exe
===============================================
Default Project..................................................ADAC-T2
-R3
Projects:
ADAC-T2-R3......................................................
.ADAC : MIDFIELD AIRSIDE ROAD TUNNEL CONSTRUCTION : PACKAGE 2 - RESEQUENCE WORK
PROGRAMME
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Actual
Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calculate float based on finish date of .........................Each pr
oject
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................1907
# Not Started....................................................1443
# In Progress....................................................27
# Completed......................................................437
# Relationships..................................................3131
# Activities with Constraint.....................................27
Project:
ADAC-T2-R3
Activity:
CN0100RI004551
Taxiway "E" Commissioned (Taxiway E7 and E8 Remain Closed)
Project:
ADAC-T2-R3
Activity:
CN01PSEX010110
Excavation Clearance for Pump and Tech Room after Utility Diversion if any (By M
ain Contractor)
Project:
ADAC-T2-R3
Activity:
CN01S300004571
Removal of 24" Jet Fuel Line @ Seg 03 ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN020000005872
Closure of Taxiway "S" (By ADAC) and Stand downgrading/Closure
Project:
ADAC-T2-R3
Activity:
CN0200EX005940
Excavation Clearance for Units 05,06 after Utility Diversion if any (By Main Con
tractor)
Project:
ADAC-T2-R3
Activity:
CN0200EX5990
Excavation Clearance for Units 01,02 after Utility Diversion if any (By Main Con
tractor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6030
Excavation Clearance forUnit 03,04 after Utility Diversion if any (By Main Contr
actor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6090
Excavation Clearance for Spcl seg 01 and 02 after Utility Diversion (By Main Con
tractor)
Project:
ADAC-T2-R3
Activity:
CN0200UD005851
Diversion of AGL - Preparation work ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN3B00EX007500
Excavation Clearance for Open Section after Utility Diversion if any (By Main Co
ntractor)
Project:
ADAC-T2-R3
Activity:
DSKD0000000661
Issue of Builder Work drawing 100%
Project:
ADAC-T2-R3
Activity:
FGD2010 DELAYED
DIVERSION OF EXISTING CABLE AT ZONE 1 AFFECTING COMPLETION OF EXCAVATION
Project:
ADAC-T2-R3
Activity:
FGD3010 TOTAL TI
ME LOSS IN EXCAVATION COMPLETION DUE TO SITE ACCESS, POLICE INSPECTION AND SECUR
ITY ISSUE
Project:
ADAC-T2-R3
Activity:
FGD4010 IFC Draw
ing Issued for Utility Trench at Unit 07 (05 May 15 Issued)
Project:
ADAC-T2-R3
Activity:
FGD4015 Revised
IFC Drawing issued for Utility Trench at Unit 07 ( 17 May 15 Issued)
Project:
ADAC-T2-R3
Activity:
GNAD0000000020
Advance Notification to ADAC for Taxiway "E,E7 and E8" Closure ( Part of RFP, Co
ntractual Milestone)
Project:
ADAC-T2-R3
Activity:
GNAD0000000021
Advance Notification to ADAC for Taxiway "F" and "TLS" Closure (30 Days Notice)
Project:
ADAC-T2-R3
Activity:
GNAD0000000051
Closure of Taxiway E,E7 and E8 By ADAC
Project:
ADAC-T2-R3
Activity:
GNAD0000000091
ADAC Clearance to Start Preparatory Work for AGL Diversion Taxiway "F" Zone 2
Project:
ADAC-T2-R3
Activity:
GNAD0000000101
Closure of Taxiway "F"
Project:
ADAC-T2-R3
Activity:
GNCM0000000001
Notice to Commence (Commencement Date)
Project:
ADAC-T2-R3
Activity:
GNCM0000999998
Completion of Section 5
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GR000000000371
Removal of Facilities
Project:
ADAC-T2-R3
Activity:
GR000000000391
Removal of Site Laboratory
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS200
0
Final Design Drawing for MJF Chambers
Project:
ADAC-T2-R3
Activity:
SAP1 M008
Project Completion
Errors:
------Warnings:
--------Activities without predecessors..................................4
Project:
ADAC-T2-R3
Activity:
GNCM0000000001
Notice to Commence (Commencement Date)
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS200
0
Final Design Drawing for MJF Chambers
Project:
JET FUEL LINE DIVERSION
Project:
Commencement Date
ADAC-T2-R3
Activity:
SAP1 A1000
ADAC-T2-R3
Activity:
SAP1 M001
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
0
Access to Chamber 26B from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
0
Access to Chamber 26A from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
Reinstatement of Cable Ducts (By Others)
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 102
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 103
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 101
Project:
ADAC-T2-R3
Activity:
Completion of 24" MJF Diversion Including E&I Works
Project:
ADAC-T2-R3
Activity:
Project Completion
GNCM0000999999
GNCM0000999999
GNCM0000999999
