.25
0.85
7.10

254 mm RCC terrazo finished sink (or constructed at site with 50.80 mm
ver brackets, 31.75 mm dia PVC flexible waste pipe 914.4 mmm length of
materials labour charges etc., complete for finished item of work
Nos
0.00

791.00
63.75
854.75
116.37
971.15

ain board of size 914.4 mm x 457.2 mm 1 mm thick of indian make on


waste coupling supply & fixing 31.75 mm dia PVC flexible waste pipe of
g brick masonry wall and making good restoring to original srufaces etc.,
SR No.692
Nos
7552.00
0.00
126.50
7678.50
1045.43
8723.95
ole with nominal reinforecement 3" thick with hookcs for lfifting including
rges etc., complete for finished tiem of work
Nos
0.00

WS-Data

734.00
126.50
860.50
117.16
977.70

140 of 209

UNIT Amount (Rs.)

thout using CM and keeping vertical dry joints of 15 to 20mm as directed


d conveyance of all amterials to site seignorage charges, sales and other
work for Soak Pit.
Nos.

3521.70

Nos.
Each
Each
Each

-528.25
672.00
256.00
772.00
4693.44

e socket ISI marked confirming to IS: 1729 - 1979 of reputed make with
japan paint and fixing with necessary woden blocks fixed in the masoery
ps of necessary size and required no of Bombay nails etc., complete
to site all labour charges sales and other taxes on all materials etc.,,
Nos
0.00

484.00
56.75
540.75
73.62
614.40

socket ISI marked confirming to IS: 1729 - 1979 of reputed make with
japan paint and fixing with necessary woden blocks fixed in the masoery
ps of necessary size and required no of Bombay nails etc., complete
to site all labour charges sales and other taxes on all materials etc.,,
Nos
0.00

255.00
56.75
311.75
42.44
354.20

") brick in CM (1:6) prop. Masonry inspection chamber upto 914.4mm (3'57.2mm (1'-6" x 1"-6") frame and cover of 20kg., including cost and
charges, sales and otehr taxes on all materials etc., complete for finished
Nos
0.00

3825.00
0.00
3825.00
520.77
4345.80

f 3 mts lenth fitted with AC cowl and mosquito proof wire mesh including
plete for finished item of work.
Nos
0.00

2247.00
0.00
2247.00
305.93
2552.95

all necessary requirements including all operational , incidental sales and


te including cost and convenyance of all materials complete for finished

WS-Data

141 of 209

UNIT Amount (Rs.)


Nos
0.00

17.00
3.50
20.50
2.79
23.30
all necessary requirements including all operational , incidental sales and
te including cost and convenyance of all materials complete for finished
Nos
0.00

9.00
2.75
11.75
1.60
13.35

th 2.267 Kg steel and rabit wire mesh in CM (1:3) prop: with fine rendering
convenyance of all materials to site, seigonarage charges sales and othe
c., complete for finished item of work.
Nos
0.00

251.00
11.00
262.00
35.67
297.70

d ventilating pipe of 3.00 Mt length of 100mm dia with double socket for
yance of all materials to site, all labour charges sales and all other taxes
of work.
Nos
0.00
Nos
0.00

2247.00
0.00
71.00
3.50
2321.50
316.07
2637.60

t Weight CI Manhole Frame and Cover (30 Kgs) complete for finished item
aterials to site, all labour charges, sales and other taxes on all materials
ost SSR item No 656
Nos
0.00

2020.00
35.00
2055.00
279.79
2334.80

Manhole complete for finished item of work including cost and conveyance
and other taxes on all materials etc., complete for finished item of work.
Nos
0.00

WS-Data

142 of 209

65.00
2.75
67.75
9.22
77.00

UNIT Amount (Rs.)

sh white PVC low level flushing system parryware, slimline with internal
conveyance of all materials to site, all labour charges, sales and other
item of work for all floors. Initial cost SSR item No 342
Nos
0.00

1455.00
0.00
1455.00
198.10
1653.10

or) bends 1st quality ISI marked conforming to IS : 1729-1979 with cement
s with standard practice including cost and conveyance of all materials to
n all materials etc., complete for finished item of work for all floors Initial
Nos
0.00

107.00
18.00
125.00
17.02
142.05

or) bends 1st quality ISI marked conforming to IS with cement caulked
tandard practice including cost and conveyance of all materials to site, all
erials etc., complete for finished item of work for all floors
Nos
0.00

367.00
18.00
385.00
52.42
437.45

dia HDPE pipes conforming to IS 4984 - 1995 at 6Kg/Sqcm. including cost


bour charges, sales and other taxes on all materials etc., complete for
pipes as per BIS No. 7634 part -II/75 and specials /fittings including
l soils except rock requires blasting and refilling trenches after laying and

RMT
RMT

67.00
31.00
7.75
105.75
14.40
120.15

f 1st quality conforming to IS: 2556-Part-2-1973 of Hindware /Neycer of


Supply and fixing best indian make plastic seat and lid for European water
548 -1996 with 10 Litres capacity Single Flush white PVC low level flushing
ents and short bend including cost and conveyance of all materials to site,
materials etc., complete for finished item of work for all floors.

WS-Data

Nos
Nos

1964.00
981.00

Nos

1455.00

143 of 209

UNIT Amount (Rs.)


4400.00
599.06
4999.06

t quality including cost and conveyance of all materials to site, all labour
etc., complete for finished item of work for all floors.
Nos

271.00
36.90
307.90

a first quality Indian Make heavy duty Seiko/ Senior/ Nice or equivalent
to site, labour charges etc., complete for finished item of work.
178 Nos

474.00
64.54
538.54

of approved make with complete including cost and conveyance of all


Nos
50.00
6.81
56.81

operties & weight as per IS 1239 ISI mark with GI fittings in ground or
ducers, couplings, running joints, union flanges, unions etc. with
rock requiring blasting, refilling, chiselling masonry walls and making
d fixing MS clamps on TW blocks on walls including cost and conveyance
finished item of work.

WS-Data

Rmt

204.00
10.25
214.25
30.00
244.25

Rmt
Rmt

227.00
10.25
237.25
33.22
270.50

RMT
Rmt

297.00
10.25
307.25
43.02
350.30

RMT
Rmt

466.00
11.00
477.00
66.78

144 of 209

UNIT Amount (Rs.)


543.80

RMT
Rmt

466.00
11.00
477.00
66.78
543.80

RMT
Rmt

503.00
16.75
519.75
72.77
592.55

RMT
Rmt

892.00
16.75
908.75
127.23
1036.00

peet ) valve as per IS-778 Class - I , Indian make heavy type including
arges etc. complete for finished item of work.

Nos
0.00

636.00
11.00
647.00
88.09
735.10

valve as per IS-778 Class - I , Indian make heavy type including cost and
complete for finished item of work.

WS-Data

Nos
0.00

858.00
11.00
869.00
118.31
987.35

Nos
0.00

1233.00
11.00
1244.00
169.37
1413.40

Nos
0.00

2533.00
16.75
2549.75

145 of 209

UNIT Amount (Rs.)


347.15
2896.90

Nos
0.00

3711.00
22.50
3733.50
508.32
4241.85

Nos
0.00

5730.00
28.00
5758.00
783.95
6541.95

,Assistant Engineer
APEWIDC, TADIPATRI

WS-Data

146 of 209

DATAS FOR DOORS AND WINDOWS


Name of work :Construction of School building under R&R Centre to MPUPS In Various
components at Chinnayakkaluru (V) of Peddapappur (M) in Ananthapuramu (Dist)
S.
No

Description

Qty

Rate (Rs.)

Per Unit

Amount

1 S & F of MS Door (Double shutter) by using alround frame of MS 'L' angle


35x35x5mm, for shutter by using 25x25x4mm covered by 18gauge MS sheet, rear
side supports with MS flat 25x3mm of 0.55mt. long - 6Nos, 2.10mts-2nos and
25x25x25x5mm tee centre 0.55ms -1no for each shutter iron fixtures like 'Z' Hold
fasts - 35x35x5mm MS 'L' angle - 0.20m long - 6 Nos, MS Aldrops 300x16mm - 2
Nos, 125mm long Butt Hinges - 6Nos, MS Door Handle 150mm long - 3 Nos, MS
Tower bolts of 200long size - 3Nos including c/c of all m/l, fabrication charges with
one coat of red oxide, etc., complete. of size 1.22x2.13 Mt.
Frame MS 'L' angle 35x35x5mm
(1.22+2.13)2 x 2.60 Kg/Rmt
= 17.42
Hold fast - 6 x 0.23 x 2.60 Kg/Rmt = 3.59

21.01

Kgs

45.07

Kgs

946.84

Shutter - MS 'L' angle 25 x 25 x 4mm


2x2(0.59+2.10)x1.40 Kg/Mt = 15.06Kgs Centre
T bar (2x0.59)x1.40= 1.65

16.71

Kgs

45.07

Kgs

753.05

21.01
MS sheet of 18 gauge
2x2x0.59x1.053 x 9.80 Kg/Rmt

24.28

Kgs

44.07

Kgs

1069.92

6.00

Nos

33.00

1 Nos

198.00

2.00

Nos

176.00

1 Nos

352.00

3.00

Nos

54.00

1 Nos

162.00

3.00

Nos

49.00

1 Nos

147.00

62.00
62.00
5.85

Kgs
Kgs
Sqm

22.00
4.00
38.08

1 Kgs
1 Kgs
1 Sqm

24.28

Kgs

Cost of 125mm long M.S.Powder Coated but


hinges (BMT-G29)
MS-Powder Coated Aldrop (IS:2681) 300 mm
long(BMT-G.45)
MS-Powder Coated Tower Bolt-10 mm Bolt
(IS:204) 200 mm Long (BMT-G.16)
MS-Powder Coated Door Handles (IS:208) 150
mm Long (BMT-G.36)
Fabrication charges
Fixing charges
Single coat of Red oxide
Over head charges @ 14 %

0.14

5463.46

1364.00
248.00
222.65
5463.46
1
764.88
6228.34
Say 6228.30

2 Supply and fixing of 18 gauge MS Plain sheet windows with frame made of L section
35x35x5mm with 10mm Sq rods at 100 centre to centre (horizontals ) and Shutter
frame with 25x25x4mm angle and Shutters (3 No.s)are made of 18 gauge Mild steel
Plain Sheet and welded and MS flot 20x4mm for shutter alround and horizontal
5nos with 4 No.s of 300mm long hold fasts of 35 x 35 x 5mm and alongwith the
following fixtures for each shutter such as 2 No.s of 100mm long MS but Hinges, 1
No.s of 100mm MS Powder coated tower bolts and 1 No. of 125mm MS Powder
coated handles, 1 No. of MS Wind appliance including red oxide paint including
sales and other taxes on cost of all materials including cost and conveyance of all
materials to site etc., complete for finished item of work.
A WINDOWS SIZE :1.22x1.22 Mtrs
1.22
x
Window size
:
1.37
1.67
Area of Window :
1.67 Sqmts
THEORITICAL REQUIREMENT
Window Outer Frame 'L' Angle 35x 35 x 5 mm
Verticles
2
1.37
2.74
Horizontals
2
1.22
2.44

Hold fasts

0.23

Equivalent Weight
Total Weight

2.60
6.10

Kg/MT

Verticle T Sections 35 x 35x 5 mm


Intermediate verticles : 2
Equivalent Weight
Total Weight

2.00
3.90
2.74

Kg/MT

3.90
Say

10.69
10.69 Kgs

SHUTTER FRAME 25 x 25 x 4 MM
Horizontals
Verticles

6.00
6.00

0.35
1.37

2.10
8.22
10.32 RM

1.40
10.32

Kg/MT

3.00
9.80
1.44

0.35

Equivalent Weight
Total Weight
18 Gauge MS Sheet
Area of sheet
Equivalent Weight
Total Weight
10 mm Square rods
Horzontals : 10 x 1.22
Equivalent weigth
Total weigth

2.60
Say
1.37

1.40
Say

0.92
6.10

15.86 Kgs
15.86 Kgs
2.74

14.45 Kgs
14.45 Kgs
1.37

1.44 Sqm

Kg/1Sqm

9.80
Say

14.10 Kgs
14.10 Kgs

12.20
12.20 0.785
Say

DATA for Red Oxide Primer


Cost of Red oxide
Painter
Total

Rm

9.58
9.58

Kgs

0.07
0.07

###
###

9.10
28.98
38.08
1 Sqm Sqm

15.86
10.69
14.45

Kgs.
Kgs.
Kgs.

