Documente Academic
Documente Profesional
Documente Cultură
Horsens, 25.09.2012
PROJECT NR 11
Supervisors:
sakj@viauc.dk
sf@viauc.dk
Tele: + 45 87 55 42 82
Tele: +45 87 55 41 04
Table of Contents
4. Types of diaphragm wall analysis and selection the best type ......................... 24
4.1. Cantilever diaphragm wall embedded in soil ................................................................................... 24
4.2. Strutted diaphragm wall .................................................................................................................. 25
4.3. Anchored diaphragm wall ................................................................................................................ 26
4.4. Conclusion ...................................................................................................................................... 27
DRAWINGS
DRAWING NR 1. LAND USE PLAN
1:500
1:100
1:100
1:50
1. General introduction
The Skyscraper will be situated in the center of the down, which will make the construction more
complex in many ways, including the excavation works.
1.4. Climate
Study of the climate is very important when carrying out the works, because it changes the conditions of
the works. If the works takes place in a rainy period the problems with the water will be higher, also if it
is a snowy period it will be more difficult to work with the concrete/bentonite.
The graph below shows the Temperature relations in the city of Wroclaw during the year, its essential
that for designed excavation its necessary to pick the months with the temperatures above the freezing
point
Figure 1.4 Average minimum and maximum temperature over the year. The monthly mean minimum
and maximum daily temperature.
Figure 1.5 Average monthly precipitation over the year (rainfall, snow)
This is the mean monthly precipitation, including rain, snow, hail etc.
Precipitation is different throughout the year, Generally, Wroclaw experience precipitation from 2 cm to
8,4 cm with the maximum in July. Snowfall occurs mainly from late November until early March, but
snow cover seldom lasts long. Snow during January and February is common and the average
temperatures for these two winter months are near the freezing point.
Figure 1.6 Average monthly hours of sunshine over the year. This is the monthly total of sunhour
To improve working conditions excavation work should be carried out in good light. The best time is
from May till August.
References:
[1] http://forum.investmap.pl/dolnoslaskie-infrastruktura-spoleczna-f77/nowa-siedziba-izby-skarbowejt6129.html
[2] http://www.weather.com/weather/today/Wroclaw+Poland+PLXX0029
2. Geological Analyze
2.1 General information about soils in Poland
In Poland Eurocode 7 is obligatory. Soil classification system according to Eurocode 7 [ PN EN 19971:2004] is enclosed as ANNEX 4.
As this current project is about deep excavations, it is quintessential to have sufficient knowledge about
the soil and characteristics of it. By geological analysis the wider background of current area is briefly
introduced. Geological analysis according to existing information in some circumstances can point out
some aspects that should be focused on during geotechnical drillings.
Soils in Poland
Poland has many different soils. Sandy formations (20% of particles less than 0.2mm in diameter)
occupy about 50 % of the total area. Their water properties depend upon the depth of the ground-water
table, substratum soil profile layers, and content of silt particles less than 0.02 mm in diameter.
Appropriate agrotechnical and land reclamation (water conservation) measures are necessary for the
improvements of these soils. The main type of soils include swampy boulder loam, organogenic soils
developed on peat, alluvial soils, silty and loess formations. More data on soil types in Poland are
shown in Table 1.
Table 1 Parent rock soil types in Poland
comment: datebase has a lot of information about the area of Wroclaw, but not very accurate. It
is not enough to design the foundation.
Geological documentation made by Polish Company GEOBAD
comment: documentation is very detailed, but it was made for other project and the building in
that project was in different location (the distance from that building to the Skyscraper in is less
than 1 km)
Unfortunately, it was impossible to get detailed information about soils in designed area from design
engineer who is engaged in designing Skyscraper in Wroclaw. That kind of documentation is prepared
by specialist and expensive.
It is necessary to assume soils according to available data ( details - point 2.3.1.)
2.3 Previous drilling in the area
2.3.1 Information according to Polish geo-engineering database
The geo-engineering database and the geo-engineering atlas of the Wrocaw agglomeration were
prepared between 2007 and 2008 by Geological Enterprise of Wrocaw PROXIMA and the Polish
Geological Institute in the collaboration with Geological Enterprise of Katowice and the Geological
Company Geoprojekt Szczecin.
Figure 2.1 Wroclaw division of the city according to Polish Internet database.
10
The Atlas of Wrocaw covers the area of Wrocaw City County (293 km2) as well as parts of the
neighbouring communes of Wrocaw County (Dugoka, Czernica, wita Katarzyna, rawina,
Kobierzyce and Kty Wrocawskie Communes) and roda lska County (Mikina Commune). The
total area covered by the maps is 719,8 km2.
The database of the geo-engineering atlas of the Wroclaw contains more than 50 000 boreholes that
come from archives and were also made especially for the purpose of this project. The average density
of survey points were 70 boreholes per km2 of the agglomeration area.
Borehole profiles collected in the database have been used to prepare 6 geo-engineering sections in the
scale of 1:5000 / 1:200 to present the geological structure synthetically.
Figure 2.2 Wroclaw location of building site Scale 1:10000(red place).
The geo-engineering database and the geo-engineering atlas of the Wrocaw shows soils at three
levels:
at a depth of 1 meter
at a depth of 2 meters
at a depth of 4 meters
Maps (print screens) from the database with descriptions are given below:
11
at a depth of 2 meters (Figure 2.5) and a depth of 4 meters (Figure 2.6) in Wroclaw city center is :
glacial till
Figure 2.5 Building site - soils at 2 meters according to Polish Internet database
Figure 2.6 Building site - soils at 4 meters according to Polish Internet database
12
Borehole nr 1
Borehole nr 2
Borehole nr 3
Borehole nr 4
Deep [m p.p.t.]