GNCM0000999999
SAP1 16" CONS107
SAP1 16" CONS120
SAP1 24" ESD2010
SAP1 M003
SAP1 M004
SAP1 M005
SAP1 M006
SAP1 M008
Scheduling/Leveling Results:
---------------------------# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................1907
# Relationships with other projects..............................0
Data Date........................................................16-Dec15
Earliest Early Start Date........................................16-Dec15
Latest Early Finish Date.........................................13-Feb17
Exceptions:
----------Critical Activities..............................................283
Project:
ADAC-T2-R3
Activity:
CN0000AS011171
Asphalt Leveling Course Carriageway- Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000AS011181
Asphalt Tack Coat Carriageway - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000AS011191
Asphalt Wearing Course Carriageway - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000KB011121
Installation of Kerb - Side Walk ( 3rd Stage 400 Meter)
Project:
ADAC-T2-R3
Activity:
CN0000MC011131
Mass Concrete Blinding - Side Walk ( 3rd Stage 400 Meter)
Project:
ADAC-T2-R3
Activity:
CN0000MI011041
Fire Protection Board at Wall and Ceiling
Project:
ADAC-T2-R3
Activity:
CN0000MI011151
Installation of Channel Grating Heavy Duty - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000MI011161
Installation of Manhole Cover - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000MP011021
Fan Installation
Project:
ADAC-T2-R3
Activity:
CN0000MP011031
MEP First and Second Fix
Project:
ADAC-T2-R3
Activity:
CN0000PB011141
Project:
ADAC-T2-R3
Activity:
CN01S2RC008753
Concreting of Wall-West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2WP008753
Waterproofing wall for Spcl. Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S300004571
Removal of 24" Jet Fuel Line @ Seg 03 ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN01S3BC004621
Leveling & Blinding Works-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004711
Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004811
Stripping wall Shutter and Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004871
Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3EX004571
Excavation for found. Hard strata of tunnel -Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004581
Excavation for found. Soft Strata of tunnel - Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004591
Trimming of Exc. Surface soft strata of tunnel - Special Seg.3 and Seg 2 (Partia
l)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004601
Trimming of Exc. Surface Hard strata of tunnel - Special Seg.3 and Seg 2 (Partia
l)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004611
Disposal of Exc. Material tunnel -Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3FW004691
Closing of Side Shutters-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004751
Scaffold Erection for Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004761
Erection & Placement of One side shutter-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004791
Closing of Shutters-Wall SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004821
Scaffold Erection for Slab-SG 3 (Using Gantry)
Project:
ADAC-T2-R3
Activity:
CN01S3FW004831
Erection & Placement of Soffit-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004851
Closing of Shutters-Slab West side SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3ME004781
MEP Inserts-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3PS004631
1000 Gauge PE Foil-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3PS4631
Force Main - Trenching ,Blinding,Sleeve,Concrete Encasement and backfill
Project:
ADAC-T2-R3
Activity:
CN01S3RB004681
Rebar Fixing for Bases-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RB004771
Rebar Fixing for Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RB004841
Rebar Fixing for slab-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004701
Concreting of Bases-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004801
Concreting of Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004861
Concreting of Slab-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC4861
Leveling and Concrete saddle casting for Installation of RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4871
RC Pipe Placing in Position - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4881
Concrete Surround RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4891
Site Measurement for Ordering Cut Length - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4901
Procurement of Cut Piece - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4911
Installation of Cut Pieces - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4921
