Petroleum Development Oman L.L.C.

UNRESTRICTED
Aug-10

Document ID: PR-1005


Filing Key: Business Control

Engineering and Operations


Maintenance and Inspection
Activity Variance and
Deviation Control

User Note:
The requirements of this document are mandatory. Non-compliance shall only be authorised by
the Document Owner or his Delegate through STEP-OUT approval.
A controlled copy of the current version of this document is on PDO's EDMS. Before making
reference to this document, it is the user's responsibility to ensure that any hard copy, or
electronic copy, is current. For assistance, contact the Document Custodian or the Document
Controller.
Users are encouraged to participate in the ongoing improvement of this document by providing
constructive feedback.
Please familiarise yourself with the
Document Security Classification Definitions
They also apply to this Document!

This document is the property of Petroleum Development Oman LLC. Neither the whole nor
any part of this document may be disclosed to others or reproduced, stored in a retrieval
system, or transmitted in any form by any means (electronic, mechanical, reprographic
recording or otherwise) without prior written consent of the owner

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

This page was intentionally left blank

Page 2

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Document Authorisation

Authorised For Issue August 2010

Page 3

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

ii Revision History
The following is a brief summary of the 4 most recent revisions to this document. Details of all
revisions prior to these are held on file by the issuing department.
Revision No.

Date

Author

Scope / Remarks

4.0

Aug-10

Robin Norman UOP6

Full
Revision.
Main
additions
alignment
of
Non-SCE
Activity
Variance and addition of FSR for SCE
Deviation

3.0

Dec. 01

Leo de Best

Alignment of deviation bands to SAP


PM work order management

2.0

Apr. 99

Shaun Wilson,
OMO/4

Revision.

1.0

Mar. '98

Shaun Wilson,
OTT/331

New Procedure - Initial Issue.

iii Related Business Processes


Code
EP72

Business Process (EPBM 4.0)


Maintain and Assure Facilities Integrity

iv Related Corporate Management Frame Work (CMF)


Documents
The related CMF Documents can be retrieved from the CMF Business Control Portal.
Refer to Appendix 3 Reference Material

Page 4

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

TABLE OF CONTENTS
1

Introduction........................................................................................................................... 3
1.1

Background..................................................................................................................... 3

1.2

Purpose........................................................................................................................... 3

1.3

Distribution / Target Audience.......................................................................................... 3

1.4

Changes to the Document............................................................................................... 3

1.5

Step-out Approval............................................................................................................ 3

Roles and Responsibilities.................................................................................................... 3

Maintenance and Inspection Activity Variance and Deviation Control..................................3


3.1

Non-SCE Variance Control.............................................................................................. 3

3.1.1

Overview................................................................................................................... 3

3.1.2

Compliance Category............................................................................................... 3

3.1.3

Planning.................................................................................................................... 3

3.1.4

Non-SCE Maintenance and Inspection Activity Variance Control Process...............3

3.2

SCE Deviation Control.................................................................................................... 3

3.2.1

Overview................................................................................................................... 3

3.2.2

SCE Maintenance and Inspection Deviation Control Process..................................3

Appendix 1 Maintenance and Inspection Deviation Ranges.....................................................3


Appendix 2 - Abbreviations.......................................................................................................... 3
Appendix 3 Reference Material................................................................................................. 3
Appendix 4 - User Feedback Page.............................................................................................. 3

FIGURES
Figure 1 - Compliance and Planning Dates and Data..............................................................9
Figure 2 Maintenance and Inspection Activity Variance Control Process Flow....................11
Figure 3 High Level SCE Deviation Process.......................................................................13

Page 5

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Introduction

1.1

Background

Revision: 4.0
Effective: Aug-10

Maintainable Items in the Asset Register are recorded in the Computerised


Maintenance Management System (CMMS) . Each maintainable item will be allocated
a maintenance and / or inspection routine which will be managed and maintained by
the CMMS. Within the CMMS, Safety Critical Equipment (SCE) is identified and
recorded. Refer to EP 2009-9009 Safety Critical Element Management.
The maintenance and inspection tasks allocated to each item of equipment, SCE or
Non-SCE, will have specific periodicity and dates for the execution of the maintenance
and / or inspection task. These tasks and their due dates will be used by the area
planner to build the Integrated Activity Planning (IAP) plan.
At the lower level each task will be assigned a compliance category or tolerance which
provides float for the activity and is applied to the completion date of the task. Tasks
that cannot be started to complete or be completed by the planned duration plus the
tolerance are considered as not in compliance and will require an activity variance to
be raised.