45.07
45.07
45.07

1
1
1

Kgs.
Kgs.
Kgs.

714.75
481.58
651.11

14.10

Kgs.

44.07

Kgs.

625.48

9.58
4.60

Kgs.
Sqmt

44.50
38.08

1
1
1

Kgs.
Sqmt
0

447.38
175.03
0.00

8.00

No.s

22.00

No.s

176.00

4.00

No.s

25.00

No.s

100.00

4.00

No.s

33.00

No.s

132.00

4.00
76.44
76.44

No.s
Kgs.
Kgs.

25.00
22.00
4.00

1
1
1

No.s
Kgs.
Kgs.

100.00
1681.68
305.76
###
782.71
###
###

DATA

Window Outer Frame 'L' Section Angle


35x35x6mm
T Section 35x35x5m
Inner frame 25 x 25 x3 mm
18 Gauge MS Sheet (Rate approved by C.E. for
RSC, Piler)

10mm Square Rods

Data for Red Oxide Primer

FIXTURES
MS-Powder Coated Butt hinges (IS:205)- 100 mm
Long (BMT-G.28)
MS-Powder Coated Tower Bolt-10 mm Bolt
(IS:204) 100 mm Long (BMT-G.14)
MS-Powder Coated Door Handles (IS:208) 125
mm Long (BMT-G.35)
MS (Powder Coated) Wind Appliance
Fabrication Charges
Fixing Charges

Over head charges @ 14 %


Say

A WINDOWS SIZE :0.90x1.22 Mtrs


0.90
Window size
:
Area of Window :
1.10
THEORITICAL REQUIREMENT
Window Outer Frame 'L' Angle 35x 35 x 5 mm
Verticles
2
Horizontals
2
Hold fasts
4
Equivalent Weight
Total Weight

2.60
5.16

Verticle T Sections 35 x 35x 5 mm


Intermediate verticles : 1
Equivalent Weight
Total Weight

1.00
3.90
1.20

x
Sqmts

1.22

0.9
1.22
0.23

1.80
2.44
0.92
5.16

2.60
Say
1.20

13.42 Kgs
13.42 Kgs
1.20

Kg/MT

3.90
Say

4.68
4.68

Kgs

1.40
4.80
6.20

RM
Kgs
Kgs

4.00
4.00

0.35
1.20

Equivalent Weight
Total Weight

1.40
6.20

Kg/MT

1.40
Say

8.68
8.68

18 Gauge MS Sheet
Area of sheet
Equivalent Weight
Total Weight

2.00
9.80
0.84

0.35

1.20

DATA for Red Oxide Primer


Cost of Red oxide
Painter
Total

Rm

Kg/MT

SHUTTER FRAME 25 x 25 x 4 MM
Horizontals
Verticles

10 mm Square rods
Horzontals : 10 x 0.90
Equivalent weigth
Total weigth

1.10

0.84 Sqm

Kg/1Sqm

9.80
Say

8.23
8.23

Kgs
Kgs

Say

7.07
7.07

9.00
9.00

0.785

Kgs

0.07
0.07

###
###

9.10
28.98
38.08
1 Sqm Sqm

13.42
4.68
8.68

Kgs.
Kgs.
Kgs.

45.07
45.07
45.07

1
1
1

Kgs.
Kgs.
Kgs.

604.61
210.91
391.17

8.23

Kgs.

44.07

Kgs.

625.48

7.07
3.02

Kgs.
Sqmt

44.50
38.08

1
1
1

Kgs.
Sqmt
0

447.38
114.98
0.00

8.00

No.s

22.00

No.s

176.00

4.00

No.s

25.00

No.s

100.00

4.00

No.s

33.00

No.s

132.00

DATA

Window Outer Frame 'L' Section Angle


35x35x6mm
T Section 35x35x5m
Inner frame 25 x 25 x3 mm
18 Gauge MS Sheet (Rate approved by C.E. for
RSC, Piler)

10mm Square Rods

Data for Red Oxide Primer

FIXTURES
MS-Powder Coated Butt hinges (IS:205)- 100 mm
Long (BMT-G.28)
MS-Powder Coated Tower Bolt-10 mm Bolt
(IS:204) 100 mm Long (BMT-G.14)
MS-Powder Coated Door Handles (IS:208) 125
mm Long (BMT-G.35)

MS (Powder Coated) Wind Appliance


Fabrication Charges
Fixing Charges

4.00
76.44
76.44

No.s
Kgs.
Kgs.

25.00
22.00
4.00

1
1
1

No.s
Kgs.
Kgs.

Over head charges @ 14 %


Say

100.00
1681.68
305.76
###
684.60
###
###

3 Supply and Fixing of Ventilator of size 1.22 x 0.30 Mtrs with 25mm x 25mm x 3mm

thick equal L angles and 10mm square rods @ 150mm c/c fixing in position
,complete for finsihed item of work
VENTILATOR SIZE 1.20 x 0.30 mtrs :
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 0.30
=
Horizental 1 x2 x 1.20
=
For Hold fasts 1 x 2 x 0.15 =
Total
=
10 mm square rods @ 150 mm c/c
Verticals 1 x 8 x 0.30
=
Horizental 1 x2 x 1.20
=
total

1.20

0.60
2.40
0.30
3.30

m
m

0.30

0.36

3.63

Kgs

2.40
2.40
4.80

3.768
7.40

Kgs

7.40

1Kgs

45.07

1Kgs

333.43

7.40
7.40

1kgs
1kgs

22.00
4.00

1
1

1Kgs
1kgs

162.76
29.59
525.78
73.61
0.02
599.40

ABSTRACT
a)MATERIAL
Cost of Structural Steel
a) LABOUR
Fabrication Charges
Fixing Charges
Add overheads @

0.14

Rate per / Each


4 Supply and Fixing of Ventilator of size 0.9 x 0.30 Mtrs with 25mm x 25mm x 3mm

thick equal L angles and 10mm square rods @ 150mm c/c fixing in position
,complete for finsihed item of work
VENTILATOR SIZE 0.90 x 0.30 mtrs :
Angular frame 25 x 25 x 3mm thick
Verticals 1 x 2 x 0.30
=
Horizental 1 x2 x 0.90
=
For Hold fasts 1 x 2 x 0.15 =
Total
=
10 mm square rods @ 150 mm c/c
Verticals 1 x 6 x 0.30
=
Horizental 1 x2 x 0.9
=
total
ABSTRACT
a)MATERIAL
Cost of Structural Steel
a) LABOUR
Fabrication Charges
Fixing Charges
Add overheads @

0.90

0.60
1.80
0.30
2.70

m
m

0.30

0.27

2.97

Kgs

1.80
1.80
3.60

2.826
5.80

Kgs

5.80

1Kgs

45.07

1Kgs

261.23

5.80
5.80

1kgs
1kgs

22.00
4.00

1
1

1Kgs
1kgs

127.51
23.18
411.92
57.67
0.01

0.14

Rate per / Each

Executive
,Engineer
APEWIDC,
ANANTAPUR

469.60

,Dy.Executive Engineer
APEWIDC, ANANTAPUR

,Assistant Engineer
APEWIDC, ANANTAPUR

DATAS FOR DOORS AND WINDOWS


Sno

Qty

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.52x2.13
mtrs with MediumTeak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

Rate

Unit

Per

DOOR SIZE 1.52 x 2.13 mtrs : Area = 3.24 Sqm

1.52

2.13

Medium Teak Wood for Frame


Verticals 2 x 2.13 x 0.075 x 0.10

= 0.0319

0.03195

cum

Horizental 1 x 1.52 x 0.075 x 0.10

= 0.00864

0.01140

cum

0.04335

cum

2.89

sqm

Total

= 0.04054

35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.41x2.05 = 2.89 Sqm
ABSTRACT
a)MATERIAL
1

0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M ( BMT-E.02)

88994.00

Cum

0.01140 Cost of medium Teak wood scantling of size up to 2.0 M ( BMT-E.1)

80094.00

Cum

1488.00

Sqm

2.89

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)

6.00

MS Hold Fasts

25.00

Each

1.00

Cost of 300mm Long Aluminium Aldrops(BMT-G.42)

425.00

Each

2.00

Cost of 300 long Aluminium Towerbolts (BMT-G.11)

198.00

Each

2.00

Cost of 150mm Long Aluminium Handles (BMT-G.34)

140.00

Each

6.00

Cost of 125mm long M.S. Powder Coated but hinges (BMT-G29)

34.00

Each

1.00

Cost of Flat latch Aluminium 300long (BMT-G.50)

188.00

Each

10

2.00

Cost of Door Stoper (BMT-G.53)

50.00

Each

685.00

Sqm

2.89
11

a)
LABOUR
Labour
charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)

152

Sno
12

Qty
0.20

Description of Item
Add munipal area allowance @ 20 %

13

Rate
685.00

Unit
1

Per

2.13

0.03195
0.01500
0.04695

cum
cum
cum

3.87

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

Add overheads @ 14.000%


Rate per / Each
Supply and Fixing of Door with Double leaf shutter, Door Size 2.0x2.13 mtrs
with MediumTeak wood Frame of sections size 75mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

1
2

3
4
5
6
7
8
9
10

DOOR SIZE 2.0 x 2.13 mtrs : Area = 4.26 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
= 0.0319
Horizental 1 x 2.0 x 0.075 x 0.10
= 0.01500
Total
= 0.04695
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.89x2.05 = 3.87 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.01500 Cost of medium Teak wood scantling of size up to 2.0 M

3.87
6.00
1.00
2.00
2.00
6.00
1.00
2.00
3.87

11
12

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %

13

Add overheads @
Rate per / Each

153

685.00
685.00
14%

Sno

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 2.4 x 2.13 mtrs : Area = 5.11 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
= 0.0319
Horizental 1 x 2.4 x 0.075 x 0.10
= 0.01800
Total
= 0.04995
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x2.3x2.05 = 4.9Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.01800 Cost of medium Teak wood scantling of size up to 2.0 M

4.9
6.00
1.00
2.00
2.00
6.00
1.00
2.00
4.90

11
12

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 2.4x2.13 mtrs
with MediumTeak wood Frame of sections size 125mm x 100mm with Flush
Door Shutter Solid Bond Wood black board type with commercial ply on
both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 250mm long 2 Nos, Aluminium Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame and shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 250 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %

13

Add overheads @
Rate per / Each

154

Rate

Unit

Per

2.4

2.13

0.03195
0.01800
0.04995

cum
cum
cum

4.9

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

685.00
685.00
14%

Sno

Qty

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.22x2.13
mtrs with Medium teak wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Alluminimum Handles 150mm long 2 Nos,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 6Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.

Rate

Unit

Per

1.22

2.13

0.03195
0.00915
0.04110

cum
cum
cum

2.28

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

1
2

3
4
5
6
7
8
9
10

DOOR SIZE 1.22 x 2.13 mtrs : Area = 2.60 Sqm


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.22 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x1.11x2.05 = 2.45 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00915 Cost of medium Teak wood scantling of size up to 2.0 M

2.28
6.00
1.00
2.00
2.00
6.00
1.00
2.00
2.28

12

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %

14

Add overheads @
Rate per / Each

155

14%

Sno
3

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 0.90 x 2.13 mtrs : Area =


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 0.90 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.78x2.05 =
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00675 Cost of medium Teak wood scantling of size up to 2.0 M

1.6
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.60

12

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.90x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed utem of work.
D6

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %

14

Add overheads @
Rate per / Each

156

Rate

Unit

Per

0.9

2.13

0.03195
0.00675
0.03870

cum
cum
cum

1.6

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

14%

Sno

Qty

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 0.76x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 150mm long 1 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
250 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Fixing in position of Aluminium Sheet 24 guage of full width of
shutter to a height of 0.60 mtrs for interior face and 0.15 mtrs to external
face , Sales and Other Taxes cost and convenyance of all materials to site
all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complte for finsihed item of work.

