Sunteți pe pagina 1din 15

Scheduling/Leveling Report - 15-Feb-16 - PM.

exe
===============================================
Default Project..................................................ADAC-T2
-R3
Projects:
ADAC-T2-R3......................................................
.ADAC : MIDFIELD AIRSIDE ROAD TUNNEL CONSTRUCTION : PACKAGE 2 - RESEQUENCE WORK
PROGRAMME
Scheduling/Leveling Settings:
----------------------------General
------Scheduling ......................................................Yes
Leveling ........................................................No
Ignore relationships to and from other projects .................No
Make open-ended activities critical .............................No
Use Expected Finish Dates .......................................Yes
Schedule automatically when a change affects dates ..............No
Level resources during scheduling ...............................No
Recalculate assignment costs after scheduling ...................No
When scheduling progressed activities use .......................Retaine
d Logic
Calculate start-to-start lag from ...............................Actual
Start
Define critical activities as Total Float less than or equal to .0
Compute Total Float As ..........................................Finish
Float
Calculate float based on finish date of .........................Each pr
oject
Calendar for scheduling Relationship Lag ........................Predece
ssor Activity Calendar
Advanced
-------Calculate multiple float paths...................................No
Statistics:
----------# Projects.......................................................1
# Activities.....................................................1907
# Not Started....................................................1443
# In Progress....................................................27
# Completed......................................................437
# Relationships..................................................3131
# Activities with Constraint.....................................27
Project:
ADAC-T2-R3
Activity:
CN0100RI004551
Taxiway "E" Commissioned (Taxiway E7 and E8 Remain Closed)
Project:
ADAC-T2-R3
Activity:
CN01PSEX010110
Excavation Clearance for Pump and Tech Room after Utility Diversion if any (By M
ain Contractor)
Project:
ADAC-T2-R3
Activity:
CN01S300004571
Removal of 24" Jet Fuel Line @ Seg 03 ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN020000005872
Closure of Taxiway "S" (By ADAC) and Stand downgrading/Closure
Project:
ADAC-T2-R3
Activity:
CN0200EX005940
Excavation Clearance for Units 05,06 after Utility Diversion if any (By Main Con
tractor)

Project:
ADAC-T2-R3
Activity:
CN0200EX5990
Excavation Clearance for Units 01,02 after Utility Diversion if any (By Main Con
tractor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6030
Excavation Clearance forUnit 03,04 after Utility Diversion if any (By Main Contr
actor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6090
Excavation Clearance for Spcl seg 01 and 02 after Utility Diversion (By Main Con
tractor)
Project:
ADAC-T2-R3
Activity:
CN0200UD005851
Diversion of AGL - Preparation work ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN3B00EX007500
Excavation Clearance for Open Section after Utility Diversion if any (By Main Co
ntractor)
Project:
ADAC-T2-R3
Activity:
DSKD0000000661
Issue of Builder Work drawing 100%
Project:
ADAC-T2-R3
Activity:
FGD2010 DELAYED
DIVERSION OF EXISTING CABLE AT ZONE 1 AFFECTING COMPLETION OF EXCAVATION
Project:
ADAC-T2-R3
Activity:
FGD3010 TOTAL TI
ME LOSS IN EXCAVATION COMPLETION DUE TO SITE ACCESS, POLICE INSPECTION AND SECUR
ITY ISSUE
Project:
ADAC-T2-R3
Activity:
FGD4010 IFC Draw
ing Issued for Utility Trench at Unit 07 (05 May 15 Issued)
Project:
ADAC-T2-R3
Activity:
FGD4015 Revised
IFC Drawing issued for Utility Trench at Unit 07 ( 17 May 15 Issued)
Project:
ADAC-T2-R3
Activity:
GNAD0000000020
Advance Notification to ADAC for Taxiway "E,E7 and E8" Closure ( Part of RFP, Co
ntractual Milestone)
Project:
ADAC-T2-R3
Activity:
GNAD0000000021
Advance Notification to ADAC for Taxiway "F" and "TLS" Closure (30 Days Notice)
Project:
ADAC-T2-R3
Activity:
GNAD0000000051
Closure of Taxiway E,E7 and E8 By ADAC
Project:
ADAC-T2-R3
Activity:
GNAD0000000091
ADAC Clearance to Start Preparatory Work for AGL Diversion Taxiway "F" Zone 2
Project:
ADAC-T2-R3
Activity:
GNAD0000000101
Closure of Taxiway "F"
Project:
ADAC-T2-R3
Activity:
GNCM0000000001
Notice to Commence (Commencement Date)
Project:
ADAC-T2-R3
Activity:
GNCM0000999998
Completion of Section 5
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GR000000000371
Removal of Facilities
Project:
ADAC-T2-R3
Activity:
GR000000000391
Removal of Site Laboratory
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS200
0
Final Design Drawing for MJF Chambers
Project:
ADAC-T2-R3
Activity:
SAP1 M008
Project Completion
Errors:
------Warnings:
--------Activities without predecessors..................................4
Project:
ADAC-T2-R3
Activity:
GNCM0000000001
Notice to Commence (Commencement Date)
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS200
0
Final Design Drawing for MJF Chambers

