Documente Academic
Documente Profesional
Documente Cultură
SAIC NUMBER
SAIC-A-2009
WBS / BI / JO NUMBER
EQUIPMENT ID NUMBER(S)
EQUIPMENT DESCRIPTION
REV. NO.
DATE APPROVED
25-May-05
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
EQPT CODE
SYSTEM ID.
PLANT NO.
MH's SPENT
TRAVEL TIME
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
A1
Best Practice
A2
Best Practice
A3
Best Practice
A4
Flanges that will not be disturbed after the pressure test are
marked/identified and tightened WITH the approved SAIC-L-2014 &
SATR-L-2001.
Best Practice
A5
SAES-A-004,
Para. 7.1.2
A6
SAES-A-004,
Para. 7.1.4
A7
SAES-A-004,
Para. 7.2
A8
SAES-A-004,
Para. 7.5.2
A9
Expansion joints and spring hangers or spring supports are provided with
temporary restraints where needed to prevent excessive travel or
deformation under the test loads.
SAES-L-150,
Para. 6.4
All joints including welded joints are left exposed for visual leak detection
A10 during the strength test.
(NOTE: This excludes joints that will be subject to 24-hr recorded test. )
SAES-L-150,
Para. 7.3
A11
Work permit is obtained for all pressure testing and associated work
within restricted areas as covered in G.I. 2.100, Work Permit System.
G.I.-2.102,
Para. 5.6
A12
Equipment and appurtenances that are not adequate for test pressures
are isolated.
G.I.-2.102,
Para. 5.7
Page 1 of 3
PASS
FAIL
N/A
RE-INSP DATE
SAIC NUMBER
SAIC-A-2009
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
G.I.-2.102,
Para. 5.7
G.I.-2.102,
Para. 5.9
A15
The test areas are marked and warning signs posted to alert
approaching personnel.
G.I.-2.102,
Para. 5.11
A16
G.I.-2.102,
Para. 5.11
G.I.-2.102,
Para. 5.12
B1
Test piping, fittings and hoses are designed or have pressure rating that
matched or exceed the system test pressure.
G.I.-2.102,
Sec.4
B2
Paddle blinds or spectacle blinds used to isolate the test sections are of
the same class rating of the system or may be fabricated based on
appropriate calculations.
SAES-A-004
Para. 7.3
Test Manifold
C1
C2
G.I.-2.102,
Para. 5.5
C3
G.I.-2.102,
Para. 5.5
C4
G.I.-2.102,
Para. 5.5
D1
SAES-A-004
Para 5.5.1
D2
The relief valve(s) are tested, dated, and tagged within one week prior to
the pressure testing.
SAES-A-004
Para 5.5.1
D3
Isolation valves installed on the inlet and outlet of the relief valve are
sealed open during the test.
G.I.-2.102,
Para. 5.5
D4
The relief valve is located in the system under test and near the test
pump.
G.I.-2.102,
Para. 5.5
Page 2 of 3
SAES-A-004
Para 5.5.4
DATE APPROVED
25-May-05
QR NUMBER
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
DATE APPROVED
SAIC-A-2009
PROJECT TITLE
WBS / BI / JO NUMBER
ITEM
No.
ACCEPTANCE CRITERIA
REFERENCE
E1
A minimum of two pressure gages are required for the test system.
Their accuracy shall be within 5% of one another.
(NOTE: When large systems are tested, Inspection personnel will
determine the need for additional gages. )
SAES-A-004
Para 7.1.5
E2
Pressure gages and pressure recorders are calibrated within one (1)
month prior to the test. Stickers shall be applied indicating the latest
calibration date.
SAES-A-004
Para 7.1.5
E3
G.I.-2.102,
Sec.4
E4
All gages have a range such that the test pressure is within 30% to 80%
of the full range.
F1
QR NUMBER
25-May-05
MECH-
CONTRACTOR / SUBCONTRACTOR
PASS
FAIL
N/A
RE-INSP DATE
SAES-A-004
Para 7.1.5
SAES-L-150,
Para. 11.3
REMARKS:
REFERENCE DOCUMENTS:
1. SAES-A-004, General Requirements for Pressure Testing, (30 April, 2002)
2. GI-2.102, Saudi Aramco General Instruction-Pressure Testing Safely , (22 July, 2001)
3. SAES-L-150, Pressure Testing of Plant Piping and Pipelines, (30 September, 2003)
Contractor / Third-Party
Saudi Aramco
Construction Representative*
PMT Representative
T&I Witnessed
QC Record Reviewed
T&I Witnessed
QC Record Reviewed
T&I Witnessed
QC Record Reviewed
Work Verified
QC Inspector
PID Representative
Performed Inspection
Work Verified
QC Supervisor
Name, Organization,
Initials and Date:
Y = YES
Page 3 of 3
Work Verified
N = NO F = FAILED