Layer
Symbol
Density
Humidity
0 1,1
Embankment
Loose
wet
1,1 2,0
Fine sand
FSa
ID=0,4
semi dry
2,0 5,2
Clayey silt
saclSi
IL=0,07
semi dry
5,2 6,4
silty sand
siSa
ID=0,5
wet
13
6,4
clayey silt
saclSi
IL=0,29
wet
Borehole nr 2
Nr
Deep [m p.p.t.]
Layer
Symbol
Density
Humidity
0 0,9
Embankment
Loose
wet
0,9 1,2
Fine sand
FSa
ID=0,33
semi dry
1,2 5,0
Clayey silt
saclSi
IL=0,12
semi dry
5,0 6,1
silty sand
siSa
ID=0,8
wet
6,1
clayey silt
saclSi
IL=0,22
wet
Borehole nr 3
Nr
Deep [m p.p.t.]
Layer
Symbol
Density
Humidity
0 1,4
Embankment
Loose
wet
1,4 2,2
Fine sand
FSa
ID=0,39
semi dry
2,2 4,8
Clayey silt
saclSi
IL=0,09
dry
4,8
clayey silt
saclSi
IL=0,27
wet
Borehole nr 4
Nr
Deep [m p.p.t.]
Layer
Symbol
Density
Humidity
0 1,3
Embankment
Loose
wet
1,3 2,8
Fine sand
FSa
ID=0,4
semi dry
2,8 3,8
Clayey silt
saclSi
IL=0,07
semi dry
3,8 4,7
silty sand
siSa
ID=0,5
wet
4,7
clayey silt
saclSi
IL=0,29
wet
Using information about boreholes , it is possible to prepare soil profiles, in problematic places where
no drillings are made, it can be estimated what kind of soil is present at this place by using two closest
holes and guessing what is between them.
According to information above, four cut sections are assumed:
- Cut section I (between borehole nr 1 and borehole nr 2)
- Cut section II (between borehole nr 2 and borehole nr 3)
- Cut section III (between borehole nr 3 and borehole nr 4)
- Cut section IV (between borehole nr 4 and borehole nr 1)
Cut sections are enclosed as ANNEX 3
Area of Wroclaw is very poor of water resources. This is a result of geological history. Ground
waters are very deeply located under the ground level and surface waters appear very seldom.
Due to the present conditions, ground water level for this project is assumed at depth of 11,8
meters.
14
15
Diaphragm walls
Pile walls (Contiguous, Tangent or Secant)
Soldier pile with wooden lagging walls
Sheet pile walls
Composite supporting systems that is, any of the retaining systems (1) to (4) above
strengthened by Anchors, internal strutting etc.
3.1.1. Diaphragm walls
Typical wall thickness varies between 0.6 to 1.1m. The wall is constructed panel by panel in full
depth. Panel width varies from 2.5m to about 6m. Short widths of 2.5m are selected in less stable soils,
16
under very high surcharge or for very deep walls. Different panel shapes other than the conventional
straight section like T, L are possible to form and used for special purposes. Slurry wall technique is a
specialized technique and apart from the crane mounted Grab, other equipment involved are cranes,
pumps, tanks, desanding equipment, air lifts, mixers etc.
Steps involved in the construction of diaphragm wall can be broadly listed as follows:
1.
2.
3.
Bentonite flushing
4.
5.
The sequence of construction of diaphragm wall panel has been schematically illustrated in Fig.
3.1
It must be remembered that Diaphragm walls are constructed as a series of alternating primary
and secondary panels. Alternate primary panels are constructed first which are restrained on either side
by stop-end pipes. Before the intermediate secondary panel excavation is taken up, the pipes are
removed and the panel is cast against two primary panels on either side to maintain continuity. Water
stoppers are sometimes used in the construction joints between adjacent panels to prevent seepage of
ground water.
Diaphragm wall construction is relatively quiet, and minimum noise and vibration levels
make it suitable for construction in urban areas. The water tight walls formed can be used as permanent
structural walls and are most economical when used in this manner. The finished structural wall formed
prior to excavation allows subsequent construction of the basement in a water tight and clean
environment. Once the diaphragm walls are constructed, work can be planned to proceed
simultaneously above and below the ground level. There is a minimum of space wasted. Work may be
carried out right against existing structures and the line of wall may be adjusted to any shape in plan.
Diaphragm walls however, require the use of heavy construction equipment that requires
reasonable headroom, site area, and considerable mobilization costs. In limited headroom conditions,
smaller cranes can be used though this could compromise efficiency. They are not considered efficient
means in hard and rocky grounds, where the conventional grabs are undeployable.
17
18
19
They are however, not considered suitable for construction in areas of high water table, as retention and
containing water is not possible in contiguous piles. Perfect alignment of piles is often difficult to achieve
at site, and this in turn is found to affect the dimension and alignment of the Capping beams. In design
parlance, only the portion of concrete and steel away from the neutral axis is known to offer resisting
moment. As a result, some concrete and steel area remains under-utilized.