Project:
JET FUEL LINE DIVERSION
Project:
Commencement Date

ADAC-T2-R3

Activity:

SAP1 A1000

ADAC-T2-R3

Activity:

SAP1 M001

Activities without successors....................................7


Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS186
0
Casing pipe installation
Project:
ADAC-T2-R3
Activity:
SAP1 16" PROC164
0
Gaskets
Project:
ADAC-T2-R3
Activity:
SAP1 24" PROC129
0
Junction Boxes
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST109
0
Cover Slab Removal of CH-35A & CH-35B By Others
Project:
ADAC-T2-R3
Activity:
SAP1 SDE A1050
Cable Tray Routing Layout for Valve Chamber CH- 35A
Project:
ADAC-T2-R3
Activity:
SAP1 SDE A1060
Cable Tray Routing Layout for Valve Chamber CH- 35B
Out-of-sequence activities.......................................2
Project:
ADAC-T2-R3
Activity:
SB000000002101
Issue RFP and MEP Subcontractor Response
Project:
ADAC-T2-R3
Activity:
SB000000002181
Issue RFP and Fire Protection Subcontractor Response
Activities with Actual Dates > Data Date.........................15
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1000
Level Transmitter
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1010
Junction Box
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1020
Cable Tray & Tray Supports
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1030
Earthing Material
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1040
Leak Detection System (Cable Type)
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1050
Cathodic Protection System
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1060
Instrument Cable
Project:
ADAC-T2-R3
Activity:
SAP1 MSE S1070
Cable Glands
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1000
Casing Sleeve Pipe
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1010
16" and Below Carbon Steel Pipe
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1020
CNAF Gasket
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1030
External Coating & Internal Lining of CS Fittings
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1040
Field Joint Coating
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1050
External Coating & Internal Lining of Pipes
Project:
ADAC-T2-R3
Activity:
SAP1 MSM A1060
CS Pipes
Milestone Activities with invalid relationships..................0

Finish milestone and predecessors have different calendars.......41


Project:
ADAC-T2-R3
Activity:
CN010000002791
Receipt of approval of passes for all plants required for excavation
Project:
ADAC-T2-R3
Activity:
CN0100RI004551
Taxiway "E" Commissioned (Taxiway E7 and E8 Remain Closed)
Project:
ADAC-T2-R3
Activity:
CN0100RI004551
Taxiway "E" Commissioned (Taxiway E7 and E8 Remain Closed)
Project:
ADAC-T2-R3
Activity:
CN020000005872
Closure of Taxiway "S" (By ADAC) and Stand downgrading/Closure
Project:
ADAC-T2-R3
Activity:
CN0200RI007071
Taxiway "F and TLS" Reinstated
Project:
ADAC-T2-R3
Activity:
CN0200RI007071
Taxiway "F and TLS" Reinstated
Project:
ADAC-T2-R3
Activity:
CN0200RI007071
Taxiway "F and TLS" Reinstated
Project:
ADAC-T2-R3
Activity:
GNAD0000000051
Closure of Taxiway E,E7 and E8 By ADAC
Project:
ADAC-T2-R3
Activity:
GNAD0000000101
Closure of Taxiway "F"
Project:
ADAC-T2-R3
Activity:
GNCM0000999998
Completion of Section 5
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6

Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
0
Access to Chamber 26B from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
0
Access to Chamber 26A from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
Reinstatement of Cable Ducts (By Others)
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 102
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 103
Project:
ADAC-T2-R3
Activity:
Completion of Relocation for Stand 101
Project:
ADAC-T2-R3
Activity:
Completion of 24" MJF Diversion Including E&I Works
Project:
ADAC-T2-R3
Activity:
Project Completion

