Documente Academic
Documente Profesional
Documente Cultură
The municipalities arguments regarding the breadth of the substantially change and base station definitions
were also rebuffed. Under the framework outlined by the Supreme Court in Chevron, USA, Inc. v. Natural
Resources Defense Council, the court reviewed the FCCs rules to determine whether they were based on a
permissible construction of the statute. The FCCs interpretation could have only been set aside if deemed
arbitrary, capricious, an abuse of discretion or otherwise not in accordance with law.
Defining Substantial
The court first addressed whether the term substantially change was improperly defined. Specifically, the
municipalities argued that the term substantial was inherently subjective and could not be properly defined by
any objective measures within the FCCs Rules or otherwise. Recognizing that the primary concern of the
municipalities was to retain discretionary power to evaluate whether a proposed change was substantial, Judge
Duncan unequivocally stated that the Spectrum Act intentionally preempted any discretion that a local
government previously possessed. The Circuit Panel determined that it was not unreasonable to define
substantial in strict numerical terms because physical dimensions were inherently quantifiable standards. The
court also noted that contextual analyses incorporated in the FCC Rules eliminated the need for localities to
make case-by-case contextual substantiality determinations.
Defining Base Station
Lastly, the court addressed the municipalities assertion that the definition of base station was overbroad.
Indeed, the court noted that the definition considers most structures to be base stations, including buildings
and utility poles upon which wireless facilities are equipped. However, the court found that the breadth of the
new definition was inconsequential to the constitutionality of its application because it comported with the
thrust of the Spectrum Act. One of these goals is to put towers and support structures on equal footing.
Following the Fourth Circuits decision, wireless carriers now have a clear-cut avenue to perform the
infrastructure modifications necessary to accommodate an increasingly wireless population. However, wireless
carriers must still ensure that companies must ensure that the modifications sought are within parameters
outlined in the Spectrum Act to receive the benefit of this expedited process.
Court Leaves Door Open for Municipalities
In addition, wireless companies will have to navigate the normal channels of local government when seeking
permits for new telecommunications facilities. The court left the door open for municipalities to create obstacles
in these scenarios. One argument advanced by the petitioners against the definition of substantially change
reasoned that many existing facilities were granted upon the condition that there would be no future
modifications to the site. In the petitioners view, these modifications should be considered per se substantial.
The petitioners further stated that the ignoring of conditional approvals in this manner would deter
municipalities from issuing new permits to build necessary infrastructure and thwart the intent of the statute.
The court noted that this might be a valid policy concern, but ruled that there was no room for policy arguments
targeting the goals of the underlying statute in a simple statutory interpretation case. It remains to be seen
whether the concerns will be realized and whether the deemed granted procedure will deter local governments
from issuing permits for new telecommunications infrastructure moving forward.