Activity ID
Activity Name
OD
Start
Finish
Cost (USD)
2017
Q1
787
CCGT
02-Jan-17
29-Oct-21
86383286
PA.NTP
Project start
02-Jan-17
PA.COD
Project finish
29-Oct-21
0
6139286
ENGINEERING / DESIGN
787
02-Jan-17
29-Oct-21
PA.01.03
260
02-Jan-17
06-Aug-18
675000
PA.01.01
217
02-Jan-17
02-May-18
1125000
PA.01.02
234
02-Jan-17
08-Jun-18
2025000
PA.01.04
787
02-Jan-17
29-Oct-21
2314286
534
02-Jan-17
10-Apr-20
52234000
343
02-Jan-17
07-Feb-19
38230000
PROCUREMENT
PROCURE MAIN EQUIPMENT
PA.02.01.05
300
02-Jan-17
02-Nov-18
750000
PA.02.01.04
Procure Condenser
257
02-Jan-17
31-Jul-18
980000
PA.02.01.03
279
02-Jan-17
18-Sep-18
8500000
PA.02.01.02
343
02-Jan-17
07-Feb-19
10000000
PA.02.01.01
321
02-Jan-17
20-Dec-18
18000000
300
08-Jun-18
10-Apr-20
2451000
Q2
Q3
2018
Q4
Q1
Q2
2019
Q3
Q4
Q1
Q2
2020
Q3
Q4
Q1
Q2
Q3
Q1
Q2
ENGINEE
Prepare Electrical Engineering
Prepare Civil Engineering
Prepare Mechanical Engineering
Project a
PROCUREMENT
PROCURE MAIN EQUIPMENT
Procure Control System
Procure Condenser
Procure Heat Recovery Steam Generators
Procure Steam Turbine
Procure Gas Turbines
PROCURE PACKAGE PLANTS
236
08-Jun-18
19-Nov-19
459000
214
08-Jun-18
01-Oct-19
642000
PA.02.02.01
300
08-Jun-18
10-Apr-20
1350000
257
08-Jun-18
06-Jan-20
6257000
193
08-Jun-18
15-Aug-19
625000
Procure valves
236
08-Jun-18
19-Nov-19
832000
PA.02.03.01
193
08-Jun-18
15-Aug-19
1300000
PA.02.03.03
257
08-Jun-18
06-Jan-20
3500000
214
07-Aug-18
28-Nov-19
5296000
PA.02.04.05
129
07-Aug-18
22-May-19
156000
PA.02.04.06
Procure intruments
171
07-Aug-18
23-Aug-19
270000
Procure intruments
PA.02.04.02
150
07-Aug-18
08-Jul-19
420000
PA.02.04.03
Procure MV system
171
07-Aug-18
23-Aug-19
640000
Procure MV system
PA.02.04.04
Procure cables
171
07-Aug-18
23-Aug-19
1350000
PA.02.04.01
214
07-Aug-18
28-Nov-19
2460000
484
02-May-18
20-Apr-21
23510000
CIVIL WORKS
248
02-May-18
07-Nov-19
8210000
PA.03.01.01
Site preparation
69
02-May-18
03-Oct-18
900000
PA.03.01.04
60
03-Oct-18
14-Feb-19
1250000
PA.03.01.05
71
03-Oct-18
12-Mar-19
1500000
PA.03.01.03
94
03-Oct-18
01-May-19
2250000
PA.03.01.02
179
03-Oct-18
07-Nov-19
2310000
223
14-Feb-19
29-Jun-20
10730000
420000
CONSTRUCTION
Install Condenser
94
08-Nov-19
05-Jun-20
PA.03.02.05
104
08-Nov-19
29-Jun-20
550000
PA.03.02.02
125
14-Feb-19
21-Nov-19
1600000
PA.03.02.03
174
12-Mar-19
03-Apr-20
3360000
PA.03.02.01
117
02-May-19
20-Jan-20
4800000
252
01-Oct-19
16-Apr-21
940000
84
20-Nov-19
26-May-20
150000
PA.03.03.03
Q1
Project finish
PA.02.03.04
Q4
Project start
PA.02.02.02
PA.02.03.02
Q3
CCGT
PA.02.02.03
2022
2021
Q4
17-Feb-16
page: 1 of 2
Procure cables
Procure main trafos
CONSTRUCTION
CIVIL WORKS
Site preparation
Build Foundations Steam Turbine
Build Foundations HRSGs
Build Foundations Gas Turbines
Execute main building
INSTALL MAIN EQUIPMENT
Install Condenser
Install Control System
Install Steam Turbine
Install Heat Recovery Steam Generator
Install Gas Turbines
INSTALL PACKAGE PLANTS
Install Auxiliary boilers
CCGT
Activity ID
Activity Name
OD
Start
Finish
Cost (USD)
2017
Q1
PA.03.03.01
126
10-Apr-20
18-Jan-21
PA.03.03.02
252
01-Oct-19
16-Apr-21
410000
236
08-Nov-19
20-Apr-21
2125000
Q2
Q3
2018
Q4
Q1
Q2
Q3
2019
Q4
Q1
Q2
Q3
2020
Q4
Q1
Q2
2022
2021
Q3
Q4
380000
Q1
Q2
Q3
Q4
Q1
PA.03.04.02
21
08-Nov-19
25-Dec-19
80000
PA.03.04.01
126
08-Nov-19
17-Aug-20
150000
PA.03.04.04
Install valves
168
20-Nov-19
30-Nov-20
495000
PA.03.04.03
210
06-Jan-20
20-Apr-21
1400000
210
08-Nov-19
19-Feb-21
1505000
210
08-Nov-19
19-Feb-21
75000
PA.03.05.02
21
08-Nov-19
25-Dec-19
120000
PA.03.05.06
Install intruments
126
08-Nov-19
17-Aug-20
250000
PA.03.05.01
21
28-Nov-19
14-Jan-20
300000
PA.03.05.04
Install cables
210
08-Nov-19
19-Feb-21
360000
PA.03.05.03
Install MV system
168
08-Nov-19
18-Nov-20
400000
218
29-Jun-20
29-Oct-21
4500000
COMMISSIONING
PA.04.02
64
29-Jun-20
18-Nov-20
700000
PA.04.05
86
22-Feb-21
01-Sep-21
800000
PA.04.01
43
29-Jun-20
02-Oct-20
900000
PA.04.03
64
29-Jun-20
18-Nov-20
900000
PA.04.04
86
20-Apr-21
29-Oct-21
1200000
17-Feb-16
page: 2 of 2