Rate

Unit

Per

0.76

2.13

0.03195
0.00570
0.03765

cum
cum
cum

1.29

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
114.00
391.00
140.00
34.00
179.00
302.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Sqm

685.00

Sqm

685.00

4
1

1
2

3
4
5
6
7
8
9
10
11

DOOR SIZE 0.76 x 2.13 mtrs : Area =


Salwood Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 0.76 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.63x2.05 = 1.30 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00570 Cost of medium Teak wood scantling of size up to 2.0 M

1.29
6.00
1.00
1.00
2.00
3.00
1.00
0.48
1.29

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 150 long Aluminium Towerbolts (BMT-G.08)
Cost of 250mm Long Aluminium Aldrops(BMT-G.41)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 250 MM long (BMT-G.49)
Cost of 24 guage Alluminium Sheet (BMS-W.18)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %
Add overheads @
Rate per / Each

157

14%

Sno
4

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 1.05 x 2.13 mtrs : Area =


Medium Teak Wood for Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.05 x 0.075 x 0.10
=
Total
=
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.95x2.05 = 1.947 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00788 Cost of medium Teak wood scantling of size up to 2.0 M

1.95
6.00
1.00
2.00
2.00
6.00
1.00
2.00
1.95

11
12
13
14

Description of Item
Supply and Fixing of Door with Double leaf shutter, Door Size 1.05x2.13
mtrs with Medium Teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 300mm long 2 Nos, MS Powder coated Handles 150mm long 2
Nos, 300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges
6Nos, 300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS
Hold fasts 6Nos, Sales and Other Taxes cost and convenyance of all
materials to site all Labour charges such as Fixing of Door Frame on
shutter Fixing in position , with Hardware fixtures etc., complete for finsihed
utem of work.

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 300 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %
Add overheads @
Rate per / Each

158

Rate

Unit

Per

1.05

2.13

0.03195
0.00788
0.03983

cum
cum
cum

1.95

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

685.00

Sqm

685.00

14%

Sno
5

1
2

3
4
5
6
7
8
9
10

Qty

DOOR SIZE 1.00 x 2.13 mtrs : Area = 2.13 Sqm


Salwood Frame
Verticals 2 x 2.13 x 0.075 x 0.10
=
Horizental 1 x 1.00 x 0.075 x 0.10
= 0.0075
Total
= 0.0394
35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
1x0.875x2.05 = 1.79 Sqm
ABSTRACT
a)MATERIAL
0.03195 Cost of medium Teak wood scantling of size 2.0 to 3.0 M
0.00750 Cost of medium Teak wood scantling of size up to 2.0 M

1.79
6.00
1.00
2.00
1.00
3.00
1.00
1.00
1.79

12

Description of Item
Supply and Fixing of Door with Single leaf shutter, Door Size 1.00x2.13
mtrs with Medium teak Wood Frame of sections size 75mm x 100mm with
Flush Door Shutter Solid Bond Wood black board type with commercial ply
on both faces of 35mm thick including cost of fixtures such as Aluminium
Tower Bolts 200mm long 2 Nos, Aluminium Handels 150mm long 1 No,
300mm long Aluminium Aldrops 1No, 125mm long M.S. But hinges 3 Nos,
300 mm long Aluminium Flat latch 1No, Door stoppers 2 Nos, MS Hold
fasts 6Nos, Sales and Other Taxes cost and convenyance of all materials to
site all Labour charges such as Fixing of Door Frame on shutter Fixing in
position , with Hardware fixtures etc., complete for finsihed item of work.

0.20

Cost 35mm thick flush door shutter of soild wood block board type with
commercial play on both faces
(BMT-N.17)
MS Hold Fasts
Cost of 300mm Long Aluminium Aldrops(BMT-G.42)
Cost of 200 long Aluminium Towerbolts (BMT-G.11)
Cost of 150mm Long Aluminium Handles (BMT-G.34)
Cost of 125mm long M.S. but hinges (BMT-G29)
Cost of Flat latch Aluminium 300long (BMT-G.50)
Cost of Door Stoper (BMT-G.53)
a) LABOUR
Labour charges for wrought and put up including fixing in position frames
of any size , shutters for doors, windows, ventilators including fixing all
necesssary fixtures etc complete for other than teak wood flush type
door shutter including frame. (BMM-V.42)
Add munipal area allowance @ 20 %

14

Add overheads @
Rate per / Each

Providing and fixing factory made Polyvinyl chloride (PVC) Door Frame of
the size 50 x 47mm with a wall thickness of 5mm, made out of extruded
5mm rigid PVC foam sheet, mitre cut at two corners and joined with 2nos.
of 150mm long brackets of 15x15mm M.S. square tube. The two vertical
door profiles are to be reinforced with 19x19mm M.S. Square tube of 19
gauge. The door frame shall be fixed to the wall using 65/100mm long M.S.
Screws through the frame by using PVC fasteners. A minimum of 4nos. of
screws to be provided for each vertical member & minimum 2nos. for
horizontal member etc. complete as per manufacturers specification and
direction of Engineer-in-Charge for finished item of work

159

Rate

Unit

Per

0.9

2.13

0.03195
0.00750
0.03945

cum
cum
cum

1.79

sqm

88994.00
80094.00

1
1

Cum
Cum

1488.00
25.00
425.00
198.00
140.00
34.00
188.00
50.00

1
1
1
1
1
1
1
1

Sqm
Each
Each
Each
Each
Each
Each
Each

Sqm

685.00
685.00
14%

Sno

Qty
1 rmt

Description of Item
cost of PVC door frame (BMT-N.01)
Add overheads @
Rate per / Each
Providing and fixing 30mm thick Solid panel PVC door shutter consisting of
frame made out of M.S. tubes of 19 gauge thickness and size of 19mm x
19mm for stiles, & 15mm x 15mm for top & bottom rails. M.S. frame shall
have a coat of steel primers of approved make and manufacture. M.S.
frame shall be covered with 5mm thick heat moulded PVC C channel of
size 30 x 50mm forming stiles, and 5mm thick, 75mm wide PVC sheets for
top rail, lock rail & bottom rail on either side, and 10mm (5mm x 2) thick,
20mm wide cross PVC sheet as gap insert for top rail & bottom rail.
Panelling of 5mm thick PVC sheet to be fitted in the M.S. frame welded /
sealed to the stiles & rails with 30mm wide x 5mm thick PVC sheet beading
on either side, and joined together with solvent cement adhesive etc. An
additional 5mm thick PVC strip of 20mm width is to be stuck on the interior
side of the C Channel using PVC solvent adhesive. Complete as per
direction of Engineer-in-charge, manufacturers specification & drawing for
finished item of work .

cost of PVC shutter (BMT-N.02)


Add overheads @

Rate
325.00
14%

Unit
1

Per
Rmt

2362.00
14%

sqm

7288
558

1
-1

SQM

Rate per 1 sqm

8
Providing & Fixing of Openable Windows with Fly-mesh made of
pre-painted steel (Base Steel as per IS 513 of 0.6mm thick
galvanized as per IS 277 with zinc of 150 GSM) primer coated
with epoxy primer of 5-7 microns thick, finish painted with a
polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer and the section for outer frame of 72 x
55mm, centre mullion of 72 x 50mm, section for fixed glass
beading section of 12 x 12 mm and section for shutters of 47 x 20
mm and outer frame & mullion sections with rebate for glazed
shutters, fly mesh and a 20 mm provision for guard bars/grills and
fly mesh shutter section of 20 x 40 mm and the sections cut to
length metre joined with corner bracket, centre mullions fixed with
mullion cap, stay, handles, latch 2 Nos of heavy duty stainless
steel pivot hinges per shutter and panelled with 5mm thick plain
float glass and S.S. Mesh for fly mesh shutter (304 grade), fitted
using rubber gaskets
including fixing the windows in the concrete/masonry wall by
means of self expanding screws, including 10mm Square guard
bars with 6 (152.4mm) pitch , complete for finished item of work
a)

Centre fixed both side openable shutter window 50x40


(1524mm x1219.2mm). Outer frame section size of 72x50mm.
Shutter frame section size of 47x20mm. Mullion section size of
72x50mm. Fixed beading section size of 12x12mm.
basic rate as per ssr item code BMT-P.31
Deduct 5 mm plain glass BMT-I.02

160

Sno

Qty

Description of Item
Add 0.5 mm thick Galvalume corrugated sheet BMS-W.55
Add 14% overheads
Rate per sqmt.

b)

Double shutter Window with vertical mullion outer frame section


size of 72x50mm shutter frame section size of 47x20mm. Mullion
section size of 72x50mm.
basic rate as per ssr item code BMT-P.95 & 96
Deduct 5 mm plain glass BMT-I.02
Add 0.5 mm thick Galvalume corrugated sheet BMS-W.55
Add 14% overheads
Rate per sqmt.

Rate
456
Total
14%

Unit
1

Per
SQM

7069

SQM

456
Total
14%

SQM

4737
14%

SQM

9
Supply and fixing of Fixed Louvered Ventilators with sections
made of pre - painted steel (base steel as per IS 513 of 'D"
quality, galvanized as per IS 277 with zinc of 120 GSM) primer
coated with epoxy primer of 5-7 microns thick, finish painted with
a polyester paint of 12-16 microns thick and back coated with 5-7
microns thick alkyd backer with total coated thickness of 0.6mm.
Section for louvered ventilator frame should be of 33x57mm. All
the above closed and seamed sections should be made out of
single sheet and with stitch at a single place as per enclosed
drawings; The ventilators should be paneled with 4 mm pinhead
glass with Ethyl propylene Diamine monomer Gasket (EPDM). The
sections are to be cut to length mitre joined with corner bracket.
Gaskets are to be made of Ethyl propylene Diamine
monomer(EPDM). Corner brackets made of CRCA with Zinc
Phosphate. The above frames should be fixed to the concrete
/masonry wall by means of self expanding brackets & screws
including 10 mm square guard bars with 6" pitch and all taxes
complete for finished item of work.
Basic rate as per item code BMT-P.20
Add 14% overheads
Rate per sqmt.

161

Sno
10

Qty

Description of Item
Rate
Unit
Providing and fixing Structural Glazing fabricated from Roll formed sections made of Pre-painted Steel /
Powder coated (Base steel as per IS 513 of D quality, galvanized as per IS 277 with Zinc of 120
Gm/Sqm) with total coated thickness of 0.72 mm and the glass holding section made of 304 grade
stainless steel of 0.58 mm thick galvanised steel section as stiffeners inside the colour coated steel powder
coated sections as per the design requirement & calculations to suit wind pressures as given in IS: 875, the
primer coat with epoxy primer of 5 7 microns thick, finish painted with a polyester paint of 12-16
microns thick and back coated with Alkyd backer of 5-7 microns or powder coated with pure polyester
powder up to 50-60 microns thick and the vertical section of 50 mm x 99 mm x 0.72 mm, 33 mm x 56
mm x 0.72 mm for frame horizontal section, stiffener section of 47 mm x 97 mm x 1 mm, cover profiles
sections of 20 mm x 58 mm x 0.58 mm, glass holding section of 37 mm x 37 mm & 37 mm x 18 mm
including fixing 5mm thick Ocean Blue reflective glass, brackets made of CRCA powder
coated/Electroplated to connect vertical to horizontal, vertical to slab, to fix verticals at top & bottom as
per site requirement and gasket made of Ethyl Propylene Diamine Monomer, U.V. resistant silicon sealant
including fixing in concrete/masonry wall with self-expanding cap & screws inclusive of cost and
conveyance of all materials to site, all labour charges, incidental charges, cost of all consumables etc. and
fixing

Basic rate as per item code BMT-Q.1


Add 14% overheads
Rate per sqmt.