Installation of Precast Chamber - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4931
Backfilling with Suitable material over RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3SC004661
Screed Protection over Waterproofing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3SG004651
Slip Sheet Geotextile 100g/m2-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3WP004641
Waterproofing Base-SG 3
Project:
ADAC-T2-R3
Activity:
CN0200BC6921
1000 Gauge PE Foil/Blinding Approach Slab Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7001
Backfilling : First Stage Wall for Units Spcl.Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7011
Final Fill Roof for Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7021
Backfilling upto Approach Slab Units Spcl.Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7051
Backfilling : First Stage Wall for Units Spcl.Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200BK7061
Backfilling : First Stage Wall for Units Spcl.Seg 4
Project:
ADAC-T2-R3
Activity:
CN0200EJ006851
EJ/CJ-Wall Unit Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200EX6011
Trimming of Exc. Surface soft strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6021
Trimming of Exc. Surface Hard strata of tunnel -Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6030
Excavation Clearance forUnit 03,04 after Utility Diversion if any (By Main Contr
actor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6031
Disposal of Exc. Material tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6041
Excavation for found. Hard Strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6051
Excavation for found. Soft Strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6111
Reinstatement of 24" Jet Fuel line over Seg 03 (By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6121
Removal of 16" Jet Fuel line from Unit 03/04(after 24" Reinstatement )
Project:
ADAC-T2-R3
Activity:
CN0200PD6881
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200PD6901
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200PD6911
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 4
Project:
ADAC-T2-R3
Activity:
CN0200PW6871
3.2 mm Protection Membrane for wall Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200PW6881
Project:
ADAC-T2-R3
Activity:
CN02S1FW006111
Closing of Shutters-East Wall SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006231
Scaffold Erection for Slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006241
Erection & Placement of Soffit-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006261
Closing of Shutters-Slab SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006291
Stripping of Falsework-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1ME006101
MEP Inserts-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RB006091
Rebar Fixing for Wall-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RB006251
Rebar Fixing for slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RC006121
Concreting of Wall-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RC006271
Concreting of Slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN3B00BC8951
1000 Gauge PE Foil/Blinding Approach Slab Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00BK10101
Backfilling : First Stage Wall for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00BK10111
Final Fill Roof for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000141
EJ/CJ-Wall Unit 3
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000151
EJ/CJ-Wall Unit 4
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000161
EJ/CJ-Wall Unit Seg 2 West Side
Project:
ADAC-T2-R3
Activity:
CN3B00EX10061
Removal of Sheet Pile Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00MI007551
Shoring Work (Units 03 - 04)
Project:
ADAC-T2-R3
Activity:
CN3B00MI7561
Shoring Work ( Seg 3)
Project:
ADAC-T2-R3
Activity:
CN3B00MI7571
Removal of Jet Fuel line Chamber at Unit 03/04 and Fence Readjustment before sho
ring
Project:
ADAC-T2-R3
Activity:
CN3B00PD1000051
300/200 Perforated GRP Pipes with Gravel Surround for Units seg 02
Project:
ADAC-T2-R3
Activity:
CN3B00PD1000061
300/200 Perforated GRP Pipes with Gravel Surround for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00PW10041
3.2 mm Protection Membrane for wall Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00RB8991
Rebar for Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00RC10081
Concrete of Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00SC8931
50m Thick Sand Cement Protection Screed at Roof Top Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10031
Waterproofing wall and Roof for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10041
Waterproofing below approach Slab for Units(3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10051
