Documente Academic
Documente Profesional
Documente Cultură
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
1 of 9
METHOD STATEMENT
FOR
CONTRACTOR
Title
Issued By:
QA/QC Inspector
Reviewed by
Project Engineer
Approved By:
Executive Manager
Signature
Date
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
2 of 9
CONTENTS
1. PURPOSE
2. SCOPE
3. RESPONSIBILITIES
4. PROCEDURE
4.1
4.2
Deployment
4.1.1
4.1.2
Assembly
4.2.1
4.2.2
4.2.3
4.2.4
4.2.5
4.2.6
4.2.7
4.2.8
of parts
Preparation of the area
Unloading of material
Installation of scaffolding
Anchor bolt fixing
Erection of components
Beam /support erection
Installation of additional scaffolding
Non-Destructive Testing
Surface preparation & protective coating application
Dismantling
6. REFERENCE DOCUMENTS
1.
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
3 of 9
Purpose
2.
Scope
3.
Responsibilities
Site Engineer: Site Engineer is responsible for executing the
job and manpower control according to plan schedule to work
and client/customer standard.
QC Engineer: QC Engineer is responsible for maintaining
the job according to Customer quality need.
Safety Officer: Safety Officer is responsible to maintain
the site in safe condition and keep monitoring the ongoing work
according to Customer Safety Standards.
Site Supervisor: Site supervisor is responsible to execute the
job according to method statement. Constantly monitor the
approved plan and identify improvement for future.
4.
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
4 of 9
PROCEDURES
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
5 of 9
4.2 Assembly
4.2.1 Installation of scaffolding
a. Scaffolding shall be erected for access purpose during the
erection phase of the elevator shaft. These access
platforms shall be positioned on certain locations where
the erectors require adequate access space during
assembly.
b. The scaffolds shall be checked and warranted safe to use
by the Safety Officer prior for use.
4.2.2 Anchor bolt fixing
a. Lay-outing shall be carried out as per the design drawing
issued by the client for the location of the anchor bolts. The
dimensions stated on the drawing shall serve as the
guidelines to obtain the exact position of the anchor bolts
to be installed.
b. After the lay-out has been done and exact position has
been obtained, drilling of the ground shall proceed. This
shall be done on the specified locations where the column
shall be erected. The depth of the hole shall be 180mm
minimum. After drilling has been done, the hole shall be
cleaned to remove loose dust particles.
c. After cleaning, each hole shall be applied with Hilti HITRe500 anchor chemical, followed by embedding of the
anchor bolts. Mixing and application of the anchor
chemical shall be in accordance with the instruction stated
on the Technical Data sheet of Hilti HIT-Re500.
c.
d.
e.
f.
g.
h.
i.
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
6 of 9
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
7 of 9
Non-Destructive Testing
c.
d.
e.
f.
g.
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
8 of 9
4.2.8 Dismantling
a. After the paint application has been completed, dismantling of
the lifting frame and scaffoldings shall proceed.
b. Components of the lifting frame shall be disassembled by
removing the lifting beam first. The chain blocks shall be
removed from their connector plates one by one. After that, the
bolted connection shall be loosened up and be brought down.
Afterwards, the A-frames are to follow.
c. After the lifting frame has been removed, the scaffolding shall be
dismantled next.
d. Extra caution shall be observed during dismantling stage in order
to avoid damaging the coated structure.
e. Any surface of the steel structure damaged during the
dismantling stage shall be subject for repair.
6.
ME-05-MS-001-16
Rev.
DATE
03/01/2016
PAGE
9 of 9
MANAGEMENT
AND
Reference document(s)
Reference drawing