UNRESTRICTED
Aug-10
User Note:
The requirements of this document are mandatory. Non-compliance shall only be authorised by
the Document Owner or his Delegate through STEP-OUT approval.
A controlled copy of the current version of this document is on PDO's EDMS. Before making
reference to this document, it is the user's responsibility to ensure that any hard copy, or
electronic copy, is current. For assistance, contact the Document Custodian or the Document
Controller.
Users are encouraged to participate in the ongoing improvement of this document by providing
constructive feedback.
Please familiarise yourself with the
Document Security Classification Definitions
They also apply to this Document!
This document is the property of Petroleum Development Oman LLC. Neither the whole nor
any part of this document may be disclosed to others or reproduced, stored in a retrieval
system, or transmitted in any form by any means (electronic, mechanical, reprographic
recording or otherwise) without prior written consent of the owner
Revision: 4.0
Effective: Aug-10
Page 2
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Document Authorisation
Page 3
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of all
revisions prior to these are held on file by the issuing department.
Revision No.
Date
Author
Scope / Remarks
4.0
Aug-10
Full
Revision.
Main
additions
alignment
of
Non-SCE
Activity
Variance and addition of FSR for SCE
Deviation
3.0
Dec. 01
Leo de Best
2.0
Apr. 99
Shaun Wilson,
OMO/4
Revision.
1.0
Mar. '98
Shaun Wilson,
OTT/331
Page 4
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
TABLE OF CONTENTS
1
Introduction........................................................................................................................... 3
1.1
Background..................................................................................................................... 3
1.2
Purpose........................................................................................................................... 3
1.3
1.4
1.5
Step-out Approval............................................................................................................ 3
3.1.1
Overview................................................................................................................... 3
3.1.2
Compliance Category............................................................................................... 3
3.1.3
Planning.................................................................................................................... 3
3.1.4
3.2
3.2.1
Overview................................................................................................................... 3
3.2.2
FIGURES
Figure 1 - Compliance and Planning Dates and Data..............................................................9
Figure 2 Maintenance and Inspection Activity Variance Control Process Flow....................11
Figure 3 High Level SCE Deviation Process.......................................................................13
Page 5
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Introduction
1.1
Background
Revision: 4.0
Effective: Aug-10
1.2
Purpose
The purpose of this procedure is to define the processes to ensure that scheduled
maintenance and / or inspection tasks that cannot be carried out or completed within
the planned period + tolerance, are recorded and re-scheduled as appropriate.
1.3
1.4
Production Coordinators
Page 6
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Step-out Approval
Not applicable for this procedure.
Page 7
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Delivery Team
Leader
Advise Maintenance
Variance
Corporate Discipline
Focal Point
Technical Authority /
Discipline Engineer
Area Planning
Engineer
Area Planner
Maintenance
Coordinator
Maintenance
Supervisor
Production
Coordinator /
Page 8
Coordinator
of
Activity
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
3.1
Overview
All surface facilities maintenance and inspection tasks contained within the CMMS, in
particular those that are Integrity Critical, are required to be executed within a given
time span in order to ensure that Design Integrity is maintained. This time span is
calculated in CMMS from the data entered and is referred to as the 'Deviation Range'.
Page 9
Original Due Start 04-12-2007. This is the date planned in CMMS for the
work to be undertaken.
Original Due Finish 04-12-2007. This is the date planned in CMMS for the
work to be completed and signed off.
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
The work has been allowed a deviation range of 73 days called the Tolerance in
days. This is a function of the Compliance Category and interprets in this illustration
to an allowance of 73 days to plan the start of the work from the Original Due Start.
Based on this the Original Latest Allowed Start Date (OLASD) becomes 15-022008. This is original due start + 73 days. If the work were to be completed within the
deviation range then the Original Latest Allowed Finish Date (OLAFD) would be
15-02-2008.
However in Figure 1 the Latest Allowed Start Date is still 15-02-2008 but the Latest
Allowed Finish Date is 31-12-2009 which indicates that an Activity Variance has been
applied to the work.
Effectively this means that the required external inspection of the vessel can be
deferred until 31-12-2009 before the vessel is no longer in compliance and requires to
be removed from service.
Compliance Category
The compliance category is obtained from a data base which lists the task lists and the
deviation band allowed. The deviation bands will be reviewed and approved by the
Corporate Discipline Focal Point (CDFP) at least every two years. The compliance
category is used to develop the tolerance period.
Planning
The CMMS can produce look-ahead plans for two years and 90 days which the IAP
planner will use to minimise deferment and optimise resources.