7288
14%

Per

SQM

Supply and fixing of MS grill Window of 2.73X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 2.73
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 26x 2.69
MS Aldrop,Tower Bolt and Holdfast
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14
Fixing Charges BMM -V-15
Over Head Charges

2.7
5.46
8.16

3.5

28.56

18.48
69.94
88.42

0.78

68.968
0.55
98.078

98.08
98.08
98.08
6872.30

42.07
24.00
4.00
0.14

Say

Supply and fixing of MS grill Window of 3.23X 1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35
Harizontal 2 x 3.23
10 mm SQ rod@ 100c/c
Verticals 14 x 1.32
Harizontal 30x 2.93
MS Aldrop,Tower Bolt and Holdfast

162

2.7
6.46
9.16

3.5

32.06

18.48
87.9
106.38

0.78

82.976
0.55

Sno

Qty

Description of Item
total weight
Rate analysis
cost of MS steel
Fabrication charges BMM -V-14

Rate

Unit

115.59
115.59

42.07
24.00

Fixing Charges BMM -V-15

115.59

4.00

Over Head Charges

8099.14

0.14

Per
115.59

Say

Supply and fixing of MS grill Window of 2.26 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35

2.7

Harizontal 2 x 2.26

4.52
7.22

3.5

25.27

0.78

46.332

10 mm SQ rod@ 100c/c
Verticals 14 x 1.32

18.48

Harizontal 22x 1.86

40.92
59.4

MS Aldrop,Tower Bolt and Holdfast

0.55

total weight

72.152

Rate analysis
cost of MS steel

72.15

42.07

Fabrication charges BMM -V-14

72.15

24.00

Fixing Charges BMM -V-15

72.15

4.00

Over Head Charges

5055.69

0.14

Say

Supply and fixing of MS grill Window of 3 x1.35 mts by using 40 x40 x 6mm MS Angle section for
outer frame and 10 mm square safety bars @ 100 mm C/C both ways including cost & conveyance of
all materials and labour charges for finished item of work
Frame 40x40x6 mm (GW)
Verticals 2 x 1.35

2.7

Harizontal 2 x 3

6
8.7

3.5

30.45

0.78

73.226

10 mm SQ rod@ 100c/c
Verticals 14 x 1.32

18.48

Harizontal 29x 2.6

75.4
93.88

163

Sno

Qty

Description of Item

Rate

Unit

Per

MS Aldrop,Tower Bolt and Holdfast

0.55

total weight

104.23

Rate analysis
cost of MS steel

104.23

42.07

Fabrication charges BMM -V-14

104.23

24.00

Fixing Charges BMM -V-15

104.23

4.00

Over Head Charges

7303.14

0.14

Say

164

Amount

3.24

2843.36
913.07

4300.32
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1979.65

165

Amount
137.00
11916.40
1668.30
13584.70

4.26

2843.36
1201.41

5758.56
150.00
425.00
396.00
280.00
204.00
188.00
100.00
2650.95

137.00
14334.28
2006.80
16341.10

166

Amount

5.11

2843.36
1441.69

7291.20
150.00
425.00
396.00
280.00
204.00
188.00
100.00
3356.50

137.00
16812.75
2353.79
19166.55

167

Amount

2.6

2843.36
732.86

3392.64
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1561.80

137.00
10410.66
1457.49
11868.20

168

Amount

1.92

2843.36
540.63

2380.80
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1096.00

137.00
8448.79
1182.83
9631.65

169

Amount

1.62

2843.36
456.54

1919.52
150.00
114.00
391.00
280.00
102.00
179.00
144.96
883.65

137.00
7601.03
1064.14
8665.20

170

Amount

2.24

2843.36
630.74

2901.60
150.00
425.00
396.00
280.00
204.00
188.00
100.00
1335.75

137.00
9591.45
1342.80
10934.30

171

Amount

1.92

2843.36
600.71

2663.52
150.00
425.00
396.00
140.00
102.00
188.00
50.00
1226.15

137.00
8921.74
1249.04
10170.80

172

Amount
325.00
45.50
370.50

2362.00
330.68
2692.70

7288.00
-558.00

173

Amount
456.00
7186.00
1006.04
8192.05

7069.00
-558.00
456.00
6967.00
975.38
7942.40

4737.00
663.18
5400.20

174

Amount

7288.00
1020.32
8308.35

4126.12
2353.86
392.31
962.12
7834.42
7835.00

175

Amount

4862.72
2774.07
462.35
1133.88
9233.02
9234.00

3035.43
1731.65
288.61
707.80
5763.49
5764.00

176

Amount

4384.80
2501.43
416.91
1022.44
8325.58
8326.00

177

Sl.No

###

1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
32
33
34
35
36
37
38
39
40
41
42
43
44
45
46
47
48
49
50
51

CONVEYANCE CHARGES AS PER COMMON SSR 2013-14


Lead in Earth/Sand/G Rubble/Size Cement/Steel/R
PCC
Water
Kms ravel/Murrum/
Stone/Cut
CC poles/A.C & Slabs/Shabad
Lime/Surki
Stone/Coarse
G.I
Slabs/CC &
aggregates
Sheets/Packed
Laterite
materials
Blocks/Wood
1.00
2.00
3.00
4.00
5.00
6.00
7.00
8.00
9.00
10.00
11.00
12.00
13.00
14.00
15.00
16.00
17.00
18.00
19.00
20.00
21.00
22.00
23.00
24.00
25.00
26.00
27.00
28.00
29.00
30.00
31.00
32.00
33.00
34.00
35.00
36.00
37.00
38.00
39.00
40.00
41.00
42.00
43.00
44.00
45.00
46.00
47.00
48.00
49.00
50.00
51.00

0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59

0.00
10.92
23.65
34.57
45.49
56.41
67.33
78.25
89.17
100.09
111.01
121.93
132.85
143.77
154.69
165.61
176.53
187.45
198.37
209.29
220.21
231.13
242.05
252.97
263.89
274.81
285.73
296.65
307.57
318.49
327.59
336.69
345.79
354.89
363.99
373.09
382.19
391.29
400.39
409.49
418.59
427.69
436.79
445.89
454.99
464.09
473.19
482.29
491.39
500.49
509.59

0.00
6.82
14.78
21.60
28.43
35.25
42.07
48.89
55.71
62.53
69.35
76.17
82.99
89.81
96.63
103.45
110.27
117.09
123.91
130.73
137.55
144.37
151.19
158.01
164.83
171.65
178.47
185.29
192.11
198.93
204.62
210.31
216.00
221.69
227.38
233.07
238.76
244.45
250.14
255.83
261.52
267.21
272.90
278.59
284.28
289.97
295.66
301.35
307.04
312.73
318.42

0.00
16.05
34.78
50.83
66.88
82.93
98.98
115.03
131.08
147.13
163.18
179.23
195.28
211.33
227.38
243.43
259.48
275.53
291.58
307.63
323.68
339.73
355.78
371.83
387.88
403.93
419.98
436.03
452.08
468.13
481.51
494.89
508.27
521.65
535.03
548.41
561.79
575.17
588.55
601.93
615.31
628.69
642.07
655.45
668.83
682.21
695.59
708.97
722.35
735.73
749.11

0.00
6.49
14.06
20.55
27.05
33.54
40.03
46.52
53.01
59.50
65.99
72.48
78.97
85.46
91.95
98.44
104.93
111.42
117.91
124.40
130.89
137.38
143.87
150.36
156.85
163.34
169.83
176.32
182.81
189.30
194.71
200.12
205.53
210.94
216.35
221.76
227.17
232.58
237.99
243.40
248.81
254.22
259.63
265.04
270.45
275.86
281.27
286.68
292.09
297.50
302.91

Bricks

0.00
17.54
38.00
55.54
73.09
90.63
108.17
125.71
143.25
160.79
178.33
195.87
213.41
230.95
248.49
266.03
283.57
301.11
318.65
336.19
353.73
371.27
388.81
406.35
423.89
441.43
458.97
476.51
494.05
511.59
526.21
540.83
555.45
570.07
584.69
599.31
613.93
628.55
643.17
657.79
672.41
687.03
701.65
716.27
730.89
745.51
760.13
774.75
789.37
803.99
818.61

52
53
54
55
56
57
58
59
60
61
62
63
64
65
66
67
68
69
70
71
72
73
74
75
76
77
78
79
80
81
82
83
84
85
86
87
88
89
90
91
92
93
94
95
96
97
98
99
100
101
102
103
104
105
106
107
108

52.00
53.00
54.00
55.00
56.00
57.00
58.00
59.00
60.00
61.00
62.00
63.00
64.00
65.00
66.00
67.00
68.00
69.00
70.00
71.00
72.00
73.00
74.00
75.00
76.00
77.00
78.00
79.00
80.00
81.00
82.00
83.00
84.00
85.00
86.00
87.00
88.00
89.00
90.00
91.00
92.00
93.00
94.00
95.00
96.00
97.00
98.00
99.00
100.00
101.00
102.00
103.00
104.00
105.00
106.00
107.00
108.00

518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29

518.69
527.79
536.89
545.99
555.09
564.19
573.29
582.39
591.49
600.59
609.69
618.79
627.89
636.99
646.09
655.19
664.29
673.39
682.49
691.59
700.69
709.79
718.89
727.99
737.09
746.19
755.29
764.39
773.49
782.59
791.69
800.79
809.89
818.99
828.09
837.19
846.29
855.39
864.49
873.59
882.69
891.79
900.89
909.99
919.09
928.19
937.29
946.39
955.49
964.59
973.69
982.79
991.89
1000.99
1010.09
1019.19
1028.29

324.11
329.80
335.49
341.18
346.87
352.56
358.25
363.94
369.63
375.32
381.01
386.70
392.39
398.08
403.77
409.46
415.15
420.84
426.53
432.22
437.91
443.60
449.29
454.98
460.67
466.36
472.05
477.74
483.43
489.12
494.81
500.50
506.19
511.88
517.57
523.26
528.95
534.64
540.33
546.02
551.71
557.40
563.09
568.78
574.47
580.16
585.85
591.54
597.23
602.92
608.61
614.30
619.99
625.68
631.37
637.06
642.75

762.49
775.87
789.25
802.63
816.01
829.39
842.77
856.15
869.53
882.91
896.29
909.67
923.05
936.43
949.81
963.19
976.57
989.95
1003.33
1016.71
1030.09
1043.47
1056.85
1070.23
1083.61
1096.99
1110.37
1123.75
1137.13
1150.51
1163.89
1177.27
1190.65
1204.03
1217.41
1230.79
1244.17
1257.55
1270.93
1284.31
1297.69
1311.07
1324.45
1337.83
1351.21
1364.59
1377.97
1391.35
1404.73
1418.11
1431.49
1444.87
1458.25
1471.63
1485.01
1498.39
1511.77

308.32
313.73
319.14
324.55
329.96
335.37
340.78
346.19
351.60
357.01
362.42
367.83
373.24
378.65
384.06
389.47
394.88
400.29
405.70
411.11
416.52
421.93
427.34
432.75
438.16
443.57
448.98
454.39
459.80
465.21
470.62
476.03
481.44
486.85
492.26
497.67
503.08
508.49
513.90
519.31
524.72
530.13
535.54
540.95
546.36
551.77
557.18
562.59
568.00
573.41
578.82
584.23
589.64
595.05
600.46
605.87
611.28

833.23
847.85
862.47
877.09
891.71
906.33
920.95
935.57
950.19
964.81
979.43
994.05
1008.67
1023.29
1037.91
1052.53
1067.15
1081.77
1096.39
1111.01
1125.63
1140.25
1154.87
1169.49
1184.11
1198.73
1213.35
1227.97
1242.59
1257.21
1271.83
1286.45
1301.07
1315.69
1330.31
1344.93
1359.55
1374.17
1388.79
1403.41
1418.03
1432.65
1447.27
1461.89
1476.51
1491.13
1505.75
1520.37
1534.99
1549.61
1564.23
1578.85
1593.47
1608.09
1622.71
1637.33
1651.95

109
110
111
112
113
114
115
116
117
118
119
120
121
122
123
124
125
126
127
128
129
130
131
132
133
134
135
136
137
138
139
140
141
142
143
144
145
146
147
148
149
150
151
152
153
154
155
156
157
158
159
160
161
162
163
164
165

109.00
110.00
111.00
112.00
113.00
114.00
115.00
116.00
117.00
118.00
119.00
120.00
121.00
122.00
123.00
124.00
125.00
126.00
127.00
128.00
129.00
130.00
131.00
132.00
133.00
134.00
135.00
136.00
137.00
138.00
139.00
140.00
141.00
142.00
143.00
144.00
145.00
146.00
147.00
148.00
149.00
150.00
151.00
152.00
153.00
154.00
155.00
156.00
157.00
158.00
159.00
160.00
161.00
162.00
163.00
164.00
165.00

1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99

1037.39
1046.49
1055.59
1064.69
1073.79
1082.89
1091.99
1101.09
1110.19
1119.29
1128.39
1137.49
1146.59
1155.69
1164.79
1173.89
1182.99
1192.09
1201.19
1210.29
1219.39
1228.49
1237.59
1246.69
1255.79
1264.89
1273.99
1283.09
1292.19
1301.29
1310.39
1319.49
1328.59
1337.69
1346.79
1355.89
1364.99
1374.09
1383.19
1392.29
1401.39
1410.49
1419.59
1428.69
1437.79
1446.89
1455.99
1465.09
1474.19
1483.29
1492.39
1501.49
1510.59
1519.69
1528.79
1537.89
1546.99