1.2

Purpose
The purpose of this procedure is to define the processes to ensure that scheduled
maintenance and / or inspection tasks that cannot be carried out or completed within
the planned period + tolerance, are recorded and re-scheduled as appropriate.

1.3

Distribution / Target Audience


This procedure targets and should be distributed to:

1.4

Delivery Team Leaders

Maintenance Coordinators and Supervisors

Production Coordinators

Integrated Activity Planning Team Leaders / Planning Engineers / Area


Planners

Corporate Discipline Focal Points

Discipline Engineers / Technical Authority

Maintenance Strategy and Support Teams

Changes to the Document


Responsibility for the upkeep of the Document shall be with the Functional
Maintenance and Integrity Management Team Leader UOM, the Owner. Changes to
this document shall only be authorised and approved by the Owner.
Users of the Document who identify changes, revisions or update requirements can
notify the Custodian or his / her delegate and request changes be initiated. The
Requests shall be forwarded to the Custodian using the User Feedback Page provided
in this Document.
The Document Custodian on behalf of the Document Owner shall ensure review and
re-verification of this procedure every 3 years.

Page 6

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC


1.5

Revision: 4.0
Effective: Aug-10

Step-out Approval
Not applicable for this procedure.

Page 7

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 4.0
Effective: Aug-10

Petroleum Development Oman LLC

Roles and Responsibilities


Operations Manager

Approve FSR Deviation (High Risk)

Delivery Team
Leader

Approve FSR Deviation (Low and Medium Risk)

Provide input at Maintenance Challenge Meeting

Accountable for the adherence to the planning of


activities and execution within the deviation bands

Approve Z6 Notification for Non-SCE changes

Review FSR Deviation request

Approve SCE Standard

Reviewing FSR Deviation request

Developing Technical Standards when required

Schedule maintenance and inspection task(s) to


realise opportunities

Provide input at Maintenance Challenge Meeting

Raise Z6 Notification for look ahead maintenance

Create FSR deviation request for SCE as required

Schedules the Maintenance and Inspection tasks


into weekly or monthly plans

Integrates Contractor schedules

Chairs the Maintenance Challenge Meeting

Create FSR Deviation request

Advise Maintenance
Variance

Raise Z6 Notification for Non-SCE changes

Create FSR Deviation request

Attends Maintenance Challenge Meeting

Create FSR Deviation request

Corporate Discipline
Focal Point

Technical Authority /
Discipline Engineer

Area Planning
Engineer

Area Planner

Maintenance
Coordinator

Maintenance
Supervisor

Production
Coordinator /

Page 8

Coordinator

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

of

Activity

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Maintenance and Inspection Activity Variance and


Deviation Control
There are two methods for controlling Variance and Deviation Activities, one being
applied to non-SCEs and the other to SCEs. Non-SCEs are recorded and controlled
using the Z6 Notification and SCEs through the Facilities Status Report (FSR). The Z6
is an integral function of the CMMS, whereas the FSR is an external Web Based
application that interfaces with CMMS.
Further Reference should be made to PR-1528 Z6 Notification Procedure and
Facilities Status Report for more detailed descriptions.

3.1

Non-SCE Variance Control

Overview
All surface facilities maintenance and inspection tasks contained within the CMMS, in
particular those that are Integrity Critical, are required to be executed within a given
time span in order to ensure that Design Integrity is maintained. This time span is
calculated in CMMS from the data entered and is referred to as the 'Deviation Range'.

Figure 1 - Compliance and Planning Dates and Data


Referring to Figure 1 the deviation range is defined as the maximum period, from the
Original Start Date on a work order, within which an activity may be rescheduled,
without the need for further approval or action.

Page 9

Original Due Start 04-12-2007. This is the date planned in CMMS for the
work to be undertaken.

Original Due Finish 04-12-2007. This is the date planned in CMMS for the
work to be completed and signed off.