GNCM0000999999
GNCM0000999999
GNCM0000999999
GNCM0000999999
SAP1 16" CONS107
SAP1 16" CONS120
SAP1 24" ESD2010
SAP1 M003
SAP1 M004
SAP1 M005
SAP1 M006
SAP1 M008

Scheduling/Leveling Results:
---------------------------# Projects Scheduled/Leveled.....................................1
# Activities Scheduled/Leveled...................................1907
# Relationships with other projects..............................0
Data Date........................................................16-Dec15
Earliest Early Start Date........................................16-Dec15
Latest Early Finish Date.........................................13-Feb17
Exceptions:
----------Critical Activities..............................................283
Project:
ADAC-T2-R3
Activity:
CN0000AS011171
Asphalt Leveling Course Carriageway- Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000AS011181
Asphalt Tack Coat Carriageway - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000AS011191
Asphalt Wearing Course Carriageway - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000KB011121
Installation of Kerb - Side Walk ( 3rd Stage 400 Meter)
Project:
ADAC-T2-R3
Activity:
CN0000MC011131
Mass Concrete Blinding - Side Walk ( 3rd Stage 400 Meter)
Project:
ADAC-T2-R3
Activity:
CN0000MI011041
Fire Protection Board at Wall and Ceiling
Project:
ADAC-T2-R3
Activity:
CN0000MI011151
Installation of Channel Grating Heavy Duty - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000MI011161
Installation of Manhole Cover - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000MP011021
Fan Installation
Project:
ADAC-T2-R3
Activity:
CN0000MP011031
MEP First and Second Fix
Project:
ADAC-T2-R3
Activity:
CN0000PB011141

Paving Block - Side Walk ( 3rd Stage 400 Meter)


Project:
ADAC-T2-R3
Activity:
CN0000PM011201
Pavement Marking - Tunnel
Project:
ADAC-T2-R3
Activity:
CN0000TC011050
Testing and Comm. Mechanical and Plumbing System
Project:
ADAC-T2-R3
Activity:
CN0000TC011051
Testing and Comm. Overall Electrical System
Project:
ADAC-T2-R3
Activity:
CN0000TC011052
Power On
Project:
ADAC-T2-R3
Activity:
CN0000TC011053
Final Overall System Integration
Project:
ADAC-T2-R3
Activity:
CN0000TC011054
Testing and Comm. Complete
Project:
ADAC-T2-R3
Activity:
CN0100BK7031
Final Fill Roof Over slab to reach the bottom of Jet Fuel line - Seg 03
Project:
ADAC-T2-R3
Activity:
CN0100EJ005291
EJ/CJ-Wall Unit Seg 3
Project:
ADAC-T2-R3
Activity:
CN0100UD004421
Diversion of 24'' Jet Fuel Line -Zone 1 (Main Contractor Scope)
Project:
ADAC-T2-R3
Activity:
CN01PSEX010161
Installation of Secant Pipe around Tech Building and Pump Room Instruction on 01
jan 16
Project:
ADAC-T2-R3
Activity:
CN01S2BK008754
Backfilling: First Stage Wall Seg-02 incl. Ramp (18000 Cum)
Project:
ADAC-T2-R3
Activity:
CN01S2CU008751
Curing-Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2CU008753
Stripping wall Shutter and Curing-West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2FW008631
Scaffold Erection for Wall- Seg 04
Project:
ADAC-T2-R3
Activity:
CN01S2FW008641
Erection & Placement of One side shutter- Seg 04
Project:
ADAC-T2-R3
Activity:
CN01S2FW008661
Closing of Shutters-Wall East Side Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2FW008701
Scaffold Erection for Slab-Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2FW008711
Erection & Placement of Soffit-Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2FW008731
Closing of Shutters-Slab Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2FW008761
Stripping of Falsework-Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2FW008763
Scaffold Erection for Wall- West Side Seg 2 ( Access through Inside Tunnel)
Project:
ADAC-T2-R3
Activity:
CN01S2FW008773
Erection & Placement of One side shutter-West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2FW008783
Closing of Shutters-Wall West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2PW008752
3.2 mm Protection Membrane for wall Units Spcl. Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2RB008651
Rebar Fixing for Wall- Seg 04
Project:
ADAC-T2-R3
Activity:
CN01S2RB008721
Rebar Fixing for slab-Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2RB008723
Rebar Fixing for Wall-West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2RC008671
Concreting of Wall-East Side Seg 4
Project:
ADAC-T2-R3
Activity:
CN01S2RC008741
Concreting of Slab-Seg 4