Waterproofing above Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B03BC007841
CN3B03CU007921
CN3B03FW007901
CN3B03FW007931
CN3B03FW007941
CN3B03FW007971
CN3B03FW008001
CN3B03FW008011
CN3B03FW008031
CN3B03ME007961
CN3B03PS007851
CN3B03RB007891
CN3B03RB007951
CN3B03RB008021
CN3B03RC007911
CN3B03RC007981
CN3B03RC008041
CN3B03SC007881
CN3B03SG007871
CN3B03WP007861
CN3B04FW008391
CN3B04FW008401
CN3B04FW008431
CN3B04FW008461
CN3B04FW008471
CN3B04FW008491
CN3B04ME008421
CN3B04RB008411
CN3B04RB008481
CN3B04RC008441
CN3B04RC008501
Concreting of Slab-Unit 4
Project:
ADAC-T2-R3
Activity:
CO000000000441
As Built Drawing Submission and Approval
Project:
ADAC-T2-R3
Activity:
CO0000SN011209
Punchlisting Item - System wise
Project:
ADAC-T2-R3
Activity:
CO0000SN011210
Authority Inspection (GCAA and other Authorities)
Project:
ADAC-T2-R3
Activity:
CO0000SN011211
Snagging and Desnagging Tunnel
Project:
ADAC-T2-R3
Activity:
DSKD0000000663
Issue Secant Pile Design for Shoring around Tech. and Pump Room
Project:
ADAC-T2-R3
Activity:
DSKD0000000672
Final Design Drawing for Spcl. Seg 1 to 4
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GR000000000371
Removal of Facilities
Project:
ADAC-T2-R3
Activity:
GR000000000391
Removal of Site Laboratory
Project:
ADAC-T2-R3
Activity:
MB000000000572
Sub Contractor Secant Pile - Mobilization
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS107
0
Access to Chamber 26B from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS108
0
Install Pipe Supports under Existing Line in New Chamber Location
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS109
0
Closing of Isolation Valves of South Line in existing chamber 33 and 5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS110
0
Draining of the Fuel Line between Chamber 33 and 5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS111
0
Nitrogen Purging
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS112
0
Cold cutting of existing 16" existing line between Ch 5 and 33 at the lo
cation of new chamber 26B
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS114
0
Welding of Flange in proposed new chamber and NDT
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS115
0
Installation of 16" Gate Valve and pre fabricated spools
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS116
0
Installation of supports
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS117
0
Opening of valves in chamber 33 and 5, check for leaks,open Valve in 26B
& put Line back to Service
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS120
0
Access to Chamber 26A from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS121
0
Closing of Isolation Valves of South Line in existing CH-33 and CH-5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS122
0
Checking in existing Low Points for Fuel residue and Draining
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS123
0
Nitrogen Purging
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS124
0
Tie in of Pipe work in Chamber 26A, including tee, elbow, make up piece
etc. for South Line
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS127
0
Installation of supports
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS132
0
Opening of valves in chamber 33 and 5, check for leaks,open Valve in 26A
& put South Line back to Service
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS136
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS135
Removal of Flushing Manifold and installation of Pit Valve
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS136
0
Removal of Flushing Manifold and installation of Pit Valve
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS137
0
ADNOC checks with Pit Cleaner
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS138
0
ADNOC checks with Pit Cleaner
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS144
0
Backfilling up to 1.5M Below the Pit Box Top By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS145
0
Backfilling Surround Pit Box up to FGL By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS146
0
Backfilling up to 1.5M Below the Pit Box Top By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS147
0
Backfilling Surround Pit Box up to FGL By Others
Project:
ADAC-T2-R3
Activity:
SAP1 M008
Project Completion
Project:
ADAC-T2-R3
Activity:
SD000000000702
Shop Drawing Submittal - Excavation - Tech Room and Pump Room Incl. Secant Pile
Project:
ADAC-T2-R3
Activity:
SD000000000742
Shop Drawing Approval - Excavation - Tech Room and Pump Room Incl. Secant Pile
Project:
ADAC-T2-R3
Activity:
SD000000000841
Shop Drawing Submission - Tunnel Base Unit Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
SD000000001021
Shop Drawing Approval - Tunnel Base Unit Spcl. Seg 3