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

The work has been allowed a deviation range of 73 days called the Tolerance in
days. This is a function of the Compliance Category and interprets in this illustration
to an allowance of 73 days to plan the start of the work from the Original Due Start.
Based on this the Original Latest Allowed Start Date (OLASD) becomes 15-022008. This is original due start + 73 days. If the work were to be completed within the
deviation range then the Original Latest Allowed Finish Date (OLAFD) would be
15-02-2008.
However in Figure 1 the Latest Allowed Start Date is still 15-02-2008 but the Latest
Allowed Finish Date is 31-12-2009 which indicates that an Activity Variance has been
applied to the work.
Effectively this means that the required external inspection of the vessel can be
deferred until 31-12-2009 before the vessel is no longer in compliance and requires to
be removed from service.

Compliance Category
The compliance category is obtained from a data base which lists the task lists and the
deviation band allowed. The deviation bands will be reviewed and approved by the
Corporate Discipline Focal Point (CDFP) at least every two years. The compliance
category is used to develop the tolerance period.

Planning
The CMMS can produce look-ahead plans for two years and 90 days which the IAP
planner will use to minimise deferment and optimise resources.
As previously stated all CMMS Work Order (WO) will have an original due start and
an original due finish. The maintenance team and /or the planning team will use these
dates to best utilise the resources available by implementing as required the inclusion
of the deviation range. Movement of start and finish dates with in the deviation range
is termed as Planned Start for maintenance and Extended Date for inspection.
However should the work be scheduled for whatever reason outside of the deviation
range then approval is required from the CDFP. The approval is an integral part of the
Z6 Notification process as detailed in PR-1528 Z6 Notification Procedure.
Once approved by this process a new Latest Allowed Start and / or Finish dates will be
given. Provided the work is completed within the Activity Variance time period
compliance will not be affected. Failure to complete within the Latest Allowed Finish
date will take the maintenance or inspection task out of compliance and result in the
system, unit or plant being taken out of services.

Page 10

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Non-SCE Maintenance and Inspection Activity Variance Control Process

Figure 2 Maintenance and Inspection Activity Variance Control Process Flow


1.

WOs are issued from CMMS before the due start date to enable the work to be
planned. The work is scheduled by the planner into the IAP.
NOTE: This applies to breakdown maintenance as well.

2.

The WO will be reviewed by the Maintenance and Planning Team and the work
prioritised for execution with the deviation range, but before the latest allowable
finish date.
In the case of WOs raised for breakdown maintenance the above will still apply.
The WO will have a latest allowable finish date which must be met for the item to
remain in compliance.

3.

Page 11

If, for sound business reasons, the WO cannot be completed by the latest allowable
finish date (including the deviation range), then an Activity Variance will require to
be raised. The process for this activity can be referenced in PR-1528 Z6
PR-1005 - Maintenance and Inspection Activity and
Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Notification Procedure Section 3.6.


4.

Approval of the Z6 by the CDFP will enable a new latest allowable start and / or
finish date to be entered into CMMS and a new updated WO issued.

5.

The work will be scheduled to start on or before the latest allowable start date and to
be completed by the latest allowable finish date.

6.

On completion of the work the WO will be closed out and the CMMS history
updated.
End of Process

3.2

SCE Deviation Control

Overview
The acronym FSR stands for Facility Status Report. This sub-section does not intend to
reproduce the web pages that can be accessed from the following link FSR.
A fundamental principle in the management of technical integrity is that our facilities
have been designed so that the risk of failure endangering the safety of personnel,
environment or asset value is . Failure to undertake critical maintenance and
inspection by the latest allowable finish date would constitute a failure to meet
the standard.
FSR has been designed as tool to support the business and manage the technical
integrity of its facilities, by providing 3 main functions:
1.

Identifying the CMMS work order and notification.

2.

Provide FSR flags and monitors those items that require action.

3.

Controlling Deviation

This procedure will concentrate on the third function, deviation.

SCE Maintenance and Inspection Deviation Control Process


NOTE: The detailed information on FSR is maintained on a separate dedicated web
site on the PDO Intranet and will not be duplicated here. Reference where applicable
shall be made to the reference material with links as necessary.
The FSR is interfaced with CMMS for all identified SCEs. The FSR monitors the SCEs
and uses the flags, Red, Amber and Green to provide visual status indication.
The following are carried out once the failure to meet the required performance
standard is indicated, either by incomplete maintenance and inspection or inability to
complete required maintenance and inspection in time.