Project:
ADAC-T2-R3
Activity:
CN01S2RC008753
Concreting of Wall-West Side Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S2WP008753
Waterproofing wall for Spcl. Seg 2
Project:
ADAC-T2-R3
Activity:
CN01S300004571
Removal of 24" Jet Fuel Line @ Seg 03 ( By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN01S3BC004621
Leveling & Blinding Works-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004711
Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004811
Stripping wall Shutter and Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3CU004871
Curing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3EX004571
Excavation for found. Hard strata of tunnel -Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004581
Excavation for found. Soft Strata of tunnel - Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004591
Trimming of Exc. Surface soft strata of tunnel - Special Seg.3 and Seg 2 (Partia
l)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004601
Trimming of Exc. Surface Hard strata of tunnel - Special Seg.3 and Seg 2 (Partia
l)
Project:
ADAC-T2-R3
Activity:
CN01S3EX004611
Disposal of Exc. Material tunnel -Special Seg.3 and Seg 2 (Partial)
Project:
ADAC-T2-R3
Activity:
CN01S3FW004691
Closing of Side Shutters-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004751
Scaffold Erection for Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004761
Erection & Placement of One side shutter-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004791
Closing of Shutters-Wall SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004821
Scaffold Erection for Slab-SG 3 (Using Gantry)
Project:
ADAC-T2-R3
Activity:
CN01S3FW004831
Erection & Placement of Soffit-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3FW004851
Closing of Shutters-Slab West side SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3ME004781
MEP Inserts-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3PS004631
1000 Gauge PE Foil-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3PS4631
Force Main - Trenching ,Blinding,Sleeve,Concrete Encasement and backfill
Project:
ADAC-T2-R3
Activity:
CN01S3RB004681
Rebar Fixing for Bases-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RB004771
Rebar Fixing for Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RB004841
Rebar Fixing for slab-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004701
Concreting of Bases-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004801
Concreting of Wall-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC004861
Concreting of Slab-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3RC4861
Leveling and Concrete saddle casting for Installation of RC Pipes

Project:
ADAC-T2-R3
Activity:
CN01S3RC4871
RC Pipe Placing in Position - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4881
Concrete Surround RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4891
Site Measurement for Ordering Cut Length - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4901
Procurement of Cut Piece - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4911
Installation of Cut Pieces - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4921
Installation of Precast Chamber - RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3RC4931
Backfilling with Suitable material over RC Pipes
Project:
ADAC-T2-R3
Activity:
CN01S3SC004661
Screed Protection over Waterproofing-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3SG004651
Slip Sheet Geotextile 100g/m2-SG 3
Project:
ADAC-T2-R3
Activity:
CN01S3WP004641
Waterproofing Base-SG 3
Project:
ADAC-T2-R3
Activity:
CN0200BC6921
1000 Gauge PE Foil/Blinding Approach Slab Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7001
Backfilling : First Stage Wall for Units Spcl.Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7011
Final Fill Roof for Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7021
Backfilling upto Approach Slab Units Spcl.Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200BK7051
Backfilling : First Stage Wall for Units Spcl.Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200BK7061
Backfilling : First Stage Wall for Units Spcl.Seg 4
Project:
ADAC-T2-R3
Activity:
CN0200EJ006851
EJ/CJ-Wall Unit Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200EX6011
Trimming of Exc. Surface soft strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6021
Trimming of Exc. Surface Hard strata of tunnel -Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6030
Excavation Clearance forUnit 03,04 after Utility Diversion if any (By Main Contr
actor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6031
Disposal of Exc. Material tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6041
Excavation for found. Hard Strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6051
Excavation for found. Soft Strata of tunnel - Units 03,04
Project:
ADAC-T2-R3
Activity:
CN0200EX6111
Reinstatement of 24" Jet Fuel line over Seg 03 (By Main Contractor)
Project:
ADAC-T2-R3
Activity:
CN0200EX6121
Removal of 16" Jet Fuel line from Unit 03/04(after 24" Reinstatement )
Project:
ADAC-T2-R3
Activity:
CN0200PD6881
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200PD6901
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200PD6911
300/200 Perforated GRP Pipes with Gravel Surround for Units Spcl. Seg 4
Project:
ADAC-T2-R3
Activity:
CN0200PW6871
3.2 mm Protection Membrane for wall Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200PW6881

