Documente Academic
Documente Profesional
Documente Cultură
No. 4
ABSTRACT
Good mooring management practices for vessels
alongside piers are recommended and called for by
various organizations and regulatory bodies. The Oil
Companies International Marine Forum (OCIMF)
publishes specific mooring guidelines and load calculation
procedures for tankers and gas carriers, including
environmental load data. Until recently it has generally
been impractical to carry out such an analysis on each
mooring arrangement, especially considering that the
mooring is temporary, mooring line elasticity is nonlinear, draft, tide and environment forces vary with time,
and the solution of force vectors is indeterminate.
Computer programs can now perform the necessary
mooring analyses on personal computers. These programs allow the mooring arrangement to be planned in
advance and to be simulated and managed in real time
while the vessel is moored, accounting for changes in
forcing environment, draft and trim, and tides.
INTRODUCTION
Prudent practice dictates that the vessel mooring be
adequate for the various stages of loading, expected tides
and currents, and potential wind environment. The
OCIMF Mooring Equipment Guidelines1 state :
"The mooring equipment guidelines promulgated
by OCIMF are based firmly on the following
criteria: "Ships intended for worldwide trading
shall have outfits able to restrain them alongside
berths in winds of 60 knots from any direction
simultaneously with either:
3 knots current from ahead or astern, or
2 knots current from 10/ off bow or stern
quarter, or
0.75 knots current from the direction of
maximum beam current loading.
"Where the environmental conditions at any
particular berth are likely to exceed the criteria, it
4-1
12-E
0.72
57.1
58.2
48%
12-E
0.91
88.0
88.0
73%
12-E
70.3
70.3
70.3
58%
Connection ........
Pull-in (m) ..........
OCIMF Calculation..
Tension (t) .........
% of Strength ....
1-A
0.34
56.7
56.7
47%
|
Midship Spring Lines |
5-B
6-C
7-C
8-D
0.40
.060
.060
0.0
44.9
13.2
13.2
6.3
18.4
18.2
16.5
16.4
37%
15%
15%
14%
9-D
0.0
6.3
44.4
14%
|
13-F
0.78
55.2
55.2
46%
14-F
0.80
47.6
47.6
39%
13-F
0.72
6.3
6.3
4%
14-F
0.97
73.0
72.7
68%
13-F
46.3
46.3
46.3
39%
14-F
45.8
45.8
45.8
38%
4-3
12-E
wire
1.12
77.9
64%
12-E
wire
1.01
67.9
56%
Connection ........
Mooring line .......
Pull-in (m) ..........
Tension (t) .........
% of Strength ....
1-A
wire
0.48
76.3
63%
|
Midship Spring Lines |
5-B
6-C
7-C
8-D
wire
wire
wire
wire
0.56
0.34
.034
.040
62.1
24.1
24.1
17.8
51%
20%
20%
15%
9-D
wire
0.40
17.8
15%
|
13-F
synth.
2.34
24.9
18%
14-F
wire
1.23
64.7
54%
13-F
synth.
3.09
39.4
28%
14-F
wire
1.11
56.0
46%
4-4
14-F
wire
0.66
56.7
47%
|
Forward Breast Lines
|
Midship Spring Lines |
Aft Breast Lines
|
Connection ........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 11-E 12-E 13-F 14-F
Pull-in (m)
0.31
0.34
0.51
0.36
0.36
0.45
0.45
1.03
0.97
0.87
Mooring
line..........
.......
wire
H.M. 0.51
wire
H.M. 0.44
wire
wire
wire
wire
wire
wire
H.M. 0.92
wire
H.M. 0.91
wire
Tension
(t) ..........
.........
58.5
50.1
49.4
47.1
67.5
32.2
32.5
18.9
18.8
50.2
48.7
58.4
50.5
48.8
Pull-in (m)
0.41
0.55
0.51
0.73
0.49
0.32
0.32
0.37
0.37
0.97
1.17
0.92
1.17
1.02
56% 19.7
27%
27%
16%
16%
42%
40%
48%
42%
40%
Tension
(t) .........
59.5
50.1
43.9
36.3
48.9
19.9
13.6
13.4
47.5
38.4
60.5
44.8
50.9
% of Strength
....
48%
41%
41%
39%
61% 37%
62% 33%
45%
27%
50%
20%
20%
14%
14%
47%
28%
52%
% of Strength ....
Case 10 ! Improved "Non-Ideal" Berth, 20 t pretension, only one fender in contact with hull.
Case 7! Mixed-Mooring
with High-Modulus
Fiber Lines
|
Forward
Breast Lines Synthetic
|
Midship
Spring Lines |
Aft Breast Lines
|
Connection ........
2-A Breast
3-B Lines
4-B
5-C
6-D Spring
7-D Lines
8-E | 9-E Aft
10-F
| 1-A Forward
|
Midship
Breast11-G
Lines 12-G | 13-H 14-H
Pull-in
(m) ..........