20
Figure 3.5 Soldier Piles and Wooden Lagging System at Udyog Bhawan, New Delhi
21
A pile is designed to be beaten into the ground next to other piles already set up. Each sheet
pile are set between themselves via lateral veins called locks. The material can be wood, but mostly
steel. Once planted into the ground, their assembly may form a retaining wall or a waterproof screen.
There are several shapes of sheet pile. These differences come from the performance of their joints. In
an urban context, it is more interesting to drive the piles with a hydraulic cylinder: this method, silent and
resulting in no vibration on adjacent structures, requires soil differential settlement in long term state.
The nature of steel sheet tends to concentrate the leak rates in the locks. The locks are the
weaknesses of the sheet pile walls. Use of sheet pile walls to retain contaminated soil requires very
low leakage rates and therefore must necessarily use special fixing at the locks. Besides welding, these
devices are based on the use of bituminous materials, wax or water blowing.
Generally the following permeability is expected:
- Greater than 10-7 m/s with joints without sealant
- 10-7 m/s with tar or wax seals
- 5x10-10 m/s with hydro swelling joints
Traditional sheet pile shapes are Z type and U type. Z-Type (Z): Used for intermediate to deep wall
construction, Z sections are considered one of the most efficient pile available today. Z- piles are
commonly used for cantilevered and tiedback systems. Additional applications also include load bearing
bridge abutments. U Type (U) sheet piles are used for the applications similar to Z- Type.
22
3.2. Comparison
The following table is suitable to summarize the above.
Soldier pile
with wooden
lagging walls
Diaphragm
medium
medium
medium
medium
small
medium
hight
medium
NOISE/ VIBRATION
medium
high
small
medium
WATER TIGHTNESS
TRANSFORMING INTO
BASEMENT WALLS
medium
medium
medium
medium
COST
WEIGHT
TIME OF IMPLEMENTATION
walls
23
24
Figure 3.10 Single and double strutted diaphragm wall with maximum dimensions.
Figure 3.11 Example of single strutted diaphragm wall and stress distribution.
25
Strutted diaphgram wall is recommended for this project. The maximum dimension of the wall above the
ground (Hn) is 12 meters, that means that it is ideal dimension for 2 floors of underground garage. In
this project retaining wall could be strutted by floor slabs.
4.3. Anchored diaphragm wall
Anchored diaphragm walls are often used when securing deep foundation pits, e.g. in built-up areas or
under groundwater levels
26
Anchored diaphgram wall is also recommended for this project. The maximum dimension of the wall
above the ground (Hn) is 12 meters, that means that it is ideal dimension for 2 floors of underground
garage.
4.4. Conclusion
In sum we have to choose between strutted and anchored method. Cantilever diaphragm wall was
excluded. Due to the construction of floors in garage (reinforced concrete slabs), it seems to be the
better idea to use strutted method. The construction of garage will be used in two ways slabs can take
to loads from cars and other object in garage, and slabs can take over the role of struts. The connection
between diaphragm wall and each slab is designed as fixed (rotation of the slab towards diaphragm
wall is impossible)
The best method is strutted diaphragm wall.
27
28
29
30
The soil is excavated just below roof slab level of the underground structure. Struts are installed to
support the retaining walls, which in turn support the soil at the sides
Step nr 3: Construction of underground structure
31
The side walls are constructed upwards, followed by removal of the intermediate struts. The access
openings on the roof slab are then sealed
STRUCTURAL MEMBERS REQUIRED FOR TOP-DOWN CONSTRUCTION
Design and construction principles for top-down method primarily call for two major structural elements.
Columns with sufficient capacity must be pre-founded in bored piles or barrettes to sustain the
construction load and to utilize as part of bracing system. Excavation for basement must be carried out
with the support of permanent retaining wall so that basement floor slabs can be utilized as lateral
bracing.
Diaphragm wall of 0.8m to 1.2m in thickness with sufficient embedment in firm soil layers is commonly
used as a retaining wall whereas prefabricated steel columns known as Stanchions embedded in either
large diameter deep-seated bored piles or barrettes are utilized as structural columns. Figure 4.6
illustrates the top-down construction method with utilization of stanchions and diaphragm wall.
General information
Light stanchion
Steel H-beams
350x350x390 kg/m
Application
For semi top-down
construction
For temporary decking
For semi and full top-down
construction of shallow to
32
Heavy stanchion
Steel H-beams
508x457x738kg/m
Composite steel columns
built up by 2 or more small
to medium size H-beams
Large section pre-cast RC
column (seldom use)
STANCHION INSTALLATION METHODS
Stanchion installation method is usually selected by the piling contractor who takes into consideration
three main factors such as installation depth, size of stanchion and size of bored or barrette piles.
Though installation details may be different from one contractor to another, stanchion installation can be
categorized under two main methods, post-concreting or plunging installation and pre-concreting
installation or placing stanchion prior to concreting.
Post-concreting installation or plunging method
In this method, stanchion is installed immediately after completion of bored pile concreting process.
General construction sequence involved in this method is demonstrated in Figure 4.7.
Guide frame is used to install the stanchion at the correct position.
33
34
35
During diaphragm wall installation, the basement columns (steel beams) and concrete barrettes are
made. Basement columns and the concrete barrettes are load-bearing elements that will carry the future
super-structure. The construction process of those elements is beyond the scope of this project.
