Documente Academic
Documente Profesional
Documente Cultură
Sri C. Sawmliana
Dr. P. Pal Roy
Scientists
Blasting Department
Central Mining Research Institute, Dhanbad, India
ABSTRACT
Blasting Gallery (BG) method was introduced in India for higher production and low cost of excavation
to substitute conventional hand section and stowing methods for thick coal seam. The Singareni
Collieries Company Ltd. (SCCL) adopted this method in the year 1989 and since then successfully
operating at GDK-10, GDK-8 & VK-7 Incline mines in Andra Pradesh, a southern state of India. It is
also successful at Chora 10 Pit Colliery of Eastern Coalfields Ltd. (ECL) in West Bengal whereas at
East Katras Colliery of Bharat Coking Coal Ltd. (BCCL) in Jharkhand State, the method has been
partially successful due to some geological constraints of the area.
An important aspect of BG method of extraction is the fragmentation of blasted coal which should be at
optimum level so that they can easily be lifted totally by remote controlled LHDs thereby mitigating the
possibility of occurrence of spontaneous heating in BG districts before exhaustion of the panel.
Central Mining Research Institute (CMRI) undertook one S&T Project sponsored by the Ministry of
Coal and Mines, Govt. of India to study this sensitive problem in order to evolve suggestive guidelines
of design patterns under varying geomining and site constrains. Under such scheme, a total of 180 ringblasts were conducted at different sites and thoroughly monitored for establishing optimum design
patterns. Different drill designs, staggered charging patterns, use of smaller and bigger spacers while
charging, strata monitoring and blast damage index were the key parameters mostly concentrated upon.
This paper briefs the scientific approaches and consequent field investigations followed during trial
blasts to improve fragmentation of coal to a significant level at reduced charge.
1. INTRODUCTION
In India, recent estimates indicate that several thousand million tonnes of coal are locked up in
underground pillars and a good proportion of which is in seam thicker than 4 m. Extraction of thick
seams by conventional hand section is neither productive nor effective from the conservation point of
1 of 14
view. The percentage of extraction by hand section mining in thick seams is as low as 25 - 30%. Lot of
good grade of coal has been lost and million tonnes are standing on pillars. Sand stowing for working of
thick seams cannot be considered as an option because the cost is prohibitive. Sand has become an
increasingly scarce commodity along with timber. At the same time, the coal industry was in search of
an economic method for dealing with standing thick seam pillars. As a solution, Blasting Gallery (BG)
method was tried as one of the supplemental measures. The Singareni Collieries Company Ltd. (SCCL)
adopted this method in the year 1989 and since then successfully implemented at GDK-10, GDK-8 &
VK-7 Incline mines. It was also adopted at Chora lo-Pit colliery of Eastern Coalfields Ltd. (ECL), and
East Katras Colliery of Bharat Coking Coal Ltd. (BCCL).
Blasting Gallery method is a French technique for winning of thick coal seam. The Charbonnage de
France (CdF) introduced this technique in India for gentle gradient of seam (less than 1 in 6 or 9) with
thickness varying from 6.5 - 12.0 m. In this method, total seam thickness is extracted in one go by
drilling a set of drillholes in a ring pattern (Figure-l/b). The blasted coal is loaded out from the goaf by
remote controlled LHD and subsequently unloads to chain conveyor. From the chain conveyor, the coal
is then fed into the lump breaker where they are broken into (<) 200 mm sizes. Finally, the coal is
transported to the surface from underground through a series of belt conveyors.
In Blasting Gallery Method, fragmentation of coal plays a very important role for higher production and
better performance of LHDs in the panel. Good fragmentation results in higher production and
increased efficiency of LHDs performance. Also more percentage of blasted coal can be recovered
from the goaf area thereby, reducing chances of spontaneous heating in the goaf. Whereas, poor
fragmentation lowers productivity in that it requires secondary blasting. Also, pneumatic stone breaker
is used to clear the coal lump onto the chain conveyor.