0.39
0.42
0.63
0.64
0.55
0.45
0.45
0.56
0.56
1.28
Connection
........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 1.21
11-E 1.14
12-E 10.8
13-F 1.13
14-F
Tension (t)
.........
69.8
56.4
40.1
40.1
22.3
22.3
56.7
56.7
57.8
55.8
Mooring
Line.......
H.M. 59.9
H.M.. 59.2
wire
wire. 80.7
wire
wire
wire
wire
wire
wire
wire. 66.5
wire
H.M.
H.M.
58% 0.62
67% 0.23
46%
50%
49%
47%
33%
33%
18%
18%
47%
46.4
55%
48%
%
of Strength
....
Pull-in
(m) ..........
0.64
0.46
0.50
0.45
0.22
0.28
0.28
0.88
0.91
0.84
1.21
1.25
Tension (t) .........
50.7
51.0
46.7
40.0
52.6
17.7
17.9
12.0
11.9
50.0
41.4
64.6
46.0
43.1
Case 11! Double-Hull Tanker, no extra lines, 20 t pretension, only one fender in contact with hull.
37% 37%
53% 34%
32%
39%
41%
43%
15%
15%
10%
10%
50%
41.4
% of Strength ....
|
Forward Breast Lines
|
Midship Spring Lines |
Case
8!
Mixed-Mooring
with
High-Modulus
Synthetic
and
Stern
Lines,
wires
pretensioned
to
10
t,
H.M.
synthetics
to
15
t
Connection ........
1-A
2-A
3-B
4-B
4'-C
5-C
6-D
7-D
8-E
9-E
Pull-in (m) ..........
0.34
0.37 Breast
0.55 Lines
0.55
0.52
0.63 Spring
0.37 Lines
0.37 | 0.47 Aft
0.47
|
Forward
|
Midship
Breast Lines
|
Tension
(t) .........
56.0
48.3
47.4
45.3
59.8
63.5
30.9
31.1
19.5
19.4
Connection
........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E
11-E 12-E 13-F 14-F
% of Strength
....
46%
40%
39%
37%
49%
53%
Mooring
Line ......
wire
wire
wire
wire
wire
H.M. 26%
H.M. 26%
H.M. 16%
H.M. 16%
wire
wire
wire
wire
wire
Aft Breast
Pull-in (m) ..........
0.68
0.67
0.90
0.89
0.83
0.71
0.70 | 0.74
0.75
1.43Lines1.44
1.31 | 1.44
1.49
Connection
........
10-F
11'-F
11-G 44.8
12-G 58.3
H-F
14-H 49.2
Tension
(t) .........
56.0
56.4
41.7
42.2
46.4
21.4
21.6
15.5
15.5
45.5
52.6
Pull-in
(m) ..........
1.15
1.16
1.08
1.03
1.97
43% 1.02
38%
36%
%
of Strength
....
41%
41%
31%
31%
34%
16%
16%
11%
11%
33%
33%
Tension (t) .........
48.7
48.2
46.9
56.0
45.3
46.7
Case
9!
All
High-Modulus
Synthetic
Fiber
Mooring
Lines
39% 46%
40%
39%
% of Strength ....
40%
40%
Case 12 ! Double Hull Tanker, extra line fore and aft, two fenders in contact with hull.
Figure 4 - Tide, Current, and Vessel Draft for Mooring Tending Example
The following examples demonstrate the problem of
providing adequate mooring lines for such a double-hull
vessel. These examples were developed from Cases 3 and
10, those of the OCIMF all-wire 250,000 dwt tanker
moored at a "non-ideal berth". To simulate the doublehull tanker, the molded depth of that OCIMF hull was
increased by 8% to 26 m.
As in all of the preceding cases, the tanker draft is
6.1 m, and its trim is 5 m by the stern. However, because
of the 8% increase in hull depth, the freeboard at midship
is now 19.9 m instead of 17.9 m.
Case 11 shows the increase in mooring line loads
caused by that extra freeboard. Here the pretension had
to be increased to 20 t to hold the vessel against even one
fender. Three lines exceed the OCIMF criteria. One line
reached 67% of its break load. The load in each of the
forward breast lines increased by over 19%, and the load
in each of the aft breast lines increased by over 14%.
In Case 12 two additional mooring lines have been
provided. These lines are designated 4' and 11' and are
essentially clones of lines 4 and 11. They are run to berth
mooring points C and F respectively. Again, all lines
were pretensioned to 20 t. Now none of the lines are
overloaded. The highest line load is 53% of the break
strength.
These examples indicate the need to conduct mooring
line analyses on double-hull tankers. If hull volume is
increased without providing additional mooring winches,
then line overload will probably result.
4-6
12-E
0.17
14.7
12%
Case 13! Line Tending Example, Starting Position, 0200 hrs, draft = 14.1 m, tide = -0.19m (low tide).
|
Forward Breast Lines
|
Midship Spring Lines |
Aft Breast Lines
Connection ........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 11-E
Pull-in (m) ..........
0.10
0.12
-0.07 -0.19 -0.28 -0.64 -0.63 0.16
0.16
0.17
0.17
Tension (t) .........