36
EXCAVATION: STEP NR 1
The top floor slab is constructed with at least on construction (glory) hole left open to allow removal of
spoil material (Figure 4.9)
Top-down construction involves casting the ground floor slab and excavating the ground below while
work on the superstructure above can continue
37
EXCAVATION: STEP NR 2
The excavation starting at the glory hole begins once the top floor has gained sufficient strength. Soil
under the top basement floor is excavated around the basement columns to slightly lower than the first
basement floor elevation in order to allow for the installation of the forms for the first level basement
slab. Glory holes are left open within each newly formed basement floor slab and the procedure is
repeated. Each floor rests on the basement columns that were constructed earlier
EXCAVATION: STEP NR 3
Figure 4.12 Excavation - Step nr 3 - Second level basement slab (foundation slab) construction
38
7. Geotechnical description
7.1. Introduction to soil properties
Geotechnical description is the last step of 'theoretical part' before the calculation. The geotechnical
description is important in all kind of project in civil engineering. In this part the subsurface conditions
and materials are investigated. It is necessary to determine the physical and mechanical properties of
materials.
It is really important to have an overview on the surrounding buildings because the Skyscraper
will be located in an urban area, in the heart of Wroclaw. The building site is surrounded by other
buildings, and road - located next to the area which will be excavated and possibly causing the collapse
to these road and buildings as a result of the excavation or dewatering.
Water level is between at depth 11,8 meters under the ground level. So it is not necessary to
perform a temporary dewatering for the excavation (the deep of excavation is 7 meters). In case when
the excavation is at depth e.g. 11 meters, the dewatering should then be arranged so that the water
table is lowered at least 1 meter below the excavation level. There will probably be a dug in clay, in
which case the dewatering of the excavation possibly will be done by simple drainage.
The safety of any geotechnical structure is dependent on the strength of the soil. Understanding
shear strength is the basis to analyze soil stability problems. If the soil fails, the structure
founded on it can collapse.
Figure 4.13 Foundation failure by liquefaction after the 1964 Niigata Earthquake.
Shear strength is a term used to describe the magnitude of the shear stress that a soil can sustain. The
shear resistance of soil is a result of friction and interlocking of particles, and possibly cementation or
bonding at particle contacts. Due to interlocking, particulate material may expand or contract in volume
as it is subject to shear strains. If soil expands its volume, the density of particles will decrease and the
strength will decrease; in this case, the peak strength would be followed by a reduction of shear stress.
The stress-strain relationship levels off when the material stops expanding or contracting, and when
interparticle bonds are broken.
39
According to BS EN ISO 14688-2:2004,5.3,Table 5 the shear strength of soils when measured by Field
or Hand Shear Vane Apparatus, or in the laboratory by Quick Undrained Triaxial compression test,
shall be expressed as below:
Table 4 shear strength of soils
Term based on measurement
Extremely low
<10
Very low
10 - 20
Low
20 - 40
Medium
40 - 75
High
75 - 150
Very high
150 - 300
Extremely high
300 - 600
40
41
Is composed of unconsolidated rock fragments that have a general particle size range and include size
classes from granule- to boulder-sized fragments. Gravel is sub-categorized by the Udden-Wentworth
scale into granular gravel (>2 to 4 mm or 0.079 to 0.16 in) andpebble gravel (>4 to 64 mm or 0.2 to 2.5
in). One cubic yard of gravel typically weighs about 3000 pounds (or a cubic metre is about 1,800
kilograms).
Gravel is an important commercial product, with a number of applications.
Many roadways are surfaced with gravel, especially in rural areas where there is little traffic. Globally,
far more roads are surfaced with gravel than with concrete or tarmac; Russia alone has over 400,000
km (250,000 mi) of gravel roads. Both sand and small gravel are also important for the manufacture
of concrete.
SOIL
HUMIDITY
Particle
density
gS
dry
Bulk density g
depending on the ID
ID = 1,0 0,68
ID = 0,67 0,24
ID = 0,33 0,0
1,7
1,65
1,6
1,85
1,75
1,7
2,0
1,9
1,85
FSa
semi dry
2,65
siSa
wet
Example:
42
For Fine Sand (dry, ID = 0,5) the particle density equals 2,65 g*cm3 and the bulk density equals 1,65
g*cm3
Table for cohesion soils:
Bulk density g
depending on the IL
Particle
density
gS
SOIL
saclSi
2,68
IL < 0
ID = 0,0 0,25
IL = 0,25 0,5
IL = 0,5 1,0
2,15
2,10
2,00
1,9
fk [ ]
Nr
Layer
Symbol
Density
Humidity
Embankment
Loose
wet
18,0
22
Fine sand
FSa
ID=0,4
semi dry
16,5
30
Clayey silt
saclSi
IL=0,07
semi dry
21
35
20,7
cu,k [kPa]
43
Silty sand
siSa
ID=0,5
wet
17,5
30,5
Clayey silt
saclSi
IL=0,29
wet
20
28,3
16,6
Borehole nr 2
0
Nr
Layer
Symbol
Density
Humidity
g[kN/m3]
cu,k [kPa]
Embankment
Loose
wet
18,0
22
Fine sand
FSa
ID=0,33
semi dry
16,0
28
Clayey silt
saclSi
IL=0,12
semi dry
21
36
20
Silty sand
siSa
ID=0,8
wet
18,5
30,5
Clayey silt
saclSi
IL=0,22
wet
21
30
17,5
fk [ ]
Borehole nr 3
0
Nr
Layer
Symbol
Density
Humidity
g[kN/m3]
Embankment
Loose
wet
18,0
22
Fine sand
FSa
ID=0,39
semi dry
16,5
30
Clayey silt
saclSi
IL=0,09
dry
21
36
22,5
Clayey silt
saclSi
IL=0,27
wet
20
27
16,5
cu,k [kPa]
fk [ ]
Borehole nr 4
g[kN/m3]
fk [ ]
Nr
Layer
Symbol
Density
Humidity
Embankment
Loose
wet
18,0
22
Fine sand
FSa
ID=0,4
semi dry
16,5
30
Clayey silt
saclSi
IL=0,07
semi dry
21
35
22
silty sand
siSa
ID=0,5
wet
17,5
30,5
clayey silt
saclSi
IL=0,29
wet
20
28,3
16,6
cu,k [kPa]
44
8. Introduction to calculations
In chapter following rules will be described and explained: partial factors of safety,
method of geotechnical design by calculation, method of retaining wall design by
calculation.