3.2 mm Protection Membrane Roof Side Units Spcl. Seg 1


Project:
ADAC-T2-R3
Activity:
CN0200PW6901
3.2 mm Protection Membrane for wall Units Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200PW6911
3.2 mm Protection Membrane Roof Side Units Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200PW6921
3.2 mm Protection Membrane for wall Units Spcl. Seg 4
Project:
ADAC-T2-R3
Activity:
CN0200RB6961
Rebar Fixing for Approach Slab for Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200RC6971
Concrete for Approach Slab for Units Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200RI007011
Reinstatement of taxiway "F,TLS and other Area" - Base Course (CTBC)
Project:
ADAC-T2-R3
Activity:
CN0200RI007031
Reinstatement of taxiway "F,TLS and other Area" - Asphalt Base Course (ACBC)
Project:
ADAC-T2-R3
Activity:
CN0200RI007041
Reinstatement of taxiway"F,TLS and other Area" - Asphalt Wearing Course (PMA-2 L
ayers)
Project:
ADAC-T2-R3
Activity:
CN0200RI007051
Pavement Marking taxiway"F,TLS and other Area"
Project:
ADAC-T2-R3
Activity:
CN0200RI007071
Taxiway "F and TLS" Reinstated
Project:
ADAC-T2-R3
Activity:
CN0200SC7001
Preparation Work and Sealent over Approach Slab
Project:
ADAC-T2-R3
Activity:
CN0200SC7051
50m Thick Sand Cement Protection Screed at Roof Top Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200UD007021
AGL Duct Laying taxiway "F,TLS and other Area"
Project:
ADAC-T2-R3
Activity:
CN0200UD007022
AGL Manhole Installation taxiway "F,TLS and other Area"
Project:
ADAC-T2-R3
Activity:
CN0200UD007023
AGL Cable Puling taxiway "F,TLS and other Area"
Project:
ADAC-T2-R3
Activity:
CN0200UD007061
Fixing AGL Light and Comm. taxiway "F,TLS and other Area"
Project:
ADAC-T2-R3
Activity:
CN0200UD007062
Fence Removal Authority Inspection (GCAA, Police, Operation) for "F" and "TLS"
Project:
ADAC-T2-R3
Activity:
CN0200WP6981
Waterproofing wall for Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200WP6991
Waterproofing below approach Slab for Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200WP7001
Waterproofing above Approach Slab for Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200WP7011
Waterproofing Roof Side for Spcl. Seg 1
Project:
ADAC-T2-R3
Activity:
CN0200WP7061
Waterproofing wall for Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200WP7071
Waterproofing Roof Side for Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200WP7081
Waterproofing Roof for Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
CN0200WP7091
Waterproofing wall for Spcl. Seg 4
Project:
ADAC-T2-R3
Activity:
CN02S1CU006131
Stripping wall Shutter and Curing-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1CU006281
Curing-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006071
Scaffold Erection for Wall-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006081
Erection & Placement of One side shutter-SG 1