Extensive field investigations were carried out at VK-7, GDK-8 and GDK-10 Incline mines of M/s
Singareni Collieries Company Ltd. (SCCL), Andhra Pradesh and at Chora-10 Pit Colliery of M/s
Eastern Coalfields Ltd. (ECL), West Bengal. In SCCL, because of hard coal, fragmentation problems
were seen to be predominant excepting at VK-7 Incline, where the problem was comparatively lesser.
During investigations, special attention was paid to identify the causes of poor fragmentation and
boulder formation during ringhole blasting. Large number of trial blasts was conducted using staggered
charging patterns with the help of smaller and larger spacers for better fragmentation. Based on such
trials, different causes of boulder formations were critically analyzed and consequent trials were
conducted. Modified patterns were evolved by rectifying drilling and charging patterns for improved
fragmentation.
Drilling is done by crawler mounted electro-hydraulic Jumbo drill, which can drill at any angle in the
vertical plane. As BG method envisages drilling of holes in a fan cut pattern, length of holes depends on
their position and the seam thickness. During experimental trials, it was seen to vary between 2 and 14.5
m. When the top section is already developed, a thin parting of 0.3 to 0.5 m of coal is left during drilling
2 of 14
to get better impact of gas energy, which would otherwise puncture the gallery and venting of gases may
occur.
The Jumbo drill machine can drill up to 30 m long incline holes with a speed of 1 m per minute. The
drill rods are 1.13 m long with connecting features (female types) at the ends. The drill rods are provided
with a longitudinal central hole to facilitate wet drilling. Water at the rate of 2.5 m3/hr under a pressure
of 8 - 10 bars is flushed during drilling to clean drill-cuttings out of the hole. This minimizes pollution
from coal/rock dust during drilling operation. The diameters of drillrod and drillbit are respectively 32
and 34 mm. The finished hole diameter is around 43 mm.
During trials, on an average, 19 - 24 (for half ring) and 34 -39 (for full ring) holes were drilled in a ring
pattern (Figure-l/b). All the holes were drilled in the roof leaning towards the goaf line at 55 -60 (55
average) from horizontal (Figure-l/a) and 45 towards the goaf from the pillar side. The holes in the
roof were drilled up to the seam thickness leaving 0.3 m parting in the roof. Whereas, holes in the side
pillars were drilled in such a manner that they covered nearly half of the pillar on both dip and rise sides
from the gallery where Jumbo was operating. A curtain of about 1.5 m in the middle of each pillar was
left after such drilling to facilitate safe loading by LHDs. However, it was observed that this curtain falls
automatically in successive blasting round. The distance between the two consecutive rings was
maintained at about 1.5 m.
STONE ROOF
COAL SEAM
FLOOR
/
-+A
FLOOR
141-m A
FLOOR
3 of 14
:
:
:
..
..
..
..
4 of 14
..
600 mm
190 mm
3.4: Detonators
3.5: Spacers
inner =
2.4 cm
0 outer = 2.5 cm
50 cm
60 cm
(li*l,r =
(A) Longer Spacer
3.4
Clll, (Iouter =
3.5 cm
H
(B) & (C) Shorter spacers
4. CASE STUDIES
As mentioned earlier, field investigations were conducted in three mines of M/s SCCL and one mine of
M/s ECL. In VK-7 incline (SCCL) and Chora-10 Pit colliery (ECL), the problem of fragmentation was ,
insignificant as compared to GDK-8 and 10 Incline mines in Ramagundem area. As such, focus was
predominantly given to these later two mines to rectify fragmentation problem which were seriously
hampering production and productivity.
5 of 14
Instantaneous
Details of A portion
6 of 14
7 of 14
Sources of boulder
formation due to
wide gap at corners
Stook after
blastim\
Boulder
Sources
Stook after
blasting
..........
/
/
/
/
.
f
of adjacent
room
B l a s t i n g zone of
adjacent room
Designed
drink (0 7%
DesGed
stook (0.75)
8 of 14
Insufficient hole depths at both dip and rise sides of the gallery also results formation of large stook
pillar. This case was distinctly observed in 63 level of the panel where big stook was standing in
between 63 Level and 63A Level. Such occurrence may result in poor percentage of coal recovery and
more chance of spontaneous heating of coal inside the goaf area.