648.44
654.13
659.82
665.51
671.20
676.89
682.58
688.27
693.96
699.65
705.34
711.03
716.72
722.41
728.10
733.79
739.48
745.17
750.86
756.55
762.24
767.93
773.62
779.31
785.00
790.69
796.38
802.07
807.76
813.45
819.14
824.83
830.52
836.21
841.90
847.59
853.28
858.97
864.66
870.35
876.04
881.73
887.42
893.11
898.80
904.49
910.18
915.87
921.56
927.25
932.94
938.63
944.32
950.01
955.70
961.39
967.08

1525.15
1538.53
1551.91
1565.29
1578.67
1592.05
1605.43
1618.81
1632.19
1645.57
1658.95
1672.33
1685.71
1699.09
1712.47
1725.85
1739.23
1752.61
1765.99
1779.37
1792.75
1806.13
1819.51
1832.89
1846.27
1859.65
1873.03
1886.41
1899.79
1913.17
1926.55
1939.93
1953.31
1966.69
1980.07
1993.45
2006.83
2020.21
2033.59
2046.97
2060.35
2073.73
2087.11
2100.49
2113.87
2127.25
2140.63
2154.01
2167.39
2180.77
2194.15
2207.53
2220.91
2234.29
2247.67
2261.05
2274.43

616.69
622.10
627.51
632.92
638.33
643.74
649.15
654.56
659.97
665.38
670.79
676.20
681.61
687.02
692.43
697.84
703.25
708.66
714.07
719.48
724.89
730.30
735.71
741.12
746.53
751.94
757.35
762.76
768.17
773.58
778.99
784.40
789.81
795.22
800.63
806.04
811.45
816.86
822.27
827.68
833.09
838.50
843.91
849.32
854.73
860.14
865.55
870.96
876.37
881.78
887.19
892.60
898.01
903.42
908.83
914.24
919.65

1666.57
1681.19
1695.81
1710.43
1725.05
1739.67
1754.29
1768.91
1783.53
1798.15
1812.77
1827.39
1842.01
1856.63
1871.25
1885.87
1900.49
1915.11
1929.73
1944.35
1958.97
1973.59
1988.21
2002.83
2017.45
2032.07
2046.69
2061.31
2075.93
2090.55
2105.17
2119.79
2134.41
2149.03
2163.65
2178.27
2192.89
2207.51
2222.13
2236.75
2251.37
2265.99
2280.61
2295.23
2309.85
2324.47
2339.09
2353.71
2368.33
2382.95
2397.57
2412.19
2426.81
2441.43
2456.05
2470.67
2485.29

166
167
168
169
170
171
172
173
174
175
176
177
178
179
180
181
182
183
184
185
186
187
188
189
190
191
192
193
194
195
196
197
198
199
200
201
202
203
204
205
206
207
208
209
210
211
212
213
214
215
216
217
218
219
220
221
222

166.00
167.00
168.00
169.00
170.00
171.00
172.00
173.00
174.00
175.00
176.00
177.00
178.00
179.00
180.00
181.00
182.00
183.00
184.00
185.00
186.00
187.00
188.00
189.00
190.00
191.00
192.00
193.00
194.00
195.00
196.00
197.00
198.00
199.00
200.00
201.00
202.00
203.00
204.00
205.00
206.00
207.00
208.00
209.00
210.00
211.00
212.00
213.00
214.00
215.00
216.00
217.00
218.00
219.00
220.00
221.00
222.00

1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69

1556.09
1565.19
1574.29
1583.39
1592.49
1601.59
1610.69
1619.79
1628.89
1637.99
1647.09
1656.19
1665.29
1674.39
1683.49
1692.59
1701.69
1710.79
1719.89
1728.99
1738.09
1747.19
1756.29
1765.39
1774.49
1783.59
1792.69
1801.79
1810.89
1819.99
1829.09
1838.19
1847.29
1856.39
1865.49
1874.59
1883.69
1892.79
1901.89
1910.99
1920.09
1929.19
1938.29
1947.39
1956.49
1965.59
1974.69
1983.79
1992.89
2001.99
2011.09
2020.19
2029.29
2038.39
2047.49
2056.59
2065.69

972.77
978.46
984.15
989.84
995.53
1001.22
1006.91
1012.60
1018.29
1023.98
1029.67
1035.36
1041.05
1046.74
1052.43
1058.12
1063.81
1069.50
1075.19
1080.88
1086.57
1092.26
1097.95
1103.64
1109.33
1115.02
1120.71
1126.40
1132.09
1137.78
1143.47
1149.16
1154.85
1160.54
1166.23
1171.92
1177.61
1183.30
1188.99
1194.68
1200.37
1206.06
1211.75
1217.44
1223.13
1228.82
1234.51
1240.20
1245.89
1251.58
1257.27
1262.96
1268.65
1274.34
1280.03
1285.72
1291.41

2287.81
2301.19
2314.57
2327.95
2341.33
2354.71
2368.09
2381.47
2394.85
2408.23
2421.61
2434.99
2448.37
2461.75
2475.13
2488.51
2501.89
2515.27
2528.65
2542.03
2555.41
2568.79
2582.17
2595.55
2608.93
2622.31
2635.69
2649.07
2662.45
2675.83
2689.21
2702.59
2715.97
2729.35
2742.73
2756.11
2769.49
2782.87
2796.25
2809.63
2823.01
2836.39
2849.77
2863.15
2876.53
2889.91
2903.29
2916.67
2930.05
2943.43
2956.81
2970.19
2983.57
2996.95
3010.33
3023.71
3037.09

925.06
930.47
935.88
941.29
946.70
952.11
957.52
962.93
968.34
973.75
979.16
984.57
989.98
995.39
1000.80
1006.21
1011.62
1017.03
1022.44
1027.85
1033.26
1038.67
1044.08
1049.49
1054.90
1060.31
1065.72
1071.13
1076.54
1081.95
1087.36
1092.77
1098.18
1103.59
1109.00
1114.41
1119.82
1125.23
1130.64
1136.05
1141.46
1146.87
1152.28
1157.69
1163.10
1168.51
1173.92
1179.33
1184.74
1190.15
1195.56
1200.97
1206.38
1211.79
1217.20
1222.61
1228.02

2499.91
2514.53
2529.15
2543.77
2558.39
2573.01
2587.63
2602.25
2616.87
2631.49
2646.11
2660.73
2675.35
2689.97
2704.59
2719.21
2733.83
2748.45
2763.07
2777.69
2792.31
2806.93
2821.55
2836.17
2850.79
2865.41
2880.03
2894.65
2909.27
2923.89
2938.51
2953.13
2967.75
2982.37
2996.99
3011.61
3026.23
3040.85
3055.47
3070.09
3084.71
3099.33
3113.95
3128.57
3143.19
3157.81
3172.43
3187.05
3201.67
3216.29
3230.91
3245.53
3260.15
3274.77
3289.39
3304.01
3318.63

223
224
225
226
227
228
229
230
231
232
233
234
235
236
237
238
239
240
241
242
243
244
245
246
247
248
249
250
251
252
253
254
255
256
257
258
259
260
261
262
263
264
265
266
267
268
269
270
271
272
273
274
275
276
277
278
279

223.00
224.00
225.00
226.00
227.00
228.00
229.00
230.00
231.00
232.00
233.00
234.00
235.00
236.00
237.00
238.00
239.00
240.00
241.00
242.00
243.00
244.00
245.00
246.00
247.00
248.00
249.00
250.00
251.00
252.00
253.00
254.00
255.00
256.00
257.00
258.00
259.00
260.00
261.00
262.00
263.00
264.00
265.00
266.00
267.00
268.00
269.00
270.00
271.00
272.00
273.00
274.00
275.00
276.00
277.00
278.00
279.00

2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39

2074.79
2083.89
2092.99
2102.09
2111.19
2120.29
2129.39
2138.49
2147.59
2156.69
2165.79
2174.89
2183.99
2193.09
2202.19
2211.29
2220.39
2229.49
2238.59
2247.69
2256.79
2265.89
2274.99
2284.09
2293.19
2302.29
2311.39
2320.49
2329.59
2338.69
2347.79
2356.89
2365.99
2375.09
2384.19
2393.29
2402.39
2411.49
2420.59
2429.69
2438.79
2447.89
2456.99
2466.09
2475.19
2484.29
2493.39
2502.49
2511.59
2520.69
2529.79
2538.89
2547.99
2557.09
2566.19
2575.29
2584.39

1297.10
1302.79
1308.48
1314.17
1319.86
1325.55
1331.24
1336.93
1342.62
1348.31
1354.00
1359.69
1365.38
1371.07
1376.76
1382.45
1388.14
1393.83
1399.52
1405.21
1410.90
1416.59
1422.28
1427.97
1433.66
1439.35
1445.04
1450.73
1456.42
1462.11
1467.80
1473.49
1479.18
1484.87
1490.56
1496.25
1501.94
1507.63
1513.32
1519.01
1524.70
1530.39
1536.08
1541.77
1547.46
1553.15
1558.84
1564.53
1570.22
1575.91
1581.60
1587.29
1592.98
1598.67
1604.36
1610.05
1615.74

3050.47
3063.85
3077.23
3090.61
3103.99
3117.37
3130.75
3144.13
3157.51
3170.89
3184.27
3197.65
3211.03
3224.41
3237.79
3251.17
3264.55
3277.93
3291.31
3304.69
3318.07
3331.45
3344.83
3358.21
3371.59
3384.97
3398.35
3411.73
3425.11
3438.49
3451.87
3465.25
3478.63
3492.01
3505.39
3518.77
3532.15
3545.53
3558.91
3572.29
3585.67
3599.05
3612.43
3625.81
3639.19
3652.57
3665.95
3679.33
3692.71
3706.09
3719.47
3732.85
3746.23
3759.61
3772.99
3786.37
3799.75

1233.43
1238.84
1244.25
1249.66
1255.07
1260.48
1265.89
1271.30
1276.71
1282.12
1287.53
1292.94
1298.35
1303.76
1309.17
1314.58
1319.99
1325.40
1330.81
1336.22
1341.63
1347.04
1352.45
1357.86
1363.27
1368.68
1374.09
1379.50
1384.91
1390.32
1395.73
1401.14
1406.55
1411.96
1417.37
1422.78
1428.19
1433.60
1439.01
1444.42
1449.83
1455.24
1460.65
1466.06
1471.47
1476.88
1482.29
1487.70
1493.11
1498.52
1503.93
1509.34
1514.75
1520.16
1525.57
1530.98
1536.39

3333.25
3347.87
3362.49
3377.11
3391.73
3406.35
3420.97
3435.59
3450.21
3464.83
3479.45
3494.07
3508.69
3523.31
3537.93
3552.55
3567.17
3581.79
3596.41
3611.03
3625.65
3640.27
3654.89
3669.51
3684.13
3698.75
3713.37
3727.99
3742.61
3757.23
3771.85
3786.47
3801.09
3815.71
3830.33
3844.95
3859.57
3874.19
3888.81
3903.43
3918.05
3932.67
3947.29
3961.91
3976.53
3991.15
4005.77
4020.39
4035.01
4049.63
4064.25
4078.87
4093.49
4108.11
4122.73
4137.35
4151.97

280
281
282
283
284
285
286
287
288
289
290
291
292
293
294
295
296
297
298
299
300
301
302
303
304
305
306
307
308
309
310
311
312
313
314
315
316
317
318
319
320
321
322
323
324
325
326
327
328
329
330
331
332
333
334
335
336

280.00
281.00
282.00
283.00
284.00
285.00
286.00
287.00
288.00
289.00
290.00
291.00
292.00
293.00
294.00
295.00
296.00
297.00
298.00
299.00
300.00
301.00
302.00
303.00
304.00
305.00
306.00
307.00
308.00
309.00
310.00
311.00
312.00
313.00
314.00
315.00
316.00
317.00
318.00
319.00
320.00
321.00
322.00
323.00
324.00
325.00
326.00
327.00
328.00
329.00
330.00
331.00
332.00
333.00
334.00
335.00
336.00

2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09

2593.49
2602.59
2611.69
2620.79
2629.89
2638.99
2648.09
2657.19
2666.29
2675.39
2684.49
2693.59
2702.69
2711.79
2720.89
2729.99
2739.09
2748.19
2757.29
2766.39
2775.49
2784.59
2793.69
2802.79
2811.89
2820.99
2830.09
2839.19
2848.29
2857.39
2866.49
2875.59
2884.69
2893.79
2902.89
2911.99
2921.09
2930.19
2939.29
2948.39
2957.49
2966.59
2975.69
2984.79
2993.89
3002.99
3012.09
3021.19
3030.29
3039.39
3048.49
3057.59
3066.69
3075.79
3084.89
3093.99
3103.09