Polish Standard PN 81 B 03020 (ANNEX 5) use g for unit weight (weight density)
In calculations designed values are used by combining the characteristic value with the appropriate
factor of safety.
8.1.2. Geotechnical design by calculation
The algorithm below shows the steps of calculations
The algorithm was prepared by Dr Ian Smith from Edinburgh Napier University
8.1.3. Designed values of actions
45
46
During the verification of geotechnical strength (i.e. GEO limit state) some effects of the actions will
depend on the strength of the ground in addition to the magnitude of the applied action and the
dimensions of the structure. Thus, the effect of an action in the GEO limit state is a function of the
action, the material properties and the geometrical dimensions.
During the verification of static equilibrium (i.e. EQU limit state) some effects of the actions (both
destabilising and stabilising) will depend on the strength of the ground in addition to the magnitude of
the applied action and the dimensions of the structure. Thus, the effect of an action in the EQU limit
state, whether it be a stabilising or a destabilising action, is a function of the action, the material
properties and the geometrical dimensions.
8.1.7. EQU
EQU: loss of equilibrium of the structure or the supporting ground when considered as a rigid body and
where the internal strength of the structure and the ground do not provide resistance.
Limit state is satisfied if the sum of the design values of the effects of destabilising actions (Edst;d) is less
than or equal to the sum of the design values of the effects of the stabilizing actions (Estb;d) together with
any contribution through the resistance of the ground around the structure (Td),
47
8.1.8. GEO
GEO: failure or excessive deformation of the ground, where the soil or rock is significant in providing
resistance.
This limit state is satisfied if the design effect of the actions (Ed) is less than or equal to the design
resistance (Rd),
8.1.9. STR
STR: failure or excessive deformation of the structure, where the strength of the structural material is
significant in providing resistance.
As with GEO limit state, the STR limit state is satisfied if the design effect of the actions (Ed) is less than
or equal to the design resistance (Rd),
48
Three Design Approaches are offered. The design approach followed reflects whether the safety is
applied to the material properties, the actions or the resistances.
Design Approach 1:
Combination 1: A1 + M1 + R1
Combination 2: A2 + M2 + R1
Design Approach 2: A1 + M1 + R2
Design Approach 3: A* + M2 + R3
A*: use set A1 on structural actions, set A2 on geotechnical actions
For axially loaded piles, DA1, Combination 2 is: A2 + (M1 or M2) + R4
POLISH NATIONAL ANNEX STATES THAT DESIGN DESIGN APPROACH NR 2 SHALL BE USED
8.2.
failure of a structural element such as a wall, anchorage, wale or strut or failure of the
connection between such elements;
combined failure in the ground and in the structural element;
failure by hydraulic heave and piping;
movement of the retaining structure, which may cause collapse or affect the appearance or
efficient use of the structure or nearby structures or services, which rely on it;
unacceptable leakage through or beneath the wall;
unacceptable transport of soil particles through or beneath the wall;
unacceptable change in the ground-water regime.
And for :
-
Gravity walls:
Embedded walls:
49
EN 1997-1:2004 9.2(1)
Examples:
50
In this chapter one panel of diaphragm wall will be calculated and designed. The
method of calculations will be explained using cut section I as an example.
Calculations will be made for each step of construction process.
51
Nr
Layer
Symbol
Density
Humidity
Depth
Thickness
Embankment
Loose
wet
0,0 1,1
1,1
Fine sand
FSa
ID=0,4
semi dry
1,1 2,0
0,9
Clayey silt
saclSi
IL=0,07
semi dry
2,0 5,2
3,2
Silty sand
siSa
ID=0,5
wet
5,2 6,4
1,2
Clayey silt
saclSi
IL=0,29
wet
Characteristics values of: soil parameters, active earth pressure coefficient (Ka), passive earth pressure
coefficient (Kp) are given below in the table. Earth pressure coefficient are taken from ANNEX 7 page
126.
g[kN/m3]
f'k [ ]
Ka
Kp
22
0,48
2,5
16,5
30
0,31
3,2
saclSi
21
35
20,7
0,46
2,3
Silty sand
siSa
17,5
30,5
0,31
3,2
Clayey silt
saclSi
20
28,3
16,6
0,41
2,0
Nr
Layer
Symbol
Embankment
18,0
Fine sand
FSa
Clayey silt
4
5
cu,k [kPa]
52
In the DA2 (A1 + M1 + R2 ) partial safety factor for reduction of soil resistance in front of the wall
gR = 1,4 will be considered in further calculations.
