StxTherm Eco
Application Guide
Introduction
StxTherm Eco
A silicone rendered system
suitable for low to medium rise
buildings such as terraced or
semi-detached housing.
1. Substrate
2. Adhesive mortar
3. Grey EPS insulation board
4. Mineralic reinforcing coat
1 2 3
4 5
6 7
General information
It is to be noted that the details, illustrations, general technical information
and drawings contained on the following pages only represent general
suggestions and details which serve solely to outline the essential modes
of functioning of the products concerned. No dimensional exact tolerances
apply. The applicator/client is responsible for verifying the applicability and
completeness of the system in the specific construction project concerned.
Adjacent trades are shown in schematic form only. All specifications and
details are to be adapted according to the on-site situation and do not
constitute detailed or installation planning for the respective trades. The
technical specifications and information on the products in the technical
data sheets and in the system descriptions/approvals must be observed.
Checklist
Materials Checklist
Starter track, full system stop beads,
reinforcing coat
Stomix primer
Equipment Checklist
Gloves, overalls, masks, goggles,
Gauging trowels
hardhats, boots
Smoothing trowels
Hammer
Texturing trowels
reinforcing coat
and beads
primer
Contents | 3
Application Procedure
Substrate Preparation
1 Test existing surfaces
Remove or repair non-loadbearing
coatings. Use a fungal wash to remove
existing algae or mould growth.
2 Fix the starter track
Fixings at maximum 300mm centres
and in hole nearest to the end of the
starter track.
Use packing shims to ensure the
track is level with the wall.
Fix full system stop beads if specified.
3 Prepare the Stomix Multibond
Add each sack of Stomix Multibond to
between 6.0 to 6.75 litres of water.
Mix for 2-10 minutes to a smooth
consistency. Allow to mature for 10
minutes and then briefly stir again.
4 | Application Procedure
Application Procedure
Filling & Rasping the Insulation
7 Fill any gaps between boards with
PU Filler Foam
8 Allow the adhesive to set
Leave to set for a minimum of 24
hours. More time may be required in
low temperatures or high humidity.
Protect the surface from rain.
9 Rasp the entire surface of the EPS
This creates a flat surface and provides
a key. Pay particular attention to board
joints.
Application Procedure | 5
Application Procedure
Apply Mesh and Primer
13 Trowel the reinforcing mesh into
the wet material
Ensure it is covered completely. All
mesh overlaps must be a minimum of
100mm.
14 Trowel smooth
Ensure a perfectly flat and even surface
by using a wide levelling trowel
(butterfly knife).
15 Allow to set for at least 24 hours
Low temperatures and/or high humidity
may increase the setting/drying time
to 48 hours or more. Protect the work
from rain.
16 Apply Stomix Primer to the entire
dry surface with a brush or roller
Allow to dry for at least 12 hours, or
longer in periods of low temperatures/
high humidity.
Stomix Primer may be diluted with
up to max. 0.9l water per pail to aid
workability.
6 | Application Procedure
Application Procedure
Apply the Render Finish
17 Apply Stomix Silkotex
Apply the Stomix Silkotex render finish
directly onto the dry primer with a
trowel or spray application machine.
Stomix Silkotex may be diluted with
up to 2% clean water to achieve a
working consistency. Ensure the same
amount of water is added to each pail
of the same batch.
Application should be to an entire
elevation or between natural
breaks (corners, stop beads, behind
downpipes, etc.) in one single
operation.
Application Procedure | 7
Head Office
Sto Ltd.
Sto Ltd.
2 Gordon Avenue
Antura
Hillington Park
Wade Road
Tel
Tel
info.uk@sto.com
www.sto.co.uk
Midlands Training & Distribution Centre
www.stomix.co.uk
Sto Ltd.
Unit 700
Catesby Park
Kings Norton
Birmingham B38 8SE
Tel