Documente Academic
Documente Profesional
Documente Cultură
BNCL
CLIENT:
PROJECT:
Clause
1
1.1
2
Doc. Ref.:
Revision:
Rev. Date:
Page #
QP072
00
th
12 April 13
1 of 4
Description
SCOPE
This document describes the procedure to be followed during the application of three
layer polyethylene coating. Adherence to this procedure by the relevant personnel is
mandatory.
REFERENCES
2.1
2.2
RESPONSIBILITIES
3.1
Project Manager is responsible for the provision of personnel, equipment and resources
necessary for the full and correct execution of this procedure.
3.2
Yard Superintendent is responsible for ensuring that all personnel observe the
requirements of this procedure. This responsibility is normally delegated to the
Production Supervisors under his immediate charge.
3.3
Quality Manager is responsible for ensuring that the quality requirements of this
procedure are met at all times. This responsibility is normally delegated to the QC
Inspectors under his charge. Quality Manager is also responsible for raising nonconformance reports (NCRs) where discrepancies are noted and for ensuring that any
identified corrective actions arising from such NCRs are carried out fully and completely.
3.4
Materials Controller is responsible for the call-off, storage and issue of raw materials
required during execution of the project, and for the establishment and maintenance of a
materials control system such that raw materials usage is accurately recorded and any
necessary stock rotation requirements are met.
4
4.1
4.1.1
4.2
4.2.1
Revision
PROCESS DESCRIPTION
HEATING
Pipes progress along the helical coating conveyor through induction heating coil. This
coil raises the temperature of the steel to a degree sufficient to permit the application of
FBE powder primer.
FBE PRIMER APPLICATION
Fusion bonded epoxy (FBE) powder is sprayed onto the hot pipe surface by means of a
set of electrostatic spray guns located within a purpose designed spray booth. The
powder is transferred from a fluidising bed and towards the spray gun by air passing
through an ejector venturi. As the powder passes through the gun, it is given an
electrostatic charge. Since the pipe is earthed through the conveyor, the charged powder
is attracted to the pipe, thus reducing overspray and waste.
Number in Revision column denotes change over previous issue using current revision number
CLIENT:
PROJECT:
Doc. Ref.:
Revision:
Rev. Date:
Page #
QP072
00
th
12 April 13
2 of 4
Clause
Description
4.2.2
Over sprayed powder is reclaimed from the booth by means of a vacuum recovery
system. It is passed through a rotary valve where it is mixed with fresh powder in a fixed
proportion governed by the setting of the valve. The mixed powder then passes through
a vibrating sieve to exclude oversized particles, followed by a set of magnets to remove
any metallic contamination, before being fed into the fluidising bed.
4.2.3
The nature of the vacuum recovery process means that some powder will accumulate in
the booth and on the extraction system filters. This will be removed at the end of each
shift, bagged and safely disposed of in an approved manner. Such powder may not be
reintroduced into the coating system.
4.2.4
All air used in the FBE system is chilled, dried and oil free to prevent contamination or
premature curing of the material.
4.3
4.3.1
Adhesive is applied to the FBE coated pipe by a side extrusion process. An automated
vacuum transfer system moves adhesive pellets from an open storage hopper to a feed
hopper above the extruder. Reclaimed material is not used in this process.
4.3.2
As the extruder runs, the screw draws adhesive pellets into the barrel from the hopper
above. The barrel of the extruder is divided into independent zones, controlled such that
the heat profile along the barrel is sufficient to melt the material for extrusion without
overheating. The processed material is extruded from a flat die in a continuous sheet,
which is wrapped around the FBE coated pipe as it moves along the helical conveyor.
4.3.3
The timing of adhesive application is critical, in that it must be applied before the FBE
primer has gelled. During plant setup, heat input levels and conveyor speeds are
adjusted to ensure that adhesive is applied within this time limit, and the process is
monitored continuously during production.
4.4
4.4.1
4.5
4.5.1
Revision
Number in Revision column denotes change over previous issue using current revision number
CLIENT:
PROJECT:
Doc. Ref.:
Revision:
Rev. Date:
Page #
QP072
00
th
12 April 13
3 of 4
Clause
Description
4.5.2
After exiting the cooling system, pipes are kicked off the conveyor and onto the final
inspection station.
5
5.1
Revision
QUALITY REQUIREMENTS
COATING CUTBACK
Where tape is used to mask off the cutback, monitor correct tape application throughout
production and record once per hour. Note that tape is not necessarily used for this
purpose and in such case this requirement will not be applicable.
Acceptance Criteria: Coating cutback 150 +/- 20mm
5.2
PIPE TEMPERATURE
Monitor throughout production with infrared pyrometer between the induction coil and the
start of the FBE booth. Record once per hour at the lead, midpoint and trail of a single
pipe.
Acceptance Criteria: Temperatures within the range 200 to 250 deg. C
5.3
LINESPEED
Monitor throughout production and record once per hour.
Acceptance Criteria: Line-speed must not result in the FBE curing before application of
adhesive, and must permit even application of adhesive and topcoat with no gaps
between successive wraps.
5.4
FBE APPLICATION
Monitor throughout production.
Acceptance Criteria: Full coverage. Thickness of coating and degree of cure will be
determined and recorded as detailed in procedure QP074.
5.5
Number in Revision column denotes change over previous issue using current revision number
CLIENT:
PROJECT:
Clause
5.6
Doc. Ref.:
Revision:
Rev. Date:
Page #
QP072
00
th
12 April 13
4 of 4
Description
Revision
5.8
DOCUMENTATION
The following documents will be completed as required:
6.1
6.2
6.3
Number in Revision column denotes change over previous issue using current revision number