Soil nr 1 Embankment
f1,k = 22,00o
f 1,d =arc(tg f 1,k / )= arc(tg22,00 / 1,00 ) = 22,0 o
f 2,k = 30,00o
f 2,d =arc(tg f 2,k / )= arc(tg30,00 / 1,00 ) = 30 o
f 3,k = 20,70o
f 3,d =arc(tg f 3,k/)= arc(tg20,70 / 1,00 ) = 20,70 o
Soil nr 4 siSa
53
f 4,k = 30,50o
f 4,d =arc(tg f 4,k/ )= arc(tg30,50 /1,00 ) = 30,50 o
f 5,k = 16,60o
f 5,d =arc(tg f 5,k/ )= arc(tg16,60 /1,00 ) = 16,6 o
PHASE 1
PHASE 2
PHASE 3
All phases will be calculated by GEO5 software. PHASE 3 will be calculated manually.
54
55
56
IMPORTANT : t is the dimension of the wall under the excavation level, that means that
7,5 m +t = total height of the wall.
ea,k (7,5 +t) = 14,12 + 0,41 * 20,00 *(t + 1,1) = 8,2 t + 23,14 kN/m2
ea,d (7,5 +t) = 14,12 + 1,35 *0,41 * 20,00 *(t + 1,1) = 8,2 t + 31,24 kN/m2
To calculate the resultant value of active earth pressure from permanent load (RBg,k )we assume
57
Active earth pressure from weight of the surrounding buildings and machines (temporary load):
load from the surrounding buildings = 115 kN/m2
load from the machines = 5 kN/m2
Total temporary load = 120 kN/m2
characteristic value of active earth pressure : eakn
designed value of active earth pressure : eadn
Formula according to PN EN 1997 - 1:
58
59
Water pressure was ignored, because of the high depth of ground water level (- 11 m GWL).
Passive earth pressure from weight of the soil layers (permanent load):
Formula according to PN EN 1997 - 1:
60
F(t) = 18,83
t=2,5
F(t) = 7,29
t=2,8
F(t) = 0,25
t=2,9
F(t) = -2,10
t=3
F(t) = -4,46
Assumed value t=2,8m,
61
[Annex 9]
f=p;gr*t/2=0,5p*t/2
According to PN-83/B-03010 graph nr 9 :
for:
f 5,k = 16,60o
and for :
t = 2,8 m
f=(0,5*0,072*280)/2=5,04 mm
The minimum value of the wall displacement in relation to the soil behind the wall:
A=5,04/(410+280)=0,0073
For soils, appearing behind the wall according to graph 8 PN-83/B-03010:
for:
f = 30,50o
and for:
h = 10,7 3,4 = 7,3 m
Referring to obtain parameters:
A=0,0073 > a=0,002
CONCLUSION
Wall anchorage length can be considered as sufficient.
62
Requirement anchorage length t is assumed as 3,2 m according to previous calculations, that gives
the total length of diaphragm wall equals 10,7 m.
Active earth pressure from weight of the soil layers (permanent load) at level z=7,5 m + 3,2 m
ea,k (6,4 +3,2) = 8,2 *3,2 + 23,14 = 49,38 kN/m2
ea,d (6,4 +3,2) = 49,38 * 1,35 = 66,66 kN/m2
Passive earth pressure from weight of the soil layers (permanent load) at level z=3,2 m under the
excavation level
eph2,k= 40t+80,04=40*3,2+80,04=208,04 kN/m2
eph2,d=208,04/1,4 = 148,6 kN/m2
Reaction from active pressure from temporary load
RBpk = 1/(4,1+0,5*3,2)(24,6*3,22 + 204,18*3,2 + 97,95) = 176,01 kN/m
RBpd = 176,01 * 1,5 = 264,15 kN/m
Reaction from active earth pressure from permanent load
RBgk = 1/(4,1+0,5*3,2) (5,49*3,23 + 52,76*3,22 + 139,19*3,2 + 185,71) = 183,34 kN/m
RBgd = 183,34 * 1,35 = 247,5 kN/m
Graphs of the eart active and passive pressures are given below.
63
Graph 3. Active and passive soil pressures - characteristic values (from temporary and permanent
loads)
64
Graph 4. Active and passive soil pressures - designed values (from temporary and permanent
loads)
65
K*=(Kp-Ka)*g;
K*u= ed 0,5*C
earth active pressure from the weight of the soil at the bottom level of excavation:
ea,k (7,5) = (18,0*1,1+16,5*0,9+21,00*3,2+17,5*1,2+20,00*1,1) * 0,41 2 * 28,30 * =
23,14 kN/m2
ea,d (7,5) = 23,14 * 1,35 = 31,24 kN/m2
earth active pressure from the temporary load at the bottom level of excavation:
ea,k2 (7,5) = 49,2 kN/m2
ea,d2 (7,5) = 49,2 * 1,5 = 73,8 kN/m2
earth passive pressure from the weight of the soil at the bottom level of excavation:
ep,h1k = 80,04 kN/m2
ep,h1 d = 80,04 / 1,4 = 57,17 kN/m2
Resultant pressure at the bottom level of the excavation
ed = 57,17 - (73,8 + 31,24 ) = - 47,87 kN/m2
At the bottom level of excavation , the resultant earth pressure on the wall equals - 47,87 kN/m2 ('-' in
this case means the active pressure)
Resultant earth pressure value at the depth of -3,2 m under the excavation level .