Project:
ADAC-T2-R3
Activity:
CN02S1FW006111
Closing of Shutters-East Wall SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006231
Scaffold Erection for Slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006241
Erection & Placement of Soffit-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006261
Closing of Shutters-Slab SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1FW006291
Stripping of Falsework-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1ME006101
MEP Inserts-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RB006091
Rebar Fixing for Wall-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RB006251
Rebar Fixing for slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RC006121
Concreting of Wall-SG 1
Project:
ADAC-T2-R3
Activity:
CN02S1RC006271
Concreting of Slab-SG 1
Project:
ADAC-T2-R3
Activity:
CN3B00BC8951
1000 Gauge PE Foil/Blinding Approach Slab Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00BK10101
Backfilling : First Stage Wall for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00BK10111
Final Fill Roof for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000141
EJ/CJ-Wall Unit 3
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000151
EJ/CJ-Wall Unit 4
Project:
ADAC-T2-R3
Activity:
CN3B00EJ1000161
EJ/CJ-Wall Unit Seg 2 West Side
Project:
ADAC-T2-R3
Activity:
CN3B00EX10061
Removal of Sheet Pile Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00MI007551
Shoring Work (Units 03 - 04)
Project:
ADAC-T2-R3
Activity:
CN3B00MI7561
Shoring Work ( Seg 3)
Project:
ADAC-T2-R3
Activity:
CN3B00MI7571
Removal of Jet Fuel line Chamber at Unit 03/04 and Fence Readjustment before sho
ring
Project:
ADAC-T2-R3
Activity:
CN3B00PD1000051
300/200 Perforated GRP Pipes with Gravel Surround for Units seg 02
Project:
ADAC-T2-R3
Activity:
CN3B00PD1000061
300/200 Perforated GRP Pipes with Gravel Surround for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00PW10041
3.2 mm Protection Membrane for wall Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00RB8991
Rebar for Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00RC10081
Concrete of Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00SC8931
50m Thick Sand Cement Protection Screed at Roof Top Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10031
Waterproofing wall and Roof for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10041
Waterproofing below approach Slab for Units(3,4)
Project:
ADAC-T2-R3
Activity:
CN3B00WP10051
Waterproofing above Approach Slab for Units (3,4)
Project:
ADAC-T2-R3
Activity:
CN3B03BC007841

Leveling & Blinding Works-Unit 3


Project:
ADAC-T2-R3
Activity:
Curing-Unit 3
Project:
ADAC-T2-R3
Activity:
Closing of Side Shutters-Unit 3
Project:
ADAC-T2-R3
Activity:
Scaffold Erection for Wall-Unit 3
Project:
ADAC-T2-R3
Activity:
Erection & Placement of One side shutter-Unit 3
Project:
ADAC-T2-R3
Activity:
Closing of Shutters-Wall Unit 3
Project:
ADAC-T2-R3
Activity:
Scaffold Erection for Slab-Unit 3
Project:
ADAC-T2-R3
Activity:
Erection & Placement of Soffit-Unit 3
Project:
ADAC-T2-R3
Activity:
Closing of Shutters-Slab Unit 3
Project:
ADAC-T2-R3
Activity:
MEP Inserts-Unit 3
Project:
ADAC-T2-R3
Activity:
1000 Gauge PE Foil-Unit 3
Project:
ADAC-T2-R3
Activity:
Rebar Fixing for Bases-Unit 3
Project:
ADAC-T2-R3
Activity:
Rebar Fixing for Wall-Unit 3
Project:
ADAC-T2-R3
Activity:
Rebar Fixing for slab-Unit 3
Project:
ADAC-T2-R3
Activity:
Concreting of Bases -Unit 3
Project:
ADAC-T2-R3
Activity:
Concreting of Wall-Unit 3
Project:
ADAC-T2-R3
Activity:
Concreting of Slab-Unit 3
Project:
ADAC-T2-R3
Activity:
Screed Protection over Waterproofing-Unit 3
Project:
ADAC-T2-R3
Activity:
Slip Sheet Geotextile 100g/m2-Unit 3
Project:
ADAC-T2-R3
Activity:
Waterproofing Base-Unit 3
Project:
ADAC-T2-R3
Activity:
Scaffold Erection for Wall-Unit 4
Project:
ADAC-T2-R3
Activity:
Erection & Placement of One side shutter-Unit 4
Project:
ADAC-T2-R3
Activity:
Closing of Shutters-Wall Unit 4
Project:
ADAC-T2-R3
Activity:
Scaffold Erection for Slab-Unit 4
Project:
ADAC-T2-R3
Activity:
Erection & Placement of Soffit-Unit 4
Project:
ADAC-T2-R3
Activity:
Closing of Shutters-Slab Unit 4
Project:
ADAC-T2-R3
Activity:
MEP Inserts-Unit 4
Project:
ADAC-T2-R3
Activity:
Rebar Fixing for Wall-Unit 4
Project:
ADAC-T2-R3
Activity:
Rebar Fixing for slab-Unit 4
Project:
ADAC-T2-R3
Activity:
Concreting of Wall-Unit 4
Project:
ADAC-T2-R3
Activity:

CN3B03CU007921
CN3B03FW007901
CN3B03FW007931
CN3B03FW007941
CN3B03FW007971
CN3B03FW008001
CN3B03FW008011
CN3B03FW008031
CN3B03ME007961
CN3B03PS007851
CN3B03RB007891
CN3B03RB007951
CN3B03RB008021
CN3B03RC007911
CN3B03RC007981
CN3B03RC008041
CN3B03SC007881
CN3B03SG007871
CN3B03WP007861
CN3B04FW008391
CN3B04FW008401
CN3B04FW008431
CN3B04FW008461
CN3B04FW008471
CN3B04FW008491
CN3B04ME008421
CN3B04RB008411
CN3B04RB008481
CN3B04RC008441
CN3B04RC008501

Concreting of Slab-Unit 4
Project:
ADAC-T2-R3
Activity:
CO000000000441
As Built Drawing Submission and Approval
Project:
ADAC-T2-R3
Activity:
CO0000SN011209
Punchlisting Item - System wise
Project:
ADAC-T2-R3
Activity:
CO0000SN011210
Authority Inspection (GCAA and other Authorities)
Project:
ADAC-T2-R3
Activity:
CO0000SN011211
Snagging and Desnagging Tunnel
Project:
ADAC-T2-R3
Activity:
DSKD0000000663
Issue Secant Pile Design for Shoring around Tech. and Pump Room
Project:
ADAC-T2-R3
Activity:
DSKD0000000672
Final Design Drawing for Spcl. Seg 1 to 4
Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Project:
ADAC-T2-R3
Activity:
GR000000000371
Removal of Facilities
Project:
ADAC-T2-R3
Activity:
GR000000000391
Removal of Site Laboratory
Project:
ADAC-T2-R3
Activity:
MB000000000572
Sub Contractor Secant Pile - Mobilization
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS107
0
Access to Chamber 26B from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS108
0
Install Pipe Supports under Existing Line in New Chamber Location
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS109
0
Closing of Isolation Valves of South Line in existing chamber 33 and 5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS110
0
Draining of the Fuel Line between Chamber 33 and 5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS111
0
Nitrogen Purging
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS112
0
Cold cutting of existing 16" existing line between Ch 5 and 33 at the lo
cation of new chamber 26B
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS114
0
Welding of Flange in proposed new chamber and NDT
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS115
0
Installation of 16" Gate Valve and pre fabricated spools
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS116
0
Installation of supports
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS117
0
Opening of valves in chamber 33 and 5, check for leaks,open Valve in 26B
& put Line back to Service
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS120
0
Access to Chamber 26A from ADNOC and ATC
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS121
0
Closing of Isolation Valves of South Line in existing CH-33 and CH-5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS122
0
Checking in existing Low Points for Fuel residue and Draining
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS123
0
Nitrogen Purging
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS124
0
Tie in of Pipe work in Chamber 26A, including tee, elbow, make up piece
etc. for South Line
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS127
0
Installation of supports
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS132
0
Opening of valves in chamber 33 and 5, check for leaks,open Valve in 26A
& put South Line back to Service
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS136

Install pipe supports under existing line in new chamber location


Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS137
0
Closing of Isolation Valves of North Line in existing chambers 33 and 26
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS138
0
Checking in existing Low Points for Fuel residue and Draining
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS141
0
Nitrogen Purging
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS143
0
Tie in of Pipe work in Chamber 26A, including tee, elbow, make up piece
etc. for North Line
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS148
0
Installation of supports
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS150
0
Opening of valves in chamber 33 and 26, check for leaks,open Valve in 26
A & put North Line to back to Service
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS152
0
Open new gate valves and allow fuel into the new sections by venting at
high and low points
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS154
0
Closing of Valves in Chamber 3 and 26
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS155
0
Draining of the old network between Chamber 26 and Chamber 3
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS156
0
Install loop
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS195
0
Draining of Fuel Between CH-33 & CH-5
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS196
0
Cold cutting and beveling of existing 16" existing south line at the loc
ation of the new chamber
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS197
0
Checking in existing Low Points for Fuel residue and Draining
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS198
0
Draining of Fuel between CH-33 & CH-26
Project:
ADAC-T2-R3
Activity:
SAP1 16" CONS199
0
Cold cutting and beveling of existing 16" existing north line at the loc
ation of the new chamber
Project:
ADAC-T2-R3
Activity:
SAP1 24" ESD2210
Reinstatement of LDS Cable Ducts
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1040
Handover of Trench by Others Sp Seg 3
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1050
Re-install removed pipe sections, fit up and welding
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1060
NDT
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1070
Field Joint Insulation
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1080
Backfilling Up To Duct Bank Level (By Others)
Project:
ADAC-T2-R3
Activity:
SAP1 24" PR1140
Weld Pit Backfilling By Others
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST100
0
Pneumatic Test of the new line between Chamber 35 A and 35 B
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST101
0
Air Blowing of the new line between Chamber 35 A and 35 B
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST102
0
Fuel Filling of New Line 501 & 502 (Subject Availabilty of Fuel from ADN
OC)
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST103
0
Pressure Test
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST104

