KIZINGO
CLIENT:
CORPORATION
ARCHITECT:
MAIN CONTRACTOR:
CONTRACT PERIOD:
75 WEEKS
COMMENCEMENT DATE:
COMPLETION DATE:
TIME ELAPSED:
PERCENTAGE OF WORK COMPLETED:
Week No.
CLERK
2.2 SUPERSTRUCTURE
2.2.1 CONCRETE WORKS
2.4 PLASTERING
Plaster started on first floor ceiling. This has been stopped due to
poor workmanship till the MC corrects on the instructions given
on site.
MC Matters
a) Delay on laying of conduits and drainage pipes has been rampant and
urged the subs to cooperate to finish on agreed time.
b) MC asked the subs to ensure that they report to work on time and not
to leave early
c) MC asked the Subcontractors to add on labour to finish their parts on
time
Electrical Subcontractor Matters
a) Requested the MC to give them two full working days to lay their
conduits after he finishes his work.
b) Asked the MC to make sure his people are keen not to break their
pipes.
c) Esb agreed to cooperate with the MC and to work within his
programme.
Plumbing Subcontractor Matters
a) Requested the MC to speed up the construction of Store to keep their
materials safe.
Clerk of works Matters
a) Asked the MC and the Subcontractors to submit a list of Submitted and
approved shop drawings and samples.
b) Asked the MC to build a Sample room for all approved samples.
c) Asked the MC to build up nice offices and stores for subcontractors and
look at sanitary facilities which are not good.
No report.
SHOP
SHOP
DRGS.SUBMITTED DRGS.APPROVED
REMARKS
MC
PLUMBING
ELECRICAL
MECHANICAL
LIFT
SOLAR
SCHEDULE
SAMPLES ON
SITE
SAMPLES
APPROVED
REMARKS
MC
PLUMBIN
G
ELECTRIC
AL
MECHANI
CAL
LIFT
SOLAR
SAMUEL M MUTINDA- mutindadesign@gmail.com - 254727995026
|Clerk of Works Weekly Report
DESCRIPTION
NO
Site Manager
Formwork Foreman
Steel Fixing Foreman
Masonry Foreman
Site Accountant
Crane operator
Site Clerk/Store
Masons
Drivers
Carpenters
Steel Fixers
Welder
Mixer Operator
Helpers
Security
1
1
1
1
1
1
1
7
3
20
15
1
2
20
2
DESCRIPTIOM
NO
Cement
Pingo (Steel)
Black pipes
Ballast
River sand
Timber
Y8
Y10
Y12
Y16
Y20
Y25
Hollow blocks
Binding wire
Nails
Dust Masks
1050 bags
1400pcs
2500pcs
140 tones
70 tones
4000 fts
623 pcs
768 pcs
611 pcs
522 pcs
473 pcs
578 pcs
500 pcs
8 rolls
6 bags
5 boxes
17
18
19
20
21
Gloves
Overalls
Safety Boots
Gumboots
Gum poles
200 Pcs
50 Pcs
40 pcs
20 pcs
2500 pcs
DESCRIPTION
NO
Concrete Mixer
Electrical Timber saw
Smoothening Timber machine
Heavy Metal cutting machine
Bending machine
Small trend machine
Bole drilling Machine
Welding machine
Electrical generator
Breaker vibrating machine
Various timber machines
Wheelbarrows
Crane
2
1
1
1
1
1
1
1
1
1
16
22
1
Weather
C
P
M
Weather
Time Lost
Saturd
ay
Sunda
y
Monda
y
2
Sunny
5
3
3
Sunny
Tuesda
y
Wedne
sday
Thursd
ay
Friday
2
Sunny
6
3
3
Sunny
2
Sunny
6
3
3
Sunny
2
Sunny
5
3
3
Sunny
2
Sunny with
6 clouds
3
3
Sunny
DESCRIPTION
Walling Details
Wardrobe Details
ACTIO COMMENTS
N
Archite
ct
Archite
ct
Progress is good.
MC working on third floor slab grids 5-9/A-F and Fifth floor slab
grids 1-4
Plaster work is expected to progress on first floor ceiling as well
as walling.
Unit one setting out for walling has begun in third floor.
RC wall
Third
10