148,6 - (73,8 + 66,6 ) = 8,2 kN/m2
At a depth of 3,2 m under the excavation level, the resultant earth pressure on the wall equlas 8,2
kN/m2 ('+' in this case means the passive pressure)
66
67
68
Location of '0' point (where resultant of passive and active earth pressure equals zero)
According to the graph 6 'u' value (zero point) is assumed at the depth of 2,7 m under the excavation
level.
Determination of resultant forces of active and passive earth pressures (designed values)
The graph of results from the table above is given on page 70. According to the graph , the Ra
force can be determined from thr scheme:
69
70
Determination of reactions
According to:
The diaphragm wall was divided into 9 sections, according to locations of resultant forces. Then, all
parameters were introduced to the mathematical software RM-WIN (Polish engineering software) to
obtain the graphs:
71
The maximum shear force according to table from software equals 555,506 kN and the maximum
bending moment -401, 585 kNm.
The maximum bending moment manually calculated according to graph 7:
Mmax1= - 101,79 * (0,98+1,85) - 60,45*1,85 + 353,50*0,2 +123,39*2,41 + 108,85* (1,07+2,41) - 96,5* (1,98 +
1,32 + 1,07 + 2,21 +0,2) = - 401,6 kNm
The difference between bending moments from manually calculation and software calculation
equals 0,015. The manually calculation can be considered as correct.
72
The method of calculation diaphragm wall with one strut is already known. To calculate the diaphragm
wall in 5.phase (with 3 struts) we have to only change the static model and add two additional reactions.
-18,64 * 0,57 16,51 * (0,98 + 0,57 - 0,2) 121,66 * (0,57 + 0,98 + 2,05 0,2)
-64,8* (0,57 + 0,98 + 2,05 + 2,21) 37,82 * (1,07 +2,21 + 2,05 + 0,98 +0,57
0,2) + 80,36 * (2,5 + 1,07 +2,21 + 2,05 + 0,98 + 0,57) + RC *7,35 + Rb * 3,2 = 0
3,87 +7,35 Rc = - 3,2 Rb
Rb = -1,2 2,29 Rc
MB = 0; Ra*3,2 - 18,64 * (3,2 0,57) - 16,51 * (3,2 + 0,57 - 0,98) 121,66 * 0,2 - 64,8 *
(2,21 +0,2 ) - 37,82 * (1,07 +2,21 +0,2) 80,36 * (2,5 + 1,07 + 2,21 + 0,2) Rc
* 3,95 = 0
Ra = 1,23 Rc - 88
73
MC = 0; 18,64 * (3,2 + 3,95) + 16,51 * (2,05 + 2,21 + 1,07) + 121,66 * (2,21 + 1,07) 64,8 * 1,07 + 37,82 * 0,1 + 80,36 * 2,5 + Rb*3,95 +Ra * 7,15 = 0
Rb = 1,81 Ra + 395,2
X = 0;
Using relations between different reactions it is possible to find the values of forces:
-1,2 2,29 Rc = 1,81(1,23 Rc 175) + 191,31
Rc = -76,80 kN
Ra = - 1,23 Rc 88 = 1,23* -76,80 88
Ra = - 6,04 kN
Rb = 1,81 Ra + 395,2
Rb = 465,4 kN
Then, all parameters are introduced to the mathematical software RM-WIN to obtain the graphs. The
method of calculation are analogous to previous ones, but more complicate due to number of unknown
reactions.
74
161,46 kN/m
508,20 kNm
Max.displacement
1,2 mm
PHASE 2
Max. shear force
351,35 kN/m
537,97 kNm
Max.displacement
8,6 mm
PHASE 3
Max. shear force
513,90 kN/m
864,8 kNm
Max.displacement
18,5 mm
PHASE 4
Max. shear force
531,93 kN/m
828,47 kNm
Max.displacement
4,0 mm
PHASE 5
Max. shear force
546,61 kN/m
75
861,42 kNm
Max.displacement
3,6 mm
h=0,80 m
H=10,7 m
Ribs cover
c=0,05m
Concrete class
C30/37
Steel AI,
Steel AIII-RB400W
Assumed reinforcement :
fctd=1,33 MPa
Ecm=32 GPa
Calculations:
cover:
a=c+c+1+0,5*2
a = 50+10+12+0,5*40=92 mm
d = h-a
d= 80 9,2 cm = 70,8 cm
Reinforcement As1
76
Assumed reinforcement :
The value 85,59 cm2 is a reinforcement that we need for 1 linear meter of wall.
In this project diaphragm walls are mostly made of panels that are 750 cm length. Required
reinforcement for 750cm length panel is:
77
78
200x200 = 40000ZL
50x1200 = 6000 ZL
5x100x14 = 7000ZL
The global price : 56000+474000+40000+6000+7000 =583000 ZL = 1 166 000Dkk
79
80
It is recommend to :
look around for obvious signs of underground services, eg valve covers or patching of the road
surface.
Use locators to trace any services. Mark the ground accordingly.
Make sure that the person supervising excavation work has service plans and knows how to
use them. Everyone carrying out the work should know about safe digging practices and
emergency procedures.
Access
It is recommend to provide good ladder access or other safe ways of getting in and out of the
excavation.
Fumes
Exhaust fumes can be dangerous. Do not site petrol or diesel-engined equipment such as generators or
compressors in, or near the edge of, an excavation unless fumes can be ducted away or the area can
be ventilated.
Protecting the public
Fence off all excavations in public places to prevent pedestrians and vehicles falling into them.