Installation of Flushing Manifolds and hook up to Flushing Pumps


Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST105
0
Flushing and API filtration
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST106
0
Open Gate Valves in Chambers 35A and 35B
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST107
0
Removal of Flushing manifolds & Installation of Spools in CH-35A & 35B
Project:
ADAC-T2-R3
Activity:
SAP1 24" TEST108
0
Millipore Lab Report from ADNOC
Project:
ADAC-T2-R3
Activity:
SAP1 CO0010
Close-out Documentation
Project:
ADAC-T2-R3
Activity:
SAP1 CO0020
Demobilization
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS103
0
Site Access / Permit to Work
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS104
0
Closing of Valves in Chamber 3 and Chamber 26B
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS105
0
Opening of Bleed Points for venting and Draining of Fuel through Chamber
6 (Low Point)
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS106
0
Nitrogen Purging and checking for Fuel Residue
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS107
0
Cold cutting of existing pipe (two cuts per pipe)
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS108
0
Fit up and welding of pipes and fittings
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS109
0
Installation of Pit Boxes
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS110
0
Installation of Hydrant Isolation Valves and Pit Valves
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS111
0
Opening of Valves in Chamber 3 and Chamber 26B and Flushing into Bridger
s supplied by APC and Millipore tests by ADNOC
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS112
0
Removal of Flushing Manifold and installation of Pit Valve
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS113
0
ADNOC checks with Pit Cleaner
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS117
0
Site Access / Permit to Work
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS118
0
Closing of Valves in Chamber 3 and Chamber 26B
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS121
0
Opening of Bleed Points for venting and Draining of Fuel through Chamber
6 (Low Point)
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS123
0
Nitrogen Purging and checking for Fuel Residue
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS125
0
Cold cutting of existing pipe (two cuts)
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS127
0
Fit up and welding of pipes and fittings
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS129
0
Installation of Pit Boxes
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS131
0
Installation of Hydrant Isolation Valves and Pit Valves
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS133
0
Opening of Valves in Chamber 3 and Chamber 26B and Flushing into ADNOC B
ridgers
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS134
0
Opening of Valves in Chamber 33 and Chamber 5 and Flushing into ADNOC Br
idgers

Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS135
Removal of Flushing Manifold and installation of Pit Valve
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS136
0
Removal of Flushing Manifold and installation of Pit Valve
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS137
0
ADNOC checks with Pit Cleaner
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS138
0
ADNOC checks with Pit Cleaner
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS144
0
Backfilling up to 1.5M Below the Pit Box Top By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS145
0
Backfilling Surround Pit Box up to FGL By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS146
0
Backfilling up to 1.5M Below the Pit Box Top By Others
Project:
ADAC-T2-R3
Activity:
SAP1 FHR CONS147
0
Backfilling Surround Pit Box up to FGL By Others
Project:
ADAC-T2-R3
Activity:
SAP1 M008
Project Completion
Project:
ADAC-T2-R3
Activity:
SD000000000702
Shop Drawing Submittal - Excavation - Tech Room and Pump Room Incl. Secant Pile
Project:
ADAC-T2-R3
Activity:
SD000000000742
Shop Drawing Approval - Excavation - Tech Room and Pump Room Incl. Secant Pile
Project:
ADAC-T2-R3
Activity:
SD000000000841
Shop Drawing Submission - Tunnel Base Unit Spcl. Seg 3
Project:
ADAC-T2-R3
Activity:
SD000000001021
Shop Drawing Approval - Tunnel Base Unit Spcl. Seg 3
0

Activities with unsatisfied constraints..........................1


Project:
ADAC-T2-R3
Activity:
GNCM0000999999
Project Completion -Section 6
Activities with unsatisfied relationships........................0
Activities with external dates...................................0

S-ar putea să vă placă și