As previously stated all CMMS Work Order (WO) will have an original due start and
an original due finish. The maintenance team and /or the planning team will use these
dates to best utilise the resources available by implementing as required the inclusion
of the deviation range. Movement of start and finish dates with in the deviation range
is termed as Planned Start for maintenance and Extended Date for inspection.
However should the work be scheduled for whatever reason outside of the deviation
range then approval is required from the CDFP. The approval is an integral part of the
Z6 Notification process as detailed in PR-1528 Z6 Notification Procedure.
Once approved by this process a new Latest Allowed Start and / or Finish dates will be
given. Provided the work is completed within the Activity Variance time period
compliance will not be affected. Failure to complete within the Latest Allowed Finish
date will take the maintenance or inspection task out of compliance and result in the
system, unit or plant being taken out of services.
Page 10
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
WOs are issued from CMMS before the due start date to enable the work to be
planned. The work is scheduled by the planner into the IAP.
NOTE: This applies to breakdown maintenance as well.
2.
The WO will be reviewed by the Maintenance and Planning Team and the work
prioritised for execution with the deviation range, but before the latest allowable
finish date.
In the case of WOs raised for breakdown maintenance the above will still apply.
The WO will have a latest allowable finish date which must be met for the item to
remain in compliance.
3.
Page 11
If, for sound business reasons, the WO cannot be completed by the latest allowable
finish date (including the deviation range), then an Activity Variance will require to
be raised. The process for this activity can be referenced in PR-1528 Z6
PR-1005 - Maintenance and Inspection Activity and
Deviation Variance Control
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Approval of the Z6 by the CDFP will enable a new latest allowable start and / or
finish date to be entered into CMMS and a new updated WO issued.
5.
The work will be scheduled to start on or before the latest allowable start date and to
be completed by the latest allowable finish date.
6.
On completion of the work the WO will be closed out and the CMMS history
updated.
End of Process
3.2
Overview
The acronym FSR stands for Facility Status Report. This sub-section does not intend to
reproduce the web pages that can be accessed from the following link FSR.
A fundamental principle in the management of technical integrity is that our facilities
have been designed so that the risk of failure endangering the safety of personnel,
environment or asset value is . Failure to undertake critical maintenance and
inspection by the latest allowable finish date would constitute a failure to meet
the standard.
FSR has been designed as tool to support the business and manage the technical
integrity of its facilities, by providing 3 main functions:
1.
2.
Provide FSR flags and monitors those items that require action.
3.
Controlling Deviation
Page 12
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
A risk assessment using the Risk Assessment Matrix (RAM) is carried out on the SCE
that has entered, or is about to enter non-compliance. The risk assessment uses PEAR
to provide the overall risk severity. All information including the participants of the risk
assessment is entered in FSR.
Mitigation Actions
Following the risk assessment mitigation will be proposed to address the findings and
reduce the risks to ALARP. The mitigation implemented will be reviewed and recorded.
Execute Mitigation Action
This is outside of FSR and is reliant on close inspection and monitoring to ensure that
all required measures identified to reduce the risk of an incident are implemented.
Review and Approval
FSR is configured to provide a Key Reviewer for each type of SCE, who will have the
correct level of technical authority and experience. All reviewer can also nominate
additional reviewers if and as required.
Documentation to back up the deviation can be attached and sent via a work flow to
the appropriate reviewers.
Repairs or modification that may be recommended to support the deviation and will
require to have a standard provided or an existing standard modified. The standard
requires to be approved by the appropriate technical authority before the deviation can
be approved.
When all the required information has been entered in the FSR and the FSR creator
submit the deviation, automatic email with FSR link will be sent to the reviewers. Once
all reviewers acknolowedged the deviation, the final deviation will be transmitted,
depending in the risk, to the right party for final approval.
For Low to Medium risk deviations this will be the Delivery Team Leader or equivalent
and for High risk deviations the Operations Manager.
Once the FSR deviation approved, the LAFD will be reflected in CCMS and the item
will be shifted to the deviation column in FSR screen
Page 14
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Deviation Ranges
Page 15
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Appendix 2 - Abbreviations
The following abbreviations are used in this Procedure.
CDFP
CMMS
FSR
IAP
LAFD
OLAFD
OLASD
PEAR
RAM
SCE
TA
Technical Authority
WO
Work Order
Page 16
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
CP-156
Procedure
PR-1528
Z6 Notification Procedure
PR-1721
Shutdown Management
On-Line Help
Facility Status Reporting
Shell Process
EP 2009-9009 Safety Critical Element Management.
Page 17
Printed 15/08/10
The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.
Revision: 4.0
Effective: Aug-10
Date:
Brief Description of Change Required and Reasons
UOM2
Custodian of Document
Page 18
Date:
Printed 15/08/10