1621.43
1627.12
1632.81
1638.50
1644.19
1649.88
1655.57
1661.26
1666.95
1672.64
1678.33
1684.02
1689.71
1695.40
1701.09
1706.78
1712.47
1718.16
1723.85
1729.54
1735.23
1740.92
1746.61
1752.30
1757.99
1763.68
1769.37
1775.06
1780.75
1786.44
1792.13
1797.82
1803.51
1809.20
1814.89
1820.58
1826.27
1831.96
1837.65
1843.34
1849.03
1854.72
1860.41
1866.10
1871.79
1877.48
1883.17
1888.86
1894.55
1900.24
1905.93
1911.62
1917.31
1923.00
1928.69
1934.38
1940.07

3813.13
3826.51
3839.89
3853.27
3866.65
3880.03
3893.41
3906.79
3920.17
3933.55
3946.93
3960.31
3973.69
3987.07
4000.45
4013.83
4027.21
4040.59
4053.97
4067.35
4080.73
4094.11
4107.49
4120.87
4134.25
4147.63
4161.01
4174.39
4187.77
4201.15
4214.53
4227.91
4241.29
4254.67
4268.05
4281.43
4294.81
4308.19
4321.57
4334.95
4348.33
4361.71
4375.09
4388.47
4401.85
4415.23
4428.61
4441.99
4455.37
4468.75
4482.13
4495.51
4508.89
4522.27
4535.65
4549.03
4562.41

1541.80
1547.21
1552.62
1558.03
1563.44
1568.85
1574.26
1579.67
1585.08
1590.49
1595.90
1601.31
1606.72
1612.13
1617.54
1622.95
1628.36
1633.77
1639.18
1644.59
1650.00
1655.41
1660.82
1666.23
1671.64
1677.05
1682.46
1687.87
1693.28
1698.69
1704.10
1709.51
1714.92
1720.33
1725.74
1731.15
1736.56
1741.97
1747.38
1752.79
1758.20
1763.61
1769.02
1774.43
1779.84
1785.25
1790.66
1796.07
1801.48
1806.89
1812.30
1817.71
1823.12
1828.53
1833.94
1839.35
1844.76

4166.59
4181.21
4195.83
4210.45
4225.07
4239.69
4254.31
4268.93
4283.55
4298.17
4312.79
4327.41
4342.03
4356.65
4371.27
4385.89
4400.51
4415.13
4429.75
4444.37
4458.99
4473.61
4488.23
4502.85
4517.47
4532.09
4546.71
4561.33
4575.95
4590.57
4605.19
4619.81
4634.43
4649.05
4663.67
4678.29
4692.91
4707.53
4722.15
4736.77
4751.39
4766.01
4780.63
4795.25
4809.87
4824.49
4839.11
4853.73
4868.35
4882.97
4897.59
4912.21
4926.83
4941.45
4956.07
4970.69
4985.31

337
338
339
340
341
342
343
344
345
346
347
348
349
350
351
352
353
354
355
356
357
358
359
360
361
362
363
364
365
366
367
368
369
370
371
372
373
374
375
376
377
378
379
380
381
382
383
384
385
386
387
388
389
390
391
392
393

337.00
338.00
339.00
340.00
341.00
342.00
343.00
344.00
345.00
346.00
347.00
348.00
349.00
350.00
351.00
352.00
353.00
354.00
355.00
356.00
357.00
358.00
359.00
360.00
361.00
362.00
363.00
364.00
365.00
366.00
367.00
368.00
369.00
370.00
371.00
372.00
373.00
374.00
375.00
376.00
377.00
378.00
379.00
380.00
381.00
382.00
383.00
384.00
385.00
386.00
387.00
388.00
389.00
390.00
391.00
392.00
393.00

3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79

3112.19
3121.29
3130.39
3139.49
3148.59
3157.69
3166.79
3175.89
3184.99
3194.09
3203.19
3212.29
3221.39
3230.49
3239.59
3248.69
3257.79
3266.89
3275.99
3285.09
3294.19
3303.29
3312.39
3321.49
3330.59
3339.69
3348.79
3357.89
3366.99
3376.09
3385.19
3394.29
3403.39
3412.49
3421.59
3430.69
3439.79
3448.89
3457.99
3467.09
3476.19
3485.29
3494.39
3503.49
3512.59
3521.69
3530.79
3539.89
3548.99
3558.09
3567.19
3576.29
3585.39
3594.49
3603.59
3612.69
3621.79

1945.76
1951.45
1957.14
1962.83
1968.52
1974.21
1979.90
1985.59
1991.28
1996.97
2002.66
2008.35
2014.04
2019.73
2025.42
2031.11
2036.80
2042.49
2048.18
2053.87
2059.56
2065.25
2070.94
2076.63
2082.32
2088.01
2093.70
2099.39
2105.08
2110.77
2116.46
2122.15
2127.84
2133.53
2139.22
2144.91
2150.60
2156.29
2161.98
2167.67
2173.36
2179.05
2184.74
2190.43
2196.12
2201.81
2207.50
2213.19
2218.88
2224.57
2230.26
2235.95
2241.64
2247.33
2253.02
2258.71
2264.40

4575.79
4589.17
4602.55
4615.93
4629.31
4642.69
4656.07
4669.45
4682.83
4696.21
4709.59
4722.97
4736.35
4749.73
4763.11
4776.49
4789.87
4803.25
4816.63
4830.01
4843.39
4856.77
4870.15
4883.53
4896.91
4910.29
4923.67
4937.05
4950.43
4963.81
4977.19
4990.57
5003.95
5017.33
5030.71
5044.09
5057.47
5070.85
5084.23
5097.61
5110.99
5124.37
5137.75
5151.13
5164.51
5177.89
5191.27
5204.65
5218.03
5231.41
5244.79
5258.17
5271.55
5284.93
5298.31
5311.69
5325.07

1850.17
1855.58
1860.99
1866.40
1871.81
1877.22
1882.63
1888.04
1893.45
1898.86
1904.27
1909.68
1915.09
1920.50
1925.91
1931.32
1936.73
1942.14
1947.55
1952.96
1958.37
1963.78
1969.19
1974.60
1980.01
1985.42
1990.83
1996.24
2001.65
2007.06
2012.47
2017.88
2023.29
2028.70
2034.11
2039.52
2044.93
2050.34
2055.75
2061.16
2066.57
2071.98
2077.39
2082.80
2088.21
2093.62
2099.03
2104.44
2109.85
2115.26
2120.67
2126.08
2131.49
2136.90
2142.31
2147.72
2153.13

4999.93
5014.55
5029.17
5043.79
5058.41
5073.03
5087.65
5102.27
5116.89
5131.51
5146.13
5160.75
5175.37
5189.99
5204.61
5219.23
5233.85
5248.47
5263.09
5277.71
5292.33
5306.95
5321.57
5336.19
5350.81
5365.43
5380.05
5394.67
5409.29
5423.91
5438.53
5453.15
5467.77
5482.39
5497.01
5511.63
5526.25
5540.87
5555.49
5570.11
5584.73
5599.35
5613.97
5628.59
5643.21
5657.83
5672.45
5687.07
5701.69
5716.31
5730.93
5745.55
5760.17
5774.79
5789.41
5804.03
5818.65

394
395
396
397
398
399
400
401
402
403
404
405
406
407
408
409
410
411
412
413
414
415
416
417
418
419
420
421
422
423
424
425
426
427
428
429
430
431
432
433
434
435
436
437
438
439
440
441
442
443
444
445
446
447
448
449
450

394.00
395.00
396.00
397.00
398.00
399.00
400.00
401.00
402.00
403.00
404.00
405.00
406.00
407.00
408.00
409.00
410.00
411.00
412.00
413.00
414.00
415.00
416.00
417.00
418.00
419.00
420.00
421.00
422.00
423.00
424.00
425.00
426.00
427.00
428.00
429.00
430.00
431.00
432.00
433.00
434.00
435.00
436.00
437.00
438.00
439.00
440.00
441.00
442.00
443.00
444.00
445.00
446.00
447.00
448.00
449.00
450.00

3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49

3630.89
3639.99
3649.09
3658.19
3667.29
3676.39
3685.49
3694.59
3703.69
3712.79
3721.89
3730.99
3740.09
3749.19
3758.29
3767.39
3776.49
3785.59
3794.69
3803.79
3812.89
3821.99
3831.09
3840.19
3849.29
3858.39
3867.49
3876.59
3885.69
3894.79
3903.89
3912.99
3922.09
3931.19
3940.29
3949.39
3958.49
3967.59
3976.69
3985.79
3994.89
4003.99
4013.09
4022.19
4031.29
4040.39
4049.49
4058.59
4067.69
4076.79
4085.89
4094.99
4104.09
4113.19
4122.29
4131.39
4140.49

2270.09
2275.78
2281.47
2287.16
2292.85
2298.54
2304.23
2309.92
2315.61
2321.30
2326.99
2332.68
2338.37
2344.06
2349.75
2355.44
2361.13
2366.82
2372.51
2378.20
2383.89
2389.58
2395.27
2400.96
2406.65
2412.34
2418.03
2423.72
2429.41
2435.10
2440.79
2446.48
2452.17
2457.86
2463.55
2469.24
2474.93
2480.62
2486.31
2492.00
2497.69
2503.38
2509.07
2514.76
2520.45
2526.14
2531.83
2537.52
2543.21
2548.90
2554.59
2560.28
2565.97
2571.66
2577.35
2583.04
2588.73

5338.45
5351.83
5365.21
5378.59
5391.97
5405.35
5418.73
5432.11
5445.49
5458.87
5472.25
5485.63
5499.01
5512.39
5525.77
5539.15
5552.53
5565.91
5579.29
5592.67
5606.05
5619.43
5632.81
5646.19
5659.57
5672.95
5686.33
5699.71
5713.09
5726.47
5739.85
5753.23
5766.61
5779.99
5793.37
5806.75
5820.13
5833.51
5846.89
5860.27
5873.65
5887.03
5900.41
5913.79
5927.17
5940.55
5953.93
5967.31
5980.69
5994.07
6007.45
6020.83
6034.21
6047.59
6060.97
6074.35
6087.73

2158.54
2163.95
2169.36
2174.77
2180.18
2185.59
2191.00
2196.41
2201.82
2207.23
2212.64
2218.05
2223.46
2228.87
2234.28
2239.69
2245.10
2250.51
2255.92
2261.33
2266.74
2272.15
2277.56
2282.97
2288.38
2293.79
2299.20
2304.61
2310.02
2315.43
2320.84
2326.25
2331.66
2337.07
2342.48
2347.89
2353.30
2358.71
2364.12
2369.53
2374.94
2380.35
2385.76
2391.17
2396.58
2401.99
2407.40
2412.81
2418.22
2423.63
2429.04
2434.45
2439.86
2445.27
2450.68
2456.09
2461.50

5833.27
5847.89
5862.51
5877.13
5891.75
5906.37
5920.99
5935.61
5950.23
5964.85
5979.47
5994.09
6008.71
6023.33
6037.95
6052.57
6067.19
6081.81
6096.43
6111.05
6125.67
6140.29
6154.91
6169.53
6184.15
6198.77
6213.39
6228.01
6242.63
6257.25
6271.87
6286.49
6301.11
6315.73
6330.35
6344.97
6359.59
6374.21
6388.83
6403.45
6418.07
6432.69
6447.31
6461.93
6476.55
6491.17
6505.79
6520.41
6535.03
6549.65
6564.27
6578.89
6593.51
6608.13
6622.75
6637.37
6651.99

451
452
453
454
455
456
457
458
459
460
461
462
463
464
465
466
467
468
469
470
471
472
473
474
475
476
477
478
479
480
481
482
483
484
485
486
487
488
489
490
491
492
493
494
495
496
497
498
499
500
501
502
503
504
505
506
507

451.00
452.00
453.00
454.00
455.00
456.00
457.00
458.00
459.00
460.00
461.00
462.00
463.00
464.00
465.00
466.00
467.00
468.00
469.00
470.00
471.00
472.00
473.00
474.00
475.00
476.00
477.00
478.00
479.00
480.00
481.00
482.00
483.00
484.00
485.00
486.00
487.00
488.00
489.00
490.00
491.00
492.00
493.00
494.00
495.00
496.00
497.00
498.00
499.00
500.00
501.00
502.00
503.00
504.00
505.00
506.00
507.00