22.6
12.1
29.0
24.8
24.3
29.1
30.6
2.2
1.3
30.1
26.5
19% 10%
24%
20%
20%
24%
25%
2%
1%
25%
22.4
% of Strength ....
12-E
0.17
28.4
23%
Connection ........
Pull-in (m) ..........
Tension (t) .........
% of Strength ....
1-A
0.10
7.4
6%
|
Midship Spring Lines |
5-B
6-C
7-C
8-D
0.08
0.06
0.06
0.16
3.5
2.8
2.9
9.8
3%
2%
2%
8%
9-D
0.16
9.7
8%
|
13-F
0.12
7.5
6%
14-F
0.13
7.3
6%
13-F
0.12
28.8
24%
14-F
0.12
20.6
17%
Case 14! Line Tending Example, after tending at 0700 hrs, draft = 12.2, tide = 1.9 m rising, current = 2.7 kt.
|
Forward Breast Lines
|
Midship Spring Lines |
Aft Breast Lines
|
Connection ........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 11-E 12-E 13-F
Pull-in (m) ..........
0.10
0.12
-0.07 -0.19 -0.28 -0.64 -0.63 0.16
0.16
0.17
0.17
0.17
0.12
Tension (t) .........
33.1
29.3
39.9
43.1
50.1
44.9
47.2
38.7
36.7
50.1
44.7
51.8
26.2
37% 43%
22%
% of Strength ....
27%
24%
33%
36%
41%
37% 39%
32%
30%
41%
14-F
0.12
14.9
12%
Case 15 ! Line Tending Example, before tending at 1700 hrs, draft = 8.4 m, tide = 0.7 m rising, current =1.7 kt.
|
Forward Breast Lines
|
Midship Spring Lines |
Aft Breast Lines
|
Connection ........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 11-E 12-E
Pull-in (m) ..........
-0.93 -0.75 -1.33 -1.56 -1.70 -1.68 -1.66 -0.15 -0.16 -0.92 -0.82 -0.87
Tension (t) .........
22.0
25.0
21.3
15.3
12.4
12.1
14.9
8.1
6.0
20.6
23.6
12.6
10%
% of Strength ....
18%
21%
18%
13%
10%
10%
12%
7%
5%
17%
20.4
13-F
-0.75
26.9
22%
14-F
-0.70
18.8
16%
Case 16! Line Tending Example, after tending at 1700 hrs, note differences in Pull-in compared with Case 15.
|
Forward Breast Lines
|
Midship Spring Lines |
Aft Breast Lines
|
Connection ........
1-A
2-A
3-B
4-B
5-B
6-C
7-C
8-D
9-D
10-E 11-E 12-E
Pull-in (m) ..........
-0.93 -0.75 -1.33 -1.56 -1.70 -1.68 -1.66 -0.15 -0.16 -0.92 -0.82 -0.87
Tension (t) .........
32.0
39.1
37.3
39.3
44.8
41.1
44.9
43.2
39.9
44.9
45.3
39.2
37% 32%
% of Strength ....
26%
32%
31%
32%
37%
34% 37%
36%
33%
37%
13-F
-0.75
28.7
24%
14-F
-0.70
15.6
13%
Case 17 ! Line Tending Example, completion of discharge, 2300 hrs, draft = 6.1 m, tide = 1.13 falling.
4-7
CONCLUSIONS
Mooring analysis can reduce accidents by identifying
unsafe situations and can improve the efficiency of other
situations.
Using conventional fiber ropes together with wires is
usually not effective, but when properly utilized, these
fiber ropes can contribute to the mooring. The new highmodulus fiber ropes can be particularly effective when
properly deployed in mixed-mooring situations.
Double-hull vessels have higher freeboards, which can
significantly increase mooring loads. Thus extra mooring
lines will probably be necessary on these vessels, and
good mooring management will be even more important.
The mooring of a vessel at a berth in a particular
combination of vessel states of loading, tide, current, and
wind can now be simulated in advance. A "worse case"
superposition of the most unfavorable draft, tide, and
current may present an impossible mooring situation, but
when the timing of these events is properly modeled, the
mooring may be practical and safe. Such analysis can
also increase the effectiveness and yet decrease the
frequency of line tending.
_______________________
References
1. Oil Companies International Marine Forum,
Mooring Equipment Guidelines, Witherby and Co.,
Ltd., London, 1992.
2. Flory, J.F. and A. Ractliffe, Optimoor Mooring
Analysis Computer Program Users Guide, Tension
Technology International, Morristown, NJ and
Eastbourne, U.K., 1993.
3. Oil Companies International Marine Forum,
Guidelines and Recommendations for the Safe Mooring
of Large Ships at Piers and Sea Islands, Witherby &
Co. Ltd., London, 1978.
4. Flory, J.F., H.A. McKenna and M.R. Parsey, "Fiber
Ropes for Ocean Engineering in the 21st Century", pp
934-947, Proceedings of Civil Engineering in the
Oceans V, ASCE, New York, Nov. 1992.
4-8