5.1.3: Spacing of holes
Spacing between holes is an important parameter for controlling fragmentation. Irregular and uneven
spacing may lead to boulder formation. The recommended spacing between holes is 30 - 35 cm.
9 of 14
(9
Correction of Drilling Errors: All the Jumbo operators were cautioned by telling that the
main reason of bolder formation was due to improper drilling. They were advised to strictly
maintain the proper depth of successive holes and angle alignment specially at the corners of
the gallery.
(ii)
Charging of Holes: All shot-firers were advised to charge the shot holes as per guidelines.
Like Jumbo operators, they were also cautioned about any sort of negligence.
(iii)
Prevention Against Misfire: To prevent misfire, oblique initiation pattern was suggested.
The entire detonating cord should remain within the shot hole in-bye of the stemming
material. The detonator and the detonating cord should remain in contact throughout the
length of the detonator inside the primed cartridge. The detonating cord should be tied with
the explosive cartridges with adhesive tape. Only direct initiation should be used and the
detonator shall be put in the outermost cartridge.
(iv)
Adjustment of Spacing between Holes: The spacing between holes at the gallery sides were
adjusted to 0.3 m for all the holes.
09
Proper Stemming: Holes should be properly stemmed to prevent any sort of blown-out-shot.
At least 0.75 m stemming with clay plugs is required for proper impact.
10 of 14
Carb sandstone
1.82m
2.75 m
C O A L
Shale, Carb sandstone
Carb shale, Shaly coal
6.09 m
No. 3 SEAM
COAL
11.28 m
[ (Bottom Section1
Grev sandstone
Fig. 8: Cross sectional view of coal seam at BG-II in GKK-8 Incline mine
11 of 14
16
17
Fig. 9: Staggered charging pattern using smaller and bigger spacers in the
top and bottom parts of the seam for split level gallery
19.75 m
___I__) lin8
Fig. 10: Staggered charging pattern using smaller and bigger spacers in the top
and bottom parts of the seam for developed level gallery
12 of 14
7. CONCLUSIONS
Based on the field observations, one of the main reasons for poor fragmentation during ring blast in
Blasting Gallery method was determined as the improper drilling and charging of holes. Improper
charging of holes can result in misfire and consequent generation of oversize boulders. Due to restriction
of explosive charge per hole (maximum limit of 3.0 kg), it may not be always possible, all the time, to
achieve best fragmentation for reasonably thicker coal seam. However, if the modifications and design
patterns described in the text are followed, overall better fragmentation may be achieved. The presence
of stone band in the coal seam usually gives rise to fragmentation problem. Staggered pattern of
charging using smaller (290 mm) and larger (600 mm) spacers found to produce excellent
fragmentation.
REFERENCES
1. CMRI Interim Report (GAP/3O/MT/MOC/Ol-02): Investigations to optimize blast design and
charge loading parameters in coal for ringhole blasting and in stone for induced blasting in
degree-I seams for blasting gallery method in underground mines of VK-7 Incline, Kothagudem
Area, The Singareni Collieries Company Limited (SCCL), Ministry of Coal and Mines,
Government of India, New Delhi, July 2001, p.61.
2. CMRI Interim Report (GAP/3O/MT/MOC/Ol-02): Investigations to optimize blast design and
charge loading parameters in coal for ringhole blasting and in stone for induced blasting in
degree-I seams for blasting gallery method in underground mines of GDK-8 Incline, RG-II Area,
The Singareni Collieries Company Limited (SCCL), Ministry of Coal and Mines, Government
of India, New Delhi, November 2001, p.68.
3. CMRI Interim Report (GAP/3O/MT/MOC/Ol-02): Investigations to optimize blast design and
charge loading parameters in coal for ringhole blasting and in stone for induced blasting in
degree-I seams for blasting gallery method in underground mines of GDK-10 Incline, RG-II
Area, The Singareni Collieries Company Limited (SCCL), Ministry of Coal & Mines,
Government of India, New Delhi, July, 2002, p.70.
13 of 14
14 of 14