4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19

4149.59
4158.69
4167.79
4176.89
4185.99
4195.09
4204.19
4213.29
4222.39
4231.49
4240.59
4249.69
4258.79
4267.89
4276.99
4286.09
4295.19
4304.29
4313.39
4322.49
4331.59
4340.69
4349.79
4358.89
4367.99
4377.09
4386.19
4395.29
4404.39
4413.49
4422.59
4431.69
4440.79
4449.89
4458.99
4468.09
4477.19
4486.29
4495.39
4504.49
4513.59
4522.69
4531.79
4540.89
4549.99
4559.09
4568.19
4577.29
4586.39
4595.49
4604.59
4613.69
4622.79
4631.89
4640.99
4650.09
4659.19

2594.42
2600.11
2605.80
2611.49
2617.18
2622.87
2628.56
2634.25
2639.94
2645.63
2651.32
2657.01
2662.70
2668.39
2674.08
2679.77
2685.46
2691.15
2696.84
2702.53
2708.22
2713.91
2719.60
2725.29
2730.98
2736.67
2742.36
2748.05
2753.74
2759.43
2765.12
2770.81
2776.50
2782.19
2787.88
2793.57
2799.26
2804.95
2810.64
2816.33
2822.02
2827.71
2833.40
2839.09
2844.78
2850.47
2856.16
2861.85
2867.54
2873.23
2878.92
2884.61
2890.30
2895.99
2901.68
2907.37
2913.06

6101.11
6114.49
6127.87
6141.25
6154.63
6168.01
6181.39
6194.77
6208.15
6221.53
6234.91
6248.29
6261.67
6275.05
6288.43
6301.81
6315.19
6328.57
6341.95
6355.33
6368.71
6382.09
6395.47
6408.85
6422.23
6435.61
6448.99
6462.37
6475.75
6489.13
6502.51
6515.89
6529.27
6542.65
6556.03
6569.41
6582.79
6596.17
6609.55
6622.93
6636.31
6649.69
6663.07
6676.45
6689.83
6703.21
6716.59
6729.97
6743.35
6756.73
6770.11
6783.49
6796.87
6810.25
6823.63
6837.01
6850.39

2466.91
2472.32
2477.73
2483.14
2488.55
2493.96
2499.37
2504.78
2510.19
2515.60
2521.01
2526.42
2531.83
2537.24
2542.65
2548.06
2553.47
2558.88
2564.29
2569.70
2575.11
2580.52
2585.93
2591.34
2596.75
2602.16
2607.57
2612.98
2618.39
2623.80
2629.21
2634.62
2640.03
2645.44
2650.85
2656.26
2661.67
2667.08
2672.49
2677.90
2683.31
2688.72
2694.13
2699.54
2704.95
2710.36
2715.77
2721.18
2726.59
2732.00
2737.41
2742.82
2748.23
2753.64
2759.05
2764.46
2769.87

6666.61
6681.23
6695.85
6710.47
6725.09
6739.71
6754.33
6768.95
6783.57
6798.19
6812.81
6827.43
6842.05
6856.67
6871.29
6885.91
6900.53
6915.15
6929.77
6944.39
6959.01
6973.63
6988.25
7002.87
7017.49
7032.11
7046.73
7061.35
7075.97
7090.59
7105.21
7119.83
7134.45
7149.07
7163.69
7178.31
7192.93
7207.55
7222.17
7236.79
7251.41
7266.03
7280.65
7295.27
7309.89
7324.51
7339.13
7353.75
7368.37
7382.99
7397.61
7412.23
7426.85
7441.47
7456.09
7470.71
7485.33

508
509
510
511
512
513
514
515

508.00
509.00
510.00
511.00
512.00
513.00
514.00
515.00

4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99

4668.29
4677.39
4686.49
4695.59
4704.69
4713.79
4722.89
4731.99

2918.75
2924.44
2930.13
2935.82
2941.51
2947.20
2952.89
2958.58

6863.77
6877.15
6890.53
6903.91
6917.29
6930.67
6944.05
6957.43

2775.28
2780.69
2786.10
2791.51
2796.92
2802.33
2807.74
2813.15

7499.95
7514.57
7529.19
7543.81
7558.43
7573.05
7587.67
7602.29

HIRE CHARGES OF MACHINERY


Hire
Fuel
Crew
Charges
Charges
Charges

Total

Per

a) Hire charges of Tipper 5.00


Cum capacity

446.70

296.30

166.70

909.70

Hour

b) Hire charges of Tipper 10


Tonnes capacity

414.10

296.30

166.70

877.10

Hour

c) Hire charges of Water Tanker


8000 Ltrs capacity

402.50

296.30

166.70

865.50

Hour

d) Hire charges of Truck 10


Tonnes capacity

414.10

296.30

166.70

877.10

Hour

e) Hire charges of FE loader


1.00 Cum bucket capacity @
45 Cum

414.10

296.30

166.70

877.10

Hour

1
2
3
4
5
A)
1

RATES FOR CONVEYANCE BY MACHINERY


Mincipal area allowance
Industrial area allowance
Agency area allowance
Allowable allowance
Add Overhead Charges & Contractor's Profit
For Earth/Gravel/Sand/Morrum/Lime/Surki (per Cum):
Lead up to 1 Km:
Out put
=
5.00 Cum
Rate
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
446.70
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
296.30
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs. 166.70
0.00 add area allowance at 0% on Rs.
25.01
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0% 27.29
on Rs.
Total rate for
1.00 Cum

2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

0.00%
0.00%
0.00%
0.00%
0.00%

Per
Hour
Hour
Hour

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

38.21

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.

Rate
446.70
296.30

Per
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00

Rs.

27.29

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00

Rs.

38.21

Rs.
Rs.

Amount
125.08
82.96

0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.


0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

61.86

Hour

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

72.78

Hour

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
5.00 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

50.94

1.00 Cum

5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

166.70
46.68

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

10.92

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
5.00 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.

46.68
0.00
254.72
50.94
0.00

Rs.

50.94

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
61.86
0.00

Rs.

61.86

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00

Rs.

72.78

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00

Rs.

10.92

Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00

Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

9.10

1.00 Cum

Rs.
Rs.
Rs.

45.50
9.1
0.00

Rs.

9.10

B) For Rubble/Size stones/Cut stones/Coarse aggregates (per Cum):


1 Lead up to 1 Km:
Out put
=
5.00 Cum
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
2 Lead up to 2 Km:
Out put
=
5.00 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

27.29

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

38.21

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
5.00 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
25.01

Rate
446.70
296.30
166.70
46.68

Per
Hour
Hour
Hour

50.94

Hour

1.00 Cum

4 Lead up to 4 Km:
Out put
=
5.00 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
27.29
0.00

Rs.

27.29

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
38.21
0.00

Rs.

38.21

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
50.94
0.00

Rs.

50.94

Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30

Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

72.78

Hour

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

10.92

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
5.00 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
66.68

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
5.00 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

5 Lead up to 5 Km:
Out put
=
5.00 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
5.00 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

61.86

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

9.10

1.00 Cum

Rs.
Rs.

61.86
0.00

Rs.

61.86

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
72.78
0.00

Rs.

72.78

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
10.92
0.00

Rs.

10.92

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
9.1
0.00

Rs.

9.10

C) For Cement/Steel/RCC poles/A.C & G.I sheets/Packed materials (per Tonne):


1 Lead up to 1 Km:
Out put
=
8.00 MT
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT

Rate
446.70
296.30
166.70
25.01

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47

Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
2 Lead up to 2 Km:
Out put
=
8.00 MT
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Per
Hour
Hour
Hour

23.88

Hour

Rate
446.70
296.30
166.70
46.68

Per
Hour
Hour
Hour

31.84

Hour

1.00 MT

4 Lead up to 4 Km:
Out put
=
8.00 MT
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
35.01

1.00 MT

3 Lead up to 3 Km:
Out put
=
8.00 MT
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

17.06

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

38.66

Hour

1.00 MT

5 Lead up to 5 Km:
Out put
=
8.00 MT
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

Rs.
Rs.

17.06
0.00

Rs.

17.06

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
23.88
0.00

Rs.

23.88

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
31.84
0.00

Rs.

31.84

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
38.66
0.00

Rs.

38.66

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
45.49

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

6.82

Hour

1.00 MT

7 Lead for every Km beyond 30 Km:


Out put
=
8.00 MT
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 MT

6 Lead for every Km from 5 to 30 Km:


Out put
=
8.00 MT
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
8.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

45.49

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

5.69

1.00 MT

Rs.

0.00

Rs.

45.49

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
6.82
0.00

Rs.

6.82

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
5.69
0.00

Rs.

5.69

D) For PCC Slabs/Shabad Slabs/CC & Laterite Blocks/Wood (per Cum):


1 Lead up to 1 Km:
Out put
=
3.40 Cum
0.15 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.15 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
2 Lead up to 2 Km:
Out put
=
3.40 Cum
0.21 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.21 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum

Rate
446.70
296.30
166.70
25.01

Per
Hour
Hour
Hour

40.14

Rate
446.70
296.30
166.70
35.01

Per
Hour
Hour
Hour

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
67.01
44.45
25.01
0.00
136.47
40.14
0.00

Rs.

40.14

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
93.81
62.22
35.01
0.00
191.04
56.19

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

Per
Hour
Hour
Hour

74.92

Hour

Rate
446.70
296.30
166.70
56.68

Per
Hour
Hour
Hour

90.97

Hour

1.00 Cum

5 Lead up to 5 Km:
Out put
=
3.40 Cum
0.40 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.40 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
46.68

1.00 Cum

4 Lead up to 4 Km:
Out put
=
3.40 Cum
0.34 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.34 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Hour

1.00 Cum

3 Lead up to 3 Km:
Out put
=
3.40 Cum
0.28 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.28 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

56.19

Rate
446.70
296.30
166.70
66.68

Per
Hour
Hour
Hour

107.02

Hour

1.00 Cum

6 Lead for every Km from 5 to 30 Km:


Out put
=
3.40 Cum
0.06 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.06 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum

Rate
446.70
296.30
166.70
10.00

Per
Hour
Hour
Hour

Rs.

0.00

Rs.

56.19

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
125.08
82.96
46.68
0.00
254.72
74.92
0.00

Rs.

74.92

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
151.88
100.74
56.68
0.00
309.30
90.97
0.00

Rs.

90.97

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
178.68
118.52
66.68
0.00
363.88
107.02
0.00

Rs.

107.02

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
26.80
17.78
10.00
0.00
54.58
16.05

0.00 add overheads and contractors profit at 0%


on Rs.
Total rate for

16.05

Hour

1.00 Cum

7 Lead for every Km beyond 30 Km:


Out put
=
3.40 Cum
0.05 Hrs. hire charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. fuel charges of Tipper 5.00 Cum @ Rs.
0.05 Hrs. crew charges of Tipper 5.00 Cum @ Rs.
0.00 add area allowance at 0% on Rs.
Rate for
3.40 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for

Rate
446.70
296.30
166.70
8.34

Per
Hour
Hour
Hour

13.38

1.00 Cum

E) For Water (per 1000 Ltrs):


1 Lead up to 1 Km:
Out put
=
8000 Ltrs
0.15 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

Rs.

0.00

Rs.

16.05

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

Amount
22.34
14.82
8.34
0.00
45.50
13.38
0.00

Rs.

13.38

Rate
402.50

Per
Hour

Rs.

Amount
60.38

0.15 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

44.45

0.15 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

25.01

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

25.01

Rs.
Rs.
Rs.
Rs.

0.00
129.84
16.23
0.00

Rs.

16.23

2 Lead up to 2 Km:
Out put
=
8000 Ltrs
0.21 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

16.23

Rate
402.50

Per
Hour

Rs.

Amount
84.53

0.21 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

62.22

0.21 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

35.01

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

35.01

Rs.
Rs.
Rs.
Rs.

0.00
181.76
22.72
0.00

Rs.

22.72

3 Lead up to 3 Km:
Out put
=

8000 Ltrs

22.72

Rate

Per

Amount

0.28 Hrs. hire charges of water tanker 8000 ltrs


capacity @ Rs.

402.50

Hour

Rs.

112.70

0.28 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

82.96

0.28 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

46.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

46.68

Rs.
Rs.
Rs.
Rs.

0.00
242.34
30.29
0.00

Rs.

30.29

4 Lead up to 4 Km:
Out put
=
8000 Ltrs
0.34 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

30.29

Rate
402.50

Per
Hour

Rs.

Amount
136.85

0.34 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

100.74

0.34 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

56.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

56.68

Rs.
Rs.
Rs.
Rs.