Page 12

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Figure 3 High Level SCE Deviation Process


NOTE: The FSR records and manages failures of the SCE barriers due to breakdown
and malfunction in addition to maintenance and inspection activities.
Flag Status
SCEs status is monitored in FSR using flags, Red, Amber and Green.
Red a severity status indicating an unacceptable reduction or loss of Technical
Integrity that requires immediate attention;
Amber A severity status indicating an imminent need for action or a temporary,
controlled reduction in Technical Integrity that requires time-bounded action
Green A severity status indicating no current integrity impact
A red flag will signal the SCE is out of compliance e.g. outside of latest allowable start /
finish date, and requires a deviation to be raised immediately; an amber flag will signal
the SCE is approaching non-compliance and a deviation should be prepared or
remedial actions carried out; a green flag indicates the SCE is in compliance.
The method for raising a deviation is covered in detail in the overview help or help
index in the FSR Web Page.
Risk Assessment
Page 13

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

A risk assessment using the Risk Assessment Matrix (RAM) is carried out on the SCE
that has entered, or is about to enter non-compliance. The risk assessment uses PEAR
to provide the overall risk severity. All information including the participants of the risk
assessment is entered in FSR.
Mitigation Actions
Following the risk assessment mitigation will be proposed to address the findings and
reduce the risks to ALARP. The mitigation implemented will be reviewed and recorded.
Execute Mitigation Action
This is outside of FSR and is reliant on close inspection and monitoring to ensure that
all required measures identified to reduce the risk of an incident are implemented.
Review and Approval
FSR is configured to provide a Key Reviewer for each type of SCE, who will have the
correct level of technical authority and experience. All reviewer can also nominate
additional reviewers if and as required.
Documentation to back up the deviation can be attached and sent via a work flow to
the appropriate reviewers.
Repairs or modification that may be recommended to support the deviation and will
require to have a standard provided or an existing standard modified. The standard
requires to be approved by the appropriate technical authority before the deviation can
be approved.
When all the required information has been entered in the FSR and the FSR creator
submit the deviation, automatic email with FSR link will be sent to the reviewers. Once
all reviewers acknolowedged the deviation, the final deviation will be transmitted,
depending in the risk, to the right party for final approval.
For Low to Medium risk deviations this will be the Delivery Team Leader or equivalent
and for High risk deviations the Operations Manager.
Once the FSR deviation approved, the LAFD will be reflected in CCMS and the item
will be shifted to the deviation column in FSR screen

Page 14

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Appendix 1 Maintenance and Inspection Deviation Ranges


The embedded file contains a spreadsheet of Maintenance and Inspection Deviation
Ranges that are applied to CMMS Work Orders.

Deviation Ranges

Page 15

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Appendix 2 - Abbreviations
The following abbreviations are used in this Procedure.
CDFP

Corporate Discipline Focal Point

CMMS

Computerised Maintenance Management System

FSR

Facility Status Report

IAP

Integrated Activity Plan

LAFD

Latest Allowed Finish Date

OLAFD

Original Latest Allowed Finish Date

OLASD

Original Latest Allowed Start Date

PEAR

People, Environment, Asset, Reputation

RAM

Risk Assessment Matrix

SCE

Safety Critical Element

TA

Technical Authority

WO

Work Order

Page 16

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Petroleum Development Oman LLC

Revision: 4.0
Effective: Aug-10

Appendix 3 Reference Material


Code of Practice
CP-114

Maintenance and Integrity Management CoP

CP-156

Integrated Activity Planning CoP

Procedure
PR-1528

Z6 Notification Procedure

PR-1721

Shutdown Management

On-Line Help
Facility Status Reporting

Shell Process
EP 2009-9009 Safety Critical Element Management.

Page 17

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.

Revision: 4.0
Effective: Aug-10

Petroleum Development Oman LLC

Appendix 4 - User Feedback Page


PR-1005 Maintenance and Inspection Activity and Deviation variance
Control User Feedback Page
Any user who identifies an inaccuracy, error or ambiguity is requested to notify
the custodian so that appropriate action can be taken. The user is requested
to return this page fully completed, indicating precisely the amendment(s)
recommended.
Name:
Ref ID
Page Ref:

Date:
Brief Description of Change Required and Reasons

UOM2
Custodian of Document

Page 18

Date:

PR-1005 - Maintenance and Inspection Activity and


Deviation Variance Control

Printed 15/08/10

The controlled version of this CMF Document resides online in Livelink. Printed copies are UNCONTROLLED.