Where children might get onto a site out of hours, take precautions (eg backfilling or securely
covering excavations) to reduce the chance of them being injured.
Supervision
A competent person must supervise the installation, alteration or removal of excavation support.
People working in excavations should be given clear instructions on how to work safely.
Inspecting excavations
A competent person must inspect excavations:
- at the start of each shift before work begins;
- after any event likely to have affected the strength or stability of the excavation;
- after any accidental fall of rock, earth or other material.
81
12. Conclusion
This project was about excavation works for Skyscraper in Wroclaw (Poland) . Because the
foundations have been designed using Polish methods and Standards, the aim was to provided to
Danish companies an idea about how the other European countries (in this case:Poland) work and how
they design foundations. The designed elements are relevant to be able to start the construction and
the drawing provide an easy way to build the structure diaphragm walls. The Polish way to calculate
the structural element are probably different from the Danish way but thanks to the Eurocodes we are
going to move to a standardization of the construction rules to make the international projects as that
one more accessible to European companies.
Deep excavations in urban areas require retaining structures to ensure the slopes and protect
surrounding buildings. Geological and geotechnical analysis were made at first. According to assumed
soil layers and water level in the area, all calculations have been done.
An important issue of this project was determination of retaining structures. For all sides of the
constructions site, the best solution diaphragm walls were chosen. The main reason was the proximity
to other existing buildings. The next step was to find proper type of diaphragm wall (in this case: strutted
method ) and to analyze deep excavation methods. The best solutions for Skyscraper occurred top and
down method very fast one.
Calculations for dimensioning the walls were made in two different ways: by hand and Polish
engineering software RM WIN, and by GEO 5 . Calculations were made by using safety factors from
relevant parts of Eurocode 7 and some Polish Standards. Calculation methods and equations are found
mainly from study materials from Polish geotechnic' books .
For dewatering, the method called Simple Drainage was selected, because it is suitable in clay soils.
To conclude, the estimation of the price and of the duration were done.
82
13. References
CONSULTATIONS WITH LECTURERS
Consultations with Sara Elisabeth Kjrgaard - emails
COURSES AT WARSAW UNIVERSITY OF TECHNOLOGY
Bsc of Civil Engineering with specialization : geotechnics
BOOKS AND LITERATURE
[1] Wysokiski L., Kotlicki W., Godlewski T., Projektowanie geotechniczne wedug Eurokodu 7, Instytut
Techniki Budowlanej, Warszawa 2011
[2] Kosiski B. Projektowanie obudw gbokich wykopw. Seminarium GBOKIE WYKOPY NA
TERENACH WIELKOMIEJSKICH, Warszawa 19 listopada 2011
[3] Kotlicki W., Wysokiski L. Ochrona zabudowy w ssiedztwie gbokich wykopw. Wydawnictwo ITB
nr 376/2002.
[4] Siemiska-Lewandowska A., Grzegorzewicz K., Kosiski B. Problemy budowy gbokich podziemi
budynkw uytecznoci publicznej. Konferencja Naukowa KRYNICA 2003.
[5] Siemiska-Lewandowska A., Mitew-Czajewska M., Design of deep excavations according to
Eurocode 7, Warsaw University of Technology, Studia Geotechnica et Mechanica, Vol. XXX, No. 12,2008
[6] Siemiska-Lewandowska A., Aktualne problemy budowy i projektowania gbokich wykopw, cz.1.
Nowoczesne Budownictwo Inynieryjne, Marzec - Kwiecie 2010.
[7] Siemiska-Lewandowska A., Aktualne problemy budowy i projektowania gbokich wykopw, cz.2.
Nowoczesne Budownictwo Inynieryjne, Maj - Czerwiec 2010.
[8] Rychlewski P., Gbokie wykopy w zabudowie miejskiej, GEOINYNERIA drogi mosty tunele
03/2006 (10)
[9] Florkiewicz A., cigao J., Problemy projektowe wymiarowania gbokich budowli podziemnych,
GEOINYNERIA drogi mosty tunele 04/2005 (07)
[10] Krasiski A., Obliczanie i projektowanie cianek szczelnych. Katedra Geotechniki, Geologii i
Budownictwa Morskiego, Wydzia Inynierii Ldowej i rodowiska Politechniki Gdaskiej, Gdask 2007.
[11] Warunki techniczne wykonywania cian szczelinowych. Instytut Badawczy Drg i Mostw,
Informacje, Instrukcje zeszyt nr 35 Warszawa 1992.
[12] Wiun Z. Zarys geotechniki. Wydawnictwa Komunikacji i cznoci, wydanie 7, Warszawa 2005.
[13] Pisarczyk S. Mechanika gruntw. Oficyna Wydawnicza Politechniki Warszawskiej, wydanie III,
warszawa 1999.
[14] P.B Yurkevivh, DEVELOPMENT TOP-DOWN METHOD OF UNDERGROUND CONSTRUCTION
OR HI-TECH IN RUSSIAN, Yurkevich Engineering Bureau ltd, Moscow, Russian Federation
STANDARDS:
[15] PN EN 1538:2002 Wykonawstwo specjalnych robt geotechnicznych. ciany szczelinowe
[16] PN - EN 1997 -1:2008 Eurokod 7 Projektowanie geotechniczne. Cz 1:Zasady oglne
83
SOFTWARES:
[26] GEO 5
[27] RM-WIN
[38] Autocad 2009
[29] MS Office
84