0.00
294.27
36.78
0.00

Rs.

36.78

5 Lead up to 5 Km:
Out put
=
8000 Ltrs
0.40 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

36.78

Rate
402.50

Per
Hour

Rs.

Amount
161.00

0.40 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

118.52

0.40 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

66.68

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

66.68

Rs.
Rs.
Rs.
Rs.

0.00
346.20
43.28
0.00

Rs.

43.28

6 Lead for every Km from 5 to 30 Km:


Out put
=
8000 Ltrs
0.06 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.
0.06 Hrs. fuel charges of water tanker 8000 ltrs
capacity @ Rs.

43.28

Rate
402.50

Per
Hour

Rs.

Amount
24.15

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

10.00

7 Lead for every Km beyond 30 Km:


Out put
=
8000 Ltrs
0.05 Hrs. hire charges of water tanker 8000 ltrs
capacity @ Rs.

Hour

6.49

Rs.

10.00

Rs.
Rs.
Rs.
Rs.

0.00
51.93
6.49
0.00

Rs.

6.49

Rate
402.50

Per
Hour

Rs.

Amount
20.13

0.05 Hrs. fuel charges of water tanker 8000 ltrs


capacity @ Rs.

296.30

Hour

Rs.

14.82

0.05 Hrs. crew charges of water tanker 8000 ltrs


capacity @ Rs.

166.70

Hour

Rs.

8.34

0.00 add area allowance at 0% on Rs.


Rate for
8000 Ltrs
Rate for
1000 Ltrs
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Ltrs

8.34

Rs.
Rs.
Rs.
Rs.

0.00
43.29
5.41
0.00

Rs.

5.41

F) For Bricks (per 1000 Nos):


1 Lead up to 1 Km:
Out put
=
3000 Nos
0.15 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

5.41

Rate
414.10

Per
Hour

Rs.

Amount
62.12

0.15 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

44.45

0.15 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

25.01

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

25.01

Rs.
Rs.
Rs.
Rs.

0.00
131.58
43.86
0.00

Rs.

43.86

2 Lead up to 2 Km:
Out put
=
3000 Nos
0.21 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

43.86

Rate
414.10

Per
Hour

Rs.

Amount
86.96

0.21 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

62.22

0.21 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

35.01

0.00 add area allowance at 0% on Rs.

35.01

Rs.

0.00

Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

Rs.
Rs.
Rs.

184.19
61.40
0.00

61.40

Rs.

61.40

3 Lead up to 3 Km:
Out put
=
3000 Nos
0.28 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

Rate
414.10

Per
Hour

Rs.

Amount
115.95

0.28 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

82.96

0.28 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

46.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

46.68

Rs.
Rs.
Rs.
Rs.

0.00
245.59
81.86
0.00

Rs.

81.86

4 Lead up to 4 Km:
Out put
=
3000 Nos
0.34 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

81.86

Rate
414.10

Per
Hour

Rs.

Amount
140.79

0.34 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

100.74

0.34 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

56.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

56.68

Rs.
Rs.
Rs.
Rs.

0.00
298.21
99.40
0.00

Rs.

99.40

5 Lead up to 5 Km:
Out put
=
3000 Nos
0.40 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

99.40

Rate
414.10

Per
Hour

Rs.

Amount
165.64

0.40 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

118.52

0.40 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

66.68

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.

66.68

Rs.
Rs.
Rs.
Rs.

0.00
350.84
116.95
0.00

116.95

Total rate for

1000 Nos

6 Lead for every Km beyond 5 Kms up to 30 Kms:


Out put
=
3000 Nos
0.06 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

Rs.

116.95

Rate
414.10

Per
Hour

Rs.

Amount
24.85

0.06 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

10.00

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

10.00

Rs.
Rs.
Rs.
Rs.

0.00
52.63
17.54
0.00

Rs.

17.54

7 Lead for every Km beyond 30 Kms:


Out put
=
3000 Nos
0.05 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

17.54

Rate
414.10

Per
Hour

Rs.

Amount
20.71

0.05 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

14.82

0.05 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

8.34

0.00 add area allowance at 0% on Rs.


Rate for
3000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

8.34

Rs.
Rs.
Rs.
Rs.

0.00
43.87
14.62
0.00

Rs.

14.62

14.62

LOADING & UNLOADING CHARGES BY MANUAL MEANS (EXCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

83.75

15.23

Per
day
day

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00

Rs.

15.23

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Labour:
0.005 day Head mazdoor
0.125 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

Rate

Per

375.00
320.00

day
day

41.88

7.61

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

1.88
40.00
41.88
0.00
41.88
41.88
7.61
0.00

Rs.

7.61

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for masonry work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
C) For Cement (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

Rate

Per

375.00
320.00

day
day

167.50

30.45

Rate

Per

375.00
320.00

day
day

83.75

15.23

Rate

Per

375.00
320.00

day
day

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

7.50
160.00
167.50
0.00
167.50
167.50
30.45
0.00

Rs.

30.45

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
15.23
0.00

Rs.

15.23

Amount
Rs.
Rs.

22.50
480.00

0.00 add area allowance at 0% on Rs.


Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
D) For Structural steel, Steel bars (per Tonne):
(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT
(ii) Unloading & Stacking charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.

502.50

50.25

Rate

Per

375.00
320.00

day
day

502.50

50.25

Rate

Per

375.00
320.00

day
day

602.25

60.23

Rate

Per

375.00
320.00

day
day

602.25

60.23

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

502.50
0.00
502.50
502.50
50.25
0.00

Rs.

50.25

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50
502.50
50.25
0.00

Rs.

50.25

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00

Rs.

60.23

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25
602.25
60.23
0.00

Total rate for

1.00 MT

E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos):


(i) Loading charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos
(ii) Unloading & Stacking charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

Rs.

Rate

Per

375.00
320.00

day
day

83.75

41.88

Rate

Per

375.00
320.00

day
day

83.75

41.88

60.23

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00

Rs.

41.88

Amount
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75
83.75
41.88
0.00

Rs.

41.88

LOADING & UNLOADING CHARGES BY MANUAL MEANS (INCLUDING IDLE HIRE CHARGES
OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Labour:
0.01 day Head mazdoor
375.00
0.25 day Mazdoor
320.00

Per

Amount

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

207.05

0.50 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

148.15

0.50 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

83.35

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.50 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

83.75

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum
(ii) Unloading charges:
Out put
=
5.50 Cum
a) Labour:
0.005 day Head mazdoor
0.125 day Mazdoor

83.35

94.96

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
438.55
522.30
522.30
94.96
0.00

Rs.

94.96

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

1.88
40.00
41.88
0.00
41.88

414.10

Hour

Rs.

68.74

0.166 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

49.19

0.166 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

27.67

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

27.67

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
145.60
187.48
187.48
34.09
0.00

Rs.

34.09

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.166 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

41.88

34.09

Amount

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Labour:
0.02 day Head mazdoor
0.50 day Mazdoor

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

7.50
160.00
167.50
0.00
167.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.50 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

167.50

414.10

Hour

Rs.

207.05

0.50 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

148.15

0.50 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

83.35

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor

Hour

110.19

Rs.

83.35

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
438.55
606.05
606.05
110.19
0.00

Rs.

110.19

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

103.53

0.25 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

74.08

0.25 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

41.68

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

41.68

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
219.29
303.04
303.04
55.1
0.00

Rs.

55.10

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
0.25 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

C) For Cement (per Tonne):


(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

83.75

55.10

Amount

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

502.50

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

(ii) Unloading & Stacking charges:


Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

Hour

137.96

Rs.

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1379.60
1379.60
137.96
0.00

Rs.

137.96

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

D) For Structural steel, Steel bars (per Tonne):


(i) Loading charges:
Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

147.94

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

(ii) Unloading & Stacking charges:


Out put
=
10.00 MT
a) Labour:
0.07 day Head mazdoor
1.80 day Mazdoor

Hour

147.94

Rs.

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

26.25
576.00
602.25
0.00
602.25

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

602.25

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
10.00 MT
Rate for
1.00 MT
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 MT

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1479.35
1479.35
147.94
0.00

Rs.

147.94

E) For Bricks of size 225 x 140 x 70mm (per 1000 Nos):


(i) Loading charges:
Out put
=
2000.00 Nos
a) Labour:
0.01 day Head mazdoor
0.25 day Mazdoor
0.00 add area allowance at 0% on Rs.
Total labour charges
b) Machinery:
0.33 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.
0.33 Hrs. fuel charges of Truck 10 Tonnes
capacity @ Rs.

147.94

Rate

Per

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

3.75
80.00
83.75
0.00
83.75

414.10

Hour

Rs.

136.65

296.30

Hour

Rs.

97.78

83.75

Amount

0.33 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

55.01

(ii) Unloading & Stacking charges:


Out put
=
2000.00 Nos
a) Labour:
0.06 day Head mazdoor
1.50 day Mazdoor

Hour

186.60

Rs.

55.01

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
289.44
373.19
373.19
186.60
0.00

Rs.

186.60

Rate

Per

Amount

375.00
320.00

day
day

Rs.
Rs.
Rs.
Rs.
Rs.

22.50
480.00
502.50
0.00
502.50

0.00 add area allowance at 0% on Rs.


Total labour charges
b) Machinery:
1.00 Hrs. hire charges of Truck 10 Tonnes
capacity @ Rs.

502.50

414.10

Hour

Rs.

414.10

1.00 Hrs. fuel charges of Truck 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

296.30

1.00 Hrs. crew charges of Truck 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

166.70

0.00 add area allowance at 0% on Rs.


Total machinery charges
Total labour and machinery charges
Rate for
2000 Nos
Rate for
1000 Nos
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1000 Nos

166.70

Rs.
Rs.
Rs.
Rs.
Rs.
Rs.

0.00
877.10
1379.60
1379.60
689.8
0.00

Rs.

689.80

689.80

LOADING & UNLOADING CHARGES BY MECHANICAL MEANS (INCLUDING IDLE HIRE


CHARGES OF TRUCKS)
A) For Earth, Sand, Morrum, Manure, Fly Ash (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
Rate
a) Machinery:
0.11 Hrs. hire charges of Tipper 10 Tonnes 414.10
capacity @ Rs.

Per

Amount

Hour

Rs.

45.55

0.11 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

32.59

0.11 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

18.34

0.06 Hrs. hire charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

414.10

Hour

Rs.

24.85

0.06 Hrs. fuel charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

296.30

Hour

Rs.

17.78

0.06 Hrs. crew charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

166.70

Hour

Rs.

10.00

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

28.34

Rs.
Rs.
Rs.
Rs.
Rs.

0.00
149.11
149.11
27.11
0.00

Rs.

27.11

(ii) Unloading charges:


Out put
=
5.50 Cum
a) Machinery:
0.08 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.

27.11

Rate

Per

414.10

Hour

Rs.

33.13

0.08 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

23.70

0.08 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

13.34

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum
Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

13.34

Rs.
Rs.
Rs.
Rs.
Rs.

0.00
70.17
70.17
12.76
0.00

Rs.

12.76

12.76

Amount

B) For Lime, Agrregate, Stone Boulder, Brick aggregate, Kankar, Building rubbish, Crushed
slag, Stone for machinery work (per Cum):
(i) Loading charges:
Out put
=
5.50 Cum
a) Machinery:
0.17 Hrs. hire charges of Tipper 10 Tonnes
capacity @ Rs.

Rate

Per

Amount

414.10

Hour

Rs.

70.40

0.17 Hrs. fuel charges of Tipper 10 Tonnes


capacity @ Rs.

296.30

Hour

Rs.

50.37

0.17 Hrs. crew charges of Tipper 10 Tonnes


capacity @ Rs.

166.70

Hour

Rs.

28.34

0.12 Hrs. hire charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

414.10

Hour

Rs.

49.69

0.12 Hrs. fuel charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

296.30

Hour

Rs.

35.56

0.12 Hrs. crew charges of FE loader 1.00 Cum


bucket capacity @ 45 Cum @ Rs.

166.70

Hour

Rs.

20.00

0.00 add area allowance at 0% on Rs.


Total machinery charges
Rate for
5.50 Cum

48.34

Rs.
Rs.
Rs.

0.00
254.36
254.36

Rate for
1.00 Cum
0.00 add overheads and contractors profit at 0%
on Rs.
Total rate for
1.00 Cum

46.25

Rs.
Rs.

46.25
0.00

Rs.

46.25

S-ar putea să vă placă și